SSIGL 1 Project Initiation, Planning and Organization Ver-6
SSIGL 1 Project Initiation, Planning and Organization Ver-6
NATIONAL GUIDELINES
For Small Scale Irrigation Development in Ethiopia
November 2018
Addis Ababa
MINISTRY OF AGRICULTURE
November 2018
Addis Ababa
National Guidelines for Small Scale Irrigation Development in Ethiopia
First Edition 2018
© MOA 2018
Ministry of Agriculture
Small-Scale Irrigation Development Directorate
P. O. Box 62347
Tel: +251-1-6462355
Fax: +251-1-6462355
Email: [email protected]
[email protected]
eDMS (intranet): MoA SSID DMS (http://172.28.1.188:8080/DMS/login.jsp)
Website: www.moa.gov.et
DISCLAIMER
Ministry of Agriculture through the Consultant and core reviewers from all relevant stakeholders included the
information to provide the contemporary approach about the subject matter. The information contained in the
guidelines is obtained from sources believed tested and reliable and are augmented based on practical
experiences. While it is believed that the guideline is enriched with professional advice, for it to be
successful, needs services of competent professionals from all respective disciplines. It is believed, the
guidelines presented herein are sound and to the expected standard. However, we hereby disclaim any
liability, loss or risk taken by individuals, groups, or organization who does not act on the information
contained herein as appropriate to the specific SSI site condition.
National Guidelines for Small Scale Irrigation Development MOA
FORWARD
Ministry of Agriculture, based on the national strategic directions is striving to meet its commitments in
which modernizing agriculture is on top of its highest priorities to sustain the rapid, broad-based and
fair economic growth and development of the country. To date, major efforts have been made to
remodel several important strategies and national guidelines by its major programs and projects.
While efforts have been made to create access to irrigation water and promoting sustainable irrigation
development, several barriers are still hindering the implementation process and the performance of
the schemes. The major technical constrains starts from poor planning and identification, study, design,
construction, operation, and maintenance. One of the main reasons behind this outstanding challenge,
in addition to the capacity limitations, is that SSIPs have been studied and designed using many ad-
hoc procedures and technical guidelines developed by various local and international institutions.
Despite having several guidelines and manuals developed by different entities such as MoA (IDD)-
1986, ESRDF-1997, MoWIE-2002 and JICA/OIDA-2014, still the irrigation professionals follow their
own public sources and expertise to fill some important gaps. A number of disparities, constraints and
outstanding issues in the study and design procedures, criteria and assumptions have been causing
huge variations in all vital aspects of SSI study, design and implementation from region to region and
among professionals within the same region and institutions due mainly to the lack of agreed standard
technical guidelines. Hence, the SSI Directorate with AGP financial support, led by Generation
consultant (GIRDC) and with active involvement of national and regional stakeholders and international
development partners, these new and comprehensive national guidelines have been developed.
The SSID guidelines have been developed by addressing all key features in a comprehensive and
participatory manner at all levels. The guidelines are believed to be responsive to the prevalent study
and design contentious issues; and efforts have been made to make the guidelines simple, flexible and
adaptable to almost all regional contexts including concerned partner institution interests. The outlines
of the guidelines cover all aspects of irrigation development including project initiation, planning,
organizations, site identification and prioritization, feasibility studies and detail designs, contract
administration and management, scheme operation, maintenance and management.
Therefore, I congratulate all parties involved in the success of this effort, and urge partners and
stakeholders to show a similar level of engagement in the implementation and stick to the guidelines
over the coming years.
Transforming agricultural production from its dependence on rain-fed practices by creating reliable irrigation
system in which smallholder farmers have access to at least one option of water source to increase
production and productivity as well as enhance resilience to climate change and thereby ensure food
security, maintain increasing income and sustain economic growth.
ACKNOWLEDGEMENTS
The preparation of SSIGLs required extensive inputs from all stakeholders and development partners.
Accordingly many professionals from government and development partners have contributed to the
realization of the guidelines. To this end MOA would like to extend sincere acknowledgement to all
institutions and individuals who have been involved in the review of these SSIGLs for their
comprehensive participation, invaluable inputs and encouragement to the completion of the guidelines.
There are just too many collaborators involved to name exhaustively and congratulate individually, as
many experts from Federal, regional states and development partners have been involved in one way
or another in the preparation of the guidelines. The contribution of all of them who actively involved in
the development of these SSIGLs is gratefully acknowledged. The Ministry believes that their
contributions will be truly appreciated by the users for many years to come.
The Ministry would like to extend its appreciation and gratitude to the following contributors:
Agriculture Growth Program (AGP) of the MoA for financing the development and
publication of the guidelines.
The National Agriculture Water Management Platform (NAWMP) for overseeing, guidance
and playing key supervisory and quality control roles in the overall preparation process and
for the devotion of its members in reviewing and providing invaluable technical inputs to
enrich the guidelines.
Federal Government and Regional States organizations and their staff for their untiring effort
in reviewing the guidelines and providing constructive suggestions, recommendations and
comments.
National and international development partners for their unreserved efforts in reviewing the
guidelines and providing constructive comments which invaluably improved the quality of the
guidelines.
Small-scale and Micro Irrigation Support Project (SMIS) and its team for making all efforts to
have quality GLs developed as envisioned by the Ministry.
The MOA would also like to extend its high gratitude and sincere thanks to AGP‟s multi development
partners including the International Development Association (IDA)/World Bank, the Canada
Department of Foreign Affairs, Trade and Development (DFATD), the United States Agency for
International Development (USAID), the Netherlands, the European Commission (EC), the Spanish
Agency for International Development (AECID), the Global Agriculture and Food Security Program
(GAFSP), the Italy International Development Cooperation, the Food and Agriculture Organization
(FAO) and the United Nations Development Program (UNDP).
Moreover, the Ministry would like to express its gratitude to Generation Integrated Rural Development
Consultant (GIRDC) and its staff whose determined efforts to the development of these SSIGLs have
been invaluable. GIRDC and its team drafted and finalized all the contents of the SSIGLs as per
stakeholder suggestions, recommendations and concerns. The MoA recognizes the patience,
diligence, tireless, extensive and selfless dedication of the GIRDC and its staff who made this
assignment possible.
Finally, we owe courtesy to all national and International source materials cited and referred but
unintentionally not cited.
Ministry of Agriculture
DEDICATIONS
The National Guidelines for Small Scale Irrigation Development are dedicated to Ethiopian smallholder
farmers, agro-pastoralists, pastoralists, to equip them with appropriate irrigation technology as we envision
them empowered and transformed.
LIST OF GUIDELINES
TABLE OF CONTENTS
FORWARD ........................................................................................................................... I
ACKNOWLEDGEMENTS .................................................................................................. III
LIST OF GUIDELINES ........................................................................................................V
ACRONYMS..................................................................................................................... XIII
PREFACE ........................................................................................................................ XV
UPDATING AND REVISIONS OF GUIDELINES ........................................................... XVII
1 BACKGROUND ............................................................................................................ 1
1.1 GENERAL ........................................................................................................................ 1
1.2 OBJECTIVES ................................................................................................................... 1
1.3 SCOPE OF THE GUIDELINE ........................................................................................... 2
1.4 THE NEED FOR PROJECT INITIATION, PLANNING, AND ORGANIZATION................. 2
2 PLANNING OVERVIEW ............................................................................................... 3
3 PROJECT PHASESES IN PERVIOUS GUIDELINES .................................................. 5
3.1 PROJECT PHASES PRACTICED IN THE REGIONAL STATES ..................................... 5
3.1.1 SSI project phases in Oromia regional state .............................................................. 5
3.1.2 SSI project phases in SNNPRS ................................................................................. 5
3.1.3 SSI project phases in Benishangul Gumuz regional state .......................................... 6
3.1.4 SSI project phases in Amhara regional state ............................................................. 6
3.1.5 SSI project phases in Tigray regional state ................................................................ 7
3.2 PROJECT PHASES IN PERVIOUS GUIDELINES ........................................................... 7
4 SSIP POTENTIALS, OPPORTUNITIES, AND CHALLENGES.................................. 11
4.1 SMALL-SCALE IRRIGATION (SSI) POTENTIAL AND DEVELOPMENT ....................... 11
4.2 OPPORTUNITIES .......................................................................................................... 11
4.3 CHALLENGES ............................................................................................................... 12
5 SSIP PLANNING ANDDEVELOPMENT PHASES .................................................... 13
5.1 GENERAL ...................................................................................................................... 13
5.1.1 Project initiation, planning, and organization ............................................................ 13
5.1.2 Site identification and prioritization ........................................................................... 14
5.1.3 Feasibility study and detail design............................................................................ 14
5.1.4 Contract administration, construction and construction supervision ......................... 15
5.1.5 Operation and management phase .......................................................................... 15
6 PLANNING APPROACHES AND GUIDING PRINCIPLES........................................ 17
6.1 DEMAND DRIVEN ......................................................................................................... 17
6.2 BOTTOM-UP APPROACH ............................................................................................. 17
6.3 ITERATIVE APPROACH ................................................................................................ 17
6.4 FLEXIBLE APPROACH .................................................................................................. 18
6.5 CATCHMENT-BASED PLANNING APPROACH ............................................................ 18
6.6 INTEGRATED AND INTERDISCIPLINARY APPROACH ............................................... 18
7 STACKHOLDERS PARTICIPATION, OWNERSHIP AND COMMITMENT ............... 21
7.1 PRINCIPLES .................................................................................................................. 21
7.2 BUILDING ON EXISTING KNOWLEDGE AND INSTITUTIONS ..................................... 22
7.3 PUBLIC AWARENESS CREATION, COMMUNITY PARTICIPATION, AND OWNERSHIP22
7.4 STAKEHOLDERS PARTICIPATION AND COMMITMENT ............................................. 22
7.5 INVOLVEMENT AND COMMITMENT OF PRIVATE CONSULTANTS, CONTRACTORS,
AND SUPPLIERS .......................................................................................................... 23
LIST OF APPENDICES
LIST OF TABLES
Table 9-1: Proposed staffing for Project Management Unit (PMU) .......................................... 31
Table 12-1: Time required for site identification and investment prioritization study ................ 41
Table 12-2: List of person power by disciplines and qualifications........................................... 42
Table 12-3: Proposed budget for site identification and investment prioritization ..................... 44
Table 13-1: Time required for a feasibility study and detail design study ................................. 45
Table 13-2: List of person power by disciplines and qualifications for FS & DD....................... 46
Table 13-3: Proposed Budget for Feasibility Studies, Detail Design SSI projects .................... 47
Table 14-1: Person power for contact administration and construction supervision ................. 53
Table 14-2: Person power by disciplines and qualifications for construction ........................... 53
Table 15-1: Person power by disciplines and qualifications for operation & management of ssi
scheme ............................................................................................................................. 56
Table 15-2: Planning of person power by responsibilities for operation & management of SSI
scheme ............................................................................................................................. 56
Table 15-3: Planning of tools and equipment for SSIP operation and maintenance works ...... 58
Table 19-1: Detailed work activities and schedule ................................................................... 72
Table 19-2: Budget schedule .................................................................................................. 72
Table 19-3: Budget summary for SSIP implementation ........................................................... 72
LIST OF FIGURES
Figure 9-1: Organizational structures of Project Management Unit (PMU) .............................. 30
Figure 14-1: Project organization for contract administration and construction supervision
service .............................................................................................................................. 52
ACRONYMS
PREFACE
While irrigation development is at the top of the government‟s priority agendas as it is key to boost
production and improve food security as well as to provide inputs for industrial development.
Accordingly, irrigated land in different scales has been aggressively expanding from time to time.
To this end, to enhance quality delivery of small-scale irrigation development planning,
implementation and management, it has been decided to develop standard SSI guidelines that
must be nationally applied. In September 2017 the Ministry of Agriculture (MoA) had entrusted
Generation Integrated Rural Development Consultant (GIRDC) to prepare the National Small-
scale Irrigation Development Guidelines (SSIGLs).
Preparation of the SSIGLs for enhancing development of irrigated agriculture is recognized as one
of the many core initiatives of the MoA to improve its delivery system and achieve the targets in
irrigated agriculture and fulfill its mission for improving agricultural productivity and production. The
core objective of developing SSIGLs is to summarize present thinking, knowledge and practices to
enable irrigation practitioners to properly plan, implement and manage community managed SSI
schemes to develop the full irrigation potential in a sustainable manner.
As the SSIGLs are prepared based on national and international knowledge, experiences and
practices, and describe current and recommended practice and set out the national standard
guides and procedures for SSI development, they serve as a source of information and provide
guidance. Hence, it is believed that the SSIGLs will contribute to ensuring the quality and timely
delivery, operation and maintenance of SSI schemes in the country. The SSIGLs attempt to
explain and illustrate the important concepts, considerations and procedures in SSI planning,
implementation and management; and shall be used as a guiding framework for professionals
engaged in SSI development. Illustrative examples from within the country have been added to
enable the users understand the contents, methodologies presented in the SSIGLs.
The intended audiences of the SSIGLs are government organizations, NGOs, CSOs and the
private sector involved in SSI development. Professionally, the SSIGLs will be beneficial for
experienced and junior planners, experts, contractors, consultants, suppliers, investors, operators
and managers of SSI schemes. The SSIGLs will also serve as a useful reference for academia
and researchers involved and interested in SSI development. The SSIGLs will guide to ensure
that; planning, implementation and management of SSI projects is formalized and set procedures
and processes to be followed. As the SSIGLs provide information and guides they must be always
fully considered and applied by adapting them to the local specific requirements.
In cognizance with the need for quality SSIGLs, the MoA has duly considered quality assurance
and control during preparation of the guidelines. Accordingly, the outlines, contents and scope of
the SSIGLs were thoroughly discussed, reviewed and modified by NAWMP members (senior
professionals from public, national and international stakeholder) with key stakeholders in many
consultative meetings and workshops. Moreover, at each milestone of SSIGL preparation,
resource persons from all stakeholders reviewed and confirmed that SSIGLs have met the
demands and expectations of users.
Moreover, the Ministry has mobilized resource persons from key Federal, National Regional States
level stakeholders and international development partners for review, validation and endorsement
of the SSIGLs.
Several hundreds of experienced professionals (who are very qualified experts in their respective
fields) from government institutions, relevant private sector and international development partners
have significantly contributed to the preparation of the SSIGLs. They have been involved in all
aspects of the development of SSIGLs throughout the preparation process. The preparation
process included a number of consultation meetings and workshops: (i) workshop to review
inception report, (ii) workshop on findings of review of existing guidelines/manuals and proposed
contents of the SSIGLs, (iii) meetings to review zero draft SSI GLs, (iv) review workshop on draft
SSI GLs, (v) small group review meetings on thematic areas, (vi) small group consultation
meetings on its final presentation of contents and layout, (vii) consultation mini-workshops in the
National States on semi-final versions of the SSIGLs, and (viii) final write-shop for the appraisal
and approval of the final versions of SSIGLs.
The deliberations, concerns, suggestions and comments received from professionals have been
duly considered and incorporated by the GIRD Consultant in the final SSIGLs.
There are 34 separate guidelines which are categorized into the following five parts concurrent to
SSI development phases:
Part-I. Project Initiation, Planning and Organization Guideline which deals with key considerations
and procedures on planning and organization of SSI development projects.
Part-II. Site Identification and Prioritization Guideline which treats physical potential identification
and prioritization of investment projects. It presents SSI site selection process and
prioritization criteria.
Part-III. Feasibility Study and Detail Design Guidelines for SSID dealing with feasibility study
and design concepts, approaches, considerations, requirements and procedures in the
study and design of SSI systems.
Part-IV. Contract Administration and Construction Management Guidelines for SSI development
presents the considerations, requirements, and procedures involved in construction of
works, construction supervision and contract administration.
Part-V. SSI Scheme Management, Operation and Maintenance Guidelines which covers SSI
Scheme management and operation.
Moreover, Tools for Small Scale Irrigation development are also prepared as part of SSIGLs.
It is strongly believed and expected that; the SSIGLs will be quickly applied by all stakeholders
involved in SSI development and others as appropriate following the dissemination and
familiarization process of the guidelines in order to ensure efficient, productive and sustainable
irrigation development.
The SSIGLs are envisioned to be updated by incorporating new technologies and experiences
including research findings. Therefore, any suggestions, concerns, recommendations and
comments on the SSIGLs are highly appreciated and welcome for future updates as per the
attached format below. Furthermore, despite efforts in making all types of editorial works, there
may still errors, which similarly shall be handled in future undated versions.
.
This current version of the GLs has particular reference to the prevailing conditions in Ethiopia and
reflects the experience gained through activities within the sub-sector during subsequent years.
This is the first version of the SSI development GLs. This version shall be used as a starting point
for future update, revision and improvement. Future updating and revisions to the GLs are
anticipated as part of the process of strengthening the standards for planning, study, design,
construction, operation and management SSI development in the country.
Completion of the review and updating of the GLs shall be undertaken in close consultation with
the federal and regional irrigation institutions and other stakeholders in the irrigation sub-sector
including the contracting and consulting industry.
In summary, significant changes to criteria, procedures or any other relevant issues related to
technological changes, new policies or revised laws should be incorporated into the GLs from their
date of effectiveness. Other minor changes that will not significantly affect the whole nature of the
GLs may be accumulated and made periodically. When changes are made and approved, new
page(s) incorporating the revision, together with the revision date, will be issued and inserted into
the relevant GL section.
All suggestions to improve the GLs should be made in accordance with the following procedures:
I. Users of the GLs must register on the MOA website: Website: www.moa.gov.et
II. Proposed changes should be outlined on the GLs Change Form and forwarded with a
covering letter or email of its need and purpose to the Ministry.
III. Agreed changes will be approved by the Ministry on recommendation from the Small-scale
Irrigation Directorate and/or other responsible government body.
IV. The release date of the new version will be notified to all registered users and authorities.
Users are kindly requested to present their concerns, suggestions, recommendations and
comments for future updates including any omissions and/or obvious errors by completing the
following revisions form and submitting it to the Ministry. The Ministry shall appraise such requests
for revision and will determine if an update to the guide is justified and necessary; and when such
updates will be published. Revisions may take the form of replacement or additional pages. Upon
receipt, revision pages are to be incorporated in the GLs and all superseded pages removed.
To: ---------------------------------------------------------------
From: -----------------------------------------------------------
Date: -----------------------------------------------------------
Description of suggested updates/changes: Include GL code and title, section title and #
(heading/subheading #), and page #.
Note that be specific and include suggested language if possible and include additional sheets for
comments, reference materials, charts or graphics.
The following table helps to track initial issuance of the guidelines and subsequent Updates/Versions and
Revisions (Registration of Amendments/Updates).
Revision Register
Version/Issue/Revision Reference/Revised Description of Authorized Date
No Sections/Pages/topics revision by
(Comments)
1 BACKGROUND
1.1 GENERAL
A Guideline is defined as a technical and an official recommendation indicating how tasks or works
should be done; steps to follow; what sort of action should be taken and when to act during the
execution process.
To accelerate irrigation development and at the same time increasing the effectiveness and
efficiency of SSI, improving the knowledge and capacity of the sector has a paramount importance
of providing updated and comprehensive technical guidelines together with other inputs.
The country national plans, which spell a range of economic and social objectives and strategies
meant to enhance growth and developments. Projects provide an important means by which
investment and other development expenditures foreseen in the plans can be clarified, justified
and realized. A project is a complex set of activities where resources are used in the expectation
of returns and which lends itself to planning, organizing, financing and implementing as a unit.
Project planning and organization is an initial stage for the execution of projects. Planning is a core
area of all the stages that shape the framework and guides the overall project phases in its
implementation of sequential procedures. These stages of planning should be in place prior to the
start of projects in the irrigation implementation institutions of the respective regions.
Accordingly, the planning is prepared for each of the phases and includes - physical plan with
critical path, financial plan, person power, logistics and other resources required for each phase.
The plan begins with the project phase, idea initiation, and formulation of the projects. The
schedule, inputs, and outputs depend on the type of project phases. Therefore, formulation of
project phases is an initial aspect of project planning and organization as covered in this guideline.
Review of the respective region existing and working guidelines and manuals indicate that most of
the regional state's guidelines do not consider one of the important phases' i.e. The planning and
organization aspect as an independent project phase. Therefore, this guideline is prepared with
the intention of managing, resolving the problems of Irrigation project planning and organization.
1.2 OBJECTIVES
The main objective of this guideline is to produce a more inclusiveand simplified directionto assist
professionals (planner, manager, decision maker, implementers)to clearly set the procedures,
criteria, and guidelines to be used in proper planning and organization of irrigation projects.
