CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
DyCEE/C/AGRA acting for and on behalf of The President of India invites E-Tenders against Tender No AGC-EL-C-T-
EPC-02-2024-25 Closing Date/Time 31/12/2024 16:00 Hrs. Bidders will be able to submit their original/revised bids
upto closing date and time only. Manual offers are not allowed against this tender, and any such manual offer received
shall be ignored.
1. NIT HEADER
Design, Supply, Erection, Testing and Commissioning of 220/2x25 kV & 132/2x25
kV Traction Sub-station along with SP/SSPs between Mathura-Dholpur-Antri-Bina
Name of Work
section of North Central Railway in connection with raising of speed to 160
Kmph/200 Kmph.
Bidding type EPC [ Single Stage ]
Tender Type Open Bidding System Two Packet System
Tender Closing Date Date Time Of Uploading
31/12/2024 16:00 19/11/2024 18:41
Time Tender
Pre-Bid Conference Pre-Bid Conference Date
Yes 29/11/2024 16:00
Required Time
2nd Pre-Bid Conference 2nd Pre-Bid Conference Date
No Not Applicable
Required Time
Advertised Value 5186900254.00 Tendering Section AGC ELC
Bidding Style Single Rate for Tender Bidding Unit Above/Below/Par
Earnest Money (Rs.) 10000000.00 Validity of Offer ( Days) 180
Tender Doc. Cost (Rs.) 0.00 Period of Completion 720 Days
Contract Type Works Contract Category Expenditure
Are Joint Venture (JV) firms
Bidding Start Date 17/12/2024 Yes
allowed to bid
Ranking Order For Bids Lowest to Highest Expenditure Type Capital (Works)
Docs. Receipt
Required
Confirmation
2. SCHEDULE
S.No. Item Item Qty Unit Basic Value Escl.(%) Amount Bidding
Code Qty Unit Rate Unit
Schedule 1-Overall cost of work 5186900254.00
Please see Item Breakup for details. 5186900254.00 AT Par 5186900254.00
1
Description:- Overall cost of work
3. ITEM BREAKUP
Schedule Schedule 1-Overall cost of work
Item- 1 Overall cost of work
S No. Item Description of Item Unit Qty Rate Amount
No
1 1 Overall cost of work Job 1.00 5186900254.00 5186900254.00
Total 5186900254.00
4. ELIGIBILITY CONDITIONS
Important All documents uploaded and remarks / confirmation entered by the bidders against any
: eligibility condition shall be opened as part of technical bid only
Special Financial Criteria
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
2.2.2.2 Financial Capacity: The Bidder shall have a minimum Net Worth
Allowed
1 (the "Financial Capacity") of 5% of Estimated Project cost at the close of No No
(Mandatory)
the preceding Financial Year.
Special Technical Criteria
Page 1 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
2.2.2.1 Technical Capacity- For demonstrating Technical Capacity and
experience (the "Technical Capacity"), the Bidder shall, during the last 5
(five) previous financial Years and the current financial year up to the
Base month, (i)Have received payments for construction of Eligible
Project(s), or has undertaken construction works by itself in a PPP
project, such that the sum total thereof, as further adjusted in
accordance with clause 2.2.2.4 (i) & (ii), is more than 2.5(two and half)
times the Estimated Project Cost (the "Threshold Technical Capacity").
Provided that at least one fourth of the Threshold Technical Capacity
shall be from the Eligible Projects in Category 1and/or Category3
specified in Clause 2.2.2.4 (i) &(ii) (ii)undertaken at least one Eligible
Project of Railway Sector as mentioned in clause 2.2.2.4/iii of value of Allowed
1 No No
not less than 35% (thirty five) per cent] of the Estimated Project Cost (Mandatory)
and have received payments for not less than 75(seventy-five)percent
value of present Contract value (excluding the payment made for
adjustment of price variation (PVC), if any) of such project. Illustration for
received payments for not less than 75(seventy five) percent: For
contract wherein there is provision for part payment on procurement of
goods and equipments on basis of indemnity bond/Bank Guarantee. In all
such contracts 'received payments for not less than 75 (seventv-five)
percent value of present Contract Value payment' means not less thon
75% payment received under 'procurement of goods and equipments' as
well as not less than 75% payment received under 'execution/
installation/ commissioning'.
