We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 4
ADDENDUM NO. 1 TO THE CONDITIONS OF CONTRACT
PWD 203/203A (Rev. 1/2010)
‘AMENDMENTS
General
Amend all the words “Government” contained in the Articles of Agreement and conditions
of contr
fact and Appendix to the conditions of contract to read Employer
Page 20, Clause 28
Substitute the whole of Clause 28.0 with the new Clause 28.0 as follows:
28.1
28.2
28.3
28.4
Subject to compliance with the terms and conditions under this Contract. The
Contractor shall be entitled for interim Payment certified by the S.0.’s monthly
evaluation (or more often at the discretion of the S.0.]. Provided always that the
Contractor shall submit to the S.O., at such times and in such form as the S.O. may
prescribe, written application for Interim Payments showing the amounts which in the
Contractor's opinion are due under the Contract Payments. The submission shall
include the following:
{a) the value of Works done and properly executed and valued in accordance
with these terms of Contract;
(b) the amount of any valuation of variations or of the instructions by the 5.0.
(clause 25);
()__ the amount in regard to the expenditure of Provisional Sums and Prime Cost
‘Sums executed or expended (clause 34);
(a) the value of any goods or unfixed materials delivered to or adjacent to the
Site intended for use to be incorporated into the Works;
{e) the value of fluctuation of price pursuant to clause 30: and
(fall relevant documents including site measurement, working diagrams,
delivery orders, relevant invoices, as-built drawings, shop drawings relevant
tests and environmental impact assessment of the Works or other relevant
documents as the 5.0, may require, to substantiate the Contractor's written
application for interim payments,.
The 5.0. shall within fourteen (14) days from the date of receipt of the application for
Interim Payments, inspect and verify the Works, and make a valuation of the same
and issue an Interim Payment Certificate stating the amount due to the Contractor
from the Government PROVIDED THAT the total value in each monthly valuation shall
not be less than the sum referred to in Appendix 1.
If the Contractor fails to submit full particulars of written application for interim.
Payments as stipulated in Clause 28.1, the S.O. shall make the valuation of works
based on the available documents to him for the purpose of the Interim Payment
Certificate. The Government shall be discharged from all liabilities in connection with
the Interim Payments.
The amount stated as due in an Interim Payment Certificate shall be the estimated
total value of the Works done and properly executed and up to ninety (90) percent of
the value of any goods or unfixed materials delivered to or adjacent to the Site
intended for use or to be incorporated into the Works up to and including the date
1 (RA)3.
28.5
the valuation was made, less any payments (including Advance Payment) previously
paid under this Contract. PROVIDED THAT such Certificate shall only include the value
of the said goods or unfixed materials as and from such time as they are reasonably
and properly and not prematurely delivered to or adjacent to the Site and adequately
protected against weather, damage or deterioration.
Within a number of days as stated in Appendix (or if none stated then within thirty
(30) days of the issues of any such Interim Certificate), the Government shall make a
Payment to the Contractor as follows:
(a) where the Performance Bond is in the form of a Banker's, Insurance or
Finance Company Guarantee, payment shall be made on the amount certified
as due to the Contractor in the said Interim Certificate; or
(b) where the Performance Bond is in the form of a Performance Guarantee Sum,
payment of ninety percent (90%) on the amount certified as due to the
Contractor shall be made with the remaining ten percent (10%) being
retained by the Government as a Performance Guarantee Sum. PROVIDED
THAT when the sum retained is equivalent to the five percent (5%) of the
Contract Sum then in any subsequent Certificate, payment shall be made on
the full amount certified as due to the Contractor.
Page 21, Clause 30
Delete entire clause.
Page 21, Clause 31
Substitute the whole of Clause 31.0 with the new Clause 31.0 as follows:
314
312
313
‘As soon as is practicable but not later than three (3) months after the issuance of the
Certificate of Practical Completion, the Contractor shall submit full particulars
complete with receipts, vouchers records that would substantiate the Contractor's
claim under clause 44 together with any documents relating to the accounts of
Nominated Sub-Contractors or Nominated Suppliers, which may be necessary to
enable the Final Account to be prepared by the 5.0. PROVIDED ALWAYS the
Contractor had given the notice of claim in writing within the stipulated time or times
in the said provisions.
Within three (3) months after issuance of the Certificate of Completion of Making
Good Defects, the Contractor shall submit to the S.O. a statement of the final account
showing in detail the value in accordance with the Contract, of the Works carried out
together with all further sums which the Contractor considers to be due to him after
giving credit to the Government for all amounts previously paid by the Government
and for all sums to which the Government is entitled under the Contract up to the
date of the Certificate of Completion of Making Good Defects or the Certificate of
‘Completion of Maintenance, as the case may be. The Final Account shall be supported
by all documentation substantiating the value of the same.
IF the Contractor fails to submit full particulars of all claims within the stipulated
period, the 5.0. shall forthwith make the assessment based on the available
documents submitted by the Contractor for the purpose of the Final Account. The
Government shall be discharged from all liabilities in connection with the claims.
2 (Ru)5a
52
314
315
31.6
Within three (3) months after the expiry of the Defects Liability Period for the whole
of the Works or three (3) months after the issue of the Certificate of Completion of
Making Good Defects under clause 48 hereof, whichever is the later, the 5.0. shall
issue the Final Certificate
The Final Certificate shall be supported by documents, and full particulars complete
with receipts, vouchers records showing the S.0.’s final valuation of Works and any
amount determined in Clause 31.1 in accordance with the terms of this Contract. After
setting out or allowing for all payments or other expenditure of the Government or
any permitted deductions made by the Government or the 5.0. on its behalf, the Final
Certificate shall state any final balance due from the Government to the Contractor
or from the Contractor to the Government, as the case may be, which shall thereupon
become the debt payable. Such certificate shall also take account of any outstanding
permitted deductions not yet made by the Government under the terms of this
Contract whether by way of liquidated damages or otherwise.
No final payment due to the Contractor under the Final Certificate, shall be made
unless and until the Contractor shall have satisfied the S.O. by means of a Statutory
Declaration made by or on behalf of the Contractor to the effect that the workmen
who have been employed by the Contractors on the Works including workmen
employed by sub-contractors, whether nominated or otherwise (including “labour
only” sub-contractors) have received all wages due to them in connection with such
employment, and that all dues or contributions under the Employment Act 1965 and
any other laws relevant to the employment of workmen, have been paid.
Page 26, Clause 40
Substitute clause 40.1 with the new clause 40.1 as follows:
40.1
If the Contractor fails to complete the Works by the Date for Completion or within any
extended time granted pursuant to clause 43, the S.O. shall issue a Certificate of Non-
Completion to the Contractor.
Substitute clause 40.2 with the new clause 40.2 as follows:
40.2
Without prejudice to the Government's right to terminate this Contract, when the
S.0. issues the Certificate of Non-Completion, the Government shall be entitled to
recover from the Contractor, Liquidated and Ascertained Damages calculated at the
rate stated in Appendix 1 from the date of the failure to complete the work pursuant
to clause 40.1 to the date of the Practical Completion or the date of termination of
this Contract. The 5.0. may deduct such Liquidated and Ascertained Damages from
any money due or to become due to the Contractor, failing which such damages shall
be recovered from the Performance Bond or as a debt due from the Contractor. The
5.0. shall inform the Contractor in writing of such deduction.
Page 36, Clause 52
Delete entire clause.
Page 43, Clause 66
Delete entire clause.
3(R1)PAGE 45, Clause 69
Delete entire clause,
PAGE 48 & 49, Clause 80
Delete entire clause.
Ra)