According to the previous work assessment, not all regional states guidelines/ manuals gave
adequate attention for planning and organization of an irrigation project. This guideline supposed
to be a major springboard for site-specific irrigation development proposal. Considering the above
indicated and other gaps, this guideline includes all-important components and procedures of
small-scale irrigation project planning and organization issues.
In this respect, planning aspects of each phase will be discussed, namely: SSIP Initiation,
planning, and Organization, Planning for Site Identification & Investment Prioritization, Planning for
Feasibility Studies, Detail Design and Tender Document Preparation, Planning for Contract
Administration, Construction Supervision and Construction, planning for Operation and
Management phases including Monitoring and evaluation.
Project initiation, planning, and organizations are the processes of formulating work procedures or
methods for arranging resources (person power, logistics, budgets, and materials), time schedules
and implementing identified project works or activities. Similarly, a project is an essential part of
the overall planning and composed of prescribed activities, time boundary, costs and deliverables
as a final benefit for intended target beneficiaries. Sustainable irrigation project implementation
and development requires an organized project idea initiation, planning and organization tasks.
However, the absence of organized project planning and organization will result in poor potential
site identification, study and design, which in turn resulted in the impediment of implementations.
Similarly, weak planning and organization will result in ineffective contract administration and
construction supervision, including construction itself that automatically lead to failure of SSI
projects. These again drop to poor operation and maintenance condition and in most time resulted
in non-functionality of most irrigation schemes. Therefore, prior to any irrigation project
development, good project initiation, planning, and organization, including quality control will
endure all the issues and problems at each phase and resulted in sustainable SSI scheme
development.
2 PLANNING OVERVIEW
The government of Ethiopia has a national macro-level development plan and adopts national
development plans, policies and strategies every five years. Accordingly, the national plans,
policies, and strategies have emphasized on both smallholder and commercial irrigation and
drainage development as major drivers of agricultural growth and transformation of the country.
Some of the policies, strategies and national plans linked with irrigation development includes:
Water Resources Management Policy (2001), Water Sector Strategy (2001), Agriculture and Rural
Development Policy and strategies (2003), Plan for Accelerated and Sustained Development to
End Poverty (2005), Agriculture Sector Policy and Investment Framework (2009), Growth and
Transformation Plan-I (2010), Small Scale Irrigation Capacity Building Strategy (2011), Climate
Green Resilient Economy Strategy (2013), Growth and Transformation Plan-II (2015).
Similarly, the Plan for Accelerated and Sustained Development to End Poverty (PASDEP) adopted
for the period 2005/6-2009/10 has given prime importance for rural and agricultural development
with the aims for accelerated, sustained and people-centered economic development.
Following the PASDEP, Growth and Transformation Plan (GTP-I and II) adopted for the period
[
In the planning direction of GTP, smallholder farming will continue to be the major source of
agricultural growth with the shift into commercialization. To complement this development
objective, concentrated policy support should be provided for private investment in large
commercial farms. Fundamentals of the strategy include the shift to producing high value crops, a
special focus on high-potential areas, facilitating the commercialization of agriculture, supporting
the development of small and large-scale commercial agriculture where it is feasible. In general,
agriculture will direct on placing major effort to support the intensification of marketable farm
products by small and large farmers for domestic and export market.
[[[
During the GTP period, it is planned to transform agriculture sector to a high growth path in order
to ensure the food security challenge of the country and to curb inflationary pressure as well as
broadening the export base of the country. The sector also serves as a springboard to bring about
structural transformation in the long run through contribution to industrial growth. To promote
multiple cropping, better cope with climate variability, and ensure food security, the Growth and
Transformation Plan (GTP) has adopted an agricultural development and focus strategies include;
Scaling up production and productivity of land, labor and available natural resource use
based on agro ecological suitability.
Specialization, diversification & strengthening agricultural production and marketing system
Strengthen extension service for majorities of smallholders
Provide support for the private large-scale commercial farms.
Promotes the appropriate use of rain water and another water source,
Improve water use efficiency by expanding of irrigation schemes with special attention to
small-scale irrigation schemes development.
Strengthen public participation in the planning and implementation and take affirmative
action is to enhance women's participation at woreda and kebele level; engaging and
mobilizing the public in the construction of local infrastructure development activities
(road, schools, health stations, irrigation and others).
Similarly, GTP-II also prepared in a participatory approach in a more comprehensive manner and it
assesses the gaps observed under GTP-I implementation process and tries to fill the gaps. In
general, the agricultural Transformation Plan-II has adopted a range of interventions and public
investments directed to basic infrastructure development mainly road, market infrastructures, and
others to support and scale-up on the success in economic growth of the country. In line with the
general development policy and strategic framework, several attempts underway in the study and
design of small-scale irrigation project initiated by the respective regions with a vision towards
water centered irrigated agriculture development for the smallholder benefit through efficient
utilization of the existing water resource. These kinds and similar policies, strategies and
regulations shall be analyzed during the planning of SSIP study and design and serves as an input
to the formulation of the projects.
The Terms of References prepared for conducting the study and design of SSIPs could serve as
one of the sources for indicating the types of project phases practiced in Regional states. The aim
of the TORs is to serve as a guiding framework for project studies and design, but it contains
implementation and operation aspects. Despite these limitations, they provide an indication for
project phases, specifically for study phases. In this respect, some TOR is referred and reviewed.
The available regional TORs that are reviewed and presented here refer to Oromia, SNNPRS,
Amhara, Tigray and Benishangul Gumuz Regional States as well as AGP project at the Federal
level.
Under the scope of the study presented under the TOR entitled “Oromia Water, Mineral& Energy
Bureau, for feasibility & detail design studies of small scale irrigation projects”, it was mentioned
that the OWMEB and later Oromia Irrigation Development Authority (OIDA) conducts a
reconnaissance survey or prefeasibility study before feasibility study and detail design. The point
that has to be taken from this presentation is that the bureau performs reconnaissance and
prefeasibility tasks and contract out a feasibility study and detail design then construction.
This approach has limitations‟ It is not clear whether the reconnaissance survey and the
prefeasibility studies are performed under a single or different phase. Second, the planning aspect
is not mentioned as a component of project phases. The process of Implementation and
operational phases were not clearly given. Moreover, the project identification is not discussed and
is not known whether it is skipped or combined with reconnaissance.
One of the Terms of Reference issued in the RFP by Irrigation Development and Scheme
Administration Agency for the study and design of Small Scale Irrigation Schemes (SNNP,
Hawasa, June 2015,) indicated different project phases that the consultants have to follow to
conduct the assignment provided.
Here, the assignment of the consultancy service is proposed to have three stages: 1) Identification
of most potential/prospective sites, 2) Preliminary Planning & Design or Reconnaissance/pre-
feasibility study for identified/prioritized SSIP and 3) Feasibility Studies and Detailed Designs
including preparation of bidding documents and Operation and Maintenance (O & M) manuals of
the most potential SSIP.
contract administration, and construction supervision phase, and operation and maintenance
phases, as there is no SSIP guideline in the region.
The TOR demanded to undertake a mixed phase‟s work at a time since it lumped Preliminary
Planning & Design or Reconnaissance/pre-feasibility works into one. On the other hand, the
identification stage can involve all the tasks of resource identification, reconnaissance,
prefeasibility and preliminary design works for all potential candidate projects and then transfer to
feasibility and detail design works for a viable project screened using investment prioritization
criteria.
The TOR of this region, under the scope of services, states that the given project is studied at
identification level and the next assignment is aimed at the execution of the pre-feasibility study,
feasibility study and detail design and preparation of operation and maintenance manual. These
studies are expected to be accomplished within two major phases. These phases consist of Phase
one - Prefeasibility and preliminary design and Phase two - detail design and operation and
maintenance preparation. Therefore, the entire project consists of 3 steps which are a)
identification phase, b) Prefeasibility and preliminary design phase and c) detail design and
preparation of operation & maintenance.
The TOR is provided for selected projects, which are given by name and location and does not
indicate if this is the Regional state standard project phases. In this respect, it does not show the
level of identification study whether the reconnaissance study is included in it or not. Besides,
Project Planning and Organization phase is not shown.
There is no mention of any procedures /standard steps to adopt for implementation and operation,
which include contract administration & construction supervision.
One of the Terms of Reference issued by the Bureau of Water Resource Development for the
study and design of Small Scale Irrigation Schemes of Agricultural Growth Program was referred
to here.
As it mentioned under the introduction part of the TOR, regional governments have conducted
identification study, reconnaissance surveys and/or prefeasibility for the SSIPs under
consideration. Apart from mentioning the accomplished names of studies, it is not, however, clear
whether these mentioned types of studies are conducted in one single phase or not. The scope of
the service given in the TOR is mentioned to be limited to the Feasibility Study and Design of SSIP
schemes. Besides, Operation and Maintenance Manual and preparation of tender documents are
provided as part of the assignment.
[[
We have fallen from a review of these TOR and discussions with regional staffs that; SSIP project
study steps followed in the Amhara Regional state is not yet standardized.
The guidelines which have been prepared (but not yet finalized) by the Tigray Water Resources
Bureau are referred to identify the types of project cycles followed by the region and then
augmented with regional stakeholder consultation.
One of the guidelines entitled “Tigray Water Resources Bureau, Socio economy Guidelines for
Irrigation Projects” gave the different project cycles for the study in their sequential orders. As per
this guideline, project cycles to be followed are 1) reconnaissance, 2) pre-feasibility, 3) feasibility
and 4) Detail design. In here tender document preparation, contract management, and
construction supervision are missed.
As could be referred in another guideline entitled “Guideline Manual on Feasibility Study, Detail
Design of Irrigation Projects”, the project cycles provided in different places in the guideline
document could be summarized as 1) Project Identification, 2) Feasibility study and preliminary
design & Costing, 3) Detail engineering design & Costing, 4) Tender document preparation &
Reporting, and 5) Preparation of Operational manuals & Reporting. In here too contract
management and construction supervision are missed.
The limitations in the region are; there are no clear, definitively established stages of project
cycles, which declared as regional applied standard in the study, design, and implementation of
SSIPs. There is a differencein project cycles between the different groups, for example, the first
does not include identification and starts at the reconnaissance stage. Though it looks like
shortened and time effective, the second approach has not made clear how to handle
reconnaissance and prefeasibility study. Therefore, there is a need to standardize the project
cycle.
Project phases are not clearly and separately provided in the existing national and regional
guidelines. There is an attempt at referring to different project phases that should be followed in
the preparation and implementation of SSIPs. Different guidelines are reviewed; the findings are
summarized as follows. The result shows that different guidelines recommended different phases.
i. The guideline, Manuals and Standard Design of Small and Medium Scale Irrigation
Projects in Ethiopia, the FDRE Ministry of Water Resources, July 2002
Different types of project phases are provided within one of the guidelines under the title of “Part E:
- Study Guideline for Irrigation”. The document simply explained conventional project cycles,
which are 1) preparation for project formulation & identification 2) reconnaissance 3) pre-feasibility
4) feasibility 5) detailed design 6) construction and 7) monitoring & evaluation.
Unlike the conventional project cycle for the study of small and medium scale irrigation projects,
the guideline lumped the three phases. (I) Preparation for project formulation, (2) reconnaissance
and (3) pre-feasibility as one stage and named "identification and reconnaissance phase" followed
by the feasibility stage. Thus, the guideline proposed four phases namely I) identification and
reconnaissance 2) feasibility 3) detailed design and 4) construction. It also stated that the adoption
of the convention project cycle is not ruled out if circumstances warrant its use.
The guideline does not consider the planning aspect as an independent project phase and is
provided under a title of the project. Besides, the construction phase is given in its broad sense
without distinctively sub-classifying into contract administration & construction supervision.
Operation and maintenance aspects have not given due emphasis.
Phases of SSIPs in this manual are discussed in “steps in the study and design of irrigation
projects “provided under the title of “study & design” guideline. They are given as 1) Resource
Identification, 2) Pre-Feasibility (some part) & 3) Feasibility (some part of Pre-feasibility and
Feasibility) and Basic Design. The pre-feasibility study is split into two parts. Some parts of the
study are undertaken at the pre-feasibility phase while the remaining part of the feasibility stage.
Resource identification is executed before the pre-feasibility study. The last stage is the design
stage, which is expected to be continued right after the result of the feasibility study is found to be
promising for the continuation of design work.
Resource identification is not supported with prioritization and ranking steps and thus will not
enable to help determine which project to proceed and which projects to be rejected or postponed.
Besides, splitting the prefeasibility phase into two phases of prefeasibility and partial feasibility
studies will not lead to conclude the potentiality and alternative options of the project that has to be
promoted to the further level of studies. This phase should show the decision whether to study the
proposed project further without incurring additional resources at the latter stage of the feasibility
level. Similarly, the feasibility study should take all its own contents instead of performing some of
the tasks of prefeasibility studies.
The proposed phases of resource identification and prefeasibility level are thus not established in
the way, which can reduce cost and time, whereas they transfer the decision to invest, or not to
the feasibility level. The prefeasibility and feasibility studies have split indivisible study
components, which however can result in an integrated decision criterion. In addition, instead of
conducting detailed design after the results of the feasibility studies are known, it could have been
better to undertake the preliminary level of designs so that the level of accuracy would significantly
be improved later in detail design stage. The SSIP project stage proposed here are not common
and will lead to ambiguities.
iii. Small Scale Irrigation Project (Gravity) Technical Handbook, Ethiopian Social
Rehabilitation, and Development Fund (ESRDF) 1997
The different project phases provided within this guideline are under the title of “component 1,
Guideline on SSIP”, and provided under chapter title of Project Formulation and implementation
cycle. The phases provided in this guideline are: 1) Project formulation and identification phase 2)
Reconnaissance phase 3) Feasibility phase 4) Detailed design phase 5) construction phase and 6)
Handing over. Besides, monitoring and evaluation are given at the center of the phases indicating
that it is applicable to all the different phases.
From the above given project phases, whether the pre - feasibility study is omitted or combined
with one of the indicated phases is not shown. Since the outputs of the pre-feasibility phase enable
to show better projects, their tasks should have been seen to which project phase it is merged.
This manual provides various project stages in Table 1 under the title “Project development stages
and activities for smallholder irrigation (Adapted from Chancellor and Hide, 1996)”. These phases
are classified into 8 distinct activities, namely 1) Project Identification, 2) Pre-Feasibility, 3)
feasibility, 4) Conditional Approval, 5) Detailed Design, 6) Final Approval, 7) Implementation, 8)
Monitoring and Evaluation. Such international experience of project phasing helps to establish
project phase applicable for SSIPs. However, the following limitations are observed.
The initial stage, which is project planning is not included in this system. Project identification is
perceived only from the Farmers‟ request for assistance point of view, doesn‟t include planned
project interventions, and doesn‟t include ranking and prioritization aspects. The degrees of
identification are limited to only requests coming from farmers and thus simply enter to a higher
level of prefeasibility phase without undertaking screening activities. The two stages i.e.
prefeasibility and feasibility studies take substantial time and cost whereas they are separately
recommended as separate phases. Implementation is given without its breakdowns into contract
administration and construction supervision components. Besides, project operation and
maintenance are not provided as a separate phase. One of the important points provided in the
document is approvals. However, as such, they should not take own phases and should be part of
each phase whereby work is done shall be appropriately handled.
This guideline has proposed 3stages, namely 1) Project Ideas, Profiles and Preliminary Screening
2) Pre-Feasibility Study 3) Feasibility Study.
The guideline is prepared as a general framework for public sector projects and doesn‟t address
SSIPs in particular. It focuses on mainly study parts. The reconnaissance study does not give
consideration by the guideline. Besides, it discusses up to the study phase, whereas the
implementation and operation phases are not included in the document.
Many of them are focusing on reducing the project phases and in doing so; they have underlined
the importance of the resource identification stage though did not produce identification guideline.
Description of Contract administration, operation, and maintenance phases are skipped by many
of the reviewed documents. Site handover of project designs is not provided almost with all
guidelines. In general, in all guidelines, a completed project cycle that ranges from identification up
to operation and maintenance is not given.
Clear steps of project phases have not been adopted in all regions. Some part of Prefeasibility
phase is given to the identification and feasibility of some stages, which reduces the importance of
profitability studies. A preliminary design is omitted and only detail design is recommended. The
guideline focused on identification and planning phases and do not include operation and
maintenance stages which are crucial activity.
The guidelines, which are prepared, by MOWIE and the then EVDSA concerns mainly for large
and medium projects and contain many project phases, which are not applicable for SSIPs. The
guideline that is prepared by MOFED serves for public sector projects in general and is not directly
applicable for SSIPs.
Irrigation potentials are mostly considered as the availability of water; land and labor resources in
a particular area. Several previous studies have attempted to estimate the irrigation potential of the
country, focusing on the surface, ground or rainwater, or some combination of these. MOAL
recently estimated SSI potential to be 10.10 Million hectares, of which 2.8 Million hectares are
already developed. Others sources like IWMI‟s Irrigation Potential study (2010), reported that;
Ethiopia has surface water, groundwater and rainwater sources that can develop for at least 5.3
million hectares of irrigation land. This means that up to one-sixth of the country‟s cultivable land
could be irrigated through existing water sources – which is a significant increase from the current
levels. This includes 3.7 Million hectares from gravity-fed surface water and an additional 1.1 and
0.5 Million hectares from groundwater and rainwater harvesting, respectively.
Recently, study conducted by MOWIE has indicated that the irrigation potential is over 20 million
hectares. The water resource including ground water is estimated at more than 220BCM. All these
cases prove that the available potential land, conducive climate, availability of surface, ground
water resource and rainfall, favorable social and infrastructure condition of market linkages,
availability of inputs, technologies, and support institutions will vitalize SSI development.
4.2 OPPORTUNITIES
The basic opportunistic considerations regarding irrigation developments in the country are but not
limited to:-
Government‟s policy, strategies, strong political commitment and encouragement to the
private sector and public enterprise's involvement in irrigation development,
Emphasis and priorities are given to irrigation in the growth and transformation plan of
the country,
Indigenous knowledge and the introduction of promising household water harvesting
and micro-irrigation technologies,
Abundant water resources, climate, and land suitability,
Availability of inexpensive labor,
Availability of suitable lands and water resources potential for irrigation developments,
especially in arid areas of the country,
The existence of some equipped institutions,
Availability of well-established infrastructure
Availability of local &neighboring markets,
The existence of support from development partners
Therefore, this guideline will support planners and implementers to initiate and plan
SSID and make use of these immense potentials.
[
[[[
4.3 CHALLENGES
Therefore, SSI implementer shall initiate, plan and establish an SSI organization system, which will
review, and assess the potential, opportunities, and constraints of the potential and to is developed
SSI area.
Development of irrigation projects follows well-defined phases and each of them takes projects a
step forward milestone in the development cycle, based on the findings from the actual and
previous stages. The investigation and planning pass several milestones before projects are
acceptable for implementation and subsequent operation. The stepwise and sequential
development of small scale irrigation project planning shall be technically sound and economically
prudent and time conscious. While planning SSIPs, the time element must be given priority to be
substantially acceptable. Optimum planning time is often achieved through the reduction of
planning steps without losing efficacy and quality in the process.
In this respect, planning time can be saved by joining identification, reconnaissance and
prefeasibility studies under Site identification and prioritization phase as well as feasibility and
detail design studies to go as one-step. Therefore, this guideline advises the following project
phases;
The project initiation stage is the first stage within the SSI development phase, as it involves
starting up a new project. It identifies a need or an opportunity and devices a project to address
that need. During the initiation, the problem or opportunity is identified, a possible solution will be
hypothesized or defined, a project is formed, and a project team that can handle planning will be
appointed to envisage and draw pertinent project notion. The notion may indicate the project type,
location, crude scope and responsible institutions.
Project planning is the main and initial framework for all subsequent project study phases and
includes overall preparation of types of project activities, schedules and resource identification and
arrangement of time, human, Equipment and cost/budget. Thus, it enables to decide on what is to
be achieved when to achieve, how to achieve it and enables to look forward and anticipate the
future. Project planning, in general, is a core area of all the stages that shape framework and
guides the overall project phases.
The planning stage produces a roadmap that shows various stages of project phases that have to
be followed from identification up to operation and monitoring and evaluation phases of SSIP. The
different types of project phases are as mentioned in the preceding section are identical, feasibility
and detail design, contract administration, construction& construction supervision phase, and
operation and maintenance phases. It also shows the size of irrigation systems that have to be
followed for small-scale irrigation projects.
