The 14087-50DB/6 rig installation guide provides detailed instructions for installing a drilling rig, including foundation preparation, component assembly, and safety measures. It emphasizes the importance of aligning components accurately and ensuring all connections are secure. Additional notes and references to related manuals are included for further guidance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
113 views143 pages

05 Rig Installation Guide Manual

The 14087-50DB/6 rig installation guide provides detailed instructions for installing a drilling rig, including foundation preparation, component assembly, and safety measures. It emphasizes the importance of aligning components accurately and ensuring all connections are secure. Additional notes and references to related manuals are included for further guidance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 143

14087-50DB/6 rig installation guide manual

J14087-50DB/6 Project
Rig installation guide manual

Q001.00AZ
14087-50DB/6 项目钻机安装指导手册

Notes:
1.According to foundation drawings(SUQ001.00),rig well require flattening with cement foundation;
2.Set well center line as a datum, draw longitudinal and transverse center line across well center and position line for all the ground
equipment.;
3. All the spinning pins surface must spread the grease.
4. Rig installation works are alternative. After substructure bottom layer installed , solid control system, mud pump units, diesel generator
room, etc. could be installed separately according to (SUQ001.00) rig plane layout drawing.
5. Safety pin must be installed when connecting pin fixed. Spring gasket must be installed where bolt connection is single nut.
6.Pay attention to the following notes when installing solid control system:
a.After place mud tanks in position and then installing attachments, equipments and process pipeline;
b.After fix all the equipments and then connecting the pipeline;
c.Part of the pipeline cross over platform or handrail,pay attention to installation order during the installation ;
d.Connecting relevant pipeline between tanks;
e.After installation, check every process and attachments from shale shaker tank,make sure that no left and each pipeline connecting
tightness
7. Other items need attention, please refer to “ZJ50/3150DB drilling rig operation manual”.

1 / 143
14087-50DB/6 项目钻机安装指导手册

1.Place steel wood foundation

Place 8 pcs 5000mm x3000mm x210mm steel wood and 26 pcs 4000mm x3000mm x210mm steel wood foundation according to layout
14087 项目钻机安装指导手册

NO. Name Drawing QTY. Remark


1 Steel wood foundation 5000mm x3000mm x210mm 8
2 Steel wood foundation 4000mm x3000mm x210mm 26

2.Installing bottom base (Left front lower base,Right front lower base )

Before install bottom base,make sure steel wood in position and fixed tightly.

After check the steel wood foundation installation, check the components quantity of bottom base,fill up or repair the components that lost

or deformation

After everything prepared,installing the bottom base according to drawing SUKR112.75.10.00 and pin diagrammatic drawing

a) Place left front lower base, right front lower base on steel wood foundation and make sure well center coincide with well center on the ground

b) Place left back lower base,right back lower base on steel wood foundation and make sure front lower base, back lower connecting pin hole

coincidence, make sure that 8 pcs single taper pin Φ140x280 can be inserted

c) Installing pulling beam1, pulling beam 2, pulling beam 3 in turn and make sure connecting pin hole of pulling beam and lower base

coincidence

d) Finally,install 2 diagonal draw bar.

iii / 143
14087 项目钻机安装指导手册

Note:During installation,make sure left and


1 right base center line parallel;make sure left and
right lowerbase and be coaxial andperpendicular
to left and right loer base center line and well
hole center line

NO. Name Drawing NO. QTY. Remark


1 Left front lower base KR112.75.10.00 1 SUKR112.75.10.00
2 Right front lower base KR112.75.50.00 1 SUKR112.75.50.00

(1)Installing left front lower base and right front lower base on the steel wood in turn,make sure the center distance of two belly

board is 7660mm;

iv / 143
14087 项目钻机安装指导手册

(2)Make sure left front lower base and right front lower base well center line that marked on the nameplate coincide with well

center line on the ground

3.Installing bottom base(left back lower base,right back lower base) Note:Single taper pin install from outside to inside

3、4

v / 143
14087 项目钻机安装指导手册

NO. Name Drawing NO. QTY. Remark


1 Left back lower base KR112.75.35.00 1 SUKR112.75.35.00
2 Right back lower base KR112.75.60.00 1 SUKR112.75.60.00
3 Single taper pin Φ140x280 KR112.75.01.01 8
4 Shear pin Φ25x160 KRT-02-06 16

(1)Installing left back lower base (NO.1)and Right back lower base(NO.2) on the steel wood,and make sure pin hole of left front base

coincide with right front lower base;

(2)installing 8 single taper pinsΦ140x280 (NO.3) and 16 shear pins Φ25x160(NO.4 safety pin included),Connect front and back base

4.Installing bottom base(pulling beam)

vi / 143
14087 项目钻机安装指导手册

1 5、6

Note:After install bottom base,make sure well line nameplate of left, right front lower

base align to well center line

vii / 143
14087 项目钻机安装指导手册

NO. Name Drawing NO. QTY. Remark


1 pullling beam1 KR112.75.70.00 1
2 pullling beam2 KR112.75.73.00 1
3 pullling beam3 KR112.75.75.00 1
5 Single taper pin Φ70x225 KRT070-03-01 20
6 Shear pin Φ15x75 KRT-02-02 40

(1)Differentiate left and right remark according to pulling beam end, installing pulling beam 1(NO.1) and Pulling beam 2(NO.2) on left

front base and right front base in turns, and installing pulling beam 3 (NO.3)between left back lower base and right back lower base, make

sure each pin hole coincided

(2)“L” on behalf of left side and “R” on behalf of right side on the end mark

(3)Pin 24 single taper pinsΦ70x225 (NO.5) and 48 shear pinΦ15x75 (NO.6 safety pin included), make sure that before install the pulling

beam, the former one has been installed firmly

viii / 143
14087 项目钻机安装指导手册

5.Install ground floor(diagonal draw bar) Note:single taper pin installed from up to down

1 2、3

NO. Name Drawing NO. QTY. Remark


1 diagonal draw bar KR112.75.78.00 2
2 Single taper pin Φ60x125 KRT-03-03 4
3 Shear pin Φ15x75 KRT-02-02 8

(1) According to the pulling beam end to differentiate left and right mark,install 2 diagonal draw bars (NO.1)in turns and make sure

each pin hole coincided

ix / 143
14087 项目钻机安装指导手册

(2) “L” on behalf of left side and “R” on behalf of right side on the end mark,differentiate same piece by“L1”“R1”“L2”“R2”

(3)Pin 24 single taper pinsΦ60x125 (NO.2) and 8 shear pinΦ15x75 (NO.3 safety pin included)

6.install middle level(back stand column)

Before install middle level, count components and parts of middle level and repair transmutative components

After everything prepared,install middle level according to attached drawing SUKR112.75.100.00 and pins schematic diagram and

following steps

a) Install two rear column on base and make sure the pinhole of rear column coincide with front lower base connecting pinhole, and ensure

four taper pins can go through smoothly. Then, put the other end of column on rear lower base.

b) Place two inclined column support on suitable area around pull beam, and install two rear inclined column. Put in two taper pins

Φ100x305, then put free end of rear inclined column on pull beam 2.

c) At last, install two front inclined column and put in two taper pins Φ130x420, at this point, middle-level installation finished.

x / 143
14087 项目钻机安装指导手册

NO. Name Drawing NO. QTY. Remark


1 Left rear column KR112.05.130.00 1
2 Right rear column KR112.05.140.00 1
3 Single taper pin Φ130x535 KRT130-03-03 4
4 Shear pin Φ25x140 KRT-02-05 8

(1) Distinguish the mark left and right side, install #1,#2 column on left front base and right front base successively, ensure column lifting

padeye upside.

(2) Adjust the pinhole between left and right rear column and rear lower base,put in 4 single cone pin Φ130x535(#3) and 8 shear pins

Φ25x140(#4 including safety pin),lay down the left and right rear column(#1 and 2)on left and right rear lower seat.

xi / 143
ZJ14087-50DB/6 rig installation guide manual

7.Install middle layer structure (inclined stand column)

2、3

12 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 Inclined stand column KR112.22.120.00 4
2 Single taper pinΦ100x305 KR112.75.100.01 4
3 Sheer-pin Φ20x120 KRT-02-04 8
(1) Installation for rear inclined stand column:According to part number and marks for left and right,install 2 rear inclined stand
columns inside left-front-bottom base and right-front-bottom base,to make sure lifting lug coincide with all pin holes,plug in 2
single tapper pinsΦ100x305(No.2) and 4 sheer-pinsΦ20x120(No.3 ,including safety pin) ,and then put 2 rear inclined stand columns
down on pull beam;
(2) Installation for front inclined stand column:According to part number and marks for left and right,install 2 front inclined stand
columns inside left-front-bottom base and right-front-bottom base,to make sure lifting lug coincide with all pin holes,plug in 2
single tapper pinsΦ100x305(No.2) and 4 sheer-pinsΦ20x120(No.3 ,including safety pin) ,and then put 2 front inclined stand
columns down on rear inclined stand column .

13 / 143
ZJ14087-50DB/6 rig installation guide manual

8.Installation for front stand column

2、3

No. Name Drawing No. Qty. Remarks


1 Front stand column KR112.75.110.00 2
2 Single taper pinΦ130x420 KRT130-03-02 4
3 Sheer pin Φ25x140 KRT-02-05 8
(1)Put left-front stand column down on left-front-bottom base and left-upper base to make sure all pin holes coincide,plug in 2 single
tapper pinsΦ130x420(No.2) in the left-front-bottom base and 4 sheer-pinsΦ25x140(No.3 ,including safety pins),2 single tapper pins where are

14 / 143
ZJ14087-50DB/6 rig installation guide manual

connected front stand column and left-upper base would be installed for the time being ;
(2)Put right-front stand column down on right-front-bottom base and right-upper base to make sure all pin holes coincide,plug in 2 single
tapper pinsΦ130x420(No.2) in the right-front-bottom base and 4 sheer-pinsΦ25x140(No.3 ,including safety pins),2 single tapper pins Φ130x535
where are connected front stand column and right-upper base would be installed for the time being.

