RFP - Pkg-II & III Chhattisgarh (PBMC) Final Mode
RFP - Pkg-II & III Chhattisgarh (PBMC) Final Mode
For
February 2024
CONTENTS
2. The complete BID document can be viewed / downloaded from official portal of theNHAI
http://nhai.gov.in or the CPPP website https://etenders.gov.in from 01.02.2024 to
19.03.2024 (upto 15:00 Hrs. IST). Bidder must submit its Financial bid and Technical Bid at
NHAI http://nhai.gov.in or the CPPP website https://etenders.gov.in on or before Bid Due Date
i.e. 19.03.2024 (upto 15:00 hours IST). Bids received online shall be opened on 20.03.2024
(at 1 7 : 0 0 hours IST).
3. Bid through any other mode shall not be entertained. However, originals of Bid Security,
document fee, Power of Attorney and Joint Bidding Agreement etc. shall be submitted physically
by the L-1 Bidder before issuance of Letter of Acceptance (LOA) by the Authority. Please note
that the Authority reserves the right to accept or reject all or any of the BIDs without assigning
any reason whatsoever.
The information contained in this Request for Proposal document (the “RFP”) or
subsequently provided to Bidder(s), whether verbally or in documentary or any other
form by or on behalf of the Authority or any of its employees or advisors, is provided
to Bidder(s) on the terms and conditions set out in this RFP and such other terms
and conditions subject to which such information is provided.
This RFP is not an Agreement and is neither an offer nor invitation by the Authority
to the prospective Bidders or any other person. The purpose of this RFP is to provide
interested parties with information that may be useful to them in making their
financial offers (BIDs) pursuant to this RFP. This RFP includes statements, which
reflect various assumptions and assessments arrived at by the Authority in relation
to the Project. Such assumptions, assessments and statements do not purport to
contain all the information that each Bidder may require. This RFP may not be
appropriate for all persons, and it is not possible for the Authority, its employees or
advisors to consider the investment objectives, financial situation and particular
needs of each party who reads or uses this RFP. The assumptions, assessments,
statements and information contained in the Bidding Documents, may not be
complete, accurate, adequate or correct. Each Bidder should, therefore,
conduct its own investigations, inspections and analysis and should check the
accuracy, adequacy, correctness, reliability and completenessof the assumptions,
assessments, statements and information contained in this RFP and obtain
independent advice from appropriate sources.
Information provided in this RFP to the Bidder(s) is on a wide range of matters, some
of which may depend upon interpretation of law. The information given isnot
intended to be an exhaustive account of statutory requirements and should not be
regarded as a complete or authoritative statement of law. The Authority accepts no
responsibility for the accuracy or otherwise for any interpretation or opinion on law
expressed herein.
The Authority, its employees and advisors make no representation or warranty and
shall have no liability to any person, including any Applicant or Bidder under any
law, statute, rules or regulations or tort, principles of restitution or unjust
enrichment or otherwise for any loss, damages, cost or expense which may arise
from or be incurred or suffered on account of anything contained in this RFP or
otherwise, including the accuracy, adequacy, correctness, completeness or
reliability of the RFP and any assessment, assumption, statement or information
contained therein or deemed to form part of this RFP or arising in any way for
participation in this BID Stage.
The Authority also accepts no liability of any nature whether resulting from
negligence or otherwise howsoever caused arising from reliance of any Bidderupon
the statements contained in this RFP. The Authority may in its absolute discretion,
but without being under any obligation to do so, update, amend or supplement the
information, assessment or assumptions contained in this RFP.
The issue of this RFP does not imply that the Authority is bound to select a Bidder
or to appoint the Selected Bidder JV or Contractor, as the case may be, for the
4
Project and the Authority reserves the right to reject all or any of the Bidders or
BIDs without assigning any reason whatsoever.
The Bidder shall bear all its costs associated with or relating to thepreparation
and submission of its BID including but not limited to preparation, copying, postage,
delivery fees, expenses associated with any demonstrations or presentations which
may be required by the Authority or any other costs incurredin connection with or
relating to its BID. All such costs and expenses will remain with the Bidder and the
Authority shall not be liable in any manner whatsoever for the same or for any other
costs or other expenses incurred by a Bidder in preparation or submission of the BID,
regardless of the conduct or outcome of the Bidding Process.
SECTION – 2
TABLE OF CLAUSES
Clause A. General Clause
1. Scope of Bid 20. Deadline for Submission of Bids
21. Late Submission of Documents in Physical
2. Source of Funds Form
22. Modification and Withdrawal of Bids
3. Eligible Bidders E. Bid Opening, Clarification of bids and
Evaluation
4. Qualification of the Bidder 23. Bid Opening, Clarification of Bids
and Evaluation
5. One Bid per Bidder 24. Process to be Confidential
6. Cost of Bidding 25. Contacting the Employer
7. Site Visit 26. Examination of Bids and Determination
of Responsiveness
B. Bidding Documents 27. Deleted
8. Content of Bidding 28. Evaluation and Comparison of Financial
Documents Bids
9. Clarifications on Bidding F. Award of Contract
Documents
10. Amendment of Bidding 29. Award Criteria
Documents
C. Preparation of bids 30. Employer’s Right to Accept any Bid and to
Reject any or all Bids
11. Language of Bid 31. Notification of Award and Signing of
Agreement
12. Documents Comprising the 32. Performance Security
Bid
13. Bid Prices 33. Advances
14. Currencies of Bid and G. Corrupt or Fraudulent Practices
Payment
15. Bid Validity 34. Corrupt or Fraudulent Practices
16. Earnest Mone y /Bid H. Labour Laws and Fundamental breach
Security / Forfeiture/
Debarment
17. Alternative Proposals by 35. Labour Laws and Regulations
Bidders
18. Format and Signing of Bid 36. Fundamental Breach and other
Obligations
D. Submission of bids
19. Marking of Bids Appendix to ITB
A. GENERAL
1. Scope of bid
1.1 The National Highways Authority of India invites Bids for Performance-
Based Maintenance of Roads through e-tendering from experienced
firms/organizations for operation and maintenance works and activities for the
following sections of the National Highways as described in these documents and
referred to as “the Works”. The name and identification number of the Works is as
defined in the Appendix to ITB.
1.2 The successful Bidder will be expected to complete the Works by the
intended Completion Date specified in the Contract Data.
1.3 Throughout these Bidding Documents, the terms “bid” and “tender” and
their derivatives (bidder/tenderer, bid/tender, bidding/tendering, etc.) are
synonymous.
2. Source of Funds
2.1 The expenditure under this contract will be met by [Name of
Organization].
3. Eligible bidders
3.1 This Invitation for Bids is open to all bidders meeting the qualification
requirements prescribed in Clause 4 of ITB.
3.2 In case the Bidder is a Joint Venture, it shall comply with the following
additional requirements:
(a) Number of members in a Joint Venture shall not exceed 2 (two) for
projects of cumulative length less than or equal to 80 km and shall not exceed 3
(Three) for projects of cumulative length more than 80 km;
(b) Subject to the provisions of clause (a) above, the Bid should contain the
information required for each Member of the Joint Venture;
(c) Members of the Joint Venture shall nominate one member as the lead
member (the “Lead Member”). Lead Member shall meet at least 60% requirement
of Bid Capacity, Technical and Financial Capacity. The nomination(s) shall be
supported by a Power of Attorney, as per the format in RFP, signed by all the
other Members of the Joint Venture. Other Member(s) shall meet at least 20%
requirement of Bid Capacity, Technical and Financial Capacity requirement and
the JV as a whole shall cumulatively/collectively fulfil the 100% requirement;
(d) the Bid should include a brief description of the roles and responsibilities
of individual members, particularly with reference to financial, technical and defect
liability obligations;
(e) the Lead Member shall itself undertake and perform at least 51(fifty- one)
per cent of the total length of the Project Highway,
(f) members of the Joint Venture shall have entered into a binding Joint
Bidding Agreement, substantially in the form specified in the RFP (the “Jt. Bidding
Agreement”), for the purpose of making the Application and submitting a Bid. The
Jt. Bidding Agreement, Uploaded on e-Tendering portal along with the Application,
shall, inter alia:
(i) convey the commitment(s) of the Lead Member in accordance with this
RFP, in case the contract to undertake the Project is awarded to the Joint
Venture; and clearly outline the proposed roles & responsibilities, if any, of
each member;
(ii) commit the approximate share of work to be undertaken by each
member conforming to sub-clause (e) mentioned above;
(iii) include a statement to the effect that all members of the Joint
Venture shall be liable jointly and severally for all obligations of the
Contractor in relation to the Project until the Defect Liability Period is
achieved in accordance with the Contract; and
(g) except as provided under this RFP, there shall not be any amendment to
the Jt. Bidding Agreement.
3.3 Any entity which has been blacklisted or barred or declared Non-Performer
by the Ministry of Road Transport & Highways or its implementing agencies;
NHAI/ NHIDCL/State PWDs/BRO, from participating in any project, and the bar
subsists as on the Bid due date, shall not be eligible to submit the bid.
3.4 It is mandatory for all the Bidders to have class-III Digital Signature Certificate
(DSC) (in the name of Authorized Signatory / Firm or Organisation / Owner of the
Firm or Organisation) from any of the licensed Certifying Agency (Bidders can see
the list of licensed CAs from the link www.cca.gov.in) to participate in e-tendering
of Employer.
3.5 DSC should be in the name of the authorized signatory as authorized in Appendix
III of this RFP or person executing/delegating such Appendix III in favour of
Authorized Signatory. It should be in corporate capacity (that is in Bidder capacity /
in case of JV in the Lead Member capacity, as applicable). The Bidder shall submit
document in support of the class III DSC. In other cases, the bid shall be considered
Non-responsive.
N = Number of years prescribed for completion of work for which Bid is invited.
B = Value (updated to the price level of the year indicated in table at Note-3 below)
of existing commitments, works for which the bidder has emerged as the winner of
the bids or on-going works to be completed during the period of completion of the
works for which BID is invited. For the sake of clarification, it is mentioned that
works for which bidder has emerged as the winner of the bids but LOA has not been
issued as on the day before opening the financial bids shall also be considered while
calculating value of B.
C = The amount of bonus received, if any, in EPC Projects during the last 5 years
(updated to the price level of the year indicated in table at Note-3 below).
Note:
1. The Statement showing the value of all existing commitments, works for
which the contractor has emerged as the winner of the bid is given by bidder and
ongoing works as well as the stipulated period of completion remaining for each
of the works listed should be countersigned by the Client or its Engineer-in-charge
not below the rank of Executive Engineer or equivalent in respect of EPC Projects
or Concessionaire / Authorised Signatory of SPV in respect of BOT Projects and
verified by Statutory Auditor.
3. The factor for the year for updation to the price level is indicated as under:
4. The Bid capacity status of the bidder to be updated as on the day before
opening the financial bids.
4.3 Technical Capacity
(i) For demonstrating technical capacity and experience (the “Technical
Capacity”), the Bidder shall, over the past 5 (five) financial years preceding the
Bid Due Date, have received payments for construction of Eligible Project(s), or has
undertaken construction works by itself in a PPP project, such that the sum total
thereof, as further adjusted in accordance with clause 4.6 (i) & (ii), is more than
the tendered / Bid value Rs. 59.33 crore (Rupees Fifty-Nine crore and Thirty-
Three lakh only) (the “Threshold Technical Capacity”).
(iii) The updation factor to update the price of the eligible projects for theyear
indicated in table below:
(ii) The Bidder shall have a minimum Average Annual Turnover (updated to
the price level of the year based on factors indicated in table below) of 15% of
tendered / Bid value Rs. 8.90 Crore (Rupees Eight crore and Ninety lakh only) for
the last 5 (five) financial years.
Note: Notwithstanding anything to the contrary contained herein, in the event that
the bid due date falls within three months of the closing of the latest financial years,
it shall ignore such financial year for the purpose of the bid and furnish annual
financial turnover w.r.t. 5 years preceding in last financial year.
4.5 In case of a Joint Venture:
(i) The Bid Capacity, Technical Capacity and Financial Capacity of all the
Members of Joint Venture would be taken into account for satisfying the above
conditions of eligibility. Further, Lead Member shall meet at least 60% requirement
of Bid Capacity, Technical and Financial Capacity and each of other JV members
shall meet at least 20% requirement of Bid Capacity, Technical and Financial
Capacity individually. For avoidance of doubt it is further clarified that the Joint
Venture must collectively and individually satisfy the above qualification criteria
i.e. JV shall cumulatively/collectively fulfill the 100% requirement.
(ii) For requirement of 4.3 (ii), one similar work of 20% of Estimated Project Cost
should have been completed from the Eligible Projects in Category 1 and/or
Category 3 specified in Clause 4.6 individually by any of the JV members as a single
work.
(II) Maintenance works are considered as eligible project for evaluation under
Technical capacity 4.3 (i) and for singly completed works 4.3 (ii). As such works
with nomenclature like IRQP, PR, OR, FDR,SR, site/micro grading, surface renewal,
resurfacing work, Tarring, B.T. surface work, temporary restoration, urgent works,
periodic maintenance, repair & rehabilitation, one time maintenance, permanent
protection work of bank, short term / long term OMT contract, Any performance
based maintenance contract, etc, shall be considered.
(IV) Project in Highway sector shall constitute the following for the purpose of
consideration under category 1 or 3 as applicable, if:
(V) The projects with the title of RIDF, PMGSY road, link road, city roads, rural
road, sector/ municipality road, Bridges for railway line, work of metro rails
(bridges/ tunnel), which demonstrate road development/construction bridges or
culverts may be considered for overall technical capacity only.
(VI) In case both the estimated cost of project and revised cost of project are
provided, the revised cost of project shall be considered for evaluation.
(ii) For a project to qualify as an Eligible Project under Category 3, the Bidder
should have received payments from its client(s) for construction/maintenance
works executed, fully or partially, or work executed and certified by the Engineer-
in-charge/Independent Engineer/Authority‟s Engineer during the 5 (five) financial
years immediately preceding the Bid Due Date, and only the amounts (gross)
actually received/ work executed, during such 5 (five) financial years shallqualify
for purposes of computing the Experience Score. However, receipts of or work
executed amount less than 5% of Bid Value shall not be reckoned as receipts for
Eligible Projects. For the avoidance of doubt, construction/maintenance works shall
not include supply of goods or equipment except when such goods orequipment
form part of a turn-key construction contract / EPC contract for the project.
Further, the cost of land and also cost towards pre-construction activities (like
shifting of utilities etc.) shall not be included hereunder.
(iii) The Bidder shall quote experience in respect of a particular Eligible Project
under any one category only, even though the Bidder (either individually or along
with a member of the Joint Venture) may have played multiple roles in the cited
project. Double counting for a particular Eligible Project shall not be permitted in
any form.
(iv) Experience for any activity relating to an Eligible Project shall not be claimed
by two or more Members of the Joint Venture. In other words, no double counting
by a Joint Venture in respect of the same experience shall be permitted in any
manner whatsoever.
(ii) The Bidder must provide the necessary information relating to Technical
Capacity as per format at Annex-II of Appendix-IA.
(iii) The Bidder should furnish the required Project-specific information and
evidence in support of its claim of Technical Capacity, as per format at Annex -IV
of Appendix-IA.
(ii) In case the annual accounts for the latest financial year are not audited
and therefore the Bidder cannot make it available, the Bidder shall give an
undertaking to this effect and the statutory auditor shall certify the same. In such
a case, the Bidder shall provide the Audited Annual Reports for 5 (five) years
preceding the year for which the Audited Annual Report is not being provided.
(iii) The Bidder must establish the minimum Net Worth specified in Clause 1.3,
and provide details as per format at Annex-III of Appendix-IA.
4.10 The Bidder shall enclose with its Technical Bid, to be uploaded on e –
tendering portal as per the format at Appendix-IA, complete with its Annexes, the
following:
(i) Certificate(s) from its statutory auditors$ or the concerned client(s) stating
the payments received or in case of a PPP project, the construction/maintenance
carried out by itself, during the past 5 years, in respect of the Eligible Projects. In
$In case duly certified audited annual financial statements containing explicitly the requisite details are
provided, a separate certification by statutory auditors would not be necessary in respect of Clause
4.10 (i). In jurisdictions that do not have statutory auditors, the firm of auditors which audits the annual
accounts of the Applicant may provide the certificates required under this RFP.
case a particular job/ contract has been jointly executed by the Bidder (as part of
a Joint Venture), it should further support its claim for the payments received or
construction carried out by itself in PPP Projects as applicable the share in work
done for that particular job/ contract by producing a certificate from its statutory
auditor or the client; and
(ii) Certificate(s) from its statutory auditors specifying the net worth of the
Bidder, as at the close of the preceding financial year, and also specifying that
the methodology adopted for calculating such net worth conforms to the
provisions of this Clause 4.10 (ii). For the purposes of this RFP, net worth (the
“Net Worth”) shall mean the aggregate value of the paid-up share capital and
all reserves created out of the profits and securities premium account, after
deducting the aggregate value of the accumulated losses, deferred expenditure
and miscellaneous expenditure not written off, as per the audited balance sheet,
but does not include reserves created out of revaluation of assets, write-back
of depreciation and amalgamation.
4.11 Even though the bidders meet the above qualifying criteria, they are
subject to be disqualified if they have:
i) Made misleading or false representations in the forms, statements, affidavits
and attachments submitted in proof of the qualification requirements; and/or
ii) Record of poor performance such as abandoning the works, not properly
completing the contract, inordinate delays in completion, litigation history, or
financial failures etc. or debarring from work etc.
6. Cost of bidding
6.1 The Bidder shall bear all costs associated with the preparation and
submission of his Bid, and the Employer will, in no case, be responsible or liable for
those costs.
7. Site Visit
7.1 The Bidder, at his own cost, responsibility and risk, is encouraged to visit,
examine and familiarise himself with the Site of Works and its surroundingsincluding
source of earth, water, road aggregates, availability of labour etc. and obtain all
information that may be necessary for preparing the Bid and entering into a
contract for undertaking the maintenance Works. The costs of visiting the site shall
be at the Bidder’s own expense. For this purpose, he may contact the person whose
contact details are given in the Appendix to ITB.
B. BIDDING DOCUMENTS
8. Content of bidding Documents
8.1 The set of bidding documents comprises the documents listed below
and addenda (if any) issued in accordance with Clause 10:
Section 1: Notice Inviting Tender
Section 2: Instructions to bidders (ITB) and Appendix to ITB
Section 3: Qualification Information
Section 4: Forms of Bank Guarantees for Bid Security, Performance Security &
Advance Payment, Letter of Application, Letter of Acceptance (LOA),
Form of Agreement, Format for POA for Signing of Bid, Format for
POA for Lead Member ofJV, Format for JBA, Integrity Pact
Section 5: General Conditions of Contract and Contract Data
Section 6: Addendum to General Conditions of Contract
Section 7: Road Maintenance Standards and Specifications for Road
Maintenance Work, Part-I and Part-II
Section 8: Drawings and Schedule of Drawings
Section 9: Financial bid form and bill of Quantities
Section 10: Summary of Assets
9.2.4 Non-attendance at the pre-bid meeting will not be a cause for disqualification
of a bidder.
(a) Original Power of Attorney for signing the BID as per format at Section-4;
(b) if applicable, Original Power of Attorney for Lead Member of Joint Venture as
per the format at Section-4;
(c) if applicable, Original Joint Bidding Agreement (JBA) for Joint Venture as per
the format at Section-4;
(d) BID Security of Rs. 5 9 . 9 4 (Rupees Fifty -Nine Lakh and Ninety- Four
Thousand only) in the form of Original Bank Guarantee in theformat at
Section-4 from a Scheduled Bank;
(e) Copy of online receipt towards payment of cost of Bid document of Rs. 10,000/-
(Rupees Ten Thousand Only) in favor of National Highways Authority of India
towards cost of Bid document;
(f) Deleted;
(g) Bidder shall comply with the provisions of Office Memorandum No. RW/NH-
37010/4/2010/PIC-EAP(Printing) dated 22.02.2016 and its subsequent
amendments if any issued by MoRT&H (Section-4) regarding Integrity Pact (IP)
and the Integrity Pact (IP)duly signed by Authorized signatory shall be
submitted by the Bidder with the RFP Bid & shall be part of the Contract
Agreement; and
(h) An undertaking from the person having PoA referred to in Sub. Clause-(a) above
that they agree and abide by the Bid documents uploaded by
MoRT&H/AGENCIES and amendments uploaded, if any
12.3 The following documents, which are not submitted with the bid, will be
deemed to be part of the bid.
i) Notice Inviting Tender
ii) Instructions to the Bidders and Appendix to ITB
iii) General Conditions of Contract and Contract Data
iv) Addendum to General Conditions of Contract
v) Road Maintenance Standards and Specifications for Road Maintenance
Works, Part-I and Part-II
vi) Drawings and Schedule of Drawings
13.2 The bidder shall make its own assessment of Cost for execution of the
Initial rectification (IR), periodic maintenance (PM) and Routine Maintenance (RM)
. Emergency works are indicative in nature with fixed cost and quantities to be
executed in case of emergency as directed by the Engineer. Contractor may take
guidance from the indicative BOQ attached by the Employer in the Bill of Quantities
Chapter. The Bidder shall only be required to quote the single percentage (%)
above or below in the Summary Abstract of Bid Cost Form of the Financial Bid
Form. The same discount/premium so quoted shall be applicable on payments of
all RM, IR, PM and Emergency works.
13.3 All duties, taxes (excluding GST), royalties and other levies payable by
the Contractor under the Contract, or for any other cause, shall be included in
the rates, prices, and total bid price submitted by the Bidder.
13.4 The rates and prices quoted by the Bidder shall be fixed for the duration
of the Contract, save except for price adjustment as per clause 17 of Contract data.
13.5 The rates and bid prices quoted by the contractor shall be deemed
inclusive of all labour, materials, Plants, Equipment, machinery, management,
supervision, overheads etc., including other miscellaneous charges associated for
execution of works
16.1 A Bidder is required to submit, along with its BID, Security of Rs. 59.94
(Rupees Fifty -Nine Lakh and Ninety- Four Thousand only) (the "BID Security"),
refundable not later than 150 (One hundred & fifty) days from the BID Due Date,
except in the case of the Selected Bidder whose BID Security shall be retained
till it has provided a Performance Security and Additional Performance Security
(if any) as per the provision of this RFP and LOA. This Guarantee shall be
transmitted through SFMS Gateway to NHAI‟s Bank. The Bidders shall also submit,
through online payment methods such as NEFT/RTGS Rs. 10,000/- (Rupees
Thousand Only)- in favour of National Highways Authority of India, as cost of
bidding document. The bank details are as under:
16.2 .
A. Bank Guarantee, in the name of the Employer, from following banks would
be accepted: -
i) State Bank of India or its subsidiaries,
ii) Any Indian Nationalized Bank
iii) IDBI/ICICI Bank
iv) A Foreign Bank (issued by a branch outside India) with a counter guarantee
from SBI or its subsidiaries or any Indian Nationalized Bank.
v) Any Scheduled Commercial Bank approved by RBI having a net worth of not
less than Rs. 1000 crore as per the latest Annual Report of the Bank. In the case of
a Foreign Bank (issued by a branch in India), the net worth in respect of the Indian
operations shall only be taken into account.
B. The acceptance of the guarantees shall also be subject to the
conditions that the capital adequacy of the Bank shall not be less than the latest
norms prescribed by RBI.
C. The bank guarantee issued by a Cooperative Bank shall not be accepted.
16.3 Any Bid not accompanied by an acceptable Bid Security, shall be rejected by
the Employer as non-responsive.
16.4 The Earnest Money/ Bid securities of the unsuccessful bidders will be
returned latest by 7th Day from the date of LOA.
16.5 Bid security/Earnest Money shall be refunded to the successful bidder on
receipt of a performance security and signing of Contract Agreement.
16.6 The Bid Security/Earnest Money will be forfeited:
(a) If the Bidder withdraws the Bid after Bid due date.
(b) Impairs or derogates from the tender in any respect within the period of
validity of the tender.
(c) If the bidder does not accept the correction of his bid price during evaluation;
and
(d) If the successful bidder fails to sign the contract or furnish the required
performance security within the specified period
16.7 In case of forfeiture of bid security, the bidder shall also be debarred from
participation in the works of MoRTH and its Agencies for a period of one year.
18.3 It is mandatory for all the Bidders to have class-III Digital Signature Certificate
(DSC)(in the name of Authorized Signatory / Firm or Organization / Owner of the
Firm or Organization) from any of the licensed Certifying Agency (Bidders can see
the list of licensed CAs from the link www.cca.gov.in) to
participate in e-tendering of Employer.
In the above pretext, the Class – I Local Supplier, Class – II Local Supplier and the
Non- Local Supplier are defined as under:
(i) “Class – I local Supplier‟ means a supplier or service provider, whose goods,
services or works offered for procurement, meets the minimum local content as
prescribed for “Class – I local Supplier‟ under this RFP. The ‘local content‟
requirement to categorize a supplier as “Class – I local Supplier‟ is minimum 50%.”
(ii) Class – II local Supplier‟ means a supplier or service provider, whose goods,
services or works offered for procurement, meets the minimum local content as
prescribed for ‘Class – II local Supplier‟ under this RFP. The ‘local content‟
requirement to categorize a supplier as “Class – II local Supplier‟ is minimum 20%”.
(iii) “Non - local Supplier‟ means a supplier or service provider, whose goods,
services or works offered for procurement, has local content less than that
prescribed for “Class – II local supplier‟ under this RFP”.
(iv) “Local content‟ means the amount of value added in India which shall be the
total value of item procured (excluding net domestic indirect taxes) minus the value
of imported content in the item (including all customs duties) as a proportion of
the total value, in percent
In case of procurement for a value in excess of Rs. 10 crores, the ‘Class – I local
supplier‟ / ‘Class – II local supplier‟ shall provide a certificate from the statutory
auditor or cost auditor of the company (in case of companies) or from a practicing
cost accountant or practicing chartered accountant (in respect of suppliers other
than companies) giving the percentage of local content
20.6 Entities of countries which have been identified by Ministry of Road Transport
& Highways as not allowing Indian companies to participate in their Government
procurement for any item related to Ministry of Road Transport & Highways shall
not be allowed to participate in Government procurement in India for all items
related to Ministry of Road Transport & Highways, except for the list of items
published by the Ministry of Road Transport & Highways permitting their
participation.
20.7 For determining the eligibility of Bidder from a country which shares a land
border with India the following shall apply:
(i) Any Bidder from a country which shares a land border with India will be
eligible to bid, only if the Bidder is registered with the Competent Authority,
specified in Annexure I of Order (Public Procurement No. 1) issued by Ministry of
Finance, Department of Expenditure Public Procurement Division vide F. No.
6/18/2019-PPD, dated 23rd July 2020, which shall form an integral part of RFPand
DCA (Copy enclosed).
(ii) "Bidder from a country which shares a land border with India" means:
a) An entity incorporated, established or registered in such a country, or
b) A subsidiary of an entity incorporated, established or registered in such a
country; or
c) An entity substantially controlled through entities incorporated,
established or registered in such a country; or
d) An entity whose beneficial owner is situated in such a country; or
e) An Indian (or other) agent of such an entity; or
f) A natural person who is a citizen of such a country; or
g) A Consortium or joint venture where any member of the consortium or
joint venture falls under any of the above.