Project Organization and Management refer to the organization type (unit, team, project office
etc.), Structure, roles, and responsibilities. Here the Project Coordination Office (PCO) can be
modified according to the project context and size.
Identification is the second phase coming after the planning phase. It covers a wide variety of
study components that will be undertaken to identify and select a better project. This phase is
classified into two stages:
There may be many small-scale irrigation project possibilities and a large number of alternatives to
be investigated. Each project has different physical properties and conditions, which have to be
considered in order to serve as a basis for planning and design. Therefore, the first part which is
the identification of potential irrigable sites are carried out as part of an inventory of water and land
resources; to identify, register and catalogue irrigation resources existing in a given sub basin,
areas and sites. They may also be carried out region wide to prepare inventories of the overall
irrigation potentials.
The third phase includes a feasibility study and detail design, which will be conducted in the best
ranked and prioritized project decided at the identification phase. During the feasibility and detail
design of comprehensive project studies and detail, final design should be conducted for each
prioritized and ranked project. The feasibility study is the logical conclusion of planning
investigations, technical and economic evaluation of a proposed project.
The types of studies and designs that would be performed at this stage are:
Hydro-meteorological analysis and water resources planning,
Topography survey and mapping,
Soil survey and land suitability evaluation,
Irrigated agronomy,
Socio economy,
Organization and management,
Watershed management,
Geology and Geotechnical investigation,
Engineering
Operation and maintenance
Environmental Impact Assessment
Financial and economic analysis
The output of this stage will be independent and synchronized technical report of each discipline
including detail engineering working drawings. The report should clearly indicate the project
technically, socially, financially feasibility and parallel the report should explain how the project can
be Environmental and socially acceptable. Based on this report the client can decide to take the
project to the next phase or to consider further options. The detail study and design of the projects
should be done in accordance of „‟The National Guideline for SSID-feasibility and detail design‟‟.
The next phase in the life of the project is its infrastructure establishment, contract administration,
and construction supervision. This phase includes the execution of the outputs of feasibility and
detail design phase: - procurement of consultant and contractors, managing the contract,
construction supervision and ensuring the quality. More specifically, implementation of different
types of activities, which are listed in the contract, detail design and work drawings,
commissioning, as built drawings, operation and maintenance manual, personnel training on the
operation and management should be performed.
This phase in its inherent nature is continuing and routine in the life of a project. It commences
when projects are completed or at some stage of project construction. This phase includes
commissioning, the operation of structures, irrigation scheduling; agricultural development,
capacity development (beneficiaries and nearby experts);maintenance and replacement,
monitoring & evaluation.
The demand-led approach starts with the consent and participation of beneficiary communities in
the project conception, preparation, construction, construction supervision, operation and
management phases. Therefore, the project will be a demand driven type and implemented in
such a way that the first initiation has to come from the beneficiary communities.
Considering the beneficiaries' incapability to identify their resources and needs in a manner that it
is required in the form of the project proposal, governmental institutions can be involved to assist
them in various forms such as promotional works, preparation of technical proposals and project
preparation following the request of the project beneficiaries.
Many Irrigation Projects have failed because farmers and local communities were not involved in
the planning process. Farmers heavily populated on irrigation or watershed development project
areas. Therefore, any irrigation development plan will not be successfully carried out without their
support or participation.
Several ways and methods could be employed to involve farmers in the planning process. For
instance, existing farmers' organizations can be included in the survey and planning body. Local
irrigation development committees can be organized in planning and implementation purposes.
Conducting individual irrigation project planning or group planning with the farmers will obtain
details on how farmers will use, develop and protect their farms. Involving communities in planning
irrigation infrastructures needs are also scopes of the bottom-up approach. During such planning
processes, government policy and farmers' needs can be fully discussed. For irrigation
development plans to be useful and workable, they should be well understood and accepted at the
grass-root level.
Irrigation Development Planning follows an iterative approach. Before a final plan is prepared,
many studies, assessments, alternative water sources considerations, technology option, and
revisions will have to be made. Generally, a preliminary or interim report should be made by
gathering the results and reports of each team. After receiving comments from all the related
sources, a review and revision period begins. The process may need to be repeated several times
to find the best final results of the plan.
A final Irrigation plan is not like a blueprint of an irrigation system. The Irrigation Development Plan
should be considered as a starting point and should be kept under constant monitoring and
adjustment. There are many reasons for these cases. First, project life may cover more years and
many unpredictable things, caused by nature or man-made, may happen during the period. New
problems need new policies, approaches, and techniques to cope with them. Second, irrigation
development is a complex task dealing with social, economic, cultural, legal, institutional, and
physical problems. Difficulties may arise during implementation and many times the original
strategies and goals need to be revised. Therefore, learning by doing is a very important process;
hence, any such plan should be kept flexible.
Flexibility means leaving room for future adjustment, modification, or revision. Consequently, a
monitoring and evaluation process should be built into the plan for this purpose. This also means
that the plan targets should be progressive, i.e. smaller at the very beginning and gradually
expanding with the added experience.
A number of SSI schemes have failed due to lack of catchment-based planning and development.
Catchment-based planning is important from the viewpoint of water resource planning,
assessment of soil and water conservation requirements and the preventing of conflicts between
downstream and upstream users. Scheme based approach should be replaced by the catchment
based approach. Hence, catchment water balance studies should be undertaken to determine the
potentials we have in the given catchments.
Of all, demand is driven and participatory approach is the most effective and feasible approach if
supported by the other planning tools as discussed above.
The SSIP plan has to be integrated with other existing and planned developments mainly
agricultural (extension, improved input & technology, research, market & value chain...etc.),
natural resource (Watershed management, land use…etc.), Socioeconomic, and of all cross
cutting issues such as women and youth, nutrition, climate smart / resilient, HIV, environment,
..etc.
Moreover, a shift from a single discipline approach to multi-disciplinary approach is crucial for
sustainability and balanced emphasis that required interaction and technical agreement among the
different disciplines, institutions and involving in irrigation and agriculture.
[[[
The interdisciplinary approach should be pursued among scientific disciplines, through cooperation
and coordination among the relevant specialized organizations of government at all levels and
within the extension services and between subject matter specialists. An interdisciplinary approach
requires experts to persistently cross-disciplinary boundaries in their understanding of local
realities and to recognize the structures, functions, systems, and patterns of interdependence that
are the local reality.
The involvement of all relevant Federal, Regional, zone, Woreda and kebele, level stakeholders in
the planning, study, design, construction, and operation of irrigation schemes should be given due
attention. Woreda stakeholders should be given the opportunity to participate at all levels of
implementation.
Full participation of beneficiaries and all stakeholders in the planning, study, design, construction,
and O&M works of SSI schemes has to be made more effective and real. The plan seeks to
establish a sense of ownership and control by the beneficiaries over their own schemes.
Building ownership and commitment through participation has often been difficult to achieve in the
past. The conventional sequence of identification/preparation, carried out against tight deadlines
by external planning teams, has seldom allowed time for genuine participation (which should go
beyond mere consultation), either by government staff or farmers. On implementation, government
irrigation engineers, for their part, have usually seen irrigation only from engineering, rather than a
farming or social, perspective. They have been reluctant to adopt participatory approaches with
farmers, mainly because of a misplaced belief that farmers are unable to understand or contribute
to technical matters, or because of concerns that participation might delay implementation or result
in design changes that compromise the quality of the final product.
Undue delays in project approval and implementation are undesirable, not least for the farmers;
but taking time over stakeholders' participation in planning does not necessarily mean delay. It can
often pay dividends, by preparing the implementers, ensuring smooth start-up, building farmers'
commitment to change, and might ultimately lead to more rapid implementation and a more
sustainable development impact. Experience has shown that the ultimate scheme design usually
benefits of involving the users in the planning process. Farmers, or at least those with some
experience or knowledge of irrigation, from the poorest illiterate smallholder to the richest well-
educated commercial farmer, usually have practical ideas of what works and what does not, from
their detailed local knowledge of weather patterns, hydrology, soils, markets, and so on.
Communities often have strong preferences regarding the nature and location of development that
needs to influence planning, such as aligning a canal to avoid excavation in sacred ground.
[
As described above, involving farmers and stakeholders in system design can also often result in
significant cost savings, particularly if the farmers themselves are expected to take a share in the
equity by contributing to the investment costs. The sound engineering is essential, but it can
nonetheless take account of the farmers' experiences and preferences. Yet engineers still too
often ignore farmers, as a possible source of system design input and as a result, schemes are
often inappropriately planned against the interest of the beneficiaries usually resulting in the un-
functional system.
In the planning process, first analyzing and building on local knowledge and practices before
considering innovations should be the basic parameter. The beneficiaries' perspective should
always be the point of departure for analysis of problems and solutions. Avoid an interventionist
approach. Instead, during planning listen to farmers and strive to understand specific local
contexts. Respond to the problems identified by beneficiaries and facilitate planning and solutions
based on techniques/technology they see as acceptable and useful. Participate in the fulfillment of
their goals and understand their opportunities and constraints. Strengthening institutions that
already exist with the aim of increasing their effectiveness is important. Try to minimize the
creation of new water management institutions over the traditional ones.
Adoption of irrigation technology is limited due to incorrect attitudes and perceptions about the
importance of irrigated agriculture. A number of irrigation schemes have failed to achieve the
intended goals due to lack of public awareness. Hence, the degree of public awareness of irrigated
agriculture is of crucial importance, awareness creates forums for the beneficiaries, and other
stakeholders shall be arranged. The beneficiary‟s participant shall start right from the inception of
the project throughout O & M including M & E
Based on the existing institutional arrangements MOA, BOWIE/OIDA & ICSAA, BoANR is the
planning and implementing institutions of SSI projects. The MOA is responsible for the overall
coordination of SSIP at Country level. However, the general direction is to use other existing
institutional structure at all levels (Federal, Region, Zone, Woreda, Kebele, and beneficiary level)
such as CPA, Marketing & Input Agency, Research organization, Youth & Sport, Women &
Children, RLAU, EIA, IWUA its offices. These offices at all levels shall be encouraged for their full
participation and demonstrate strong ownership and commitment in the planning, organization,
and implementation of the SSI Project in their respective regions. The implementing institution or
the organization needs to be more strengthened and empowered with respect to its planning and
implementation capacity at a different level.
Study, design, construction supervision even construction can be executed by implementers own
force in most cases, if and only the implementing agent is supposed to have adequate capacity for
the work, the work doesn't attract private organization due to different reasons, etc. Whatever, the
case it is not advisable for the stakeholders to handle rather concentrates on regulatory and
supervisory activities including technical support of the beneficiaries at all stages.
Therefore, it is recommended that; local consultants, contractors and technology suppliers shall be
deployed for study and design, construction and construction supervision of irrigation schemes.
These groups have to be encouraged to abide by; professional ethics, standards, contractual
obligation, laws and regulations and above all prove their commitment. During planning, it has
been made sure who is who and assesses the history and profile of these groups.
The first stage in the project life is to find the project idea, hence initiation is the first and the most
essential stage in the irrigation project formulation. At this stage, multiple ideas regarding a
required intervention in a specific area to address an identified problem have to be developed.
This idea is usually hatched through discussion with the community, specialists or local leaders in
a community as need-based issues and crystallized into the proposal. This stage is the idea
generation phase at which the concerned community or the concerned government body or NGOs
take the initiative to point out the idea of SSI development. The initiated idea might be a new
project, modernization of traditional irrigation from rivers, springs, ground water development or
water harvesting irrigation development.
8.2.1 Communities, groups of farmers, Individual Innovative Farmers, and Local Leaders
The community and local leaders will usually have important ideas, which they, together with the
local people, have identified as being important in improving the welfare of the people. In the case
of Irrigation Development, for instance for a completely new SSI scheme, a group of farmers
through the Kebele Administration request or suggest or apply the existence of water and land
resources in their locality and generate the idea of a new SSI scheme development. Similarly, in
the case of a traditional SSI system, water user groups, the “water fathers”, or existing informal
water users' committee will suggest or point out the idea for the improvement/upgrading of their
scheme. In a modern SSI scheme, the existing water user groups, water users‟ committee, or
irrigation cooperatives (if any) will also suggest or point out the idea of rehabilitation of their
scheme. If the project idea comes from the farmers themselves, it has a significant contribution to
project sustainability and future managements'.
Ideas will usually tend to come from technical specialists, who by virtue of their experience and/or
research findings will give useful information, which may lead to the local level economic
development and agricultural transformation, through the improvement of production and
productivity of crops and livestock.
Likewise, the existing water user farmers or groups, water user‟s committee, IWUA (if any),
Irrigation Cooperative (if any) or village leaders or Kebele Administration may point out the idea or
request the DAs and/or staff of the Woreda office to assist farmers with the preparation of the SSI
development idea formulation. It is also possible that DAs or the staff of the Woreda office would
identify the opportunity to develop a new SSI scheme, improve an existing traditional SSI scheme
or rehabilitation of an existing modern SSI scheme. In that case, the DAs and/or Woreda staff
should consult the concerned farmers and assess if they would be interested. If the concerned
farmers are interested, the DAs and/ or Woreda staff may support them with the preparation of the
SSI development idea formulation.
In all the cases, the guiding principles and strategic issues for project idea initiation are that the
project should be demand driven and ensure public participation. This requires that the project will
be implemented in such a way that it shall be a demand driven type in which has to be initiated
that, the first project idea has to come from the community themselves. Therefore, the undertaking
of project initiatives for study and design, construction, operation, and maintenance should be
compatible with the community demands, even though some preparatory works are undertaken by
local institutions due to technical limitations of the community. Under this situation, the community
with the support of the kebele administration council will point out their idea or request to the
nearest Woreda irrigation development institution for the successive stages of project
development.
Currently, most governments in the world are moving away from directly initiating community
projects. However, government produces short and long-term national development plans, which
spell out the directions of what the government is likely to do to achieve certain targets in various
sections of the economy and help as guidelines to various organizations to plan in detail. The
information contained in these documents is useful in generating ideas for new projects. The
emphases are on the local participation of the people in all development matters. All rural
development policies and strategies of the Ethiopian Government expresses the intention to have
all the smallholder farmers‟ participation in the economic development of the country in order to
increase the efficiency and effectiveness of development projects. Therefore, individuals using
government policy guidelines as a source for project ideas must make sure that they operate
within the overall national policy framework as contained in the relevant documents such as the
country's irrigation sector policy documents, basin master plan studies, irrigation potential
assessment, and other similar documents.
For commercial projects in this case out growers system with small holders, entrepreneurship is an
important source of the idea. Entrepreneurship includes the characteristics of perception of
managerial competence and motivation to achieve results. Although entrepreneurship skills have
been passed on from one generation to another, along with family and socioeconomic circle, it has
been recognized that programs for entrepreneurship development will help individuals to come up
with useful ideas, which can be translated, into viable projects.
Project ideas also emerged from international and bilateral development partners such as WB,
AfDB, FAO, IFAD, USAID, JICA, KOICA, Millennium Development Goal (MDG) /Sustainable
Development Goal (SDG) and others by themselves or through a request by the Government
Project Initiation and planning document (PIPD) have to prepare before the start of any SSIP or
group of SSIP with the intent to describe the basis for initiating, planning approach and plans,
projects organization and person power requirement, work activities and schedules, the budget
required and financial plan, Administrative procedure, procurement plans. The PIPD has to be
used as a working guideline during subsequent SSIP phases.
A project is an undertaking that has a beginning and an end. It is carried out to meet established
goals within cost, time and quality objectives. The project management unit brings together and
optimizes the resource necessary to successfully complete the project. These resources include
the skill, talents and cooperative efforts of a team of people (human resources), facilities, tools and
equipment, information systems and techniques and budget.
In all the case, Organization and Project Management unit is the systematic management of
projects in alignment with the achievement of strategic goals. The concept of organization and
project management unit is based on the idea that there is a correlation between an organization's
capability in project management, program management, and portfolio management and the
organization's effectiveness in implementing the strategy.
Therefore, establishing the functional type of organization and management unit for
implementation of projects will be optional and functional. The unit should be part of the
implementing institutions. This type of organization as one of the possible forms of realizing a
project in the implementing institution represents the possibility of its realizing in one, existing
functional part of the institution. The major advantage of this organization and management unit
can be grouped in the following way:-
There is a maximum flexibility in using the staffs and they could be engaged in many
different projects
Experts can exchange knowledge, the experience they possess and the unit has access
to any technical knowledge and the team can be the biggest resource of synergic
solution for solving technical problems
The project management unit serves as a basis of technological continuity and in the
continuity of procedural, administrative and other policies which will result when the
project continues in the implementing institution
The PMU is also responsible to identify and address cross cutting issues (Gender, Climate Smart
Agriculture, and Nutrition) in the planning, design, and implementation of SSI projects. Generally,
these are the recommended approaches and strategies for project organization and
managements. However, depending on the size and complexity of the project and whenever there
are cases PMU could be established in the respective regional irrigation implementing institutions
considering the existing situations at the ground level.
It is proposed that the implementing agency establish the independent project Management unit.
Moreover, the unit can form clusters in assigning group staffs in different areas to cover all parts of
the region for supervisory activities. This may include two administrative zones for regional staff
where regional experts to be included in the supervision team. Therefore, the delay and untimely
follow up intervention will be avoided. Figure 8.1 shows an organizational chart of the project
management unit.
Implementing Institution
BoWIE/ Irrigation Development
Authority/Agency
Human resources are the basic inputs in the Project Management Unit. Thus, the Project
Management Unit (PMU) is a group of staff members designated officially to work together full-
time, each with independents and group accountability, to coordinate and manage specific project
or group of projects. The PMU would be responsible for coordinating Irrigation Projects, planning
study and design, construction management activities mainly programming and supervising
projects, evaluation for quality assurance and implementation as well as overall administration of
budgeting, procurement, record keeping and reporting matters related to irrigation project
implementation. The PMU is also responsible to identify and address cross cutting issues (Gender,
Climate Smart Agriculture, and Nutrition) in the planning, design, and implementation of SSI
projects. Proposed staffing for Project Management Unit (PMU) is presented in Table 9.1 below-
[
Budget and basic logistics are very necessary for the full functioning of the Project Management
Unit (PMU). Detail budget and logistics plan expressed in quantitative terms that specifies how the
implementing institutions will acquire and use resources during project lifetime should be prepared.
The budget and logistics plan should indicate what the organization plans to do next year and what
result it expects. It should state how available resources will be needed and priority would be
placed and the performance required. Annual budget and the required logistics preparation must
be framed within a sound available resource and should be organized along the funding program
lines and procedures.
However, PMU in consultation with the Implementing Institutions is responsible for preparing their
requests on an annual and quarterly basis within the spending limits provided. The request should
be consistent with the notified ceilings or guidelines, and costs of the programs. It should be clear
and adequate for proper implementation, without any under or over estimated. Implementing
Institutions budget requests should clearly indicate the amount necessary to undertake planned
activities and programs. PMU with the implementing institution must coordinate the preparation of
the budget of their subordinate offices and give them appropriate directives. Moreover, the budget
approval mechanisms and eligibility and/or priority criteria, among others will consider the
technical feasibility of the proposed activities, the social and environmental impacts and the
synergy effect between implementing activities. A high consideration will also be given to the
cross-cuttings issues: gender, nutrition and climate change. Similarly, the Unit should be
supported with basic logistics such as vehicles, fuel, stationery and other necessary logistics.
Thus, the PMU will participate in the preparation, approval, and implementation of the endorsed
budget for the respective implementing institutions for the proposed intervention following its
budget rules, regulations, and schedules.
The project Management Unit (PMU) should be supported by the basic office and field equipment
in order to implement their day-to-day tasks successfully. The office of the PMU could be inside
the implementing institution compound or rented one in the adjacent of the implementing institution
offices. Office equipment such as a table, chair, computers, photocopy machines, iron shelf and
others are very necessary. Basic field equipment for the work such as GPS, electronic total
station, compass, scales, plane meter, meter tape, soil color chart, rock color chart, binoculars,
auger, level with its accessories, Laptop, software, geological hammer, infiltro-meter and others
are also required to be fulfilled.
Procedure and description of Administration and human resource management, Property and
logistics management, Financial Management including auditing system, procurement plan shall
beprepared as one of project planning task and discussed with all implementing stakeholders in
order all to make all actors internalize the overall project management system.
10.2 RESPONSIBILITY
Irrigation development implementing institutions in the respective regions shall be responsible for
preparing the TOR for the service required. Accordingly, drafting the TOR requires expertise in the
field of the assignment, as well as familiarity with the project background, knowledge of the terrain
and the site. If the capacity to prepare a good TOR is not available in-house, the implementing
institution should hire a competent external specialist.
