Contractor:
Zeng ZhiQiang DecorationEngineering Co.,LTD SITE DAILY REPORT Project: Rain Rock Apartment
Location: Phnom Penh
Date: 28th-Oct-2022
Equipment
Work Description & Location
Description Quan. Unit Remark
1 Toolbox meeting Laser leveling machine 5 pcs
2 Install mullion L17,L18,L19,L20,L21 Satety belt 8 pcs
3 transfer aluminum frame from Factory Scaffolding 2 set
4 Welding machine 5 pcs
5 Ladder 5 pcs
6 Fire extinguisher 5 pcs
7 Gondola 1 pcs
Tomorrow Activities Manpower on Site
1 Toolbox meeting Description Quan. Unit Remark
2 Install mullion L19,L20,L21,L22,L23 Manager 1 pax
3 Site Manager 1 pax
4 Team Leader 1 pax
5 Technician 10 pax
6 Total worker 8 pax
7 Morning No
Rainy
8 Afternoon No
Material Delivery
Name Quantity Unit Photo Remark
1 Aluminum Frame 317 pcs
2
3
4
5
6
7
Prepared & Checked by:
Name: Vantha Sany
Position: Site Manager
Date: 28th-Oct-2022