Rampal Jetty-Geotechnical Investigation Spec-BHEL
Rampal Jetty-Geotechnical Investigation Spec-BHEL
PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 1 OF 50
TECHNICAL SPECIFICATION
FOR
GEOTECHNICAL INVESTIGATION
1.0 GENERAL
2.0 SCOPE
2.2 The contractor shall make his own arrangements for locating the co-
ordinates and position of bore holes, trial pits and other field tests as
per the drawings/sketches supplied to him and for determining the
reduced levels at these locations with respect to a single bench mark
indicated by the engineer-in-charge. Two established reference lines
will be indicated to him. The contractor has to provide at the site all
the required survey instruments to the satisfaction of the engineer-in-
charge so that the work can be carried out accurately according to the
specification and drawings.
2.3 All the field data shall be recorded in the proforma recommended in
Indian Standard Codes and the field records shall be counter signed
by the engineer-in-charge. The contractor shall submit two copies of
the field borelogs to the engineer-in-charge soon after the completion
of each bore hole. All the investigations are to be carried out by the
contractor as per the priority requirements of the engineer-in-charge.
2.6 All the laboratory test data shall be recorded in the proforma
recommended in the Indian Standard Codes and a copy of these shall
be sent to the engineer-in-charge every week during the progress of
laboratory testing. Whenever desired during the progress of work the
owner/engineer-in-charge may be present at the laboratory where the
contractor is arranging for execution of the laboratory tests.
3.2 The bidder must visit the site prior to submitting his quotations to
acquaint himself fully with the nature, type, scope of work and
involvement therein. The rates quoted shall remain firm during the
entire period of execution till completion of the work and any
additional claim for lack of knowledge shall not be entertained.
4.1 In areas which have already been developed, the contractor shall take
advantage of existing local knowledge, record of trial pits, bore holes
etc in the vicinity and the type of foundations adopted and behaviour
of existing structures particularly those of similar nature to the ones
proposed for this project.
4.2 The contractor shall make use of information gathered from quarries,
unlined wells, cuttings from nearby areas etc. The general
topography of the near by areas will often give some indication about
the variation of the soil conditions which are likely to exist.
4.3 The contractor shall gather data regarding the removal of overburden
by excavation, erosion or land slides in the areas which may give an
idea of the amount of reconsolidation that the soil strata has
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 4 OF 50
4.4 The water level in streams and water courses if any in the
neighbourhood shall be noted. Reliable information regarding ground
water level shall also be gathered from water level in the near by
wells.
4.5 The contractor shall make enquiries and verify regarding earlier use
of the site which can have important bearing on its suitability for the
proposed structures. This is important particularly in areas where
there have been underground works e.g. worked out ballast pits,
quarries, old brick fields, mines, mineral workings etc. The
possibility of damage to the structures, sewers, conduits and drainage
system by subsidence shall also be investigated.
4.6 It is essential that the equipments/instruments are properly calibrated
at the commencement of the work so that they represent true values
and submit the test reports to the engineer-in-charge. If the engineer-
in-charge so desires, the contractor shall arrange for having the
instruments tested in presence of the engineer at an approved
laboratory at the contractor’s cost and the test reports shall be
submitted to the engineer-in-charge.
4.7 When blasting with explosives is involved, agency/contractor shall
arrange statutory clearances and also the portable magazine for
storing/carrying the explosives.
5.2 In case of conflict between this specification and those (IS codes and
standards etc) referred to herein the former shall prevail.
5.3 All work shall be carried out as per the specification and the
following standards and codes.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 5 OF 50
IS: 2132 Code of practice for thin walled tube sampling of soils
IS: 2470 Code of practice for design and construction of septic tanks
Part-I
IS: 4078 Code of practice for indexing and storage of drill cores
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 6 OF 50
IS: 4434 Code of practice for in-situ vane shear test for soils
IS: 5529 Code of practice for in-situ permeability test - Test in bed
Part-II rock
IS: 6926 Code of practice for diamond core drilling for site
investigation of river valley projects
IS: 10108 Code of practice for sampling by thin wall sampler with
stationary piston
6.1 Boring
c) Casing pipe shall be used in the borehole to support its sides when
side fall is suspected to occur inside the borehole. When casing pipe
is used, it shall be ensured that its bottom end is at all times 15 cm
above the bottom of the bore hole. In case of cohesionless soils the
advancement of the casing pipe shall be such that it does not disturb
the soil to be tested or sampled. The casing shall be advanced by
slowly turning the casing pipe and not by driving.
e) The bore hole shall be cleaned using suitable tools up to the depth
of testing or sampling ensuring that there is minimum disturbance of
soil at the bottom of the bore hole. The process of jetting through an
open tube sampler shall not be permitted. In cohesive soils, the
borehole may be cleaned using a bailer with a flap valve. Gentle
circulation of drilling fluid shall be done when rotary mud circulation
boring is adopted.