Explanation:
a) "Controlling ownership interest" means ownership of or entitlement to more
than twenty-five per cent of shares or capital or profits of the company.
b) "Control" shall include the right to appoint majority of the directors or to
control the management or policy decisions including by virtue of their shareholding
or management rights or shareholding agreements or voting agreements;
4. Where no natural person is identified under (1) or (2) or (3) above, the
beneficial owner is the relevant natural person who holds the position of senior
managing official;
"I/We have read the clause regarding restrictions on procurement from a bidder of
a country which shares a land border with India and on sub-contracting to
contractors from such countries;
I/We certify that this bidder is not from a country or, if from such a country, has
been registered with the Competent Authority as defined in Public Procurement
Order no. F.no.6/18/2019- PPD dated 23rd July 2020 and will not sub-contract any
work to a contractor from such countries unless such contractor is registered with
the Competent Authority;
I/We hereby certify that this bidder fulfils all requirements in this regard and is
eligible to be considered."
It may be noted that in case the above certification is found to be false, this
would be a ground for immediate rejection of Bid/termination and further legal
action in accordance with law.
Validity of Registration:
In respect of RFP, registration should be valid at the time of submission of bids
and at the time of acceptance of bids. If the Bidder was validly registered at the
time of acceptance, registration shall not be a relevant consideration during
contract execution.
20.8 The Bidder should neither be a non-performing party on the date of opening
of tender nor on the date of issue of Letter of Acceptance (LoA). The Bidder shall
be deemed to be a non-performing party, if it attracts any or more of the following
conditions in any of its ongoing or completed project:
(iii) Fails to complete or has missed any milestone and progress not
commensurate with contiguous unencumbered project length /ROW availableeven
after lapse of 6 months from respective project milestone /Schedule Completion
date, unless Extension of Time has been granted due to Authority’s Default of Force
Majeure;
(iv) Fails to achieve progress commensurate with funds released from Escrow
Account (Equity +Debt + Grant) in BOT or HAM project and variation is more than
25% in the last 365 days;
(v) Fails to achieve target progress or complete the project as per schedule
agreed at the time of sanctioning of funds under One Time Funds Infusion (OTFI)
or relaxations to contract conditions to improve cash flow solely on account of
Concessionaire’s/contractor’s failure/default;
(x) Fails to complete Punch List items even after lapse of time for completion
of such items excluding delays attributable to the Authority;
(xiv) Fails to make premium payments excluding the current instalment in one or
more projects;
(xv) Fails to achieve financial closure in two or more projects within the given
or extended period (which shall not be more than six months in any case);
(xvi) Fails to submit the Performance Security within the permissible time period
in more than one project;
(xviii) Failed to perform for the works of Expressways, National Highways, ISC & EI
works in the last 2(two) years, as evidenced by imposition of a penalty by an arbitral
or judicial authority or a judicial pronouncement or arbitral award against the
Bidder, including individual or any of its Joint Venture Member, as the case may be.
(xix) Expelled from the contract or the contract terminated by the Ministry of
Road Transport & Highways or its implementing agencies for breach by such Bidder,
including individual or any of its Joint Venture Member; Provided that any such
decision of expulsion or termination of contract leading to debarring of the Bidder
from further participation in bids for the prescribed period should have been
ordered after affording an opportunity of hearing to such party.
(xx) Fails to start the works or causes delay in maintenance & repair/overlay of
the project.
In case, any debarred/declared non performer firm submits, the bid, the same
will be ignored. In case such firm is lowest (L-1), next lowest firm shall be
considered as L-1
27. Deleted
If the Bid Price offered by the Selected Bidder is lower than 20% of the estimated
Project Cost/ cost put to tender, then the Additional Performance Security shall be
calculated @20% of the difference in the (i) Estimated Project Cost (as mentioned
in RFP)-20% of the Estimated Project Cost and (ii) the Bid Price offered by the
selected Bidder.
30. Employer’s Right to accept any bid and to reject any or all bids
30.1 Notwithstanding Clause 29, the Employer reserves the right to accept or
reject any Bid, and to cancel the bidding process and reject all bids, at any time
prior to the award of Contract, without thereby incurring any liability to the
affected Bidder or bidders or any obligation to inform the affected Bidder or bidders
of the grounds for the Employer’s action.
1 Up to 50 km 1
2 More than 50 km and up to 150 km 2
3 More than 150 km and up to 300 km 3
(*)- Project length specified in Table above is indicative. The Employer while
inviting bids may review for making appropriate provision about number of
mobile units required.
The MMU shall be a new truck or already purchased (minimum 6 tonne) well
fabricated and GPS enabled to meet the requirement, painted and labelled
appropriately for safety and public awareness to the Employer’s satisfaction. Each
MMU shall have as a minimum requirement:
i. 1 No. Patrol Foreman
ii. 1 No Heavy Vehicle Driver
iii. 5 No. Maintenance Workers
iv. MMU to be equipped with 2 no Mobile Phone
v. Geotag Enabled Camera for video recording the section in Full HD quality
(1920 x 1080 pixels)
vi. 1 No. Jack Hammer
vii. 1 No. Compressor
viii. 1 No. Vibrating Plate Compactor
ix. 1 No. Chainsaw
x. 2 No. Portable grinder
xi. 2 No. steel wire brush
xii. 5 No. Putty knife
xiii. 1.0. m3 Cold Storable Bituminous Premix and 0.5 m3 of sand
xiv. 25 kg of General Purpose, Non-shrink Cementitious Grout
xv. 5 kg Epoxy Grout
xvi. 0.25 m3 GSB Grade-V/VI (MoRTH specification 401)
xvii. 0.25 m3 WMM (MoRTH specification 406)
xviii. Cold Poured Joint Sealing Compound (MoRTH specification 602.2.10)
xix. 2 No. “Half Road Closed” Signs
xx. 2 No. “Roadworks Ahead Signs”
xxi. 12 No. 300 mm plastic „high visibility‟ coloured traffic cones
xxii. 200 kg drum of Bitumen Emulsion
xxiii. A hand (or electric) Emulsion Spray Pump
xxiv. A Portable Electric Air Blower
xxv. 200 litre drum of Water
xxvi. 2 No. Rakes
xxvii. 2 No. Long Handle Shovels
xxviii. 2 No. Long Handle Heavy Duty Brooms
xxix. 2 No. Picks
xxx. High Visibility Jackets (Uniform) for all the MMU crew
xxxi. Foldable aluminium ladder.
xxxii. Operational Flashing amber lights fitted to the Patrol Truck
xxxiii. Mobile Maintenance Unit (MMU) Vehicle Identification visibly painted on
Vehicle (Contractor‟s Name, Client‟s Name, Road Names, Unit No., and
Emergency Contact Phone No.)
xxxiv. Grass Cutter
The MMU shall also be the "Initial Emergency Response Unit" along with Route
Patrol Vehicle and shall have the capability of the following:
▪ Capable to hold a half cubic metre of sand (or other suitable absorptive or
granular material depending on the nature of the requirement);
▪ After hour response a minimum two person crew;
▪ Emergency kit of temporary warning signs, flashing lights, barriers, safety
clothing, shovels and brooms.
Also the MMU must carry at all times the Emergency No. of Police, Fire, Ambulance,
Medical/Hospital centre along entire route to facilitate help in eventof accidents
and emergency encountered. A listing of all emergency contact phone numbers shall
be circulated by the Contractor to all relevant officers, including the Contractor’s
staff and the Employer prior to the Start Date.
2. ** Sensor Paver 1
3. * *Vibratory Roller (8/10 T) 1
4. Static Roller (8/10 T) 1
5. Small Roller/Compactor 1
6. Bitumen/emulsion sprayer 1
7. Mechanical Broom (1250 sqm per hour) 1
8. Air compressor 2
9. Grader/Backhoe loader 1
10. Water Tanker 2
11. Dewatering Pumps 2
12. Tipper/dumper Truck 2
13. Mini hot mix plant (6/10 T/Hr capacity) with indirect 1
heating arrangements
14. * *Hot Mix Plant 1
15. **String line set 1
Note: (**) - Equipment to be included if periodic maintenance is also included in
the contract.
Note: The bidder must upload scanned copy of the documentary evidence in support
of his owning/ leased/rented of the above equipment along with fitness certificates.
In case the bidder proposes to hire or take the above equipment on lease, he should,
along with the lease/rent agreement, attach the proof of ownership of this
equipment with the company/entity from whom the equipment are proposed to be
hired on lease/rent. Any conditional evidence of deployment of above equipment
or inadequate proof as required for any of the equipment shall make the bid non-
responsive and financial bid shall not be opened.
[4.1 j (2)]4 The Number of Technical Personnel, Qualifications and Experience will
be as follows:
The information to be filled in by the Bidder in this section and documents submitted
in physical form by the lowest Bidder will be used for the purposes of post
qualification as provided for in Clause 4 of the Instructions to Bidders. This
information will not be incorporated in the Contract.
Appendix IA
Annex-I
ANNEX-I
Details of Bidder
1. (a) Name:
(b) Country of incorporation:
$All provisions contained in curly parenthesis shall be suitably modified by the Applicant to reflect the
particulars relating to such Applicant.
* The role of each Member, as may be determined by the Applicant, should
be indicated in accordance with instruction 4 at Annex-IV.
(d) The following information shall also be provided w.r.t clause 3.3 for each
Member of the Joint Venture:
Name of Applicant/ member of Joint Venture:
Sl.
Criteria Yes/No
No.
1. Has the Bidder/ constituent of the Joint
Venture been barred by the Ministry of Road
Transport & Highways or its implementing
agencies for the works of Expressways,
National Highways, ISC and El works, from
participating in bidding.
2 If the answer to 1 is yes, does the bar subsist
as on BID due date.
6(a) I/ We certify that in the last two years, we/ any of the JV partners have neither
failed to perform for the works of Expressways, National Highways, ISC & EIworks,
as evidenced by imposition of a penalty by an arbitral or judicial authority or a
judicial pronouncement or arbitral award against us, nor been expelled or
terminated by Ministry of Road Transport & Highways or its implementing agencies
for breach on our part.
(b) I/ We certify that we/ any of the JV partners do not fall in any of the categories
of being a non-Performing entity given at Clause 3.3 of Instructions to Bidders in the
projects of Expressways, National Highways, ISC and EI works of Ministry of Road
Transport & Highways or its implementing agencies and furnished the complete
details.
@ Provide details of only those projects that have been undertaken by the Applicant, or
its Lead member including members in case of joint venture, under its own name
separately and/ or by a project company eligible under Clause 4.7(i)(b). In case of
Categories 1 and 2, include only those projects which have an estimated capital cost
exceeding the amount specified in Clause 4.7 (i)(c) and for Categories 3 and 4, include
only those projects where the payments received exceed the amount specified in Clause
4.7(ii).
** Construction shall not include supply of goods or equipment except when such goods
or equipment form part of a turn-key construction contract/ EPC contract for the project.
In no case shall the cost of maintenance and repair, operation of Highways and land be
included while computing the Experience Score of an Eligible Project.
$$For conversion of US Dollars to Rupees, the rate of conversion shall be Rupees ** (**) 5
to a US Dollar.
5The conversion rate of USD into Rupees shall be the daily representative exchange rates published by the
Reserve Bank of India for the relevant date. Where relevant date should be as on the date 28 (twenty eight)
days prior to the Application Due Date.
49
£. In the case of an Eligible Project situated in an OECD country, the Experience Score so
arrived at shall be further multiplied by 0.5, in accordance with the provisions of Clause
4.6 (ii) and the product thereof shall be the Experience Score for such Eligible Projects.
50
Appendix-IA
Annex-III
ANNEX-III
Financial Capacity of the Bidder
(Refer to Clauses 4.4, 4.10(i), 4.9(iii) of the RFP)
(In Rs. crore$)
Bidder type Net Cash Accruals Net Worth£
Year Year Year Year Year Year 1
1 2 3 4 5
Single entity Bidder or Lead Member
including other members of theJoint
Venture
TOTAL
Instructions:
1. The Bidder shall attach copies of the balance sheets, financial statements
and Annual Reports for 5 (five) years preceding the Bid Due Date. The financial
statements shall:
51
(a) reflect the financial situation of the Bidder;
(b) be audited by a statutory auditor;
(c) be complete, including all notes to the financial statements; and
(d) correspond to accounting periods already completed and audited
(no statements for partial periods shall be requested or
accepted).
2. Net Cash Accruals shall mean Profit After Tax + Depreciation.
3. Net Worth (the “Net worth”) shall means the aggregate value of the paid-up share
capital and all reserves created out of the profits and securities premium
account, after deducting the aggregate value of the accumulated losses, deferred
expenditure and miscellaneous expenditure not written off, as per the audited
balance sheet, but does not include reserves created out of revaluation of assets,
write-back of depreciation and amalgamation.
4. Year 1 will be the latest completed financial year, preceding the bidding. Year
2 shall be the year immediately preceding Year 1 and so on. In case the Bid Due
Date falls within 3 (three) months of the close of the latest financial year, refer
to Clause 4.4.
5. In the case of a Joint Venture, a copy of the Jt. Bidding Agreement shall be
submitted in accordance with Clause 3.2 (f) of the RFP document.
6. The Bidder shall also provide the name and address of the Bankers to the
Bidder.
7. The Bidder shall provide an Auditor’s Certificate specifying the net worth of the
Bidder and also specifying the methodology adopted for calculating such net
worth in accordance with Clause 4.10 (ii) of the RFP document.
52
ANNEX-IV
Details of Eligible Projects
(Refer to Clauses 4.3, 4.6 and 4.8 of the RFP)
Project Code: Entity: Self/Members:
Appendix IAAnnex-IV
Item Refer Particulars of the
Instruction Project
Title & nature of the project
Category 5
Year-wise 6
(a) payments received for construction/
maintenance or work executed and certified by the
Engineer-in-charge/Independent
Engineer/Authority’s Engineer, and/or
(b) revenues appropriated for self-construction/
maintenance under PPP projects
Entity for which the project was constructed 7
/Maintained
Location
Project cost 8
Date of commencement of project/ contract
Date of completion/ commissioning 9
Equity shareholding (with period during which equity 10
was held)
Instructions:
1. Bidders are expected to provide information in respect of each Eligible Projects in
this Annex. The projects cited must comply with the eligibility criteria specified in
Clause 4.7 (i) and 4.7 (ii) of the RFP, as the case may be. Information provided in
this section is intended to serve as a backup for information provided in the
Application. Applicants should also refer to the Instructions below.
2. The Project Codes would be a, b, c, d etc.
3. A separate sheet should be filled for each Eligible Project.
4. In case the Eligible Project relates to other Members, write “Member”.
5. Refer to Clause 4.6 of the RFP for category number.
6. The total payments received and/or revenues appropriated for self-construction/
maintenance for each Eligible Project are to be stated in Annex-II of this Appendix-
I. The figures to be provided here should indicate the break-up for the past 5 (five)
financial years. Year 1 refers to the financial year immediately preceding the Bid
Due Date; Year 2 refers to the year before Year 1, Year 3 refers to the year before
53
Year 2, and so on (Refer Clause 4.3). For Categories 1 and 2, expenditure on
construction/maintenance of the project by the Applicant itself should be provided,
but only in respect of projects having an estimated capitalcost exceeding the
amount specified in Clause 4.7 (i)(c). In case of Categories 3 and 4, payments
received only in respect of construction/ maintenance should be provided, but only if the
amount received exceeds the minimum specified in Clause 4.7(ii). Receipts for
construction works include capital expenditure, as wellas expenditure on maintenance &
repair and operation of Highways.
7. In case of projects in Category 1, particulars such as name, address and contact
details of owner/ Authority/ Agency (i.e. concession grantor, counter party to
concession, etc.) may be provided. In case of projects in Category 3, similar
particulars of the client need to be provided.
8. Provide the estimated capital cost of Eligible Project. Refer to Clauses 4.7 (i) and
4.7 (ii)
9. For Category 1, the date of commissioning of the project, upon completion, should
be indicated. In case of Categories 3, date of completion of construction should be
indicated. In the case of projects under construction, the likely date of completion
or commissioning, as the case may be, shall be indicated.
10. For Category 1, the equity shareholding of the Bidder, in the company owning the
Eligible Project, held continuously during the period for which Eligible Experience
is claimed, needs to be given (Refer Clause 4.7 (i)).
11. Experience for any activity relating to an Eligible Project shall not be claimed twice.
In other words, no double counting in respect of the same experience shall be
permitted in any manner whatsoever.
12. Certificate from the Bidder’s statutory auditor$ or its respective clients must be
furnished as per formats below for each Eligible Project. In jurisdictions that do not
have statutory auditors, the auditors who audit the annual accounts of the Bidder
may provide the requisite certification.
13. If the Bidder is claiming experience under Categories 1£, it should provide a
certificate from its statutory auditor in the format below as per Clause 4.7 (i) (d)
:
$ In case duly certified audited annual financial statements containing the requisite details are provided, a
separate certification by statutory auditors would not be necessary.
£ Refer Clause 4.6 of the RFP.
Provide Certificate as per this format only. Attach Explanatory Notes to the Certificate, if necessary.
54
Statutory auditor means the entity that audits and certifies the annual accounts of the company.
€ Refer instruction no. 10 in this Annex-IV.
¥ In case the project is owned by the Applicant company, this language may be suitably modified to read: “It
is certified that …………….. (name of Applicant) constructed and/ or owned the..................... (name of project)
from ……………….. (date) to .......................... (date).”
55
appointed for the purpose of construction/ maintenance by the aforesaid Applicant
itself, during the past five financial years as per year-wise details noted below:
………………………
………………………
Name of the audit firm:
Seal of the audit firm: (Signature, name and designation
Date: of the authorized
signatory)
14. If the Bidder is claiming experience under Category 3 & 4, as per Clauses 4.6 and
4.7 (ii) of the RFP, it should provide a certificate from its Statutory Auditor/client/
Engineer-in charge/ Independent Engineer/Authority’s Engineer inthe format below:
Certificate regarding construction/ maintenance works
Based on its books of accounts and other published information authenticated by
it, This is to certify that ……………………..(name of the Bidder) was engaged by
………………..(title of the project company) to execute ……………… (name of project)
for ........................(nature of project). The construction/ maintenance of the project
commenced on …………..(date) and the project was/ is likely to be commissioned
on …………… (date, if any). It is certified that Bidder received payments from its
Clients for Construction/ Maintenance Works executed by them or work executed
and certified by the Engineer-in-charge/Independent Engineer/Authority’s
Engineer, in the aforesaid construction works.
We further certify that the total estimated capital cost of the project is Rs cr.
(Rupees …………………crore), of which the Applicant received or has executed the
work as certified by the Engineer-in-charge/Independent Engineer/Authority’s
Engineer Rs. ……… cr. (Rupees ……………………… crore), during the past five financial
years as per year-wise details noted below:
………………………
………………………
It is further certified that the receipts indicated above are restricted to the share
of the Applicant who undertook these works as a partner or a member of joint
venture.
We further certify that applicant has a share of % in the Joint Venture/Consortium.
(Authorized Signatory)
Date:
Refer Clauses 4.6 and 4.7(ii) of the RFP.
Provide Certificate as per this format only. Attach Explanatory Notes to the Certificate, if necessary. Statutory
auditor means the entity that audits and certifies the annual accounts of the company. However, in case the
work of other member(s) is also executed by the applicant, then this fact should also be certified by the Statutory
Auditor and accordingly the language may be suitably modified.
This certification should be strike out in case of jobs/ contracts, which are executed a sole firm. The payments
indicated in the certificate should be restricted to the share of Applicant in such partnership/ joint venture. This
portion may be omitted if the contract did not involve a partnership/ joint venture. In case where work is not
executed by partnership/ joint venture, this paragraph may be deleted.
56
15. It may be noted that in the absence of any detail in the above certificates, the
information would be considered inadequate and could lead to exclusion of the
relevant project in computation of Experience.
57
Appendix -IA
Annex-V
ANNEX-V
Statement of Legal Capacity
(To be forwarded on the letterhead of the Applicant/ Lead Member of Joint Venture)
Ref. Date:
To,
General Manager (T)
National Highways Authority of India,
G-5 & 6, Sector-10, Dwarka,
New Delhi-110075
Dear Sir,
We hereby confirm that we/ our members in the Joint Venture (constitution of which has
been described in the application) satisfy the terms and conditions laid out in the RFP
document.
We have agreed that …………………… (insert member’s name) will act as the Lead Member
of our Joint Venture.*
We have agreed that ………………….. (insert individual’s name) will act as our representative/
will act as the representative of the Joint Venture on its behalf* and has been duly
authorized to submit the RFP. Further, the authorized signatory is vested with requisite
powers to furnish such letter and authenticate the same.
Thanking you,
Yours faithfully,
58
Appendix - IA
Annexure-VI
Information required to evaluate the BID Capacity under clause 4.2:
To calculate the value of “A” and “C”
1. A table containing value of Civil Engineering Works in respect of EPC Projects (Turnkey
projects / Item rate contract/ Construction works) undertaken by the Bidder during
the last 5 years is as follows (the amount of bonus received, if any, shall be indicated
separately):
2.
Sl. Year Value of Civil Engg. Amount of Net Value
No. Works undertaken w.r.t. bonus (Rs. excluding
EPC Projects including in Crores) bonus (Rs. in
bonus, if any (Rs. in Crores)
Crores)
1 2022-23/2022
2 2021-22/2021
3 2020-21/2020
4 2019-20/2019
5 2018-19/2018
3. Maximum value of projects that have been undertaken during the F.Y.
out of the last 5 years and value excluding amount of bonus thereof is Rs.
Crores (Rupees ). Further, value updated to
the price level of the year indicated in Appendix is as follows:
4. Amount of bonus received, if any, in EPC Projects during the last 5 years (updated
to the price level of the year indicated in Appendix):
Sl. F.Y. / Calendar Amount Updation Updated Amount of
No. Year of Bonus Factor Bonus (Rs. in
(Rs. in Crores)
Crores)
1 2022-23/2022 1.00
2 2021-22/2021 1.05
3 2020-21/2020 1.10
4 2019-20/2019 1.15
5 2018-19/2018 1.20
Total (C)=
………………………… ……………………..
…………………………. ……………………..
Name of the Statutory Auditor’s firm: Signature, name and designation of Authorized
Seal of the audit firm: (Signature, name and Signatory
designation
: and Membership No. of
authorized signatory) For and on behalf of ………………(Name of
Date: Place:
59
To calculate the value of “B”
A table containing value of all the existing commitments and on-going works to be
completed during the next 05 years is as follows:
Sl. Name Percentag Dater of Constructi Value Value of Balance Anticipat Balance
No. of e of start / on period of work value of ed date value of
Projec participati appointe as per contrac complete work to of work at
t/Wor on of d date Agreemen t as per d be completi 2022-
k Bidder in of t/ LOA Agreem complete on 23/2022
the project ent d price level
project /LOAβ
60
Date:
Place:
β
In case balance period of construction is less than the value of period of maintenance of the project
for which bid is invited, then full value of contract as per Agreement/LOA to be mentioned, else,
anticipated value of work to be completed in the period of construction of the project for which bid is
invited is to be mentioned. In the absence of the anticipated value of work to be completed,the
proportionate value shall be considered while evaluating the Assessed Available Bid Capacity.
61
APPENDIX-IA
Annexure VII
Guidelines of the Department of Disinvestment
(Refer Clause1.2.1)
No. 6/4/2001-DD-II
Government of India
Department of Disinvestment
Block 14, CGO Complex
New Delhi.
th
Dated 13 July, 2001.
OFFICE MEMORANDUM
Sub: Guidelines for qualification of Bidders seeking to acquire stakes in Public Sector
Enterprises through the process of disinvestment
Government has examined the issue of framing comprehensive and transparent guidelines
defining the criteria for Bidders interested in PSE-disinvestment so that the parties
selected through competitive bidding could inspire public confidence. Earlier, criteria like
net worth, experience etc. used to be prescribed. Based on experience andin consultation
with concerned departments, Government has decided to prescribe the following
additional criteria for the qualification/ disqualification of the parties seeking to acquire
stakes in public sector enterprises through disinvestment:
(a) In regard to matters other than the security and integrity of the country, any
conviction by a Court of Law or indictment/ adverse order by a regulatory
authority that casts a doubt on the ability of the Bidder to manage the public
sector unit when it is disinvested, or which relates to a grave offence would
constitute disqualification. Grave offence is defined to be of such a nature
that it outrages the moral sense of the community. The decision in regard to
the nature of the offence would be taken on case to case basis after
considering the facts of the case and relevant legal principles, by the
Government of India.
(b) In regard to matters relating to the security and integrity of the country,
any charge-sheet by an agency of the Government/ conviction by a Court of
Law for an offence committed by the bidding party or by any sister concern
of the bidding party would result in disqualification. The decision in regard
to the relationship between the sister concerns would be taken, based on the
relevant facts and after examining whether the two concerns aresubstantially
controlled by the same person/ persons.
(c) In both (a) and (b), disqualification shall continue for a period that
Government deems appropriate.
(d) Any entity, which is disqualified from participating in the disinvestment
process, would not be allowed to remain associated with it or get associated
merely because it has preferred an appeal against the order based on which
it has been disqualified. The mere pendency of appeal will have no effect on
the disqualification.
(e) The disqualification criteria would come into effect immediately and would
apply to all Bidders for various disinvestment transactions, which have not
been completed as yet.
62
(f) Before disqualifying a concern, a Show Cause Notice why it should not be
disqualified would be issued to it and it would be given an opportunity to
explain its position.
(g) Henceforth, these criteria will be prescribed in the advertisements seeking
Expression of Interest (EOI) from the interested parties. The interested
parties would be required to provide the information on the above criteria,
along with their Expressions of Interest (EOI). The Bidders shall be required
to provide with their EOI an undertaking to the effect that no investigation
by a regulatory authority is pending against them. In case any investigation
is pending against the concern or its sister concern or against its CEO or any
of its Directors/ Managers/ employees, full details of such investigation
including the name of the investigating agency, the charge/ offence for which
the investigation has been launched, name and designation of persons
against whom the investigation has been launched and other relevant
information should be disclosed, to the satisfaction of the Government. For
other criteria also, a similar undertaking shall be obtained along with EOI.
sd/-
(A.K. Tewari)
Under Secretary to the Government of India
63
Appendix - IA
Annexure-VIII
(In the event that the Bidder had failed to achieve the Completion of any project
within a period of 90 (ninety) days from the Schedule Completion Date of the
project, unless such failure had occurred due to Force Majeure or for reasons solely
attributable to the Authority, the Bidder shall be deemed to be ineligible forbidding
this project (under bidding), both as the sole party or as one of the parties of Joint
Venture/ Consortium, if any, during the period from Scheduled Completion Date to
issuance of Completion Certificate for that project. Thisrestriction is applicable if
the contract value of the delayed project was not less than Rs. 300 Crore.)
#To be supported with valid certificate issued from Independent Engineer /
I / We certify that all the information furnished above is true in all respects.
Date:
Place:
64
In addition, Bidders should upload the scanned copy of the following
affidavits/undertakings as per formats enclosed hereinafter and also send original
copy of Affidavit/Undertakings: -
i) Affidavit (it should be on stamp paper attested by Notary Public)
ii) Deleted
iii) Undertaking that the Bids shall remain valid for the period
specified in Clause 15.1.
65
Appendix-IA
Annexure-IX
AFFIDAVIT
(To be submitted by each JV Member)
1. I, the undersigned, do hereby certify that all the statements made in the
enclosed attachments are true and correct.
