Advanced Software Engineering: Prof. Luigi Casalegno

The document summarizes key activities in the bid assignment process for public utility work. It describes publishing and assigning the bid, including evaluating preliminary documentation, gathering offers, and selecting a winner. It also describes opening and verifying folders to check documentation and ensure integrity. A use case diagram is included but not described. The activities and documentation requirements are presented at a high level to provide essential information about the bid assignment process.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views6 pages

Advanced Software Engineering: Prof. Luigi Casalegno

The document summarizes key activities in the bid assignment process for public utility work. It describes publishing and assigning the bid, including evaluating preliminary documentation, gathering offers, and selecting a winner. It also describes opening and verifying folders to check documentation and ensure integrity. A use case diagram is included but not described. The activities and documentation requirements are presented at a high level to provide essential information about the bid assignment process.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Advanced Software Engineering

Lab2

Prof. Luigi Casalegno

Diogo Borges Krobath


Guilherme Mussi Toschi
Júlio Cesar Sartori
Content

Publish and assign a bid ................................................................................................ 3


Open and verify the folders .......................................................................................... 5
Use case diagram .......................................................................................................... 6

2
Publish and assign a bid

Use Case name: Publish and assign a bid;

Brief Description: activity related with issuing a bid for a public utility work and determines the
winner company of the bid assignment;

Level: Summary goal;

Primary Actor: the team designated by government to manage the bid process;

Stakeholders and interests: a public sector which needs a company for providing a service;

Precondition: the government has a need of some service provided by a private company, that
himself cannot do;

Minimal Guarantee: find some company that can provide the service needed;

Success Guarantee: the public sector which requested the bid issuing will find the best options
into the set of companies that can provide the service needed;

Main Success Scenario:

1. Publish the call for the bid on the Italian official gazette;
2. Assemble a committee and evaluate the preliminary documentation and select the
companies that are able to apply for the bid;
3. Await and gather the offers of the selected companies within 60 days from the day in
which the committee met;
4. Assemble the two committees to evaluate the offers;
5. Open and verify folders integrity;
6. Perform the technical evaluation of the proposal (after 15 days from the first session in
which the folders were evaluated);
7. Technical evaluation results are passed to the administrative committee and this one
performs the economical evaluation;
8. Announce the winner of the bid;

Extensions:

• Alternatives:

1. Whether the value of the bid is higher than 1 M€ it has to be published on the
European official gazette too;

• Exceptions:

2. No company applies;
3. Companies don’t send their offers within 60 days.
5a. Folder integrity violated;
5b. Documentation insufficient, the company is excluded from the bid;

3
Technology and Data Variations: not applicable

Related Information: not applicable

Open Issues: the content of the preliminary documents and who will examine the preliminary
documentation

4
Open and verify the folders

Use Case name: Open and verify the folders;

Brief Description: session held to open and verify the folders integrity as well as the required
documentations and specifications;

Level: User goal level;

Primary Actor: Administrative committee;

Stakeholders and interests: the public sector be aware of the final set of companies
competing for the public bid;

Precondition: the companies have applied to the bid, have sent the folder sealed up with all
the requirement documents inside and the candidate firms be presented for the opening
session;

Minimal Guarantee: an unready company is taken out of the bid;

Success Guarantee: confirm that all companies are able to apply to the second part of the bid;

Main Success Scenario:

1. Administrative committee checks the folder integrity for each company;


2. It opens the administrative envelope to validate the required documentation and the
guarantee value;

Extensions:

• Exceptions:

1. Folder integrity violated;


2. Documentation insufficient, the company is excluded from the bid;

Technology and Data Variations: not applicable;

Related Information: not applicable;

Open Issues: whether the administrative committee opens all envelopes and checks, for each
one, the required documents or if it is only executed in the administrative envelope.

5
Use case diagram