9.Installation for top layer (left-upper base ,right-uppper base )


Before installation ,we should count the quantity of components and parts ,complete missing components and parts and repair
transformative components and parts.
If all preparation is ok,install top layer according to SUKR112.67.200.00 drawing and pin installation schematic and the following steps:
(1)Firstly ,put left and right upper base on bottom layer and plug in connecting pin.;
(2)Sencondly ,connect stand column upper part and top base via pins;
(3)Install set back beam,front beam,drawworks beam , RT beams ,independent drive support and hydraulic catheand support and make
sure plug in pins successfully ;

15 / 143
ZJ14087-50DB/6 rig installation guide manual

3、4

Note:When installing top layer, make sure the plane


degree requirement.

16 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 Left-upper base KR112.75.225.00 1
2 Right-upper base KR112.75.300.00 1
3 Single tapper pin Φ110x325 KR112.75.02 8
4 Sheer-pin Φ20x120 KRT-02-04 16
(1)Put left-upper base(No.1) on left-front-bottom base and left-rear-bottom base and make sure all pin holes in the low level
coincide,plugin 4 single tapper pinsΦ110x325(No.3) and 8 sheer-pinsΦ20x120 (No.4,including safety pin) in lower level support base;
(2)Put right-upper base(No.2) on right-front-bottom base and right-rear-bottom base and make sure all pin holes in the low level
coincide,plugin 4 single tapper pinsΦ110x325(No.3) and 8 sheer-pinsΦ20x120 (No.4,including safety pin) in lower level support base..

17 / 143
ZJ14087-50DB/6 rig installation guide manual

10.Installation for top layer (setbacks beam) 4、5

2、3

No. Name Drawing No. Qty. Remarks


1 Setback beam KR112.22.205.00 1
2 Single tapper pin Φ100x225 KRT100-03-01 4
3 Sheer pin Φ20x120 KRT-02-04 8
4 Single tapper pin Φ130x270 KR112.75.200.01 4
5 Sheer pin Φ25x140 KRT-02-05 8

18 / 143
ZJ14087-50DB/6 rig installation guide manual

(1) Connect setbacks beam (No.1) with left and right top base and align pin holes;
(2)Plug in 4 single tapper pinsΦ100x225(No.2) and 8 sheer pinsΦ20x120(No.3 ,including safety pin) in setback front beam ;plug in 4
single tapper pinsΦ130x270(No.4) and 8 sheer-pinsΦ25x140 (No.5 ,including safety pin ) .

19 / 143
ZJ14087-50DB/6 rig installation guide manual

11. Installation for top layer (Front beam,drawworks beam )


2
1 3、4

3、4

No. Name Drawing No. Qty. Remarks


1 Front beam KR112.75.330.00 1
2 Drawworks beam KR112.75.280.00 1
3 Single tapper pin Φ100x225 KRT100-03-01 12
4 Sheer pin Φ20x120 KRT-02-04 24
(1) Connect front beam (No.1) and left and right top base and align pin hole and plug in 4 single tapper pinΦ100x225(No.3) and 8
sheerpinsΦ20x120(No.4 including safety pin);
(2) Connect drawworks beam (No.2 ) and left and right top base,align pin holes and plug in 8 single tapper pinsΦ100x225(No.3)
and 16 sheer pinsΦ20x120(No.4 including safety pin).

20 / 143
ZJ14087-50DB/6 rig installation guide manual

12. Installation for top layer (RT beam,independent drive device support base ,operation platform)

1 2

6、7

4、5

21 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 RT beam KR112.22.261.00 1
2 Independent drive device support base KR112.75.265.00 1
4 Single tapper pin Φ90x180 KRT-03-06 8
5 Sheer pin Φ20x120 KRT-02-04 16
6 Single tapper pin Φ60x125 KRT-03-03 8
7 Sheer pin Φ15x75 KRT-02-02 16
(1)Connect Rt beam(No.1 ) with setback beam and front beam,align pin hole ,plug in 8 single tapper pinsΦ90x180(No.4) and 8 sheer
pinsΦ20x120(No.5 ,including safety pin );
(2)Connect independent drive devi ce support base(No.2) with front beam and drawworks beam,align pin holes,plug in 8 single tapper
pinsΦ60x125(No.6) and 16 sheer pinsΦ15x75(No.7 ,including safety pin);

22 / 143
ZJ14087-50DB/6 rig installation guide manual

13.Installation for top layer(mud receiving box,operation


2 platform
3、4

4、5

23 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remark


1 Drip pan KR112.22.264.00 1
2 Platform KR112.22.272.00 2
3 Shell pin Φ30x60 KRT/H-05-14 4
4 Clip Φ30 KRT-01-01 12
5 Shell pin Φ40x90 KRT-03-15 8
(1)Put drip pan(No.1)on rotary table beam, connect with 4 shell pinΦ30x60(No.3)and 4 clips Φ30(No.4);
(2)Connect platform(No.2)to left top layer and independent drive beam, fixed with 4 shell pinΦ40x90(No.5)and 8 clipsΦ30(No.4).

14.Rotary table independent drive and drawworks


Before installation, count all the parts, make sure all the parts are available and under good condition.
a、Rotary table drive installation procedure:
1)、Install the rotary table according to the well center position. Fix the rotary with stopper. Install the rotary table motor and gear box as
per drawing.
2)、Adjust the shims keep the gear box and rotary table alignment less than 0.5mm, the gear box and motor alignment is less than 0.15mm.
3)、Install the brake frame, adjust the brake, make sure the brake disc have same distance on each side. The distance is0.55±0.2mm。
4)、Install the blower motor to correct position.

24 / 143
ZJ14087-50DB/6 rig installation guide manual

Notice:1、Lifting the rotary have to use the specified padeye.


2、Motor and gearbox should lifting the padeye on the body, the other position is not allowed.
3、Chose different wire line according to the weight.
4、Detailed installation procedure see KR108.26.00SM ZP495 Rotary table independent drive manual
b、Drawwork installation procedure:
1)、Install the drawworks on the substructure according to the drum center line.
2)、Fix the drawworks skid and beam by bolts(M36x140) and torque as requirement.
3)、Install the air hose, water hose and cable as per drawing.
Notice:1、Lifting the drawworks must use the specified tools.see drawing SUKR100.10.638.00 DW lifting diagram.
2、Lifting the drawworks need to use two crane according the weight.
3、Detailed installation see KR106.23.00 E-1500-AC manual.

25 / 143
ZJ14087-50DB/6 rig installation guide manual

1
2

No. Name Drawwing No. Qty. Remark


1 RT dependent drive device KR108.29.00 1
2 E-1500-AC Drawworks KR106.23.00 1 SUKR100.10.638.00DW lifting
diagram
(1)Install the rotary table independent drive No.1 to roatry table beam and rotary table independent drive beam.
(2)Install E-1500-AC drawworks No.2 to drawworks beam.
15. Install top layer(Back connection beam、BOP rail)

26 / 143
ZJ14087-50DB/6 rig installation guide manual

1 2、3

4 3、5、6
No. Name Drawing No. Qty. Remark
1 Back connection beam KR112.75.290.00 1
2 Double taper pin Φ40x95 KRT-04-15 4
3 clip Φ30 KRT-01-01 24
4 BOP rail KR112.22.600.00 2
5 Single taper pin Φ40x95 KRT-03-01 8

27 / 143
ZJ14087-50DB/6 rig installation guide manual

6 Shear pin Φ10x55 KRT-02-01 16


(1)Install back connection beam No.1 to top layer DS and ODS, fix by 4 double taper pin4Φ40x95(No.2)and 3 clips Φ50(No.2 including
clip);
(2)Install the bop rail No.4 to set back beam, front beam and rotary table beam, fix by 8 single taper pin Φ40x95(No.5)and 16 shear pin
Φ10x55(No.6 inculding clip)

16. Install the air tank lifting frame(including air tank)


Fix the air tank lifting frame to back connection beam by shell pinΦ40x85、and clipΦ30.

28 / 143
ZJ14087-50DB/6 rig installation guide manual

1 2

No. Name Drawing No. Qty. remark


1 Air tank lifting frame Q001.20.00 1
2 2.5m³air tank 1
3 Shell pin Φ40x85 KRT-05-15 4
4 clip Φ30 KRT-01-01 4
(1) Install the air tank together with air tank lifting frameNo.1.then connect air tank lifting frame to back connection frame. Fix by 4
、4 clipΦ30(No.4);
shell pinΦ40x85(No.3)

29 / 143
ZJ14087-50DB/6 rig installation guide manual

17. Install platform and drilling operator room suport


1 2 3

5 4

30 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawwing No. Qty. Remark


1 Platform(2) KR112.22.410.00 1
2 Platform (3) KR112.75.415.00 1
3 Platform (4) KR112.22.425.00 1
4 Platform(5) KR112.22.430.00 1
5 Platform (7) KR112.22.440.00 1
6 Drilling operator room support KR112.22.405.00 5

(1)Install the platform as per turn platform(3)


(No.2),Platform(2)
(No.1), Platform(5)
(No.4), Platform(7)
(No.5), Platform
(4)(No.3);
(2)Install 5pcs drilling operator room supportNo.6 fix by KRT-03-03 single taper pinΦ60x125 10 pcs, 20pcs KRT-02-02 shear
pinΦ15x75(with clip).

31 / 143
ZJ14087-50DB/6 rig installation guide manual

18. Install Driller’s cabin, tool hose, dog hose

2
1

3 Connecting
device

Put dog house and tool house on the substructure


support and connect them with connecting device.

32 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty.


