JSA For Installation and Testing of Above Ground Drainage Piping 080324
JSA For Installation and Testing of Above Ground Drainage Piping 080324
RSG-HS-FRM-0001
RED_SEA_GLOBAL
Section I -Enter general information about the site and job task.
Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment requirements.
Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.
Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row between steps in c a s e you need
1 them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to accommodate all job steps.
Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking about different types of
2 hazards and energy sources.
List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy provided to trigger your
thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more effective at minimizing the severity and/or likelihood of
3
an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue to step 4. Otherwise, repeat steps 2-3 for each of the job steps identified, then
Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job step. Use the severity table
4 provided. Write the severity number in column D (Severity).
Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the likelihood table provided. Write
5 the likelihood number in column E (Likelihood).
Multiply the severity number by the likelihood number and enter the product in column F (Risk).
6
Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
7
🗸 Very low and low risk ratings of 1-2. This level is generally considered acceptable provided that all control measures are applied.
Medium risk ratings of 3-9. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be documented on the risk
🗸
assessment form.
High and Very High-Risk ratings of 10-25. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk to a medium or low
🗸 level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager must personally review the activities
with a High or Very High residual risk score and approve additional control measures by signing off the JSA
Repeat steps 2-7 for each of the job steps identified.
8
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or facility Manager must review
and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided for crew members to sign the JSA if desired.
Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)
RED_SEA_GLOBAL
Reference Table in completing Section III – Job Safety Analysis (Column C – Control Measure)
Controls Examples
Elimination
(Remove the hazard altogether)
Substitution
(Replace the material/process with a less
hazardous one)
Engineering/Isolation
(Design effective control measures to protect
people and the environment)
Warning
(Alert people to the hazards)
Administrative
(Provide training, procedures, etc.)
PPE
Less (Personal Protective Equipment)
Effective
Impact On Chances of
Severity Level &Likelihood Level Probability&
Occurrence
People Equipment / Property
Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Risk Matrix
Very Low Low Medium High Very High
Likelihood Severity 1 2 3-9 10-16 20-25
1-Negligible 2-Minor 3–Moderate 4-Significant 5-Major
Medium Hgh High High High High and Very High-Risk ratings of 10-25.
5 – Almost Certain
(5) (10) (15) (20) (25)
Additional control measures must be implemented to further reduce the High
Medium Medium High High High
4 – Likely and very high risk to acceptable level.
(5) (5) (12) (16) (20)
3 – Possible
Medium Medium High High Note: The Construction Director/Manager or Facility Manager must personally
-5
(5) (5) (12) (15)
review the activities with a High or Very High residual Risk score and approve
Low Medium Medium Medium High
2- Rare suitable additional control measures by signing the JSA.
(2) (5) (5) (8) (10)
Very Low Low Medium Medium Medium
1 – Unlikely
(1) (2) (5) (4) (5)
Details
Company Name
Program / Facility / Operations Program 03 - Coastal Village Economic Homes Contracting Co
JSA /Risk Assessment Title Mechanical (Installation and Testing of Above Ground Drainage piping Category New
Plant Tools & Equipment Require : Measuring Tapes, Drilling Machine, Hammer, Water Spirit Levels, Certified Mobile Scaffolds / Step Ladder, Pipe Area
Cutter, Hacksaw, Speed Cutter
Work Scope/Description INSTALLATION AND TESTING OF ABOVE GROUND WATER SUPPLY NETWORK, PIPING, FITTINGS, DEVICES AND VALVES all over the OAF & TC project
Musculoskeletal injuries Manual lifting techniques and awareness 3 3 9 Daily TBT, STA, Pre-Task Briefing for site 2 1 2
Manual handling injuries material to be posted on site workers on daily activities.
Sharp edges Employ proper lifting techniques Avoid excessive manual handling
No lifting allowed over 25 KG
Additional help shall be asked for
complicated and heavy loads
Segregate pedestrian movement paths
from equipment movement paths
Mechanical aids (trolleys, pallet jacks) to
be used wherever possible
Mechanical failure Inspect the vehicle as per checklist prior 4 3 12 Full supervision by construction team, 2 1 2
Uninspected equipment’s to take in operation Safety officer
Incompetent operators/personnel Certified operator and driver should
operate the vehicles
Adhere to the site traffic rules and speed
limits.
Third party inspection to be available for
the equipment as per RSG MVA
procedure requirements
Third party certificate to be available for
the operators as per RSG MVA
procedure requirements.
