0% found this document useful (0 votes)
90 views50 pages

Rampal Jetty-Geotechnical Investigation Spec-BHEL

The document provides a technical specification for a geotechnical investigation of a proposed power project site. It outlines the scope of work to be performed, including field testing, laboratory testing, data analysis and reporting. It describes coordination needed with the engineer in charge and requirements for personnel qualifications and experience. It also references drawings of the site and requires the contractor to visit the site.

Uploaded by

CEG Bangladesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
90 views50 pages

Rampal Jetty-Geotechnical Investigation Spec-BHEL

The document provides a technical specification for a geotechnical investigation of a proposed power project site. It outlines the scope of work to be performed, including field testing, laboratory testing, data analysis and reporting. It describes coordination needed with the engineer in charge and requirements for personnel qualifications and experience. It also references drawings of the site and requires the contractor to visit the site.

Uploaded by

CEG Bangladesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 50

TECHNICAL SPECIFICATION FOR SPEC. NO.

PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 1 OF 50

TECHNICAL SPECIFICATION
FOR
GEOTECHNICAL INVESTIGATION

1.0 GENERAL

1.1 This specification covers the technical requirements for a detailed


“Geotechnical investigation and submission of a detailed geotechnical
report”. The detailed geotechnical investigation shall be carried out
onshore/offshore (on Land/River) to provide the designer with
sufficiently accurate information both general and specific about the
substrata profile and relevant soil and rock parameters at site on the
basis of which the foundation for various structures and equipments
of the power station can be designed rationally. Such structures would
include main power house, Bypass Stack, boiler foundation, turbo-
generator foundation, foundation for vibratory equipments, deep pits,
reservoir, pipe supports and all other related structures of the power
station etc. The above list is indicative and not exhaustive. The range
of load intensities from the various structures are expected to be
between 50 kN/sqm and 500 kN/sqm.

2.0 SCOPE

2.1 The work shall include mobilization of all necessary equipments,


providing necessary engineering supervision and technical personnel,
skilled and unskilled labours, arranging water for drilling etc as
required to carry out the entire field as well as laboratory
investigation, analysis and interpretation of test data collected and
preparation of a geotechnical report. The entire field as well as
laboratory investigation work shall be supervised by a graduate in
civil engineering with atleast 5 years of site experience in respective
areas of geotechnical investigation work. A geologist shall also be
deputed at site during investigation whenever rock drilling is
undertaken. The scheduling of laboratory tests, analysis and
interpretation of test results, drafting of report and recommendations
shall be carried out by a post graduate in geotechnical engineering
with atleast 5 years of experience.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 2 OF 50

2.2 The contractor shall make his own arrangements for locating the co-
ordinates and position of bore holes, trial pits and other field tests as
per the drawings/sketches supplied to him and for determining the
reduced levels at these locations with respect to a single bench mark
indicated by the engineer-in-charge. Two established reference lines
will be indicated to him. The contractor has to provide at the site all
the required survey instruments to the satisfaction of the engineer-in-
charge so that the work can be carried out accurately according to the
specification and drawings.

2.3 All the field data shall be recorded in the proforma recommended in
Indian Standard Codes and the field records shall be counter signed
by the engineer-in-charge. The contractor shall submit two copies of
the field borelogs to the engineer-in-charge soon after the completion
of each bore hole. All the investigations are to be carried out by the
contractor as per the priority requirements of the engineer-in-charge.

2.4 The contractor shall intimate the engineer-in-charge giving reasons if


any additional specific tests he consider necessary to be carried out
duly considering local sub-soil conditions before starting of such
tests.

2.5 Whenever the contractor is unable to extract undisturbed samples he


should immediately inform the engineer-in-charge. In such a case
payment for boring charges shall be subject to the engineer-in-charge
being satisfied that adequate effort has been made to extract
undisturbed samples.

2.6 All the laboratory test data shall be recorded in the proforma
recommended in the Indian Standard Codes and a copy of these shall
be sent to the engineer-in-charge every week during the progress of
laboratory testing. Whenever desired during the progress of work the
owner/engineer-in-charge may be present at the laboratory where the
contractor is arranging for execution of the laboratory tests.

2.7 The contractor shall interact with the engineer-in-charge to get


acquainted with the different type of structures envisaged and in
assessing the load intensities on the foundations for the various
structures of the power project in order to enable him to make
specific recommendation for the depth & type of foundation and the
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 3 OF 50

allowable bearing pressure. The contractor shall submit detailed


geotechnical report after incorporating the comments (if any) on the
draft report.

3.0 TENDER DRAWING

3.1 The enclosed Topographical survey & Geotechnical Investigation


Layout (DRG. No. PE-DG-K45-601-C001) indicate the tentative
location of the bore holes and field tests/areas to be investigated for
locating the project. The location, extent and depth of bore holes &
field tests/area(s) indicated in the drawing is subject to change that
may be necessary during actual execution of the work. No claim
whatsoever shall be entertained for differences between the location,
extent and depth/area(s) etc of soil tests indicated on the construction
drawings and those shown on the tender drawings. The work shall be
carried out as per the instructions of the engineer-in-charge.

3.2 The bidder must visit the site prior to submitting his quotations to
acquaint himself fully with the nature, type, scope of work and
involvement therein. The rates quoted shall remain firm during the
entire period of execution till completion of the work and any
additional claim for lack of knowledge shall not be entertained.

4.0 GENERAL REQUIREMENTS

4.1 In areas which have already been developed, the contractor shall take
advantage of existing local knowledge, record of trial pits, bore holes
etc in the vicinity and the type of foundations adopted and behaviour
of existing structures particularly those of similar nature to the ones
proposed for this project.

4.2 The contractor shall make use of information gathered from quarries,
unlined wells, cuttings from nearby areas etc. The general
topography of the near by areas will often give some indication about
the variation of the soil conditions which are likely to exist.

4.3 The contractor shall gather data regarding the removal of overburden
by excavation, erosion or land slides in the areas which may give an
idea of the amount of reconsolidation that the soil strata has
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 4 OF 50

undergone. Similarly data regarding recent fills shall also be studied


to determine the characteristics of the fill as well as the original strata.

4.4 The water level in streams and water courses if any in the
neighbourhood shall be noted. Reliable information regarding ground
water level shall also be gathered from water level in the near by
wells.
4.5 The contractor shall make enquiries and verify regarding earlier use
of the site which can have important bearing on its suitability for the
proposed structures. This is important particularly in areas where
there have been underground works e.g. worked out ballast pits,
quarries, old brick fields, mines, mineral workings etc. The
possibility of damage to the structures, sewers, conduits and drainage
system by subsidence shall also be investigated.
4.6 It is essential that the equipments/instruments are properly calibrated
at the commencement of the work so that they represent true values
and submit the test reports to the engineer-in-charge. If the engineer-
in-charge so desires, the contractor shall arrange for having the
instruments tested in presence of the engineer at an approved
laboratory at the contractor’s cost and the test reports shall be
submitted to the engineer-in-charge.
4.7 When blasting with explosives is involved, agency/contractor shall
arrange statutory clearances and also the portable magazine for
storing/carrying the explosives.

5.0 CODES AND STANDARDS

5 .1 All standards, specification and codes of practice referred to herein


shall be the latest editions including all applicable official
amendments and revisions.

5.2 In case of conflict between this specification and those (IS codes and
standards etc) referred to herein the former shall prevail.

5.3 All work shall be carried out as per the specification and the
following standards and codes.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 5 OF 50

IS: 1080 Code of practice for design and construction of simple


spread foundations

IS: 1498 Classification and identification of soils for general


engineering purposes

IS: 1888 Method of load test on soils

IS: 1892 Code of practice for subsurface Investigation for


foundation

IS: 1904 Code of practice for design and construction of


foundations in soils: General requirements

IS: 2131 Method of standard penetration test for soils

IS: 2132 Code of practice for thin walled tube sampling of soils

IS: 2470 Code of practice for design and construction of septic tanks
Part-I

IS: 2720 Method of test for soils (Relevant parts)

IS: 2809 Glossary of terms and symbols relating to soil


engineering

IS: 2810 Glossary of terms relating to soil dynamics

IS: 2911 Code of practice for design and construction of pile


foundations (Relevant parts)

IS: 2950 Code of practice for design and construction of raft


Part- I foundation

IS: 3025 Methods of sampling and testing (Physical and chemical)


for water used in Industry

IS: 3043 Code of practice for earthing

IS: 4078 Code of practice for indexing and storage of drill cores
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 6 OF 50

IS: 4434 Code of practice for in-situ vane shear test for soils

IS: 4453 Code of practice for exploration by pits, trenches, drifts


and shafts

IS: 4464 Code of practice for presentation of drilling information


and core description in foundation investigation

IS: 4968 Method for subsurface sounding for soils- Dynamic


Part -II method using cone and bentonite slurry

IS: 4968 Method for subsurface sounding for soils-Static cone


Part-III penetration test

IS: 5249 Method of test for determination of in-situ dynamic


properties of soil

IS: 5313 Guide for core drilling observations

IS: 5529 Code of practice for in-situ permeability test – Test in


Part-I overburden

IS: 5529 Code of practice for in-situ permeability test - Test in bed
Part-II rock

IS: 6065 Recommendation for the preparation of geological and


geotechnical maps for river valley project

IS: 6403 Code of practice for determination of allowable bearing


pressure on shallow foundation

IS: 6926 Code of practice for diamond core drilling for site
investigation of river valley projects