Shell and Auger boring can be used in all types of soil free from
boulders. For cohesionless soil below ground water table, the water
level in the bore hole shall always be maintained at or above the
ground water level. The use of chisel bit shall be permitted in hard
strata with SPT-N value greater than 100. Chisel bits may also be
used to extend the borehole through local obstruction such as old
construction, boulders, rocky formations etc. All other requirements
in clause 6.1.2 shall apply for this type of boring also.
This method can be adopted in soil with gravel and boulders when the
boring has to be done at a faster rate. This method consists of
breaking of the strata by repeated blows from a chisel or drilling bit
and bailing out the debris at intervals by adding water into the bore
hole. This method is not suitable for careful and very reliable
sampling operation because of the disturbance caused during boring.
This method shall not be adopted unless otherwise specified or
permitted by the engineer-in-charge.
This method can be used in all types of soil below water table. In this
method boring shall be done by rotating the bit fixed at the bottom of
the drill rod. Proper care shall be taken to keep a firm contact
between the bit and the bottom of the borehole. Bentonite or mud
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 11 OF 50
This test shall be conducted in all types of soil deposits met within
the bore hole to find the variation in the soil stratification by
correlating with the number of blows required for unit penetration of
a standard penetrometer. This test shall be conducted at 3m intervals,
at every change of strata, at depths wherever undisturbed soil samples
could not be collected and as per the directions of the engineer-in-
charge. The starting depth of performing SPT shall be either 1m or
2.5m depth below ground level. This depth shall be staggered in
alternate boreholes. The depth interval between the top level of
standard penetration test and to that of (next) undisturbed sampling
shall not be less than 1m. The specification for equipments and other
accessories, procedure for conducting the test, presentation of test
results and collection of disturbed soil samples etc shall conform to
IS: 2131.
This test shall be carried out by driving a standard split spoon sampler
in the borehole by means of a 650 N hammer having a free fall of
0.75m. The sampler shall be driven using the hammer for 450 mm
penetration. While driving, the number of blows for every 150 mm
penetration and the penetration for every 50 blows shall be recorded.
The number of blows for the last 300 mm drive shall be reported as
‘N’ value. This test shall be discontinued when the blow count is
equal to 100 and the penetration shall be recorded. Refusal shall be
considered to be met with when the blow count is equal to 100. At
the location where the test is discontinued, the penetration and the
corresponding number of blows shall be reported. Sufficient quantity
of disturbed soil samples shall be collected from the split spoon
sampler for identification and laboratory testing. The samples shall
be visually classified & recorded at the site and shall be properly
preserved and labelled for future identification & testing.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 12 OF 50
6.3 Sampling
6.3.1 General
c) All the samples shall be identified with date, bore hole or trial pit
number, depth of sampling etc. It is also essential to mark an arrow
pointing towards the top surface of the undisturbed sample as the soil
was in-situ. Care shall be taken to keep the undisturbed soil samples
and box samples vertically with the arrow directing upwards. The
tube samples shall be properly trimmed at both ends and suitably
sealed with molten paraffin wax at both ends immediately after
extracting the samples from the bore hole/trial pit and suitably capped
on both sides.
Undisturbed samples in very loose saturated sandy & silty soils and
very soft clays shall be obtained by using a piston sampler consisting
of a sampling cylinder and piston system. In soft clays and silty clays
with water standing in the casing pipe, piston sampler shall be used to
collect undisturbed samples. During this method of sampling expert
supervision is called for.
a) The sampler shall be pushed into the soil and driving of sampler
shall be resorted to only when it cannot be pushed into the soil. This
shall be done only with the permission of the engineer-in-charge and
all the details about the same shall be recorded in the bore logs.
6.4.l One of the following methods shall be adopted for determining the
ground water table in bore holes as per IS:6935 and as per the
instructions of the engineer-in-charge.