Bidders shall confirm and certify on the behalf of the tenderer including its constituents as under:
S.No. Description
1 I/we the tenderer (s) am/are signing this document after carefully reading the contents.
I/We the tenderer(s) also accept all the conditions of the tender and have signed all the pages in confirmation
2
thereof.
I/we hereby declare that I/we have downloaded the tender documents from Indian Railway website
www.ireps.gov.in . I/we have verified the content of the document from the website and there is no addition, no
3 deletion or no alteration to the content of the tender document. In case of any discrepancy noticed at any stage
i.e. evaluation of tenders, execution of work or final payment of the contract, the master copy available with the
railway Administration shall be final and binding upon me/us.
I/we declare and certify that I/we have not made any misleading or false representation in the forms,
4
statements and attachments in proof of the qualification requirements.
I/We also understand that my/our offer will be evaluated based on the documents/credentials submitted along
5
with the offer and same shall be binding upon me/us.
I/We declare that the information and documents submitted along with the tender by me/us are correct and I/we
6
are fully responsible for the correctness of the information and documents, submitted by us.
I/we certify that I/we the tenderer(s) is/are not blacklisted or debarred by Railways or any other Ministry /
7 Department of Govt. of India from participation in tender on the date of submission of bids, either in individual
capacity or as a HUF/ member of the partnership firm/LLP/JV/Society/Trust.
I/we understand that if the contents of the certificate submitted by us are found to be forged/false at any time
during process for evaluation of tenders, it shall lead to forfeiture of the Bid Security and may also lead to any
8
other action provided in the contract including banning of business for a period of upto two year. Further, I/we
and all my/our constituents understand that my/our offer shall be summarily rejected.
I/we also understand that if the contents of the certificate submitted by us are found to be false/forged at any
time after the award of the contract, it will lead to termination of the contract, along with forfeiture of Bid
9
Security/Security Deposit and Performance guarantee and may also lead to any other action provided in the
contract including banning of business for a period of upto two year.
I/We have read the clause regarding restriction on procurement from a bidder of a country which shares a land
border with India and certify that I am/We are not from such a country or, if from such a country, have been
10
registered with the competent Authority. I/We hereby certify that I/we fulfil all the requirements in this regard
and am/are eligible to be considered (evidence of valid registration by the competent authority is enclosed)
Partnership firm/Joint Venture (JV) / Hindu Undivided Family (HUF) / Limited Liability Partnership
(LLP) etc.
S.No. Description
Page 2 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
Partnership firm/Joint Venture (JV) / Hindu Undivided Family (HUF) / Limited Liability Partnership
(LLP) etc. Please submit a certificate in the prescribed format (please download the format from the link given
1 below). Non submission of the certificate, or submission of certificate either not properly filled in, or in a format
other than the prescribed format shall lead to summary rejection of your offer.
( Click here to download the Format of Self Certification)
5. COMPLIANCE
Important All documents uploaded and remarks / confirmation entered by the bidders against any
: compliance condition shall be opened as part of technical bid only.
Commercial-Compliance
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
Please enter the percentage of local content in the material
being offered. Please enter 0 for fully imported items, and 100
Allowed
1 for fully indigenous items. The definition and calculation of local No Yes
(Optional)
content shall be in accordance with the Make in India policy as
incorporated in the tender conditions.
The tenderer shall upload scanned copies of mandatory
credential such as Experience, Turn over certificates and any
other documents as applicable, all documents related to Allowed
2 No No
Partnership Deed/Joint Venture/ Consortium/ MOU, Registration (Optional)
details, TIN No., registered address, email ID etc. should be up
loaded in PDF format only at the time of submission of bid.
Credentials of Tenderers: The tenderers shall provide
satisfactory documentary evidences acceptable to Railway
Allowed
3 (certificate from private individuals for whom such works are No No
(Mandatory)
executed / being executed will not be accepted) along with the
tender to show that:
They have an established technically competent and adequate
staff organization to ensure that the services required under this
Allowed
3.1 tender can do satisfactorily. The Tenderer shall provide the list No No
(Mandatory)
of personnel available in hand and proposed to be inducted for
the subject work along with the offer.
They have sufficient equipments; plants and machinery to meet
the obligations under the contract and to complete the work
contract all within the stipulated time schedule and accepted by
Allowed
3.2 him. The Tenderer shall provide the list of equipments, plants No No
(Mandatory)
and machinery available in hand and proposed to be inducted
(own and hired basis separately) for the subject work along with
the offer.