Similarly, the scope of the services described in the TOR shall be compatible with the available
budget. If the transfer of knowledge or training is an objective, it should be specifically outlined
along with details of staffs to be trained, and so forth, to enable service providers to estimate the
required resources. TOR shall list the services and surveys necessary to carry out the assignment
and the expected outputs (for example, reports, data, maps, surveys). However, TOR should not
be too detailed and inflexible, so that competing service providers may propose their own
methodology and staffing. Service providers shall be encouraged to comment on the TOR in their
proposals. The implementing institution and service provider‟s respective responsibilities should be
clearly defined in the TOR. Generally, the TOR comprises the following main sections:
i. Project background
The background information summarizes the main features of the project and describes the
assignment‟s key objectives and general purpose. In particular, it should include the following:
Name of the implementing institutions
Project location
The rationale for the project
Project history (what has been done so far and by whom)
List of relevant studies and basic data
Need for consultants in the project and issues to be resolved
Activities to be carried out by the consultants
The TOR should precisely describe the objectives and expected results of the assignment. The
typical objectives of the assignment in most projects may include the following:
Sector and strategy studies or assessments
Studies on public sector reform, institutional and regulatory reforms, or leadership and
management change
Project feasibility before investment
Preparation of bidding documents and project detailed design
Project management and implementation supervision
Capacity building and training
Collection and analysis of data
Monitoring and Evaluation
The scope of the work/assignment in the TOR details all the main activities (or tasks) to be
conducted by the service providers and the expected results of those activities (or tasks). The
TOR should describe only the activities, the approach or methodology by which the results are to
be achieved and the TOR may provide strong suggestions on the approach and indications on the
methodology that the service providers could or should use to execute the assignment. Under
certain selection methods, the implementing institution can disclose its own estimated staff-months
or its estimated cost of the services, but not both.
Often the project may require a phased service provider‟s assignment. In such cases, the TOR
should be more detailed for the first phase and less detailed for the subsequent ones. The TOR for
the subsequent phases will be refined based on the outcomes of the earlier phases.
In a TOR, the scope of the work of the assignment is usually defined by addressing the following
issues (depending on the project features and objectives of the assignment):
The relevance of the assignment for the implementation of the project
Definition, scope, and limits of the assignment
The desired level of detail (level of design, accuracy, the composition of cost estimates,
and so forth)
The span of projections (time horizon, the life span of project components, and so forth)
Necessary comparison of the assignment with similar projects
Main issues to be addressed by sector or activity
Alternatives to be considered, and the main criteria to be used to compare them
Required surveys, special analyses, and models
Special equipment requirements
Implementing the institutional framework, organization, and legal setting
Transfer of knowledge, objectives, and scope
Language requirements
Units of measurement to be used
Need for continuity, such as data gathering
Quality management requirements (if needed)
Phased assignments are likely to require that the scope of work be modified, depending on
intermediate results. For instance, the scope of work for a feasibility study originally covering a
number of alternatives will be reduced if, during the execution of the assignment, some
alternatives prove not viable. Similarly, the scope of work can be expanded if more-accurate
studies than initially anticipated becoming necessary. In such cases, the TOR should clearly
indicate the circumstances under which a decision will be made by the implementing institution to
modify the scope of work.
iv. Capacity-building and knowledge transfer
If capacity building and transfer of knowledge are a specific objective of the assignment, the TOR
should provide specific details on the characteristics of the required services and propose
approaches and methodology for such services. The most frequently used implementation tools
include on-the-job training, formal stand-alone training for individuals, and twinning programs when
organizations are involved.
v. Reports and schedule of deliveries
The TOR should indicate the estimated duration of the assignment, from the date of
commencement to the date of the implementing institution receives and accepts the consultant‟s
final report or a specified completion date. The assignment reporting requirements should be
clearly specified. In particular, for inception and progress reports, there should be a balance
between keeping the implementing institution well informed and not forcing the service providers to
spend an excessive amount of time preparing reports. The TOR should indicate the format,
frequency, and content of reports, as well as the number of copies, the language, and the names
of the prospective recipients of the reports. For all major reports, an executive summary is
recommended as a separate volume. Similarly, the TOR should clearly identify and define the
output and deliverables required from the consultants, such as reports, data, maps, drawings, or
software. Depending on the assignment, the following reports are usually required:
(a) Inception report: this report should be submitted shortly after the commencement date of the
services. The report includes primary findings of the desk review, data collection instrument, data
collection methodology, potential bottlenecks that needdecision from client sides and others. Any
major inconsistency in the TOR, deficiency in implementing institution assistance, or staffing
problems that have become apparent during this period should be included. The inception report is
designed to give the implementing institution confidence that the assignment can be carried out as
planned and as agreed on in the contract, and it should bring to the implementing institution's
attention major problems that might affect the direction and progress of the work. The actual
revised methodology of the service providers to be employed should be clearly presented in this
report. Significant changes from the TOR scope should be supported by supplementary
agreement.
(b) Preliminary reports, at this stage data type, data source, data quality and verification of the
inception report should be conducted. Preliminary reports are required to inform the implementing
institutions of preliminary results, alternative solutions and major decisions that need to be made if
any.
(c) Draft report:- shall be submitted in order to give to the client or reviewing the findings and the
result. The draft report should include, but not limited to a technical report of all disciplines with
analyzed results and interpretation. Moreover, topography surveying, irrigation system layout,
abstraction system design should be presented. In general, at this stage near to completed report
should be submitted. The owner and the stakeholders shall review the draft report within a short
reasonable time, even check in the field, and give comments, suggestions for improvements. If the
service providers do not accept comments or recommendations it should be included in the report
the reasons for not accepting especially if it is for good reasons
(d) Final report: The final report is due at the completion of the assignment. At this stage
specification, tender document, working drawing album, refined reports of all disciplines approved
by the community should be submitted. The final report should incorporate all clients‟ comments
and suggestions.
(e) Progress reports: these reports keep the implementing institution regularly informed about the
progress of the assignment. They may also provide warnings of anticipated problems or serve as a
reminder for payment of invoices due. Depending on the needs of the assignment, progress
reports may be delivered monthly. For technical assistance and implementation supervision (in
construction, for instance) progress reports are best submitted monthly. Progress reports may
include a bar chart showing details of progress and any changes in the assignment schedule.
Photographs are a quick and easy way of conveying the status of a project, and their use in
progress reports is encouraged. For technical assistance services, progress reports also serve to
set out the work program for the following months. Each team member usually contributes to the
preparation of the monthly report.
To avoid difficulties caused by delays in allocating the implementing institution's counterpart staff
to the project, the TOR should be provided for such staff before the assignment begins. The
implementing institution's inputs, if not well defined in advance, are often a matter of contention for
the duration of the assignment. Service providers tend to overestimate the implementing
institution's contribution, and as a result, they reduce their proposal price, particularly if the method
of selection considers the price. Implementing institutions also tend to promise more than they can
actually deliver. It is therefore important that the implementing institution's inputs are defined in the
TOR as precisely and realistically as possible.
For reference typical, TORs for different service providers are attached to this guideline as follow;
Appendix II: Typical TOR for Site Identification and prioritization adopted from different
regions
Appendix III: Typical TOR for Feasibility Study, Detail Design, Specification and Tender
Document preparation; complied, adopted and then enriched mainly from TORs of regions)
The purpose of procurement planning is for the procuring entity (implementing institutions) to
schedule its procurement activities in advance. It should be consistent with its approved budget
and its target date of implementation, including a list of procurement of works, goods, and services
to be procured under the program yearly with estimated cost and method of procurement shall be
detailed in appropriate formats for the budget year. Here the procurement plan clearly includes the
plan of site identification and investment prioritization, feasibility study and design, construction
and construction supervision and capacity developments activities and requirements.
12.2 OBJECTIVE
The basic objectives of the Site Identification & Investment Prioritization study include: -
Assess the available land and water resources potentials for irrigation development
Collect necessary data for selection of potential SSI sites and analyze based on proposed
criteria
Characterize the potential SSI sites from physical and socioeconomic aspects
Plan the possible means of water abstraction for the proposed irrigation development.
Determine whether a project appears technically, economically, socially and
environmentally feasible and whether a feasibility study will be pursued or not.
Conduct SSI projects prioritization for Investments
Table 12-1: Time required for site identification and investment prioritization study
No. Description Unit Field work Office Works Total
1 Own-force bases Days 3 10 13workingDays
2 Consultant bases Days 3 5-7 8-10workingDays
The key professional staff qualifications, competence, and composition for the assignment will be
the major one. Key staff refers to the consultant‟s staff who have management responsibilities or
the key qualifications required for the assignment. The success of the assignment depends to a
large extent on the performance of the team leader and the remaining key experts. The study crew
will be small teams and/or large teams, which depends on the scale of an irrigation project.
Person Power by Disciplines and Qualifications required for the assignment should be evaluated
based on the general qualification, adequacy for the assignment and experience.
General qualifications criterion covers the general experience of the key expert (total duration of
professional activity), level of education and training, positions held by the candidate, time spent
on similar assignments, experience in the region where the assignment is to be carried out, and so
forth.
Adequacy for the assignment this sub-criterion relates to the education, training, and experience
of the candidate in the specific sector, field, subject, and so forth directly relevant to the
assignment and the proposed position. This factor is critical and should be given the greatest
weight among the three sub-criteria.
Generally, study and design of an irrigation project require multi- disciplinary key professionals by
its very nature and the required Person Power by Disciplines and Qualifications responsible for
field and office work of SSIP site identification and investment prioritization are summarized in the
Table below.
In conducting the site, identification and investment prioritization study the proposed person power
has the following responsibilities. The responsibilities of the key personnel were classified as pre-
field (desk-based investigation) work, fieldwork and post field tasks. The detailed responsibilities of
each discipline in the site, identification and investment prioritization study are presented in
SSIGL-2
12.6.1 Logistics
One of the basic resources that have a significant contribution for site identification and investment
prioritization study is the availability of logistics. These logistics include vehicles, fuel, lubricant,
etc.
It is suggested that the study crew who carry out the site identification and investment prioritization
study need to have at least the following equipment‟s; topographic map (s) of the area (scale
1:50,000 or any available scale), GPS, electronic total station, scales, meter tape, soil color chart,
portable pH and EC meter, rock color chart, binoculars, auger, stop watch, note book etc.
Table 12-3: Proposed budget for site identification and investment prioritization
S No Disciplines Unit Total Required Budget
1 Person power Cost/fees Birr Xxxxx
2 Per diem allowances) „‟ Xxxxx
3 Fuel & Lubricants ,, Xxxx
4 Consumable Materials & Stationary ,, Xxxx
4 Vehicle Maintenance, Spare part/vehicle rent, ,, Xxxx
5 Surveying materials rent, ,, Xxxx
6 Daily laborers, (Soil, Hydrologist, Geologist & Surveyor) ,, Xxxx
Contingency of 10% ,, Xxxxx
VAT (15%) ,, Xxxxx
Total Xxxxxxxxx
13.2 OBJECTIVE
The objectives of conducting the feasibility study are to insure that the project is:
Selected the possible alternatives based on the most appropriate technical approach; in
other words, assess the technical feasibility of the project:-
Economically and financially viable
Socially and environmentally acceptable
Prepare detail design with full participation of communities and stakeholders
Prepare contract documents and construction plan
Table 13-1: Time required for a feasibility study and detail design study
No. Description Unit Field work Office Works Total
1 Own-force bases Days 15 3-5 months 90-150working days
2 Consultant bases Days 15 3-5 months 90-150working days
The key professional staff qualifications, competence, and composition for the assignment will be
the major issue of this phase. Key staff refers to the consultant‟s staff who have management
responsibilities or the key qualifications required for the assignment. The success of the
assignment depends largely on the performance of the team leader and the remaining key
experts. The study crew will be small teams and/or large teams, which depends on the scale of an
irrigation project.
Person power by Disciplines and Qualifications required for the assignment should be evaluated
based on the general qualification, Adequacy for the Assignment and Experience.
Generally, study and design of an irrigation project require multi- Disciplinary key professionals by
its very nature and the required Person power by Disciplines and Qualifications responsible for
field and office work of SSIP Feasibility Studies, Detail Design and Tender Document Preparation
are summarized in Table below.
Table 13-2: List of person power by disciplines and qualifications for FS & DD
No Description Quantity
1 Irrigation and head work engineer/Team Leader 1
2 Hydraulic and structural Engineer As required
3 Hydrologist As required
4 Geologist/geotechnical engineer As required
5 Soil and Land Suitability Analysis Expert As required
6 Socio-Economist As required
7 Sociology/Community promotion expert As required
8 Irrigation Agronomist As required
9 Watershed Expert As required
10 Environmentalist As required
11 Surveyor As required
12 Drafts Person /AutoCAD/GIS expert As required
Total
The responsibilities of the key personnel were classified as pre-field (desk-based investigation)
work, fieldwork and post field tasks. The detailed responsibilities of each discipline in the
Feasibility Studies, Detail Design and Tender Document preparation are presented in Appendix-III.
13.6.1 Logistics
One of the basic resources that have a significant contribution for site identification and investment
prioritization study is the availability of logistics. These logistics include vehicles, fuel,
lubricant..,etc.
At this stage detail, data collection is necessary and each member of the study crew requires
important equipment. Essentially, it is recommended that the study crew requires the following
basic equipment; topographic map (s) of the area (scale 1:50,000 or any available scale), GPS,
electronic total station, altimeter, stereoscope, scales, meter tape, soil auger of different types,
color chart, rock color chart, binoculars, auger, stop watch, level with its accessories, Laptop,
software, geological hammer, infiltrate-meter, buckets, ropes, sample bags, etc. To locate
reference control points and data collecting sites, satellite imagery, Google map and DEM are also
required.
Table 13-3: Proposed Budget for Feasibility Studies, Detail Design SSI projects
S. No Disciplines Unit Total Required Budget
1 Person power fees Birr Xxxxx
2 Per diem /allowances
3 Fuel & Lubricants ,, Xxxx
4 Consumable Materials & Stationary ,, Xxxx
5 Vehicle Maintenance, Spare part/ vehicle rent ,, Xxxx
6 Surveying materials rent, ,, Xxxx
7 Soil & Water sample Laboratory test, ,, Xxxx
8 Geology and other related sample Laboratory tests ,, Xxxxx
Daily laborers, (Soil, Hydrologist, Geologist &
9 ,, Xxxx
Surveyor)
Contingency of 10% ,, Xxxxx
VAT (15%) Xxxxx
Total Xxxxxxxxx
Construction works include tender preparation, bid evaluation, construction award, contract
management, construction supervision and project handover. The major construction activities are
considered to be undertaken by contractors whereas the implementing institution would manage,
follow and monitor the progress of construction activities. The kebele and Woreda administration
councils play a significant role in the task of monitoring, evaluation, mobilizing the community
participation and resolving local conflict issues if they arise in the construction site.
Contract administration: -Under this phase, the contract will be established in the construction
phase and there is contract implementation inthe project study and design phase. However, in
both cases the main contract management implementation subjects or procedures mainly include
the following:
Contract Mobilization
Contract Documentation and Record Keeping
Contract Management Roles and Responsibilities
Managing Relationships
Performance Management
Contract Monitoring
Negotiating Contract Variations
Managing Contract Disputes
Ethics in Contract
Construction Supervision: -On the other hand, small-scale irrigation project implementation
passes three phases, namely the Pre-Construction Phase, Construction Phase, and Post-
Construction Phase.
Pre-Construction Phase covers the period of the signature of the contract up to the
commencement of the works. Construction Phase covers the period from the commencement of
the works up to completion of the works. Post-Construction Phase it covers the period from project
provisional hand over up to final hand over of the project at the end of the defect liability period.
Hence, construction supervision services shall be undertaken in these three phases as discussed
here under.
Construction Operation: - It is a Work contract legally binding agreement entered into between
the employer and the contractor for the execution of the works desired by the employer. Here, it is
an expression of the willingness of the employer to pay the contractor and of the contractor to do
the work as per the agreement. Irrigation projects are capital projects that need to follow general
contract management procedures during their implementation. In order to accomplish the job as
per the contract, the contractor needs an effective project management system at the
organizational level as well as at the operational level on the site. Generally, it is the day-to-day
and periodical construction tasks managed by the members of a construction crew in a sequential
order. (For detail Refer to SSIGL-29 construction Operation)
The project coordination office shall be established at supervisor head office for smooth liaison
with the project client. At project coordination, office the assigned project engineer and contract
engineer deliver their responsibilities, even for more than one lot. A lotshould be established
considering Administrative Zones in order to optimize time cost as the result of long travel from
one site to the other.
At each project site Supervisor Engineer, Surveyor, and Community Promoter should be
permanently assigned as a member of the construction supervision team. For this typical project
organization, project site -2 (as shown below in Figure 11-1) is a site located in the center, where
the base camp and resident engineer's office situated. The Resident Engineer can serve even for
three to four projects.
Pool
Design Engineer,
Geotechnical/Materials Engineer,
Electro-Mechanical Engineer,
Quantity Surveyor
Figure 14-1: Project organization for contract administration and construction supervision service
Contract administration, construction supervision and construction of SSI Projects require the
relatively long time of implementation. The total time required for, construction supervision and
construction of one SSI project will be 6- 24 months or 180-720 calendar days depending on the
size and complexity of the project.
Person power is the most influential element in the construction process. Construction team for a
project can comprise a complement of professional, technical and administrative staff. In
general, the following skilled/professionals, semi-skilled and unskilled person power as the
technical staffs together with the other administrative staffs as per the demand have a paramount
importance for the construction of small-scale irrigation projects at the site level.
Table 14-1: Person power for contact administration and construction supervision
No. Position Required Number Location Remarks
1 Project Manager 1 Consultant Head Office For different lots
2 Contract Engineer 1 Consultant Head Office For different lots
3 Resident Engineer 1 Project Site For different lots
4 Supervisor Engineer 1 Project Site Per project
5 Geotechnical/Materials Engineer 1 Project Site For different lots
6 Electromechanical Expert 1 Project Site For different lots
7 Surveyor 1 Project Site Per project
8 Laboratory Technician 1 Project Site For different lots
Assigned by the
9 Community Promoter 1 Project Site
client
14.6.1 Logistics
Contract Administration, Construction Supervision and Construction works of SSI Projects requires
the availability and existences of significant logistics. These logistics includes vehicles, fuel, oil.
Similarly, during construction works the supply of basic logistics and materials such as Stone,
Cement, Sand, Gravel, Reinforcement steel bar, Water, Formwork, Pipe and Fittings, Cement
Mortar and Concrete mix are very necessary.(For detail Refer to SSIGL-29 Construction
Operation).
The small-scale irrigation project uses construction equipment‟s, tool and materials for the quality
constructions. In order to increase job‐site productivity, it is advantageous to select equipment with
the proper characteristics and size most suitable for the work conditions at a construction site.
Some of the equipment‟s that should be considered during planning for construction works are
summarized in the SSIGL-29Construction Operation.
The operation, maintenance and management tasks are necessary for the continued functioning
and effective delivery of benefits of SSI investment in the near future. The community should be
fully responsible for the continued operations and management of the SSI systems. Responsibility
for the continuing management and operation of the SSI project system will be with the
community, through the IWUA. Implementing agency should ensure the community understands
that, unless it accepts this responsibility long-term, sustainability of the system is not possible; and
hence should continue to assist the community for an appropriate period following completion of
the SSI project implementation.
Mostly, operation and management procedures and instructions are the most important services
that the irrigation engineer or canal and gate operators provide to farmers in the delivery of
irrigation water. Delivery of irrigation water from the farmer's point of view is freedom in terms of
Timing, Flow-rate, and Duration of irrigation applications. However, there are four reasons for flow
control in Irrigation systems: Meeting water requirements of crops in order to achieve optimum
production; Water savings; Safety of operation; and Recovery of operating costs. For detail, the
description refers SSIGL-30: Operation and Maintenance
Here, in some complex SSI projects, there are cases to consider person power planning and
organization for irrigation system operation and management. However, in most SSIP the direct
users', the community and its IWUA committee will be the person power required for system
operations and management. Accordingly, users', the community member and its IWUA committee
need technical and advisory assistance for some time following the implementation of the project.
The IWUA committee should be responsible for carrying out the operation and maintenance plan.
Woreda and kebele technical units should help the community prepare and implement this plan
and provide minor amounts of assistance in carrying it out.
