SAUDI ARAMCO INSPECTION CHECKLIST
Soil Improvement Vibro Replacement (Stone Columns) Pre-
SAIC-A-1013 31-Jul-22 CIVIL-
Installation (Survey) and Installation Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Pre- Installation (Survey) Inspection
Coordinates will be based on the Universal Transverse Mercator (UTM)
SAES-A-100
A1 coordinate system and referenced to the International 1924 Ellipsoid, Ain
Sec. 4.1
(Ayn) Al Abd 1970 Datum¹.
Major Plant facilities will be referenced to a local plant grid which in turn is SAES-A-100
A2
tied into the UTM coordinate system. Sec. 4.3
Offshore depth soundings are referenced to Lowest Astronomical Tide SAES-A-100
A3
(LAT). Sec. 5.1
Land elevations are referenced to Mean Sea Level (MSL) vertical datum SAES-A-100
A4
for all. Sec. 5.2
To obtain accurate horizontal ground distances obtained from UTM
coordinates (or opposite), sea level factor and scale (projection) factor
corrections (or a locally computed combined factor) shall be applied.
SAES-A-100
A5 Scale factor corrections should be calculated on a project by project basis
Sec. 8.5
(except for long pipelines which should be segmented). Scale factor
parameters shall be referenced on
each sheet.
ACI 117
Tolerance for deviation of location shall be 1/24 of diameter but not more
A6 Sec. 3.2.2.1
than 3 in (75 mm).
B Stone Column Installation Inspection
ACI 117
B1 Tolerances for the depth of Stone Columns shall be - 2 in. & + 6 in.
Sec. 5.2.1
Saudi Aramco: Company General Use Saudi Aramco: Company General Use
#
#
Ampere readings for S-Vibrator for Compaction of Stone Columns
B2 Method Statement
(printout review) shall range between 160 to 180 amps.
Depth Installation of Stone Column Depth and Compaction shall be as per
SAES-A-100/ IFC
B3 issued IFC drawings and referenced to survey markings as conducted
Drawings
officially based on SAIC-A-1014.
Setting out of Stone Column Positions shall be as per issued IFC
SAES-A-100/ IFC
B4 drawings and referenced to survey markings as conducted officially based
Drawings
on SAIC-A-1014.
Working Levels (W.L.) have been established before any Soil SAES-A-100/ IFC
B5
Improvement Works are commenced. Drawings
Load Tests have been performed as per approved project specifications
B6 Method Statement
and Method Statement.
Daily Vibro Records have been accomplished and officially submitted to
B7 Method Statement
Saudi Aramco representatives.
Load Test Reports have been accomplished and officially submitted to
B8 Method Statement
Saudi Aramco representatives.
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-A-100 - Survey Coordinates, Datum's and Data Formats, 19 February 2018
2- Approved Method Statement for Soil Improvement
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
QC Inspector PID Representative
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED
Saudi Aramco: Company General Use Saudi Aramco: Company General Use
#