1 DCC 1
2 PF-10.5/2.8/3.1 Dog house KR114.44.00 1
3 Tool house KR114.52.00 1
4 Shell pin Φ40x85 KRT-05-01 4
5 Shear pin Φ10x55 KRT-02-01 4
(1)Install the DCC and fixed by stopper.
(2)Install dog house and tool house as per drawing, fix by 4 shell pinΦ40x85(No.4),4 shear pinΦ10x55(with clip).

33 / 143
ZJ14087-50DB/6 rig installation guide manual

19. Install handrails

Notice:According to below sheet, make sure all the 3


handrails are installed as per mark on the handrail and
substructure socket. 4

2 5
1
6

11

7
8
9
10

34 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Qty. Remark


1 handrail(1) KR112.75.523.00 1 S01
2 handrail(2) KR112.75.524.00 1 S02
3 handrail(3) KR112.75.533.00 1 S03
4 door KR112.75.558.00 1
5 handrail (4) KR112.75.534.00 3 S04

S05

S06
6 handrail (5) KR112.75.535.00 1 S07
7 handrail (6) KR112.75.537.00 1 S08
8 handrail (7) KR112.75.538.00 1 S09
9 handrail (8) KR112.75.540.00 1 S10
10 handrail (9) KR112.75.549.00 1 S12
11 handrail (10) KR112.75.553.00 1 S13

(1)According to part number,install handrail on the corresponding location withΦ30 safety pin .
20. Install A frame
SUKR111.52.890.00。A frame shall be assembled an integral whole and connected with left-right-front-lower seat via shell pin to make
sure backlash uniformity.Note:lifting loads see schematic diagram.

35 / 143
ZJ14087-50DB/6 rig installation guide manual

2、3

3、4

36 / 143
ZJ14087-50DB/6 rig installation guide manual

11
10

12
9

13
8

7
14

37 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Qty. Remark


1 A frame assy. KR111.05.180.00 1 SUKR111.52.890.00
2 Shell pin Φ120x680 KRT120-05-07 2
3 shear-pin Φ25x160 KRT-02-06 4
4 Shell pin Φ130x680 KRT130-05-06 2
5 Front support KR111.05.210.00 2
6 Support KR111.05.214.00 2
7 Platform(left) KR111.05.198.00 1
8 Rear leg KR111.05.200.00 1
9 Small stage(1) KR111.05.190.00 1
10 Handrail(1) KR111.05.189.00 1
11 Handrail(2) KR111.05.194.00 1
12 Small stage(2) KR111.05.195.00 1
13 Large cross beam KR111.05.181.00 1
14 Platform(right) KR111.05.192.00 1
(1)A frame shall be an integral whole before assembly.According to part number,connect rear leg(No.8) and big cross beam (No.13) with
4 shell pins (KRT090-05-02)and shear-pinsΦ20x100(KRT-02-03)(including safety pin);
(2)According to part number,connect front support(No.5) and rear leg(No.8) with 2 shell pins (KRT130-05-07 ) and 2pcs Φ25x140
shear-pins (KRT-02-05)(including safety pin)
(3)According to part number,connect 2 pcs supports (no.6)to front support(no.5) and rear leg (no.8)with 4 pcsΦ40x85 shell pin

38 / 143
ZJ14087-50DB/6 rig installation guide manual

(including safety pin);


(4)According to part number,fix 2 pcs platforms (No.7 and No.14) with A frame with 4 pcsΦ30x80shell pin (KRT030-05-04)(including
safety pin);
(5)Set up A frame with two 50t cranes;
(6)Lift appropriate location and then align pin hole with 2 pcs Φ120x680 shell pin( KRT120-05-07 )(No.2) ,2 pcsΦ130x680 shell
pin( KRT130-05-06)(No.4),4 pcsΦ25x160 shear-pins ( KRT-02-06)(including safety pin);
(7)At last ,According to part number,handrail(1)handrail(2)(No.10、No.11)are fixed on big cross beam,plug safety pin.

39 / 143
ZJ14087-50DB/6 rig installation guide manual

21. install right and left 1section


Before installing ,tidy mast main body components and parts,count interchangeable part quantity on site and tidy all components and parts
according to letter marks and supply missing parts, repair collision transformation during transportation.
After all parts being present,installation will start according to SUKR111.52.01.00 drawing and pin schematic .
When installing mast section and pull rod,connecting pin should be plugged in from top to botto.
When installing steel frame,it should make sure pin can only quit from bottom to top.
Note: 1°In order to distinguish mast main body installing direction ,mark shall be welded.Among which,A-main body,B-steel frame ,C-
diagonal rod,R-right,L-left,01-I section, 02-II section, 03-III section, 04-IV section.For example ,AL-02 is left II section of main leg .When
installing steel frame and diagonal rod, “L”、“R”mark is to distinguish left and right,and “T”、“B”mark is to distinguish top and bottom .
2°Lifting load see lifting schematic diagram SUKR111.52.800.00、SUKR111.52.810.00、SUKR111.52.820.00、SUKR111.52.830.00、
SUKR111.52.840.00、SUKR111.52.850.00、SUKR111.52.860.00、SUKR111.52.870.00、SUKR111.52.880.00、SUKR100.10.623.00、
SUKR100.10.624.00。

40 / 143
ZJ14087-50DB/6 rig installation guide manual

Note:lower support should bear the first node of mast I

section.N

4、5
3

41 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Qty. Remark


1 Left Ⅰ section KR111.05.10.00 1 SUKR111.52.800.00
2 RightⅠ section KR111.05.01.00 1 SUKR111.52.800.00
3 Lower support L/KR111.05.17.00 2
4 Shell pin Φ150x680 KRT150-05-04 2
5 Sheer-pin Φ25x160 KRT-02-06 2
(1)According to part number,lift left I section(No.1) to appropriate location of left-front base, align mast main leg pin hole and padeye
hole of left-front-bottom-base ,plug inΦ150x680 (No.4),sheer-pinΦ25x160(No.5 ,including safety pin).After installing ,put leftI
section(No.1) on the lower support(No.3);
(2)According to part number, lift right I section(No.2) to appropriate location of right-front-bottom base, align mast main leg pin hole and
padeye hole of right-front-bottom-base ,plug inΦ150x680 (No.3),sheer-pinΦ25x160(No.4 ,including safety pin).After installing ,put right I
section(No.2) on the lower support(No.3).

42 / 143
ZJ14087-50DB/6 rig installation guide manual

22. Stand column and left&right top base connecting pin before installing

The connecting part of front stand column and left&right top base has 4 pcs KRT130-03-03 pyramid pinΦ130x535(No.1), 8 pcs KRT-02-05
sheer-pinΦ25x140(No.2 including safety pin )

43 / 143
ZJ14087-50DB/6 rig installation guide manual

23. install left and right II section

3、4、5

No. Name Drawing no. Qty. Remark


1 Left Ⅱ section KR111.05.35.00 1
2 Right Ⅱsection KRT-02-02 1
3 Bolt M36x220 GB/T5782-2000 28
4 Washer 36 GB/T97.1-2002 28
5 Nut M36 GB/T6170-2000 56

44 / 143
ZJ14087-50DB/6 rig installation guide manual

24. install back steel frame , diagonal member,steel frame 6

45 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Qty. Remark


1 Back steel frame KR111.05.165.00 1
2 Steel frame(6) KR111.05.153.00 1
3 diagonal member module(2) KR111.05.160.00 1
4 Shell pinΦ50x170 KRT050-05-07 12
5 Sheer-pin Φ10x55 KRT-02-01 20
6 Twin cones pin Φ40x100 KRT040-04-01 4
(1)According to part number, lift back steel frame(No.1) to the between of mast left and right II section , align padeye connecting pin
hole ,plug in 8 pcs shell pinΦ50x170 (No.4),8 pcs sheer-pinΦ10x55 (No.5 ,including safety pin);
(2)According to part number, lift steel frame(6)(No.2) to the between of mast left and right II section , align padeye connecting pin
hole ,plug in 4 pcs shell pinΦ50x170 (No.4),4 pcs sheer-pinΦ10x55 (No.5 ,including safety pin);
(3)According to part number, lift diagonal member module(2)(No.3) to the between of mast left and right II section , align padeye
connecting pin hole ,plug in 4 pcsΦ40x100 (No.6) twin cones pin ,8 pcs sheer-pinΦ10x55 (No.5 ,including safety pin).

46 / 143
ZJ14087-50DB/6 rig installation guide manual

25. Left and right section Ⅲ installation


put lower support holding on second joint of mast section II

2 3、4

No. Name Drawing No. Qty. Remarks


1 left section Ⅲ KR111.05.50.00 1 SUKR111.52.810.00
2 right section Ⅲ KR111.05.40.00 1 SUKR111.52.810.00
3 double taper pin Φ60x145 KRT060-04-02 8
4 shear pin Φ15x75 KRT-02-02 16
(1)Put lower support to the second joint of mast section II firstly. After lower support in position, according to part No., lifting up left
section III (No. 1), align pad eye connection pin hole, and insert 4 pieces of doublr taper pinΦ60x145 (No. 3), and 8 pieces of shear pinΦ15x75
(No. 4 including safety pin);

47 / 143
ZJ14087-50DB/6 rig installation guide manual

(2)According to part No., lifting up right section III (No. 2), align connecting pad eye pin hole, and insert 4 pieces of double taper
pinΦ60x145 (No. 3), and 8 pieces of shear pinΦ15x75 (No. 4 including safety pin).
26. Install pull rod and steel frame

2 1

4
5、6 7、8
3

48 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 steel frame(5) KR111.05.145.00 1 SUKR111.52.870.00
2 steel frame(4) KR111.05.135.00 1 SUKR111.52.860.00
3 inclined pull rod assembly(1) KR111.05.150.00 1 SUKR111.52.870.00
4 inclined pull rod(5) KR111.05.140.00 1 SUKR111.52.860.00
5 shell pin Φ50x170 KRT050-05-07 8
6 shear pin Φ10x55 KRT-02-01 20
7 double taper pin Φ40x100 KRT040-04-01 6