2. The undersigned also hereby certifies that neither our
firm M/s
Name of Firm
Date
66
Appendix-IA
Annexure-X
UNDERTAKING FOR BID VALIDITY
(Signed by an Authorized
Representative of the
Firm)
Name of Firm
Date
67
SECTION – 4
FORMS OF BANK GUARANTEES LETTER OF ACCEPTANCE (LOA) AND AGREEMENT
1. In consideration of you, National Highways Authority of India, having its office at G-5 &
6, Sector-10, Dwarka, New Delhi-110075, (hereinafter referred to as the “Authority”,
which expression shall unless it be repugnant to the subject or context thereof include
its, successors and assigns) having agreed to receive the BID of
…………………… and having its registered office at ............................. (and acting on behalf
of its JV) (hereinafter referred to as the “Bidder” which expression shall unlessit
be repugnant to the subject or context thereof include its/their executors,
administrators, successors and assigns), for the PBMC O&M work of 4 Laning of Simga-
Sargaon (PKG - II) of NH-200 section from Km 48+580 to Km 91+026 and Sargaon-
Bilaspur (PKG - III) of NH-200 section from Km 91+026 to Km 126.525 section of
Raipur-Bilaspur in the State of Chhattisgarh. on Performance based Maintenance
Contracts (PBMC) basis (hereinafter referred to as “the Project”) pursuant to the Bid
Document dated …………… issued in respect of the Project and other related
documents including without limitation the draft contract Agreement (hereinafter
collectively referred to as “Bidding Documents”), we (Name of the Bank) having our
registered office at ………………… and one of its branches at ……………………..
(hereinafter referred to as the “Bank”), at the request of the Bidder, do hereby in terms
of Clause 16 read with Clause 32.3 of the Bid Document, irrevocably, unconditionally
and without reservation guarantee the due and faithful fulfilment and compliance
of the terms and conditions of the Bidding Documents (including the Bid
Document) by the said Bidder and
unconditionally and irrevocably undertake to pay forthwith to the Authority an amount
of Rs. 59.94 (Rupees Fifty -Nine Lakh and Ninety- Four Thousand only) (hereinafter
referred to as the “Guarantee”) as our primary obligation without any demur,
reservation, recourse, contest or protest and without reference to the Bidder if the
Bidder shall fail to fulfil or comply with all or any of the terms and conditions
contained in thesaid Bidding Documents.
2. Any such written demand made by the Authority stating that the Bidder is in default
of the due and faithful fulfilment and compliance with the terms and conditions
contained in the Bidding Documents shall be final, conclusive and bindingon the Bank.
3. We, the Bank, do hereby unconditionally undertake to pay the amounts due and payable
under this Guarantee without any demur, reservation, recourse, contest or protest and
without any reference to the Bidder or any other person and irrespective of whether
the claim of the Authority is disputed by the Bidder or not, merely on the first demand
from the Authority stating that the amount claimed is due to the Authority by reason of
failure of the Bidder to fulfil and comply with the terms and conditions contained in the
Bidding Documents including failure of the said Bidder to keep its BID open during the
BID validity period as set forth in the said Bidding Documents for any reason whatsoever.
Any such demand made on the Bank shall be conclusive as regards amount due and
payable by the Bank under this Guarantee. However, our liability under this Guarantee
shall be restricted to an amount not exceeding Rs. 59.94 (Rupees Fifty -Nine Lakh and
Ninety- Four Thousand only) This Guarantee shall be irrevocable and remain in full
68
force for a period of 150 (one hundred and fifty) days from the BID Due Date inclusive
of a claim period of 60 (sixty)
days or for such extended period as may be mutually agreed between the Authority and
the Bidder, and agreed to by the Bank, and shall continue to be enforceable till all
amounts under this Guarantee have been paid.
4. We, the Bank, further agree that the Authority shall be the sole judge to decide as
to whether the Bidder is in default of due and faithful fulfilment and compliance
with the terms and conditions contained in the Bidding Documents including, inter
alia, the failure of the Bidder to keep its BID open during the BID validity period set
forth in the said Bidding Documents, and the decision of the Authority that the Bidder is
in default as aforesaid shall be final and binding on us, notwithstanding any
differences between the Authority and the Bidder or any dispute pending before any
Court, Tribunal, Arbitrator or any other Authority.
5. The Guarantee shall not be affected by any change in the constitution or winding
up of the Bidder or the Bank or any absorption, merger or amalgamation of the Bidder
or the Bank with any other person.
6. In order to give full effect to this Guarantee, the Authority shall be entitled to treat the
Bank as the principal debtor. The Authority shall have the fullest liberty without
affecting in any way the liability of the Bank under this Guarantee from time to time to
vary any of the terms and conditions contained in the said Bidding Documents or to
extend time for submission of the BIDs or the BID validity period or the period for
conveying acceptance of Letter of Acceptance by the Bidder or the period for fulfilment
and compliance with all or any of the terms and conditions contained in the said Bidding
Documents by the said Bidder or to postpone for any time and from time to time any
of the powers exercisable by it against the said Bidder and eitherto enforce or forbear
from enforcing any of the terms and conditions contained in the said Bidding
Documents or the securities available to the Authority, and the Bank shall not be
released from its liability under these presents by any exercise by the Authority of the
liberty with reference to the matters aforesaid or by reason of time being given to the
said Bidder or any other forbearance, act or omission on the partof the Authority or
any indulgence by the Authority to the said Bidder or by any change in the constitution
of the Authority or its absorption, merger or amalgamation withany other person or
any other matter or thing whatsoever which under the law relatingto sureties would but
for this provision have the effect of releasing the Bank from its such liability.
9. It shall not be necessary for the Authority to proceed against the said Bidder before
proceeding against the Bank and the guarantee herein contained shall be enforceable
against the Bank, notwithstanding any other security which the Authority may have
obtained from the said Bidder or any other person and which shall, at the time when
proceedings are taken against the Bank hereunder, be outstanding or unrealized.
We, the Bank, further undertake not to revoke this Guarantee during its currencyexcept
with the previous express consent of the Authority in writing.
69
10. The Bank declares that it has power to issue this Guarantee and discharge the obligations
contemplated herein, the undersigned is duly authorized and has fullpower to execute
this Guarantee for and on behalf of the Bank.
11. For the avoidance of doubt, the Bank’s liability under this Guarantee shall be
restricted to Rs. 59.94 (Rupees Fifty -Nine Lakh and Ninety- Four Thousand only).
The Bank shall be liable topay the said amount or any part thereof only if the
Authority serves a written claim on the Bank in accordance with paragraph 9 hereof,
on or before [*** (indicate date falling 210 days after the BID Due Date)].
12. This guarantee shall also be operatable at our……………….. Branch at New Delhi, from
whom, confirmation regarding the issue of this guarantee or extension / renewal
thereof shall be made available on demand. In the contingency of this guarantee being
invoked and payment thereunder claimed, the said branch shall accept such invocation
letter and make payment of amounts so demanded under the said invocation.
13. The guarantor/bank hereby confirms that it is on the SFMS (Structural Finance Messaging
System) platform & shall invariably send an advice of this Bank Guarantee to the
designated bank of NHAI, details of which is as under:
(Official-Seal)
70
FORM OF BANK GUARANTEES FOR PERFORMANCE SECURITY
1. The Bank hereby unconditionally and irrevocably guarantees the due and
faithful performance of the Contractor’s obligations during the {Defects Liability
Period and Contract Period} under and in accordance with the Contract, and agrees
and undertakes to pay to the Authority, upon its mere first written demand, and
without any demur, reservation, recourse, contest or protest, and without any
reference to the Contractor, such sum or sums up to an aggregate sum of the
Guarantee Amount as the Authority shall claim, without the Authority being required
to prove or to show grounds or reasons for its demand and/or for the sum specified
therein.
2. A letter from the Authority, under the hand of an officer not below the rank
of [Superintending Engineer of Ministry of Road Transport & Highways or equivalent
Officer of NHAI/NHIDCL/BRO], that the Contractor has committed default in the
due and faithful performance of all or any of its obligations under and in accordance
with the Contract shall be conclusive, final and binding on the Bank.The Bank
further agrees that the Authority shall be the sole judge as to whether the Contractor
is in default in due and faithful performance of its obligations during and under the
Contract and its decision that the Contractor is in default shall be final and binding
on the Bank, notwithstanding any differences between the Authority and the
Contractor, or any dispute between them pending before any court, tribunal,
arbitrators or any other authority or body, or by the discharge ofthe Contractor for
any reason whatsoever.
In order to give effect to this Guarantee, the Authority shall be entitled to act as if
the Bank were the principal debtor and any change in the constitution of the Contractor
and/or the Bank, whether by their absorption with any other bodyor corporation or
otherwise, shall not in any way or manner affect the liability or obligation of the Bank
under this Guarantee.
3. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its demand
under this Guarantee.
4. The Authority shall have the liberty, without affecting in any manner the
liability of the Bank under this Guarantee, to vary at any time, the terms and
conditions of the Contract or to extend the time or period for the compliance with,
fulfillment and/ or performance of all or any of the obligations of the Contractor
contained in the Contract or to postpone for any time, and from time to time, any of
the rights and powers exercisable by the Authority against the Contractor, and either
to enforce or forbear from enforcing any of the terms and conditions contained in
the Contract and/or the securities available to the Authority, and the Bank shall not
be released from its liability and obligation under these presents by any exercise by
the Authority of the liberty with reference to the matters aforesaid or by reason of
time being given to the Contractor or any other forbearance, indulgence, act or
omission on the part of the Authority or of any other matter or thing whatsoever
which under any law relating to sureties and guarantors would butfor this provision
have the effect of releasing the Bank from its liability and obligation under this
Guarantee and the Bank hereby waives all of its rights under any such law.
7. The Guarantee shall cease to be in force and effect on ****$. Unless a demand
or claim under this Guarantee is made in writing before expiry of the Guarantee, the
Bank shall be discharged from its liabilities hereunder.
8. The Bank undertakes not to revoke this Guarantee during its currency,except
with the previous express consent of the Authority in writing, and declares and
warrants that it has the power to issue this Guarantee and the undersigned has full
powers to do so on behalf of the Bank.
11. This Guarantee is subject to the Uniform Rules for Demand Guarantees (URDG)
2010 Revision, ICC Publication No. 758, except that the supporting statement under
Article 15(a) is hereby excluded.
12. This guarantee shall also be operatable at our……………….. Branch at New Delhi,
from whom, confirmation regarding the issue of this guarantee or extension / renewal
thereof shall be made available on demand. In the contingency of this guarantee
being invoked and payment thereunder claimed, the said branch shall accept such
invocation letter and make payment of amounts so demanded under the said
invocation.
13. The guarantor/bank hereby confirms that it is on the SFMS (Structural Finance
Messaging System) platform & shall invariably send an advice of this Bank Guarantee
tothe designated bank of NHAI, details of which is as under:
(Signature)
(Name)
(Designation)
(Code Number)
(Address)
BANK GUARANTEE FOR ADVANCE PAYMENT
7. The Guarantee shall cease to be in force and effect on ****. $ Unless a demand or
claim under this Guarantee is made in writing on or before the aforesaid date,
the Bank shall be discharged from its liabilities hereunder.
8. The Bank undertakes not to revoke this Guarantee during its currency, except
with the previous express consent of the Authority in writing, and declares and
warrants that it has the power to issue this Guarantee and the undersigned has
full powers to do so on behalf of the Bank.
9. Any notice by way of request, demand or otherwise hereunder may be sent by
post addressed to the Bank at its above referred branch, which shall be deemed
to have been duly authorized to receive such notice and to effect payment
thereof forthwith, and if sent by post it shall be deemed to have been given at
the time when it ought to have been delivered in due course of post and in proving
such notice, when given by post, it shall be sufficient to prove that the envelope
containing the notice was posted and a certificate signed by an officer of the
Authority that the envelope was so posted shall be conclusive.
10. This Guarantee shall come into force with immediate effect and shall remain in
force and effect up to the date specified in paragraph 8 above or until it is
released earlier by the Authority pursuant to the provisions of the Agreement.
11. This guarantee shall also be operatable at our……………….. Branch at New Delhi,
from whom, confirmation regarding the issue of this guarantee or extension /
renewal thereof shall be made available on demand. In the contingency of this
guarantee being invoked and payment thereunder claimed, the said branch shall
accept such invocation letter and make payment of amounts so demanded
under the said invocation.
12. The guarantor/bank hereby confirms that it is on the SFMS (Structural Finance
Messaging System) platform & shall invariably send an advice of this Bank
Guarantee tothe designated bank of NHAI, details of which is as under:
To,
General Manager (T)
National Highway Authority of India
G-5&6, Sec.10, Dwarka
New Delhi- 110075
DESCRIPTION OF WORKS: BID FOR PBMC O&M work of 4 Laning of Simga-Sargaon (PKG - II) of
NH-200 section from Km 48+580 to Km 91+026 and Sargaon-
Bilaspur (PKG - III) of NH-200 section from Km 91+026 to Km
126.525 section of Raipur-Bilaspur in the State of Chhattisgarh.
Dear Sir,
Having examined the Bid Document, Instructions to Bidders, Qualification Information,
Scope of Works, etc. for the subject work and after visiting the site& conducting all
requisite engineering studies we hereby submit our bid for the subject work.
It is certified that the information furnished in this document is true and correct. The
proposal is unconditional and unqualified. We undersigned accept that the Employer
reserves the right to reject any or all applications without assigning any reason.
Thanking you,
Yours faithfully,
(Authorized Signatory)
For and on behalf of M/s
FORM OF LETTER OF
ACCEPTANCE
To
M/s………………………….
Sub.: PBMC O&M work of 4 Laning of Simga-Sargaon (PKG - II) of NH-200 section from Km 48+580 to
Km 91+026 and Sargaon- Bilaspur (PKG - III) of NH-200 section from Km 91+026 to Km 126.525
section of Raipur-Bilaspur in the State of Chhattisgarh.
Sir,
Based on your bid submitted on ............in compliance of bidding document of [the
Employer] for execution of the works of .., it is hereby notified that your bid for a Contract
Price of Rs…………… (Rupees in words… ) which is at a premium/discount of
% from the estimated project cost has been accepted for and on behalf of [the
Employer]
You are hereby requested to furnish Performance Security plus additional security in
the form detailed in Clause 32.1 of ITB for an amount equivalent to Rs…............. (Rupees
in words… ) within 30 days and as per provisions of Clause 32.2 of ITB of the bid
document, sign the contract agreement failing which the actions as stipulated in Clause-
32.3 of ITB shall be taken.
Thanking you,
Yours faithfully,
(.................... ) Employer
FORM OF AGREEMENT
AGREEMENT
AND WHEREAS the Employer invited bids from eligible bidders for the maintenance of
certain National Highway Section, viz………………………………………………
AND WHEREAS pursuant to the bid submitted by the Contractor, vide (here in
after referred to as the “BID” or “ÖFFER”) for the execution of works and maintenance
of the subject project, the Employer by his letter of acceptance dated accepted
the offer submitted by the Contractor for the execution and completion of such works,
maintain the subject project and remedying of any defects thereon, on terms and
conditions in accordance with the documents listed in Para 2 below. The Contractor has
further represented to the effect that it has delivered to the Authority a legal opinion
with respect to the authority of the Contractor to enter into this Contract Agreement
and the enforceability of the provisions thereof.
AND WHEREAS the Contractor has agreed to undertake such works and has furnished a
Performance Security pursuant to Clause 32 of ITB (Section-2).
B. Name : 2. Name:
Address: Address:
APPENDIX-III
Format for Power of Attorney for signing of BID
(Refer Clause 4.1 (a))
Know all men by these presents, We…………………………………………….. (name of the firm and
address of the registered office) do hereby irrevocably constitute, nominate, appoint
and authorize Mr./ Ms (name), …………………… son/daughter/wife of
……………………………… and presently residing at …………………., who is presently employed
with us/ the Lead Member of our Joint Venture and holding the position of
……………………………. , as our true and lawful attorney (hereinafter referred to as the
“Attorney”) to do in our name and on our behalf, all such acts, deeds and things as are
necessary or required in connection with or incidental to submission of our BID for PBMC
O&M work of 4 Laning of Simga-Sargaon (PKG - II) of NH-200 section from Km 48+580
to Km 91+026 and Sargaon- Bilaspur (PKG - III) of NH-200 section from Km 91+026 to
Km 126.525 section of Raipur-Bilaspur in the State of Chhattisgarh.on Performance
based Maintenance Contracts (PBMC) by the National Highways Authority of India (the
“Authority”) including but not limited to signing and submission of all applications,
BIDs and other documents and writings, participate in Pre-BID and other conferences
and providing information/ responses to the Authority, representing us in all matters
before the Authority, signing and execution of all contracts including the agreement and
undertakings consequent to acceptance of our BID, and generally dealing with the
Authority in all matters in connection with or relating to or arising out of our BID for the
said Project and/ or upon award thereof to us and/or until the entering into of the PBMC
Contract with the Authority.
AND we hereby agree to ratify and confirm and do hereby ratify and confirm all acts,
deeds and things done or caused to be done by our said Attorney pursuant to and in
exercise of the powers conferred by this Power of Attorney and that all acts, deeds
and things done by our said Attorney in exercise of the powers hereby conferred shall
and shall always be deemed to have been done by us.
Witnesses:
1.
2.
Accepted
……………………………
(Signature)
(Name, Title and Address of the Attorney)
(Notarized)
Person identified by me/ personally appeared before me/
Attested/ Authenticated*
(*Notary to specify as applicable)
(Signature Name and Address of the Notary)
▪ Wherever required, the Bidder should submit for verification the extract of the
charter documents and documents such as a board or shareholders’ resolution/ power of
attorney in favour of the person executing this Power of Attorney for the delegation of
power hereunder on behalf of the Bidder.
▪ For a Power of Attorney executed and issued overseas, the document will also
have to be legalized by the Indian Embassy and notarized in the jurisdiction where the
Power of Attorney is being issued. However, the Power of Attorney provided by Bidders
from countries that have signed the Hague Legislation Convention 1961 are not required
to be legalized by the Indian Embassy if it carries a conforming Appostille certificate.
APPENDIX-IV
Whereas the (“the Authority”) has invited BIDs for the PBMC O&M work of
4 Laning of Simga-Sargaon (PKG - II) of NH-200 section from Km 48+580 to Km 91+026 and
Sargaon- Bilaspur (PKG - III) of NH-200 section from Km 91+026 to Km 126.525 section of Raipur-
Bilaspur in the State of Chhattisgarh. (PBMC) Project (the“Project”).
Whereas, it is necessary for the Members of the Joint Venture to designate one of them
as the Lead Member with all necessary power and authority to do for and on behalf of
the Joint Venture, all acts, deeds and things as may be necessary in connection with
the Joint Venture‟s BID for the Project and its execution.
We, …… having our registered office at ……., M/s having our registered office at …,
M/s. … having our registered office at ….., and ….. having our registered office at ,
(Hereinafter collectively referred to as the “Principals”) do hereby irrevocably designate,
nominate, constitute, appoint and authorize M/S ……. having its registered office at
………., being one of the Members of the Joint Venture, as the Lead Member and true and
lawful attorney of the Joint Venture (hereinafter referred to as the “Attorney”). We
hereby irrevocably authorize the Attorney (with power to sub- delegate) to conduct all
business for and on behalf of the Joint Venture and any one of us during the bidding
process and, in the event the Joint Venture is awarded the contract, during the execution
of the Project and in this regard, to do on our behalfand on behalf of the Joint Venture,
all or any of such acts, deeds or things as are necessary or required or incidental to the
pre-qualification of the Joint Venture and submission of its BID for the Project, including
but not limited to signing and submission of all applications, BIDs and other documents
and writings, participate in pre BID and other conferences, respond to queries, submit
information/ documents, sign and execute contracts and undertakings consequent to
acceptance of the BID of the Joint Venture and generally to represent the Joint Venture
in all its dealings with the Authority, and/ or any other Government Agency or any person,
in all matters in connection with or relating to or arising out of the Joint Venture’s BID
for the in all respect Project and/ or upon award thereof till the PBMC Contract is entered
into with the Authority & Compelled.
AND hereby agree to ratify and confirm and do hereby ratify and confirm all acts, deeds
and things done or caused to be done by our said Attorney pursuant to and in exercise
of the powers conferred by this Power of Attorney and that all acts, deeds and things
done by our said Attorney in exercise of the powers hereby conferred shall and shall
always be deemed to have been done by us/ Joint Venture.
IN WITNESS WHEREOF WE THE PRINCIPALS ABOVE NAMED HAVE EXECUTED THIS POWER
OF ATTORNEY ON THIS …………………. DAY OF ………. 2..…
1.
2.
Notes:
▪ The mode of execution of the Power of Attorney should be in accordance with the
procedure, if any, laid down by the applicable law and the charter documents of the
executant(s) and when it is so required, the same should be under common seal affixed
in accordance with the required procedure.
▪ Also, wherever required, the Bidder should submit for verification the extract of
the charter documents and documents such as a board or shareholders’ resolution/
power of attorney in favour of the person executing this Power of Attorney for the
delegation of power hereunder on behalf of the Bidder.
▪ For a Power of Attorney executed and issued overseas, the document will also
have to be legalized by the Indian Embassy and notarized in the jurisdiction where the
Power of Attorney is being issued. However, the Power of Attorney provided byBidders
from countries that have signed the Hague Legislation Convention 1961 are not required
to be legalised by the Indian Embassy if it carries a conforming Appostille certificate.
APPENDIX V
THIS JOINT BIDDING AGREEMENT is entered into on this the ………… day of ..............20…
AMONGST
1. {………… Limited, and having its registered office at ............. } (hereinafter referred to
as the “First Part” which expression shall, unless repugnant to the context include its
successors and permitted assigns)
AND
2. {………… Limited, having its registered office at.............. }and (hereinafter referred to
as the “Second Part” which expression shall, unless repugnant to the context include
its successors and permitted assigns)
AND
3. {………… Limited, and having its registered office at …………} (hereinafter referred to
as the “Third Part” which expression shall, unless repugnant to the context include its
successors and permitted assigns)
The above-mentioned parties of the FIRST, {SECOND and THIRD} PART are
collectivelyreferred to as the “Parties” and each is individually referred to as a
“Party”
WHEREAS,
(B) The Parties are interested in jointly bidding for the Project as members of a Joint
Venture and in accordance with the terms and conditions of the RFP document and other
bid documents in respect of the Project, and
(C) It is a necessary condition under the RFP document that the members of the Joint
Venture shall enter into a Joint Bidding Agreement and furnish a copy thereof with the
Application.
In this Agreement, the capitalized terms shall, unless the context otherwise requires,
have the meaning ascribed thereto under the RFP.
2. Joint Venture
2.1 The Parties do hereby irrevocably constitute a Joint Venture (the “Joint Venture”)
for the purposes of jointly participating in the Bidding Process for the Project.
2.2 The Parties hereby undertake to participate in the Bidding Process only through this
Joint Venture and not individually and/ or through any other Joint Venture constituted
for this Project, either directly or indirectly.
3. Covenants
The Parties hereby undertake that in the event the Joint Venture is declared the selected
Bidder and awarded the Project, it shall enter into a PBMC with the Authority for
performing all its obligations as the Contractor in terms of the PBMC for the Project.
The Parties hereby undertake to perform the roles and responsibilities as described
below:
(a) Party of the First Part shall be the Lead member of the Joint Venture and shall
have the power of attorney from all Parties for conducting all business for and on
behalf of the Joint Venture during the Bidding Process and for performing all its
obligations as the Contractor in terms of the PBMC for the Project;
(b) Party of the Second Part shall be {the Member of the Joint Venture; and}
(c) Party of the Third Part shall be {the Member of the Joint Venture.}
The Parties do hereby undertake to be jointly and severally responsible for all obligations
and liabilities relating to the Project and in accordance with the terms ofthe RFP and
the PBMC, till such time as the completion of the Project is achieved under and in
accordance with the PBMC.
The Parties agree that the proportion of construction in the PBMC to be allocated
among the members shall be as follows:
First Party:
Second Party:
{Third Party:}
Further, the Lead Member shall itself undertake and perform at least 51 (fifty one) per
cent of the total length of the project highway if the Contract is allocated to the Joint
Venture.
7. Representation of the Parties
Each Party represents to the other Parties as of the date of this Agreement that:
(a) Such Party is duly organized, validly existing and in good standing under the laws of
its incorporation and has all requisite power and authority to enter into this Agreement;
(b) The execution, delivery and performance by such Party of this Agreement has been
authorized by all necessary and appropriate corporate or governmental action and a copy
of the extract of the charter documents and board resolution/ power of attorney in
favor of the person executing this Agreement for the delegation of power and authority
to execute this Agreement on behalf of the Joint Venture Member is annexed to this
Agreement, and will not, to the best of its knowledge:
(ii) violate any Applicable Law presently in effect and having applicability to it;
(iii) violate the memorandum and articles of association, by-laws or other applicable
organizational documents thereof;
(iv) violate any clearance, permit, concession, grant, license or other governmental
authorization, approval, judgment, order or decree or any mortgage agreement,
indenture or any other instrument to which such Party is a party or by which such Party
or any of its properties or assets are bound or that is otherwise applicable to such
Party; or
(v) create or impose any liens, mortgages, pledges, claims, security interests, charges
or Encumbrances or obligations to create a lien, charge, pledge, security interest,
encumbrances or mortgage in or on the property of such Party, except for encumbrances
that would not, individually or in the aggregate, have a material adverse effect on the
financial condition or prospects or business of such Party so as to prevent such Party from
fulfilling its obligations under this Agreement;
(c) this Agreement is the legal and binding obligation of such Party, enforceable in
accordance with its terms against it; and
(d) there is no litigation pending or, to the best of such Party's knowledge, threatened
to which it or any of its Affiliates is a party that presently affects or which would have
a material adverse effect on the financial condition or prospects or business of such Party
in the fulfillment of its obligations under this Agreement.
8. Termination
This Agreement shall be effective from the date hereof and shall continue in full force
and effect until Project completion or expiry of the “Defects Liability Period” whichever
is achieved under and in accordance with the PBMC, in case the Project is awarded to
the Joint Venture. However, in case the Joint Venture is either not pre- qualified for the
Project or does not get selected for award of the Project, the Agreement will stand
terminated in case the Applicant is not pre-qualified or upon return of the Bid Security
by the Authority to the Bidder, as the case may be.
9. Miscellaneous
9.2 The Parties acknowledge and accept that this Agreement shall not be amended by
the Parties without the prior written consent of the Authority.
IN WITNESS WHEREOF THE PARTIES ABOVE NAMED HAVE EXECUTED AND DELIVERED THIS
AGREEMENT AS OF THE DATE FIRST ABOVE WRITTEN.SIGNED, SEALED AND DELIVERED
Notes:
1. The mode of the execution of the Joint Bidding Agreement should be in accordance
with the procedure, if any, laid down by the Applicable Law and the charter documents
of the executant(s) and when it is so required, the same should be under common seal
affixed in accordance with the required procedure.
2. Each Joint Bidding Agreement should attach a copy of the extract of the charter
documents and documents such as resolution / power of attorney in favor of the person
executing this Agreement for the delegation of power and authority to execute this
Agreement on behalf of the Joint Venture Member.
3. For a Joint Bidding Agreement executed and issued overseas, the document shall be
legalized by the Indian Embassy and notarized in the jurisdiction where the Power of
Attorney has been executed.
APPENDIX-VI
INTEGRITY PACT
Draft Integrity Pact Format applicable for works having value of Rs. 5 Cr and above
( Division)
Tender No.
This Integrity Pact is made at on this day of 2022
BETWEEN
THE NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI) , Address at G-5 & 6, Sector -10,
Dwarka, New Delhi-110075, hereinafter referred to as “The Principal”, which expression
shall unless repugnant to the meaning or contract thereof include its successors and
permitted assigns.
and
hereinafter referred to as
“The Bidder/ Contractor/ Contractor/ Consultant” and which expression shall unless
repugnant to be meaning or context thereof include its successors and permitted assigns.
