Authors :
Trisanto; Henry Wardhan
Volume/Issue :
Volume 6 - 2021, Issue 1 - January
Google Scholar :
http://bitly.ws/9nMw
Scribd :
https://bit.ly/39xdDR0
Abstract :
A construction project is an activity that
requires a detailed calculation in its planning. It is not
only planning that needs attention, but construction
projects have their complexities in terms of management.
The management of a construction project has targets
that must be fulfilled by a contractor in terms of quality,
implementation time, and cost. This study aimed at
determining how the application of Earned Value in
estimating the cost and project time. This study took a
case study on the 8.505 m Maliku-Bantanan road
improvement project located in Maliku and Sebangau
Kuala sub-district, Pulang Pisau district, Central
Kalimantan province, Indonesia. This earned value
included budget and cost plans, unit price analysis, and
project progress reports processed to obtain BCWS
(Budgeted Cost of Work Scheduled), ACWP (Actual
Cost of Work Performance), and BCWP (Budgeted Cost
of Work Performance)which affected the control of the
implementation time and project costs. The results
showed that in the fifth month, the BCWP value was
IDR 13,668,602,892.99 and the BCWS value was IDR
13,513,565,248.85from the second calculation. The value
of BCWS was smaller than the value of BCWP, which
was 1.13% of the budget plan. The conditions indicated
that the implementation of activities in the field has been
following the planned schedule at a lower cost. These
results are expected to be used as a guide for contractors
and consultants in project planning that are more
effective and efficient as well as on quality, time, and
cost.
Keywords :
Earned Value (EV), Construction Project, BCWS, BCWP
A construction project is an activity that
requires a detailed calculation in its planning. It is not
only planning that needs attention, but construction
projects have their complexities in terms of management.
The management of a construction project has targets
that must be fulfilled by a contractor in terms of quality,
implementation time, and cost. This study aimed at
determining how the application of Earned Value in
estimating the cost and project time. This study took a
case study on the 8.505 m Maliku-Bantanan road
improvement project located in Maliku and Sebangau
Kuala sub-district, Pulang Pisau district, Central
Kalimantan province, Indonesia. This earned value
included budget and cost plans, unit price analysis, and
project progress reports processed to obtain BCWS
(Budgeted Cost of Work Scheduled), ACWP (Actual
Cost of Work Performance), and BCWP (Budgeted Cost
of Work Performance)which affected the control of the
implementation time and project costs. The results
showed that in the fifth month, the BCWP value was
IDR 13,668,602,892.99 and the BCWS value was IDR
13,513,565,248.85from the second calculation. The value
of BCWS was smaller than the value of BCWP, which
was 1.13% of the budget plan. The conditions indicated
that the implementation of activities in the field has been
following the planned schedule at a lower cost. These
results are expected to be used as a guide for contractors
and consultants in project planning that are more
effective and efficient as well as on quality, time, and
cost.
Keywords :
Earned Value (EV), Construction Project, BCWS, BCWP