IS: 6935 Method of determination of water level in a bore hole

IS: 6955 Code of practice of subsurface exploration for earth and


rockfill dams
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 7 OF 50

IS: 7422 Symbols and abbreviations for use in geological maps,


sections and subsurface exploratory logs (Relevant parts)

IS: 8009 Code of practice for calculation of settlement of


Part-I foundation subjected to symmetrical vertical loads -
Shallow foundations

IS: 8009 Code of practice for calculation of settlement of


Part-II foundation subjected to symmetrical vertical loads –
Deep foundations

IS: 8763 Guide for undisturbed sampling of sands

IS: 8764 Method for determination of point load strength index of


rocks

IS: 9143 Method for the determination of unconfined compressive


strength of rock materials

IS: 9179 Method for preparation of rock specimen for laboratory


testing

IS: 9198 Compaction rammer for soil testing

IS: 9214 Determination of modulus of sub-grade reaction in field

IS: 9259 Specifications for liquid limit apparatus

IS: 9640 Specifications for split spoon sampler

IS: 9669 Specifications for CBR mould and its accessories

IS: 10050 Method for determination of slake durability index of


rocks

IS: 10060 Code of practice for subsurface investigation for power


house sites

IS: 10074 Specification for compaction mould assembly for light


and heavy compaction
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 8 OF 50

IS: 10108 Code of practice for sampling by thin wall sampler with
stationary piston

IS: 10589 Equipment for determination of subsurface sounding of


soils

IS: 10837 Specifications of moulds for determination of relative


density and its accessories

IS: 11229 Specifications for shear box testing of soils

IS: 11315 Description of discontinuities in rock mass - Core


Part-II recovery and rock quality

IS: 12070 Code of practice for design and construction of shallow


foundations on rocks

IS:13372 Seismic testing of rock mass – Code of practice


(Part I & II)

6.0 FIELD INVESTIGATION - SOIL

6.1 Boring

6.1.1 General Requirements

a) Bore holes shall be drilled at specified locations to obtain


information about the sub-soil profile, its nature, strength and to
collect soil samples for strata identification and conducting laboratory
tests. The minimum diameter of the bore hole shall be 150 mm and
boring shall be carried out in accordance with the provisions of IS:
1892 and as per this specification.

b) All bore holes shall extend up to the depths shown on the


construction drawings or as directed by the engineer-in-charge. If the
strata with standard penetration test (SPT) ‘N’ value greater than 100
with characteristics of rock is met with earlier, the bore hole shall be
advanced further by chiselling. Chiselling shall be continued for a
maximum depth of 20cm or upto 2 hours whichever is earlier.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 9 OF 50

During chiselling rock fragments/rock cores shall be collected.


Identification of rock strata shall be on the basis of visual
examination of SPT sample and rock fragments. After it is
established that rock is met with, the borehole shall be advanced
further by drilling in rock as specified in clause 7.0 and cores shall be
collected. When the bore hole is terminated in soil strata, an
additional standard penetration test shall be carried out at the
termination depth.

c) Casing pipe shall be used in the borehole to support its sides when
side fall is suspected to occur inside the borehole. When casing pipe
is used, it shall be ensured that its bottom end is at all times 15 cm
above the bottom of the bore hole. In case of cohesionless soils the
advancement of the casing pipe shall be such that it does not disturb
the soil to be tested or sampled. The casing shall be advanced by
slowly turning the casing pipe and not by driving.

d) In-situ tests and collection of undisturbed samples (UDS) shall be


carried out at regular intervals and at change of strata or as decided
by the engineer-in-charge. Representative disturbed and undisturbed
samples shall be preserved for conducting various tests in the
laboratory. Water table in the borehole shall be carefully recorded
and reported. No water/drilling mud shall be added while boring
above ground water table. For cohesionless soil below water table,
the water level in the borehole shall all times be maintained at slightly
above the water table.

e) The bore hole shall be cleaned using suitable tools up to the depth
of testing or sampling ensuring that there is minimum disturbance of
soil at the bottom of the bore hole. The process of jetting through an
open tube sampler shall not be permitted. In cohesive soils, the
borehole may be cleaned using a bailer with a flap valve. Gentle
circulation of drilling fluid shall be done when rotary mud circulation
boring is adopted.

f) On completion of the borehole, the portion drilled in soil shall be


backfilled with sand unless otherwise directed by the engineer-in-
charge.

g) Wash boring shall not be adopted.


TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 10 OF 50

6.1 .2 Auger Boring

Auger boring can be adopted in soft to stiff cohesive soils above


water table. Augers shall be of helical or post hole type which may
be manually or power operated. While boring care shall be taken to
minimise the disturbance to the deposits below the bottom of the
borehole. The cuttings brought up by the auger shall be carefully
examined in the field and the description of all the strata shall be duly
recorded in the field borelog as per IS:1498. No water shall be used
while auger boring.

6.1.3 Shell and Auger Boring

Shell and Auger boring can be used in all types of soil free from
boulders. For cohesionless soil below ground water table, the water
level in the bore hole shall always be maintained at or above the
ground water level. The use of chisel bit shall be permitted in hard
strata with SPT-N value greater than 100. Chisel bits may also be
used to extend the borehole through local obstruction such as old
construction, boulders, rocky formations etc. All other requirements
in clause 6.1.2 shall apply for this type of boring also.

6.1.4 Percussion Drilling

This method can be adopted in soil with gravel and boulders when the
boring has to be done at a faster rate. This method consists of
breaking of the strata by repeated blows from a chisel or drilling bit
and bailing out the debris at intervals by adding water into the bore
hole. This method is not suitable for careful and very reliable
sampling operation because of the disturbance caused during boring.
This method shall not be adopted unless otherwise specified or
permitted by the engineer-in-charge.

6.1.5 Rotary Mud Circulation Drilling

This method can be used in all types of soil below water table. In this
method boring shall be done by rotating the bit fixed at the bottom of
the drill rod. Proper care shall be taken to keep a firm contact
between the bit and the bottom of the borehole. Bentonite or mud
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 11 OF 50

laden fluids shall be used as the drilling fluid to serve as the


protective surface inside the borehole.

6.2 Standard Penetration Test (SPT)

This test shall be conducted in all types of soil deposits met within
the bore hole to find the variation in the soil stratification by
correlating with the number of blows required for unit penetration of
a standard penetrometer. This test shall be conducted at 3m intervals,
at every change of strata, at depths wherever undisturbed soil samples
could not be collected and as per the directions of the engineer-in-
charge. The starting depth of performing SPT shall be either 1m or
2.5m depth below ground level. This depth shall be staggered in
alternate boreholes. The depth interval between the top level of
standard penetration test and to that of (next) undisturbed sampling
shall not be less than 1m. The specification for equipments and other
accessories, procedure for conducting the test, presentation of test
results and collection of disturbed soil samples etc shall conform to
IS: 2131.

This test shall be carried out by driving a standard split spoon sampler
in the borehole by means of a 650 N hammer having a free fall of
0.75m. The sampler shall be driven using the hammer for 450 mm
penetration. While driving, the number of blows for every 150 mm
penetration and the penetration for every 50 blows shall be recorded.
The number of blows for the last 300 mm drive shall be reported as
‘N’ value. This test shall be discontinued when the blow count is
equal to 100 and the penetration shall be recorded. Refusal shall be
considered to be met with when the blow count is equal to 100. At
the location where the test is discontinued, the penetration and the
corresponding number of blows shall be reported. Sufficient quantity
of disturbed soil samples shall be collected from the split spoon
sampler for identification and laboratory testing. The samples shall
be visually classified & recorded at the site and shall be properly
preserved and labelled for future identification & testing.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 12 OF 50

6.3 Sampling

6.3.1 General

a) Sufficient number of soil samples shall be collected for reliable


estimation of soil properties. The samples collected shall be either
disturbed or undisturbed. Disturbed soil samples shall be collected
for field identification and conducting laboratory tests such as sieve
analysis, index properties, specific gravity, chemical analysis etc.
Undisturbed samples shall be collected to estimate physical, strength
and settlement properties of the soil.

b) All the accessories required for sampling and the method of


sampling shall conform to IS:2132. All disturbed and undisturbed
samples collected in the field shall be classified at site as per IS:
1498.

c) All the samples shall be identified with date, bore hole or trial pit
number, depth of sampling etc. It is also essential to mark an arrow
pointing towards the top surface of the undisturbed sample as the soil
was in-situ. Care shall be taken to keep the undisturbed soil samples
and box samples vertically with the arrow directing upwards. The
tube samples shall be properly trimmed at both ends and suitably
sealed with molten paraffin wax at both ends immediately after
extracting the samples from the bore hole/trial pit and suitably capped
on both sides.

d) When the contractor fails to collect undisturbed soil sample at


a specified depth, the borehole shall be advanced by 0.50m and
shall be performed with a standard penetration test. The reason
for not obtaining the undisturbed soil sample shall be indicated in
the borelog.

e) Precaution shall be taken to ensure that there shall not be any


change in moisture content and disturbance of the soil samples and
they shall be placed in a temporary store at the end of the day's work.
All the samples shall be kept over a bed of sand, jute bags, saw dust
etc and covered over the top with similar material. The bed and top
cover shall be kept moist till they are properly packed in wooden
boxes. The contractor shall be responsible for packing and
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 13 OF 50

transporting of all the samples from site to the laboratory within


seven days after sampling with proper protection against loss and
damage.

f) All the samples shall be suitably packed in wooden boxes using


sand, saw dust etc all around the samples before transporting to the
laboratory for testing.