(1)According to part No., lifting up steel frame(5) (No. 1), steel frame (4)(No. 2) successively, align steel frame connecting pad eye pin
hole according to drawing, and insert 8 pieces of shell pin Φ50x170 (No. 5), 8 pieces of shear pin Φ10x55 (No. 6 including safety pin);
(2)According to part No., lifting up inclined pull rod assembly (1)(No. 3), inclined pull rod (5) (No. 4) successively, align steel frame
connecting pad eye pin hole according to drawing, and insert 6 pieces of double taper pin Φ40x100 (No. 7), 12 pieces of shear pin Φ10x55 (No.
6 including safety pin)

49 / 143
ZJ14087-50DB/6 rig installation guide manual

27. Install mast section Ⅳ 3、4

2
Put lower support holding on second joint of mast
sectionIII

No. Name Drawing No. Qty. Remarks


1 left section Ⅳ KR111.05.70.00 1 SUKR111.52.820.00
2 right section Ⅳ KR111.05.60.00 1 SUKR111.52.820.00
3 double taper pin Φ60x145 KRT060-04-02 8
4 shear pin Φ15x75 KRT-02-02 16
(1)Put lower support to the second joint of mast section III firstly. After lower support in position, according to part No., lifting up left

50 / 143
ZJ14087-50DB/6 rig installation guide manual

section IV (No. 1), align pad eye connection pin hole, and insert 4 pieces of doublr taper pinΦ60x145 (No. 3), and 8 pieces of shear pinΦ15x75
(No. 4 including safety pin);
(2)Lifting load is shown as lifting schematic diagram SUKR111.52.820.00. According to part No., lifting up right section IV (No. 2),
align pad eye connection pin hole, and insert 4 pieces of double taper pinΦ60x145 (No. 3), and 8 pieces of shear pinΦ15x75 (No. 4 including
safety pin)

51 / 143
ZJ14087-50DB/6 rig installation guide manual

28. Install pull rod and steel frame

3 2 1 5、6 6、7

No. Name Drawing No. Qty. Remarks


1 inclined pull rod(4) KR111.05.130.00 1 SUKR111.52.870.00
2 steel frame(3) KR111.05.125.00 1 SUKR111.52.860.00
3 inclined pull rod(3) KR111.05.120.00 1 SUKR111.52.870.00

52 / 143
ZJ14087-50DB/6 rig installation guide manual

4 steel frame(2) KR111.05.115.00 1 SUKR111.52.860.00


5 shell pin Φ50x170 KRT050-05-07 8
6 shear pin Φ10x55 KRT-02-01 16
7 double taper pin Φ40x100 KRT040-04-01 4

(1)Lifting load is shown as lifting schematic diagram SUKR111.52.860.00. According to part No., lifting up right steel frame (3) (No.
2), steel frame (2) (No. 4) successively , align steel frame connection pad eye pin hole, and insert 8 pieces of shell pin Φ50x170 (No. 6), and 8
pieces of shear pin Φ10x55 (No. 6 including safety pin);
(2)Lifting load is shown as lifting schematic diagram SUKR111.52.870.00.According to part No., lifting up inclined pull rod (4) (No. 1),
inclined pull rod (3) (No. 3), align section connecting pad eye pin hole, and insert 4 pieces of double taper pinΦ40x100 (No. 7), and 8 pieces of
shear pinΦ10x55 (No. 6 including safety pin).

53 / 143
ZJ14087-50DB/6 rig installation guide manual

29. Install mast section Ⅴ

3、4

2 put lower support holding on first joint of mast


section IV
No. Name Drawing No. Qty. Remarks
1 left section Ⅴ KR111.05.90.00 1 SUKR111.52.830.00
2 right section Ⅴ KR111.05.80.00 1 SUKR111.52.830.00
3 double taper pin Φ60x145 KRT060-04-02 8
4 shear pin Φ15x75 KRT-02-02 16
(1)Remove lower support to the first joint of mast section IV firstly. According to part No., lifting up left section V (No. 1) align section
connecting pad eye pin hole, and insert 4 pieces of double taper pin Φ60x145 (No. 3) , 8 pieces of shear pin Φ15x75 ( No. 4 including safety
pin);
(2)According to part No., lifting up right section V (No. 2), align section connecting pad eye pin hole, and insert 4 pieces of double taper

54 / 143
ZJ14087-50DB/6 rig installation guide manual

pin Φ60x145 (No. 3) , 8 pieces of shear pin Φ15x75 ( No. 4 including safety pin);
30. Install steel frame and pull rod
1

2 6、7
3
7、8

No. Name Drawing No. Qty. Remarks


1 inclined pull rod(2) KR111.05.110.00 1 SUKR111.52.840.00
2 steel frame(1) KR111.05.105.00 1 SUKR111.52.840.00
3 inclined pull rod(1) KR111.05.100.00 1
4 pull rod KR111.05.95.00 1
5 front pull rod assembly KR111.05.97.00 1
6 shell pin Φ50x170 KRT050-05-07 4

55 / 143
ZJ14087-50DB/6 rig installation guide manual

7 shear pin Φ10x55 KRT-02-01 24


8 double taper pin Φ40x100 KRT040-04-01 10
(1)According to part No., lifting up steel frame (1) (No. 2), align steel frame connecting pad eye pin hole, and insert 4 pieces of shell pin
Φ50x170 (No. 6) , 4 pieces of shear pin Φ10x55 ( No. 7 including safety pin);
(2)According to part No., lifting up inclined pull rod (2) (No. 1), inclined pull rod (1) (No. 3), pull rod (No.4), and front pull rod assembly
(No.5) successively, align section connecting pad eye pin hole according to drawing, and insert 10 pieces of double taper pin Φ40x100 (No. 8) ,
20 pieces of shear pin Φ10x55 ( No. 7 including safety pin).

56 / 143
ZJ14087-50DB/6 rig installation guide manual

31. Put upper support in position

Note:upper support should hold on the second joint of mast section V Note:To avoid mast deformation,two cranes should cooperate to lift simultaneously.

Put the upper support holding on the second joint of mast section V.

57 / 143
ZJ14087-50DB/6 rig installation guide manual

32. Install crown block

2, 3, 4, 5, 6

58 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 crown block KR101.29.00 1 SUKR101.29.200.00
2 bolt M30x160 GB/T31.1-1988、 12
3 taper liner (1) KR111.05.05 4
4 taper liner (2) KR111.05.06 8
5 nut M30 GB/T6178-1986 12
6 washer 30 GB/T97.1-2002 12
7 Pin 6.3x50 GB/T91-2000 12
Connect crown block and mast firmly with bolts.

59 / 143
ZJ14087-50DB/6 rig installation guide manual

33. Install counterweight device


1

Note:to avoid abnormal sound, put counterweight

device barrel in lower position

No. Name Drawing No. Qty. Remarks


1 counterweight device KR111.05.320.00 1

(1)According to part No., lifting up each parts of counter weight device (No.1 ) successively, connect wirerope and balance bucket with 3
pieces of (DX6.5t-7/8) D type shackle, and 2 pieces of wire rope assembly cross 3 pieces of KR111.05.321.00 snatch block of mast section III

60 / 143
ZJ14087-50DB/6 rig installation guide manual

from another end.


34. Install monkey board and stand pipe operating platform

3, 4

4, 5, 6

1 2

Note:Whenever mast installation ,mast rising or mast down, monkey board is not be used as support.

61 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 monkey board KR111.05.240.00 1
2 stand pipe operating platform KR111.05.490.00 1
3 shell pin Φ60x115 KRT-05-03 2
4 shear pin Φ15x75 KRT-02-02 6
5 shell pin Φ50x110 KRT050-05-06 4
6 shell pin Φ25x75 KRT025-05-03 7
(1)Lifting monkey board (including stay bar) to installation position of mast section III ,(the height will be decided by engineer, and there
are three options for choosing, 24.5m, 25.5m, and 26.5m ), insert 2 pieces of shell pinΦ60x115 (No. 3), 4 pieces of shell pin Φ50x110 (No. 5), 6
pieces of shear pinΦ15x75 (No. 4 including safety pin);
(2)Install each part of stand pipe operating platform together, and insert 7 pieces of shell pinΦ25x75 (No. 6), 7 pieces of safety pinΦ30.

62 / 143
ZJ14087-50DB/6 rig installation guide manual

35. Install cage ladder

6 5

1 2 3 4

7、8

63 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing No. Qty. Remarks


1 cage ladder(1) KR111.05.466.00 2
2 cage ladder(2) KR111.05.470.00 1
3 cage ladder(3) KR111.05.473.00 1
4 cage ladder(4) KR111.05.476.00 2
5 cage ladder(6) KR111.05.482.00 1
6 cage ladder(7) KR111.05.484.00 1
7 shell pin Φ20x55 KRT-05-13 78
8 safety pin Φ30 KRT-01-01 78
(1)According to part No., install ladders of left and right side from top to bottom in position, and fixed with 78 pieces of shell pinΦ20x55
and 78 pieces of safety pinΦ30.

64 / 143
ZJ14087-50DB/6 rig installation guide manual

36. Install raising platform and travelling block


1

No. Name Drawing No. Qty. Remarks


1 YC450 travelling block KR102.16.00 1
2 rising platform KR111.05.19.00 1
(1)According to part No., put rising platform (No. 2) in position.
(2)Put YC 450 travelling block (No. 1) on rising platform (No. 2).

