Internal Wall Finishes FYP

The document outlines the construction details for a two-story bungalow in Marang, Terengganu, including various internal wall finishes such as plastering, painting, and tiling. It specifies quantities and materials required for each task, with measurements provided in square meters. The document serves as a taking-off list for the project, detailing the necessary work and materials for completion.

Uploaded by

Marini Maruki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views3 pages

Internal Wall Finishes FYP

The document outlines the construction details for a two-story bungalow in Marang, Terengganu, including various internal wall finishes such as plastering, painting, and tiling. It specifies quantities and materials required for each task, with measurements provided in square meters. The document serves as a taking-off list for the project, detailing the necessary work and materials for completion.

Uploaded by

Marini Maruki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Job : Bil No. Element No. Slip no. Job : Bil No. Element No. Slip No.

CADANGAN MEMBINA DAN MENYIAPKAN 1 CADANGAN MEMBINA DAN MENYIAPKAN 1


UNIT RUMAH BANGLO 2 TINGKAT DI ATAS UNIT RUMAH BANGLO 2 TINGKAT DI ATAS
LOT 10331 (GRN 11954).KG.BATU 9,BUKIT LOT 10331 (GRN 11954).KG.BATU 9,BUKIT 10 1
PAYONG,MARANG, TERENGGANU PAYONG,MARANG, TERENGGANU

Heading : Heading : 19 mm thick cement and sand (1:6)


plastering mixed with a proof plastisizer finished with steel trowelled
internally to vertical surface
Description : Unit : Description : Unit :
M2
Quantity : Plaster Quantity :
501
Taking off list for internal wall finishes
1.Plaster
2.Painting 501.23 Quantity taken from schedule 10.1
3.Bed and backing work
4.Tiling work
Job : Bil No. Element No. Slip no. Job : Bil No. Element No. Slip No.
CADANGAN MEMBINA DAN MENYIAPKAN 1 CADANGAN MEMBINA DAN MENYIAPKAN 1
UNIT RUMAH BANGLO 2 TINGKAT DI ATAS UNIT RUMAH BANGLO 2 TINGKAT DI ATAS
LOT 10331 (GRN 11954).KG.BATU 9,BUKIT 10 2 LOT 10331 (GRN 11954).KG.BATU 9,BUKIT 10 3
PAYONG,MARANG, TERENGGANU PAYONG,MARANG, TERENGGANU

Heading : Prepare and apply one coat undercoat and two finishing coats of Heading : 19 mm thick cement and sand (1:3)
emulsion paint or other equal and approved weather shield paint including as screeded backing to receive glazed wall tiles (measured separetely)
obtaining certificate of guarantee for five years finished with steel trowelled to internal vertical surface
Description : Unit : Description : Unit :
M2 M2
Painting Quantity : Bed & Backing Work Quantity :
470 90

469.79 Quantity taken from schedule 10.1 89.69 Quantity taken from schedule 10.1
Job : Bil No. Element No. Slip no. Job : Bil No. Element No. Slip No.
CADANGAN MEMBINA DAN MENYIAPKAN 1 CADANGAN MEMBINA DAN MENYIAPKAN 1
UNIT RUMAH BANGLO 2 TINGKAT DI ATAS UNIT RUMAH BANGLO 2 TINGKAT DI ATAS
LOT 10331 (GRN 11954).KG.BATU 9,BUKIT 10 4 LOT 10331 (GRN 11954).KG.BATU 9,BUKIT
PAYONG,MARANG, TERENGGANU PAYONG,MARANG, TERENGGANU

Heading : 300 mm x 300 mm x 6 mm thick glazed ceramic tiles or equal Heading :


and approved in standard local colour beded and jointed in cement & sand
(1:3) on screeded bed (measure separately) and pointed in matching colour
cement and laid internally to wall
Description : Unit : Description : Unit :
M2
Glazed Ceramic Tiles Quantity : Quantity :
90

89.69 Quantity taken from schedule 10.1