Name of the Project: Gurmura and Panari Water Supply Scheme
Cluster:
Avail. Duration of ESR Lucknow
:Construction 2 Years
Geo.tech. investigation
SL NO Location status Land clearance Drawing status
status
1 OHSR-2 KOTA CLEARED COMPLETED
2 OHSR-AMMATOLA PENDING PENDING
3 OHSR-TELGURWA PENDING PENDING
4 OHSR-KANOPANI PENDING PENDING
NIL
5 OHSR-GURMURA PENDING PENDING
6 OHSR-PANARI CLEARED COMPLETED
7 OHSR-KHAIRAHI PENDING PENDING
8 OHSR-BAIRPUR CLEARED COMPLETED
# Sensitivity: LNT Construction Internal Use
Type Formwork Material Workmen
Scheduled
Capacity of Formwork
Ht.of staging construction Formwork Workmen
ESR(KL) Intz Flat set
duration set required available
available
250 12 2 Year No No No
400 20 2 Year No No No
200 20 2 Year No No No
125 20 It will finalized 2 Year No No No
after Drawing
200 24 finalization 2 Year No No No
200 24 2 Year No No No
150 24 2 Year No No No
100 24 2 Year No No No
# Sensitivity: LNT Construction Internal Use
Workmen
MEP -pipe , puddle Painting spec
Workmen Hydro test Remarks
flange available finalized
required
No No No No
No No No No
No No No No
No No No No
No No No No
No No No No
No No No No
No No No No
# Sensitivity: LNT Construction Internal Use