No one to come under the suspended
loads.
Cuts and abrasions Flying bits Correct PPE to be worn (face shield, 4 3 12 Regular conduct the trainings for the safe 2 1 2
Burns gloves, safety glass, helmet, safety shoes) procedure of hot work
Pipe Cutting Fires Assign competent workers for handling Wear apron for the grinding activities
power tools / hand tools Regular tool maintenance
Electrocution
Erect fire blankets, put barricade and Use ear plug or earmuff
Fall of personnel/equipment
signage, and assign a competent fire
Speed cutter watch person along with hot work
Hand tools permit for any hot work activity Remove
the combustible material from
surroundings
Make sure emergency fighting
equipment (fire extinguisher, running
water source) are available nearby.
Inspect the cords for
Cover the drains around 75feet hot work
area
Inspect the cords for electrical tools and
color code
Visual inspection of all tools before use
No damaged tools to be used
Assure that connections are secure and
properly plugged/insulated when using
power tools
Pipe Installation at Heights Falls from height Use chain block to lift the heavy weight 3 3 9 Conduct work at height training 2 1 1
Dropped tools pipes Good supervision of activity
Improper working platform Use designated platforms/MEWPs for Regular inspection of fall protection
work at height
Train workers on fall arrest systems
Use A type ladder with working platform
Use designated platforms/MEWPs for
work at height
Make sure that the work at height
support/platform is inspected
Use fall arrest/fall restraint systems to
avoid fall
Store equipment and material away
from edges. Toe boards/edge protections
to be used
Tools to be attached with tool-lanyards
to avoid fall when working at height
Pipe Joint Testing Hydro Testing of Pipe Joints Follow proper testing procedures 3 4 12 Conduct pre-test inspections and checks 2 1 2
Water leaks Wear appropriate PPE (gloves, face for each equipment’s
Pressurized system hazards shields, rubber boots) Train workers on emergency response
Ensure area is clear of non-essential procedures
Slips and trips
personnel Provide spill containment materials
Chemical exposure (if additives are used)
Use pressure relief valves Regularly inspect hoses and connections
Properly secure testing equipment with Use non-toxic additives if required
whip check Provide emergency response training
Cleanup and Demobilization Slips, trips, and falls Maintain clear walkways Conduct post-work site inspection 2 1 2
Waste handling hazards Follow waste disposal guidelines 3 2 6 Ensure proper labeling and storage of
waste materials
Staff engaged in working shall be aware
of Emergency call out procedure.
Fire Immediate help shall be called by Emergency no. posters shall be displayed
calling EOC number 011 212 7111 at sites and rest shelters
Unexpected Event Explosion 2 1 2
considering the emergency situations.
Emergency condition Full supervision by construction team.
First Aiders will be available on site. 3 3 9
Safety supervisor.
Standby emergency vehicles as
Daily TBT, Pre-Task Briefing for site
applicable
workers including drivers on daily
Do not panic in emergency situations activities.
and respond correctly.
All employees must be included in the
emergency drills
The Project Emergency Preparedness
Plan will be communicated and
implemented.
Emergency no. posters shall be displayed
Employees will be trained how to act in
Uncertainty/ at sites and rest shelters.
case of Emergency.
Emergency Response dangerous condition Full supervision by construction team. 1 2 2
Assemble point and direction sign Safety supervisor.
Fatality should be displayed on site. Daily TBT, STA, Pre-Task Briefing for site
injury Suitable emergency communication workers including drivers on daily
Property damage 9
means shall be provided. activities.
3 3
Emergency contacts to be displayed.
Emergency equipment & services shall
be readily available like crane with man
basket, standby dewatering pumps,
tripod with winch as applicable or
sewerage tanker and spill kit with
emergency team.
Full time supervision availability for the
assign tasks at site so that he/she to
minimize the situation of emergency to
occur at site by arranging safe
equipment/safe workplace and monitor
the work and provide required
information/instruction/training to
workforce to minimize the condition to
develop as emergency.
Lone work must be avoided.
Sleeping / resting in unauthorized areas
shall not be permitted, provision of
adequate welfare at designated locations
with good illumination.
Provision of sufficient safe access to
emergency services / ambulance
Provision of full time first aiders / male
nurse
Provision of emergency standby vehicle
at site.
Note: All High and Very High residual risk ratings (10-25) require review and approval by Construction Director/Manager/Facility or Operations Manager before starting work to ensure that the additional controls are adequate to execute
the task safely.
Page 6 of 7