65 / 143
ZJ14087-50DB/6 rig installation guide manual

37. Put electrical spooler in position and install raising line

3, 4

No. Name Drawing No. Qty. Remarks


1 raising line Φ80 2 53.7m
2 drilling line 1
3 shell pin Φ130x315 KRT130-05-01 4
4 shear pin Φ25x140 KRT-02-05 4

66 / 143
ZJ14087-50DB/6 rig installation guide manual

(1)Drilling line stringing schematic diagram

Note:Number in figure stands for stringing step,arrow stands for stringing direction.

A frame fast line guide sheaves


Crown block fast
line sheaves set

Drawworks
drum
Crown block main
sheaves set

Travelling
Deadline anchor block

67 / 143
ZJ14087-50DB/6 rig installation guide manual

procedure 1 2 3 4 5-14 15
Come out from
Wind between
last sheave of
from wire line Wind A-frame fast crown block main
Drilling line Wind crown block Wind travelling crown block,
spooler tow rope line boom sheave, sheave group and
fast line sheave block, leading to leading to
drum, leading to leading to crown travelling block
(tow rope group, leading to crown block main deadline anchor,
A-frame fast line block fast line successively, on 6
stringing) travelling block sheave group connecting to
boom sheave sheave group sheaves from top
drilling line on
to bottom
spooler

(2)Raising line stringing procedure


1°Firstly, put one end of the raising line, and connect to counterbalance tripod through shell pinφ130x315(KRT130-05-01)and shear
pinφ25x140(KRT-02-05 including safety pin);
2°Secondly put another end of raising line to cross mast section Ⅰ simply supported pulley, jib pulley and A-frame jib pulley orderly, and then
connect to substructure raising line pad eye through shell pinφ130x315(KRT130-05-01)and shear pinφ25x140(KRT-02-05 including safety
pin);
3°Stringing procedures are the same for left and right raising line.

68 / 143
ZJ14087-50DB/6 rig installation guide manual

38.Put main body of generator house trailer in position Generator house trailer axis
78’-10 3/4”(24045mm)

3 2

5 4

55’-3”(16840mm)

No. Name Drawing No. Qty. Remarks


1 Frame assembly 1
2 60T hydraulic cylinder 6
3 80T mechanical outrigger 6
4 tire assembly 2
5 support plate 3

69 / 143
ZJ14087-50DB/6 rig installation guide manual

39.Installation of generator room platform and working ladder 1

No. Name Drawing No. Qty. Remarks


1 Platform assy. 91950-9036000 1
2 Working ladder 9700-3906000 2

40. Install generator house and platform

70 / 143
ZJ14087-50DB/6 rig installation guide manual

1 2
3
4 5

No. Name Drawwing Qty. Remark


1 #4 generator house KR123.30.80.00 1
2 #3 generator house KR123.30.40.00 1
3 #2 generator house KR123.30.40.00 1
4 #1 generator house KR123.30.40.00 1
5 Auxiliary generator house KR123.30.01.00 1
6 Big platform KR123.30.98.00 1
7 Small platform KR123.30.96.00 3

71 / 143
ZJ14087-50DB/6 rig installation guide manual

41. Install platform of VFD trailer and work

1
4 5 6
21’-5 1/2”(6540mm)

78’-10 3/4”(24045mm)
2

No. Name Drawing Qty. Remark


1 VFD trailer body 91350-2800000 1 7
2 Platform assembly 91350-9036000 1
3 Work ladder 91350-3906000 2
4 60T hydraulic oil cylinder 4
5 80T machinery support 4
6 Wheel assembly 2
7 Base plate 2

72 / 143
ZJ14087-50DB/6 rig installation guide manual

42. Install VFD house

No. Name Drawing Qty. Remark


1 VFD 1 1
2 VFD 2 1

73 / 143
ZJ14087-50DB/6 rig installation guide manual

43. Install handrail and accessory

No. Name Drawing Qty. Remark


1 Handrail assembly 91350-9013000 1
2 Cable trough I Q001.33.00 1

74 / 143
ZJ14087-50DB/6 rig installation guide manual

44. Location the mud pump trailer

20’-4”(6200mm)

1 2

Frame center line

3
86’-11 1/2”(26505mm)
4

No. Name Drawing Qty. Remark


1 Mud pump trailer body 1
2 Platform assembly 1
3 80T machinery support 4
4 60T hydraulic pressure support 4

75 / 143
ZJ14087-50DB/6 rig installation guide manual

45. Install platform and work ladder


2

No. Name Drawing Qty. Remark


1 Platform assembly 92100-7705000 1
2 Work ladder 92100-3906000 2

76 / 143
ZJ14087-50DB/6 rig installation guide manual

46. Install mud pump device

No. Name Drawing Qty. Remark


1 F-1600 mud pump device KR107.06.00 3

77 / 143
ZJ14087-50DB/6 rig installation guide manual

47. Install rotary cable trough and middle cable trough


1

No. Name Drawing Qty. Remark


1 Rotary cable support Ⅰ Q001.39.00 1
2 Middle cable support Q001.47.00 1
3 Rotary cable support Ⅱ Q001.50.00 1

78 / 143
ZJ14087-50DB/6 rig installation guide manual

48. Install flod cable trough 1、2、3 4

1、2、3

79 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing Qty. Remark


1 Pin bearing Q001.36.02 3
2 Shear pin Φ15x75 KRT-02-02 3
3 Safety pin Φ30 KRT-01-01 3
4 Cable trough Ⅱ Q001.38.00 1
5 Cable trough I Q001.37.00 1

39. Mast before raising


1.String the air winch wire line , man-riding winch wire line and travelling block hanging line.
2. Install the mast high pressure manifold on the right position and connect rotary hose.
3. Install the prevent falling device and escape device on position.

80 / 143
ZJ14087-50DB/6 rig installation guide manual

50. During mast raising

Note:During the mast raising , should have one person command , pay

attention to safety , make sure safe operation .

81 / 143
ZJ14087-50DB/6 rig installation guide manual

51. The mast raising to 90°

Note: Extend the buffer cylinder before

mast raising , when the mast raising to


1、2、
85°,the driller moving the mast to right 3、4

position smoothly.

No. Name Drawing Qty. Remark


1 U-bolt KR111.05.03 2
2 Platen KR111.05.04 2
Nut M36 GB/T6170-2000 72
Gasket 36 GB/T97.1-2002 36

82 / 143
ZJ14087-50DB/6 rig installation guide manual

52. Exit lower install pin

2 3、4

No. Name Drawing Qty. Remark


1 KR112.75.30.00 Lower support seat 1 8
2 KR112.75.250.00 Lower support seat 2 8
3 KR112.75.02 Single cone pin φ110x325 8
4 KRT-02-04 Shear pin φ20x140 16
After mast raising , before substructure raising ,should take out the single taper pinφ110x325(KR112.75.02) and shear pinφ25x140
(KRT-02-04 with safety pin)between low support seat 1 (KR112.75.30.00)and low support seat 2(KR112.75.250.00).

83 / 143
ZJ14087-50DB/6 rig installation guide manual

Note:Note:During the mast raising , should have one person command , pay

attention to safety , make sure safe operation .

84 / 143
ZJ14087-50DB/6 rig installation guide manual

53. Install oil tube board

4、5

2、3、4

No. Name Drawing Qty. Remark


1 Oil pipe board KR111.05.600.00 1
2 Shell pin Φ30x80 KRT030-05-04 2
3 Pin Φ30 KRT-01-01 6

85 / 143
ZJ14087-50DB/6 rig installation guide manual

54. Install casing stabbing board

2、3

No. Name Drawing Qty. Remark


1 Casing stabbing board KR137.04.00 1
2 Pin Φ50x245 KR137.01.02 1
3 Shear pin Φ10x55 KRT-02-01 1
4 Shell pin Φ50x95 KRT-05-16 2

86 / 143
ZJ14087-50DB/6 rig installation guide manual

55. Install top drive guide rail fixed device ( guide rail 1)

2、3、4 5、6

7、8

No. Name Drawing Qty. Remark


1 Guide rail 1 KR111.52.671.00 1
2 Bolt M20x120 GB/T31.1-1988 8
3 Nut M20 GB/T6178-1986 8
4 Gasket 20 GB/T93-1987 8
5 Shell pin Φ60x240 KR111.52.670.02 6
6 Shear pin Φ15x75 KRT-02-02 6
7 Shell pin Φ40x160 KR111.52.670.05 2
8 Shear pin Φ10x55 KRT-02-01 2

87 / 143
ZJ14087-50DB/6 rig installation guide manual

56. Intsall top drive

No. Name Drawing Qty. Remark


1 Top drive 500ESI-1000 1
2 Elevator link 2

88 / 143
ZJ14087-50DB/6 rig installation guide manual

57. Install rig floor equipment

2 3 1 2
1
No. Name Drawing Qty. Remark
1 hydraulic cat head YM-16B 2
2 5T air winch XJFH-5/35KZS 2
3 Man riding winch FA150KGiMR12A1-A-CE 1

89 / 143
ZJ14087-50DB/6 rig installation guide manual

58. Install BOP lifting device

1 1

No. Name Drawing Qty. Remark


1 BOP lifting device FY-50Y 2

90 / 143
ZJ14087-50DB/6 rig installation guide manual

59. Install pipe rack and high pressure manifold

No. Name Drawing Qty. Remark


1 High pressure mainfold 1
2 Pipe rack Q001.10.00 1

91 / 143
ZJ14087-50DB/6 rig installation guide manual

60. Lay out mud tanks


Make sure the suction tank trailer position based on the rig arrange drawing and mud pump position , then make sure the middle tank trailer ,
shale shaker tank trailer , trip tank trailer , reserve tank trailer and mixing tank trailer based on stop lever.