Table 15-1: Person power by disciplines and qualifications for operation & management of ssi
scheme
No. Person power Quantity
A Technical Staffs
I Skilled/Professionals
1 Soil and Water Management Engineer 1
2 Irrigation Agronomist 1
3 Social Worker/ Social Mobilizer/Sociologists 1
4 Water shade Management Specialist 1
5 Irrigation Technicians (DAs) 1
II Semi-skilled
1 Get Operator/Scheme Operator As required
2 Carpenters As required
3 Masons As required
4 Guards As required
III Unskilled
1 Daily Laborer As required
2 Farmers As required
B Administrative Staffs
1 IWUA Committee Members 5-7
2 Conflict Management Committee 3
3 Other Committee members As required
Table 15-2: Planning of person power by responsibilities for operation & management of SSI scheme
Person power and their
No. Responsibilities
Professions
A Technical Staffs
I Skilled/Professionals
Responsible for coordinating and lead the works of O & M, develop
system operation, maintenance and management plan, budgeting &
implementation schedule, give clarification when ambiguity arises in
Soil and Water
1 water management, operation & maintenance works, draw technical
Management Engineer
recommendation if required, successful completion of the project O
&M as per technical specification and as built drawings forming the
contract, etc.
2 Irrigation Agronomist Responsible for preparation of irrigation water scheduling,
15.6.1 Logistics
Operation and management of SSI projects require the availability and existences of significant
logistic. The logistics that should be considered during planning includes Motorcycles, fuel, oil, etc.
Especially, during conducting maintenance works the supply and availability of basic logistics and
materials such as Stone, Cement, Sand, Gravel, Pipe and Fittings, Cement Mortar and spare parts
for pump irrigation projects are very necessary and should be incorporated in the planning
process.
[
During operation and maintenance works of SSIP necessary equipment, tool and materials will be
used for the quality maintenance activities. This equipment that should be considered in the
planning, operation and maintenance works of SSIP includes Earth Work Equipment‟s, Hauling
Equipment, Electromechanical Equipment, Surveying Instruments, Small Hand Tools, and
Equipment. The detail description of this equipmentis presented in the following Table.
Table 15-3: Planning of tools and equipment for SSIP operation and maintenance works
No. Name of Tools and Equipment’s Quantity Types of equipment
1 Excavator As required Earth Work Equipments
2 Dump Truck ,,
3 Tractor ,,
Hauling Equipment
4 Double Cabin 4WD ,,
5 Wheelbarrow ,,
6 Mixer ,,
7 Vibrator ,, Construction Plants
8 Crusher ,,
9 Pump ,,
Electromechanical Equipments
10 Generator ,,
11 Total Station ,,
12 Automatic Level ,,
13 Meter Tape ,, Surveying Instruments, Equipment
14 Computer ,, and Tools
15 Hammer ,,
16 Peg ,,
17 Shovel ,,
18 Spade ,,
Small Hand Tools and Equipment
19 Fork ,,
20 Vessel ,,
Participation: - its emphasis on the participation of a more diverse set of stakeholders and it could
be externally led, internally led or jointly involved
Learning: - it is a learning platform for those involved in the process and can be characterized as
a process of individual and collective learning, through which people become more aware of their
strengths and weakness. Should serve to increase the analytical capacities of community
members and empower them to question and become pro-active in development initiatives
Flexibility: - Flexibility and experimentation are also regarded as integral parts of Monitoring &
Evaluation. There is no blueprint or a prescribed set of approaches to carry out Monitoring &
Evaluation. The process of M&E should be continually evolving and adapting according to
intervention-specific circumstances and needs.
Achievable: the objective should describe something that can be achieved within the time scale
and resources set for the project
Realistic: objectives describe something that can actually be done
Time bounded: timescale should be set as to when the objective is to be achieved
16.3 MONITORING
Monitoring is a continuous process of gathering, compiling, analyzing, and interpretation of
information mainly focusing on inputs‟ delivery and utilization, the process of transforming inputs
into outputs and outputs generated against the target. In monitoring the major tasks mainly, focus
on stipulating information requirements, collecting, recoding and processing information,
comparing target and actual performance of planned activities, inputs of resources, assumptions,
project impacts and assessing deviations of outputs from the objectives of the project.
In this phase, the progress and implementation of each project phase as well as the involvement
of the community and forming of the IWUA should be monitored in order to follow the progress, to
provide corrective measures, to check whether the proposed results of the scheme are as
anticipated or not, to monitor the physical and financial activities of the scheme.
All responsible agencies should monitor the work of their affiliates in order that irrigation project will
be carried out in accordance with the construction schedule and to the standard by agencies /
Bureaus at all levels in the process. Monitoring takes place throughout project implementation and
helps management to keep track of project progress. Monitoring reports provide the bulk of the
information required for evaluating a project.
Therefore, monitoring records of inputs, activities, and results, Identifies deviations from work
plans, Identifies constraints/ bottlenecks, gives information about overall system performance,
learn from the achievements and mistakes and share results with others
16.4 EVALUATION
Evaluation is a systematic and periodical gathering, analyzing, and interpretation of information on
the relevance, efficiency, effectiveness, and impacts of the project tasks/ activities and
sustainability of benefits accruing to the target groups. The objective of the evaluation is to assess
the sustainability and performance of all the project phases, including the technical, institutional
and financial aspects. The focus will be on the relevance, efficiency, effectiveness, and impact of
the project. Periodic evaluation results would provide pertinent information on how:
In order to undertake evaluation at any phase of the project, there should be the establishment of
indicators and the following areas of evaluation indicators are important for irrigation schemes
and both the financial and the implementing body. These are:
Technical Performance Indicators
Agricultural Performance Indicators
Financial Performance Indicators
Socioeconomic Performance Indicators
The evaluationcould be conducted in different aspects. Based on who conducts the evaluation, the
evaluation could be an internal evaluation, external evaluation, and joint evaluation. Based on
when/time they are conducted, the evaluation could be an Ex-ante evaluation, Ongoing
Evaluation, and Ex-post evaluation
Inputs: - Inputs are resources such as person power, finance, equipment, materials and others
used in a project to complete activities.
Outputs: - Are immediate or short-term development results that are the logical consequence of
activities. At this level, the information needs related to products or services, which are the direct
products and services delivered by a program and/or short-term result of the interventions. E.g.
Improved knowledge and skill of farmers on the use of Irrigation Service Fee (ISF) and OM that
increased availability of water for irrigated agriculture. Generally, outputs are specific results
expected from project inputs to achieve the immediate objective for which the project is
implemented.
Outcomes - Are changes about the use/utilization of outputs, outcomes are stated in past tenses
indicating adoption of outputs. The information required at this level relates to whether, how and to
what extent outputs have been utilized by intended beneficiaries. E.g. Farmers adopt regular
Irrigation Service Fee (ISF) and OM tasks, irrigation technology, and farmers started irrigated
agriculture.
Impact - Are changes that result from outcomes. They are the logical consequence of outcomes
and the result of the intervention.
Generally, the choice of technologies should be based on social acceptability, technical and
economic feasibility, and previous experience with the technology, technical and financial capacity
of the farmers to manage, operate and maintain the technology. The size and nature of irrigation
projects need to be small scale and simple to be managed by the beneficiaries.
Moreover, options for Irrigation systems such as pipeline, drip, sprinkler shall be assessed with
respect to its feasibility of technological, operation and maintenance system
17.3 BRING IN THE BEST PRACTICE & APPROPRIATE STUDY AND DESIGN TECHNOLOGIES
The option to bring the best local and international practices as appropriate and applicable to the
Ethiopian context shall be assed.
Smallholders irrigated Micro Household Irrigation System (MHIS) promotes and should be
established on a demand-driven basis, which includes as small stream diversions, ponds, hand-
dug shallow wells, shallow tube wells, engine and manual pumps, check dams, and springs, water
harvesting, and other micro-irrigation technologies/ structures. Generally, all possible technology
options for Micro Household Irrigation System (MHIS) should be assessed and implemented as
appropriate to specific areas and the site.
18 CAPACITY DEVELOPMENT
18.1 BACKGROUND
One of the institutional capacity building mechanisms is training as a powerful tool for institutional
capacity building and can promote interdisciplinary and managerial sustainability. It can also
accelerate the transition to a service orientation on the part of government agencies, and facilitate
a partnership between beneficiaries and institutions that serve them. In view of the current
endeavors in SSI, it is clearly vital to improving the capacity of experts and beneficiaries through
training.
Planning should consider Training and capacity building as a tool for successful implementation
and manage sustainable SSI schemes. Irrigation projects should be planned to match with local
capacity for implementation, which implies that planning teams should first acquire a thorough
appreciation of this capacity. The planning process should, therefore, give specific attention to an
analysis of institutional capacity, and to providing a detailed program to enable the implementers
to prepare themselves for carrying out the tasks expected of them, once the project becomes
effective. If there is less option, the project scope and content may be reduced to match the
existing implementation capacity.
Beneficiaries should also get training on how to use or operate the newly introduced technology,
their participation at different project stage, water management, O&M of irrigation structures.
Experts should get training on newly introduced technologies, construction supervision, water
management, and O&M. The training can be local or abroad and short term, medium term or long
term. Abroad long term and short-term training are justified if the fields cannot be given in the
local universities and are crucial for project implementation and sustainability.
Capacity building and experience sharing activities should involve both Human and physical
capacity development of expertise in the implementing institutions and project management Unit
assigned staffs. Accordingly, human capacity development will focus on bridging knowledge and
skill gaps for experts at PMU of the implementing institution and Subject Matters Specialist (SMS)
through identifying the target needs separately and capacity development plan to respond to
identified gaps. Similarly, physical capacity development will center on furnishing and equip
offices, mobility support, and other ICT equipment, including internet connectivity and creation of a
website and information databases which will assist the planning, implementation, monitoring, and
evaluation of SSI projects supported by different programs. Experience sharing is also one of the
best capacity building methods, which should be considered in the organization of Project
Management Unit planning and budgeting.
comprehensive plan for training activities with guidelines for the preparation of the annual training
calendar. Training needs assessment should be conducted in order to prepare result-oriented
training.
However, in the absence of training needs assessment, based on the gap we identified during the
past related assignments in most regions on FS, detail design, and specification and contract
document preparation, operation and maintenance by Regional own force staffs there are
significant engineering and other sectorial deficiencies that resulted in negative technical,
contractual, construction, cost and operation and management impacts. As an indicative, the
following training topics are proposed for respective disciplines
Capacity building and experience sharing activities should involve both Human and physical
Capacity Development in the implementing institutions and project management Unit assigned
staffs. For these activities, finance resources are highly required on time and quantity. The basic
sources of such financial resources would be the respective programs, which implement SSI
projects and sometimes the implementing institutions from regular government budgets. In all
cases, the budget has to be estimated and included in the project management cost.
Scheduling requires determination of the work activities, activity durations, and logical
relationships by drawing of the logic network; and performing of the total time required. Clients and
service providers need project scheduling to
Know the project start and completion date,
Start and end of a specific activity,
Help to coordinate with other supporting institutions
Predict and calculate the cash flow,
Improve work efficiency,
Serve as an effective project control tool,
Evaluate the effect of changes, and
Prove delay claims
The Critical Path Method (CPM) is a schedule network analysis technique currently used and
offers a visual representation of the project activities. Presents the time to complete the tasks and
the overall project, and help in Tracking of critical activities
5 Supervision &Construction
Award
6 Construction
7 Handing over
8 Operation and Maintenance
Starting from SSIP site identification to final hand over there should be realistic quality planning,
assurance, and control system. Quality control involves management, technique, time and cost.
Control of quality depends on the effective execution of responsibilities among implementers in
their respective duties. All the actors, consultants, contractors, suppliers, are expected to execute
responsibilities laid down in the contract and play a role for successful completion of quality
design, construction supervision, construction Monitoring & Evaluation.
Establishment of evaluation of standards and procedures for quality control of the design and
construction of SSI projects has paramount advantages. For instance, in the construction of SSI
Projects the quality control evaluation standard could be developed with respect to Quality control
of Construction Materials, which could be evaluated with materials test result, materials produced
by the contractor, materials procured from manufacturers/ producers and storage of materials.
Accordingly, quality control of workmanship also the basic and the three most significant factors to
be closely inspected during quality control of workmanship shall be Conformity with plans,
Capability of Contractor‟s person power and Monitoring of Equipment and Plants. Similarly, the
PMU and implementing institution could use existing, also formulate fitting evaluation standards
and procedures for quality control of design, specification, draw, and cost estimates.
Everyone‟s expectations on quality are different. Therefore, it is necessary to clearly layout what
the expected grade of quality. There must be a clear idea of what tasks entail and what quality
measures will be used to confirm a task is complete. Quality within projects is an ongoing process.
Quality within projects consists of Quality Planning, Quality Assurance, and Quality Control
Quality Planning:- identify the quality standards relevant to the project and determine how to
satisfy them. The primary benefits of meeting quality requirements are that there is less rework
resulting in higher productivity, and lower costs associated with the project. Primary costs of
implementing quality requirements are the expenses associated with the quality strategies.
Quality Assurance:- evaluate the overall project performance on a regular basis to provide
confidence that the project will satisfy the relevant quality standards.
Quality Control:- monitoring specific project results to determine if they comply with relevant
quality standards. Find ways to eliminate the causes of unsatisfactory performance once they
have occurred.
Within projects, it is important to focus on quality planning and quality assurance. It is more
effective to prevent errors rather than fix them. A “0” defect attitude means you implement
processes that people follow to ensure or assure quality rather than focusing on quality control or
inspection.
In-house quality evaluation:- Design document and construction of the SSI project could be
evaluated on an in-house basis. In this evaluation necessary arrangement, experts and concerned
staffs should participate continuously. The PMU and implementing institution should take the
responsibilities and resources necessary for this evaluation. Time, place, number and composition
of participants and duration for in-house evaluation should be stated and described clearly in the
TOR that is prepared for this purpose. The advantage of the evaluation in here is that the
implementing institution and PMU could manage their evaluation issues in-house level.
Stakeholders’ quality evaluation:- Similarly, design document and construction of the SSI
project could be evaluated through the participation of different stakeholders' and in this evaluation
process concerned stakeholders should participate in the process strongly. The PMU and
implementing institution should take the responsibilities and resources necessary for this
evaluation. Time, place, number of participants and duration of this evaluation should be stated
and described clearly in the TOR that is prepared for this purpose.
Actions to be taken:- Based on the quality evaluation results obtained at each SSI project site,
actions should be taken considering the short, middle and long-term effects of the evaluation
outcomes. The action to be taken will be a correction of existing gaps and overall reworking of
PMU should take actions based on the evaluation reports and outcomes.
Kickoff meetings and orientation on the assignments is one of the inputs in the quality assurance
and control system. On the kick off meeting concerned stakeholders in the region, zone, Woreda,
and even beneficiary farmers should participate. At the meeting, detail discussion should be
conducted, on the roles, responsibilities of each party, work activities and schedule; expected
quality standard output if not accountabilities thereof should be discussed and agreed by the
parties.
Follow up on the work progress and reporting is another input to the quality assurance and control
system. All SSI project plans and implementation activities require work progress monitoring and
follow-ups. Monitoring of work progress may involve observations at key sites, regular visits, and
discussions with site level assigned counter staffs, users, officials and concerned experts. Those
responsible bodies for planning and implementation should list the tasks needed to correct
problems as they arise and should take action.
Preparation of periodic work progress report (physical activity and financial) should be mandatory
(is a must) and is a formal requirement. The assigned counter staffs at site level carry out work
progress follow-up tasks on a daily basis and prepare work progress reports monthly. For
instance, on the study, design, construction, operation, contract administration and supervision
works, work progress activities will be recorded on a daily base and later summarized for monthly
reports, these require well-prepared work progress follow-up formats. The format is indicated in
the Appendix of this report
The implementing agencies have a good experience in conducting a review workshop at each
milestone in the study and design to improve the quality of the study and design document. In this
workshop, relevant and resourceful institutions and individuals are invited to participate. It is
proved that these review workshops offer valuable inputs to the improvement of the study and
design document and should be continue.
The best alternative option is the establishment of a Quality control Peer Team within the main
implementing Agency who will be responsible to establish quality control standards, conduct
quality control, take remedial actions. The team can be a full time permanent staff or short time
independent expert. This team shall review all SSIP at all stages starting right from
initiation/inception up to operation and maintenance.
Last but not least is Quality assurance study & Design Review and endorsement of independent
firms is paramount important. The work shall include study and design review, identify gaps, make
ground verification, and recommended correction measures or restudy/redesign works and finally
endorse for implementation.
Ground level verification, approval and confirmation of the project beneficiaries and existing local
level stakeholders at the project site level are very necessary for quality control. At each phase of
an irrigation project, particularly at feasibility study & detail designs, construction and final
handover phase, the responsible government institution has to arrange a draft design appraisal
and confirmation meeting with the farmers and study and design committee members in order to
review, discuss the documents, and other necessary estimated costs including operation and
maintenance costs.
Necessary modification or adjustment compared with the first field data collected and the location
of the canal route, social infrastructures must be clearly explained to the farmers and design
committee members. In this connection, the reasons and justifications for the non-inclusion of any
proposed infrastructure must also be explained and discussed in detail with project beneficiary
communities.
Following the presentation and review of the draft detailed designs, the farmers Irrigation Water
Users Design Committee (IWUDC) members have to decide on the approval of the final detailed
designs as prepared by the responsible government institution. Similarly, ground level community
verification and community approval should be conducted in all irrigation planning phases,
following the transition of phases.
Project appraisal and phase transition activities (approval techniques) are necessary for irrigation
project development and management. The transition or forward movements from one project
phase to the other phase should get an appraisal and needs attentions in the planning and
budgeting process.
Accordingly, to identify the best SSIP from the available potential SSI schemes in a given area
(woreda) for feasibility study, Detail Design; each of them has to be evaluated using a wide range
of multi-sectorial criteria such as Engineering, topography, water resource, geology, land
suitability, agronomic, socio-economics, institutional capacity, watershed characteristics,
environmental sensitivity, project costs, and benefits. Project appraisal using these criteria should
be based on an objective assessment of each sector using both qualifying and quantified
indicators/criteria‟s.
Appraisal of each project phase requires an intensive assessment of the documents prepared by a
multi-disciplinary technical team. In the appraisal of the project phases, different indicators in the
logical framework and the alignment of the project with the national development strategies should
be assessed. The appraisal of project phase should be conducted by an established independent
in-house appraisal team or by consultants. The project phases and transitions approval process
requires agreements, proceedings of the discussion, signed by the responsible team members
and endorsed by the authorized person. Moreover, the project phase appraisal and transition
decisions should be open, transparent and participatory.
A project design appraisal should get significant attention. Design appraisal and confirmation of
the project beneficiaries and existing local level stakeholders on the project site is mandatory. As
soon as the draft detailed designs have been prepared together with the final net command area
delineation, lay-out of the project and map, the responsible government institution has to arrange a
draft design appraisal and confirmation meeting with the farmers and study and design committee
members in order to review, discuss these documents, and other necessary estimated costs
including operation and maintenance costs.
All modifications or adjustment compared with the first field data collected and the location of the
canal route, social infrastructures should be clearly explained to the farmers and design committee
members. In this connection, the reasons and justifications for the non-inclusion of any proposed
infrastructure must also be explained and discussed in detail with project beneficiary communities.
Following the presentation and review of the draft detailed designs, the farmers Irrigation Water
Users Design Committee (IWUDC) members have to decide on the approval of the final detailed
designs as prepared by the responsible government institution. In the design approval stage, there
should also be agreements, preferably written and signed by the beneficiary communities, kebele,
and wereda level administration councils.
Due to lack of budget, technical and social conflicts small-scale irrigation project design and similar
projects, phases may stay on the shelf for long-time. In such conditions costs may vary, water
resources and similar resource access will change; the appraisal process in such a situation will
require detailed investigation and site level assessment. The appraisal of a long-shelf life design
project requires time, cost and varied team compositions.
If the test run of the SSI scheme has revealed that the system cannot be operated as designed,
the responsible government institutions with the support of the Irrigation DA must investigate the
cause(s) and identify any remedial measures, which have to be discussed with the contractor and
the IWUA. If the malfunctioning of the SSI scheme is the result of one or more construction faults,
the contractor has to carry out the necessary corrections/ repair and/or reconstruction works at its
own expense. However, if one or more design faults are the reason for the malfunctioning of the
SSI scheme, the contractor at the expense of the responsible government institution should
execute any remedial works and this point should clearly fix in the detail design stage.