Preamble
Whereas, the Principal intends to award, under laid down organizational procedures
contract/s for PBMC O&M work of 4 Laning of Simga-Sargaon (PKG - II) of NH-200
section from Km 48+580 to Km 91+026 and Sargaon- Bilaspur (PKG - III) of NH-200
section from Km 91+026 to Km 126.525 section of Raipur-Bilaspur in the State of
Chhattisgarh. on Performance based Maintenance Contracts (PBMC) . The Principal
values full compliance with all relevant laws of the land, rulesof land, regulations,
economic use of resources and of fairness/ transparency in its relations with its Bidder(s)
and for Contractor(s)/Contractor(s)/Consultant(s).
And whereas in order to achieve these goals, the Principal will appoint an external
Monitor (IEM), who will monitor the tender process and the execution of the contract for
compliance with the Principles mentioned above.
And whereas to meet the purpose aforesaid, both the parties have agreed to enter into
this Integrity Pact (hereafter referred to as Integrity Pact) the terms and conditions of
which shall also be read as integral part and parcel of the Tender documents and contract
between the parties. Now, therefore, in consideration of mutual covenants stipulated in
this pact, the parties hereby agree as follows and this pact witnesses as under:-
(1) The Principal commits itself to take all measures necessary to prevent corruption
and to observe the following principle:-
(b) The Principal will, during the tender process treat all Bidder(s) with equity
and reason. The Principal will in particular, before and during the tender
process, provide to all Bidder(s) the same information and will not provide to
any Bidder(s) confidential/ additional information through which the Bidder(s)
could obtain an advantage in relation to the tender process or the contract
execution.
(c) The Principal will exclude all known prejudiced persons from the
process.
(2) If the Principal obtains information on the conduct of any of its employees which is
a criminal offence under the IPC/PC Act or any other Statutory Acts or if there be a
substantive suspicion in this regard, the Principal will inform the Chief Vigilance
Officer and in addition can initiate disciplinary actions as per its internal laid down
Rules/ Regulations.
(b) The Bidder(s)/ Contractor(s)/ Contractor(s)/ Consultant(s) will not enter with other
Bidders into any undisclosed agreement or understanding, whether formal or
informal. This applies in particular to prices, specifications, certifications, subsidiary
contracts, submission or non-submission or bids or any other actions to restrict
competitiveness or to introduce cartelization in the bidding process.
(c) The Bidder(s)/ Contractor(s)/ Contractor(s)/ Consultant(s) will not commit any
offence under the relevant IPC / PC. Act and other Statutory Acts; further the
Bidder(s)/ Contractor(s)/ Contractor(s)/ Consultant(s) will not use improperly for
purposes of completion or personal gain, or pass on to others, any information or
document provided by the Principal as part of the business relationship, regarding
plans, technical proposals and business details, including information contained or
transmitted electronically.
(f) The Bidder(s)/ Contractor(s)/ Contractor(s)/ Consultant(s) will not instigate third
persons to commit offences outlined above or be an accessory to such offences.
(g) The Bidder(s)/ Contractor(s)/ Contractor(s)/ Consultant(s) will not bring any outside
influence through any Govt. bodies/quarters directly or indirectly on the bidding
process in furtherance of his bid.
Article 3 Disqualification from tender process and exclusion from future contracts
(3) A transgression is considered to have occurred if the Principal after due consideration
of the available evidence concludes that “On the basis of facts available there are
no material doubts”.
(4) The Bidder/ Contractor/Contractor/Consultant will its free consent and without
any influence agrees and undertakes to respect and uphold the Principal’s absolute
rights to resort to and impose such exclusion and further accepts and undertakes not
to challenge or question such exclusion on any ground, including the lack of any
hearing before the decision to resort to such exclusion is taken. This undertaking is
given freely and after obtaining legal advice.
(5) The decision of the Principal to the effect that a breach of the provisions of this
Integrity Pact has been committed by the Bidder/ Contractor/Contractor/Consultant
shall be final and binding on the Bidder/ Contractor/Contractor/Consultant,
however, the Bidder/ Contractor/ Contractor/ Consultant can approach IEM(s)
appointed for the purpose of this Pact.
(6) On occurrence of any sanctions/ disqualification etc. arising out from violation of
integrity pact, Bidder/ Contractor/Contractor/Consultant shall not be entitled for
any compensation on this account.
(1) (a) If the Principal has disqualified the Bidder(s) from the tender process prior to the
award according to Article-3, the Principal shall be entitled to suspend the bidder
for participation in the tendering process for the works of MoRTH/NHAI/NHIDCL and
works under other Centrally Sponsored Schemes for a period of One Year from the
bid due date of this work apart from any other legal right that may have accrued to
the Principal.
(b) If the Principal has disqualified the Bidder(s) from the tender process prior to the
award according to Article-3, the Principal shall be entitled to forfeit the Earnest
Money Deposit/ Bid security or demand and recover the damages equivalent to
Earnest Money Deposit/ Bid Security apart from any other legal right that may
have accrued to the Principal.
(2) In addition to above, the Principal shall be entitled to take recourse to the relevant
provisions of the contract related to Termination of Contract due to
Contractor/Contractor/Consultant’s Default. In such case, the Principal shall be
entitled to forfeit the Performance Bank Guarantee of the
Contractor/Contractor/Consultant and/or demand and recover liquidated and all
damages as per the provisions of the contact/Contract agreement against
Termination.
(1) The Bidder declares that no previous transgression occurred in the last 3 years
immediately before signing of this integrity pact with any other Company in any
country conforming to the anticorruption/Transparency International (TI) approach
or with any other Public Sector Enterprise/Undertaking in India or any Government
Department in India that could justify his exclusion from the Tender process.
(2) If the Bidder makes incorrect statement on this subject, he can be disqualified
from the tender process or action for his exclusion can be taken as mentioned under
Article-3 above for transgression of Article-2 and shall be liable for compensation for
damages as per Article-4 above.
(2) The Principal will enter into agreements with identical conditions as this one with all
Bidders/Contractors/Contractor/Consultant and Subcontractors.
92
(3) The Principal will disqualify from the Tender process all Bidders who
do not signthis Pact violate its provisions.
The Principal has appointed (i) Smt. Gauri Kumar, IAS (Retd.) (ii) Sh. Ashish Bhauguna, IAS
(Retd.) and (iii) Sh. Animesh Chauhan (Ex-MD & CEO, Oriental Bank of Commerce) as
External Monitor for this Pact. The task of the Monitor is to review independently and
objectively, whether andto what extent the parties comply with the obligations under this
agreement
(1) The Monitor is not subject to instructions by the representatives of the parties and
performs his functions neutrally and independently. He reports to the Chairman, NHAI
/ MD NHIDCL / DG(RD)&SS/DGBR.
(2) The Bidder/Contractor/Contractor/Consultant accepts that the Monitor has the right to
access without restriction to all Project documentation of the Principal including that
provided by the Bidder/ Contractor/ Contractor/ Consultant. The Bidder/ Contractor/
Contractor/ Consultant will also grant the Monitor, upon his request and demonstration
of a valid interest, unrestricted and unconditional access to his Project documentation.
The same is applicable to Subcontractors.
(3) The Monitor is under contractual obligation to treat the information and documents of
the Bidder(s)/Contractor(s)/Subcontractors(s) with confidentiality. The Monitor has
also signed on „Non-disclosure of Confidential Information‟ and of „Absence of Conflict
of Interest‟. In case of any conflict of interest arising at a later date, the IEM shall
inform the Authority and recuse himself/herself from that case.
(4) The Principal will provide to the Monitor sufficient information about all meetings
among the parties related to the Project provided such meetings could have an impact
on the contractual relations between the Principal and the Bidder/Contractor/
Contractor/Consultant. The parties offer to the Monitor the option to participate in
such meetings.
(5) As soon as the Monitor notices, or believes to notice any transgression as given in Article-
2, he may request the Management of the Principal to take corrective action, or to take
relevant action. The monitor can in this regard submit non• binding recommendations.
Beyond this, the Monitor has no right to demand from the parties that they act in a
specific manner, refrain from action or tolerate action.
(6) The Monitor will submit a written report to the Authority within 8-10 weeks from the
date of reference or intimation to him by the Principal and, should the occasion arise,
submit proposals for correcting problematic situations.
93
(7) If the Monitor has reported to the Authority, a substantiated suspicion of an offence
under relevant IPC/PC Act or any other Statutory Acts, and the Authority has not, within
the reasonable time taken visible action to proceed against such offence or reported it
the Chief Vigilance Officer, the Monitor may also transmit this information directly to
the Central Vigilance Commissioner.
(8) The word 'Monitor' would include both singular and plural.
Article 9 Pact Duration
This Pact begins when both parties have legally signed it (in case of PBMC i.e. for projects
funded by Principal and consultancy services). It expires for the Contractor/Consultant
12 months after his Defect Liability Period is over or 12 months after his last payment
under the contract whichever is later and for all other unsuccessful Bidders 6 months
after this Contract has been awarded (In case of BOT projects). It expires for the
Contractor 24 months after his Contract period is over and for all other unsuccessful
Bidders 6 months after this Contract has been awarded. Any violation of the same would
entail disqualification of the bidder and exclusion from future dealings.
If any claim is made/lodged during this time, the same shall be biding and continue to
be valid despite the lapse of this pact as specified above, unless it is discharged
determined by Authority.
(1) This pact is subject to Indian Law, Place of performance and jurisdiction is the
Registered Office of the Principal, i.e. New Delhi.
(2) Changes and supplements as well as termination notices need to be made in writing.
(4) Should one or several provisions of this agreement turn out to be invalid, the
reminder of this agreement remains valid, in this case, the parties will strive to come
to an agreement to their original intentions.
(5) Issue like warranty / Guarantee etc. shall be outside the purview of IEMs.
(6) In the event of any contradiction between the Integrity Pact and its Annexure, the
clause in Integrity Pact shall prevail.
(7) Any dispute/differences arising between the parties with regard to term of this Pact,
any action taken by the Principal in accordance with this Pact or interpretation
thereof shall not be subject to any Arbitration.
(8) The actions stipulated in the integrity Pact are without prejudice to any other legal
action that may follow in accordance with the provisions of the extant law in force
relating to any civil or criminal proceedings.
94
(9) In witness whereof he parties have signed and executed this pact at the place and
date first done mentioned in the presence of following witnesses:-
(Office Seal)
Place
Date
Witness 1:
Witness 2:
95
SECTION – 5
GENERAL CONDITIONS OF
CONTRACT (GCC) AND CONTRACT
DATA
SECTION 5
GENERAL CONDITIONS OF CONTRACT (GCC)
TABLE OF CLAUSES
96
A. GENERAL
1. Definitions
1.1 Terms which are defined in the Contract Data but not defined in the Conditions
of Contract keep their defined meanings. Capital initials are used to identify defined
terms.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the
Bid.
Certificate of Completion is the document issued by the Engineer upon the full
completion of works, or parts thereof as applicable in accordance with Clause 47.
Compensation Events are those defined in Clause 40.
Contract is the Contract between the Employer and the Contractor to maintain the road
assets and to execute, complete, and maintain the Works. It consists of the documents
listed in Clause 2.3.
Contract Data defines the documents and other information, which comprise the
Contract.
Contractor is a person or corporate body whose Bid to carry out the Road
Maintenance Works and Activities has been accepted by the Employer.
Contractor’s bid is the completed Bidding Document submitted by the Contractor to the
Employer.
Contract Price is the price stated in the Letter of Acceptance and thereafter as
adjusted in accordance with the provisions of the Contract.
Days are calendar days; months are calendar months.
Defect is any part of the Maintenance Works and Activities not completed in accordance
with the Contract Specifications whether communicated by Employer or Engineer through
any Application, Portal, Website, email or physical inspection/correspondence or any
other method as described by the Employer before thecommencement of services.
Defects Liability Certificate is the certificate issued by the Engineer, after the Defects
Liability Period has ended and upon correction of Defects by the Contractor.
Defects Liability Period means the period so stipulated in the Contract Data, calculated
from the Completion Date, during which the Contractor remains responsible for the
rectification of any defect in the Works he has undertaken.
Emergency Works is a set of necessary and sufficient activities to reinstate the Road and
reconstruct its structure or right of way strip damaged as a result of natural phenomena
with imponderable consequences, such as strong storms, flooding and earthquakes. The
need for execution of Emergency Works is identified by the Engineer for starting of
execution of Emergency Works and shall also issue a Work Order.
Employer (or Authority) is the party as defined in the Contract Data, who employs the
Contractor to carry out the Works. The Employer may delegate any or all functions to a
97
person or body nominated by him for specified functions.
Engineer is the person named in the Contract Data (or any other competent person
appointed by the Employer and notified to the Contractor, to act in replacement of the
Engineer) who is responsible for supervising the execution of the Works and administering
the Contract on behalf of the Employer.
Equipment is the Contractor’s machinery and vehicles brought to the Site to execute the
Maintenance Works and Activities.
Deleted
“Key Personnel” means the positions (if any) of the Contractor’s personnel that are
stated in the Specification.
Initial rectification works are the set of civil works the Contractor needs to carry out to
bring a road to the required Service Level.
Intended Completion Date is the date, as given in contract data, on which it is intended
that the Contractor shall complete the Works as per scope under the contract. The
intended Completion Date may be revised only by the Engineer by issuing an Extension of
Time after approval from the Employer.
Letter of Acceptance means the formal acceptance of the Bid by the Employer.
Materials are all supplies, including consumables, used by the Contractor for incorporation
in the Maintenance Works and Activities.
Maximum Response Time means the maximum permissible time within which remedial
action must be completed prior to a defect exceeding the permissible tolerance. Maximum
Response Time commences from the time of earliest detection of the defect by
(i) observation of the defect by the Contractor, or (ii) notification of the defect by the
Engineer, or (iii) intimation of the defect by a road user.
Notice to Proceed (also commencement notice/letter) means the notice issued by the
Engineer / Employer to the Contractor to proceed with the work after signing of the
contract pursuant to Clause 32.1 of ITB.
Periodic Maintenance [PM] Works consists of providing a bituminous wearing course on an
existing bituminous surface, It may be preceded by a levelling course to correct the
transverse profile of the existing road. For rigid pavements, either partially bonded
overlay or fully bonded overlay shall be considered as PM work. Periodic Maintenance
works also includes Road Markings, provision of reflective Road Studs, Gravel filling to
match the Shoulder level with carriageway after laying renewal coat PM Works are specific
works defined in the Contract Data.
Permissible Tolerance means the maximum permissible amount or quantity of a defect
in road-asset condition that will not be exceeded at any time. If any defect exceeds the
permissible tolerance, it shall be treated as “non-compliance” and the Contractor shall be
paid in accordance with the relevant provisions in this contract.
Project Manager is a person appointed by the Contractor who is in charge of managing
all activities o f the Contractor under the Contract. He is also the Contractor’s
Representative for the purpose of this Contract.
Rectification Standards
The Contractor shall maintain the Road Assets in proper condition that comply with the
Road Maintenance Standards and ensure road users safety and comfort. The maintenance
activities shall be so planned that the defects are repaired well before they reach
maximum condition as per the permissible tolerance
Deleted
Road means the Road or package of roads in network or scattered for which the
Maintenance Works and Activities are to be carried out under the Contract.
“Road Assets” include the following:
i) Main carriageway with shoulders (paved and/or earthen), medians, slip roads, service
roads;
ii) Road embankment including slopes, protection works, kerbs and chute drains;
iii) Roadway in cutting including slopes protection works, drains;
iv) Culverts, Bridges, Over/Underpasses, retaining walls, Guide bunds, Floor protection
works;
v) Road signs, road markings, road delineators, guard rails, safety barriers, railings,
fencings, parapets, kilometre stones, 200 m stones, road boundary stones;
vi) All types of drains, trees, plantations and erosion control measures;
vii) Road land;
viii)Any other project facility or asset forming integral part of the road(s).
Road inventory and condition data reports are those, are compiled during inventorisation
of road assets by the contractor during the inspection jointly withEngineer/ Employer
within 01 months from the start date about the condition of road, Cross Drainage works
and road signs etc. at the site. It shall also include all surveys and reports as defined in
Clause 5.1 of Section-7, Part-I.
The Road Management Office is the location indicated by the Contractor from which the
Project Manager operates, and where the Contractor shall receive notifications.
Road Maintenance Standards is the collective term for parameters which define the
condition in which the road assets are required to be maintained and other requirements
regarding safety and quality of works to be complied with by the Contractor.
Road Maintenance Works and Activities to be carried out by Contractor shall include:
Maintenance of the road assets and incident management specified in the BOQ and section
7 and executing other items of road maintenance works as ordered by the Engineer.
Routine Maintenance of Road assets means regular maintenance of all road assets in
respect of Roads under the Contract to the Road Maintenance Standards and for the period
specified in the Contract Data.
Site is the area defined as such in the Contract Data, where maintenance works are
to be executed.
Specifications means the Specifications of the Maintenance Works including the Road
Maintenance Standards as per the Contract.
Start Date is the date notified by the contractor to the Engineer after issuance of
Commencement. It is the date when the Contractor actually commence execution of the
Works. In no case shall the Start Date shall be beyond 15 days
after the date of issue of the Notice to proceed.
Service Level means the defined condition in which the road assets are to be maintained
by the Contractor as per Annexure-E.
Sub-Contractor is a person or corporate body who has a Contract with the Contractor to
carry out a work under the Contract, which includes part of the agreed scope of works at
the Site with due approval of Authority / Employer.
Temporary Works are the temporary works designed, constructed, installed and removed
by the Contractor that are necessary & incidental for implementation for Scope of Work as
defined in the Contract or for site regulations and safety.
Time for Completion means the duration for completing the execution of maintenance
works and passing the tests on completion of the Works or any Section or part thereof as
stated in the Contract Data or as extended by the Engineer by issuing an Extension of Time
after the approval from the Employer.
Variation is an instruction given by the Engineer in writing which varies the scope of
Maintenance Works as defined in Clause 6.2 of Part-II of Section-7.
Work Order is an order issued by the Engineer to the Contractor for execution of certain
Emergency works, specifying the time limits which may be in variance with the approved
programme or in variation to the scope of work depending upon the site requirement.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male
also means female or neuter and the other way around. Headings have no significance.
Words have their normal meaning under the language of the Contract Unless specifically
defined. The Engineer will provide instructions clarifying queries about these Conditions
of Contract.
2.2 If part completion is specified in the Contract Data, references in the Conditions
of Contract to the Works, the Completion Date and the Intended Completion Date apply
to any part of the Works (other than references to the Completion Date and Intended
Completion Date for the whole of Works).
2.3 The following documents shall be deemed to form and be read and construed
as part of the Contract. In case any ambiguity or discrepancy is noted, then the Contract
shall be interpreted in the following order of priority:
i) Agreement;
ii) Notice to Proceed with the Work;
iii) Letter of Acceptance;
iv) Contractor’s Bid;
v) Contract Data;
vi) General Conditions of Contract;
vii) Road Maintenance Standards and Specifications for Road
Maintenance Works, Part I and Part Il.
viii) Priced Bill of Quantities; and
ix) Any other documents listed in the Contract Data.
4. Engineer’s Decisions
4.1 The Employer shall designate and notify to the Contractor in writing the name
of the Engineer.
4.2 Except where otherwise specifically stated, the Engineer will decide
contractual matters between the Employer and the Contractor in the role representing
the Employer. The Engineer shall have no authority to relieve the Contractor of any of
his obligations under the Contract.
5. Delegation
5.1 The Engineer, duly informing the Employer, may delegate any of his dutiesand
responsibilities to his Team leader, after notifying the Contractor and may cancel any
delegation under intimation to the Contractor.
6. Communications
6.1 Communications between parties that are referred to in the Conditions shall be
effective only when in writing. A notice shall be effective only when it is delivered as per
Indian Law.
7. Subcontracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in
Contract Data, with the approval of the Employer in writing. Subcontracting shall neither
alter the Contractor’s obligations, nor relieve the Contractor from any liability or
obligation under the Contract.
7.2 The Contractor shall not be required to obtain any consent from the Employer
for:
a) the sub-contracting of any part of the Works for which the Sub-
Contractor is named in the Contract;
b) the provision for labour, or labour component;
c) the purchase of Materials which are in accordance with the standards
specified in the Contract.
7.3 Beyond what has been stated in Clauses 7.1 and 7.2, if the Contractor proposes
sub-contracting of any part of work during execution of the Works, because of some
unforeseen circumstances to enable him to complete the Works as per terms of the
Contract, the Employer will consider the following before according approval:
a) The Contractor shall not sub-contract the whole of Works.
b) The Contractor shall not sub-contract any part of the Work without prior
consent of the Employer. Any such consent shall not relieve the Contractor
from any liability or obligation under the Contract and he shall be fully
responsible for the acts, defaults and neglects of any of his sub-
Contractor, his agents or workmen as if they were the acts, defaults or
neglects of the Contractor, his agents and workmen.
7.4 The Engineer should satisfy himself before recommending to the Employer
whether
a) the circumstances warrant such sub-contracting; and
b) the sub-Contractor so proposed for the Work possess the experience,
qualifications and equipment necessary for the job proposed to be
entrusted to him in proportion to the quantum of Works to be sub-
contracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other Contractors, public
authorities, utilities, and the Employer between the dates given in the Scheduleof Other
Contractors, as referred to in the Contract Data. The Contractor shall also provide
facilities and services for them as described in the Schedule. The Employer may modify
the Schedule of Other Contractors and shall notify the Contractor of any such modification.
The Contractor shall cooperate in such situations as well.
8.2 The Contractor should take up the works in convenient reaches as decided by
the Engineer to ensure that there is least hindrance to the smooth flow of traffic including
movement of vehicles and equipment of other Contractors till the completion of Works.
9.2 The Contractor shall use the equipment identified in the bid along with
competent operators and adequate stock of spares for smooth operations.
9.3 If the Engineer asks the Contractor to remove a person who is a member of the
Contractor’s staff or work force, stating the reasons, the Contractor shall ensure thatthe
person leaves the Site within seven days and has no further connection with the Works
under the Contract.
9.4 The Contractor shall establish, within his own organizational structure, a
planning unit, laboratory unit etc., staffed with suitably qualified personnel. The team
will be headed by a Project Manager who will be assisted by his representatives, i.e. Site
Engineer, Survey Engineer, Material Engineer as defined ITB. The task of this unit will be:
9.5 To plan, and to verify continuously the degree of compliance by the Contractor
with the specified Road Maintenance Standards and report the same to the Engineer in the
format acceptable to the Engineer.
9.5.1 To maintain and update the road condition inventory regularly.
9.5.2 To assist the Engineer in verification of the compliance.
9.6 The Contractor’s planning unit mentioned under Sub-clause 9.4 shall report the
level of compliance with the required Service Levels in the standard formats acceptable
to the Engineer.
13. Insurance
13.1 The Contractor at his cost shall provide, in the joint names of the Employer and
the Contractor, insurance cover from the Start Date to the completion of defect liability
period, in that amounts and deductibles stated in the Contract Data for the following
events which are due to the Contractor’s risks:
a) Loss of or damage to the Works and Materials
b) Loss of or damage to Equipment
c) Loss of or damage to property (except the Works Materials and
Equipment) in connection with the Contract
d) Third Party Liability Insurance
e) Automobile Liability Insurance
f) Workers‟ Compensation
g) Employer’s Liability
h) Other Insurances
13.2 Insurance policies and certificates for insurance shall be delivered by the
Contractor to the Engineer for the Engineer’s approval before the Start Date. All such
insurance shall provide for compensation to be payable in Indian Rupees to rectify the loss
or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required,
the Employer may affect the insurance which the Contractor should have provided and
recover the premiums the Employer had paid from payments otherwise due to the
Contractor or, if no payment is due, the payment of the premiums shall be a debt due
from the Contractor.
13.4 Alterations to the terms of insurance shall not be made without the approval of
the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies. The
Contractor shall ensure that wherever applicable, its Sub-Contractor(s) shall take out and
maintain in effect adequate insurance policies for their personnel and vehicles and for
works executed by them under the Contract unless such Sub-Contractor(s) is/are covered
by the policies taken out by the Contractor.
16.2 The Contractor [Class I Local Supplier/ Class II Local Supplier/ Non Local Supplier]
shall submit an undertaking to ensure minimum Local Content in the Project Highway of
at least [50% / 20%] duly complying with the provisions of Department for Promotion of
Industry and Internal Trade, Ministry of Commerce and Industry, Government of India
Order No. P-45021/2/2017-PP (BE- II) dated September 16, 2020, as amended or modified
till Bid Due Date and the provisions under Rule 144(xi) of GFR, 2017.
17. The Works to be completed by the Intended Completion Date
17.1 The Contractor shall commence execution of the Maintenance Works and
Activities on the Start Date. The Contractor shall conduct NSV, FWD, Condition survey and
inspections jointly with Engineer/ Employer within 01 months from the start dateand
finalize the necessary maintenance measures (wherever required to achieve Service Level)
on the highway pavement and structures to be completed by the Contractor as part of
Initial Rectification (IR) within 06 months from the date of start. The contractor shall carry
out the scheduled Works in accordance with the Programme as submitted,and updated
with the approval of the Engineer, and complete them by the Intended
Completion Date.
18.2 The Contractor shall submit Specifications and Drawings showing the proposed
Permanent/Temporary Works to the Engineer, who is to approve them if they comply with
Specifications and drawings.
18.3 The Contractor shall be responsible for design of all Permanent/ Temporary Works.
18.4 The Engineer’s approval shall not alter the Contractor’s responsibility for design
of the Permanent/ Temporary Works.
18.5 The Contractor shall obtain approval of third parties to the design of Permanent/
Temporary Works submitted to the Engineer.
18.6 All Drawings prepared by the Contractor for the execution of temporary or
permanent Works, are subject to prior approval by the Engineer before their use.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly
discovered on the Site is the property of the Employer. The Contractor shall notify the
Engineer of such discoveries and carry out the Engineer’s instructions for dealing with
them.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to the
maintenance works which comply with the applicable laws where the Site is located.
23.2 The Contractor shall permit the Engineer/Employer to inspect the Contractor’s
contemporary records in respect of invoice of bitumen, cement, aggregatesand steel, if so
desired by the Engineer.
24.1.2 The Parties agree to use their best efforts for resolving all Disputes arising under
or in respect of this Agreement promptly, equitably and in good faith, and further agree
to provide each other with reasonable access during normal business hours to all non-
privileged records, information and data pertaining to any Dispute.
Failing mediation by the Engineer or without the intervention of the Engineer, either Party
may require such Dispute to be referred to the Dispute Resolution Board (“DRB”)in
accordance with the procedure as below:
(1) The Board shall comprise of three Members having experience in the field of
construction or have been involved in the Works related to construction and with the
interpretation of contractual documents. One Member shall be selected by each of the
Authority and the Contractor from the list maintained by NHAI hosted on its website
(www.nhai.gov.in). In the event the parties fail to select the member within 28 days of
the date of the signing of Agreement, in that eventuality, upon the request of either or
both parties such Member shall be selected by SAROD within 14 days. The third Member
shall be selected by the other two members from the same list. If the two Members
selected by or on behalf of the parties fail to select the third Member within 14 days after
the later of their selections, then upon the request of either or both parties such third
Member shall be selected by SAROD within 14 days. The third Member shall serveas
Chairman of the Board
(2) The Board shall be constituted when each of the three Board Members has signed a
Board Member's declaration of Acceptance as required by the DRB's rules and procedures
(which, along with the declaration of acceptance form, are attached as Annexure
herewith).
(3) In the event of death, disability, or resignation of any Member, such Member shall be
replaced in the same manner as the Member being replaced was selected. If for any other
reason, a Member fails or is unable to serve, the Chairman (or failing the action of the
Chairman then either of the other Members) shall inform the Parties and such non- serving
Member shall be replaced in the same manner as the Member being replaced was selected.