6.3.2 Disturbed Samples

a) Disturbed soil samples shall be collected from cuttings and from


split spoon sampler in boreholes at regular intervals to provide
complete description of soil profile and its variation. The samples
shall be immediately stored in airtight jars or polythene bags and
labelled with borehole/trial pit number and depth.

b) In elevated areas, if superficial material is available in plenty, then


bulk samples from a depth of about 0.5m below ground level shall be
collected to establish all required properties to use it as a fill
material. Disturbed samples weighing about 250N shall be collected
at shallow depths and immediately stored in polythene bags as per IS:
1892. The bags shall be sealed properly and shall be kept in wooden
boxes.

6.3.3 Undisturbed Samples

In each borehole undisturbed sample(UDS) shall be collected at


regular intervals of 3m and as directed by the engineer-in-charge.
The starting depth of collecting UDS shall be either 2.5m (where
starting depth of SPT is 1m) or 1m (where starting depth of SPT is
2.5m) depth below ground level and as directed by the engineer-in-
charge. The starting depth shall be staggered in alternate boreholes.
Undisturbed samples shall be of 100mm diameter and 450mm length.
Samples shall be collected in such a manner that the structure of soil
and its moisture content do not get altered. The specification for the
accessories required for sampling and the sampling procedure shall
conform to IS:1892 and IS:2132. Undisturbed sampling in sand shall
be done using compressed air technique as mentioned in IS:8763.
Thin walled sampler shall be used to collect undisturbed samples by
pushing the tube into the soil. The sampling tube shall have a smooth
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 14 OF 50

finish on both surfaces and minimum effective length of 450mm.


The area ratio of sampling tubes shall be less than 12.5%. However
in case of very stiff soils, area ratio upto 20% shall be permitted.

a) Undisturbed Sampling in Cohesive Soil

Undisturbed samples in soft to stiff cohesive soils shall be obtained


using a thin walled sampler. In order to reduce wall friction, suitable
precautions such as oiling the surfaces shall be taken. The bore hole
shall be cleaned and the depth of sampling below ground level shall
be noted. The sampler shall then be attached to the bottom of boring
rods and lowered into the borehole. The sampler shall be pushed into
the clay layer by hand or by jacking and soil sample of specified
length shall be collected without disturbing the soil. The distance by
which the sampler penetrates into the soil strata shall be checked.
Care shall be taken to ensure that the sampler is not driven too far as
this will compress the soil. The sampler shall be rotated to break the
core at bottom of the sampler and then steadily drawn up.

b) Undisturbed Sampling Using Piston Sampler

Undisturbed samples in very loose saturated sandy & silty soils and
very soft clays shall be obtained by using a piston sampler consisting
of a sampling cylinder and piston system. In soft clays and silty clays
with water standing in the casing pipe, piston sampler shall be used to
collect undisturbed samples. During this method of sampling expert
supervision is called for.

The interior surface of the sampler shall be smooth, clean and


corrosion resistant. Its cutting edge and the ring seals shall be
inspected for wear and rejected if worn. Check shall be done to
ensure that the moving parts of the sampler function freely before the
sampler is lowered into the borehole. While pushing the system into
the soil and till the beginning of the sampling operations, the bottom
of the piston shall be flushed with the cutting edge of the sampler. At
the depth of sampling, the piston should be fixed relative to the
ground and the sampler cylinder shall be independently pressed down
smoothly and continuously into the ground. If an obstruction is met,
the sampler shall be withdrawn and another sample be taken after the
obstruction is removed.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 15 OF 50

Accurate measurements of the depth of sampling, height of sampler,


stroke and length of sample recovery shall be noted and recorded.
After the sampler is pushed to the required depth, both the sampler
cylinder and the piston system shall be drawn up together ensuring
that there shall not be any disturbance to the sample which shall then
be protected from changes in moisture content.

c) Undisturbed Sampling in Cohesionless Soils

Undisturbed samples in cohesionless soils shall be obtained as per


the procedure given in IS:8763. Compressed air sampler shall be
used to take the samples of cohesionless soil below water table.
Precautions shall be taken to clean the borehole before sampling.
Thin walled tube samplers of 60mm internal diameter shall be used.
The height and other dimensions of the sampler shall be recorded
before use. Proper care shall be taken to maintain the water level in
the bore hole slightly above the ground water table before and during
sampling operations. Immediately after the sample is obtained, the
ends of the sample shall be waxed and capped to avoid moisture
content changes.

6.3.4 Relaxation During Sampling

a) The sampler shall be pushed into the soil and driving of sampler
shall be resorted to only when it cannot be pushed into the soil. This
shall be done only with the permission of the engineer-in-charge and
all the details about the same shall be recorded in the bore logs.

b) In clays when ‘N’ value is greater than 50, the undisturbed


sampling may be replaced by standard penetration test.

6.4 Ground Water

6.4.l One of the following methods shall be adopted for determining the
ground water table in bore holes as per IS:6935 and as per the
instructions of the engineer-in-charge.

a) In permeable soils, the water level in borehole shall be allowed to


stabilize after lowering it adequately by bailing. When water level
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 16 OF 50

inside the borehole is found to be stable, the depth of water level


below ground level shall be measured. Stability of sides and bottom
of the borehole shall be ensured at all times.

b) For both permeable and impermeable soils, the following method


shall be suitable. The borehole shall be filled with water and then
bailed out to various depths. Observation on the rise or fall of water
level shall be made at each depth. The level at which neither a fall
nor a rise is observed shall be considered as the water table elevation.
This shall be established by three successive readings of water level
taken at an interval of two hours.

6.4.2 In case any variation in the ground water level is observed in any
specific boreholes then the water level in these bore holes shall be
recorded daily during the course of field investigation. Levels in
nearby wells, streams etc if any shall also be noted whenever these
readings are taken. If so called for, observation wells shall be drilled
for the purpose of long term studies on the fluctuation in ground
water levels and pressure. Either stand pipe or piezometer shall be
installed at the specified depths in the selected previously drilled bore
holes or specially drilled bore holes for this purpose as per the
specification and instructions of the engineer-in-charge. Daily water
level readings shall be recorded immediately following the
installation upto the time of leaving the site. At the end of field work,
these installations shall be handed over in satisfactory working
condition to the engineer-in-charge without disturbing their position
so that the owner can continue further observations.

6.4.3 Stand pipes and piezometers shall consist of 19mm internal diameter
rigid unplasticised (UPVC) tubing. All the joints in the tubing shall
be made of coupling sleeves. The top of UPVC tubing shall be
enclosed in a 75mm diameter galvanised steel pipe of 1.5m length
having a galvanised steel screw cap with well greased threads and the
caps shall be tightened such that it would be impossible to loosen by
hand. The lower end of the pipe shall have four legs of 6mm thick
and 100mm long and welded to have projection of 25mm. The pipe
shall be sealed into the ground with cement grout so that it does not
rotate. The top end of the pipe shall project about 300mm above
ground level unless otherwise specified by the engineer-in-charge.
The perforated tubing for the porous element shall be surrounded by a
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 17 OF 50

response zone of well graded sand from 500mm below to 150mm


above the lower end of the stand pipe or piezometer and the bore hole
above the response zone shall be back filled with natural soil or well
graded sand.

a) Stand pipe

Stand pipes shall be installed to measure the water level in soils with
high permeability such as sand and gravel. The stand pipe shall
consist of a perforated tubing attached to the bottom of the UPVC
tubing. The perforated tube shall be 150mm long having perforations
of diameter not greater than 1mm.

b) Piezometers

Piezometers shall be installed to measure the pore pressures in soil


with medium to low permeability. Piezometer shall consist of a
porous filter attached to the bottom of the UPVC tubing. The filter
shall be 300mm in length and shall be placed in the bore hole and
sealed at top and bottom by grouting. Hydraulic piezometers with
double line are to be used to remove the air trapped in the system.

6.4.4 Sub-Soil Water Samples

a) Sub-soil water samples shall be collected for carrying out chemical


analysis. Representative samples of ground water shall be collected
when it is first encountered in boreholes before the addition of water
to aid boring or drilling. Water samples shall not be collected when
bentonite slurry or mud has been used for drilling operations. If
water has been added for drilling purposes or if ground water has
been diluted by surface rain water then the bore hole shall be
dewatered and water be allowed to rise from which the sample may
be taken.

b) The sampling apparatus shall be such that the water at the desired
depth can be collected directly without any disturbance and any
change in concentration of constituents like dissolved gases etc.
Undue agitation shall be avoided. An ordinary suction pump with its
suction end inserted upto the required depth in the borehole shall be
used for this purpose.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 18 OF 50

c) The sample shall be collected in a clean vessel and allowed to


settle so that the supernatural liquid can be poured into a clean well
rinsed glass or polythene bottle. Sufficient quantity and number of
samples shall be collected to carry out the chemical analysis and sent
to a laboratory in airtight bottles with proper labelling. Chemical
analysis of water samples shall include determination of pH value,
turbidity, sulphate, carbonate, nitrate & chloride contents, presence of
organic matter and suspended solids etc.

d) In some cases constituents may be mixed and analysed later as


specified in the specific test methods. Chemical preservatives may be
added to the sample for cases as specified in the test method/IS codes.
This shall only be done if analysis cannot be conducted within an
hour of collection and shall have the prior written permission and
approval of the engineer-in-charge.

