Daily Report
Report No: SAPAC-RMAF-SAR-DR-60 Date: 28-Jul-2021
Project Name Remedial Measures Against Flooding In Al Jouf Province Annex 2
Owner Saudi Railway (SAR)
Consultant Khatib & Alami
Contractor Saudi Pan Kingdom Company -(SAPAC)
Cumulative Planned Progress % 8.92% Cumulative Actual Progress % 20.40%
Day
Sat Sun Mon Tue Wed Thu Fri
Weather Status:
Windy Rainy Cloudy Sunny/Clear
Humidity: Low Medium High
Temperature: 37°-20°
Contractor Manpower in Site : األيدي العاملة لدى المقاول في الموقع
Administration officer
Planning Engineer
Quantity Surveyor
Auto cad operator
Total Direct M.P
QA/QC inspector
QA/QC Engineer
Total direct M.P
QA/QC Manager
Security guard
Design Engineer
Tech. office Eng
Project Manager
Auto Electrion
Desil Mechanic
Safety inspector
Chief Surveyor
Payroll Officer
HSE Engineer
Skilled /Labor
HSE Manager
Site Engineer
Safety officer
Doc. control
Office Boy
Surveyor
Operator
Lab tech
Driver
Forman
Total
Actual
1 1 1 1 1 1 1 2 1 1 1 1 1 5 1 1 1 1 1 23 1 1 1 27 1 1 2 4 3 39 62
Planned
1 1 1 1 1 1 1 2 1 1 1 1 1 5 1 1 1 1 1 23 1 1 1 11 1 1 2 4 1 21 44
Contractor Equipment in Site :المعدات لدى المقاول في الموقع
Roller Compactor
Concrete mixer
Concrete pump
DISEL Truck
Service Truck
Mobile Crane
ISuzu Pickup
Dump Truck
Boom Truck
Water Truck
Rental Car
Excavator
Small Car
Generator
Buldozer
Raw 4x4
Poclain
Loader
Bobcat
Grader
Total
JCB
Actual
0 1 0 1 5 0 1 0 0 1 1 0 0 0 2 6 1 7 4 5 0 35
Planned
0
Work in Progress Today Work in Progress Tomorrow & RFIs
1 Earth Work at Points (35,36,37,41,45,54,55,56) 1 Compaction for Bottom of Aggregate Erosion Protection ,Zone-5, Point 53
2 Survey Work for Point (53,54,55,56,51,45) 2 checking of cutting in point (54,55,56,35,36,37)
3 Shop Drawing Point 5,6 3 Survy Work (20,21,22)
4 Riprap at Point (47) 4
5 Riprap at Point (51) 5
6 Aggregate Slope Protection Point 53 6
7 7
8 8
Progress Photograph ( Site Office Mobilization & Survey Work)
Earth Work Point 36 Earth Work Point 36
28/07/2021
Point 53 aggregate layer 2 Point 53 aggregate layer 2
Earth Work Point 35 Cut work for ditch P. 54,55,56
Areas where Work Not Available as Planned (Issue if any needed to be cleared)
Submitted By Contractor: Reviewed By Consultant:
Name: Said Mohamed (PM / Contractor Annex-2) Name: Engr. Ihab Shokry (PM - Consultant)]
Signature: Signature:
28-Jul-2021 Date:
28/07/2021