6.4.2 In case any variation in the ground water level is observed in any
specific boreholes then the water level in these bore holes shall be
recorded daily during the course of field investigation. Levels in
nearby wells, streams etc if any shall also be noted whenever these
readings are taken. If so called for, observation wells shall be drilled
for the purpose of long term studies on the fluctuation in ground
water levels and pressure. Either stand pipe or piezometer shall be
installed at the specified depths in the selected previously drilled bore
holes or specially drilled bore holes for this purpose as per the
specification and instructions of the engineer-in-charge. Daily water
level readings shall be recorded immediately following the
installation upto the time of leaving the site. At the end of field work,
these installations shall be handed over in satisfactory working
condition to the engineer-in-charge without disturbing their position
so that the owner can continue further observations.
6.4.3 Stand pipes and piezometers shall consist of 19mm internal diameter
rigid unplasticised (UPVC) tubing. All the joints in the tubing shall
be made of coupling sleeves. The top of UPVC tubing shall be
enclosed in a 75mm diameter galvanised steel pipe of 1.5m length
having a galvanised steel screw cap with well greased threads and the
caps shall be tightened such that it would be impossible to loosen by
hand. The lower end of the pipe shall have four legs of 6mm thick
and 100mm long and welded to have projection of 25mm. The pipe
shall be sealed into the ground with cement grout so that it does not
rotate. The top end of the pipe shall project about 300mm above
ground level unless otherwise specified by the engineer-in-charge.
The perforated tubing for the porous element shall be surrounded by a
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 17 OF 50
a) Stand pipe
Stand pipes shall be installed to measure the water level in soils with
high permeability such as sand and gravel. The stand pipe shall
consist of a perforated tubing attached to the bottom of the UPVC
tubing. The perforated tube shall be 150mm long having perforations
of diameter not greater than 1mm.
b) Piezometers
b) The sampling apparatus shall be such that the water at the desired
depth can be collected directly without any disturbance and any
change in concentration of constituents like dissolved gases etc.
Undue agitation shall be avoided. An ordinary suction pump with its
suction end inserted upto the required depth in the borehole shall be
used for this purpose.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 18 OF 50
6.5.2 Pump-in-Test
Only clear water shall be used for conducting the test. Before
conducting the test, the borehole shall be cleaned as specified in
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 19 OF 50
clause 6.1.1 (e). Water shall be allowed to percolate through the test
section for sufficient period of time to saturate the soil before starting
the observation.
This method shall be adopted for soils of low permeability and which
can stand without casing. The test section shall be sealed at the
bottom of the borehole and a packer at the top of the test section. If
the test has to be conducted at an intermediate section of a pre-bored
hole then double packers shall be used. Access to the test section
through the packer shall be by means of a pipe which shall extend
above the ground level. Water shall be filled into the pipe upto the
level marked just below the top of the pipe and water be allowed to
drain into the test section. The water level in the pipe shall be
recorded at regular intervals as mentioned in IS: 5529, Part-1,
Appendix-B. The test shall be repeated till constant records of water
level are achieved.
water due to percolation into the soil shall be estimated by the soil
absorption capacity.
a) Chunk Samples
wooden box to indicate the top surface of the sample along with the
location, date and depth of sampling.
b) Tube Samples
6.6.4 In case it is not possible to collect undisturbed samples in the pit, in-
situ density of soil shall be determined by sand replacement method.
The specification, equipments, accessories etc required for the test
and the procedure of testing shall be in accordance with IS: 2720,
Part-XXVIII. No separate payment shall be made for this test.
6.6.5 After the completion of the test, sampling and visual examination,
the pit shall be suitably backfilled as directed by the engineer-in-
charge. Unless otherwise specified excavated soil shall be used for
this purpose.
6.10.1 Plate load test shall be conducted to determine the bearing capacity
and load/settlement characteristics of soil at shallow depth by
loading a plane and levelled steel plate kept at the desired depth and
measuring the settlement under different loads until a desired
settlement takes place or failure occurs. The specification for
equipment and accessories required for conducting the test, the test
procedure, field observations and reporting of results etc shall
conform to IS: 1888. The location and depth of the test shall be as
given in the drawing or as indicated by the engineer-in-charge.
Undisturbed tube samples as specified in clause 6.6.3 (b) shall be
collected at 1m and 2.5m depths from the ground level for carrying
out laboratory tests.
6.10.2 The size of pit shall not be less than five times the plate size and the
depth shall be as specified. All provisions regarding excavation and
visual examination of pit under clause 6.6.1 and 6.6.2 shall apply
here also.
6.10.3 If the ground water table is at a depth higher than the specified test
depth, the ground water table shall be lowered and maintained at the
test depth for the entire duration of the test. Dewatering shall be at
the cost of the contractor.