6.5 In-situ Permeability Test

6.5.1 In-situ permeability test shall be conducted to determine the water


percolation capacity of overburden soil. This test shall be performed
inside the bore hole/trial pit at specified depths or in each layer or as
per the directions of the engineer-in-charge. The type of test shall be
either pump-in or pump-out test depending on the subsoil and ground
water conditions. Pump-in test shall be conducted whether ground
water in borehole exists or not. Pump-out test shall be conducted to
obtain data for dewatering purposes when ground water is met in the
borehole. The specification for equipments required for the test and
the procedure of testing shall be in accordance with IS: 5529, Part-1.
When it is required to carry out the permeability test for a particular
section of the soil strata above ground water table, bentonite slurry
shall not be used while boring.

6.5.2 Pump-in-Test

Pump-in test shall be conducted in the bore hole/trial pit by allowing


water to percolate into the soil. Choice of the method of testing shall
depend on the soil permeability and prevailing ground water level.

Only clear water shall be used for conducting the test. Before
conducting the test, the borehole shall be cleaned as specified in
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 19 OF 50

clause 6.1.1 (e). Water shall be allowed to percolate through the test
section for sufficient period of time to saturate the soil before starting
the observation.

a) Constant Head Method (In Bore Hole)

This test shall be conducted in boreholes where soil has a high


permeability. Water shall be allowed into the borehole through a
metering system ensuring gravity flow at constant head so as to
maintain a steady water level in the borehole. A reference mark shall
be made at a convenient level which can be easily seen in the casing
pipe to note down the fluctuations of water level. The fluctuations
shall be counteracted by varying the quantity of water flowing into
the borehole. The elevation of water shall be observed at every 5
minute interval. When three consecutive readings show constant
value, the necessary observations such as flow rate, elevation of water
surface above test depth, diameter of casing pipe etc shall be made
and recorded as per the proforma recommended in IS: 5529, Part-1,
Appendix-A.

b) Falling Head Method (In Bore Hole)

This method shall be adopted for soils of low permeability and which
can stand without casing. The test section shall be sealed at the
bottom of the borehole and a packer at the top of the test section. If
the test has to be conducted at an intermediate section of a pre-bored
hole then double packers shall be used. Access to the test section
through the packer shall be by means of a pipe which shall extend
above the ground level. Water shall be filled into the pipe upto the
level marked just below the top of the pipe and water be allowed to
drain into the test section. The water level in the pipe shall be
recorded at regular intervals as mentioned in IS: 5529, Part-1,
Appendix-B. The test shall be repeated till constant records of water
level are achieved.

c) Percolation Test (In Trial Pit)

Percolation test shall be conducted in trial pit in areas where


water/effluent is stored/discharged in ground level tanks. The loss of
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 20 OF 50

water due to percolation into the soil shall be estimated by the soil
absorption capacity.

6.5.3 Pump-Out Test

This test shall be carried out at site to determine the co-efficient of


permeability of soil below water table . This test shall be conducted
by continuous pumping out of water from a well so as to maintain a
steady water level at the desired depth in the well. The fluctuations in
the water level shall be counteracted by varying the quantity of water
pumped out of the well. The specification for the equipments &
accessories required for performing the test, the procedure of
testing, field observations and reporting of results shall conform to
IS: 5529, Part-1. The well shall be of 400mm in diameter to be
installed with a 250mm diameter perforated GI/MS pipe.
Observation pipes of 50mm diameter shall be installed at regular
intervals along three radial lines extending from the well at 120
degrees to each other. Length of these pipes shall depend upon the
ground level, estimated depth of lowering the ground water and the
distance from the well. Sufficient number of observation pipes shall
be installed along each of the radial lines so as to assess the zones of
influence due to dewatering. Draw down depth in the well shall be as
specified in the drawing.

6.6 TRIAL PIT

6.6.1 Trial pits shall be of 3m x 3m size so as to permit easy access for


visual examination of walls of the pit and to facilitate sampling and
in-situ testing operations. Pits shall be excavated upto a maximum
depth of 4m below ground level or as per the directions of the
engineer-in-charge. Precautions shall be taken to ensure the stability
of pit walls including provision of shoring if necessary as per IS:
4453. Precautions shall be taken to prevent surface water draining
into the pit. Arrangements shall be made for dewatering if the pit is
extended below water table. Trial pits shall be kept dry and a ladder
shall be provided for easy access to the bottom of the pit. ln-situ
tests shall be conducted and undisturbed samples shall be collected
immediately on reaching the specified depth so as to avoid
substantial changes in moisture content of the subsoil. Arrangements
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 21 OF 50

shall be made for barriers, protective measures and lighting


necessary for the period the pits remain open.

6.6.2 A note on the visual examination of soil strata shall be prepared.


This should include the nature, colour, consistency and visual
classification of the soil, thickness of soil strata, thickness of
expansive soil & ground water table if any etc.

6.6.3 Undisturbed samples shall be collected at 1m, 2m, 3m depth and at


the termination depth in all the pits.

a) Chunk Samples

In cohesive soils, undisturbed samples of regular shapes shall be


collected. The samples shall be cut and trimmed to a size of 0.3m x
0.3m x 0.3m. A square area of 0.35m x 0.35m shall be marked at the
centre of the levelled surface at the bottom of the pit. Without
disturbing the soil inside the marked area, the soil around this
marking shall be carefully removed upto a depth of 0.35m. The four
vertical faces of the soil block protruding at the centre shall be
trimmed slowly so that its size reduces to 0.3m x 0.3m. Wax paper
cut to suitable size shall be wrapped uniformly and covered with two
layers of thin cloth over all the five exposed surfaces of the soil
block and sealed properly using molten wax. A firmly constructed
wooden box of size 0.35m x 0.35m x 0.35m (internal dimensions)
with the top and bottom open shall be placed around the soil block
and held such that its top edge protrudes just above the surface of the
block. The space between the soil block and the box shall be filled
uniformly and tightly with moist saw dust. The top surface shall also
be covered with saw dust before nailing the wooden lid to cover the
box firmly taking care that the soil block is not disturbed. The area
of contact between the bottom portion of the block and the ground
shall be reduced slowly by removing soil in small quantities using
small rods so that the block can be separated from the ground slowly
without disturbance. After inverting the wooden box along with the
soil block, the bottom portion shall be trimmed and covered with
wax paper, cloth and to be sealed with molten wax. A wooden lid
shall be nailed to the box after providing proper saw dust cushion
below it. An arrow mark shall be made on the vertical face of the
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 22 OF 50

wooden box to indicate the top surface of the sample along with the
location, date and depth of sampling.

b) Tube Samples

Undisturbed tube samples may also be obtained by means of 100mm


diameter sampling tubes with a cutting edge. The sampler shall be
slightly oiled or greased inside and outside to reduce friction. The
sampler shall be pushed into the soil and while doing so soil around
the tube shall be carefully removed. In case it is not possible to push
the sampler it may be driven by light blows from a "monkey".

6.6.4 In case it is not possible to collect undisturbed samples in the pit, in-
situ density of soil shall be determined by sand replacement method.
The specification, equipments, accessories etc required for the test
and the procedure of testing shall be in accordance with IS: 2720,
Part-XXVIII. No separate payment shall be made for this test.

6.6.5 After the completion of the test, sampling and visual examination,
the pit shall be suitably backfilled as directed by the engineer-in-
charge. Unless otherwise specified excavated soil shall be used for
this purpose.

6.7 Vane Shear Test

Field vane shear test shall be performed inside the borehole to


determine the shear strength of cohesive soils, especially of soft and
sensitive clays which are highly susceptible to sampling disturbance.
This test shall be conducted by advancing a four winged vane of
suitable size (75mm or 100mm diameter as per the soil condition)
into the soil upto desired depth and measuring the torque required to
rotate the vane. The specification for equipments & accessories
required, the test procedure and field observations etc shall be as per
IS: 4434. This test may also be conducted by direct penetration from
the ground surface. If the cuttings at the test depth in the bore hole
show any presence of gravel, sand, shells, decomposed wood etc
which are likely to influence the test results substantially, the test at
that particular depth may be omitted with the permission of the
engineer-in-charge. However the test shall be conducted at a depth
where these obstructions cease to occur. On completion of the test
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 23 OF 50

the results shall be reported in an approved proforma as specified in


IS: 4434, Appendix-A.
6.8 Static Cone Penetration Test

Static cone penetration test shall be conducted to know the soil


stratification and to estimate the various physical and engineering
properties of soil. The cone penetrometer shall be advanced by
pushing and the static force required for unit penetration shall be
determined. The test shall be conducted using a 200kN capacity
mechanically operated equipment upto the specified depth or refusal
whichever is earlier. For this test, 'refusal' means meeting a very
hard strata which cannot be penetrated at the rate of at least
0.3cm/sec even when the equipment is loaded to its full capacity.
The specification for the equipment and accessories required for
performing the test, test procedure, field observation and reporting of
results shall conform to IS : 4968, Part-III. At the ground level,
preboring upto 0.5m depth shall be permitted if the overlying strata
is very hard. No extra payment shall be made on account of this
preboring. Continuous record of the penetration resistance shall be
maintained.