The Tenderer will submit, along with offer list of work in hand
Allowed
3.3 indicating description of work, contract value, approximate No No
(Mandatory)
value of balance work yet to be done and date of award of work.
Please submit your bank details i.e.Name of the Bank along with
Allowed
4 Bank Branch Code, IFSC Code, Beneficiary name, Account No No
(Mandatory)
Number, Type of account, PAN and GSTN Number.
General Instructions
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
1 INSTRUCTIONS TO TENDERERS No No Not Allowed
The tenderer shall thoroughly go through the entire tender
1.1 documents and strictly adhere the instructions and directions No No Not Allowed
given at different pages.
If the Tenderer(s) deliberately give(s) wrong information/
incorrect documents in his/their tender or create circumstances
for the acceptance of his/their tender, the Railway reserves the
right to reject such tender at any stage. The entire EMD and any
1.2 No No Not Allowed
other dues available with Railway against that contract will be
forfeited. Action will be taken to suspend the business with the
tenderere for a period of one year. In addition, Administration
reserves the right to prosecute under suitable law.
All terms and conditions in the tender documents are binding on
1.3 No No Not Allowed
the Tenderers.
Page 3 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
The Tenderers are advised to visit the site of work in their own
interest and acquaint themselves with the site conditions and
expected quantum of work and assess all the site specific
1.4 difficulties to be experienced while executing the same and the No No Not Allowed
rate shall be arrived duly considering all the facts above and
quoted in the tender. Any representation at a later date
specifying the site difficulties shall not be considered.
It shall not be obligatory on the said authority to accept the
2 lowest tender and no Tenderer/tenderers shall demand any No No Not Allowed
explanation for the cause of rejection of his/their tender.
If a Tenderer expires after the submission of his tender or after
the acceptances of his tender, the Railway shall deem such
tender as cancelled. If a partner of a firm expires after the
3 No No Not Allowed
submission of their tender or after the acceptance of their
tender, the Railway shall deem such tender as cancelled unless
the firm retains its character.
The special condition of tenders and contracts & the General
Condition Contract should be considered a part contract
4 agreement documents. Where the provisions of these conditions No No Not Allowed
are at variance with the general conditions of the contract, the
special conditions shall prevail.
Tenderers are advised to go through the tender booklet for
detail condition, scope of work and other technical
5 conditions/specification, maintenance schedule, all penalty No No Not Allowed
conditions, make list, earthing drawing, approved/likely source of
material related with the work before submitting their offer.
Special Conditions
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
No land belonging to or in the possession of the Railway shall be
occupied by the contractor without the permission of the
1 Railway. The contractor shall not use, or allow to be used, the No No Not Allowed
site for any purposes other than that of executing, or in relation
to the execution of the services.
No free Railway passes shall be issued by the Railway to the
contractor or any of her employees/ workers. Wherever required
2 No No Not Allowed
'authority for entering restricted area or 'authority for on board
services' shall be provided.
Indemnity by Contractors: The contractor shall indemnify and
save harmless the Railway, from and against, all actions, suit
proceedings, losses, costs, damages, charges, claims and
demands of every nature and description brought or recovered
against the Railways by reason of any act or omission of the
contractor, her agents or employees, in the execution of the
3 No No Not Allowed
services/works wherever applicable or in her guarding of the
same. All sums payable by way of compensation under any of
these conditions shall be considered as reasonable
compensation to be applied to the actual loss or damage
sustained, and whether or not any damage shall have been
sustained.
Page 4 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
Damage to Railway Property or Private Life and Property: The
contractor shall be responsible for all risk involved in the
services rendered and for trespass and shall make good at his
own expense all loss or damage whether to the works/services
themselves or to any other property of the Railway or the lives,
persons or property of others from whatsoever cause in
connection with the and this although all reasonable and proper
precautions may have been taken by the contractor, and in case
the Railway shall be called upon to make good any costs, loss or
damages, or to pay any compensation, including that payable
under the provisions of the Workmen's Compensation Act or any
statutory amendments thereof to any person or persons
sustaining damages as aforesaid by reason of any act, or any
negligence or omissions on the part of the contractor; the
4 No No Not Allowed
amount of any costs or charges including costs and charges in
connection with legal proceedings, which the Railway may incur
in reference thereto, shall be charged to the contractor. The
Railway shall have the power and right to pay or to defend or
compromise any claim of threatened legal proceedings or in
anticipation of legal proceedings being instituted consequent on
the action or default of the contractor, to take such steps as may
be considered necessary or desirable to ward off or mitigate the
effect of such proceedings, charging to contractor, as aforesaid,
any sum or sums of money which may be paid and any
expenses whether for reinstatement or otherwise which may be
incurred and the propriety of any such payment, defense or
compromise, and the incurring of any such expenses shall not
be called in question by the contractor.
