Location 3rd Ave.
Parking, 3rd Avenue, Taguig, 1203, Metro
Manila
Lot Area 5,545.42 square meters
Total Gross Building Area (sqm.) 4,798 square meters
Total Gross Floor Area (sqm.) 5,128 square meters
Sponsor / Owner The owner or the client provides and demands the spaces
required for the project. In addition, he/she provides the
budget that will be needed for starting the project.
Architect The architect is the project head which translates the
client's demands into construction drawings. He/she also
manages its construction from the start up until the end.
Engineers They specialized in the structural, mechanical and INTERNAL PROJECT COST DRIVERS
utilities aspect of the structure that is to be built and they
1. Fire Protection 19.64%
coordinate with the architect during planning and SCOPE FOR BUILD BY ADMINISTRATION
2. Air Conditioning 11.79%
construction phase.
A. Substructure ₱ 32,584,000.00 3. Interiors 30.16%
Contractor In-charge of implementing that building the construction C. Interiors ₱ 64,732,000.00 Total 61.59%
drawings created by the architect/s and engineer/s. D. Services ₱ 64,964,000.00
E. Equipment & Furnishings ₱ 16,385,000.00
Building Officials Government employees in-charge of inspecting the
F. Building Sitework ₱ 32,399,000.00
building in accordance with the law such as numerous Target Start Date for Off Site Work January 16, 2023
codes, etc. Target Start Date for On Site Work April 16, 2023
Total Direct Costs ₱ 211,064,000.00
Utility Companies Electrical, Water, Telco Companies in-charge of providing Target Turnover Date January 20, 2025
basic utility services. Indirect Costs
Z. General Requirements ₱ 20,459,000
Banks / Financial Institutions entrusted by the owner in releasing the funds Contingency ₱ 11,200,000
Institutions required for the project.
Scope can still be revised to achieve Value
Total Indirect Costs ₱ 31,659,000.00
Enhancements.
Disruptions These can be classified through unpredictable
Costs are tentative and might still be subject to
and unforeseen events SCOPE BY DIRECT PURCHASE
changes due to the ever-changing market prices.
Volatility New hasty decisions through change orders Project schedule estimation also considered tolerance
B. Shell ₱ 16,520,000.00
and changes in market pricing for materials for possible extension due to unforeseen events.
Complexity Disorganization, interconnection of multiple workflows GUARANTEED MAX PRICE Prepared by:
Ambiguity Lack of direction, misinterpretation of terms Target Cost for Administered Works ₱179,405,000.00
Builder's Fixed Fee ₱32,000,000.00
Diversity Involvement of multiple fields in a single project, Direct Purchase ₱16,520,000.00 Ar. Javin Alan F. Caluya, UAP
resulting in more factors to consider Total ₱227,925,000.00 Builder by Administration