6.10.5 A seating load of 7kN/sqm shall be applied and after the dial gauge
readings are stabilized, the load shall be released and the initial
readings of the dial gauges be recorded after they indicate constant
reading. The load shall be increased in stages. These stages shall be
20, 40, 70, 100, 150, 200, 250, 300, 400, 500, 600 and 800kN per
sqm or as directed by the engineer-in-charge. Under each loading
stage, record of ‘time vs settlement’ shall be kept as specified in
IS:1888.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 25 OF 50
6.10.7 Other than cohesive soils, each stage loading shall be maintained for
a minimum duration of one hour or till the settlement rate reduces to
0.02mm/minute whichever is later. No extrapolation of settlement
rate from periods less than one hour shall be permitted. The final
loading shall be maintained for 24 hours. During unloading, reading
of dial gauge shall be recorded for each stage of unloading.
6.10.8 Loading shall be carried out in stages as specified above till one of
the following conditions occur.
a) Failure of soil under the plate i.e. the settlement of the plate at
constant load becomes progressive and reaches a value of 40 mm or
more.
6.10.9 Backfilling of the pit shall be carried out as per the directions of the
engineer-in-charge. Unless otherwise specified the excavated soil
shall be used for this purpose.
This test shall be carried out to determine the dynamic soil properties
required for the analysis of foundation subjected to dynamic loads.
This test shall be conducted on similar lines as the ordinary plate load
test with an addition that unloading shall also be done before each
stage of loading. Test set up, load increment and maximum load
intensity etc shall be as per clause 6.10.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 26 OF 50
6.11.1 After each stage of loading, the load shall be removed in a minimum
of two stages and as directed by the engineer-in-charge. After each
stage of reduction of load, dial gauge readings and settlements shall
be taken for atleast one hour until the readings stabilize. Thereafter
the next loading stage shall commence. Recording and analysis of test
data shall be as per IS: 5249.
This test shall be carried out to obtain the properties of soil required
for the design of roads. The equipments and accessories required for
carrying out the test, test procedure, recording of observations and
presentation of results shall conform to IS: 2720 part XXXI. The test
locations and depth shall be as specified in the drawings or as
directed by the engineer-in-charge.
6.14.1 This test shall be carried out to establish the rock and soil profiles of
varying density. The dynamic shear modulus of the soil shall also
be obtained from the results of this test. The specification for the
equipments and other accessories, procedure for carrying out the
test, recording and analysis of results and their presentation shall
conform to IS: 1892.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 27 OF 50
6.14. 2 This test shall be carried out by inducing shock waves into the soil
by striking a plate placed on the ground surface with a hammer. The
shock waves shall be picked up through geophones placed on the
ground surface at regular intervals in line with the plate along a
straight line. The time elapsed before the waves reach the
geophones shall be recorded to an accuracy of one millisecond or
better.
6.14.3 The distance between the shock point and the geophones shall be
increased to cover a wider area. Alternatively, multiple geophones
shall be used simultaneously using multiple channel seismograph to
record the arrival time and intensity of waves reaching the
geophones. The spacing of geophones shall be 5m. As the distance
between geophones and the shock producing point are increased,
the time lapse for the waves passing through different underlying
strata and reaching the geophone shall be recorded. The wave forms
shall be recorded for each test using multiple channel seismograph.
This test shall be generally carried out in accordance with IS: 13372
to establish the dynamic elastic properties of soil and rock. In this
test, the seismic waves are to be picked up in two adjacent receiver
boreholes. The spacing of boreholes shall be determined so as to
obtain good results. The boreholes shall be uncased in the portion
carrying the geophones. However it should be kept filled with water
or drilling mud in order to ensure perfect contact between the
borehole wall and the geophone. In case of cased hole preferably a
low velocity material such as a high impact PVC should be used for
casing and it is essential that it should be well grouted behind in
order to make an intimate contact with the soil. The charge shall be
installed within the depth as specified and the waves shall be picked
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 28 OF 50
6.16.1 This test shall be conducted in bore holes at desired depth to obtain
the in-situ stress-strain characteristics and strength parameters of
soil/rock layer by measuring the deformation of the probe at
different pressures of the volumemeter. The location and depth of the
test shall be as given in the drawing or as per the directions of the
engineer-in-charge.