6.9 Dynamic Cone Penetration Test

Dynamic cone penetration test shall be conducted using bentonite


slurry by driving a standard size cone attached to the bottom of a
string of drill rods. The test shall be conducted upto the specified
depth or refusal whichever is earlier. Refusal shall be considered
when the blow count exceeds 150 for 300mm penetration. The
specification for the equipment and accessories required for
performing the test, test procedure, field observations and reporting
of results shall conform to IS:4968, Part-II. The driving system shall
comprise of a 650N weight having a free fall of 0.75m. The cone
shall be of 65mm diameter provided with vents for continuous flow
of bentonite slurry through the cone and rods in order to avoid
friction between the rods and soil. On completion of the test, the
results shall be presented as a continuous record of number of blows
required for every 300mm penetration of the cone into the soil in a
suitable chart supplemented by a graphical plot.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 24 OF 50

6.10 Plate Load Test

6.10.1 Plate load test shall be conducted to determine the bearing capacity
and load/settlement characteristics of soil at shallow depth by
loading a plane and levelled steel plate kept at the desired depth and
measuring the settlement under different loads until a desired
settlement takes place or failure occurs. The specification for
equipment and accessories required for conducting the test, the test
procedure, field observations and reporting of results etc shall
conform to IS: 1888. The location and depth of the test shall be as
given in the drawing or as indicated by the engineer-in-charge.
Undisturbed tube samples as specified in clause 6.6.3 (b) shall be
collected at 1m and 2.5m depths from the ground level for carrying
out laboratory tests.

6.10.2 The size of pit shall not be less than five times the plate size and the
depth shall be as specified. All provisions regarding excavation and
visual examination of pit under clause 6.6.1 and 6.6.2 shall apply
here also.

6.10.3 If the ground water table is at a depth higher than the specified test
depth, the ground water table shall be lowered and maintained at the
test depth for the entire duration of the test. Dewatering shall be at
the cost of the contractor.

6.10.4 Unless otherwise specified the reaction method of loading shall be


adopted. Settlement shall be recorded from dial gauges placed at
four diametrically opposite ends of the test plate. The test plate shall
be of 600mm x 600mm size and atleast 25mm thick. The bottom of
the pit shall be levelled before placing the plate in position for
conducting the test.

6.10.5 A seating load of 7kN/sqm shall be applied and after the dial gauge
readings are stabilized, the load shall be released and the initial
readings of the dial gauges be recorded after they indicate constant
reading. The load shall be increased in stages. These stages shall be
20, 40, 70, 100, 150, 200, 250, 300, 400, 500, 600 and 800kN per
sqm or as directed by the engineer-in-charge. Under each loading
stage, record of ‘time vs settlement’ shall be kept as specified in
IS:1888.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 25 OF 50

6.10.6 In case of cohesive soils, each load increment shall be maintained


until the settlement is less than 0.02mm/minute or 6 hours whichever
is later. Dial gauge readings for settlement shall generally be taken
at 1, 2.25, 4, 6.25, 9, 16, 25, 60, 90 and 120 minutes from the start of
each stage of loading. Thereafter the readings shall be taken at
hourly interval upto a further 4 hours and at two hours interval
thereafter for another 6 hours.

6.10.7 Other than cohesive soils, each stage loading shall be maintained for
a minimum duration of one hour or till the settlement rate reduces to
0.02mm/minute whichever is later. No extrapolation of settlement
rate from periods less than one hour shall be permitted. The final
loading shall be maintained for 24 hours. During unloading, reading
of dial gauge shall be recorded for each stage of unloading.

6.10.8 Loading shall be carried out in stages as specified above till one of
the following conditions occur.

a) Failure of soil under the plate i.e. the settlement of the plate at
constant load becomes progressive and reaches a value of 40 mm or
more.

b) Load intensity of 800 kN/sqm is reached without failure of the


soil.

6.10.9 Backfilling of the pit shall be carried out as per the directions of the
engineer-in-charge. Unless otherwise specified the excavated soil
shall be used for this purpose.

6.11 Cyclic Plate Load Test

This test shall be carried out to determine the dynamic soil properties
required for the analysis of foundation subjected to dynamic loads.
This test shall be conducted on similar lines as the ordinary plate load
test with an addition that unloading shall also be done before each
stage of loading. Test set up, load increment and maximum load
intensity etc shall be as per clause 6.10.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 26 OF 50

6.11.1 After each stage of loading, the load shall be removed in a minimum
of two stages and as directed by the engineer-in-charge. After each
stage of reduction of load, dial gauge readings and settlements shall
be taken for atleast one hour until the readings stabilize. Thereafter
the next loading stage shall commence. Recording and analysis of test
data shall be as per IS: 5249.

6.12 Field California Bearing Ratio Test

This test shall be carried out to obtain the properties of soil required
for the design of roads. The equipments and accessories required for
carrying out the test, test procedure, recording of observations and
presentation of results shall conform to IS: 2720 part XXXI. The test
locations and depth shall be as specified in the drawings or as
directed by the engineer-in-charge.

6.13 Electrical Resistivity Test

This test shall be conducted to determine the electrical resistivity of


soil required for designing safety grounding system for the entire
power plant area. The specification for the equipments and other
accessories required for performing the test, test procedure and
reporting of field observations shall conform to IS:3043. The test
shall be conducted using Wenner's four electrode method as specified
in IS:1892, Appendix-B2. Unless otherwise specified, at each test
location the test shall be conducted along two perpendicular lines
parallel to the co-ordinate axes. On each line a minimum of 8 to 10
readings shall be taken by changing the spacing of the electrodes
from an initial small value of 0.5m upto a distance of 10m.

6.14 Seismic Refraction Test

6.14.1 This test shall be carried out to establish the rock and soil profiles of
varying density. The dynamic shear modulus of the soil shall also
be obtained from the results of this test. The specification for the
equipments and other accessories, procedure for carrying out the
test, recording and analysis of results and their presentation shall
conform to IS: 1892.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 27 OF 50

6.14. 2 This test shall be carried out by inducing shock waves into the soil
by striking a plate placed on the ground surface with a hammer. The
shock waves shall be picked up through geophones placed on the
ground surface at regular intervals in line with the plate along a
straight line. The time elapsed before the waves reach the
geophones shall be recorded to an accuracy of one millisecond or
better.

6.14.3 The distance between the shock point and the geophones shall be
increased to cover a wider area. Alternatively, multiple geophones
shall be used simultaneously using multiple channel seismograph to
record the arrival time and intensity of waves reaching the
geophones. The spacing of geophones shall be 5m. As the distance
between geophones and the shock producing point are increased,
the time lapse for the waves passing through different underlying
strata and reaching the geophone shall be recorded. The wave forms
shall be recorded for each test using multiple channel seismograph.

6.14.4 The test shall be conducted along traverses in two orthogonal


directions as specified in the drawing or as directed by the engineer-
in-charge. During testing, proper care shall be taken to avoid
disturbance caused due to the movement of vehicles or other
working operations around the test location. The type of wave
(compression or shear) shall be analysed properly using the data
recorded during the test.

6.15 Cross Hole Shear Test

This test shall be generally carried out in accordance with IS: 13372
to establish the dynamic elastic properties of soil and rock. In this
test, the seismic waves are to be picked up in two adjacent receiver
boreholes. The spacing of boreholes shall be determined so as to
obtain good results. The boreholes shall be uncased in the portion
carrying the geophones. However it should be kept filled with water
or drilling mud in order to ensure perfect contact between the
borehole wall and the geophone. In case of cased hole preferably a
low velocity material such as a high impact PVC should be used for
casing and it is essential that it should be well grouted behind in
order to make an intimate contact with the soil. The charge shall be
installed within the depth as specified and the waves shall be picked
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 28 OF 50

up from the geophones installed at required depths in receiver


boreholes. Knowing the travel time from shot hole to receiver hole
and corresponding distance, the velocity of the waves is determined
which enables to estimate dynamic elastic modulus, shear modulus
and Poisson’s ratio. In each receiver borehole multiple geophones
shall be provided at 2m interval (with starting depth as 3m below
ground level) to cover the depth and various strata as specified.
Intensity of the waves shall be recorded by multiple channel
seismograph.

6.16 Pressuremeter Test

6.16.1 This test shall be conducted in bore holes at desired depth to obtain
the in-situ stress-strain characteristics and strength parameters of
soil/rock layer by measuring the deformation of the probe at
different pressures of the volumemeter. The location and depth of the
test shall be as given in the drawing or as per the directions of the
engineer-in-charge.

6.16.2 All precautions shall be taken to ensure a smooth bore hole of


required diameter with minimum disturbance to the surrounding soil.
In soft, loose and sensitive soils, the bore hole shall be predrilled
deeper than the testing depth for enough so that the cuttings settling
at the bottom of the bore hole shall not interfere with the test.

6.16.3 The equipment shall be calibrated for pressure losses (membrane


correction/air calibration) and volume or radius changes (line
calibration/thick wall rigid steel cylinder test) before starting of test
and at regular intervals as per the manufacturer’s specification.

6.16.4 Maximum value of pressure correction shall not be more than 50%
of limit pressure. The total volume loses in the system shall not
exceed 0.5% of the static probe volume per 100kPa. Volume
correction may he neglected in soil if it is less than 0.1% of probe
volume per 100 kPa.

6.16.5 The test shall be performed by expanding a cylindrical probe to


obtain a pressure vs volume or pressure vs radius curve as specified
in IS:1892. The probe may be of Ax, Bx or Nx size. However the
size of the borehole shall be compatible to the size of pressuremeter
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 29 OF 50

probe. Hose pipe connecting the probe with the surface unit shall be
of flexible tubing of single or coaxial type. The equipment should be
able to reach a maximum pressure of 5000kPa for testing in soil and
8000kPa for testing in rock. The accuracy of measuring device shall
be such that a change of 0.2% of static probe volume or 0.1% of
probe radius is measurable as specified in IS:1892.