The status of the contractor shall be that of an independent
contractor. The contractor, its employees, agents and any
subcontractors performing under this contract are not
employees or agents of the State or any agency, division or
5 department of the State simply by virtue of work performed No No Not Allowed
pursuant to this contract. Neither the contractor nor its
employees shall be considered employees of the Railways or the
Govt. of India/state simply by virtue of work performed pursuant
to this contract.
The tender offer has to comply with the requirement of current
minimum wages. The tender offers not complying with the
minimum wages requirement will be summarily rejected. The
tender offers, not meeting with the minimum wages requirement
6 No No Not Allowed
will be considered as unworkable. Contractor has to pay
applicable minimum wages to his staff, the minimum wages gets
periodically revised and revised minimum wages had to be paid
by contractor.
Contractor shall comply with the provisions of Contract Labour
(Regulation & Abolition) Act, 1970/ Rules 1950 with latest
amendments: The Contractors employing more than 20 workers
shall obtain License from the Asst. Labour Commissioner before
the commencement of the work and continue to have a valid
license until the completion of the work. Any failure to fulfill the
requirement shall attract the penal provision of the contract
arising out of the resultant non-execution of the work.
7 No No Not Allowed
Contractor is responsible for the payment of wages to the staff
deployed under section 21 of "The Contract Labour (Regulation
and Abolition) Act, 1970 and to ensure compliance especially
with the Rules 63 to 83 of "The Contract Labour (Regulation and
Abolition) Central Rules, 1971 in this regard. Contractor is
responsible for maintenance and exhibition of records as
prescribed in section 29 of the "The Contract Labour (Regulation
and Abolition) Act, 1970.
Page 5 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
Contractor shall comply with the provisions of Employees
Provident Fund and Miscellaneous Provisions Act, 1952 with
latest amendments: The contractor shall comply with the
provisions of Para 30 & 36-B of the Employees Provident Fund
Scheme, 1952; Para's 3 & 4 of Employees' Pension Scheme,
8 1995; and Para 7 & 8 of Employees Deposit Linked Insurance No No Not Allowed
Scheme, 1976; as modified from time to time through
enactment of "Employees Provident Fund & Miscellaneous
Provisions Act, 1952", wherever applicable and shall also
indemnify the Railway from and against any claims under the
aforesaid Act and the Rules.
The contractor shall accept liability for compensation in
accordance with the provisions of the Workmen's' Compensation
Act, 1923 or any statutory modification thereof for the time
being in force in respect of the persons employed by the
contractor. In every case in which by virtue of the provisions of
Section 12 Sub-Section (1) of the Workmen's Compensation Act
1923, Railway is obliged to pay compensation to a worker
9 No No Not Allowed
directly or through petty contractor or subcontractor employed
by the contractor in executing the work, Railway will recover
from the contractor the amount of the compensation so paid,
and, without prejudice to the rights of Railway under Section 12
Subsection (2) of the said Act, Railway shall be at liberty to
recover such amount or any part thereof by deducting it from
any sum due by Railway to the contractor.
Contractor shall comply with the Child Labour (Prohibition and
Regulation) Act, 1986 with latest amendments: Provisions of
10 No No Not Allowed
Child Labour (Prohibition and Regulation) Act, 1986 along with
its latest amendments would be binding on the contractor.
The contractor shall pay to his staff engaged in connection with
the contract not less than fair wages being the wage notified
from time to time by the concerned state, center or local
authority empowered therefore or where not notified, wages
paid for similar work in the neighborhood. The wage paid shall
not be less than those prescribed by any law enacted by the
11 No No Not Allowed
Govt. of India or by state Govt. concerned in so far as it may be
applicable to such staff engaged on such work on the Railways.
The contractor shall maintain proper record of payments and
submit to the administration a proof of payment along with a
certificate every month that he has paid wages in accordance
with the provisions of this clause.