Any replacement made by the parties shall be completed within 28 days after the event
giving rise to the vacancy on the Board, failing which the replacement shall be made by
SAROD in the same manner as described above. Replacement shall be considered complete
when the new Member signs the Board Member's Declaration of Acceptance. Throughout
any replacement process, the Members not being replaced shall continue to serve and the
Board shall continue to function and its activities shall have the same force and effect as
if the vacancy had not occurred, provided, however, that the Board shall not conduct a
hearing nor issue a decision until the replacement is completed
(4) If either the Authority or the Contractor is dissatisfied with any decision of the Board,
and/or if the Board fails to issue its decision within 56 days after receipt of allthe
pleadings (along with the supporting documents) of the parties by the Chairman of the
Board or any extension mutually agreed upon by the Authority and the Contractor, in such
a case, either the Authority or the Contractor may, within 28 days after his receipt of the
decision, or within 28 days after the expiry of the said period, as the case maybe, give
notice to the other party, with a copy for information to the Engineer, of his intention to
refer the matter to the Conciliation Committee of Experts (CCIE) of the Authority (if
available) for Conciliation/amicable settlement.
(5) It is mandatory to refer all the disputes to DRB before issuance of completion
certificate and satisfactory completion of punch list items. No dispute shall be entertained
after completion of aforementioned date.
(6) If the Board has issued a decision to the Authority and the Contractor within the said
56 days or any extension mutually agreed upon by the Authority and the Contractor and
no notice of intention to commence Conciliation by the Conciliation Committee of Experts
(CCIE) of the Authority for Conciliation/ amicable settlement as to such dispute has been
given by either the Authority or the Contractor within 28 days after the parties received
such decision from the Board, the decision shall become final and binding upon the
Authority and Contractor.
(7) Whether or not it has become final and binding upon the Authority and the Contractor,
a decision shall be admissible as evidence in any subsequent dispute resolution procedure,
including any arbitration or litigation having any relation to the dispute to which the
decision relates.
(8) All decision of DRB which have become final and binding or till they have been
reversed in subsequent conciliation/Arbitration process shall be implemented by the
parties forthwith. Such implementation shall also include any relevant action of the
Engineer
(9) If during the Contract Period, the Authority and the Contractor are of the opinion that
the Disputes Resolution Board is not performing its functions properly, the Authority and
the Contractor may together disband the Disputes Resolution Board and reconstitute it. In
that case, a new board shall be selected in accordance with the provisions applying to the
selection of the original Board as specified above, except that words "within 28 days after
the signing of this Contract Agreement" shall be replaced by the words "within
28 days after the date on which the notice disbanding the original Board became effective
(10) The Authority and the Contractor shall jointly sign a notice specifying that the Board
shall stand disbanded with effect from the date specified in the notice. The notice shall
be posted by email to each Member of the Board. A Member shall be deemed to have
received the e mail even if he refuses to have received the same.
(11) All other terms and conditions of the original Agreement shall remain
unaltered/unaffected and the parties shall remain bound by terms and conditions as
contained therein. Except for providing the services required hereunder, the Board
Members shall not give any advice to either party or to the Engineer concerning conduct
of the Works.
The Board Members:
(a). Shall have no financial interest in any party to the Contract Agreement, or the
Engineer, or a financial interest in the Contract, except for payment for services on the
Board.
(b). Shall have had no previous employment by, or financial ties to, any party to the
Contract Agreement, or the Engineer, except for fee based consulting services/advisers
on other projects, and/or be Retired Government Officers (not connected in whole or part
with the project), all of which must be disclosed in writing to both parties prior to
appointment to the Board.
(c). Shall have disclosed in writing to both parties prior to appointment to the Board any
and all recent or close professional or personal relationships with any director, officer,
or employee of any party to the Contract Agreement, or the Engineer, and any and all
prior involvement in the project to which the Contract relates;
(d). Shall not, while Board member, be employed whether as a consultant or adviser or
otherwise by either party to the Contract Agreement, or the Engineer, except as a Board
Member, without the prior consent of the parties and the other Board Members,
(e). Shall not, while a Board Member, engage in discussion or make any agreement with
any party to the Contract Agreement, or with the Engineer, regarding employment
whether as a consultant or otherwise whether after the Contract is completed or after
service as a Board Member is completed
(f). Shall remain and be impartial and of the parties and shall disclose in writing to the
Authority, the Contractor and one another any fact or circumstance which might be such
as to cause either the Authority or the Contractor to question the continued existence of
the impartiality and independence required of Board Members; and
(a). Furnish to each Board member one copy of all documents which the Board may
request including Agreement, progress reports and other documents pertinent to the
performance of the Contract Agreement.
(b). In cooperation with the Authority, coordinate the site visits of the Board, including
conference facilities, and secretarial and copying service.
4. The Board shall begin its activities following the signing of a Board Member's
Declaration of Acceptance by all three Board Members, and it shall terminate these
activities as set forth below:
(a). The Board shall terminate its regular activities when either
5. Board Members shall not assign or subcontract any of their work under these Rules
and Procedures.
6. The Board Members are not employees or agents of either the Authority or the
Contractor.
7. Payments to the Board Members for their services shall be governed by the following
provisions: (a). Each Board Member will receive payments as follows:
i. A retainer fee per calendar month as specified in the schedule of fee made part of this
Schedule and its revision from time to time. This retainer fee shall be considered as
payment in full for:
(A). Being available, on 7 days' notice, for all hearings, Site Visits, and other meetings of
the Board.
(B).Being conversant with all project developments and maintaining relevant files.
(C).All offices and overhead expenses such as secretarial services, photocopying and office
supplies (but not include telephone calls, faxes and telexes) incurred in connection with
the duties as a Board Member
ii. A daily fee as specified in the schedule of fee in respect of fee for site visit & meeting,
fee for meeting/ hearing not at site and extra charges for days (max. of 02days for
travel on each occasion) other than hearing/meeting days.
iii. Expenses, in addition to the above, all reasonable and necessary travel expenses
(including economy class air fare, subsistence, and other direct travel expenses) Receipts
for all expenses in excess of Rs. 2000/- (Rupees Two Thousand only) shall be provided.
iv. Reimbursement of any taxes that may be levied on payments made to the Board
Member pursuant to this paragraph 7.
(b). The retainer fee and other fees shall remain fixed for the period of each Board
Member’s term until revised by Employer. (c). Phasing out of monthly retainer fee.
Beginning with the next month after the completion certificate (or, if there are more than
one, the one issued last) has been issued, the Board members shall receive only one-third
of the monthly retainer fee till next one year. Beginning with the next month after the
Board has terminated its regular activities pursuant to paragraph 4(a) above, the Board
members shall no longer receive any monthly retainer fee.
(d). Payments to the Board Members shall be shared equally by the Authority and the
Contractor. The concerned field unit / Project Implementation Unit (PIU) of Authority
shall pay members‟ invoices within 30 calendar days after receipt of such invoices and
shall invoice the Contractor for one-half of the amounts of such invoices. The Contractor
shall pay such invoices within 30 days‟ time period after receipt of such invoices. 8.
Board Site Visits:
(a). The Board shall visit the Site and meet the representatives of the Authority, the
Contractor and the Engineer at regular intervals, at times of critical construction events,
at the written request of either party, and in any case not less than 6 times in any period
of 12 months. The timing of Site visits shall be as agreed among the Authority, the
Contractor and the Board, but failing agreement shall be fixed by the Board.
(b). Site visits shall include an informal discussion of the status of the construction of
the Works. Site visits shall be attended by personnel from the Authority, the Contractor
and the Engineer
(c). At the conclusion of each Site visit, the Board shall prepare a report covering its
activities during the visit and shall send copies to the parties and to the Engineer.
(a) If either party objects to any action or inaction of the other party or the Engineer,
the objecting party may file a written Notice of Dispute to the other party with a copy
to the Engineer stating that it is given pursuant to the Agreement and state clearly and
in details the basis of the dispute.
(b) The party receiving the Notice of Dispute will consider it and respond to it in writing
within 14 days after receipt.
(C) This response shall be final and conclusive on the subject, unless a written appeal to
the response is filed with the responding party within 10 days after receiving the response
and call upon Engineer to mediate and assist the parties in arriving an amicable settlement
thereof. Both parties are encouraged to pursue the matter further to attempt to settle
the dispute.
(d) If the Engineer receiving the Notice of Dispute fails to provide a written response
within 14 days after receipt of such Notice or failing mediation by Engineer, either party
may require such dispute to be referred to the Board, either party may refer the dispute
to the Board by written Request to the Board. The Request for decision shall state clearly
and in full detail the specific issues of the dispute (s) to be considered by Board.
Chairman of the Board, with copies to the other Board Members, the other party, and
the Engineer, and it shall state that it is made pursuant to this Agreement.
(e) When a dispute is referred to the Board, and the Board is satisfied that the dispute
requires the Board's assistance, the Board decide when to conduct a hearing on the
dispute. The Board may request that written documentation and arguments from both
parties be submitted to each Board Member before the hearing begins. The parties shall
submit insofar as possible agreed statements of the relevant facts.
(f) During the hearing, the Contractor, the Authority, and the Engineer shall each have
ample opportunity to be heard and to offer evidence. The Board's decision for resolution
of the dispute will be given in writing to the Authority, the Contractor and the Engineer
as soon as possible, and in any event not more than 56 days or any mutually extended
period between the Authority and the Contractor. The time period of 56 days of issuance
of DRB decision will reckon/start from the day of first hearing that begins after submission
of complete pleadings (including supporting documents, if any) by the parties.
(a) Normally hearings will be conducted at the Site, but any location that would be more
convenient and still provide all required facilities and access to necessary documentation
may be utilized by the Board. Private session of the Board may be heldat any cost
effective location convenient to the Board. Video recordings of all hearings shall invariably
be made.
(b) The Authority, the Engineer and the Contractor shall be given opportunity to have
representatives at all hearings. Parties should restrain to bring any Advocate/Law Firm
during DRB hearings.
(c) During the hearings, no Board Member shall express any opinion concerning the merit
of the respective arguments of the parties.
(d) After the hearings are concluded, the Board shall meet privately to formulate its
decision. The private meeting (s) of the Board shall not exceed 3 sittings. All Board
deliberations shall be conducted in private, with all Members' individual views kept strictly
confidential. The Board's decisions, together with an explanation of its reasoning shall be
submitted in writing to both parties and to the Engineer. The decision shall be based on
the pertinent Contract provisions, applicable laws and regulations and thefacts and
circumstances involved in the dispute.
(e) The Board shall make every effort to reach a unanimous decision. If this proves
impossible the majority shall decide and the dissenting Member may prepare a written
minority report together with an explanation of its reasoning for submission to both
parties and to the Engineer.
11. In all procedural matters, including the furnishing of written documents and
arguments relating to disputes, site visits and conduct of hearings, the Board shall have
full and the final authority. If a unanimous decision on any such matter proves impossible,
the majority shall prevail.
12. After having been selected and where necessary approved each Board Member shall
sign two copies of the following declaration and make one copy available each to the
Authority and to the Contractor.
(b). The provisions of Agreement and Dispute Resolution Board‟s rules and procedure
provided for establishment and operation of Dispute Resolution Board (DRB).
(c). The undersigned has been selected to serve as a Board Member on said Board; NOW
THEREFORE, the undersigned Board Member hereby declares as follows:
1. I accept the selection as a Board Member and agree to serve on the Board and to be
bound by the provisions of Contract Agreement and rules and procedure provided for
establishment and operation of Dispute Resolution Board (DRB).
2. With respect to paragraph 1 of Dispute Resolution Board’s Rules and Procedure. said
Annex A, I declare (a). that I have no financial interest of the kind referred to in
subparagraph (a): (b). that I have had no previous employment nor financial ties of the
kind referred to in subparagraph (b); and (c). that I have made to both parties any
disclosures that may be required by subparagraphs (b) and (c).
3. I declare that I have no. of Arbitrations (list enclosed) and no. of DRBs (list enclosed)
in progress and that I will give sufficient time for the current assignment.
BOARD MEMBER (insert
name of Board Member) Date:
Schedule of expenses and fees payable to the Member (s) of Dispute Resolution Board
(DRB)
The fee and other expenses payable to the Members of DRB shall be as under:-
2 (i) Fee for site visit or meetings at site 25,000/- per day
(ii) Fee for meetings/ hearings not at site 10,000/- per day
3 Travelling expenses Economy class by air, AC First Class by
train and AC Taxi by road
4 Lodging and Boarding Rs 15,000/- per day (Metro Cities) or
Rs 10,000/- per day (in other Cities) or
Rs 5,000/- per day (own arrangement)
Notes:
(i) Lodging, boarding and travelling expenses will be allowed only for those members
who are residing 100 kms away from the place of meeting.
(ii) Delhi, Mumbai, Chennai, Kolkata, Bangalore and Hyderabad shall be considered as
Metro Cites.
(iii) The above schedule of fee and expenses shall be applicable on or after the date of
issue of this circular.
(iv) The expenses are to be shared equally by the parties i.e. Authority and Contractor.
The decision(s) of the Dispute Resolution Board shall be binding on both parties who
shall promptly give effect to unless and until the same is revised/modified, as hereinafter
provided, in a Conciliation/Arbitral Tribunal.
24.2 Conciliation:
If either the Authority or the Contractor is dissatisfied with any decision of the DRB,
and/ or if the DRB is unable to resolve the dispute, either Party may refer the Dispute to
Arbitration in accordance with the provisions of Clause 24.3 but before resorting to such
Arbitration, the parties agree to explore conciliation by the Conciliation Committees of
Experts set up by the Authority in accordance with the procedure decided by the panel
of such experts and notified by the Authority on its website including its subsequent
amendments. In the event of the Conciliation proceedings being successful, the parties to
the dispute would sign the Written Settlement Agreement and the conciliators would
authenticate the same. Such Settlement Agreement would then be binding on the parties
in terms of Section 73 of the Arbitration Act. In case of failure of the Conciliation process
even at the level of the Conciliation Committee, either party may refer the Dispute to
Arbitration in accordance with the provisions of Clause 24.3.
24.3 Arbitration:
In case of Dispute or difference arising between the Employer and a contractor relating
to any matter arising out of or connected with this agreement, such disputes or difference
shall be settled as set forth below:
24.4 The arbitrators shall make a reasoned award (the “Award”), Any Award made in any
arbitration held pursuant to this Clause shall be final and binding on the Parties as from
the date its is made and the contractor and the Authority agree and undertake to carry
out such Award without delay.
24.5 The Contractor and the Authority agree that an Award may be enforced against the
Contractor and/or the Authority, as the case may be, and their respective assetswherever
situated.
24.6 This Agreement and the rights and obligations of the Parties shall remain in full force
and effect, pending the Award in any arbitration proceedings hereunder.
25. Programme
25.1 The Contractor shall submit to the Engineer for approval a work programme
within period specified in the contract data showing the requirement of manpower,
machinery and material along with required cash flow inputs, general methods,
arrangements, order, and timing etc. for all the maintenance works and activities.
25.2 The Engineer may issue the work order for Emergency Works in stages specifying
the time limit for the same as and when required except the performance- based
maintenance items. To be clear, no separate work orders shall be issued for Routine
Maintenance/Periodic Maintenance/Initial rectification works.
25.3 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of progress achieved on the timing of the
remaining Works, including any changes to the sequence of activities.
25.4 The Contractor shall submit to the Engineer for approval an updated Programme
at intervals. If the Contractor does not submit an updated Programme within
this period, the Engineer may withhold the amount stated in the Contract Data from the
next payment certificate and continue to withhold this amount until the next payment
after the date on which the overdue Programme has been submitted.
25.5 The Engineer’s approval of the Programme shall not alter the Contractor’s
obligations. The Contractor may revise the Programme and submit it to the Engineer again
at any time. A revised Programme shall show the effect of Variations and Compensation
Events.
26.2 The Engineer, within 14 days of receiving full justification from the Contractor
for extension of Intended Completion Date, will refer to the Employer his
recommendation. The Employer shall, in not more than 21 days from the date of receipt of
Engineer’s recommendation, communicate to the Engineer the acceptance or otherwise. The
Engineer shall convey the decision of the Employer to the Contractor.
28.2 The Engineer shall record the business of management meetings and provide
copies of the record to those attending the meeting including Authority. The responsibility
of the parties for actions to be taken shall be decided by the Engineer either during the
management meeting or after the management meeting and to be intimated in writing to
all those who attended the meeting.
28.3 Engineer and Contractor will mandatorily hold a meeting with the Employer at
least once in a month.
C. QUALITY CONTROL
30.1 If the Engineer instructs the Contractor to carry out a test not specified in the
Specifications to check whether any work has a Defect and the test shows that it does,
the Contractor shall pay for the testing charges and for any number of samples. Otherwise,
the Employer shall pay for the testing charges.
31.2 If any defects including shrinkage, cracks, other faults appear in the works
within the period specified hereunder rectification of defects as per required
specifications and good industry practice may be undertaken. In case defects stillprevails,
the Engineer shall give notice to the Contractor of any defects before the endof the
Defects Liability Period after issue of “Taking over” certificate. The Defects Liability
Period shall be extended for as long as the defects remain to be corrected.
31.3 Every time notice of a defect is given, the Contractor shall correct the notified
defect as per relevant specifications and good industry practice at his own cost within the
length of time specified in the Engineer’s notice.
31.4 The Defects Liability Period shall be as given in the Contract Data, counted from
the Date of Completion stated in the Certificate of Completion issued in pursuance of
Clause 47. The defect liability period is not applicable for works of routine maintenance
such as pot holes/ patch repairs/ruts repairs under performance based BOQ item.
31.5 If during the Defects Liability Period any defect is found in the design,
engineering, materials and workmanship of the Works and Services executed by the
Contractor, then the Contractor shall promptly, in consultation and agreement with the
Engineer, appropriately remedy such defects at its cost, or repair, replace or otherwise
make good (as the Contractor shall, at its discretion, determine) such defects as well as
any damage to the Road caused by such defects.
31.6 The Contractor’s obligations under this Clause 31 shall not apply to:
a) any material that is supplied by the Employer, and normally consumed in
maintenance, or have a normal life shorter than the Defects Liability Period
stated herein;
b) any design, Specification or other data, supplied or specified by or on behalf of the
Employer or any matter for which the Contractor has disclaimed responsibility herein;
31.7 The Employer shall offer the Contractor all reasonable opportunity to inspect
the defect(s) Noticed, as well as provide all necessary access to the Facilities and the Site
to enable him to perform his obligations under this Clause 31.
The Contractor may remove from the Site any Plant and Equipment or any part of the
Facilities that are defective, if the nature of the defect, and/or any damage to the
Facilities caused by the defect, is such that repairs cannot be expeditiously carried out
at the Site.
32. Work to be executed on Risk & Cost of Contractor for Uncorrected Defects
32.1 If the Contractor fails to correct a Defect as per relevant specifications and
good industry practice, to the satisfaction of the Engineer, within the time specified in
the Engineer’s notice, the Engineer will assess the cost of having the Defect corrected.
The Contractor will pay to the Employer this amount or the Engineer may deduct such
amount from any sums due to the Contractor, on correction of the Defect together with
20 percent additional costs as the damages.
32.2 In case of any non-compliance/delayed compliance of maintenance standards,
the damages/reduction in payment shall be applicable as provided under Road
Maintenance Standards Part – I.
D. COST CONTROL
In case of Emergency Works, the Engineer / Employer shall provide the details of items
to be executed along with quantities, rates and amounts. The payment will be made as
per actual work executed and measured at site.
In case of variation in quantities, the payment will be made as per agreement rates i.e.
applicable SOR adjusted with quoted and accepted percentage of the Bidder on overall
indicated amount of the Work by the Employer. If necessity of additional work items is
warranted the payment for such work will be admissible at applicable SOR/ Market rates
adjusted with quoted and accepted percentage of the Bidder on overall indicative amount
of work by the Employer.
In case of Routine Maintenance for Electric lights at locations of Project Highway
Stretch(es), the Electricity consumption Bill (s) as raised by the concerned Utility Providing
Agencies in the name of Employer will be paid by the Employer, however all such utility
services assets are to be maintained by the Contractor in the serviceable condition.
33.3 Routine Maintenance Works shall be measured and billed separately and will be
remunerated by lump-sum amount after making adjustments for deductions for lapses in
maintaining the defined service levels during the entire period of contract as stated in the
BOQ.
33.4 Initial rectification works and Periodical Maintenance works are to be paid on the
basis of the lengths completed in accordance with the approved programme.
33.5 Emergency works will be taken up and paid on the basis of work order issued by the
Engineer/ Employer which will include quantities of various items to be executed with
reference to the unit rates provided in the BOQ.
35. Variations
35.1 The Engineer may order Variations, with the prior approval of the Employer, he
considers necessary or advisable during the progress of the Works. Such Variations shall
form part of the Contract and the Contractor shall execute the varied works. Oral orders of the
Engineer for Variations, unless followed by written confirmation, shall not be taken into
account. Further, no variation to Routine Maintenance, Initial Rectification and Periodic
Renewal Works are acceptable, except as specified in Clause 6.2 of Part-II of Section-7
(Specifications for Road Maintenance Works and Operational Procedures).
39. Payments
39.1 Payments shall be adjusted for deductions for Output Performance measures,
advance payments, security deposit, other recoveries in terms of the Contract and taxes
at source, as applicable under the law. The deduction and payment methodology are
described in Clause 5.2 of Part-II of Section-7 (Specifications for Road Maintenance Works
and Operational Procedures). The Employer shall pay the Contractor the amounts the
Engineer had certified, within 28 days of the date of each certificate after submission of
the monthly statement by Contractor.
39.2 Monthly statement for routine maintenance, Initial Rectification Works and Periodic
Maintenance shall be raised on monthly basis. The authorized representative of the
Employer shall make the payment certified by the Engineer.
39.3 deleted.
39.4 Price Adjustment - Prices shall be adjusted for fluctuations in the cost of inputs
only if provided for in the Contract Data. If so provided, the amounts certified in each
payment certificate, after deducting for Advance Payment (if any), shall be adjusted by
applying the respective price adjustment factor to the payment amounts. Formula as
below shall be applied:
P = A + B Imc/Ioc
where:
Imc is the index prevailing at the end of the month being invoiced and Ioc is the
index prevailing twenty-eight (28) days before Bid due date for inputs payable;
If the value of the index is changed after it has been used in a calculation, the
calculation shall be corrected, and an adjustment made in the next payment
certificate. The index value shall be deemed to take account of all changes in
cost due to fluctuations in costs.
7 The sum of the two coefficients A and B should be 1 (one) in the formula for each currency.
Normally, both coefficients will be the same in the formulae for all currencies, since coefficient A, for
the nonadjustable portion of the payments, which is 0.15 to take account of fixed cost elements or
other nonadjustable components. The sum of the adjustments for each currency is added to the
Contract Price.
Governments, local bodies and authorities that the Contractor will have to pay for the
performance of this Contract. The Employer will perform such duties in regard to the
deduction of such taxes at source as per applicable law.
41.2 All payments shall be made in Indian Rupees.
47. Completion
47.1 The Contractor shall request the Engineer to issue a certificate of Completion of the
Works, and the Engineer will do so upon deciding that the Works are completed as per
specifications and standards given in the Contract and as per approved design.
50.3 Termination: The Employer or the Contractor may terminate the Contract if the other
party causes a fundamental breach of the Contract.
50.4 Fundamental breaches of Contract include, but shall not be limited to, the following:
A) Fundamental Breaches by the Contractor
a) the Contractor stops work or grossly neglects Routine Maintenance Works
and Services for 28 days when no stoppage of work is shown on the current
programme and the stoppage has not been authorized by the Engineer;
b) the Contractor is declared as bankrupt or goes into liquidation other than
for approved reconstruction or amalgamation;
c) the Engineer/Employer gives Notice that failure to correct a particular
Defect is a fundamental breach of Contract and the Contractor fails to
remedy the defect and correct it within the period of time determined
by the Engineer;
d) the Contractor does not maintain a Security Deposit as per clause;
e) the Contractor has delayed the completion of Works by the number of days
for which the maximum amount of liquidated damages can be paid, as
defined in Clause 43;
f) the aggregate liability of the Contractor to the Employer, exceeds the
total amount specified in the Contract Data, provided that this limitation
shall not apply to the cost of repairing or replacing defective works and
equipment;
g) the Contractor fails to provide insurance cover as required under Clause
13;
h) if the Contractor, in the judgement of the Employer, has engaged in the
corrupt or fraudulent practices as defined in Clause 34 of the
Instructions to Bidders in competing for or in executing the Contract;
i) if the Contractor fails to set up a field laboratory with the prescribed
equipment, within the period specified in the Contract Data;
j) if the Contractor does not deploy any of the personnel stated in Contract
Data within 45 days of issue of notice to proceed;
k) The Contractor violates the provisions of Child Labour (Prohibition &
Regulation) Act, 1986;
l) Breach as described in note 5 of Clause 5.2 of Part II of Specification for
Road Maintenance works and Operational Procedures as action for
repeated non compliances.
m) Any other fundamental breaches as specified in the contract data.
50.5 Without prejudice to any other right or remedies which the Employer may have under
this contract upon occurrence of a Contractor’s fundamental breach of contract, the
Employer shall be entitled to terminate this contract by issuing a Termination Notice to
the Contractor provided that before issuing the Termination Notice, the Employershall
by a Notice inform the Contractor of its intention to issue such Termination Notice and
grant 15 days to the Contractor to make a representation and may after the expiry ofsuch
15 days, whether or not it is in receipt of such representation issue the Termination Notice.
50.6 Notwithstanding the above, the Employer may Terminate/ Foreclose the Contract for
its convenience.
50.7 If the Contract is terminated/ Foreclosed, the Contractor shall stop work
immediately, make the Site safe and secure, and leave the Site as soon as reasonably
possible.
52. Property
52.1 All Materials on Site, Plant, Equipment, Temporary Works and Works shall be
deemed to be the property of the Employer for use for completing balance work if the
Contract is terminated because of the Contractor’s default.
54. Labour
54.1 The Contractor shall, unless otherwise provided in the Contract, make his own
arrangements for the engagement of all staff and labour, local or other, and for their
payment, housing, feeding and transport; and for compliance of various labour
laws/regulations.
54.2 The Contractor shall, if required by the Engineer, deliver to the Engineer a return
in detail, in such form and at such intervals as the Engineer may prescribe, showing the
staff and the numbers of the several classes of labour from time to time employed by
the Contractor on Site and such other information as the Engineer may require.
54.3 The Contractor’s personnel including equipment operators shall be appropriately
qualified, skilled and experienced in their respective trades or occupations. The Engineer
may require the Contractor to remove or cause to be removed any person employed on
the site or the works, including the Contractor’s representative, if applicable, who
a) Persists in any misconduct or lack of care;
b) Carries out duties incompetently or negligently;
c) Falls to conform with any provision of the contract;
d) Persists in any conduct which is prejudicial to safety, health or protection
of the environment.
If appropriate, the contractor shall then appoint or cause to be appointed a
suitable replacement person
55. Compliance with Labour Regulations
55.1 During continuance of the Contract, the Contractor and his sub-Contractors shall
abide at all times by all existing labour enactments and rules made thereunder,
regulations, notifications and bye laws of the State or Central Government or local
authority and any other labour law (including rules), regulations, bye laws that may be
passed or notification that may be issued under any labour law in future either by the
State or the Central Government or the local authority. (Salient features of some of the
major labour laws that are applicable to construction industry are given in Addendum to
General Conditions of Contract.) The Contractor shall keep the Employer indemnified in
case any action is taken against the Employer by the competent authority on account of
contravention of any of the provisions of any Act or rules made thereunder, regulations or
notifications including amendments. If the Employer is caused to pay or reimburse, such
amounts as may be necessary to cause or observe, or for non-observance of the provisions
stipulated in the notifications/bye taws/Acts/Rules/regulations including amendments,
if any, on the part of the Contractor, the Employer shall have the right to deduct any
money due to the Contractor including his amount of performance security. The
Employer shall also have right to recover from the Contractor any sum required or
estimated to be required for making good the loss or damage suffered by the Employer.