6.16.4 Maximum value of pressure correction shall not be more than 50%
of limit pressure. The total volume loses in the system shall not
exceed 0.5% of the static probe volume per 100kPa. Volume
correction may he neglected in soil if it is less than 0.1% of probe
volume per 100 kPa.
probe. Hose pipe connecting the probe with the surface unit shall be
of flexible tubing of single or coaxial type. The equipment should be
able to reach a maximum pressure of 5000kPa for testing in soil and
8000kPa for testing in rock. The accuracy of measuring device shall
be such that a change of 0.2% of static probe volume or 0.1% of
probe radius is measurable as specified in IS:1892.
6.16.6 The probe shall be lowered down to the required depth as soon as
the boring is completed so as to limit the expansion of soil due to
release of stresses. The probe shall be held by a clamping device
ensuring that it is not located at the interface of two different
soil/rock layers.
6.16.8 The test shall be carried out in stages till one of the following
conditions occur.
6.16.9 On completion of the test, all results mentioned in clause 9.2 shall be
reported.
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 30 OF 50
7.1.1 Equipment
b) Drilling shall be carried out with Nx size diamond tipped drill bits
or impregnated diamond bits depending on the type of rock
encountered. Double tube swivel core barrel of Type B conforming
to IS: 6926 shall be used to ensure a good core recovery and to pick
up cores from all layers of rock. Suitable core catchers shall be used
to ensure continuous and good core recovery.
7.1.2 Procedure
7.1.3 Observations
b) Immediately after withdrawal from the core barrel, the cores shall
be placed in a tray and transferred into boxes specially prepared for
the purpose. The boxes shall be made from seasoned timber or any
other durable material and shall be indexed on top of the lid as per
IS:4078. The cores shall be numbered serially and arranged in the
boxes in a sequential order. The description of the core samples
shall be recorded as per IS: 4464. Where no core is recovered, it
shall be recorded as specified in the continuous record of core
recovery and RQD in the corelog as per IS:11315, Part-II.
The test shall be conducted as described under clause 6.10 for soil
subject to the following changes.
The test plate shall be of size 45cm x 45cm and at least 25mm thick.
The maximum load shall be 2500 kN/sqm to be applied in stages of
25, 50, 100,150,200, 300, 400, 600, 800, 1000, 1500, 2000 and 2500
kN per sqm. Under each load the time Vs settlement shall be
recorded and plotted.
This test shall be conducted as described under clause 6.16 for soil
subject to the following changes. The test shall be carried out till
one of the following condition occurs.
a) The volume of the probe is doubled
b) Ultimate failure of rock
c) Load intensity of 8000 kN/sqm is reached without failure.
This test shall be conducted as described under clause 6.15 for soil.
Permeability test shall be conducted in bed rock inside the bore hole
by pumping in water under pressure to determine the percolation
capacity of the rock strata. This test shall be conducted in uncased
and ungrouted sections of the drill hole. Clear and clean water shall
be used for the purpose of both drilling and testing. The
specification for the equipments and other accessories, test
procedure etc shall conform to IS: 5529, part-II. The length of the
test section shall be either 1.5m or 3m as per field conditions and as
per the directions of the engineer-in-charge. The level of water table
(if any) in the bore hole shall be recorded and the drill hole shall be
cleaned before the start of the test. Depending upon the depth of the
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 34 OF 50
This method shall be adopted when the bottom elevation of the test
section is the same as the bottom of the drill hole. The packer shall
be fixed at the top level of test section such that only the test section
lies below the packer. Water shall then be pumped through a pipe
into the test section under a required pressure and maintaining it till a
constant quantity of water intake is observed. The amount of water
percolating through the hole shall be recorded at every 5 minute
interval. The test shall be repeated by increasing the pressure at
regular intervals upto a pressure limit as specified in IS: 5529, part-
II. The details and observations shall be recorded in a proforma as
recommended in IS: 5529, part-II, Appendix-B.
8.2 Tests
i)Unconsolidated undrained
- Visual classification
- Specific gravity
- Hardness
- Slake durability
a set of three test specimens from one sample at cell pressures equal to
100, 200 and 300kN/sqm or as required depending on the soil
conditions.
e) Consolidation test shall have loading stages of 10, 25, 50, 75, 100,
200, 400 and 800 kN/sqm. Rebound curve shall be recorded for all the
samples by unloading the specimen at the in-situ stress of the
specimen. Additional rebound curves shall also be recorded whenever
desired by the engineer-in-charge.