The content of the Project Completion Report has toconsist of the following
Project description and salient features
Assessment of implementation activities
Project cost and financial disbursement
Major problems, constraints, and remedial action are taken
Project outputs
Project development impacts
Sustainability in all aspects (technical, social, Environmental, institutional management)
Lessons learned
The possibility of scaling up
Phase out strategies
REFERENCE
The Federal Democratic Republic of Ethiopia. Ethiopian Social, Rehabilitation And
Development Fund (ESRDF). Small Scale Irrigation Project (Gravity) Technical Handbook-
Component-II Continental Consultant PLC, 1997
The Federal democratic republic of Ethiopia for A Second Agricultural Growth Project,
March 5, 2015
Federal Democratic Republic of Ethiopia Ministry of Agriculture and Rural Development,
Agriculture Sector Support Project (ASSP)small-scale irrigation Guidelines September
2006
IFAD (2012), Project completion report validation and project performance assessment.
IFAD, Participatory Small-scale Irrigation Development Program Phase II (PASIDP II),
Final Program Design Report
JOHN WILEY & SONS, INC. Harvey A. Levine, 2002.Practical Project Management Tips,
Tactics, and Tools
Ministry of Agriculture and Natural Resource, Ministry of Water, Irrigation and Electricity
and Agricultural Transformation Agency. National Smallholder Irrigation and Drainage
Strategy July (2016).
ReDIM-PPM, November 12, 2009. Project Planning Procedure Manual
APPENDICES
Project Name:_______________________
Client:__________________________________
Consultant:____________________________
Contractor:________________________________
To - Date
Accomplished Quantity
Bill Unit Previously Certified Difference
Tender
Item Activity Unit Price‟ completed Accomp- Remark
Quantity This month To - Date Quantity
No Birr quantity Certified
Planned Executed Planned Executed Quantity
Remarks: ________________________________________________________________________________________.
Prepared by Approved by
This Term of Reference indicates major activities or assignments for executing of site identification &
prioritization of potential small-scale irrigation sites. The study should be comprehensive and participatory to
identify most preferable sites for further study in feasibility and detail design phase. The site identification &
prioritization study need to be undertaken by group of specialists including irrigation engineer, geologist,
agronomist, environmentalist, socio-economist, watershed expert, topographic surveyor, and soil expert.
Engineering related assessments need to be carried out to indicate major structure requirement for
recommended type of irrigation system in turn it tentatively shows potential irrigable land and cost-
effectiveness of water storage, distribution and drainage structures. In order to compare and prioritize the
project sites, the following relevant factors should be defined
Recommend appropriate type of irrigation system for each potential sites and their alternatives
depend on cost effectiveness; complexity for management, social and environmental factors
Identify cost effective, appropriate headwork site(s) for all potential sites together with study team
members in consultation with communities, knowledgeable persons and representative of wereda
offices (preferably engineer). The headwork sites might be 2-3 in number for each potential site
Apply the recommended criteria in GL 2 site Identification and Prioritization Guideline to select
appropriate headwork type
Delineate the command area on 1:50,000 topographic maps, and recent high resolution satellite
imageries. Cross-check appropriateness of the command area boundary with additional
information from woreda irrigation experts, and the local people.
Produce preliminary layout indicating the command area boundary, primary canal, and crossing
points with close involvement of wereda irrigation/water engineer and community representatives
Estimate engineering cost per hectare from secondary sources experienced in the project area.
Summarize the engineering assessment findings and compare the potential sites to investigate
most preferable sites from engineering aspects
At this level opf study, the geological investigation and description should be based on preliminary site
observation and augering at selective pints for confirmation
Review the geological and hydrogeological condition of the project area from secondary sources
like Ethiopian geological survey map, satellite images; previous studies conducted in and around
the project area similar to the project sites
Identification of general geologic conditions of the headwork cross section i.e. weir axis
geomorphology, geology, hydrogeology and engineering geology
Check profile of canal routs and structures
Study source of irrigation water supply river‟s/spring‟s profile around the headwork site from
visual observation.
Identification of stability conditions and potential geologic failures at the same sites which will be
confirmed during feasibility study.
2-5 Topography Survey
Topographic survey of the potential sites at this level of study is limited on headwork sites cross sections and
terrains of the command area.
Carryout cross-sectional survey of the source river and its flood-plain up to 5m above the
floodplain (on both right and left banks) 50-100m on u/s, d/s & along axis of headwork.
Undertake cross-sectional survey to determine flood embankment requirements along some ±1
km of the River and its floodplain,
2-6 Soils and Land suitability evaluation
Soil and land suitability evaluation should be mainly based on preliminary investigation of bio-physical
features of the command area. at this level of land resource assessment for characterization and
prioritization of the command area of the potential sites rely on physical assessment and soil augering at
1.2m depth
Prepare soil survey base map for positional reference and to provide bio-physical data that can
assist in the prediction of soil properties
Identify major soil type, land use/cover type and distribution, topographic condition (use slope
range classification of ranges (0-3%; 3-5%, 5-8%, 8-15%, 15-20%; 20-30%, 30-60% and >60%)
Describe surface characteristics (Rock outcrops, Coarse fragment, Erosion, Surface sealing and
Surface Cracks) of the command area
Assess and determine the effective soil depth; water table; texture; color and top soil structures
from auger observation
Evaluate the identified command area for irrigated agriculture for potential prioritization
Preliminary agricultural potential assessment should be undertaken to provide inputs for project site selection
and prioritization. At this level of study, preliminary estimated figures, descriptions and analysis are adequate
to characterize the project sites and compare for their potential. The following detail tasks should be
undertaken by the agronomist
Assess the existing farming system of the project site(s) in consultation with communities and
wereda and kebele experts
Identify crops grown in the potential site and classify into food and cash crop groups
Investigate the prominent farming experiences including cropping calendar, crop intensity and
major limiting factors of crop production
Conduct climate matching analysis for selected crop groups potential for competent sites
Describe the length of growing period and make compatible analysis for potential crops
Analyze extent of environmental and climate induced vulnerability on crop production to compare
the degree of exposure of the potential sites
Propose appropriate crops and cropping pattern for preliminary assessment and determination of
their irrigation demand. The crops could be few in numbers those selected from different crop
groups like cereal, pulse, oilseed, vegetables and fruit tree crops.
Estimate crop and irrigation requirements of the proposed crops
Prepare indicative crop budget from the unit rate of the project area which can be obtained from
previous studies, and wereda/kebele data sources
Evaluate the potential of the project sites from crop requirement, water demand and production
context for prioritization
2-8 Socio-economic, marketing and agri-service support assessment
Socio-economic and marketing preliminary assessment should be carried out at preliminary level to sufficient
information to describe the SSI potential sites and compare from socio-economic and community
participation context.
During site identification phase, the willingness of the communities in the intended command area or project
kebele has to be checked whether they are interested to own and manage the proposed agricultural
development.
Identify the settlement pattern; and demographic features of the potential areas in consultation
with key informants and secondary data source
Conduct preliminary assessment on economic basis, availability of farm labor, and availability of
agricultural based investments;
Assess the attitude of the stakeholder and community in regard to the project potential to sustain
socio-economic development with close consultation of stakeholders
Conduct preliminary assessment on existing social infrastructure and agriculture support services
Assess the marketing infrastructure and participants in and around the irrigation potential areas
Carryout preliminary cost-benefit analysis to provide indicative figures to evaluate the potential
sites for prioritization
2-9 Socio-economic, marketing and agri-service support assessment
Conduct potential site screening and scoping to determine the requirement and describe the
potential sites with basic environment study requirements
Brief description of potentially affected areas including up/down steam of the potential project
sites.
Identify alternatives to be considered for planning of economically, socially and environmentally
sustainable small-scale irrigation potential sites.
Conduct preliminary bio-physical features of the potential sites
Investigate basic environmental issues and beneficiaries‟ attitude towards the sustainability of
the project and surrounding environment
Identify preliminary environmental and social impacts and their mitigation measures
3. Potential site prioritization
Evaluate and prioritize competent irrigation potential sites with multi criteria analysis (MCA) method
Identify evaluation criteria in the context of small-scale irrigation project. the evaluation criteria
should be set for each sector involved in potential study.
Examine the weighted main and sub-sector criteria for prioritization
Prioritize and identify the first potential sites to be studied at feasibility level (at least three
potential sites from the woreda depends on the client TOR)
Ensure the acceptance of the prioritized potential sites by stakeholders and beneficiaries by
organizing endorsement meeting at grass root level
Get approval from project implementer stakeholders and beneficiaries
4. Prepare site identification and prioritization work plan and schedule
1. Introduction
This TOR has been prepared targeting the development of small scale irrigation through assisting and
supporting farmers to improve irrigation management practices and the promotion of modern irrigation
systems.
Prior to the feasibility study and detail design feasible project option has been selected and agreed between
the client and the consultant, or the client should select the feasible site and provide to the consultant for
these detailed planning should be put in place. The feasibility study and detail design should have an
outcome and the outcome should be project document that is in many respects a feasibility study and detail
project design report: ideally it should define the project in all respects. The project report should therefore
demonstrate that the project is:
Similarly, the final feasibility Study and Detail Project Design Report (FS & DPDR) shall include but not
limited to the following aspects:
Topography;
Climate and Hydrology;
Assessment of Catchment Water Balance
Geological & Geotechnical;
Availability of Construction Materials;
Watershed Management Study and draft plan for proposed Soil and Water Conservation works in
the vicinity of the headwork, along the main canal and within & around the envisage command
area;
Soil Survey and Land Suitability;
Irrigation Agronomic and draft agricultural development plan for the project;
Sociological and Socio-economic Investigation;
Consultation of actual target Beneficiaries and other stakeholders;
Assessment of IWUA aspects and draft plan for proposed Capacity development for the irrigation
water users of the envisaged irrigation development,
Detail Engineering Design and Investigation; and
Environmental and social impact assessment (ESIA) and proposed Environmental and Social
Management Plan;
1.1. Objective
The prime objective of enhancing the implementation of small-irrigation project is the starting point for
securing better livelihood for the rural low income/ poor population. To make this happen, several attempts
are underway, of which studying and designing of small-scale irrigation scheme by the regional officials and
private firms is considered as a short cut for increasing the pace of irrigated agriculture development in the
country.
The implementing institutions or service providers or consultants should conducted an identification study
and ensured that beneficiaries have made the request for assistance and they are willing to form IWUA as
well as contribute minimum 10% of the total scheme development cost. Besides, the identification study
should indicate that there is a flow for the proposed irrigation development that should be confirmed by the
implementation institutions or by the consultant in the identification report and the project is free from any
conflict. Hence, there is a need to carry out feasibility study and detail design for construction.
This study should be done using PIDM (participatory Irrigation Development Management) approach in
which more participation and decision making of the community is to be practiced. Accordingly, from the very
beginning of the study like headwork selection, main canal route, night storage location and others structures
should be discussed with the community design committee/ IWUA and endorsed by them. In addition,
ground truth of the draft final design of the project should be done and presented to the beneficiaries design
committee / IWUA and endorsed.
The aim of this TOR towards implementing feasibility study and detail design of small scale irrigation as a
component of the livelihood project is:-
To carry out detail design, bill of quantities and cost estimate for the head work and its
components, canal system and its pertinent structures
For preparation of tender documents for construction, Bill of quantities, cost estimates including
break down for unit price.
To realize that the project designs are in favor of the desired social, economic, technical &
environmental objectives set for the particular project.
In each study discipline, the community should participate according to the PIDM approach
introduced in the region
Detail TOR on each discipline is attached with this document
2. Detail Service
The stakeholders in charge of the feasibility study and detail design of small scale irrigation projects will be
proposed to undertake the following services. The detail services include but not limited to the following
activities.
Detail survey works both at the headwork site and irrigable area shall be conducted and a topographic map
of the scheme area has to be prepared at a specified scale. Preparation of the topographic map of the
headwork, conveyance structures, division structures & other structures at the specified scales. The
topographical survey shall include Topographic surveys; Alignment surveys; and Structure site surveys.
1. Topographic Surveys: The topographic surveys shall cover the whole project area including source
works/head works and the irrigation command area and as required to provide adequate information
for detailed design.
2. Alignment Survey: Topographic surveys shall be carried out along the alignments of the proposed
canals and embankments.
3. Structure site survey: The Consultant shall carry out detailed topographical survey at each hydraulic
structure site to enable the preparation of an existing site layout drawing with 0.25 m contours,
detailing the canal alignments and levels, and any other relevant local features such as irrigation
structures, access roads, houses, property fences or boundaries and any other permanent reference
marks.
2.1.1 Drawings
General Arrangement and cross-section drawings shall be provided in AutoCAD format including: Plan of the
site; Longitudinal section taken through the proposed structure and approaches; and Cross sections taken at
20-30 m intervals in two directions including one on the watercourse center line.
Permanent reference benchmarks will be provided at each site to enable accurate location and control of
construction of the works. The benchmarks shall comprise steel pins set in concrete or other permanent
object. Sufficient benchmarks shall be established for each major structure site. These benchmarks (control
points and temporary benchmarks) shall be accurately identified, referenced to the base maps and
registered to the GIS system, and tabulated on the completed survey drawings. A hardcopy log shall be
prepared containing location coordinates, photographs, and elevation. Photographs shall be digital
photographs and provided in soft copy.
The survey results for the topographic maps shall be represented on a 1:1000 scale plan drawing with
elevation contours at 0.25 m intervals in height. The irrigation unit command area selected for detailed on
farm design shall be surveyed with elevation contours at 0.25 m and represented at a scale of 1: 500.
Headwork Cross-sections shall be represented at a scale of 1:200 -1:100 horizontally and 1:100 vertically
and their locations shall be shown on the plan. The plan shall also indicate land usage and the locations and
levels of the permanent survey stations and benchmarks.
The study shall examine appropriate data and provide the climatic conditions of the study area providing the
details of:
Review previous relevant study documents and clearly identify the gaps and short comings;
Ascertain and thoroughly check the availability and quality of hydro meteorological data;
Data available shall be described and presented in the form of tables, bar-diagrams, etc.
including source, location and altitude of the station, drainage area, and distance from the site
under consideration.
Internal and external checking of the consistency of available data shall be made at specific
control points and corrections made, if any.
Short data gaps shall be filled by using either of the appropriate hydrological methods
Compilation, processing and validation of hydrological, hydro-geological and meteorological data;
Assess all watershed features pertinent to analysis and simulation of hydrological data;
Assess and confirm the availability of lean flow and its dependability for irrigating the proposed
land;
Examine and confirm the quality of water and its suitability for irrigation;
Fix hydrologic criteria for design flood for weir/barrage/cross-drainage structures etc;
Carryout flood analysis in order to determine the design flood either based on available flow data
or using universally accepted methodologies;
Determine standard project storm, maximum probable storm, 25 yr. 50 yr., 100 yr, frequency
storm etc. for various structures;
Examine and describe the sediment yield of the watershed and the nature of bed load coming
along the river so as to mitigate any adverse effect on the headwork and outlet structures;
Analyze the ground water conditions of the project area;
Determine runoff and drainage characteristics so as to define drainage characteristics;
Propose suitable recommendations with regard to flow measurement and other data to be
collected such as river gauging, rainfall gauging and irrigation canal water flow measurement;
Carry out all other data considered necessary and relevant for the hydrological component
Carry out the water balance of the river/stream basin to avoid water use conflict between U/S and
D/S users;
Perform water supply and demand analysis of the proposed irrigation project;
Carry out discussion with existing water users on the U/S and D/S of the proposed irrigation
project and confirming that their already established water use right will not be breached or
jeopardized.
Ensure the availability of lean flow and its dependability for irrigating the proposed land;
Ensure the release of 20% of the lean flow to the ecology.
The possible hydrological effects that will prevail on the project area and particular on the
downstream area of the project shall be assessed and discussed.
Note: - The design flood must be estimated based on data of at least 20 – 30 years. If such data is not
available, new data must be generated (synthesized) using approaches outlined in hydrology
manuals/guidelines.
Wherever a new scheme is planned whose water supply is to be obtained from a surface source, there will
almost certainly be existing established demands for water upstream and downstream of the chosen
abstraction point. A formal system of water rights may be in operation, or local people may have an
agreement by traditional custom over the way in which water for irrigation is allocated. Therefore, base flow
of the river and impacts of the diversion for irrigation both at upstream and downstream uses shall be
assessed properly.
Therefore, information should be provided on water balance considering the minimum flow of the river, the
current users (in the command area, downstream and upstream beneficiaries) of the given water resource
for different purpose (irrigation, livestock, and domestic purpose, ecological function), the amount to be
diverted, the deficiency resulted to the downstream users due to the diversion.
Future increases in demand on the source upstream of the proposed abstraction site, taken together with
existing and any planned additional demands downstream, both net of downstream inflows, will give the
equivalent demand at the abstraction point to be deducted from the supply when assessing the water
available to the project. Where discharges at the abstraction site have been naturalized, the equivalent
demand should also include existing demands upstream.
The assessment shall contain a detailed discussion of the hydrological analysis leading to an assessment of
the available water resources and reviews of a methodology to determine the flow data series to better
assess available surface water resources.
The geological and geotechnical investigations are required for headwork and other structures foundation
verification, embankment design (if any), canal design, borrow area etc. Detailed Investigation Report on the
foundation investigations of different structures/components of the project discussing the following points and
additional points, if any, as relevant to the structure shall form an appendix of the Detailed Project Report.
Summary of the investigations carried out, results, treatments, recommendations etc. shall be furnished
under the chapter of the Detailed Project Design Report.
Generally, the consultant shall undertake the engineering geology and geotechnical investigations at the
proposed sites in accordance with the references detailed below.
Previous studies and relevant documents (geological reports and maps) if any will be thoroughly
reviewed and the gaps and shortcomings shall be clearly identified;
Visit to the proposed river diversion/dam sites of interventions and verify its suitability from
geological and geomorphologic point of view through traverse downstream and upstream of river
diversion sites;
Conduct Geotechnical assessment for foundation structures, headwork site, main canal and
appurtenant structures.
Conduct suitable field and laboratory tests to determine the composition, compaction and integrity
of existing embankments;
Carry out bulk samples at 0.5 m intervals to appropriate depth at structure and borrow locations
for soil characterization testing at a suitable laboratory. In situ and field test techniques should be
employed to supplement laboratory testing;
On purpose to acquire a complete documentation of geological conditions at the proposed site(s)
selected detailed topographic map of scale 1:1000, with 2.5 m contour intervals is of primary
importance, cross sections along axis of river diversion, at 100 m d/s and u/s, exploration of river
diversion sites and investigations of construction materials and their suitability;
Prepare details and location of the pits, along the river diversion axis and abutment, and in-situ
tests conducted for foundation investigations including other locations;
Present summary of the field investigations/observations, in-situ and laboratory tests data,
evaluation of the design parameters and treatment proposed;
Geology, engineering geology, and hydrogeology characteristics of the catchments are explained
in brief and discussed.
The drainage system, history, nature and relative age of the rivers studied and assessment on
the catchment area related to the presence of soluble rocks, erodibility and degree of weathering
with respect to sediment transport, identification of the possible sources for water quality
problems and assessment on the presence of geological structure and their trend and extent are
made.
Weir or dam axis and abutment geomorphology, geology, hydrogeology and engineering geology
are studied in detail and problems of stability, soil bearing capacity, instability, water tightness,
such as presence of faults, fissured materials, and their permeability, slop and slip, etc… are
addressed.
Investigate foundation features of the recommended headwork site, canal route and retaining
walls and determine the depths of bed rock/hard stratum.
Carryout geological test pits at a depth of 3-5m or more if necessary at reasonable interval
depending on the topographic features of headwork site along the cross section and longitudinal
section of the proposed sites;
Carryout a log profile to clearly indicate the material composition of the foundation material,
foundation level and ground water condition;
General engineering geological conditions of the main canal is investigated along the tentatively
selected route and at its immediate vicinity by approximating the change from the headwork or
from any well-known reference point, concerning its stability, permeability, workability etc,.
Moreover, major gully crossings are also studied at the assumed point of canal crossing and its
vicinity. During the investigation, samples are taken for different tests if necessary;
Identify any geological hazard in the project area which threatens sustainability;
Finally, detailed analyses of all the data are carried out and a brief engineering geologic, hydro-
geologic, geologic report is to be produced which includes location map of the site and
construction material.