In no case shall the employees of the Contractor and the Sub-Contractor be treated
as the employees of the Employer at any point of time.
The roads and road sections including service roads, all cross drainage works and all
other project facilities as defined in Section 10 of the Bid document.
The responsibility of the Contractor (“the Site”) is all roads and road sections included
in the section 10, including
• the Right-of-Way of the road;
• all junctions, intersections, and interchanges, including slip lanes and (unless
otherwise stipulated in the Contract) the first 50 meters of the connecting roads;
and
• for all river or stream beds the Contractor’s responsibilities extend (unless
otherwise stipulated in the contract) for 100 meters upstream and downstream
from the road or the relevant bridge or drainage structure.
• for all paved side roads the Contractor’s responsibilities extend (unless otherwise
stipulated in the contract) for maximum of 60 meters.
Service Roads running in parallel to the road are included in the contract and the
details to be mentioned in the asset details and service levels mentioned in this
section.
5. The Start Date shall be within 15 days after the date of issue of the Notice
to proceed [Cl.1.1 of GCC]
6. (a) The name and identification number of the Contract is
The Works consist of PBMC O&M work of 4 Laning of Simga-Sargaon (PKG - II) of NH-
200 section from Km 48+580 to Km 91+026 and Sargaon- Bilaspur (PKG - III) of
NH-200 section from Km 91+026 to Km 126.525 section of Raipur-Bilaspur in the
State of Chhattisgarh.(PBMC) [Cl. 1.1 of ITB]
7. (a) The law which applies to the Contract is the law of Union of India.
[CI.3.1 of GCC]
8. The limit of subcontracting is NIL of initial contract price [CI.7.1 of GCC]
9. Schedule of other Contractor- ………. [Cl.8.1 of GCC]
10. The Technical Personnel are ………. [Cl. 9.1 of GCC & Cl. 1.3]
17. Price Adjustment: Price Adjustment will be Applicable after 01 Year i.e.
Effective from 13th Month from the Start Date as per details below:
(i) Routine Maintenance cost to be adjusted in line with WPI where Non-
Adjustable Portion will be 0.15 (A) and Adjustable Portion will be 0.85 (B). The
Base WPI (All Commodities) is to be considered 28 days before the bid due date.
(ii) Periodical Maintenance and Emergent works cost to be adjusted for
Bitumen prices, Fuel prices to be considered as 0.40 & 0.12 coefficient
respectively and for other materials/ labour for a coefficient of 0.33 on WPI (All
Commodities) totaling to 0.85 (B) whereas, for Non-Adjustable Portion,
coefficient is to be 0.15 (A). The indices for bitumen and fuel are to be
considered as per the actual price of Bitumen from nearest Refinery and
Diesel from Indian Oil Corporation Ltd. [Cl. 39.4 of GCC]
19. The standard form of Performance Security acceptable to the Employer shall
be an unconditional Bank Guarantee of the type as specified in the Bidding
Documents. [Cl. 45.1 of GCC]
20. The percentage to apply to the value of work not completed representing the
Employer’s additional cost for completing the work shall be 20 percent. The
Performance Security shall also be forfeited if the Contract is terminated because
of a fundamental breach of Contract by the Contractor. [Cl.52.1 of GCC]
PREAMBLE
The Road Maintenance Standards and Specifications shall be read in conjunction with
all other documents constituting the Contract viz. Notice Inviting Tender,Instructions
to Bidders; Conditions of Contract, Bill of Quantities and other related documents
mentioned in the Bid Documents.
General
The Standards and Specifications for the Road Maintenance Works and Activities as
described hereinafter shall comprise of the following:
PART-I : Road Maintenance Standards and Performance Measures
PART-II : Specifications for Road Maintenance Works and Operational Procedures
Carbon foot prints shall be evaluated during the execution of project. If approved by
the Employer, the environment friendly machinery like Infrared Recycling Road
Maintenance as approved by CRRI/IRC/MoRTH shall be got deployed.
PART-I
• Operational Performance Measures relate directly to the quality of the road and
therefore to the results of the Contractor’s maintenance activities. The required
minimum acceptable road conditions and Service Levels are defined through the OPM‟s,
and these are used to define and measure the compliance of the Contractor with the
specified requirements. The defined Operational Performance Measures and indicators
are thus the accepted minimum thresholds for the quality levels of the roads for which
the Contractor is responsible.
The OPMs cover essential aspects of the roads and take account of the fact that different
roads within the contract area might require different Service Levels. Each contract will
be unique as the OPMs reflect the Employer’s strategic goals for the specific roads
covered by the contract.
For paved roads, OPM criteria refer mostly to Road User Service and Comfort measures,
which can be expressed in terms such as:
• Road Roughness
• Road and lane width
• Rutting
• Vegetation control
• Cleanliness of the road and its Right-of-way
• Visibility of road signs and markings
• Availability of traffic lanes for vehicle traffic
• Response times to rectify defects
• Maintenance of other Road assets including utility / ATMS services
required for proper operation of Traffic management and Road Safety
Periodic Maintenance Works, for specified section would be paid in the form of lump-
sum rate/ amount per km completed length that will be measured and paid in accordance
with the progress in the execution of those measured outputs (completed per km length).
Periodic Maintenance works also includes Road Markings, provision of reflective Road
Studs, Gravel filling to match the Shoulder level with carriageway after laying renewal
coat, which will be paid on measured inputs basis.
Unit prices are provided for Emergency Works in the form of a Schedule of Prices.
Payments will be made for each Emergency on a case-to-case basis, on actual execution
and value determined by the Contractor and approved by the Engineer/ Employer on
the basis of the quantities executed.
Routine Maintenance services include (but are not limited to) the following:
• Repairing road defects (such as potholes, rutting, ravelling, cracking in
pavement, edge break, etc.);
• Removing the landslides / boulders from the road section and keeping the
road lane clean for traffic flow
• Cleaning and maintenance of road signs and road markings, including their
replacement needed due to wear and tear, minor damages, etc.;
• Maintaining traffic flows and road safety during Works carried out on the
roads;
• Road Furniture – Barriers, Guard Rails, Anti glares, Road studs, Rumble strips,
Signboards, Traffic blinkers, Pavement marking, Noise Barriers, Object Markers,
Attenuators, Delineators
• Project Facilities – Bus bays, Truck Lay Byes, Toilet Blocks, Highway lighting
• Encroachment
The Routine Maintenance (RM) shall be carried out on all Roads covered by the
Contract to the specified service quality levels for a contract period, including:
• The provision of management services as required for the duration of the
Contract,
• Provide a Quality Plan for the Engineer’s approval within 8 weeks of the Start
Date and implement all quality management requirements.
As part of Routine Maintenance the Contractor has to ensure that requisite inspections
and preventive actions as per the following:
(i) Ministry’s Circular no. No. PL-67(29)/76-NH-VI dated 28.06.1979,
NHIII/P/13/79 dated 08.08.1979 dt. 07.08.1980, 04.08.1981 and
RW/N.17/KNT/32/w dt. 25.04.1982.
(ii) Ministry’s Circular no. No. RW-33044/10/2000-S&R (R) dated 12.06.2022 NH-
18014/7/2000-Pl dated 05.07.2002, RW/NH-33044/10/2002/S&R(R) dated
22.01.2003 and RW/NH-33044/10/2000-S&R (R) dated 13.01.2003
(iii) RW/NH-33044/10/2002-S&R (R) dated 31.01.2003 and RW/NH-34059/2/2001-
S&R (B) dated 31.01.2003.
(iv) Ministry’s Circular no. No. RW/NH-12037/39/2019-Misc/Z-III dated
23.07.2019.
(v) IRC Codes (SP-113-2018 on Flood Disaster Mitigation, 34-2011 on road
construction in areas affected by water logging, flooding etc., IRC:SP:35:1990
Guidelines for Inspection and Maintenance of Bridges.)
Any failure by the contractor to comply with the above, after intimation in this regard
by the Engineer, shall lead to deduction of 50% of the total RM payment payable that
month apart from other deductions as per non-compliance of service levels given in
Annexure-E.
Copy of all the circulars are attached with the Contract document.
2.2 Initial Rectification works
Initial Rectification Works are those activities that are beyond Routine Maintenance
Activities, but not defined for Periodic Maintenance Works that are needed at the initial
stage of the Contract to bring the road in the service level as defined in the contract.
The Contractor shall engage such additional resources necessary to complete the
specified Initial Rectification Works. The Contractor shall not utilize resources specified
in this Contract as being committed to Routine Maintenance activities
The Contractor is to make an estimate of the Initial Rectification Works which in his
view are necessary interventions to bring the roads at par with the service level to be
met within the 6 month Milestone, and include the cost for those works in the item for
Initial Rectification Works in his bid. It also includes other works needed to bring roads
up to the required service levels, which are beyond the scope of Routine Maintenance
at the commencement of the project, but which are not included in the items of Initial
Rectification and Periodic Maintenance Works, shall be included by the bidders in the
lump sum price for IR Services. Contractors are solely responsible for estimating the type
and quantity of Initial Rectification Works needed to meet the requirements of the
contract.
In the initial stage, for the contractor to meet the service level compliance it will be
necessary for the Contractor to undertake Initial Rectification Works for the repair of
surface defects (ravelling, stripping, de-laminations, rejuvenation of oxidized surface,
fine hair cracking repair, etc.) in bitumen roads:
• All Pavement repairs using BC, DBM to correct large areas of Roughness,
Rutting, Depressions
• Apply 7mm Light Surface Sealing for slurry seal to correct cracks > 5mm,
• Application of road marking paints, fixing of road studs, sign boards, Kilometre
stone, hectometre stone and boundary / guard/ Guide stone.
For Rigid Pavements this will include, e.g. repair of cracks, spalls, joint sealed effects
corner racks, levelling, potholes, polished surface, faulting in cracks and joints, heal
and bump, blow up or buckling, drop off, pumping and ponding, etc.
The following estimated quantities for Initial Rectification Works is the Employers
estimate to be able to achieve the desired Service Level for the entire road and has been
provided as a Guide to assist the Contractor in determining his Lump Sum for Initial
Rectification Works. Work locations have not been defined and the works to absorb the
quantities below will need to be assessed by the Contractor himself, be programmed
and completed within 6 months of start date.
Sl.
Description Quantity Unit
No.
Slurry seal to seal cracks, fill voids and minor Refer BOQ
6 depressions for thickness <5mm – MoRTH Sqm
Specification No.512
Refer BOQ
8 Clearing Light Jungle Sqm
5. Full depth repair of PQC slab by removing the entire Refer BOQ
slab and DLC and underneath layers if required. Placing
separation membrane, dowel bars 32 mm dia X 500 mm
long and tie bars 16 mm dia X 750 mm long, placing DLC
if removed and PQC M-40 grade complete as per the
provision of IRC:15 and as per directions of Engineer-in-
Charge
8. Full depth repair as per specifications and standards Refer BOQ Sqm
defined in IRC SP:83-2018
10. Diamond Grinding (Cutting) as per specifications and Refer BOQ Sqm
standards defined in IRC SP:83-2018
11. Dowel Bar Retrofit as per specifications and standards Refer BOQ No.s
defined in IRC SP:83-2018
All works and materials are to be in accordance with the relevant sections as defined
in Section 7, Part II of this Technical specification
There is no individual Performance Criteria and Service level requirement for Initial
Rectification Works. The Initial Rectification Works is for the purpose of assisting the
Contractor to bring the road below the intervention standard within 6 (six) months of
the start date. Failure to bring the road below intervention standard by the stated
time period will result in Payment Reductions in the Routine Maintenance Lump Sum
after the Initial Rectification Works completion date. On completion of the Initial
Rectification Works the Contractor is to maintain the road under Routine Maintenance.
Payment for the Initial Rectification works shall be made as details in Bill of
Quantities Chapter section 9.
2.2.1 Contractor shall carry out the monthly geotagged videography of the
entire stretch in the first week of month and prepare a comparative video
with the previous month.
Periodic Maintenance works are the pavement resurfacing activities that are
beyond Routine Maintenance Activities. Entire Project Section, if specifically mentioned
by Employer to be covered under Periodic Maintenance under this contract, shall be
provided with a renewal coat within the timeline specified by the Engineer/ Employer
but in any case, before completion of 02 Years from the start date of the work unless
otherwise decided by the Employer. However, in case the roughness of the road is within
the specified service level, the PM works can be deferred to be completed before expiry
of fourth year from start date. Such deferment shall be approved by Engineer only after
analyzing the latest NSV survey report. The Defect Liability Period (DLP) for such works
will be for the remaining Contract Duration or 36 months from the date of completion
of such work items whichever is later. In case of failure of Contractor to execute Periodic
Maintenance work items within two/four years (as the case may be) from the start date
of Contract, Liquidated damages shall be paid by the Contractor. If Contractor fails to
complete the PM works even beyond
100 days after 2/4 years of start of work, then Employer will initiate action for
termination of contract by giving suitable cure period notice and work shall be executed
at the risk and cost of the contractor through third party.
The periodic maintenance activities have to be carried out in order to restore the project
condition to meet all the relevant standards. The Contractor is to make an estimate of
the Periodic Maintenance Work quantities including camber/profile corrections, which
in his view are necessary to bring the roads to the required service level (Roughness
Index) and include the cost for those works in the item for Periodic Maintenance Works.
The Contractor would need to plan the periodic maintenance to ensure that at the time
of handover the remaining life of the road sections are meeting the requirements
mentioned in this contract. Prior to commencement of an overlay, the Contractor is to
notify the Engineer of the impending commencement of the Works for inspection in
accordance with the General Conditions.
If it is felt that IR works is not sufficient to being the road to the service level
condition with due satisfaction of the Engineer and employer, then PM works may be
carried out within the 6 months period also with prior approval of the Engineer. Such
decisions must be supported with NSV data or FWD data.
As a guide to assist the Contractor in his bid, the following is the Employer’s estimate
of the Periodic Maintenance works:
Sr.
Description Quantity Unit
NO.
Sr.
Description Quantity Unit
NO.
Refer BOQ
Partially bonded overlay as per clause 11.6.2 &
2 Cum
clause 11.6.5 of IRC SP:83, 2018
The performance Criteria for Periodic Maintenance shall meet all the requirements of
a newly laid pavement in respect of user comfort and quality of pavement andshoulders
as per relevant MoRTH specifications.
The Roughness is to be measured at the beginning of the Contract as part of the Initial
Road Condition Report to confirm the sections that do not meet this Service Level
criteria.
On completion of each milestone, the roughness shall be taken as part of the Milestone
Report.
If the measurement reveals that the road roughness is above the Service Level, the
Engineer will establish a time frame for the Contractor to complete periodic
maintenance works. That time frame should normally ensure that the corresponding
works are completed within four months. The Engineer may however grant a longer
period if, in the opinion of the Engineer, the circumstances warrant such longer
period. Upon completion of the non-conforming section the relevant section roughness
shall be measured again to confirm compliance. Liquidated Damages shall apply after
the granted date until the non-conformance has been corrected.
Payment for the Periodic Maintenance works shall be made as per the details given
in the Bill of quantities Chapter section 9.
The Contractor’s performance requirements for Maintenance Services are defined and
measured according to (i) Operational Performance Measures (OPM‟s) and (ii)
Management Performance Measures (MPM‟s), as set out below.
3.1.1 OPM-1: Main carriageway Roadway along with Service/ Slip Road The
Contractor must ensure that the Main carriageway Roadway along with
Service/ Slip Road is in good condition. The items included in OPM-1 includes
the following:
(c) Rutting
(d) Bleeding/
Ravelling/ Stripping
OPM-2
Road Shape and Shape and Position as per Daily Visual Improvemen 48 hours in IRC:67
Signs Position IRC:67- 2012. Inspection t of shape, case -2012
Signboard should beclearly with video/ in case ifof Mandatory
visible for the design speed image shape isSigns,
of thesection. backup. damage d. Cautionary and
Informatory
Relocation
Signs (Single
as per
and Dual post
requirement
signs), 15 Days
in case
of Gantry/
Cantilever Sign
boards
Retro As per specifications in Bi-Annually Testing of Change of 48 hours in IRC:67
reflectivity IRC:67-2012 each signboard case of -2012
signboard Mandatory
using Retro Signs,
Reflectivity Cautionary and
Measuring Informatory
Device. Signs (Single
In- and Dual post
accordance signs).
with ASTM D 1 Month incase
4956- of Gantry/
09. Cantilever Sign
boards
Asset Performance Level of Service (LOS) Frequency of Tools/ Standards Time limit for Maintenance
Type Parameter on each side for each km Inspection Equipment and Rectification/ Specifications
(LHS/RHS) References Repair
Accept able for
Reflective Numbers and As per specifications in Daily Counting New Within 2 IRC: SP:
Pavement Functionality IRC: SP: 99-2013 and Installation months 99-2013,
Markers . IRC: 35-2015, unless IRC: 35-2015
(Road specified in Schedule- B
Studs)
Pedestrian Functionality: Should be properlyDaily Visual Rectification Within 15 days IRC: SP:
Guardrail Functioning of maintained with proper Inspection 99-2013/
guardrail as painting, repair ofdamaged with video/ IRC:103
intended portion and replacement of image -2012
missing backup.
portion.
Traffic The existing barriers aswellDaily Visual Rectification Within 7 days IRC: SP:
Safety Functionality: as barriers installed as Inspection 99-
Barrier s Functioning of part of Initial rectification with video/ 2013,
Safety Barriers should beadequately image IRC:11 9-2015
as intended spaced, backup.
(including
parapet positioned with proper end
walls for treatment wherever
hill roads) required as per IRC 119.
There should be no
missing/damaged parapet
walls in hill roads
Any crack / breakage in
Parapet wall shall be
immediately repaired /
reconstructed
Functionality: As per Specifications Daily Visual Rectification Within 7 days IRC: SP:
Functioning of Inspection 99-
Attenuators Attenuators as with video/ 2013,
intended image IRC:11 9-2015
backup.
Guard Functionality: As per Specifications Daily Visual Rectification Within 15 days IRC:79
Posts and Functioning of Inspection -2019
Delineator Guard Posts with video/
s and image
Delineators as backup.
intended
Overhead Overhead signAs per as per IRC:67 Daily Visual Rectification Within 15 days IRC:67
Sign structure shall Inspection
Structure be structurally with video/
adequate with image
requisite backup.
retroreflectivity
Functionality: As per Specifications Daily Visual Rectification Within 7 days IRC:SP
Traffic Functioning of Inspection :99-
Blinkers Traffic Blinkers with video/ 2013
as intended image
backup.
Asset Performance Level of Service (LOS) Frequency of Tools/ Standards Time limit for Maintenance
Type Parameter on each side for each km Inspection Equipment and Rectification/ Specifications
(LHS/RHS) References Repair
Accept able for
Pavement Wear <70% of marking Bi- Visual Re- Painting Cat-1 Defect IRC:35
Marking remaining Annually Assessment within 24 hours -2015
as per Cat-2 Defect –
Annexure-F within 2
of IRC:35- months
2015
Day time During expected life Monthly As per Re- Painting Cat-1 Defect – IRC:35
Visibility Service Time Annexure- D within 24 hours -2015
Cement Road - of IRC:35- Cat-2 Defect –
130mcd/m2/lux 2015 within 2
Bituminous Road - months
100mcd/m2/lux
Night Time Initial and Minimum Initial and Initial and Re- Painting Cat-1 Defect – IRC:35
Visibility Performance for Dry Retro Minimum Minimum within 24 hours -2015
reflectivity during night Performance Performance Cat-2 Defect –
time: for Dry Retro for Dry Retro within 2
Design (RL) Retro- reflectivity reflectivity months
Speed Reflectivity during night during night
(mcd/m2/lux) time: time:
Initial (7 Minimum
Days) Threshol
d Level
(TL) and
warranty
period
require
upto 2
years
Up to 65 Up to Up to
65 65
65 - 65 - 65 -
100 100 100
above above above
100 100 100
Initial and Minimum
Performance for
Night
Visibility under
wet
condition (Retro
reflectivity):
Initial 7 days Retro
reflectivity: 100mcd/m2/lux
Minimum Threshold Level:
50 mcd/m2/lux
OPM-3
Asset Type Performance Level of Service (LOS) Frequency Testing Recommended Time limit for Specifications
Parameter on each side for each of Method Remedial Rectification and Standards
km (LHS/RHS) Measureme measures
Accept able nt
Pipe/ Free 85% of culvert normal 2 times in a Inspection Cleaning 15 IRC 5-
box/ waterway/ flow area to available. year (before by Bridge silt up soils days 2015, IRC
slab culverts unobstructed and after Engineer as and debris before SP:40-
flow section rainy per IRC SP: in culvert onset of 2019 and
season) 35- 1990 barrel after monsoon and IRC
and rainy season, within SP:13- 2004
recording of removal of 30
depth of bushes and days after
silting and vegetation, end of
area of U/s of rainy
vegetation. barrel, under
season
barrel and .
D/s of
barrel
before
rainy
season.
Leak- proof No leakage through Bi- Physical Fixing with 30 IRC: SP:
expansion expansion joints Annually inspection of sealant suitably days or 40-2019 and
joints if expansion before onset IRC: SP: 69-
any of rains 2011
joints as per
whichever
IRC SP: 35- comes earlier
1990 if any,
for leakage
strains on
walls at
joints.
Structurally Spalling of concrete not Bi- Annually Detailed Repairs to 15 IRC SP 40-
sound more than 0.25 sqm. inspection of spalling, days 2019
all cracking, and MORTH
Delamination of concrete components delamination, Specifications
not more than 0.25 sqm. of culvert as rusting shall be clause 2800
Cracks wider than 0.3 per IRC followed as per
mm not more than 1m SP:35-1990 IRC: SP:40-
aggregate length and 2019.
recording
the defects
Protection Damaged of rough 2 times in a Condition Repairs to 30 IRC: SP 40-
works in good stone apron or bank year (before survey as damaged aprons days after 2019
condition revetment not more than and after per IRC and pitching defect and IRC: SP:13
3 sqm, damage to solid rainy SP:35-1990 observation or - 2004.
apron (concreteapron)
season) 2
not morethan 1 sqm.
weeks before
onset of rainy
season
whichever is
earlier.
Bridges Riding quality No pothole in wearing Daily Visual Repairs to BC or 15 MORT&H
including or user coat onbridge deck inspection wearing coat days Specification
ROB’s, 2811
comfort as per IRC
Flyover and
SP:35-1990
Asset Type Performance Level of Service (LOS) Frequency Testing Recommended Time limit for Specifications
Parameter on each side for each of Method Remedial Rectification and Standards
km (LHS/RHS) Measureme measures
Accept able nt
Viaducts etc.
as applicable
Bridges Bumps No bump at expansion Daily Visual Repairs with BC 15 MORT&H
including joint inspection on either side of days Specification
ROB’s, as per IRC expansion joints, 3004.2
Flyover and SP:35-1990 profile correction & 2811
Viaducts etc. course on
-Super approach slab in
Structure case of
settlement to
approach
embankment
User safety No damaged or Daily Visual Repairs and 3days IRC: 5-
(condition of missing stretch of crash inspection replacement of 2015, IRC
crash barrier barrier or pedestrian and detailed crash barriers as SP: 99-
and guard hand railing or parapet. condition the case may be 2013 and IRC
rail) survey as SP: 40- 2019
The barriers should be per IRC SP: IRC 119
adequately spaced, 35- 1990
positioned with proper
end treatment wherever
required as per IRC 119.
Rusted Not more than 0.25 sqm. Bi- Annually Detailed All the corroded 15 IRC SP: 40-
reinforcement condition reinforcement days 2019
Spalling of Not more than 0.50 sqm. survey as shall need to be and MORTH
concrete per IRC SP: thoroughly Specification
35-1990 cleaned from 1600 IRC SP:
Delamination Not more than 0.50 sqm. 40-2019
using Mobile rusting and
Bridge applied with anti- and MORTH
Inspection corrosive coating Specification
Unit.
before carrying
out the repairs to
affected concrete
portion with
epoxy mortar/
concrete.
Cracks wider Not more than 1m total Bi- Annually Detailed Grouting with 48 IRC SP: 40-
than 0.30 length condition epoxy mortar, Hours 2019
mm survey as investigating and MORTH
per IRC SP: causes for Specification
35- cracks or other 2800
1990using defects
Mobile development and
Bridge carry out
Inspection
necessary
Unit.
rehabilitation.
Rainwater Leakage Quarterly Detailed Grouting of deck 1 MORTH
seepage - nil condition slab at leakage month specifications
through deck survey as areas, 2600
slab per IRC SP: waterproofing, & 2700.
35- repairs to
Asset Type Performance Level of Service (LOS) Frequency Testing Recommended Time limit for Specifications
Parameter on each side for each of Method Remedial Rectification and Standards
km (LHS/RHS) Measureme measures
Accept able nt
1990 using drainage spouts
Mobile
Bridge
Inspection
Unit.
Deflection Within design limits. Once in Load test Carry out major 6 IRC SP: 51-
due to every 10 method rehabilitation months 2015
permanent years for works on
loads and live spans more bridge to retain
loads than 40 m original design
loads capacity
Vibrations in Frequency of vibrations Once in Laser Strengthening of 4 AASHTO,
bridge deck shall not be more than 5 every 5 displacemen super structure months LRFD
due to moving Hz years for t sensors or specifications
trucks spans more laser vibro-
than 30m meters
and every
10 years for
spans
between 15
to 30
Leakage in No damage to Bi- Annually Detailed Replacement of15 MORTH
Expansion elastomeric sealant condition seal in expansiondays specifications
joints compound in strip seal/ survey as joint. 2600 and IRC
modular type expansion per IRC SP: Replacement of SP: 40-
joint, no leakage of rain 35-1990. sealing 2019.
water through expansion Using compound in
case of leakage I
joint in case of buried Mobile
copper strip type
and asphalt plug and Bridge joint.
copper strip joint. Inspection
Unit.
Debris and No dust or debris in Monthly Detailed Cleaning of 3 days MORTH
dust expansion joint gap. condition expansion joint specifications
in strip seal/ survey aspergaps thoroughly 2600, IRC
modular type IRC SP: 35- SP: 40-
expansion 1990.using 2019 and IRC:
joint Mobile SP: 69
Bridge -2011
Inspection
Unit.
OPM-4
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
Bus Bay Cleanliness & As per Daily Visual Rectification 15 Days IRC: SP: 99-2013
Painting Specifications Inspection & IRC: SP: 84-
2019
Truck Lay Cleanliness & As per Daily Visual Rectification 15 Days IRC: SP: 99-2013&
Bye Repairing Specifications Inspection IRC: SP: 84- 2019
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
(i) Main control Monthly Visual IRC Within 7 Days IRC: SP:
Availability of
centre and Inspection 84-2019
Basic
Administrative block. with video/
Construction
Equipment for image
Equipment
operation and backup.
Availability of maintenance and Monthly Visual IRC Within 7 Days IRC: SP:
Equipment storage space for Inspection 84-2019
and them. with video/
instrument in Storage space for image
Lab with equipment and backup.
Calibration material for traffic
Certificate signs and markings.
(ii) Workshop.
(iii) General Weekly Visual IRC 2-7 Days MMU shall be
garage and repair Inspection engaged full time
shop.
with video/ per PMU for a
Testing laboratory.
image minimum of 8
O&M Center Parking space for backup. hours per day and
minimum monthly
minimum 4 number
running distance of
Functionality of large vehicles
three times of
of Mobile and for other
operational road
Maintenance expected vehicle
length of package
Unit during peak hours
or all roads in a
including those for
package to be
working staff and
covered within 10
visitors.
days, will result in
proportional
payment
deductions
Availability of Monthly Visual IRC Nil IRC: SP:
Bump Inspection 84-2019
Integrator on with video/
24 hours image
notice backup.