The contractor is liable to comply with following provisions with
latest amendments in them: (i) Provisions of Contract Labour
(Regulation & Abolition) Act, 1970/ Rules 1950; (ii) Provisions of
Minimum Wages Act, 1948/Rules 1950; (iii) Provisions of
12 No No Not Allowed
Employees Provident Fund and Miscellaneous Provisions Act,
1952; (iv) Provisions of Workmen's Compensation Act; (v) Child
Labour (Prohibition and Regulation) Act, 1986 and (vi)
Apprentices Act, 1961.
Implementation of GST: - As per Railway Board Letter no.
2008/RS (G)/777/1 Dt. 29-05-2017 All the bidders/tenders should
13 No No Not Allowed
ensure that they are GST compliant and their quoted tax
structure/rates are as per GST Law.
Technical-Compliances
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
1 PVC clause:- As per tender document. No No Not Allowed
Physical Docs Mandatory Submission
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
Page 6 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
The Bidder shall submit the following documents physically
within time as mentioned in clause 1.3: (a) Original Power of
Attorney for signing the Bid as per format at Appendix-II; (b) If
applicable, Original Power of Attorney for Lead Member of
Allowed
1 Consortium/Joint Venture as per the format at Appendix-III; (c) If No No
(Mandatory)
applicable, Original Joint Bidding Agreement for Consortium/Joint
Venture as per the format at Appendix-IV; (d) Bid Security, if
submitted as Bank Guarantee, in the format at Appendix-Vll from
a Bank
Custom
S.No. Description Confirmation Remarks Documents
Required Allowed Uploading
Tenderer must note that his offer shall invariably accompany all
scanned copies of documents required for fulfilling the minimum
Allowed
1 eligibility criteria. After opening of tender no document will be No No
(Optional)
accepted. Only clarification / verification of credentials will be
done.
The tenderers shall not add any conditions on their own either in
their covering letter or in the tender documents while submitting
their offer. Any such conditions if stated and if are in violation of
Allowed
2 the Railways tender conditions or having financial implication No No
(Optional)
may lead to summary rejection of the offer. Railway reserves the
right to reject such tenders summarily without assigning any
reasons whatsoever.
6. Documents attached with tender
Document
S.No. Document Name
Description
132 2x25kv TSS
1 1322x25KVTSSSCOTT4LINEPERPEDCULARTOTRACK.pdf
scott 4 line perpend
220 2x25kv tss
2 2202X25kvtssscottconnected4linesection.pdf
scott 4 line
220 2x25kv tss
3 2202X25KVTSSSCOTTCONNECTEDFOURLINE_1.pdf
scott 4 line
220 2x25kv TSS
4 2202X25KVTSSSCOTTCONNECTEDTHREELINEPERPENDICULARTRACK.pdf
scott 3 line perpend
220 2x25kv tss v
5 2202X25KVTSSVCONNECTEDFOURLINEPERPENDUCLARTOTRACK.pdf
connected 4 line
220 2x25kv tss
6 2202x25KVTSSSCOTTCONNECTED4LINESECTIONPERPENDICULARTRACK.pdf
scott connected 4lin
220 2x25kv tss
7 2202X25KVTSSSCOTTCONNECTEDTHREELINESECTION.pdf
scott connectd 3 lin
boundary SP scott
8 boundarySPforscottconnectedtransformerdoubleline.pdf
conn transf 2line
control room build
9 CRB_SSP_SP.pdf
SP SSP
control room build
10 CRB_TSS.pdf
TSS
cross acceptance
11 CROSSACCEPTANCEPOLICY.pdf
policy
drwaing of site
12 DrawingofsiteOffice.pdf
office
letter for polluted
13 LetterforPollutedZone.pdf
zone
14 NewPSIGuidelines.pdf new psi guidelines