2.3.1 Construction Material Survey
Adequate coverage survey shall be carried out at the proposed site for identification of suitable sites for
construction material. This shall cover:
Investigation for identification of locations of potential quarries for construction materials like rock,
aggregates, sand, soils and water; and distance, quality, quantity and hauling distance including
access route are to be examined;
Estimation of quantity of material for each location, details of sample collection/testing of the
materials, quality/suitability of the material, road maps showing the transport road up to the
borrow area in relation to the construction site(s) shall be provided;
Identifying the borrow areas; and preparation of location maps, road maps etc. showing the
transport road up to the borrow area, relating the same to the construction site(s);
Collection and evaluation of samples from borrow areas (rock, sand, soil and aggregate quarry
sites) for its suitability for different types of materials shall be collected for laboratory tests;
The depth of the pits/auger holes shall depend upon the availability of the soils and economic
exploitation. The borrow area shall be located at near the working site as possible. Pits/auger
holes (diameter 15 to 30 cm) shall be taken in the proposed borrow area on 30 to 50 m grid
depending on the uniformity of soil depth & type and representative samples collected/tested for
different types of strata/soil to determine their properties and delineate the soil zones;
For assessment of quantities, drill holes shall be taken in consultation with geologist, if required;
Required details of any other material as indicated in the earlier items shall be indicated.
Note that the plan and section showing the stratification of the borrow area shall be included in the appendix.
The lead for different types of soils from the site(s) of work for different borrow areas shall be included in the
appendix.
2.4 Watershed Management Study
Previous studies, interventions and relevant documents on topography, or physical features of the
watershed, climate, catchments morphologies, vegetation, soil, land use/ cover, socio-economic
activities, erosion assessment, past conservation activities and scientific measures/
recommendations done in the area if any, will be thoroughly reviewed and the gaps and
shortcomings shall be clearly identified; and the history of the watershed area in terms of the
past land use practice and subsequent social, economical and ecological effect will have to be
described.
Investigate soil erosion and deforestation problems of the area and propose mitigating strategies;
Investigate natural and human induced factors that aggravate soil erosion and land degradation.
Any watershed management practice if existed and its ultimate output will have to be assessed
and the extent of work done or conservation efforts on agricultural land, grazing land, forest land,
etc shall be quantified for each land use type and summarized in a tabular form.
The study should cover the topography or physical features of the watershed, catchments
morphologies, (drainage and stream density etc.), soil physical features, major socio-economic
activities. It should also include land use/cover (past, present and future) of the watershed and
define each of them. It should also include erosion assessment as its type, location and amount,
past conservation activities and scientific measures done in the area;
Identify existing land use and propose land capability classification in the watershed; Land
capability classification based on criteria in relation to the most important features observed in the
field and those directly or indirectly related with soil-water erosion such as slope, soil depth, past
erosion, infiltration, water logging, soil texture, etc. Classify the land into soil requirement class
based on appropriate method;
Identify improved soil and water conservation, forestation and land use measure/technologies, for
each land use classes which are harmonious to farmers‟ activities, work volumes, etc. to be
undertaken for sustainable management of the watershed;
Carry out erosion rate and sediment yield estimation and the implication for the future project
(Diversion or Pond), before and after the project for the weir;
The computation of important hydrological parameters C, CN, TC and determination of the design
period, usually 10 years for SWC structures;
Determine, design and fix capacities and dimensions for the recommended SWC structures. The
detailed methodology used in designing and quantifying the required amount of conservation
work shall be discussed.
Prepare base maps and general SWC development maps and layouts for all the watershed area;
showing the administrative, sub-watershed units, necessary structures and other relevant
quantitative and qualitative information;
Prepare specifications and estimate costs for the conservation measures and/or structures; which
includes the time requirements, schedules and priorities including the implementation calendar
corresponding to each activities and months of the year.
Carryout hydrologic, hydraulic and structural designs of SWC structures;
Identify physical and financial inputs required for the implementation of the proposal;
If the water source for SSI is shallow groundwater, watershed management practices shall
include ways to enhance artificial recharge;
Produce watershed maps including DEM, soils, land use and land cover;
Produce detailed hydro-meteorological data for the watershed and surrounding stations;
Identify hotspots within the watershed in terms of soil and water conservation, groundwater
recharge zones, etc;
Identify the feasibility of cost sharing between upstream and downstream users, such as payment
for environmental services;
Identify availability of infrastructure such as roads, nursery, nursery store and office etc,
availability of man power such as staffs in the Office of Agriculture, guards (forest and others) and
nursery workers like foreman and the type and amount of tools and equipments for
implementation of the watershed development programme and propose necessary
measures.
2.5 Irrigation Agronomy
Aspects to be covered in the Irrigation Agronomy Studies will include: -
Assessment and description of the physical features of the project/ project area/ including
information about agro-ecology, climate, location, water resource, topography, soil and other
features of the command area, in relation to the land suitability for irrigation development;
Assessment and description of the present agricultural practices of the area; including, but not
limited to, information about major crops, productivity, cropping pattern and calendar, farming
practices, input use, crop protection, extension service and other relevant activities. Major
production constraints should be clearly assessed and described so as to seek and propose
appropriate solutions;
Select the most appropriate crops which will be suitable for the prevailing climate, soil, available
water and available labor in the new irrigation system;
Carry out the estimation of crop water requirement through widely applicable methods;
Determine cropping patterns, cropping calendar, irrigation intervals, and irrigation frequencies
considering hydrology, soil, climatic, actual cropping practice of individual farmers, and
socioeconomic data;
Propose recommendations as to the most appropriate type of inputs such as seeds, fertilizers,
and chemicals and their levels of use taking into account the environmental factors;
Propose recommendations as to the most appropriate and improved agronomic/crop
management/ practices such as crop protection, optimum planting/sowing depth, and optimum
plating, spacing, threshing, storage and other relevant practices,
Calculates the labour, animal, and machinery requirements of the farm, their distributions, and
scheduling;
Propose recommendations on the type and model of the farm machinery and tools;
Estimate the availability of labor, draught animals, machinery rental facilities, regional market
areas, etc.;
Determines the projected agricultural development costs of the area and likely returns from the
project during its early and later phases;
Estimate crop yields based on any existing data from the study area; the factors taken into
consideration for the projection should be described and justified.
Identify the need for input supply, credit services, training, extension support, marketing facilities,
and crop facilities and estimate cost for each service;
Assess the agricultural marketing values of the selected crops and prepare crop budget of the
crops at the final stage of the study;
Assess the possibility of appropriate processing and storage techniques of the identified crops
Compute the amount of water required for irrigation of the selected method of irrigation as well as
for at least two irrigation efficiencies;
Determine the critical periods for irrigation each selected crop so that to ensure adequate water
availability at these times;
Calculate and determine the consumptive use of various potential crops and the irrigation
requirements and prepare irrigation scheduling considering complex cropping at a farm level;
Collect climatic data from appropriate stations and simulate the data from the study area;
Investigate all major crop diseases, pests, weeds and suggest prevention and control strategies.
Perform land irrigability and capability classification and/or land suitability evaluation for crops for
sustainable development of irrigated agriculture;
Soil and land suitability maps must be prepared and incorporated in the report at a scale of
1:1,000 with contours having an interval of 0.25 m; to an appropriate depth of 2m or the bed rock,
whichever is shallower;
In-situ soil physical parameters such as infiltration test, hydraulic conductivity, PH, etc should be
included in the report;
Procedures as proposed in the FAO guidelines for land evaluation will be used. FAO soils
bulletin No32 (A frame work for land evaluation) and FAO bulletin No55 (A guideline for land
evaluation for irrigated agriculture) will be followed.
Note that soil auger hole observation data, soil profile description, infiltration test, hydraulic conductivity tests
and laboratory analytical data must be included in the appendices in electronic format.
The socio economy study is to be conducted by the help of focus group discussion, consultative meetings, a
sample household survey, PRA techniques and other data collection methods. If the irrigation projects cover
a relatively lower area of land, all of the households could be identified by name and by their demographic
characteristics whereas further detail study of the population and other socio economy study components
could be made through a household sample survey and other data collection methods. The sample size will
be determined based on the total number of households, the diversity of the socio economic conditions and
the availability of local resources to be collected and organized. The survey and analysis will include but are
unlikely to be limited to:-
1) Establish Study Frameworks: The Socio-economic Study shall prepare and present to the client for
review and approval general and specific Objectives, approach and methodology, Project Rationale, data
and information collection formats, data analysis tools as well as Scope and Limitation of the study.
2) Identification of the Various Components of the Project Area:- The various project places could be
classified into temporary and permanent project area categories. Those project areas consist of the
command area, headwork, camping & offices, material sites, working places and others. The study begins by
clearly identifying those places into their categories and would conduct the study by giving emphasis for
those project specific places. Apart from this the study would be made in comparison with the rest of the
places such as kebele, wereda and region within which the project is located and at country level at large.
The locations of Basin, woreda, and kebele, within which the project is found as well as the project locations
for head work , command area and the various project component places would be provided with GPS aided
reference data together with some description of the project areas.
3) Identification of the Population of the Project Area and Investigation of Population Dynamics: The
number of population and households of the project areas classified into the number of male and female
beneficiary households and population would be clearly identified. The population could be categorized into
beneficiaries and those that could be affected by the project. The classification would be identified and
analyzed by the study. In order to understand the impact of the present and future population growth on the
resources and planned irrigation schemes, population dynamic will be investigated and family planning
practice will be examined. The proportion of the economically active population will also be analysed so as to
assess the labor availability of the area of or the intended project. Population size, religion, ethnicity, age and
sex composition (heterogeneity and/or homogeneity), Population spatial distribution, population projection,
the respective demand for food, supporting capacity and other necessities in the project and the catchment
area. Assess current settlement pattern, township, population movement or migration and Infant and child
mortality situation in the area would also be investigated.
4) Investigate the Availability of Accessibility of All Social Services and Possibility of the
Contributions It has for Future Development of the Irrigation Project: The availability and accessibility of
social services such as health, education, water supply, Financial institutions, Energy supply/ Mineral source,
Communication (road, transport, telephone, other ICT services ... ) veterinary and other infrastructure and
social services are to be investigated in order to assess the potentials/ constraints and possibility of the
contribution it has for future development of irrigation project.
5) Identify and Analyze the Present and Projected Economic Systems, Input Demand, Supply and
Consumption, Product Markets and Facilities, Primary &Secondary of the present and demand, supply and
consumption; product markets and facilities; and credit services would be done. Few details are provided
below.
Economic Systems:- In this line of study, the economic base of the beneficiary farmers would be studied.
The list of activities that would be included in the study includes but not limited to : Economic source/ Major
means of livelihoods/potential income generating activities; Farming System; Crop production (potential
crops, area covered by potential crops , Current Irrigation Practices and Tradition, constraints of crop
production); Livestock production (Major livestock type, size, major diseases ; Other economic activities
&potentials (Potentials of apiculture, fish, forest &forest product etc.); Land Use Pattern (area under different
use, cultivated/ cultivable, pasture, forest, bushes & shrubs land, rivers & lakes ... ) and Land Tenure and
Size of Holdings. The analysis would very much be supported with relevant data which can represent the
study area under consideration.
Project Benefits:-The study shall identify and analyze direct and an indirect benefits of the project. The
study shall identify direct economic benefit of the project to the area including land holding of the household,
agricultural yields and production of major and minor crops, family income from both crops and livestock's
and farm income per area as a result of the proposed project. Non- economic benefits includes upper
watershed forestation, to reduce siltation problems of irrigation structures and thus lengthen the useful life of
structures and reduce annual operation and maintenance costs. Besides, project development creates
infrastructure benefits, welfare facilities and income and employment opportunities outside the project.
Input Used: - The type, quantity, availability and prices of input supply in comparison of demand and
consumption requirements and credit services (existing &future) would be studied.
Product Marketing and Facilities:- The study of product marketing includes the followings: Proportion and
quantity of marketable Agricultural products; Product marketing and agro processing; Communication
(Transport, road .... ); Storage; Marketing channels; Marketing size and structures; Marketing constraints.
Actual and projected national/ regional and project data should be provided for the intended crops. Market
potentials for project production should be identified and quantified to the extent possible such as own
consumption, local and/or regional markets, national markets, international/export markets. Price analysis
and fluctuations; prices of existing and proposed crops are required to be clearly stated and included.
Besides, how demand &supply of crops &livestock are determined need to be studied.
6) Identify Development Potentials, Constraints in Order to Involve all stakeholders in the Project
Area for Sustainability of the Project: The study shall Identify development potentials, constraints of the
scheme in order to involve all stakeholders in the project area for sustainability of the project; Existing NGO's
and area of cooperation with the community, suggestions with regard to additional government and private
institutions and services that may be required for effective implementation and operation of the scheme
would be conducted.
7) Undertake Gender Analysis: For sustainability of the schemes, the extent of Involvement of women in
the development of the project and ways of maximizing their role and active participation will be examined.
8) Social impact and mitigation measures
Direct social positive and negative impacts will be assessed and measures to mitigate negative impacts will
be recommended. In light of this the following area of impact will be considered:-
Impacts related with the reservoir area, Dam and appurtenant structures.
Impacts related with canal, road, drain etc. alignments
Impacts related with irrigation command area
Impacts in selection of borrow area and quarry sites
Social impediment impact (Compensation requirements)
Attractive beneficiary impact (upstream and downstream impacts)
Impacts on agricultural yields, water points, settlements, perennials and others for c
compensation requirements and land redistribution
Generally assessments of the social implications of the project, including displacement, land reallocation,
compensation, etc. would be undertaken. In this respect, the study should Identify the expected/existence of
displacement and asset losses due to the intended project. The effect of displacement and asset losses if
any, size and nature of land/asset that will be affected (settlement, grazing land, crop land, forest land, other
social value such as recreational, holy place, aesthetic etc) need to be identified and quantified. If there is
necessity of compensation payment or replacement of properties due to construction of the project, the study
shall be conducted with the beneficiaries and the study and design team. The agreement and the consensus
of the community shall be attached to the project document. Different option for compensation mechanisms
should be sighted. Direct social positive and negative impacts will be assessed and measures to mitigate
negative impacts will be recommended. In light of this , impacts on the headwork & appurtenant structures;
canal, road, drain etc alignments; irrigation command area ; borrow area and quarry sites , social
impediments (Compensation requirements and land redistribution) , current and projected upstream and
downstream water users; agricultural yields, water points, settlements, perennials and others will be studied.
Carry out the facilitation tasks to strengthen or establish irrigation water users association (IWUA)
by beneficiaries and work together with the assigned IWUA committee during the study and
design period.
The project development must begin with the community and with their concerns and needs. This helps to
establish a sense of ownership and control by the beneficiaries over their own schemes. This can be
achieved through a community demand-led approach where the consent and participation of beneficiary
communities in project conception, preparation, construction, and construction supervision and operation
phases is required as the main criteria for project funding. Therefore, the project will be implemented in such
a way that the schemes shall be a demand driven type in which the first initiation has to come from the
beneficiaries themselves.
The client would like to encourage communities to participate in decision-making and contribute 10% of civil
works investment cost in the form of cash, labor and/or local materials during project implementation. Such
involvement and contributions help develop a sense of community ownership of the project; enhance local
responsibility for long-term operation, maintenance and sustainability; and reduce overall project costs.
During the planning (conception, identification, survey, design) and construction stages there must be liaison
between the design and/or construction teams and the beneficiaries. The projects designs must be
discussed with and accepted by the community. The design process will proceed in parallel with the process
of setting-up the Irrigation Water Users Committee (IWUC). Therefore, the study and design team should
provide the liaison with the Community and deal with the detail of design and construction issues. The final
detailed design must be discussed with and accepted by the community through the IWUC in order to ensure
that the concerns of the community and potential impacts on non-beneficiary local residents are taken into
account. Meetings and continuous dialogue throughout the development process are necessary for the
stakeholders to contribute as well as to identify and defuse potential conflicts. There should also be
agreements, preferably written and signed, that each party will execute its function throughout the planning,
design, implementation, operation and maintenance phases of the scheme.
Undertake Public Consultation and Assessment of Attitudes: The study should conduct Clear
consultation and communication with wereda officials & wereda administration council, PA officials, DA's and
Individual farmers in the project area as well as other up and down stream users of the water. Community
awareness creation (Brief description about project idea, its plan, future direction & the objectives of the
study crew shall be given to District officials, PA officials, DA' s, individual farmers and others in & around the
project area).
General Meeting with the community: Discuss with the community openly about Irrigation project plan;
explain clearly the duties & responsibilities of the community & the client, Come to a certain consciences and
carry out the study with the representatives of community (Design committee consisting of minimum 7
members).
Community Participation in the project cycle: The study shall discuss that peoples
participation would be in all the phases of the project i.e. during Study & Design Phase; during
Implementation Phase and During Scheme Operation and management phase.
Identify forms/Modes of Community Participation: Contribution of the community (labor,
material, money, etc,) from the total cost of project; should be quantified in terms of money; type
and volume of the work they involve as well as in percentage. The beneficiaries will confirm
participation in the agreement and signed by the beneficiaries and authorized by the local
administration. Also this participation shall be quantified and clearly shown in the value (Birr) in
the project document to clearly state communities project costs share. The beneficiaries' labor
contribution schedule will be done on the basis of their slack period and they also shall approve
this.
Land Redistribution: The beneficiaries shall decide on the irrigation land distribution and confirm
this by the agreement signed by all beneficiaries and wereda administration and PA of the project
area shall authorize this.
Cost Recovery: The idea of the cost recovery will be discussed with the beneficiaries and the
opinion of beneficiaries towards the water tariff payment shall be identified and included in the
project document.
Attitudes: The important changes that population feels necessary to improve their economic conditions and
in particular their understanding and desire for the introduction of irrigated agriculture will be identified.
Assessments of the attitudes, views and opinions of different stakeholders towards the new project (Based
on the meeting and discussion) would be conducted. In this regard, positive, negative and indifferent
attitudes of the Community, kebele administration office, wereda administration council and officials, other
water users of upstream, downstream and nearby residents would be assessed.
Petition of the community, PA and District confirmation: The socio economy study should attach a copy
of a written application presented by the communities for development of the scheme and their commitment
to participate in the whole project cycle. A written agreement attachment of wereda and kebele
administration councils indicating that communities will contribute their project cost share in kind or cash is
required. Moreover, the study should contain writing confirmation letter that District Administration and PA
are consulted and certify the need for the project and community willingness to participate in the projects
It is clear that direct farmers participation or through the IWUC may take time and affect the planning and
detailed design of the irrigation layout. Careful phasing of activities in the proposed work plan can minimize
delays.
Therefore, the study and design team needs to follow the following steps to ensure and encourage the
participation/involvement of stakeholders are to:
Identify the persons, groups and organizations connected with or influenced by the project;
Identify their level of influence on the project, for example key stakeholders such as women, who
provide the bulk of the labour, and displaced persons should have a significantly stronger
influence;
Involve them in all decision-making processes and characterize their influence on the project;
Assure them and make them feel that they have the power to influence in the course of
development.
Farmers in irrigation scheme planning and design shall be involved in the following way and activities:
Endorse layout of canal network specifically Tertiary and field canals layout based upon farmer
and community meetings;
Decide on the location of canal outlets and turn outs; and location of pumping points (if any) for
diversion from canals;
Location of crossing structures such as foot bridges across canals, and cattle crossings at points;
and social structures such as washing points, cattle troughs, steps into the canal for water
collection points at locations to be identified by the community;
Endorse location of camping site and design of office as it will be used for IWUA office, which
should be constructed, based on a standardized design;
Farmers should identify and select lands to be irrigated and the irrigation design team should
assist farmers by assessing the suitability of those lands;
Farmers could provide information on past experience with floods, point out areas with potential
for flooding, and suggest to the study and design team locations for structures such as water
abstraction from the river to prevent the pump station from being flooded;
Farmers should select the crops to be grown in the project and the study and design team should
guide them only on technical matters related to the suitability of such crops for the climate, soils,
the cost of production and expected returns as well as the marketing potential of these crops.
The study and design team however should also provide farmers with various alternatives to
choose from including new crops, especially those that are high-value crops that the farmers may
not be familiar with, with clear potential for adaptation to local conditions, and potential for
production and marketing (cost and benefit);
The communities within the area to be developed should participate in the Environmental and
Social Impact Assessment (ESIA) for the project, through contributing vital information, such as
current uses of their natural resources, ecology, human health, etc;
The study and design team should facilitate the exposure of the farmers to various irrigation
methods and enlighten them as to the advantages and disadvantages of each. The farmers then
should propose the irrigation methods they would prefer to be considered during irrigation design;
The prospective irrigators should suggest the plot sizes they would prefer to irrigate and the
irrigation study and design team should provide information on the management, labor and input
costs required for different plot sizes, as well as on the potential of the land and water resources
to satisfy the various sizes.