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
OPM-6
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit Maintenance
Parameter (LOS) on each sideInspection Equipment Measure for Specifications
Standard Rectificati
for each km on
(LHS/RHS)
Accept able
Emergency Deployment Response time Daily 1033 or 112 NA Nil The vehicle
Response of Ambulance within 15 minutes of Call and staff
deployed
System * Vehicle reporting of incident Records/ should be as
including staff for every incident Computer per
within 20 km of Aided specifications
station of Dispatch mentioned in
Ambulance and on System of IRC: SP: 84-
2019
pro-rata basis for Employer if
distance over 20 available
km.
Deployment Response time Daily 1033 or 112 NA Nil The vehicle and
of Route within 15 minutes of Call staff deployed
Patrol Vehicle reporting of incident Records/ should be as per
including staff for every incident Computer specifications
within 20 km of Aided mentioned in IRC:
station of Dispatch SP: 84-2019
Ambulance and on System of
pro-rata basis for Employer if
distance over 20 available
km.
Further, continuous
patrolling of the
stretch with atleast
coverage of the
stretch 3 times in
every 24 hours.
Functionality GPS based Vehicle Daily Visual NA Nil As per AIS-140
of Vehicle Tracking System to Inspection
Tracking monitor its
System (VTS) movement on 24 hrs
x 7.
Deployment Response time Daily 1033 or 112 NA Nil The vehicle and
of crane of within 45 minutes of Call staff deployed
capacity not reporting of incident Records/ should be as per
less than 25 for every incident Computer specifications
MT within 20 km of Aided mentioned in IRC:
station of Dispatch SP: 84-2019
Ambulance and on System of
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
Work Zone Documentatio An expert on safetyDaily Measureme IRC 24 Hours IRC: SP:
Safety n of safety or an engineer nts shall be 55-2014
arrangements trained on work through
Review of zone safety from aDaily visual IRC 24 Hours IRC: SP:
safety qualified company inspection
55-2014
arrangement should be named to and shall be
implement the work supported
Validation of Daily IRC 24 Hours IRC: SP:
zone, including by video
documentatio 55-2014
installing, operating, back-up.
n
maintaining and
removing the work
zone.
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
OPM-8
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
OPM-9
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
OPM-10
Highways Video Failure of more than Daily Measureme Repair must 2-3 Days Clause 815;
Traffic Surveillance two Video Cameras nts shall be conform to MoRT&H
Management System or failure of their through clause 815; Specification.
System related visual MoRT&H
(HTMS) transmission/control inspection Specification.
system which would
render the cameras
inoperative.
Should be in Daily Measureme 24-48
Mobile Radio functional condition. nts shall be Hours
Communicati through
on System visual
inspection
Failure of more than Weekly Measureme 2-7 Days
one Video Cameras nts shall be
Video
or failure of their through
Incident
related visual
Detection
transmission/control inspection
System
system which would
(VIDS)
render the cameras
inoperative
Vehicle Should be functional Daily Measureme 2-3 Days
Actuated at all times nts shall be
Speed through
Asset Type Performance Level of ServiceFrequency of Tools/ Remedial Time limit for Maintenance
Parameter (LOS) on each sideInspection Equipment Measure Rectification Specifications
for each km Standard
(LHS/RHS)
Accept able
Display visual
System inspection
Failure of any threeWeekly Measureme 2-7 Days
consecutive Call nts shall be
Emergency boxes or failure of through
Roadside their related visual
Telephone transmission system inspection
System which would render
the call boxes
inoperative.
No display/Improper Weekly Measureme 2-7 Days
Display of VMS or nts shall be
Variable failure of their through
Message related visual
Sign (VMS) transmission/control inspection
system system which would
render the VMS
inoperative
Failure of more thanWeekly Measureme 2-7 Days
one Met or failure of nts shall be
Meteorologica
their related through
l Data System
transmission system visual
(MET)
which would render inspection
the Met inoperative.
Failure of more thanDaily Measureme 2-3 Days
Automatic one ATCC or failure nts shall be
Traffic of their related through
Counter-cum- transmission system visual
Classifier which would render inspection
the ATCC
inoperative
Note:
1. Any structure / part of the structure component during entire Contract period which
is found not complying with all /or either of the requirements of this table will be
rehabilitated to achieve the desired level of services.
2. MoRT&H Specification for Roads and Bridge works (Vth Revision) shall be applicable.
3. IRC Codes indicated above shall be applicable as per year of publication in
consonance with the start of project implementation.
4. All project assets not mentioned above shall be repaired & maintained as per good
industry practice in consultation with Engineer/ Employer.
5. All the parameters listed in Annexure-E shall be assumed to be part of the Payment
Reduction Table as per clause 5.2 of Part-II of section-7 i.e. SPECIFICATIONS FOR
ROAD MAINTENANCE WORKS AND OPERATIONAL PROCEDURES under the
corresponding heads of the highway element and shall be liable for deduction in
payment on account of non-compliance with the above stipulated service levels.
6. In case the performance level or rectification time limit or testing method or
frequency of measurement etc. is missing for any of the items from Annexure-E,
the corresponding IRC code shall be referred for the same.
7. Include ATMS service levels only if available on the project stretch.
8. Include Ambulance/Patrol Vehicle/Cranes service levels only if not otherwise
deployed on the stretch by the employer through any other agency and is part of the
PBMC contract.
9. Add other project facilities in Annexure-E scheme if available on the projectstretch
and part of the scope of instant PBMC contract
In order to respect the Contractor’s initial mobilization period and taking into account
the time needed by the Contractor to establish full compliance with all the OPM‟s over
the entire road network included in the Contact, a schedule of gradual compliance with
OPM‟s is established, as per the Table shown below.
During the period of phasing-in the full compliance with all OPM‟s as per the table below,
the Contractor shall inform at the end of each month, as part of his Monthly Compliance
Tables for Maintenance Services, the list of roads or road sections for which OPM‟s 1 to
10 are to be applied. The length of those roads or road sections must correspond to at
least the percentage of the network indicated in the Table below for that month. During
such gradual compliance of OPMs, the payment for Routine Maintenance shall be made
corresponding to percentage compliance achieved in the OPMs, i.e. if 70% compliance of
OPMs is achieved in the first month, then only 70% payment for routine maintenance shall
be payable. Normal payment and penalty procedures for Routine Maintenance work, as
defined in the document, shall start from the end of 6th month from Start Date.
9Even those roads (or road sections) for which Initial Rectification Works are programmed to
be carried out under the contract have traffic and therefore require maintenance services.
The pavements of those roads are however likely to be in a condition which does not allow the
application of normal Service Levels. The OPM’s listed below can typically not becomplied
with by the Contractor before these Works are completed.
• OPM-1 Pavement Defects shall not be applied, except those specified above and
“Cleanliness of Pavement Surface and Shoulders” which shall apply even before the
initial rectification Works are carried out.
For paved roads (or road sections) for which Initial Rectification Works are programmed
to be carried out under the contract, the OPM´s listed below shall not apply until such
time when such Works have been completed, as follows:
• Road Marking under OPM-2(b): Thermoplastic markings shall not be required for roads
or road sections which are programmed for Periodic Maintenance. In those cases,
reflective paint can be used instead. [Note: It would not be reasonable to require the
rather expensive reflective pavement markings if the pavement is to be removed as part
of the required pavement resurfacing.]
MPM‟s are a set of performance criteria to be fulfilled by the Contractor that relate to the
management of the road assets under contract. They include the quality and testing
requirements to be fulfilled by the Contractor, as well as the collection and reporting of
various types of data and timely information to the Engineer, which may be needed as input
to the Employer’s Road Asset Management System (RAMS). The applicable MPM‟s for this
contract are summarized in the table below. The specific requirements under each MPM item
are defined elsewhere in the Specifications.
Compliance with MPM‟s is measured either monthly or as otherwise defined in theContract.
Results are to be expressed as either being “in compliance” or “non-compliant”. In case of
non-compliance, such non-compliance will continue to be recorded until compliance has
been established by the Contractor to the satisfaction of the Engineer.
In case of non-compliance with MPM‟s, the monthly lumpsum payment to the Contractor for
Maintenance Services shall be reduced by the amounts stated in the table below, multiplied
by the duration (in calendar days) of the non-compliance.
Payment
reduction
Item Compliance criteria (INR)
Compliance with
requirements in the
areas of Contractor has to be in compliance at all times.
Environment, Payment reduction is applied for each separate 30,000
MPM-12 Social, Health and non-compliance, and for each day during which
Safety of workers, non-compliance persists.
and Traffic
Management Plans
The timely collection of data and presentation of reports are part of the Management
Performance Measures (MPM‟s). Some of the reports must be prepared periodically (typically
monthly) while others are one-time reports to be submitted at specific times or at special
occasions during the duration of the contract. The reports are listed in the table below and
described in the sub-sections further below.
Report Title Frequency / Periodicity
Road Asset Inventory Database and Initial Report
Condition Reports (MPM-2): Periodic updates as specified
Road Asset Damage Reports (MPM-10) These are reports due each time when
damages to road assets occur whichrequire
repairs for which the Contractor may be
entitled to claim separate payment.
Design Reports (MPM-7) These are required for all works requiring
a detailed engineering design.
Monthly Compliance Tables for Maintenance Monthly self-reporting by the Contractor
Services (MPM-8) on his own compliance with Service Level
requirements which is the basis for the
part of the Contractor Monthly Statement
Report Title Frequency / Periodicity
which relates to Maintenance Services.
Monthly Progress Report and Statement for Monthly report on progress of rectification
Works (MPM-9) and Emergency Works, which is the basis
for monthly invoicing by the Contractor
for those works.
Works Completion Reports (MPM-5) Separate reports for each specific
rectification and Emergency Works.
Contract Completion Report (MPM-11) One-time report.
Project Final Completion Report (MPM-11) One-time report (update of Contract
Completion Report)
The requirements for each of those reports are stated in the following sections.
The information collected by the Contractor during those surveys shall be used both for
the Contractor’s own purposes and for the continuous updating of data used by the Employer
for his Road Asset Management System (RAMS).
Electronic Road Asset Inventory Database: The Contractor shall record the information
collected during the various surveys (and other information, which may be furnished by the
Employer or by other third parties) in an electronic Road Asset Inventory database. In
order to ensure compatibility of the electronic database with the Employer’s Road Asset
Management System, the Contactor will propose the specific electronic format of the
database for approval by the Engineer. If the Employer does not stipulate a specific
format, the Contractor shall use an online database which can be accessed in real time by
the Engineer.
The Contractor shall also provide hardcopies (printouts) of the information from the
database to the Employer as reasonably requested. If so requested, the Contractor shall
liaise with the Employer and arrange for the delivery of hardcopies.
The electronic Road Asset Inventory Database shall include asset data and condition data
verified by the Contractor, covering the following:
• Pavements, including shoulders (Hard Shoulder / Emergency Lane)
• Slopes, Embankments and Cuttings
• Drainage facilities, gullies, culverts, lined channels, sumps etc.
• Signs, traffic signals and lighting installed
• Pavement markings
• Bridges and Major Structures
• All other road furniture (i.e. Safety Barriers, Lighting Points)
Requirements for measuring pavement strength: Road Strength (deflection) data are
required as input to the Employer’s Road Asset Management System and for the Contractorto
know the pavement condition and plan the needed interventions on the roads. If for any road
there is no reliable data on its pavement structure, the deflection measurementsshall
be complemented with pavement structure data obtained by trial pits everyone 5 km to
evaluate pavement construction and subgrade conditions. Output of the deflection
measurements shall be the basis for the calculation of the residual life of the pavement in
years, based on the expected total number of typical standard axles.
Measurement shall be by Falling Weight Deflectometer (FWD - Impulse Load Device). The
FWD shall be equipped with air and surface temperature sensors and a GPS location device.
The equipment to be used by the Contractor must be approved by the Engineer. Deflection
measurements shall be taken at 200m intervals for each traffic lane throughout the paved
network or as specified in IRC: 115.
Requirement for measuring road roughness: The Contractor shall measure the road
roughness in terms of the International Roughness Index (IRI) or Bump Integrator (BI). The
data is needed by the Employer for use under his Road Asset Management System and by the
Contractor for planning any needed interventions on the road. The equipment and data
required must comply to the following standards:
The measure of roughness is to be made in a continuous way in the wheel tracks of each lane
of the carriageway. The measuring equipment must be calibrated/validated as perthe
manufacturer’s recommendations and further calibration using several reference road
sections is also to be carried out in coordination with the Engineer. All roughness
measurements shall be executed under the supervision of the Engineer, utilizing a Class 1
precision Profile (ASTM E-950). They shall be reported as Bump Integrator (BI) in mm/km.
For damages not already repaired by the Contractor, the Contractor shall propose the
needed repairs, including any designs if necessary, and a program for carrying out the
repairs.
It is also the Contractor’s responsibility to report any event or incident of this nature to the
relevant authorities (Police, local Municipality and/or other public authorities concerned)
as soon as possible and to follow up on any actions taken by the police or other relevant
public authorities. If the damage is caused by third party intervention on theroad, the
Contractor must also actively try to stop such intervention by informing the intervening party
in writing (or verbally if writing is not feasible) of the damage being caused and the potential
physical and legal consequences of the intervening party’s action.
• The Contractor’s risk limitation for bearing the cost of necessary repairs after such
events shall be upto the limit of Insurance as stated in the Clause 11 of Contract Data.
Repairs beyond such limit of the Insurance amount as stated in the Contract Data are
the Employer’s Risk, provided that the Contractor has performed his obligations as
described above. In such cases the Contractor shall submit to the Employer a cost
estimate with a breakdown of the cost for repair. The Employermay instruct the
Contractor to repair the damage under a Change Order or a Work Order, as Emergency
Works.
The quality and the on-time submission of the “Road Asset Damage Report” is a
Management Performance Measure (MPM).
The Employer shall review the “Substantial Completion Report” and the “Full Works
Completion Report” within 14 days after receipt and provide comments, if any. If there are
comments requiring changes to the Report, a revised Report shall be submitted by the
Contractor within 14 days of receiving the comments. The “Certificate of Completion”,
which is a prerequisite for the repayment of the second half of the retention money at the
end of the Defects Liability Period, cannot be issued if the Full Works Completion Report has
not been submitted and approved.
The report shall accompany the Contractor’s request to the Employer for releasing the
Performance Security. The handing over report will also be subject to verification of
details of work completed vis-à-vis Contract scope by the Third Party Agency to beengaged
by the Authority for the purpose. Submission and Approval of the above report is a
prerequisite for issuing by the Employer of the Final Payment Certificate and release of
the Contractor’s Performance Security.
6. Specifications for Emergency Works
Emergency Works are designed to repair those damages to the roads under contract which
are caused directly by unforeseen natural phenomena with imponderable consequences
occurring either in the area of the roads or elsewhere, but with a direct impact on the roads.
“Unforeseen Natural Phenomena” are defined as follows:
Flooding where water levels rise above the crown level of the road resulting in complete or
partial washout of the culvert or road embankment causing disruption of traffic. Any damage
which results from insufficient maintenance of drainage structures will not be considered as
“emergency” and will need to be repaired from within the Routine Maintenance Services.
Major landslides (greater than 50 m3) which block the road carriageway and drains,encroach
onto the road surface and interrupts the flow of traffic or is unsafe. Can be caused by heavy
rains or earthquakes. Landslides within the right-of–way caused by overflow of poorly
maintained cut-off drains or catch dams will not be considered as an “emergency” and will
need to be removed as part of Routine Maintenance Services
Traffic accidents which interrupts traffic and causes insurmountable damage to the road.
Nevertheless, the Contractor will be responsible to provide full support to the police and
road users and arrange signing and cleanup of site or sanding as necessary is part of
Routine Maintenance Services.
6.2. Procedure for Requesting Emergency Works
The Engineer, upon receipt of the request and not later than 24 hours thereafter, will
evaluate the request made by the Contractor based on a site visit, and issue an order to
carry out the Emergency Works. The order will specify the type of works, their estimated
quantities, the remuneration to be paid to the Contractor and the time allowed for their
execution. The order may indicate a requirement for an engineering/geotechnical
assessment of the options for the permanent repairs to the site.
The total contract amount will include provisional quantities of Emergency Works during the
contract period, in accordance with the bidding data. The actual payments for Emergency
Work will be based on the tendered rates. The Emergency Works also includes a Provisional
Sum allowance in accordance with Clause 60 of the General Condition in the event of
addition unforeseen work is ordered by the Engineer.
If road traffic has been interrupted because of an emergency, the Contractor will follow the
provisions of the Traffic Management Plan included in his Quality Assurance Plan and take
the measures necessary (i) to reopen the road to traffic in the shortest time possible, and
(ii) to maintain the road open during emergency works, without being entitled to a specific
compensation for those measures. This relates particularly to trees or other objects which
may have fallen on the road, damage to access ramps to bridges, erosion of embankments,
collapse of slopes, traffic accidents, flooding, etc.
The Contractor will not be subject to payment reductions for the partial or full traffic
interruption on roads that are caused by events necessitating the use of Emergency Works
for rectification, provided that he acts according to these Specifications.
Bituminous concrete m3 20
Concrete m3 5
Embankment m3 250
PART-II
1. General
1.1 All materials, works and construction operations shall conform to the requirements
laid down in the “Specifications for Road and Bridge Works” (5th Revision), Ministry of Road
Transport and Highways, Published by Indian Roads Congress (IRC), New Delhi; IRC:82“Code
of Practice for Maintenance of Bituminous Surfaces on Highways” and IRC:SP:83 Guidelines
for Maintenance, Repairs and Rehabilitation of Cement Concrete Pavements” wherever
applicable. Where the Specification for a work is not given, sound engineering practice shall
be adopted to the satisfaction of the Engineer.
The Technical and Performance Specifications for Performance Based Maintenance
Contracts (PBMC) complement other specifications that are generally applicable in India for
use in the road sector. Notwithstanding the provisions of General conditions, the works and
materials used by the contractor shall comply with the requirements of relevant sections of
Ministry of Road Transport and Highways (MoRTH) specifications for Road and Bridge works
(5th Revision 2013, published by IRC) and these General Technical specifications shall form
part of the contract. Amendments to these MoRTH specifications shall be applicable to this
contract.
Reference to MoRTH Specifications.
The relevant sections from this document specific to, but not limited to, this contract
include the follows:
(a) General - Clauses 101 to 121
(b) Site Clearance - Clause 201, 202
(c) Earthwork, Erosion Control and Damage - Clauses 301 to 314
(d) Sub-bases (Non-bituminous) and Shoulders - Clauses 401 to 410
(e) Bases and Surface Courses - Clauses 501 to 520
(f) Geosynthetics - Clauses 701 to 708
(g) Traffic Signs, Markings and Road Appurtenances- Clauses 801 to 816
(h) Quality Control for Roadworks - Clauses 901 to 903
(i) Materials for Structures - Clauses 1001 to 1015
(j) Brick Masonry - Clauses 1301 to 1316
(k) Stone Masonry - Clauses 1401 to 1414
(l) Formwork - Clauses 1501 to 1513
(m) Steel Reinforcement (Untensioned) - Clauses 1601 to 1609
(n) Structural Concrete - Clauses 1701 to 1719
(o) Bearings - Clauses 2001 to 2010
(p) Open Foundations - Clause 2101 to 2108
(q) Sub-structures - Clause 2201 to 2210
(r) Concrete Super-structure - Clause 2301 to 2310
(s) Surface & Sub-surface Geotechnical Exploration - Clause 2401 to 2415
(t) River Training Work and Protection Work - Clause 2501 to 2510
(u) Expansion Joints - Clauses 2601 to 2615
(v) Wearing Coat and Appurtenances - Clause 2701 to 2709
(w) Repair of Structures - Clauses 2801 to 2815
(x) Pipe Culverts - Clauses 2901 to 2911
(y) Maintenance of Road - Clauses 3001 to 3005
2 Traffic Management Plan
2.1 The Traffic Management Plan shall describe the procedures to be followed
and the arrangements to be made whenever the contractor carries out the various types
of physical activities that are planned and foreseeable under the Contract. The TMP
must have been approved by the Employer before the Contractor commences work that
affects traffic flows or pedestrian safety. It shall show the methods to be applied to ensure
(i) that traffic can continue to use the road safely and with only the inevitable degree of
disturbance, (ii) the safety of road users and of people near the road. TheTMP shall
show the location, types and numbers of traffic safety devices, barricades, warning signs,
flagmen, by-pass roads, deviations and the like to be deployed under various types of
work sites and traffic restrictions, such as the partial and full closure of traffic lanes,
closure of road shoulders and moving roadside activities such as grass cutting, etc. It shall
also cover the removal of all necessary traffic diversions and the reinstatement of the
land used for such diversions. In the preparation of the TMP the Contractor must ensure
a reasonable balance between the efficiency of his work operations and the minimization
of disturbances for road users, including pedestriansand non-motorized traffic.
The Traffic Management Plan establishes the practices for traffic management at work
sites. The Traffic Management Plan must be developed by the Contractor and agreed with
the Engineer. The Contractor shall effectively implement all traffic management
requirements in accordance with MoRTH Clause 112 and contract Technical Specifications
in respect of all works under the Contract.
•Clearly define and document the responsibilities and chain of command for the
development, implementation and management of traffic control measures and
systems
• Establish the minimum requirements for temporary traffic control
• Establish the minimum geometric, cross section and surfacing standards for
temporary works
• Provide appropriate transitions and enable safe and efficient traffic flow into,
through and out of work sites
• Protect the Contractor’s personnel at all times
• Protect the Assets and the Contractor’s resources at all times.
• Meet the operational requirements for the road
The Traffic Management Plan must include at least the following:
The cost of implementing the TMP is deemed to be included in the rates or prices for
rectification Works, Emergency Works, and Routine & Periodic Maintenance Services.
2.2 All maintenance works on the road shall be carried out in a manner which would
cause least interference to the traffic. In stretches where resurfacing or riding quality
improvement works are to be taken up, the Contractor during execution of work shall
provide and maintain proper passage for traffic. Where it is not possible or safe to allow
traffic on part width of the carriageway, a temporary diversion of proper Specifications
shall be constructed by the Contractor at his cost. The Contractor shall take prior approval
of the Engineer regarding traffic arrangements during construction.
2.3 All arrangements for traffic during construction shall be considered as incidental to
the work and shall be Contractor’s responsibility. The Engineer shall determine the penalty to
be imposed on the Contractor for deficiency in compliance to the requirement.
3 Quality Control
3.1 Quality control on materials and workmanship is the primary responsibility of the
Contractor. Quality control shall be exercised in accordance with the Quality Plan approved
by the Engineer. The Engineer may, during and after construction test the quality of
materials and work in order to verify conformance with the prescribed Specifications. To
meet the requirements of the Contract, the Contractor would submit Operation and
Maintenance Manual within 15 days of mobilization on ground. Every year maintenance
schedule would also be submitted by the Contractor. Engineer would review and approve
the Operation and Operation and Maintenance Manual and Maintenance schedule, and the
Contractor would carry out the work in line with the approved Operation and Operation
and Maintenance Manual and Maintenance schedule
4. Operational Procedures
The Operational Procedures described in this Section are to be applied in the
implementation of Performance Based Maintenance Contract (PBMC).
The Payment for the work done as determined by the Contractor and certified by the AE/IE
will also be linked to the Web App based uploading of details of the work done with
reference to the Inspections so carried out as per directions of the Employer from time to
time in this regard.
The main purpose of the regular Formal Inspections is to verify the correctness of the
information presented by the Contractor in the Action Taken Report of remedial measures
about his own compliance with the Service Level requirements. The results of the Formal
Inspections are used for finalizing the monthly Interim Payment Certificate.
Formal inspections are scheduled in advance by the Engineer/ Employer and carried out
by the Contractor through his team with participation of the Engineer. The regular Formal
Inspections may be scheduled by the Engineer/ Employer once the Contractor has submitted
the ATR of remedial measures for any defect.
The Employer /Engineer must inform the Contractor’s Self-Control Unit of the date and
hour of the beginning of the Formal Inspection at least 12 hours in advance. The scheduling
of inspections between the Employer and the Contractor’s Team must be in writing, which
may include the use of e-mail or Web App/ Maintenance App. The Employer shall use the
official e-mail address of the Contractor which the Contractor must indicate in writing to
the Employer at the beginning of the Contract period.
Formal Inspections can also be scheduled to verify if the Contractor has remedied the causes
of earlier non-compliances within the time frame (Grace Period) granted by the Employer.
Failure to correct non-compliances within the specified Grace Period will lead to further
payment reductions for those non-compliances in the following Interim Payment
Certificate.
The Contractor is obliged to be present at the date, hour and location specified by the
Employer, providing the physical means (including equipment) needed for the inspection.
Both must have a signed hardcopy of the Contractor’s Action Taken Report of remedial
measure in hand. The main purpose of the Formal Inspection is to verify the information
provided by the Contractor in his Action Taken Report, for his own compliance with Service
Level requirements.
Should the Contractor fail to appear for (or participate in) a scheduled Formal Inspection,
having been requested to do so with at least 12 hours‟ notice, then the Employer/
Engineer may carry out the Formal Inspection without participation of the Contractor´s
staff. In such case, the determination of the Employer as to the nature and extent of the
defects and non-compliances detected shall be final and binding, with no possibility of
appeal or objection by the Contractor.
During the Formal Inspection the Employer and the staff of the Contractor shall travel in
the same vehicle along the road and stop as necessary, while verifying the information
provided by the Contractor in the Standard EXCEL Compliance Tables. This is to ensure that
the Contractor is immediately aware of any non-compliances identified by the
Engineer/ Employer. During the Formal Inspection any errors, discrepancies or
misrepresentations in the Compliance Tables presented by the Contractor, as well as their
locations and length, must be noted by the Engineer, communicated verbally to the
Contractor, and corrected on the Compliance ATR for Maintenance Services. The Employer
shall also indicate in the verified Action Taken Report any Grace Periods granted in
accordance with the Specifications for remedying the various non-compliances and inform
the contactor accordingly.
The Engineer must inform the Contractor of his intention to carry out a formal inspection
at least 12 hours in advance, indicating the exact date, hour and location where the formal
inspection is to begin. The Contractor is obliged to be present at the date, hourand
location specified by the Engineer, providing the physical means needed for the inspection.
In addition, the Employer shall also record any existing non-compliances which hadalready
been recorded during the previous month(s) and which have not been remediedby the
Contractor within the Grace Period granted by the Engineer, and apply thecorresponding
payment reductions for the full duration of the non-compliance.
During the formal inspection, the Engineer will prepare a brief Memorandum in which he
shall (i) describe the general circumstances of the Formal Inspection, including date, road
sections inspected, persons present, etc., (ii) show a list of all non-compliances detected
w.r.t Action Taken Report during the Formal Inspection and (iii) show the Grace Periods
granted by the Engineer to the Contractor for remedying each non-compliance. The specific
Grace Period for each non-compliance shall count from the last day of the Formal Inspection
during which the non-compliance was detected.
The Employer shall use the corrected Monthly Compliance Tables for Maintenance Services
for calculating the payment reductions for OPM‟s (and MPM‟s if applicable), and the total
amount to be paid for Maintenance Services. The Employer will then immediately transmit
his Memorandum and the corrected Compliance Tables to the Contractor, as input for the
Contractor‟s Monthly Statement.
If the Employer does not send his corrected Compliance Tables to the Contractor by the
7th day of the calendar month, the delay shall be added to the Contractor’s deadline for
submitting his Monthly Statement, which is normally due on the 10 th day of the calendar
month as per the General Conditions.