6.16.6 The probe shall be lowered down to the required depth as soon as
the boring is completed so as to limit the expansion of soil due to
release of stresses. The probe shall be held by a clamping device
ensuring that it is not located at the interface of two different
soil/rock layers.

6.16.7 The pressure shall be increased in atleast 20 equal stages as directed


by the engineer-in-charge. At each stage the pressure shall be
maintained for a period of atleast 60 seconds and volume reading
shall be taken for 7 to 14 minutes. The volume of water sent into the
probe during this period shall be measured upto an accuracy of
0.01cum. In case the water level in the volumemeter drops rapidly, it
is necessary to close the volumemeter valve quickly so that the
reservoir does not empty and allow air or gas into the tubing.

6.16.8 The test shall be carried out in stages till one of the following
conditions occur.

a) The volume of the probe is doubled


b) Ultimate failure of soil/rock occurs
c) Load intensity of 5000kPa for soil and 8000kPa for rock is reached
without failure.

6.16.9 If the shape of uncorrected pressure vs volume curve drastically


varies from the ideal test curve, the test shall be repeated at no extra
cost to the owner at a different depth as decided by the engineer-in-
charge.

6.16.9 On completion of the test, all results mentioned in clause 9.2 shall be
reported.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 30 OF 50

7.0 FIELD INVESTIGATION - ROCK

7.1 Rock Drilling

Drilling in rock shall be done at specified locations or as per the


directions of the engineer-in-charge. Before commencing drilling, it
shall be proved that characteristics of rock has been met with as
mentioned in clause 6.1.1(b). The starting depth of drilling in rock as
mentioned in clause 6.1.1(b) shall be certified by the engineer-in-
charge. The portion drilled in rock shall be backfilled with 1part of
cement : 3 part of sand (1:3) grout unless otherwise directed by the
engineer-in-charge.

7.1.1 Equipment

a) Core drilling shall be done by rotary motion using diamond bit.


The feed or thrust to the drilling bit shall be actuated by hydraulic
system. The rotary core drilling equipment and procedure for drilling
shall conform to IS: 6926. The equipment shall be provided with
necessary facilities to regulate the spindle speed, bit pressure and
water pressure during core drilling to get a good core recovery.

b) Drilling shall be carried out with Nx size diamond tipped drill bits
or impregnated diamond bits depending on the type of rock
encountered. Double tube swivel core barrel of Type B conforming
to IS: 6926 shall be used to ensure a good core recovery and to pick
up cores from all layers of rock. Suitable core catchers shall be used
to ensure continuous and good core recovery.

7.1.2 Procedure

a) The drilling fluid shall be clean water. Circulation of drilling fluid


shall be started before the core barrel reaches the bottom of the hole
to prevent cuttings or sludge from entering the core barrel at the start
of coring. Drilling fluid shall be circulated continuously down the
hollow rods and the sludge conveying the rock cuttings to the surface
shall be collected.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 31 OF 50

b) When drilling through soft/weathered/fractured rock, water


circulation must be reduced so as to avoid shattering/breaking of
core.

c) The rotational speed of the bit (spindle speed), the amount of


downward pressure applied on the bit (bit pressure) and water
pressure shall be suitably adjusted and properly monitored so that the
core is collected with least disturbance and to avoid shearing of the
core from its base. Bit speed, bit pressure, water pressure for the
type of bit for various rock types shall be as per Appendix A of
IS:6926.

d) No drill run shall exceed 0.75m in length. This can be increased to


1.5m provided the core recovery observed is more than 80% in two
successive 0.75m drill runs and on approval from the engineer-in-
charge. If the core recovery is less than 20% then SPT shall be
performed before commencing the next drill run as explained in
clause 6.2.

e) If at any time blocking of the bit or grinding of the core is


observed, the core barrel shall be immediately withdrawn from the
borehole regardless of the length of drill run completed.

7.1.3 Observations

a) The colour of return water at regular intervals, the depth at which


any change of colour of return water is observed, the depth of
occurrence and amount of flow of hot water if encountered shall be
recorded.

b) The depths through which a uniform rate of penetration was


maintained, the depth at which a marked change in rate of
penetration or sudden fall of drill rod occurs, the depth at which any
blockage of drill bit causing core loss if any etc shall be recorded.

c) Any heavy vibration or torque noticed during drilling should be


recorded together with the depth of occurrence.

d) Special conditions like the depth at which grouting was done


during drilling, presence of artesian conditions, loss of drilling fluid,
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 32 OF 50

observation of gas discharge with return water etc shall also be


observed and recorded.

e) During drilling operation, observation on return water, rate of


penetration etc shall be recorded in a proforma as given in IS: 5313,
Appendix-A.

7.1.4 Core Samples

a) Core samples shall be extracted by the application of a continuous


pressure at one end of the core with the barrel held horizontally
without vibration. Friable cores shall be extracted from the barrel
directly into a suitable sized half round plastic channel section. Care
shall be taken to maintain the direction of extrusion of sample same
as that while coring to avoid stress reversal.

b) Immediately after withdrawal from the core barrel, the cores shall
be placed in a tray and transferred into boxes specially prepared for
the purpose. The boxes shall be made from seasoned timber or any
other durable material and shall be indexed on top of the lid as per
IS:4078. The cores shall be numbered serially and arranged in the
boxes in a sequential order. The description of the core samples
shall be recorded as per IS: 4464. Where no core is recovered, it
shall be recorded as specified in the continuous record of core
recovery and RQD in the corelog as per IS:11315, Part-II.

c) The basic information for the description of rocks shall cover


i) degree of weathering ii) discontinuity spacing iii) strength iv)
colour v) grain size vi) structural condition, the mineralogy of the
grains and cementing material vii) rock name, special features like
major joint planes, features/laminations, faults etc.

7.2 Standard Penetration Test

The relevant hardness of rocks shall be tested in boreholes after


every drill run of 0.75m in rock if core recovery observed is less
than 20% or as directed by the engineer-in-charge. The testing
equipment and arrangement shall be conforming to IS: 2131. The
number of blows for each 75mm penetration to a total penetration of
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 33 OF 50

450mm shall be recorded. Penetration for every 50 blows shall be


recorded and the test shall be stopped at a total of 100 blows.

7.3 Plate Load Test

The test shall be conducted as described under clause 6.10 for soil
subject to the following changes.

The test plate shall be of size 45cm x 45cm and at least 25mm thick.
The maximum load shall be 2500 kN/sqm to be applied in stages of
25, 50, 100,150,200, 300, 400, 600, 800, 1000, 1500, 2000 and 2500
kN per sqm. Under each load the time Vs settlement shall be
recorded and plotted.

7.4 Pressuremeter Test

This test shall be conducted as described under clause 6.16 for soil
subject to the following changes. The test shall be carried out till
one of the following condition occurs.
a) The volume of the probe is doubled
b) Ultimate failure of rock
c) Load intensity of 8000 kN/sqm is reached without failure.

7.5 Cross Hole Shear Test

This test shall be conducted as described under clause 6.15 for soil.

7.6 Permeability Test

Permeability test shall be conducted in bed rock inside the bore hole
by pumping in water under pressure to determine the percolation
capacity of the rock strata. This test shall be conducted in uncased
and ungrouted sections of the drill hole. Clear and clean water shall
be used for the purpose of both drilling and testing. The
specification for the equipments and other accessories, test
procedure etc shall conform to IS: 5529, part-II. The length of the
test section shall be either 1.5m or 3m as per field conditions and as
per the directions of the engineer-in-charge. The level of water table
(if any) in the bore hole shall be recorded and the drill hole shall be
cleaned before the start of the test. Depending upon the depth of the
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 34 OF 50

test section, single or double packer method shall be adopted. Care


shall be taken to maintain water tightness of all the joints and
connections during testing.

a) Single Packer method

This method shall be adopted when the bottom elevation of the test
section is the same as the bottom of the drill hole. The packer shall
be fixed at the top level of test section such that only the test section
lies below the packer. Water shall then be pumped through a pipe
into the test section under a required pressure and maintaining it till a
constant quantity of water intake is observed. The amount of water
percolating through the hole shall be recorded at every 5 minute
interval. The test shall be repeated by increasing the pressure at
regular intervals upto a pressure limit as specified in IS: 5529, part-
II. The details and observations shall be recorded in a proforma as
recommended in IS: 5529, part-II, Appendix-B.

b) Double Packer method

This method shall be adopted when the permeability of an isolated


section inside a drill hole is to be determined. Packers shall be fixed
both at the top and bottom of the test section such that their spacing
is exactly equal to the length of the test section. The test shall then be
conducted as specified in clause 7.6(a).