To this end, the consultant is expected to bring the following certificates to ensure that adequate
consultations have been made:
The consultant should be responsible for bringing a certificate from the respective Woreda
Administration Office about acknowledgement and request made by the beneficiaries;
The scheme initiation and identification should be carried out jointly with beneficiaries in such a
way that the beneficiaries are willing to contribute 10% of the project civil works investment cost
either in the form of cash, labor and/or supplying construction materials with detail action plan
indicating what, when, where and how to implement.
The consultant should be responsible for bringing a certificate from the respective Woreda Office
of Water Resources/Office of Agriculture about agreement made between the IWUC members
and the Woreda Administration. (A scheme implementation agreement must be entered into
between the respective IWUC and Woreda Administration).
The consultant should be responsible for bringing a certificate from the respective Woreda or
Regional Bureau of Environment Protection, Land Use Planning and Administration
environmental and social screening and land holding certificates; (or Realistic arrangements must
be put into place for the issuance of land certificates to beneficiaries of the respective command
area).
The consultant should be responsible for bringing a certificate from the respective Woreda Office or Regional
Bureau of Agriculture stating that, the respective watershed has been treated or that realistic arrangements
(including finance) have been made for its treatment.
Generally assessment will be made on the existing irrigation organizational and management aspects.
Based on this and with the full participation of the beneficiaries, a Water Users Association (WUA) shall be
proposed and that will be responsible for the day to day operation & management of the irrigation system.
The organization & management proposal of the WUA should enable the irrigation system to sustainable
operate based on cost effective operation and full participation of the beneficiaries. The recommendation will
include procedures and techniques of the operation & maintenance, fee collection from beneficiaries and the
land distribution amongst the beneficiaries (as appropriate). The study O&M should include: Structure, duties
and responsibilities of WUA as well as cost estimates.
The study should contain proposals to monitor the physical and financial activities of the scheme; indicate
responsible bodies for this task of Evaluation Mechanism and indicative costs.
Previous studies and relevant documents if any will be thoroughly reviewed and the gaps and
short comings shall be clearly identified;
Carryout the selection of appropriate headwork site and associated structures to divert/store the
water and convey it to the main canal by gravity considering the location of the command area,
geology, hydrologic condition and economy;
Select and fix the type, length, height of headwork structure considering the locally available
construction material, the river morphology at the site, the magnitude of design flood, optimum
command elevation, etc;
Carry out detail hydraulic and structural designs for the headwork and other appurtenant
structures (flood protection structures, retaining walls, intakes, under sluice and other gates)
specifically Hydraulic design, to fix the overall dimensions and profiles of the structure, and
Structural design, where the various sections are analyzed for stresses under different loads and
reinforcement or other structural details are worked out;
The canal head regulator should be properly aligned to reduce silt entry into the canal to avoid
backflow and formation of stagnant zones in the pocket. To achieve this, as much as possible the
o o
axis of canal head regulator should be positioned at an angle of 90 to 110 with respect to the
axis of the diversion work.
Discharge capacity of the under sluices is kept based on the followings: (i)Two times the
maximum discharge in the off take canal; (ii) 20% of maximum flood discharge; or (iii) Maximum
flow in dry season; whichever is appropriate.
Layout, profiles and cross-sections of river diversion and its appurtenant structures as well as
canal and drainage networks and structures shall be prepared at appropriate scales;
Detail design of Night storage (if the discharge is not sufficient) to irrigate the available irrigation
land;
If in case pump system is required in the irrigation system design, in the pump part the following
points should be undertaken but not limited.
Pump house site selection and pump house design
Analysis of possible options on the number of pumps in relation to technical and economic
points of view
Design information such as elevation data including Maximum and Minimum water levels,
Foot value level, Pump seat OGL, Delivery pool OGL, Main canal out let at delivery, Delivery
pool bed level, Delivery pool Pipe outlet level etc shall be clearly shown
Determination of Suction and Delivery heads and pipe sizes (diameters and thicknesses)
Head loss and power requirement calculations considering the irrigation demand and the
required head
Comparison of the suction head along with the other accompanying losses to the theoretical
atmospheric pressure at the pumping site altitude
Pump type selection
Stilling basin site selection and Design to regulate the discharge from the delivery pipe.
Summary of pumping unit
Detail specification of the pumping unit including construction materials of different parts
such as casing, shafts, suction and delivery pipes etc.
The alignment of the field canal shall be marked along high ground so that it can command maximum area.
As far as possible, it should be taken along the boundary of a holding so that the field is not artificially divided
by the channel. The field canals will be aligned either along the ridge so that irrigation can be done on both
sides or along the contour with irrigation only on one side, depending upon topography. It should be ensured
that the turnout can be placed in the holding it serves and near the boundary. Besides, suggestions from and
endorsement by the farmers‟ organization regarding alignment, requirement and tentative location of off-
takes, outlets and turnouts, are sought. Details of the individual holding in the unit command area should be
obtained so that the number of farmers under each outlet is known at the time of design.
The profile should show the ground level, the bed level and eventually the water level at design discharge.
Bed levels and eventually water levels are tabulated at the end of each reach, which means upstream and
downstream of each structure where the water level changes. The location of outlet shall be such that it
avoids canals in deep cutting. A canal in deep cutting creates major problems of blockage of canals due to
collapse of side slopes. Location and sill level of turnout is very important. Hence, it is emphasized that
location of turnout shall invariably be decided after interaction with the respective farmer. The location of
turnouts shall be decided based on the experience (if any) and convenience of concerned farmers to irrigate
his fields in one or two seasons.
Before the actual design of field canals shall be taken up, the longitudinal section shall be run along the
alignment recording spot levels at 30 – 50 m interval. Cross section across the alignment may be taken at
50-60m interval and at the location of turnouts. The cross section may extend adequately on either side to
judge the sill levels of turnouts, with respect to area it has to serve. The L- section for each segment of field
canal shall be surveyed separately, with appropriate survey equipment.
While marking the alignment of the field canals, it should be seen that the canal can command the fields
included in the design. For this purpose, preferably the water level in the field canal shall be kept as 10-15
cm higher than the ground, it is designed to serve.
The bed width of field canals shall be wide enough to allow easy cleaning. A bed width of 0.20-0.30 m is
considered to be the minimum, as this still allows the cleaning of the canal with small tools such as a shovel.
Canal deliveries should be designed for an equal to crop water requirement during peak demand plus
irrigation and operational losses. Water losses vary with the irrigation distribution system, method of
irrigation, soils, crops grown, farm management practices, and others. For the reasons of economy, it should
not be oversized. Canal delivery should be large enough to provide adequate water for crop requirements
under existing and anticipated irrigation methods.
The consultant is expected to present canal design data for construction by drawing a longitudinal profile of
the canal route and tabulating the data needed for construction. The data are tabulated under the graph,
showing the elevation of ground and canal bed in figures at each given distance including water depths could
also be shown. The chainage starts from a reference point, which is usually the beginning of the canal.
Where possible the survey results of the topographic survey shall be used. If these are not sufficient, a
detailed survey of the proposed ali
Direction: water flow is always given from left to right.
Horizontal scale: 1: 1 000 for short canals (1 cm = 10 m) and 1: 5000 for long canals (1 cm = 50
m)
Vertical scale: 1: 20 for small canals and low gradient (1 cm = 0.2 m) and 1: 100 for larger canals
and higher gradient (1 cm = 1 m)
Based on these basic design considerations, the consultant shall carry out the following specific activities:
Carry out delineation of irrigable land based on accepted criteria;
Carry out preparation of layout clearly indicating the canal and drainage networks;
Design of proper irrigation and drainage system compatible with the local management system
conditions;
Identify canal lining requirements using the inputs from engineering geology studies and mitigate
in the design process;
Investigate drainage parameters required to perform the design of the drainage system of the
project and establish proper drainage modules for the project to effect the design of the drainage
system for the command area;
Establish flood protection requirements for the command area and canal structures;
Considering the total demand and base flow availability, perform detail hydraulic and structural
designs of irrigation canal systems including determination of water profiles and calculation of
canal cross sections and other elements to fix capacities for canals and associated structures;
and prepare an equitable water distribution system b/n different blocks and individual plots;
Carry out detail engineering design of the main irrigation system and drainage system (Intake
structure, main, secondary, tertiary and field canals and drains and related hydraulic structures)
considering the size of service unit to be between 10 ha to 20 ha;
Preparation of profiles of main, secondary, tertiary and field canals at a specified scale including
the canal and drain sections, sizing, lining type, crossing structures, division structures,
regulating, measuring and protecting structures, etc;
Compute the actual evapo-transpiration, crop water requirement, irrigation demand duty using the
existing and recent agronomic, climatologically and soil data based more appropriate and
acceptable methodologies;
Determine and estimate water application, conveyance and other losses, irrigation hours per day
and irrigation efficiencies and consider those parameters in design steps;
If necessary, design access roads, farm roads and inspection roads, which will connect the
project to the nearby road network and serve to give easy access to irrigation scheme, irrigation
structures and all the irrigation command units;
Prepare general plans and drawings for all irrigation infrastructure and irrigation system designs
to the standard quality;
Prepare specifications and priced bill of quantities for the irrigation project.
9. Environmental and Social Assessment (ELA)
9.1 Introduction
This terms of reference (TOR) is prepared for the irrigation water development project when the
environmental and social impact assessment is be conducted to determine the most critical issues that will
need to be addressed when site clearing, cut and fill, excavation, construction, camping, operation (water
application, drainage, etc), and decommissioning.
A TOR provides descriptions of the proposed project, the current environmental condition of the project site,
additional baseline data and methods that must be conducted, the probable environmental impacts
associated with the project, and potential mitigation approaches to reduce the negative impacts of the project
on the environment at a level of detail that satisfies the regional environmental protection, land use and
administration bureau, and the donor – the World Bank.
A comprehensive description of the relevant parts/component of the subproject, using maps, site plans, and
other graphic aids and images, as appropriate and necessary, and including the following information on:
location, general layout and size, general design and extent of the irrigation and design work (specification of
the irrigation headwork and infrastructures, size of the command area), size of the catchment area; as well
as pre-construction, construction, post construction plans, operation and maintenance of the irrigation works.
Description of the need for the proposed project (economic and social benefits) should also be described.
The following information should also be included:
Subproject type and its components, scope, subprojects activities during each phases (pre-
construction, construction, operation, and decommissioning if there is;
Overall suitability of the identified subproject and the proposed activity in light of the existing
environmental and social legal requirements;
Technologies involved for design, construction, operation;
Resources, manpower, time frame etc. required for the subproject implementation;
Baseline data should include the demography, settlements, and existing infrastructure facilities in
the proposed area.
Social safeguard issues as a result of water use conflict between the upstream and
downstream community. Information should be provided on water balance considering the
minimum flow of the river, the current users (in the command area, downstream and upstream
beneficiaries) of the given water resource for different purpose (irrigation, livestock, and domestic
purpose), ecological function, the amount to be diverted, the deficiency resulted to the
downstream users due to the diversion.
Control over allocation of resources use rights; community structure, employment, distribution of
income, goods and services; public health and safety (creation of pathogen breeding ground
(Malaria, Communicable Disease).
Details of the properties, houses, businesses etc. activities likely to be affected by land
acquisition and their financial lose annually should be well described.
Identification of historical and archeological sites to be affected by the subproject should be done.
While this analysis is being conducted, an assessment of public perception of the proposed
development should be conducted. A public presentation will be conducted to alert the
stakeholders about the project and its associated implications. This will be conducted on the
completion of the ESIA.
Data covering the community which is affected negatively by subproject including vulnerable
groups or persons such as women, children, elderly, and people below the poverty line should be
described.
Task-3: Policy, Legislative & Regulatory Considerations
Describe the pertinent regulations and standards governing environmental quality, safety and health,
protection of sensitive areas, protection of endangered species, sitting and land use control at the
international, national, and regional levels.
estimated costs of any associated mitigation measures. Include the alternative of not constructing the
project, in order to demonstrate environmental conditions without it.
The social impacts due to land acquisition and property loss should be described clearly. Based on the
information provided in task 2 above, information should be provided on the arrangements on how, who,
when to manage (avoid, minimize, and compensate) the social safeguard issues should be clearly described.
This should be done as per the Resettlement Policy Framework (RPF) of the program included in the ESMF
guideline of the program.
The other social safeguard issues related to SSI is social conflict between the upstream and downstream
community as a result of diverting the water. In this section of the work information should be provided,
based on the information provided in task 2 above, on the degree of the impact and the mitigation measures
for this. The impacts on the physical and cultural resources along with their mitigation measures should be
provided clearly.
The significant positive and negative impacts, direct and indirect impacts, long term and immediate impacts
should be indicated. Any avoidable as well as irreversible impacts should also be identified. A major
environmental issue is determined after examining the impact (positive and negative) on the environment
and having the negative impact significantly outweigh the positive. It is also determined by the number and
magnitude of mitigation strategies which need to be employed to reduce the risk(s) introduced to the
environment. Project activities and impacts should be represented in matrix form with separate matrices for
pre and post mitigation scenarios. For this, the assessment method/methods employed for the study
should be explained.
institutional and training requirements to implement them. Consider compensation for to affected parties for
impacts which cannot be mitigated. Prepare an environmental and social management plan (ESMP), and
resettlement action plan (RAP – if there is land acquisition and property loss).
The mitigation measures for the social safeguard should be done in detail. This may include the
arrangements on how, who, when to manage (avoid, minimize, and compensate) the social safeguard issues
should be clearly described. This should be done as per the Resettlement Policy Framework (RPF) of the
program included in the ESMF guideline of the program.
In case when resettlement action plane (RAP) is required to be prepared for the social safeguard issues
related to land acquisition and property losses, follow the elements of RAP in the ESMF prepared for AGP.
Appropriate mitigation measures should be proposed when there are impacts identified on the physical and
cultural resources of the project area. This is based on the information provided in task 2 and 5 above.
Information on the appropriate mitigation measures for the social safeguard issues to address the water
users conflict between the upstream and downstream community should be done based on the information
provided in task 2 and 5 above should be provided clearly.
The monitoring program should clearly indicate the linkages between impacts identified in the ESIA report,
indicators to be measured, methods to be used, sampling locations, frequency of measurements, detection
limits (where appropriate), and definition of thresholds that will signal the need for corrective actions, and so
forth. Although not essential to have complete details of monitoring in the ESMP, it should describe the
means by which final monitoring arrangements will be agreed. Responsibilities for mitigation and monitoring
should be clearly defined. The ESMP should identify arrangements for coordination between the various
factors responsible for mitigation. When preparing the monitoring plan table, use the mitigation plan table
template annexed in this TOR below.
outcomes and recommendations made by the participant. His has to be documented in the ESIA report in
the public involvement section. Though the public involvement is essential for the whole ESIA process,
special attention should be given when identifying social impact, developing mitigation measures, and
implementing them for those social impacts (land acquisition and property losses, and water user conflicts).
The whole process supported with evidence should be documented.
Task-10: Reporting
The environmental and social assessment report should be concise and limited to significant environment
and social issues. The main text should focus on findings, conclusions and recommended actions, supported
by summaries of the data collected and citation for any references used in interpreting those data. Detailed
or un interpreted data should be annexed or in separate volume.
An environmental impact statement (EIS) should contain the following information:
An executive summary
List of consultants/specialists who participant on the study team: Names and qualification of
members of the study team.
Introduction (scope and methodology of the study, important environmental issues in the study,
report structure)
Description of the subproject
Policy, legal and administrative requirements
Description of the environment (baseline environmental, socio-economic and health conditions
such as fauna, flora, habitats, soil, water, air, cultural artifacts, and socio-cultural, socio-economic
and health considerations).
Analysis of alternatives
An account of the prediction and assessment of each impact at all stages of the subproject cycle.
Information for each impact must be provided on: the methodology used; the magnitude of
immediate and cumulative impacts – long and short term (expressed in appropriate units);
whether it is adverse or beneficial; whether it is reversible or irreversible; likelihood of its
occurrence “with and without” scenarios; the time span for which impacts are predicted and the
geographic boundaries selected to define the study area
Description of measures to prevent or reduce significant adverse impacts and enhance beneficial
effects and an assessment of their likely outcome.
A description of residual impacts which cannot be mitigated or can only be mitigated partially.
Description of the ESMP: in this section description of the following information should be done
APPENDIX IV: Environmental and Social Mitigation and Monitoring Plan Template Tables
Operation and
Maintenance
Phase
Activity 1.
Activity 2.
.
.
Project cost estimates provide the basis of determining the project's economic and financial viability and it's
funding. Estimates should include all capital costs and incremental operating costs incurred by the project
during the disbursement period and for the subsequent operation of the project. In principle, the engineering
cost estimates should include all incremental goods and services required to complete the planned works.
Cost estimates for the main civil engineering works should be based on Bills of Quantities (BOQ), derived
from detail designs and justified unit rates. Costs of major equipment items should be based on recent
quotations from potential suppliers. Costs of on-farm development may be drawn from an aggregation of
representative farm models but it should be clearly indicated whether these include cash or non-cash
contributions (e.g. in the form of family labour or locally available materials) by farmers. Cost estimates of an
acceptable format should be prepared for all the proposed works considered at the final detailed design with
schedules of expenditure. The consultant should make sure that:
The cost per ha of the scheme shall not be more than 4000 USD as a result reasonable cost cutting
options should be included while designing and estimating;
Appropriate unit rate estimation/establishment and analysis is included in the design report;
Provisions for contractor overhead cost and profit should be included in the estimate;
Machine rental rates, material and labor costs should be based most recent data;
A value added tax (VAT) of 15% shall be considered;
A physica1financia1 contingency of 10-15% on the estimates shall be adopted to make allowance for
changes in unit price and in item quantities and/specifications during construction.
The consultant shall conduct the financial and economic analysis covering the following aspects
Prepare and present to the client for review and approval, the detailed approach, methodologies,
assumptions and tools to be applied in undertaking financial and economic analyses of the
proposed schemes, including (a) use and application of previous study methodologies,
assumptions and results if any, (b) sources and assumptions to be used for financial pricing and
conversions to economic prices, (c) discounting procedures, rates and periods to be used, ( d)
feasibility evaluation indicators and criteria to be calculated and applied (e.g. benefit/cost ratio,
net present value, internal rate of return) and (e) sensitivity and risk analyses - including
switching value calculations.
Review the recommendations of previously conducted viability study reports, in terms of crops,
cropping patterns, crop budgets, farm models, crop water and irrigation requirements, location of
irrigable areas, and investments if there is any.
Prepare crop budgets for without the project case. Prepare crop budget for the proposed range
of irrigated crops taking account of (a) input requirements including labour, (b) attainable yields
and yield development, and (c) gross and net crop margin. Compare summary of yearly
production cost and revenue under "without" and "with" project condition
In consultation with the agronomist, prepare crop production plan for the project.
Review the cost data provided within the engineering and other sectoral studies and make use of
them for the viability analysis.
Assemble and tabulate financial cost estimates, covering all initial and replacement investment
and recurrent (operation and maintenance) costs, prepared using constant prices, with physical
and price contingency allowances included and disaggregated into foreign and local currency
components, with tax and subsidy components separately identified, expressed in equivalent
BIRR and presented on an annual cash flow basis over the assumed life of the development.
Assemble corresponding estimated incremental direct agro-economic financial benefit streams,
prepared using constant prices (or suitably applied price projections if warranted) and
appropriate assumptions as to (a) likely build-up of agricultural production volumes over the
years following in the initial investments and (b) likely future agricultural production trends in the ''
without production situation''
To the extent that this is possible and significant, identify, estimate and incorporate into the
financial benefit streams the potential indirect agro-economic benefits.
Carry out a financial and economic feasibility analysis in accordance with the agreed approach
and methodologies, and involving iterative interactions with agricultural and engineering
development plans, designs, and cost and benefit estimates, as needed or as determined by the
stakeholder consultation.
Carry out a financial analysis at farm level to confirm financial viability, farmers' capacity to pay
the full O&M costs plus any capital recovery that may be decided, and, returns to labour.
Support in highlighting any other issues that would need to be resolved prior to proceeding with
detailed designs and implementation with, where possible, recommendations as to how and by
whom action is required, specifying an appropriate timeframe. These will include but are unlikely
to be limited to agronomic, engineering and other sectoral costs and benefit streams.
In addition to the outputs mentioned above in different disciplines, the following are also expected from the
final output of the study:-
Preparation of operation and maintenance manual
Detail specification and bill of quantity
Preparation of Tender Documents
Preparation of Drawing Albums for construction