9.0 REPORT
9.1 General
The report shall also include but not be limited to the following.
a) A plot plan showing the location and reduced levels of all field tests
e.g. bore holes, trial pits, plate load tests etc properly drawn to scale
and dimensioned with reference to the established grid lines.
seismicity of the region and site, core recovery and rock quality
designation etc.
c) Past observations and historical data if available for the area or for
other areas with similar soil profile for similar structures in the
surrounding areas.
d) A true cross section of all individual boreholes and trial pits with
reduced levels and co-ordinates showing the classification and
thickness of individual stratum, position of ground water table,
various in-situ tests conducted and samples collected at different
depths and the rock stratum if met with.
e vs log P
e vs P and
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 41 OF 50
The point showing initial condition (eo, Po) of the soil shall be
marked on the curves.
Test record including type of test, date and time, depth of centre point
of probe, volume readings at 30 and 60 second elapsed time and
corresponding pressure readings and notes on any deviation from
standard test procedure etc.
9.3 Recommendations
ii) Net safe bearing pressure for raft foundation of widths greater
than 6m at 2 , 3, 4 & 5m below ground level considering both shear
failure and settlement criteria.
10.1 RATES
c) The unit rates quoted shall include minor details which are
obviously and fairly intended and which may not have been
included in these documents but are essential for the satisfactory
completion of the work.
e) The quoted rates for trial pits/plate load tests/ cyclic plate load
tests shall be inclusive of dewatering and backfilling etc.
f) The quoted rates for drilling in rock shall satisfy the requirements
as furnished in specification.
g) The rates quoted for conducting pump out test shall be inclusive
of boring a well of 400mm diameter, providing and installation of
perforated GI/MS pipes and observation pipes etc .
h)The rates quoted for conducting cross hole shear test shall be
inclusive of necessary boring, providing PVC pipes, grouting, geo-
phones, backfilling the holes after completion of testing etc.
10.2 MEASUREMENTS
c) Certain tests have to be conducted in the bore holes and trial pits
etc. Such bore holes and trails pits etc shall be measured once only
and not again just because the tests are conducted therein.
PERMEABILITY(m/hr)
IS CLASSIFICATION
RELATIVE DENSITY
SPECIFIC GRAVITY
TYPE OF SAMPLE
DESCRIPTION
DEPTH (m)
REMARKS
GRAVEL
SAND
CLAY
TYPE
OMC
MDD
SILT
CBR
S.Pr
NO.
FSI
Cc
Cv
mv
Pc
eo
LL PL PI SL
C
p
For type of sample For others tests p Pressure range (kN/Sq.m)
mv Coefficient of volume
DS Disturbed soil sample LL Liquid Limit (%) compressibility (Sq.m/kN)
UDS Undisturbed soil sample PL Plastic Limit (%) Cv Coefficient of consolidation
RMS Remoulded soil sample PI Plasticity Index (%) (Sq.m/hr)
WS Water sample SL Shrinkage limit (%) MDD Maximum Dry Density (kN/Cum)
C Cohesion (kN/Sq.m) OMC Optimum moisture content (%)
For strength test Angle of internal friction (degrees) CBR California Bearing Ratio (%)
UCC Unconfined compression test S.Pr Swelling pressure (kN/Sq.m)
VST Vane shear test FSI Free swell index (%)
Tuu Unconsolidated undrained triaxial test eo Initial Void ratio
Tcu Consolidated Undrained Pc Preconsolidation pressure (kN/Sq.m)
Triaxial test with pore pressure Cc Compression index
Tcd Consolidated drained triaxial test
( Note: Replace T by D for Direct Shear test)
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 48 OF 50
ANNEXURE-B
DEPTH
MOISTURE CONTENT
SPECIFIC GRAVITY
HARDNESS
POROSITY
DRY DENSITY
SLAKE DURABILITY
POINT LOAD
STRENGTH INDEX
DEFORMABILITY
(DRY /SATURATED)
UNCONFINED
COMPRESSIVE
STRENGTH
( INSITU/SATURATED)
CORE DESCRIPTION
REMARKS
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 49 OF 50
ANNEXURE-C
1. Geotechnical Engineer
2 Engineering Geologist
3. Supervisor
4. Qualified Surveyor
5. Rig Operators
6. Mechanic
TECHNICAL SPECIFICATION FOR SPEC. NO. PE-TS-K45-602-C002
GEOTECHNICAL INVESTIGATION OF 2X660 MW VOLUME II
MAITREE SUPER THERMAL POWER PROJECT
SECTION D
AT RAMPAL, DISTRICT- BAGERHAT,
BANGLADESH REV. NO. 0 DATE 08.01.2016
SHEET 50 OF 50
ANNEXURE-D
Note:
Additional equipments shall be mobilized if required as per the directions of the
engineer-in-charge to match the work schedule.