First Prize
Integrated Steel Plants
JINDAL STEEL AND POWER LIMITED
Raigarh (Chattisgarh)
Unit Profile
242
Energy Consumption
Product
Production
(Million TPA)
2005-06
2006-07
2007-08
Sponge Iron
1017746
1196330
1185739
Hot metal
269711
577494
1278159
Steel
522334
803303
1424585
Rolled products
287389
209418
494751
Ferrochrome
32452
31070
17905
Power (MWH)
2225232
2668358
2665071
287800.00
394876.00
520503.00
Sales turn over (Rs. Lakhs)
Energy & Cost:
2005-06
2006-07
2007-08
10571.41
22332.11
17751.11
1652153
2321784
2911635
(Coking coal +Washed coal +Steam coal)
Coke purchased for process (Ton)
210994.0
76457.0
160023
(BF coke+coke fines+pero coke)
F.O. consumption in process (KL)
7835.55
6199.32
27439
Diesel consumption in the process (KL)
19401.0
24852.0
24395
Total Thermal Energy used in process (Gcal)
9020049.2
11849495.2
16300136.4
Total Energy cost (Rs. Lakhs)
34397.65
54230.78
96193.53
Total Manufacturing cost (Rs. Lakhs)
100580.0
160135.0
298521.6
Energy cost(As % of manufacturing cost)
34.20
33.87
32.20
Net Electrical Energy consumption (purchased
+generated-sold) (Lakh kWh)
Coal purchased for process (Ton)
243
Specific Energy Consumption
DRI Plant
Blast Furnace
244
SMS
SAF Plant
245
RUBM
Power Plant
246
Energy Conservation Commitment, Policy and Set up
All the above figures clearly indicate the culture of energy conservation imbibed right from initiation of
the company in 1991. When the plant started, to utilize the waste heat of rotary kilns, producing
Sponge iron, waste heat recovery boilers (WHRB) were installed on-line and the steam used for
generation of electrical power. Thus all the six kilns are fitted with WHRB. Continuing the commitment
for Energy conservation, all new kilns ( 4 Nos.) are also fitted with WHRB. Boilers generating steam
utilize the in-house waste of washery reject and rotary kiln char. In fact, commitment for energy
conservation and waste utilization is so high in the plant that the Power Plant unit-II & now power plant
unit-3 was planned for utilization of waste basically.
247
Energy Management organization set up has been made for the philosophy of the management,
energy management is part of the total management system, and that is why HODs are the key
elements in the total structure, for planning and execution of the action plans, Supported by Energy
Coordinator.
Organisation Structure
of
Energy Management Cell
EXECUTIVE DIRECTOR
RUBM
POWER
IRON &
248
MANAGEMENT
REPRESENTATIVE
(ENERGY)
SAF
FACILITATOR
DRI
(ENERGY)
SMS
FACILITATOR
BF
(ENERGY)
HOD
FACILITATOR
HOD
(ENERGY)
HOD
FACILITATOR
HOD
(ENERGY)
FACILITATOR
HOD
(ENERGY)
HOD
FACILITATOR
HOD
SYSTEM
CO-
VP (Iron
making)
ENERGY
MANAGER
Energy Conservation Achievements
Major achievements are:
1.
New producer gas plant (PGP-3) of
capacity 22,750 Nm3/hr is installed. In the
FY: 2007-08, 21584874 Nm3 producer
gas is generated and replaced petrofuels
and thus equivalent cost saving is
achieved. Thermal energy saving: 25901.0
Gcal/annum
Investment: Rs. 6000.00 Lakhs
Monetary Saving: Rs. 602.0 Lakhs/annum
2.
Initially The WHR Boilers were designed to
utilize coke oven exhaust gases.However
the Boiler could not achieve rated steam
flow due to insufficient supply of
gas.Though 8 nos. of Boilers were
designed for 33.5TPH of steam, only
20TPH to 23TPH-superheated steam was
achieved from each Boiler.BFG firing in
WHRB was envisaged and Burner
selection done by JSPL, detail designed
and supplied by M/S Thermax.BFG firing in
Coke Oven WHRB is first time in the world.
Challenges like firing a lean gas in nonfire type furnace without oil support was
successfully done. BF gas which was
earlier being flared in BF Stack was
sucessfully utilized for steam/power
generation
3.0 MW extra Power Generation from
each Boiler. Total 12 MW extra power
from four Boilers.
Electrical
power
kWh/annum.
saving:
95000400
Investment: Rs. 1205 Lakhs
Monetary Saving: Rs. 2350 Lakhs/annum
249
3.
INTER-CONNECTION
Serious problem is being faced in high stack emission due to high un-burnt
carbon in our 2*25 MW power plant, which is having 4*57 tph DRI based WHR
Boiler.During annual shutdown of one of the Boiler and after injection of around
10000 m3 air in three Boilers, 48 MW of load from three Boilers was generated.
Hence, it was concluded that steam generation is possible from these four
Boilers. Nevertheless there was a shortage of steam in our 3*25 MW PP & there
was a margin to increase the TG load by 20 MW.
Efficiency improved by 0.7% in 2100 TPH
Electrical power saving: 39600000 kWh/annum
Investment: Rs. 200 Lakhs
Monetary Saving: Rs. 982 Lakhs/annum
250
Energy Conservation Plans and Targets
Sr. No.
Energy Conservation Plans
Project commencement &
Excess BF gas utilization in two more WHRB of
1
power plant Unit-3
completion year
2008-09
Installation of VFD panel in place of DOL
2
starter in F.D. Fan no. 3A & 4A of WHRB# 9 &
2008-09
10 at 2x25 MW CPP.
Installation dual speed( High / Low ) starter in
3
place of DOL starter in C.T.Fan at 2x25 MW
CPP.
Provision of 2-way switches for On-OFF lights
4
2007-08
in cable cellers (Boiler & TG) at 3x25 MW CPP.
2008-09
Environment and Safety
Environmental Management
Following steps have been taken for Environmental Management at JSPL
Installation of Waste Heat Recovery Boilers (WHRB) to use waste heat of sponge iron unit for
generating electrical energy.
Installation of AFBC boilers to reuse solid wastes (middlings) of coal washery.
Installation of ESPs and Bag Filters in all dust generating sources.
Waste gas from blast furnace is used as fuel in our Rolling mill (reheating furnace) DRI (rotary kiln &
Coal dryer) and 63 TPH boiler.
Installation of two Sewage Treatment Plants to treat the domestic waste generated from the colonies
and offices. This treated wastewater is 100 % reused for plantation and garden development purpose.
Waste Management for reduction of the waste generation and exploring the use of the waste.
Construction of the pucca road inside the plant
Implementation of the concept of Green Productivity.
Waste water recycling and zero discharge.
Rain Water Harvesting
251
Bio-gas plant established
Vermiculture composting plant has been established.
Use of Fly Ash for Brick Manufacturing.
Use of fly Ash for various construction works.
I. Air Quality
Regular monitoring of Stacks is carried out to maintain emission level within the stipulated limits. Opacity
Meters have been installed in all the stacks.
II. Water Management
Water consumption has been optimised by taking various conservation measures. Flow meters have been
installed in all fresh water make up pipelines in all units, which helped a lot in water monitoring and
optimising specific water consumption for long steel products in coming about 5.3 m3/T of product.
Safety Control
Safety is the prime concern and companys target is zero accident. To keep employees aware about
safety and maintain zero accident targets several activities and program are being conducted in the plant.
252