8.0 LABORATORY INVESTIGATION


8.1 Essential Requirements
a) All laboratory tests shall be conducted in an approved laboratory
using approved apparatus complying with the requirements and
specifications of Indian standards or other approved standards for
this class of work. It shall be checked that the apparatus are in good
working condition before starting the laboratory tests. Calibration of
all the instruments and their accessories shall be done carefully and
precisely.

b) Depending on the type of sub strata encountered, appropriate


laboratory tests shall be conducted on soil and rock samples
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 35 OF 50

collected in the field. Laboratory tests shall be scheduled and


performed by a qualified and experienced personnel who are
thoroughly conversant with the work. Tests indicated in the
schedule of items shall be performed on soil, rock and water samples
as per relevant IS codes. One copy of all the laboratory test data
records shall be submitted to the owner progressively every week.
Laboratory tests shall be carried out concurrently with field
investigation since initial laboratory test results could be useful in
planning the later part of field work. A schedule of laboratory tests
shall be established by the contractor and the same shall be
submitted and got approved by the engineer-in-charge before
starting of laboratory tests.

c) All samples whether undisturbed or disturbed shall be extracted,


prepared and examined by a competent personnel properly trained
and experienced in soil sampling, examination, testing and in using
the apparatus as per the specified standards.

d) Undisturbed soil samples retained in liners or seamless tube


samplers shall be taken out without causing any disturbance to the
samples using suitably designed extruder just prior to actual testing.
If the extruder is horizontal, proper support shall be provided to
prevent the sample from breaking. For screw type extruders the
pushing head shall be free from the screw shaft so that no torque is
applied to the soil sample in contact with the pushing head. For soft
clay samples, the sample tube shall be cut by means of a high speed
hacksaw to specified test length and placed over the mould before
pushing the sample into it with a suitable piston.

e) While extracting a sample from a liner or tube care shall be taken


to see that its direction of movement is the same as that during
sampling to avoid stress reversal.

f) On all undisturbed soil samples tested for bulk density, water


content, grain size distribution, liquid limit and plastic limit tests
shall also be performed.

g) On all rock samples tested for unconfined compression test, bulk


density and water content tests shall also be performed.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 36 OF 50

h) After completion of all tests, a summary of test results for each


soil and rock sample shall be presented in a proforma as enclosed in
Annexure-A & B respectively. Chemical test results on soil and
water samples shall be furnished in a tabular form separately.

8.2 Tests

Tests as indicated in this specification and as called for by the


engineer-in-charge shall be conducted. The tests shall include the
following.

a) Tests on Undisturbed and Disturbed Soil Samples


 - Visual and engineering classification

 - Sieve analysis and hydrometer analysis

 - Liquid, plastic and shrinkage limits


 - Specific gravity
 - Chemical analysis
 - Swell pressure and free swell index determination
 - Proctor compaction
 - California bearing ratio

b) Test on Undisturbed Soil Samples

- Bulk density and moisture content

- Relative density (for sand)

- Unconfined compression test

- Box shear test

- Triaxial shear tests (depending on the type of soil and


field conditions on undisturbed or remoulded samples)
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 37 OF 50

i)Unconsolidated undrained

ii) Consolidated undrained test with the measurement of


pore water pressure
iii)Consolidated drained
- One dimensional consolidation test

c) Test on Rock Samples

- Visual classification

- Water absorption, porosity and density

- Specific gravity

- Hardness

- Slake durability

- Unconfined compression test (both at saturated and at


in-situ water content)
- Point load strength index
- Deformability test (both on saturated and dry samples)
c) Chemical Analysis of Sub-soil and Ground Water

8.3 Salient Test Requirements

a) Remoulded soil specimen whenever desired shall be fully reworked


at field density and natural moisture content. For conducting CBR test
and triaxial test for dyke/road material the sample shall be remoulded
to 95% of standard proctor density.

b)Triaxial shear test shall be conducted on undisturbed soil samples


saturated by the application of backpressure. Only if the water table is
at sufficient depth such that chances of its rising to the base of the
footing are meagre or nil, the triaxial tests shall be performed on the
specimens at natural moisture content. Each test shall be carried out on
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 38 OF 50

a set of three test specimens from one sample at cell pressures equal to
100, 200 and 300kN/sqm or as required depending on the soil
conditions.

c) Effective stress triaxial shear test shall be consolidated undrained


with pore water pressure measurement. The test shall be conducted at
cell pressures of 100, 200 and 300kN/sqm ensuring complete
consoIidation at each stage.

d) Direct shear test shall be conducted on undisturbed soil samples.


The three normal vertical stresses for each test shall be 100, 200 and
300 kN/sqm or as required depending on the soil conditions.

e) Consolidation test shall have loading stages of 10, 25, 50, 75, 100,
200, 400 and 800 kN/sqm. Rebound curve shall be recorded for all the
samples by unloading the specimen at the in-situ stress of the
specimen. Additional rebound curves shall also be recorded whenever
desired by the engineer-in-charge.

f) Chemical analysis of sub-soil shall include determination of pH


value, carbonate, sulphate (both S03 and S04), chloride and nitrate
contents, organic matter, salinity and any other chemicals harmful to
the foundation material. The contents in soil shall be indicated as
percentage.

g) Chemical analysis of sub-soil water sample shall include the


determination of the properties such as colour, odour, turbidity, pH
value and chemical contents such as carbonate, sulphate (both S03 and
S04), chloride, nitrate, organic matter and any other chemicals harmful
to the foundation material. The contents such as sulphate etc shall be
indicated as ppm by weight.

h) The laboratory CBR test shall be performed on undisturbed or on


remoulded sample as per the drawing or as directed by the engineer-
in-charge in soaked and unsoaked conditions.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 39 OF 50

9.0 REPORT

9.1 General

a) On completion of all the field and laboratory works, the contractor


shall submit a draft report containing geological information of the
region, procedure adopted for investigation, field observations,
summarised test data, conclusion and recommendations. The report
shall include detailed borelogs, sub-soil sections, field test results,
laboratory observations and test results in both tabular as well as
graphical forms, practical and theoretical considerations for the
interpretation of test results, the supporting calculations for the
conclusions drawn etc. Initially, the contractor shall submit three
copies of the report in draft form for the owner's review.

b) After review of the draft report, the employer’s comments will be


intimated to the contractor. The contractor shall incorporate the
comments and after getting the amended draft report approved, five
copies of the detailed final report shall be submitted alongwith one set
of reproducible of the graphs, tables etc. Any expenditure on account
of redrafting, finalising the report etc shall be deemed to have been
included in the quoted rates.

c) The detailed final report based on field observations, in-situ and


laboratory tests shall encompass theoretical as well as practical
considerations for foundation of different type of structures envisaged
in the area under investigation. The contractor shall acquaint himself
about the type of structures, foundation loads and other information
required from the engineer-in-charge.

9.2 Data to be Furnished

The report shall also include but not be limited to the following.

a) A plot plan showing the location and reduced levels of all field tests
e.g. bore holes, trial pits, plate load tests etc properly drawn to scale
and dimensioned with reference to the established grid lines.

b) Geological information of the area such as geomorphology,


geological structure, lithology, stratigraphy and tectonic faults,
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 40 OF 50

seismicity of the region and site, core recovery and rock quality
designation etc.

c) Past observations and historical data if available for the area or for
other areas with similar soil profile for similar structures in the
surrounding areas.

d) A true cross section of all individual boreholes and trial pits with
reduced levels and co-ordinates showing the classification and
thickness of individual stratum, position of ground water table,
various in-situ tests conducted and samples collected at different
depths and the rock stratum if met with.

e) A set of longitudinal and transverse soil/rock profiles connecting


various bore holes in order to give a clear picture of the variation of
the subsoil strata as per IS: 6065.

f) Water level contours and rock level contours

g) Plot of standard penetration test ‘N’ values (both uncorrected and


corrected) with depth for identified areas.

h) Results of all field tests in tabular as well as in graphical forms.

i) Results of all laboratory tests summarised (i) for each sample as


well as (ii) a consolidated table giving the layer-wise soil and rock
properties . All the relevant charts, tables, graphs, figures, supporting
calculations, conclusions and photographs of representative rock
cores and trial pits shall be furnished.

j) For all triaxial shear tests, stress vs strain diagrams as well as


Mohr's circle envelopes shall be furnished. If back pressure is
applied for saturation, the magnitude of the same shall be indicated.
The value of modulus of elasticity ‘E’ shall be furnished for all tests
along with relevant calculations.

k) For all consolidation tests the following curves shall be furnished.

e vs log P
e vs P and
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 41 OF 50

Compression vs log t or square root of t (depending upon shape of the


plot for proper determination of coefficient of consolidation)

The point showing initial condition (eo, Po) of the soil shall be
marked on the curves.

l) Values of compression index, coefficient of volume


compressibility etc shall be furnished. The procedure adopted for
calculating the compression index from the field curve and settlement
of soil strata shall be clearly specified. The time required for 50%
and 90% primary consolidation along with secondary settlement if
significant shall also be calculated.

m) For pressuremeter tests, the following shall be furnished.

Calibration record including description of membrane and sheath on


probes, dimensions of thick walled cylinder, length of flexible tubing,
calibration curves and temperature etc.

Drilling record including borehole number, method of making


borehole, log with soil type and condition, depth of water table in the
borehole, weather and temperature etc.

Test record including type of test, date and time, depth of centre point
of probe, volume readings at 30 and 60 second elapsed time and
corresponding pressure readings and notes on any deviation from
standard test procedure etc.

Field pressuremeter, creep and air calibration curves indicating Po, Pf


and Pl. Corrected pressuremeter and creep curves indicating Po, Pf,
Pl along with calculation for the corrections.

n) Values of cohesion, angle of internal friction, pressuremeter


modulus, shear modulus and co-efficient of sub-grade reaction along
with sample calculations. Calculation for allowable bearing pressures
and corresponding total settlements for shallow foundations and load
carrying capacity calculation of piles in various modes etc.

o) Analysis and discussion of test results.


TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 42 OF 50

9.3 Recommendations

Recommendations shall be given areawise duly considering the


type of soil/rock, structure, foundation type and ground water table
etc in the area. The recommendations shall include but not be
limited to the following.

a) Type of foundation to be adopted for various structures duly


considering the sub strata characteristics, water table, total
settlement permissible for the structures and equipments, minimum
depth and width of foundation etc.

b) For shallow foundations the following shall be indicated with


comprehensive supporting calculations.

i) Net safe bearing pressure for isolated square/rectangular footings


and continuous strip footings of sizes 1, 2, 3, 4 & 5m at different
founding depths of 1, 2, 3, 4 & 5m below ground level considering
both shear failure and settlement criteria giving reasons for the type
of shear failure adopted in the calculation.

ii) Net safe bearing pressure for raft foundation of widths greater
than 6m at 2 , 3, 4 & 5m below ground level considering both shear
failure and settlement criteria.

iii) Modulus of sub-grade reaction and modulus of elasticity from


plate load test results along with time-settlement curves and load-
settlement curves in both natural and log-log graph.

c) If piling is envisaged the following shall be furnished with


comprehensive supporting calculations.

i) Type of pile and reasons for recommending the same duly


considering the sub strata characteristics.

ii) Suitable founding strata for the pile.

iii) Estimated length of pile for 500 kN (400mm dia.), 750kN


(450mm dia.), 1000kN (500mm dia.) and 4500kN (1070mm dia.)
capacities. End bearing and frictional resistance shall be indicated
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 43 OF 50

separately. Safe lateral and tensile load carrying capacities of pile


with supporting calculations.

iv) Magnitude of negative skin friction if any.

d) Coefficient of permeability of various sub-soil and rock strata


based on in-situ permeability tests.

e) Cone resistance, frictional resistance, total resistance and


settlement analysis for different size of foundations.

f) Electrical resistivity of sub-soil based on electrical resistivity tests


including electrode spacing vs cumulative resistivity curves.

g) Dynamic soil properties such as dynamic shear modulus and


Poisson's ratio etc from cross-hole shear and seismic refraction tests
and coefficient of elastic uniform compression from cyclic plate
load tests.

h) Suitability of the soil for construction of roads and embankments,


their stable slopes for shallow and deep excavations, active and
passive earth pressures, earth pressure at rest and modulus of
elasticity as a function of depths for the design of underground
structures etc.

i) Suitability of locally available soils at site for filling and back


filling purposes.

j) If expansive soil is met with, then recommendation on removal or


retainment of the same under the structures/roads etc shall be given.
In the latter case, detailed specifications of any special treatment
required including specification for materials to be used,
construction method, equipments to be deployed etc shall be
furnished.

k) Protective measures based on chemical nature of soil and ground


water with due regard to the potential deleterious effects on
concrete, steel and other building materials etc. Remedial measures
for sulphate attack and acidity shall be dealt in detail.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 44 OF 50

l) Susceptibility of sub soil strata to liquefaction in the event of


earthquake. If so, recommendation for remedial measures.

m) Identification of any other potential geotechnical problems &


their remedial measures.

n) Description of measures required for erosion control.

o) Identification of corrective measures required for the


improvement of sub surface conditions such as removal of poor sub
soil/material and in-situ densification etc. If ground improvement is
recommended then its detailed specification, specification for the
materials to be used, construction method, equipments to be
deployed etc shall be furnished.

10.0 RATES & MEASUREMENTS

10.1 RATES

a) The item of work in the schedule of quantities describes the work


very briefly. The various items of the schedule of quantities shall be
read in conjunction with the corresponding sections in the technical
specification including amendments and additions if any. For each
item in the schedule of quantities, the bidder’s rates shall include all
the activities covered in the description of the items as well as for
all necessary operations in details described in the technical
specification.

b) No claims shall be entertained if the details shown on the


released for construction drawings differ in any way (e.g. location
and depth of tests, number of tests etc) from those shown on the
tender drawings.

c) The unit rates quoted shall include minor details which are
obviously and fairly intended and which may not have been
included in these documents but are essential for the satisfactory
completion of the work.

d) The bidders quoted rates shall be inclusive of providing all


equipments, men, materials, skilled and unskilled labours, making
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 45 OF 50

observations, establishing the ground level and coordinates at


location of each bore hole, test pit etc by carrying levels from one
established bench mark and distances from one set of grid lines
furnished by the engineer-in-charge. Also no extra payments shall
be made for conducting the standard penetration tests, collection,
packing and transportation of all the samples and cores, recording of
all results and submitting them in approved formats etc.

e) The quoted rates for trial pits/plate load tests/ cyclic plate load
tests shall be inclusive of dewatering and backfilling etc.

f) The quoted rates for drilling in rock shall satisfy the requirements
as furnished in specification.

g) The rates quoted for conducting pump out test shall be inclusive
of boring a well of 400mm diameter, providing and installation of
perforated GI/MS pipes and observation pipes etc .

h)The rates quoted for conducting cross hole shear test shall be
inclusive of necessary boring, providing PVC pipes, grouting, geo-
phones, backfilling the holes after completion of testing etc.

i)The rates quoted for laboratory tests shall include preparation of


samples, performing tests, recording, analysis and submission of
data etc.

j) The bidder shall submit a scheme showing the arrangement and


equipment proposed to be used for conducting the site work along
with rates. However the minimum number of staff and equipments
to be deployed/mobilised for site works shall be as per Annexure-
C & D respectively.

10.2 MEASUREMENTS

a) All measurements shall be in SI Units.

b) Length shall be measured in metres (m) correct to two places of


decimals. Areas shall be worked out in square meters(Sqm) and
volume in cubic meters(Cum) rounded off to two decimals.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 46 OF 50

c) Certain tests have to be conducted in the bore holes and trial pits
etc. Such bore holes and trails pits etc shall be measured once only
and not again just because the tests are conducted therein.

d) The depth of penetration due to SPT at the bottom of bore hole


shall not be considered for the measurement of bore hole depth.

e) Pits shall be measured in Cum.

f) Coring in rock with diamond bit shall be measured in


length(metre) correct to two places of decimal for the actual cored
length satisfying the criteria of specification.
TECHNICAL SPECIFICATION FOR GEOTECHNICAL INVESTIGATION OF SPEC. NO. PE-TS-K45-602-C002
2X660 MW MAITREE SUPER THERMAL POWER PROJECT AT RAMPAL, VOLUME II
SECTION D
DISTRICT- BAGERHAT, BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 47 OF 50
ANNEXURE - A SUMMARY OF LABORATORY TEST RESULTS ON SOIL SAMPLES
DENSITY PARTICLE ATTERBERG'S LIMITS SOIL STRENGTH CONSOLIDATION SWELL COMPACTION
(kN/Cum) SIZE (%) TEST TEST TEST TEST
BULK DRY
BORE HOLE/ TRIAL PIT

WATER CONTENT (%)

PERMEABILITY(m/hr)
IS CLASSIFICATION

RELATIVE DENSITY
SPECIFIC GRAVITY
TYPE OF SAMPLE

DESCRIPTION
DEPTH (m)

REMARKS
GRAVEL
SAND

CLAY

TYPE

OMC
MDD
SILT

CBR
S.Pr
NO.

FSI
Cc

Cv
mv
Pc
eo
LL PL PI SL


C

p
For type of sample For others tests p Pressure range (kN/Sq.m)
mv Coefficient of volume
DS Disturbed soil sample LL Liquid Limit (%) compressibility (Sq.m/kN)
UDS Undisturbed soil sample PL Plastic Limit (%) Cv Coefficient of consolidation
RMS Remoulded soil sample PI Plasticity Index (%) (Sq.m/hr)
WS Water sample SL Shrinkage limit (%) MDD Maximum Dry Density (kN/Cum)
C Cohesion (kN/Sq.m) OMC Optimum moisture content (%)
For strength test  Angle of internal friction (degrees) CBR California Bearing Ratio (%)
UCC Unconfined compression test S.Pr Swelling pressure (kN/Sq.m)
VST Vane shear test FSI Free swell index (%)
Tuu Unconsolidated undrained triaxial test eo Initial Void ratio
Tcu Consolidated Undrained Pc Preconsolidation pressure (kN/Sq.m)
Triaxial test with pore pressure Cc Compression index
Tcd Consolidated drained triaxial test
( Note: Replace T by D for Direct Shear test)
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 48 OF 50

ANNEXURE-B

SUMMARY OF LABORATORY TEST RESULTS


ON ROCK CORE SAMPLES

BORE HOLE NO.

DEPTH

CORE PIECE NO.

MOISTURE CONTENT

SPECIFIC GRAVITY

HARDNESS

POROSITY

DRY DENSITY

SLAKE DURABILITY

POINT LOAD
STRENGTH INDEX
DEFORMABILITY
(DRY /SATURATED)
UNCONFINED
COMPRESSIVE
STRENGTH
( INSITU/SATURATED)
CORE DESCRIPTION

REMARKS
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 49 OF 50

ANNEXURE-C

MINIMUM STAFF TO BE DEPLOYED

S.No. Description No. of persons

1. Geotechnical Engineer

2 Engineering Geologist

3. Supervisor

4. Qualified Surveyor

5. Rig Operators

6. Mechanic
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 50 OF 50

ANNEXURE-D

LIST OF EQUIPMENTS TO BE MOBILISED TO SITE (MINIMUM)

S.No. Description Quantity

1 Shell and auger boring set

2. Rotary drilling rig


(Hydraulic feed)

3. Dynamic cone penetration test


equipment

4. Plate load test set up

5. Field permeability test set up

6. Cross hole shear wave test set up

7. Electrical resistivity test set up

8. Static cone penetration test equipment

9. Vane shear test equipment

10. Pressure meter test set up

11. Seismic refraction test set up

Note:
Additional equipments shall be mobilized if required as per the directions of the
engineer-in-charge to match the work schedule.

You might also like