POWER PLANT ASME B31.
1
PIPING STRESS ANALYSIS
* Scope
of ASME B31.1 Code- Ed 2014
* Design
per ASME B31.1 Code
* Piping
Stress Analysis Requirements per B31.1 Code
* Stress Due to Sustained Loads -
* Piping
Stress Analysis Requirements per B31.1 Code
* Stress Due to Occasional Loads -
* Piping
Stress Analysis Requirements per B31.1 Code
* Stress Due to Expansion Loads -
* Flexibility
Analysis Requirements per B31.1 Code
CRITICAL LINE SELECTIONS STRESS CRITICAL LINES
ELEVATED TEMPERATURE LINES AS PER BECHTEL STANDARDS
FOR POWER JOBS: C.S LINES>400 Deg. F & S.S. LINES >300 Deg. F
EQUIPMENT CRITICAL LINE
LINES CONNECTED TO
ROTATING MACHINERY - PUMP (API 610), TURBINE (NEMA - SM23),
RECIPROCATING COMPRESSOR, FIRED HEATER (API 560), AIR COOLER (API
661), REFORMERS, VESSELS WITH BRITTLE LINING.
ANALYSIS TO ENSURE THE NOZZLE LOADS ARE WITHIN STIPULATED
MAXIMUM VALUE SPECIFIED BY CODES / EQUIPMENT VENDORS.
SUPPORT CRITICAL LINES
TWO PHASE FLOW LINES.
VERY THICK AND VERY THIN LINES.
THAT IS, LINES HAVING DIA TO WALL THICKNESS RATIO IN THE RANGE: 10<
D/T >90
RELIEF CRITICAL LINES
RELIEF VALVE DISCHARGE LINES.
FLARE HEADER, LIQUID BLOW DOWN LINES.
DOWNSTREAM OF BURSTING DISC.
STRESS CRITICAL LINES
POWER PLANT PRACTICES LINES TO BE ANALYSED
- Main Steam
- Hot Reheat
- Cold Reheat
- Feed water suction and discharge piping
- Blow down
- HP extraction steam
- HP heater drains
- Auxiliary steam
- Gland & Sealing steam
- Combustion / steam turbine drains
STRESS CRITICAL LINES
POWER PLANT PRACTICES LINES TO BE ANALYSED
Low pressure extraction steam
Low pressure heater drains
Condensate
Yard piping under solar temp
Fibre glass piping
Relief valve piping
Connecting to Expansion joints
* Pipe
Support Span per B31.1 Code
* Pipe
Support Span per B31.1 Code
* Pipe
Support Span per B31.1 Code