2 3 4
1

92 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing Nameplate Qty. Remark


1 Trip tank assembly KR113.84.2245.00 BJG-5+1 1
2 Shale shaker tank assembly KR113.84.01.00 NJG405/7-56/1 1
3 Middle tank assembly KR113.84.70.00 NJG405/7-55/2 1
4 Suction tank assembly KR113.84.88.00 NJG405/7-52/3 1
5 Reserve tank I assembly KR113.84.130.00 NJG405/6-72/4 1
6 Reserve tank I assembly KR113.84.130.00 NJG405/6-72/5 1
7 Reserve tank II assembly KR113.84.134.00 NJG405/7-72/6 1
8 Mixing tank assembly KR113.84.138.00 NJG405/7-26/7 1

93 / 143
ZJ14087-50DB/6 rig installation guide manual

4、5、6、7

94 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Positioning rod 1 KR113.84.256.00 1-B-1、1-B-2 2
1-2-1、1-2-2
2 Positioning rod 2 KR113.84.257.00 4
2-3-1、2-3-2
3-4-1、3-4-2
4-5-1、4-5-2
3 Positioning rod 3 KR113.84.258.00 8
5-6-1、5-6-2
6-7-1、6-7-2
4 Shell pin Φ20 KRT-11-01 40
5 Short chain Φ4 L=200 JB/T 8108.2-1999 40
6 Safety pin Φ30 KRT-01-01 40
7 Safety ring Φ4 80

95 / 143
ZJ14087-50DB/6 rig installation guide manual

61.Platform installation 9、10、11、12

8
7

6
4 5

15
2
16

17

18 14
1
20 19

13

96 / 143
ZJ14087-50DB/6 rig installation guide manual

21

22 23 24

27 26

25

97 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Platform G KR113.84.226.00 1-10 1
2 Platform F KR113.84.225.00 1-9 1
1-2
1-8
3 Platform B KR113.84.221.00 2-3 5
2-9
2-10
4 Platform E KR113.84.224.00 1-7 1
5 Platform D KR113.84.223.00 1-6 1
6 Platform C KR113.84.221.00 2-11 1
2-8
7 Platform A KR113.84.220.00 2
2-4
1-5
8 Platform S KR113.84.235.00 2
2-7
9 Shell pin Φ20 KRT-11-01 178
10 Short endless chain Φ4 L=200 JB/T 8108.2-1999 178
11 Safety pin Φ30 KRT-01-01 178
12 Safety ring Φ4 356
13 Platform T KR113.84.239.00 7-1 1
3-4-1、3-4-2
4-5-1、4-5-2
14 Framework KR113.84.237.00 8
5-6-1、5-6-2
6-7-1、6-7-2
15 Platform R KR113.84.234.00 2-6 1
16 Platform K KR113.84.230.00 1-3 2

98 / 143
ZJ14087-50DB/6 rig installation guide manual

2-5
17 Platform P KR113.84.233.00 2-2 1
18 Platform N KR113.84.232.00 2-1 1
19 Platform M KR113.84.231.00 1-4 1
20 Platform H KR113.84.227.00 1-1 1
21 Support rod1 KR113.84.216.00 1-22~1-24 3
22 Support rod2 KR113.84.217.00 1-2、1-3 2
1-1、1-4~1-7、1-13~1-15、
23 Support rod3 KR113.84.218.00 1-17~1-19 28
2-1~2-9、2-13~2-20
1-8~1-13
24 Support rod4 KR113.84.219.00 2-10~2-12 11
7-1、7-2
25 Support rod5 KR113.84.238.00 1-20、1-21 2
26 Tear plate 720×670 t6 KR113.84.215.12 1
27 Tear plate 540×480 t6 KR113.84.215.14 1

99 / 143
ZJ14087-50DB/6 rig installation guide manual

12
62. Handrail installation 7 14 15
6 11

5 8 9 10 13 16
17
4

2
25 18

29 28 27 19

26

30 31 32
24

23

22
33
21 20

100 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Handrail 1 KR113.84.93.00 1-1~1-3、1-16 4
1-4、1-14、1-15
2 Handrail 2 KR113.84.94.00 4
2-7
3 Handrail 3 KR113.84.95.00 1-13 1
4 Handrail 4 KR113.84.96.00 1-12 1
5 Handrail 5 KR113.84.97.00 1-11 1
B-1~B-4
3-9
4-1
6 Handrail 6 KR113.84.98.00 12
5-1、5-10
6-1、6-10
7-1、7-8
7 Handrail 7 KR113.84.99.00 1-10 1
1-5、1-9
8 Handrail 8 KR113.84.100.00 5
2-3、2-14、2-15
1-8
9 Handrail 9 KR113.84.101.00 2
2-16
10 Handrail 10 KR113.84.102.00 2-2、2-4、2-13 3
11 Handrail 11 KR113.84.103.00 2-12 1
2-11
3-5~3-8、3-10~3-13
12 Handrail 12 KR113.84.104.00 4-7~4-9、4-11~4-13 31
5-7~5-9、5-11~5-13
6-7~6-9、6-11~6-13

101 / 143
ZJ14087-50DB/6 rig installation guide manual

7-6、7-7、7-9、7-10
13 Handrail 13 KR113.84.105.00 2-10 1
14 Handrail 14 KR113.84.106.00 2-9 1
15 Handrail 15 KR113.84.107.00 3-16 1
16 Handrail 16 KR113.84.108.00 3-14、3-15 2
3-4
4-5、4-15
17 Handrail 17 KR113.84.109.00 5-5、5-15 8
6-5、6-15
7-11
4-6、4-14
18 Handrail 18 KR113.84.110.00 5-6、5-14 6
6-6、6-14
19 Handrail 19 KR113.84.111.00 4-10 1
20 Handrail 20 KR113.84.112.00 7-5 1
21 Handrail 21 KR113.84.113.00 7-4 1
22 Handrail 22 KR113.84.114.00 7-3 1
3-2
4-2、4-18
23 Handrail 23 KR113.84.115.00 5-2、5-18 9
6-2、6-18
7-2、7-14
3-1、3-3
4-3、4-4、4-16、4-17
24 Handrail 24 KR113.84.116.00 16
5-3、5-4、5-16、5-17
6-3、6-4、6-16、6-17

102 / 143
ZJ14087-50DB/6 rig installation guide manual

7-12、7-13
25 Handrail 25 KR113.84.117.00 2-8 1
26 Handrail 26 KR113.84.118.00 2-6 1
1-6
27 Handrail 27 KR113.84.119.00 2
2-5
28 Handrail 28 KR113.84.120.00 2-1 1
29 Handrail 29 KR113.84.121.00 1-7 1
30 Right-angle Buckle KR113.84.123.00 49
31 Handrail buckle KR113.84.92.01 73
32 Bolt M8×70 GB/T 5782-2000 171 Galvanization(unit:set)
33 Safety pin φ50 KRT-01-02 254

103 / 143
ZJ14087-50DB/6 rig installation guide manual

63.Equipment installation
12
11
10 13
0

9 14
8 15
7
6
5
3
4
2

20
1
21 19

18
17
22
16

23

104 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Poor boy HLGS1200-1.0 14087.1/S/0101 1 TSC
2 Shale shaker DP-626 14087.1/S/0201 1 DERRICK
3 Shale shaker DP-626 14087.1/S/0202 1 DERRICK
4 Shale shaker DP-626 14087.1/S/0203 1 DERRICK
5 Vacuum degasser HV-1200 14087.1/S/0301 1 TSC
6 Sander Vertical Standalone 3×10" 14087.1/S/0401 1 DERRICK
7 Cleaner HMC300×3/100×20-270-DP 14087.1/S/0601 1 TSC
8 Silter Inline Standalone 20×4" 14087.1/S/0501 1 DERRICK
9 Centrifuge LW355-1250N 14087.1/S/0701 1 Feida
10 Agitator HA-5.5 14087.1/S/1013 1 TSC
11 Agitator HA-15 14087.1/S/1004 1 TSC
12 Agitator HA-15 14087.1/S/1005 1 TSC
13 Agitator HA-15 14087.1/S/1007 1 TSC
14 Agitator HA-15 14087.1/S/1009 1 TSC
15 Agitator HA-15 14087.1/S/1011 1 TSC
16 Agitator HA-15 14087.1/S/1012 1 TSC
17 Agitator HA-15 14087.1/S/1010 1 TSC
18 Agitator HA-15 14087.1/S/1008 1 TSC
19 Agitator HA-15 14087.1/S/1006 1 TSC
20 Agitator HA-15 14087.1/S/1003 1 TSC
21 Agitator HA-15 14087.1/S/1002 1 TSC
22 Agitator HA-15 14087.1/S/1001 1 TSC
23 Electronic ignition device YPD20/3.5 14087.1/S/1402 1 Chengde jiangzuan

105 / 143
ZJ14087-50DB/6 rig installation guide manual

64.Poorboy flow

2 5、6

Connecting to choke manifolds

106 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Hose with wireline DN50 4MPa L=8000 A-612 1 NPT buckle for one
end
2 Pipeline 121 1
3 Pipeline 122 1
4 Ignition Pipeline KR113.84.253.00 6
5 Flange washer DN200 PN16 GB/T 9126-2008 9
6 Bolt M20×90 GB/T 5782-2000 96 Galvanization
(unit:set)
7 Electronic ignition device YPD20/3.5 14087.1/S/1402 1 Chengde jiangzuan
8 Support 1
9 Hose with wireline DN100 4MPa L=7000 M-613 1 NPT buckle for one
end