RDSO specs 22 to
15 RDSO22-23-24-25_compressed.pdf
25
RDSO specs 28 to
16 RDSO-28-29-30-31_compressed.pdf
31
17 rdso3456_11zon.pdf RDSO specs 3 to 6
18 RDSOSPEC1_compressed1_compressed.pdf RDSO specs 1
Page 7 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
19 rdsospec2_11zon.pdf RDSO specs 2
20 RDSOSPEC7_compressed1.pdf RDSO specs 7
RDSO specs 19 to
21 RDSOSPEC19-20_compressed1.pdf
20
22 RDSOSPEC21_compressed.pdf RDSO specs 21
RDSO specs 26 to
23 RDSOSPEC26-27_compressed.pdf
27
24 RDSOSPEC89_compressed1.pdf RDSO specs 8 to 9
RDSO specs 10 to
25 RDSOSPEC101112131415161718_compressed.pdf
18
revised PSI
26 Revised160kmphPSIGuideline25022022.pdf
guidlines
27 sp3LINEFOR2X25KVSystem.pdf SP 3 lines section
28 spdoubleline.pdf SP double ine
29 SPfor3linesection.pdf SP for 3 line section
SP for 2 lines for V
30 SPfordoublelineforVconnectedtramsformer.pdf
conn transform
SP for 4line sec
31 SPforfourlinesectionfor2x25KVAT.pdf
2x25
32 spfourlinefor2x25KVSYSTEM.pdf SP for 4 line
retaining wall
33 TypicalRetainingWallApproved.pdf
layout
132 2x25kv TSS V
34 1322X25KVTSSVCONNECTEDFOURLINESECTIONFOURLINESECTION.pdf
conn 4 line sec
132 2x25KV TSS
35 1322X25KVTSSTRIPLESECTIONV-CONNECTEDPARALLELTOTRACK.pdf
3sec V connected
132 2x25KV TSS V
36 1322X25KVTSSVCONNECTEDTRIPLESECTIONPERPENDICULARTOTRACK.pdf
conn 3sec perpe
132 2x25KV TSS V
37 1322x25KVTSSVCONNECTEDFOURLINESECTIONPARALLELTOTRACK.pdf
conn 4line sec
220 2x25KV TSS V
38 2202X25kvTSSVconnectedtriplelineparalleltrack.pdf
conn 3 line
220 2x25KV TSS V
39 2202X25KVTSSVCONNECTEDFOURLINESECTIONPARALLELTRACK.pdf
conn 4 line parall
220 2x25KV TSS V
40 220X25KVTSSvCONNECTEDTRIPLELINEPARALLELTRACK.pdf
conn 3line paralle
boundary sec SP 2
41 BoundarysectioningSPDOUBLELINESCOTTCONNECTED.pdf
line scott connec
boundary sec 3line
42 bOUNDARYSECTIONINGSPtHREELINE.pdf
SP
foundation layout of
43 LayoutofcabletrenchfoundationSP.pdf
cabl trench SP
SP 2line for V conn
44 SPDOUBLELINEFORVCOONNECTDTSS.pdf
TSS
45 SPDOUBLELINEFORVCONNECTED.pdf SP 2 line for V conn
46 SSP4Linesection2.pdf SSP 4line sec
47 SSP4Linesection2_1.pdf SSP 4line section 2
48 SSP4linesection3.pdf SSP 4 line section 3
SSP double line for
49 SSPDOUBLELINEFORVCONNECTEDTSS.pdf
V conn TSS
SSP double line
50 SSPDOUBLELINESCOTTCONNECTED.pdf
scott connected
SSP 2 line sec scott
51 SSPDOUBLELINESECTIONSCOTTCONNECTED.pdf
connected 2
52 SSPTHREELINESECTION21.pdf SSP 3 line section
53 SSPTHREELINESECTION2.pdf SSP 3 line section 2
54 SCADA0134-.pdf SCADA specification
Page 8 of 9 Run Date/Time: 19/11/2024 18:42:32
CAO-C-HQ-ELECTRICAL/NORTH CENTRAL RLY
TENDER DOCUMENT
Tender No: AGC-EL-C-T-EPC-02-2024-25 Closing Date/Time: 31/12/2024 16:00
55 TenderDocument1.pdf Tender Document
56 TenderDocument2.pdf Tender Document 2
57 RFPdocument.pdf RFP document
58 APPENDIX-III-D-ApprovedLocationPlans1.pdf Location Plan
This tender complies with Public Procurement Policy (Make in India) Order 2017, dated 15/06/2017,
issued by Department of Industrial Promotion and Policy, Ministry of Commerce, circulated vide Railway
Board letter no. 2015/RS(G)/779/5 dated 03/08/2017 and 27/12/2017 and amendments/ revisions
thereof.
As a Tender Inviting Authority, the undersigned has ensured that the issue of this tender does not
violate provisions of GFR regarding procurement through GeM.
Signed By: PRAVEEN KUMAR YADAV
Designation : Dy.CEE
Page 9 of 9 Run Date/Time: 19/11/2024 18:42:32