Daily Inspections by Contractor: All works being executed on a day shall be reported in
the daily report by the contractor and also defects w.r.t to the most important items to be
reported in this inspection. A tentative list of items for guidance are as under:
(i) Potholes
(ii) Raveling/ Rutting/ Cracking
(iii) Embankment Slope Protection & Rain cuts
(iv) Edge drop at shoulders
(v) Unevenness, vegetation growth & water stagnation on shoulder
(vi) Drainage Condition
(vii) Cleanliness of median & Vegetation affecting sight lines
(viii) Missing or deformed or non-reflective road signs/hazard markers
(ix) Missing or damaged crash barriers
(x) Road Studs
(xi) Pedestrian Guard Rails
(xii) Non-functioning Highway Lighting/Solar Blinker/ECB
(xiii) Riding quality at expansion joints
(xiv) Cracks/ settlement/ tilting/ spalling of all elements of sub-structure & super
structure
(xv) Cleanliness and functionality of toilets
(xvi) Theft or Vandalism of any highway asset
(xvii) Encroachment of NH Land
(xviii) Damaged Vehicles/ Dead Animals/ fallen trees, poles, debris on road.
(xix) Works executed on the day for the RFI/IFI Raised.
Note: Inspections w.r.t. all such requisite items/ assets defined in Annexure-E shall be
carried out as per specified frequency of inspection.
However, If during regular inspections, any defect in any Cross Drainage works / structures
comes in the notice of the Contractor / Engineer / Employer, then Contractor has to do
the detailed inspection of that Cross Drainage work / structure and take the remedial
corrective action as per the contract.
The conduct of Informal Inspections by the Employer and the notification of any identified
non-compliances in no way affects the requirement for the Contractor to continuously monitor
road conditions and his own compliance with required Service Levels, and to rectify all
defects. It is the duty of the Contractor‟s team, not of the Engineer, to identify defects and
ensure their rectification in a timely manner.
End-of-Contract Inspections: The Employer and the Contractor shall undertake joint
inspections as needed, at the following times:
• No later than six (6) months before the end of the contract, with the purpose of
determining the extent of works and activities required to be completed before the end
of the contract execution period;
• No later than three (3) months before the end of the contract, with the purpose of
identifying any additional remedial works that need to be completed before the end of
the contract period; and
• No later than one month before the expiration of the Defects Liability Period, in order
to confirm that all required remedial works have been adequately completed.
• Any other inspections found necessary by the Engineer.
“First-day” Payment Reduction: Payment Reductions in general are meant for the
Contractor to continuously and proactively identify upcoming non-compliances and to carry
out necessary remedial measures quickly. The “First-day” payment reduction in particular
has the objective to ensure that the Contractor remedies defects quickly within time limit for
rectification prescribed in Annexure-E, without waiting for the verification Inspection as
specified in time schedule. The “first-day” payment reduction is the payment reduction for
one day of non-compliance on due date after lapse of the time limit for rectification in
Annexure-E. To be clear, “First-day” is the immediately succeeding day after last day of
the time limit given for rectification in Annexure-E. To be clear, “First-day” is applied
immediately at the instant the time limit given for rectification in Annexure-E is elapsed and
defect is not rectified. The reporting time, time limits for rectification and ATR submissions
time are recorded at hourly if not minute basis as there are defects in Schedule
E which have rectification period specified in exact hours as well.
No time limit for payment reductions: If the Contractor fails to remedy a non-compliance
for which a payment reduction has already been applied during a Formal Inspection, the
respective payment reduction will continue to be applied in the same way to the following
Monthly Statement(s) for that particular cause of non-compliance, until the non-compliance
has been remedied, without a time limit being applied.
Multiple non-conformances and limitation for payment reduction: Payment reductions due
to specific non-conformances are cumulative. If a one-km section of road has several non-
compliances, then the payment reduction to be applied is the sum of the payment reductions
for each individual non-conformance. When an OPM (such as OPM-2) includes a group of Sub-
Measures (e.g. patching, cracking in Pavement, Potholes, etc.), then if theroad suffers
from several of these defects, the overall Payment Reduction is equal to the sum of each
individual payment reduction per type of defect. For accumulated OPM non- conformances
within any one-km section, the maximum cumulative payment reduction in one month shall
however be limited to 100 percent of the monthly lump-sum amount for Maintenance Services
payable for that one km of road.
The calculation of Payment Reductions for OPM’s is to be carried out as described below:
After the verification of Action Taken Report (ATR) for any defect, the Engineer/ Employer
shall apply the payment reductions for repair of that defect in the following way:
• For any non-compliances found during the verification inspection, the day after lapse of
the initial rectification period as per Annexure-E is to be considered as the “first day” of
non-compliance. The corresponding “First-day” payment reductions must be applied
immediately for the current month. Also, if the Contractor does NOT remedy the non-
compliance within the Grace Period besides the First Day payment reductions a further
payment reduction as per Note 1 of Clause 5 above shall be levied.
• Deleted
No.
1 OPM-1.1 1 0
2 OPM-1.2 1 1
3 OPM-1.3 0 0
4 OPM-1.4 0 0
5 OPM-1.5 0 0
6 OPM-1.6 1 0
7 OPM-2.1 1 1
8 OPM-2.2 0 0
9 OPM-2.3 0 0
10 OPM-2.4 0 0
11 OPM-2.5 0 0
12 OPM-2.6 1 1
13 OPM-3.1 0 0
14 OPM-3.2 1 1
15 OPM-3.3 0 0
16 OPM-3.4 0 0
17 OPM-3.5 1 0
18 OPM-3.6 0 0
19 OPM-4.1 1 1
20 OPM-4.2 0 0
21 OPM-4.3 0 0
22 OPM-4.4 1 0
23 OPM-5 0 0
24 OPM-6 0 0
25 OPM-7 1 1
26 OPM-8 0 0
27 OPM-9 0 0
28 OPM-10 0 0
Total 10 6
10% of 10 would be 1, which means that if the number of Rejected ATR‟s is higherthan
1 than the Payment reduction is triggered and to be applied.
mount of payment reduction: 5% of Monthly Rs. 5,25,000/-
Payment Amount of Routine Maintenance
for the full road section, resulting in INR
Note 1: Contractor will prepare the Monthly Table by furnishing the data regarding the
number of Action Taken Reports submitted to Engineer in writing (email) or through IT
solution or Web App/ Maintenance App as prescribed by Employer.
Note 2: Engineer shall carry out Inspection for the verification of remedial measures
reported by the Contractor as per prescribed inspection timeline. If any remedial measure
is not accepted by the Engineer, then the same will be added in the List of Rejected Action
Taken Reports. Number of Rejected ATRs will be used for the calculation of deduction for
Non-Compliance of OPM-11.
Deployment of
Ambulance Vehicle
including staff as per
Emergen IRC SP:84/87
cy specifications
Emergency
Response
System - 1 Response Functionality of 1.00 3.00
System Vehicle Tracking
Operatio
ns System (VTS)
Maintenance of
Proper registers
(Incident
Management,
Equipments)
Deployment of Route
Patrol Vehicle
including staff as per
IRC SP:84/87
specifications
Functionality of
Vehicle Tracking 1.00
System (VTS)
Maintenance of
Proper registers
(Incident
Management,
Equipments)
Deployment of crane
of capacity not less
than 25 MT
Maintenance of 1.00
Incident Management
Register alongwith
Customer
Satisfaction Report
Documentation of
safety arrangements
Work
Zone Work Zone Review of safety
1 Safety arrangement 1.00 1.00
Safety
Validation of
documentation
Documentation of
action against
encroachment
Encroach Encroachm Validation of
ment 1 ent 2.00 2.00
documented
temporary/
permanent
encroachments
Usage of Mechanical
Overall Equipment 1.00
Project
Cleanline 1 Cleanliness 3.00
ss ROW 1.00
Project Facilities 1.00
Video Surveillance
System
Mobile Radio
Communication
System
Video Incident
Advance Detection System
Traffic (VIDS)
Manageme Vehicle
nt Systems Speed DisplayActuated
System
(ATMS)
Emergency Roadside
ATMS Telephone System
1 Variable Message 2.00 2.00
Sign (VMS) system
Meteorological Data
System (MET)
Automatic Traffic
Counter-cum-
Classifier
Travel Time
Estimation System
Note 1: The penalties calculated above are as per day penalties and would be applied on
non-compliance of service level immediately after the completion of specified Time Limit
of Rectification given in Annexure-E, which is denoted as C in the formula.
Note 2: In addition to above payment reduction, defect ignore penalty shall be levied as Rs.
1000/- per day of Payment Reduction on incremental daily basis after grant of grace period
for all days of non-compliance (starting from the second day after initial deduction and until
the non-compliance is remedied), which is denoted as D in above formula.
Note: The above criteria is only indicative and may be suitably modified as per
technical prudence of the tender issuing division/department.
Note 4: All Rates are after application of tender discount quoted by the contractor.
Note 5: Penalty for repeated non-compliances: In case the total payment deduction is
more than 50% for continuous three months or deduction is more than 25% for carriageway/
pavement parameter then Engineer/Employer has to issue cure period cum intention to
terminate notice of 30 days and thereafter the contractor has to achieve compliance of at
least 80% of all parameters & 95% compliance in carriageway/pavement parameter
respectively, by the end of the cure period duration, failing which employer can
proceed with termination of the contract stating the default of the contractor. In such cases
Employer shall also be entitled to get the work executed at Risk & Cost of the Contractor.
Note 7: Add other project facilities in payment reduction scheme if available on the
project stretch and part of the scope of instant OPBMC contract
Payment Procedures
5.2.1 Payment for Initial Rectification Works (Bill No. 2):
As indicted in Bill of Quantities Chapter of Section-9
The adjustment to the payment of the monthly Lump Sum payable for MaintenanceServices,
after any additions and deletions of roads or road sections, shall be calculated in accordance
with the following formula:
LSn= LS+/- [Ln (Km)
X
Lump Sum Price per KM for Maintenance Services of roads that are similar to those
added or deleted]
LS = The value of the Total Lump Sum as stated in relevant BOQ applicable
for original length of project as per Contract.
LSn = The value of the adjusted Lump Sum applicable for NPS for the
Contract after the addition or deletion of road/road sections.
Ln = the length of the added or deleted road/road section
The Contractor is bound to calculate the reduction in the contract price (in case of
eliminating road length) on the basis of the actual rates and prices stipulated in the contract
which are applicable to the services and works on the specific road lengths (sections or
segments) which are to be eliminated.
6.4 Deleted
a) The Contractor shall, throughout the execution and completion of the Works, have
full regard to the safety of all persons deployed to the Project Highway for completion
of Works and keep the Site in an orderly state appropriate to the avoidance of danger
to such person, establish and execute traffic diversion and traffic management in
accordance with the safety requirements specified under Applicable Laws and the
Contract Agreement;
b) The Contractor shall provide and maintain at its own cost all cones, caution tapes,
batons, sign boards lights, guards, fencing, warning signs and flagmen, when and
where necessary or required by the Contractor or by any duly constituted authority
for the protection of the Works or the safety of the public or others;
c) The Contractor shall ensure that all the personnel engaged by it for the execution
and completion of Works under this Agreement are provided safety training, in
accordance with Applicable Law;
d) The Contractor shall take all reasonable steps to protect the environment and to
avoid damage and nuisance to person or to property of the public or others resulting
from pollution, noise or other causes arising as a consequence of the Works;
e) The Contractor shall comply with the relevant standards and practices in accordance
with the provisions of the Contract Agreement and all Applicable Laws and regulations
of the authorities in relation to safety and health in the executionof Works. The
Contractor shall be responsible for getting all relevant permits, permission, etc. from
all government agencies for their Works as given in Table 7.1 below;
f) Under dense traffic conditions and lane closures, the Contractor is required to provide
suitable and requisite manpower to supervise the Works in compliance with the
project requirements;
g) The Contractor shall provide all personal protective equipment (PPE) and safety
equipment i.e. safety helmets, safety jackets, safety shoes, safety cones and red
flags to the labours working on the Project Highway and at the Base Camp. Employer
will not be responsible for any fatal, major/minor injuries of the personnel related
to the Contractor;
h) The Contractor shall provide necessary medical facilities, hospitalization and medical
treatment as required for the labours engaged under their scope and shall indemnify
the Employer from such liabilities if such losses are suffered and incurred by the
Employer due to reasons not attributable to the Employer or its officials, partners,
affiliates, officers, employees, representatives, agents etc;
i) The Contractor shall obtain all necessary safety licenses and permits required under
all Applicable Laws for its labour/employees. The Employer will not be held
responsible for injury, death, partial disability, disease of occupational nature, loss
arising from unavoidable circumstances in the work area to the persons/employees.
The Contractor shall be responsible for the liability resulting from, brought for, or
on account of any personal injury or property damage of any persons or attributable
to any work performed under or related to this Agreement, resulting in whole or in
part from negligent acts or omissions of the Contractor, any subcontractor, or any
employee, agent, or representative of the Contractor or any subcontractor.
j) The Contractor shall ensure to assess and monitor the hiring, rules of conduct,
training, equipment and monitoring of appointed security personnel. Guards shall be
trained on the use of force, and that they act in alignment with the Voluntary
Principles on Security and Human Rights;
k) The Contractor shall obtain the relevant environmental licenses and permits and
comply with their requirements to the extent required for completion of the Works.
The Contractor shall comply with terms and conditions of environmental permits,
licenses, approvals if any procured by Employer in relation to execution of Works and
intimidated to it by the Company;
l) The Contractor shall establish an effective Grievance Redressal Mechanism for its
labours, workers and employee which will be monitored by the Employer;
m) The Contractor shall ensure that all the newly recruited contract workers, labours,
workmen, personnel have undergone the environment, health and safety training.
Further, an orientation/induction programme shall be organised by the Contractor on
educating the contract labour about Company’s internal rules and regulations
including governing hours of work and over-time, minimum wages and other
requirements/benefits as per labour laws and Grievance Redressal Mechanism;
n) educating them about Do’s and Don’ts aspects pertaining to health, safety and
environment; and
214
SECTION – 9
DESCRIPTION OF WORKS: BID FOR PBMC O&M work of 4 Laning of Simga-Sargaon (PKG -
II) of NH-200 section from Km 48+580 to Km 91+026 and Sargaon- Bilaspur (PKG - III)
of NH-200 section from Km 91+026 to Km 126.525 section of Raipur-Bilaspur in the
State of Chhattisgarh. on Performance based Maintenance Contracts (PBMC)
Reference letter No.
Dear Sir,
Having examined the site of works and Bid Documents, comprising Instructions to Bidders, Scope of
Works, Conditions of Contract, Technical Specifications, Bill of Quantities and schedules for the
execution of the above named works, we, the undersigned offer to execute and complete
such works and remedy any defects therein in conformity with the said bid documents at
tender premium as quoted in the Financial Bid.
2. We undertake, if our Bid is accepted, to commence the work within fifteen (15) days of
receipt of the order to commence, and to complete and deliver the sections and whole of
the works comprised in the contract within the period stated in the bid hereto.
3. If our Bid is accepted, we will furnish Performance Security (ies) in the form of a Bank
Guarantee to be jointly and severally bound on us, in accordance with the Conditions of
Contract.
4. We agree to abide by this Bid for a period of one hundred twenty (120) days from the last
date fixed for Bid Submission and it shall remain binding upon us and may be accepted
at any time before the expiry of that period.
5. We confirm our agreement to treat the Bid document and other records connected with the
works as secret and confidential documents and shall not communicate information
contained therein to any person other than the person authorized by the Employer or use
such information in any manner prejudicial to the safety and integrity of the works.
6. Unless and until an agreement is prepared and executed, this Bid, together with your
written acceptance thereof, shall constitute a binding contract between us, but without
prejudice to your right to withdraw such acceptance without assigning any reasonsthereof.
7. We understand that you are not bound to accept the lowest or any bid you may receive.
Signature of Witness
Name of witness
Address of witness _
Description of works
Financial Bid – Summary Abstract
of Bid Cost
Note: The rates and prices tendered in the BOQ shall include all equipment, tools, spares,
labour, supervision, overheads, consumables, materials, erection, maintenance, testing of
input material delivered, profit, taxes (excluding GST) and duties together with general
risks, liabilities and obligations set out and implied in the contract and other incidentals to
comply with the requirements of Standards and Specifications. The bids will be evaluated
based on Bid Price “D‟.
BILL OF QUANTITIES
1. Preamble
i) The Bill of Quantities (BOQ) shall be read in conjunction with the Instructions to Bidders,
Conditions of Contract, Road Maintenance Standards and Specifications for Road
Maintenance Works. The following bills are included in this Contract:
I. Bill 1: Routine Maintenance Services in the form of the amount of the monthly lump-
sum payment demanded by the bidder according to the conditions of Contract. This will
be the monthly amount applicable throughout the duration of the Contract. There will
be no additional payment admissible on any context for ensuring the stipulated service
levels as per the Contract except as specified in Clause 6.2 of Part-II of Section-7
(Specifications for Road Maintenance Works and Operational Procedures)
II. Bill 2: Initial Rectification Works, in the form of a lump-sum amount while indicating
the quantities of measurable outputs to be executed in order that the road achieves the
performance standards specified in the bidding documents. The quantities given are for
bid purpose, but the contractor has to achieve the minimum specified intervention levels
and the payment to be made based on lump sum prices per km. The work programme for
each km of Initial Rectification with items wise quantities to be executed in each
kilometer along with financial weightage of all such works in that particular km shall be
submitted by the Contractor to Engineer. The Engineer will either accept or request the
contractor to modify the detailed work program km wise as per the actual condition of
site within 15 days of receipt of the work program. Decision of the Engineer shall be final
in regard of IR works to be executed at site. The Contractor shall request payment for
Initial Rectification Works in his Monthly Statement, which must be supported by the
Monthly Progress Report. The payment for the Initial Rectification works shall be made
monthly after effecting the reductions for taxes, retention money and advances etc.,
based on the completed length km wise on which such work has been completed as per
the approved work program by the Engineer. All such executed works shall be duly verified
and certified by the Engineer based on the joint site inspection.
There will be no additional payment admissible for works which might be executed
by the Contractor beyond the BOQ in the bid document under this Bill for ensuring the
stipulated service levels as per the Contract.
Sample calculation for payment :-
For Eg: The total Lumpsum Amount for Bill 2 (after tender discount/premium) is Rs.
50,00,000/-. Further, as per approved work programme the following weightages have
been finalized for Initial Rectification Works for 50 km (0.00 km to 50.00 km) project
stretch:
Chainage of Section Length of Section Financial Weightage in Total Bill 2 (in
%)
Km 0.00 to Km 1.00 1 15%
Km 1.00 to Km 2.00 1 0.5%
Km 2.00 to Km 30.00 28 0%
Chainage of Section Length of Section Financial Weightage in Total Bill 2 (in
%)
Km 30.00 to Km 31.00 1 25%
Km 31.00 to Km 32.00 1 5%
Km 32.00 to Km 33.00 1 1.5%
Km 33.00 to Km 34.00 1 13%
Km 34.00 to Km 35.00 1 18%
Km 35.00 to Km 48.00 13 0%
Km 48.00 to Km 49.00 1 12%
Km 49.00 to Km 50.00 1 10%
Total 50 km 100%
In case in month “M”, the contractor does work from km 2.00 to km 33.00, then due the
payment for the month “M” shall be worked out as = Rs. 50,00,000 x [(30.00-2.00)x 0% +
(31.00-30.00) x 25% + (32.00-31.00) x 5%+ (33.00-32.00) x 1.5% = Rs. 15,75,000/-]
III. Bill 3: Periodic Maintenance Works, in the form of lump-sum amount per km length,
that will be measured and paid in accordance with the progress in the execution of those
measured outputs; periodic Maintenance works also includes road markings, provision of
road studs, gravel filling to match the shoulder level after laying renewal coat, which will
be paid on measured inputs basis.
The Employer shall provide the indicative assessed quantities of items along withamount
of such items as per applicable SOR i.e. the current SOR of the State Govt. wherein the
Highway stretch is located. The Contractor needs to make his own assessment of the
Items, Quantities and cost to maintain the Highway Stretch as per Service levels stipulated
in Contract Standards and Specifications, while quoting the percentage above or below
over and above the indicative estimated amount by the Employer.
Sample calculation for payment:-
In case the Lump Sum rate per km (for all lanes) for Periodic Maintenance Works (after
tender discount/premium) is Rs. 10,00,000/- and in any month “M”, work of PR has been
executed by the contractor for Km. 0.00 to 15.00 Km. (for all lanes) including all
associated works such as pavement markings, road studs etc. (as given in the BOQ) and
meeting the required service levels, then the payment for Periodic Maintenance Works
for Month “M” shall be worked out as = Rs. 10,00,000/- x (15.00-0.00) = Rs. 1,50,00,000/-
.
IV. Bill 4: Emergency Works: This Bid has indicative quantities and shall be executed as
per Project requirements with approval of the Engineer in emergency situation. Payments
will be made for each item on actual basis, in the amount of a lump-sumvalue
estimated by the Contractor and approved by the Engineer, on the basis of the estimated
quantities and on the quoted unit prices. In case of variation/ additional work items,
Materials, Labour, Equipment, then the provided in the indicated BOQ, are required,
payment for same will be admissible under variation at rates as per rates provided in the
BOQ adjusted for percentage above or below of the Bidder on total indicative amount of
the work assessed by the Employer.
i) In case of variation/ additional work items, Materials, Labour, Equipment,
then the provided in the indicated BOQ, are required, payment for same will
be admissible under variation at rates provided in the BOQ adjusted for
percentage above or below of the Bidder on total indicative amount of the work
assessed by the Employer. For Non-BOQ items, applicable SOR rates ason bid
due date shall be applicable adjusted for percentage above or below of the
Bidder on total indicative amount of the work assessed by the Employer.
ii) The rates and prices tendered in the BOQ shall include all equipment, tools,
spares, labour, supervision, overheads, consumables, materials, erection,
maintenance, testing of input material delivered, profit, taxes (excluding GST)
and duties together with general risks, liabilities and obligations set out and
implied in the contract and other incidentals to comply with the requirements
of Standards and Specifications.
iii) Bill No. 1 shall include for costs associated with Contract obligations which are
not specifically provided for elsewhere, including, but without being limited
to; the provision of insurances, Security, implementing Quality Plan
requirements, HIV-AIDS Prevention measures, the maintenance and operational
costs of MMU, all social, environmental, safety and traffic management
requirements, conducting various Inspections, surveys etc.
iv) Performance assessment for performance based items of work, shall be done
through inspection by the Engineer at least two times during the month and
overall rating can be done on the basis of average of assessments made during
the inspection.
v) The Contractor shall submit at least once in two months video recording of
condition of the Project Highway with special emphasis on performance-based
items.
vi) For performance-based items of work, the Contractor shall be entitled for
receiving payment proportionate to the average percentage performance
assessed for achievement between as specified in Operational Performance
Measures
vii) General directions and descriptions of work and materials are not repeated or
summarized in the Bill of Quantities. References to the relevant sections of the
Contract documentation shall be made before entering rates or prices against
each item in the Bill of Quantities.
viii) The method of measurement of completed Routine Maintenance Services shall
be in accordance with the measurement and payment provisions of the relevant
section in the Specifications.
ix) Arithmetical errors discovered prior to award of the Contract will be corrected
by the Employer pursuant to the Instructions to Bidders.
BILL NO. 1: ROUTINE MAINTENANCE SERVICES
2. Payment shall be made in accordance with the actual performance of the Contractor
and compliance with the Service Level criteria given in the Contract Specifications, for the
Highway Stretch. Failure to meet such Service Levels will result in payment reductions in
accordance with Clause 5.2 of Part-II of Section 7 (SPECIFICATIONS FOR ROAD MAINTENANCE
WORKS AND OPERATIONAL PROCEDURES) and the Performance Specifications.
2. The total indicative items, quantities and rates by the Employer for the periodical
Maintenance works is as under:
Length of Project = 77.945kms (L)
(ii) (ii) Granular surfaces treated with primes @ 0.30 kg /Sqm 135652.16 Sqm. 22
29,84,347.52
Bituminous Overlay (Providing and laying bituminous
concrete with minimum 100-120 TPH capacity batch type
hot mix plant using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.0 to 6.0%
by weight of total mix of mix and cement as a filler,
5.05 transporting the hot mix to work site, laying with a
-
hydrostatic paver finisher to the required grade, level and
1.3 alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all
respects)
(i) for Grading-I(19 mm nominal size) with bitumen 5.2 %
[Add extra to the Rate of Bituminous Concrete with
(i) 6783 Cum 10423
bitumen, if Bitumen Grade VG-40 is used instead of 7,06,95,123.18
Bitumen Grade VG-30 in the items above.]
2 ROAD PROPERTY MANAGEMENT AND OTHER MAINTENANCE
Road Marking with Hot Applied Thermoplastic Compound
with Reflectorising Glass Beads on Bituminous Surface
(Providing and laying of hot applied thermoplastic
compound 2.5 mm thick including reflectorising glass
2.1 8.13 beads @ 250 gms per sqm area, thickness of 2.5 mm is 104135 Sqm
713.00 7,42,47,912.76
exclusive of surface applied glass beads as per IRC:35 .The
finished surface to be level, uniform and free from streaks
and
holes.)
This Bill has indicative quantities and shall be executed as per project need and with
approval of Engineer. Separate work order to be issued by Engineer for such works. The same
will be payable at rates provided in the BOQ adjusted for plus/ minus quoted percentage by
the Bidder. For Non-BOQ items, payment shall be made on applicable SOR rates as on 28
days before the bid due date adjusted for percentage above or below as per the contract on
total indicative amount of the work as assessed by the Engineer with due escalation as per
the contract.
2. The overall quoted percentage by the Bidder on the indicative amounts for the stipulated
schedule items as below only shall be considered. Payment for the stipulated items will be
made on actual execution and its measurement basis after application of tender
discount/premium on the rates given by the Employer below:
Similar to 1.04
4.A.2 Rubber Tyred Roller (15 100 Hour 1200 120000
(vii)
Tonne)
Similar to 1.04
4.A.5 Backhoe (JCB) 100 Hour 1150 115000
(vi)
Similar to DSR
4.A.6 2021, S.no. Loader (1/2 m3) 100 Hour 910 91000
0052
similar to 1.04
4.A.9 Hotmix Paver 100 Hour 1000 100000
(x)
Similar to 1.04 Vibrating Smooth Drum
4.A.10 100 Hour 600 60000
(vii) Roller 10 Tonne
4.B Materials
Similar to 1.05 Supply, Deliver and Place 10
4.B.1 100 Cum 1018 101800
(vii) mm Sealing Chips
Similar to 1.05 Supply, Deliver and Place 20
4.B.2 100 Cum 1206 120600
(v) mm Fine Crushed Rock
Supply, Deliver and Place 75
4.B.3 Similar to 4.14 100 Cum 1861 186100
mm Wet mix Macadam
Supply, Deliver and Place
4.B.4 Similar to 4.19 100 Cum 632 63200
Shoulder Material
Supply and Place Semi-
4.B.5 Similar to 5.03 100 Cum 6648 664800
Dense Bituminous concrete
Supply and spray 80/100
4.B.6 Similar to 5.14 100 Cum 15799 1579900
Bitumen
4.C Labour:
4.C.1 Supervisor 100 Day 478 47800
4.C.2 Ministry of Foreman 100 Day 418 41800
Labour &
Employement,
4.C.3 CG minimum Labourer 100 Day 478 47800
wages
(attached)
Total (indicative) amount of Bill 04
34,17,300.00
SECTION – 10
SUMMARY OF ASSETS