Standard Operating Procedures
Committed to Excellence in Mining Safety Change Management
MODULE 11
Last Modified: Page:
JAN 2013 1 of 4
Change Management
I Purpose
This procedure establishes the process for managing change management applied to all new
projects and significant modifications that address regulatory requirements, as well as the
COMPANY HSLP and ESR requirements.
2 SCOPE
This procedure applies to all COMPANY activities within the scope of the IMS.
3 DEFINITIONS AND ACRONYMS
Definitions
Stage Gate Process is a disciplined, step-by-step system to move projects through the
development pipeline. It provides the work to develop and support the creation of a business
case as well as approval for expenditure.
Acronyms
AFE Authorization for Expenditure
EMR ESR Management Representative
ESR Environmental and Social Responsibility
HMR Integrated Management System
HSLP Health, Safety and Loss Prevention
IMS Integrated Management System
KPI Key Performance Indicators
4 ROLES AND RESPONSIBILITIES
Document Owner
The EMR and HMR
Responsible Roles and Position-Holders
• Change Initiator is the person requiring the change.
• Change Assessor is the person(s) reviewing and evaluating the change.
• Change Authorizer is the person approving the change.
• Change Verifier is the person(s) confirming all requirements for the
change have been addressed.
(Cont.) www.coresafety.org
Last Modified: Page:
Committed to Excellence in Mining Safety JAN 2013 2 of 4
5 DIRECTION
Change can be planned or unplanned, sudden or gradual, at any COMPANY site and any
personnel at any COMPANY site, including emergency change. Types of change include (but
are not limited to):
• Facilities and Equipment
• Processes
• Operating procedures
• Design and construction
• Maintenance procedures
• Materials used, their composition and properties
• Consumables used and by-products/wastes generated
• Organization structures and responsibilities
• Personnel changes, training or competency requirements.
• Programmable Electronic System software
• Layout/Design of mines/pits
• Individual roles and responsibilities
• Mine planning and ground control
• Departure of contractors and hand over to Newmont North America
• Regulatory and statutory requirements
• Multiple Area/Site/Functional/Departmental Impacts.
Initiating Change Project
The Change Initiator shall perform the following.
For a complete project, initiate a change by completing the relevant Change form.
a Identify the location or locations where the change is to occur.
b Identify the change
c Provide all the necessary details in the proposal for change, and include all
required drawings, photos, etc. as attachments when the form is submitted.
Note: All proposals for change which require an AFE must also be included.
For a change to parts of a project which is already approved, initiate by performing the
following:
a Document the project name, project manager, and the date the approval is
needed.
b Provide a detailed Description of the Change Requested.
c Describe the Reasons and Justification for the Change.
(Cont.) Change Management www.coresafety.org
MODULE 11
Last Modified: Page:
Committed to Excellence in Mining Safety JAN 2013 3 of 4
d Provide an analysis of the Impacts of the Proposed Changes based on the
categories listed.
e Obtain the necessary approvals for submission.
Submit to the Change Authorizer the completed Project Change Management form.
Assessing the Change Project
The Change Assessor shall assess the change request by conducting a risk assessment of
the change, by determining the following.
a The required risk assessment and control mechanisms to eliminate or
minimize the risks.
b The standards and procedures to be used.
c The operational controls which are required.
d The continued or future evaluations to be performed, (hazard
evaluations, etc).
e The regulatory requirements that must be met.
f If a change is subject to test/trial and the duration and measures for the
test/trial.
g The authorization of the change that is required which shall be at least the
same level of authority that authorized the current status.
h The highest risk rating from the risk assessment.
Authorizing the Change Project
The Change Authorizer shall authorize the change project by performing the following.
Complete the necessary information and obtain all signatures required.
Ensure the Change Assessor(s) and the Change Initiator complete all necessary information
Ensure appropriate information on the change will be released and training related to the
change provided for all those affected.
Verification of Change
The Change Verifier shall conduct or confirm the following:
Appropriate information on the change has been released and training related to the change
provided for all those affected.
Prior to a physical change being handed over for normal use, ensure:
a The changes have been carried out in accordance with the authorized
change proposal.
b All actions from the review process, including any evaluations called for have
been satisfactorily completed and all outcomes included.
(Cont.) Change Management www.coresafety.org
MODULE 11
Last Modified: Page:
Committed to Excellence in Mining Safety JAN 2013 4 of 4
c The physical change has not introduced any unforeseen risks.
A formal review is completed in order to assess the actual impact of the change against the
intended impact and the reasons for any deviation.
A system exists which allows for the revision of as-built drawings, operating procedures,
maintenance and emergency procedures.
The Project Manager has completed the commissioning form, and all sign-offs are
completed, and any identified corrective actions have been addressed.
New Products
Personnel with appropriate HSLP and ESR knowledge, shall conduct a review and approve
the acquisition of equipment, materials, chemicals, and other materials with potential
environmental, social, safety and health impacts prior to their purchase.
Change Management www.coresafety.org
MODULE 11