107 / 143
ZJ14087-50DB/6 rig installation guide manual

65.Shale shaker flow

5、6、7 8
9

2、3、4
1

21
10

20 13 11、12

17、18、19

14、15、16

108 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Current divider box assy. KR113.84.07.00 1
2 Pipeline 2 1
3 c DN300 1.6MPa 3
4 Stud M24×220 GB/T 901-1988 36 Galvanization(unit :set)
5 Pipeline 3 1
6 Butterfly valve DN250 1.6MPa 2
7 Stud M24×200 GB/T 901-1988 24 Galvanization(unit :set)
8 Pipeline 4 1
9 Shale shaker seat KR113.84.14.00 1
10 Hopper 1 KR113.84.17.00 1、2、3 3
11 Diversion trench 1 KR113.84.11.00 1、2 2
12 Bolt M10×35 GB/T 5783-2000 16 Galvanization(unit :set)
13 Pressing plate assy.1 KR129.108.00 12
14 Blind flange DN250 PN16RF GB/T 9123.1-2000 1 With waterline
15 Flange washer DN250 PN16 GB/T 9126-2008 2
16 Bolt M24×100 GB/T 5783-2000 24 Galvanization(unit :set)
17 Shell pin Φ20 KRT-11-01 4
18 Short endless chain Φ4 L=200 JB/T 8108.2-1999 4
19 Safety pin Φ30 KRT-01-01 4
20 Pipeline 5 1
21 Pipeline 1 1

109 / 143
ZJ14087-50DB/6 rig installation guide manual

66.Degasser flow

10、11 12 13

14、15、16、17

6、7、8、9

Suction line
18

2、3、4、5

110 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Sand pump fixing assy. 1 KR129.106.00 4
2 JGD Flexible rubber connector DN200 1.6MPa 1 Metric & imperial system for two ends
3 Bolt M20×100 GB/T 5782-2000 8 Galvanization(unit :set)
4 Butterfly valve DN200 1.6MPa 2
5 Stud M20×190 GB/T 5782-2000 12 Galvanization(unit :set)
6 Shell pin Φ20 KRT-11-01 4
7 Short endless chain Φ4 L=200 JB/T 8108.2-1999 4
8 Safety pin Φ30 KRT-01-01 4
9 Safety ring Φ4 8
10 Pipeline 11 1
11 Flange washer DN150 PN16 GB/T 9126-2008 2
12 Pipeline 12 1
13 Pipeline 13 1
14 JGD Flexible rubber connector DN150 1.6MPa 1 Metric & imperial system for two ends
15 Bolt M20×90 GB/T 5782-2000 24 Galvanization(unit :set)
16 Butterfly valve DN150 1.6MPa
17 Stud M20×180 GB/T 5782-2000 16 Galvanization(unit :set)
18 Hose with wireline DN50 4MPa L=4000 A-601 1 NPT buckle for two ends

111 / 143
ZJ14087-50DB/6 rig installation guide manual

67.Desand flow

11、12、13 14
15、16
25

17

10

18、19、20、21
26
27、28
22、23、24

29

1、2

3、4、5、6

7
8
9
9

112 / 143
ZJ14087-50DB/6 rig installation guide manual

Part
No. Name Drawing no. Qty. Remarks
no.
1 Sand pump fixing assy. 1 KR129.106.00 4
2 Sand pump support 1 KR113.84.41.00 1
3 JGD Flexible rubber connector DN200 1.6MPa 1 Metric & imperial
system for two ends
4 Bolt M20×100 GB/T 5782-2000 8 Galvanization
5 Butterfly valve DN200 1.6MPa 1
6 Stud M20×190 GB/T 901-1988 12 Galvanization
(unit :set)
7 Pipeline 16 1
8 Pipeline 17 1
9 Pipe support 6" KR113.84.29.00 2
10 Pipeline 20 1
11 Blind flange DN200 PN16RF GB/T9123.1-2000 1
12 Flange washer DN200 PN16 GB/T 9126-2008 3
13 Bolt M20×90 GB/T 5782-2000 60 Galvanization
(unit :set)
14 Pipeline 19 1
15 Flange washer DN250 PN16 GB/T 9126-2008 2
16 Bolt M24×100 GB/T 901-1988 24 Galvanization
(unit :set)
17 Pipeline 18 1
18 Shell pin Φ20 KRT-11-01 8
19 Short endless chain Φ4 L=200 JB/T 8108.2-1999 16

113 / 143
ZJ14087-50DB/6 rig installation guide manual

20 Safety pin Φ30 KRT-01-01 16


21 Safety ring Φ4 32
22 JGD Flexible rubber connector DN150 1.6MPa 1 Metric & imperial
system for two ends
23 Butterfly valve DN150 1.6MPa 1
24 Stud M20×180 GB/T 901-1988 8 Galvanization
(unit :set)
25 Pipeline 21 1
26 Chip space 1 assy. KR113.84.32.00 1
27 Support rod KR113.84.34.00 2
28 Shell pin Φ13 KR129.116.02 4
29 Shell pin Φ25×65 KRT025-05-02 4

114 / 143
ZJ14087-50DB/6 rig installation guide manual

68.Desilt flow

13 14

15
12
16、17、18、19、20

11

9、10

21
6、7、8

2、3、4、5 1

115 / 143
ZJ14087-50DB/6 rig installation guide manual

Fig 11 desilt flow


Part
No. Name Drawing no. Qty. Remarks
no.
1 Pipeline 41 1
2 Butterfly valve DN200 1.6MPa 1
3 JGD Flexible rubber connector DN200 1.6MPa 1 Metric & imperial
system for two ends
4 Stud M20×190 GB/T 901-1988 12 Galvanization
(unit :set)
5 Bolt M20×100 GB/T 5782-2000 8 Galvanization
(unit :set)
6 JGD Flexible rubber connector DN150 1.6MPa 1 Metric & imperial
system for two ends
7 Stud M20×180 GB/T 901-1988 8 Galvanization
(unit :set)
8 Butterfly valve DN150 1.6MPa 1
9 Sand pump fixing assy. 1 KR129.106.00 4
10 Sand pump support seat 2 KR113.84.82.00 1
11 Pipeline 42 1
12 Pipeline 43 1
13 Pipeline 44 1
14 Bolt M20×90 GB/T 5782-2000 72 Galvanization
(unit :set)
15 Chip space 1assy. KR113.84.32.00 1
16 Support rod KR113.84.34.00 2
17 Shell pin Φ13 KR129.116.02 8

116 / 143
ZJ14087-50DB/6 rig installation guide manual

18 Short endless chain Φ4 L=200 JB/T 8108.2-1999 8


19 Safety pin Φ30 KRT-01-01 8
20 Safety ring Φ4 16
21 Shell pin Φ25×65 4

69. All-in-one cleaner machine

14 15

13
1、2 29

28
3
27
4、5 30
25、26
6
7
12 11
8
9 20、21、22、23、24 31、32、33
10 34
19 16、17、18

117 / 143
ZJ14087-50DB/6 rig installation guide manual

No. Name Drawing no. Part no. Qty. Remarks


1 Flange washer DN200 PN16 GB/T 9126-2008 6
2 Bolt M20×90 GB/T 5782-2000 68 Galvanization(unit :set)
3 Pipeline 26 1
4 Butterfly valve DN200 1.6MPa 5
5 Stud M20×180 GB/T 901-1988 52 Galvanization(unit :set)
6 Pipeline 27 1
7 Pipeline 28 1
8 Pipeline 29 1
9 Pipeline 30 1
10 Pipeline 31 1
11 Diversion trench2 KR113.84.51.00 1
12 Pipeline 38 1
13 Pipeline 37 1
14 Pipeline 34 1
15 Pipeline 33 1
16 JGD Flexible rubber connector DN200 1.6MPa 2 Metric & imperial system for two ends
17 Bolt M20×100 GB/T 5782-2000 16 Galvanization(unit :set)
18 Stud M20×190 GB/T 901-1988 24 Galvanization(unit :set)
19 Pipe support 1 KR113.84.55.00 2
20 Shell pin Φ20 KRT-11-01 16
21 Short endless chain Φ4 L=200 JB/T 8108.2-1999 20
22 Safety pin Φ30 KRT-01-01 20

118 / 143
ZJ14087-50DB/6 rig installation guide manual

23 Safety ring Φ4 40
24 Pipe support 2 KR113.84.57.00 1
25 JGD Flexible rubber connector DN150 1.6MPa 2 Metric & imperial system for two ends
26 Butterfly valve DN150 1.6MPa 5
27 Pipeline 32 1
28 Pipeline 35 1
29 Pipeline 36 1
30 Hopper 2 KR113.84.62.00 1
31 Chip space 2 assy. KR113.84.63.00 1
32 Support rod KR113.84.34.00 2
33 Shell pin Φ13 KR129.116.02 4
34 Sand pump fixing assy. 1 KR129.106.00 8

119 / 143
ZJ14087-50DB/6 rig installation guide manual

70.Centrifugal process

3
5

7、8、9、10、11

120 / 143
ZJ14087-50DB/6 rig installation guide manual

Item Name Drawing number Parts No. Qty Note


1 Bolt M16×40 GB/T 5783-2000 4 Galvanization(Unit:set)
2 Rubber hose DN50 L=3000 M-604 1 Supply pipe
3 Rubber hose DN25 L=2500 M-605 1 Discharge pipe
4 Rubber hose DN25 L=1200 W-606 1 Washing pipe
5 Pipeline 46 1
6 Exhaust channel assembly KR113.84.85.00 1
7 Support rod KR113.84.34.00 2
8 Shell pin Φ13 KR129.116.02 4
9 Short circle chain Φ4 L=200 JB/T 8108.2-1999 4
10 Pin Φ30 KRT-01-01 4
11 Safety ring Φ4 8

121 / 143
ZJ14087-50DB/6 rig installation guide manual

71.Mixing hopper and super sack hoist

10 11
9
7、8

6
5 16、17
4

1、2、3
12
13、14、15

Sand pump fixing

24、25、26、27

23
19
22 20 18
21

122 / 143
ZJ14087-50DB/6 rig installation guide manual

Item Name Drawing no. Parts no. Qty Note


1 Flange cover DN150 PN16RF GB/T 9123.1-2000 1
2 Flange wahser DN150 PN16 GB/T 9126-2008 11
3 Bolt M20×90 GB/T 5782-2000 104 Galvanization(Unit:set)
4 Pipeline 126 1
5 Pipeline 129 1
6 Pipeline 132 1
7 JGD flexible rubber joint DN150 1.6MPa 2 Two ends metric、english
8 Bolt stud M20×180 GB/T 901-1988 16 Galvanization(Unit:set)
9 Pipeline 135 1
10 Pipeline 136 1
11 Super sack frame KR113.84.265.00 1
12 Pipeline 133 1
13 Shell pin Φ50×250 KRT050-05-04 4
14 Pin Φ50 KRT-01-02 4
15 Short circle chain Φ4 L=200 JB/T 8108.2-1999 4
16 Butterfly valve DN150 1.6MPa 12
17 Bolt stud M20×170 GB/T 901-1988 80 Galvanization(Unit:set)
18 Sand pump fixing assembly 1 KR129.106.00 8
19 Pipeline 134 1
20 Pipeline 131 1
21 Pipeline 128 1
22 Pipeline 130 1
23 Pipeline 127 1
24 JGD flexible rubber joint DN125 1.6MPa 1

123 / 143
ZJ14087-50DB/6 rig installation guide manual

25 Bolt M16×90 GB/T 5782-2000 8 Galvanization(unit:set)


26 Bolt M16×170 GB/T 901-1988 8 Galvanization(unit:set)
27 Butterfly valve DN125 1.6MPa 1

124 / 143
ZJ14087-50DB/6 rig installation guide manual

72.Mixing and shear process

Mixing discharge
process

Mixing suction
process
图 14 加重、剪切流程

125 / 143
ZJ14087-50DB/6 rig installation guide manual

9
12
图 1511加重吸浆流程
13、14、15
10

7、8
1、2

6 3
4、5
Mixing suction process

126 / 143
ZJ14087-50DB/6 rig installation guide manual

24
20

23
25

20

22

20

21
图 16 加重放浆流程

20

18

19

16
17

Mixing discharge process

127 / 143
ZJ14087-50DB/6 rig installation guide manual

Ite, Name Drawing number Parts no Qty Note


1 JGD flexible rubber joint DN150 1.6MPa 1 Two ends metric、english
2 Bolt M20×90 GB/T 5782-2000 8 Galvanization(unit:set)
3 Pipeline 86 1
4 Butterfly valve DN150 1.6MPa 14
5 Bolt M20×170 GB/T 901-1988 104 Galvanization(unit:set)
6 Pipeline 87 1
7 Butterfly valve DN200 1.6MPa 5
8 Bolt M20×180 GB/T 901-1988 140 Galvanization(unit:set)
9 Pipeline 89 4
10 Suction Pipeline1 KR113.84.179.00 8
11 Extension rod butterfly valve DN200 1.6MPa L=2300 8
12 Pipeline 88 1
13 JGD flexible rubber joint DN200 1.6MPa 2 Two ends metric、english
14 Bolt M20×100 GB/T 5782-2000 16 Galvanization(unit:set)
15 Bolt M20×190 GB/T 901-1988 24 Galvanization(unit:set)
16 Pipeline 76 1
17 Pipeline 77 1
18 Pipeline 78 1
19 Pipeline 79 1
20 Pipeline 80 4
21 Pipeline 81 1
22 Pipeline 82 1
23 Pipeline 83 1
24 Pipeline 84 1

128 / 143
ZJ14087-50DB/6 rig installation guide manual

25 Discharge Pipeline1 KR113.84.166.00 8

129 / 143
14087-50DB rig installation guide manual

73.Suction process
5

3、4

8、9、10
1

11、12、13、14

130 / 143
14087-50DB rig installation guide manual

24
31

18
23
30

19 20
17 22
29

26 25
16 28

27

15 21

Suction tank
32、33、34、35

36

131 / 143
14087-50DB rig installation guide manual

Item Name Drawing no Parts no Qty Note


1 Suction Pipeline7 KR113.84.159.00 9
2 Pipeline 51 5
3 Extension rod butterfly valve DN300 1.6MPa X=2150 9
4 Bolt M24×220 GB/T 901-1988 168 Galvanization(unit:set)
5 Pipeline 57 1
6 Pipeline 63 1
7 Pipeline 69 1
8 Flange cover DN300 PN16RF GB/T 9123.1-2000 2
9 Flange washer DN300 PN16 GB/T 9126-2008 6
10 Bolt M24×100 GB/T 5782-2000 72 Galvanization(unit:set)
11 JGD flexible rubber joint DN200 1.6MPa 3 Two ends metric and english
12 Bolt M20×100 GB/T 5782-2000 24 Galvanization(unit:set)
13 Butterfly valve DN200 1.6MPa 3
14 Bolt M20×190 GB/T 901-1988 36 Galvanization(unit:set)
15 Pipeline 52 1
16 Pipeline 54 1
17 Pipeline 55 1
18 Pipeline 56 1
19 Pipeline 53 1
20 Pipeline 70 1
21 Pipeline 58 1
22 Pipeline 60 1
23 Pipeline 61 1
24 Pipeline 62 1

132 / 143
14087-50DB rig installation guide manual

25 Pipeline 71 1
26 Pipeline 59 1
27 Pipeline 72 1
28 Pipeline 65 1
29 Pipeline 66 1
30 Pipeline 67 1
31 Pipeline 68 1
32 JGD flexible rubber connector DN150 1.6MPa 3 Two ends metric and english
33 Bolt M20×90 GB/T 5782-2000 48 Galvanization(unit:set)
34 Butterfly valve DN150 1.6MPa 3
35 Stud M20×170 GB/T 901-1988 24 Galvanization(unit:set)
36 Sand pump fixed assy. KR129.106.00 12

133 / 143
14087-50DB rig installation guide manual

74.Balance Pipeline

7
8

5
4
1
3
2

9
19

15、16、17、18

10、11、12 13、14

134 / 143
14087-50DB rig installation guide manual

Item Name Drawing Parts no Qty Note


1 Pipeline 91 1
2 Pipeline 92 1
3 Pipeline 93 2
4 Pipeline 94 1
5 Pipeline 95 1
6 Pipeline 96 1
7 Pipeline 97 1
8 Extension rod butterfly valve DN250 1.6MPa X=2300 5
9 Extension rod butterfly valve DN250 1.6MPa X=1130 1
10 Extension rod butterfly valve DN250 1.6MPa X=2550 1
11 Flange DN250 PN16RF GB/T 9119-2000 7
12 Bolt M24×200 GB/T 901-1988 108 Galvanization(unit:set)
13 Flange washer DN250 PN16 GB/T 9126-2008 4
14 Bolt M24×100 GB/T 5782-2000 48 Galvanization(unit:set)
15 Shell pin Φ20 KRT-11-01 26
16 Short circle chain Φ4 L=200 JB/T 8108.2-1999 26
17 Pin Φ30 KRT-01-01 26
18 Safety ring Φ4 52
19 Butterfly valve DN250 1.6MPa 2

135 / 143
14087-50DB rig installation guide manual

75.Mud gun and mud return process

4、5、6 7
1 2 3

10、11
Discharge
Pipeline

12

Mud gun 8、9

136 / 143
14087-50DB rig installation guide manual

Item Name Drawing number Parts no Qty Note


1 Mud gun 1 KR113.84.197.00 13
2 Mud gun 2 KR113.84.199.00 7
3 Discharge Pipeline1 KR113.84.200.00 12
4 Pipeline 101 5
5 Butterfly valve DN150 1.6MPa 4
6 Bolt M20×170 GB/T 901-1988 32 Galvanization(unit:set)
7 Discharge Pipeline1 KR113.84.201.00 2
8 Butterfly valve DN80 1.6MPa 21
9 Bolt M16×140 GB/T 901-1988 168 Galvanization(unit:set)
10 Butterfly valve DN200 1.6MPa 1
11 Bolt M20×180 GB/T 901-1988 12 Galvanization
12 Steel hose DN80 4MPa L=4000 M-608 1 Two ends NPT buckle

137 / 143
14087-50DB rig installation guide manual

76.Trip tank assembly

Connect diverter

1 2 3
4

18
17
8、9、10、11
16
15 12、
13
14

138 / 143
14087-50DB rig installation guide manual

Item Name Drawing no Parts no Qty Note


1 Man ladder KR113.84.04.00 2
2 Pipeline 120 1
3 Pipeline 116 1
4 Steel hose DN80 4MPa L=1800 M-609 1 Two end NPT buckle
5 Pipeline 117 1
6 Bolt M16×140 GB/T 901-1988 32 Galvanization(unit:set)
7 Sand pump fixing assembly 1 KR129.106.00 4
8 JGD flexible rubber joint DN80 1.6MPa 1 Two ends metric and english
9 Bolt M16×80 GB/T 5782-2000 16 Galvanization(unit:set)
10 Bolt M16×150 GB/T 901-1988 24 Galvanization(unit:set)
11 Butterfly valve DN80 1.6MPa 5
12 JGD flexible rubber joint DN100 1.6MPa 1 Two ends metric and english
13 Bolt M16×90 8 Galvanization(unit:set)
14 Filter KR113.84.250.00 2
15 Butterfly valve DN100 1.6MPa 2
16 Pipeline 118 1
17 Pipeline 119 1
18 Trip tank trailer 1

139 / 143
14087-50DB rig installation guide manual

77.Install mud return Pipeline

Item Name Drawing no Qty Note


1 Mud return pipeline Q001.80.00 1

140 / 143
14087-50DB rig installation guide manual

78.Diesel tank and industrial water tank set

Item Name Drawing no. Qty Note


1 Diesel tank trailer 2
2 Industrial water tank 2

79.According to SUQ001.00 layout drawing install high pressure manifold 、 catwalk 、 pipe rack etc, according
toSUQ001.30.00 cable tray assembly to install cable tray.

141 / 143
14087-50DB rig installation guide manual

80.Till now rig finish installation