Proceeding CEEDRIMS - Eka 1
Proceeding CEEDRIMS - Eka 1
net/publication/376886095
CITATIONS READS
0 73
10 authors, including:
Gi Yanto
Bandung Institute of Technology
2 PUBLICATIONS 4 CITATIONS
SEE PROFILE
All content following this page was uploaded by Eka Nugroho on 28 December 2023.
1*
Water Resources Engineering Research Group, Civil Engineering Study Program, Faculty of Civil and
Environmental Engineering, Bandung Institute of Technology (ITB)
Email: [email protected] (Corresponding author), [email protected], [email protected],
[email protected]
2
Study Program of Water Resources Engineering and Management, Bandung Institute of Technology (ITB), Labtek
1B, Let. Jen. Purn. Dr. (HC). Mashudi st. No.1, West Java
3
Badan Pengusahaan Batam (BP Batam), Ibnu Sutowo st. No. 1 Batam
Email: [email protected]
4
Magister Study Program of Water Resources Management, Civil Engineering Study Program, Faculty of Civil and
Environmental Engineering, Bandung Institute of Technology (ITB)
Email: [email protected], [email protected], [email protected]
5
Atmospheric Science Research Group, Faculty of Earth Science and Technology, Bandung Institute of Technology (ITB)
Email: [email protected]
6
Management and Construction Engineering Research Group, Civil Engineering Study Program, Faculty of Civil
and Environmental Engineering, Bandung Institute of Technology (ITB)
Email: [email protected]
ABSTRACT
Wonogiri Dam is a multifunction dam as a flood controller, irrigation, Hydro Electric Power Plant
(PLTA), and tourist destination. The dam is located in the south of Wonogiri Regency of Central Java
Province. The Wonogiri Dam was built in 1976 and began operations in 1982. As time goes by, the upstream
land cover has changed which caused an increase in the coefficient value (c). This value impacting of inflow
discharge entering the Wonogiri Dam, while the existing spillway capacity was designed based on the capacity
initial design. Spillway capacity reliability analysis is needed to determine the level of reliability and risk of
failure by the quantitative and semi-quantitative methods. The quantitative method is analyzed by Safety
Factor (level-1) and First-Order Second Moment (level-2), whether as semi-quantitative is analyzed by
multiplying the three main parameters of likelihood, Exposure and Consequence. The result shows that the
risk based on the 2011 land cover for several return period is lower than based on the RTRW. The semi-
quantitative method of two land cover conditions for the return period of 2 to 1000 shows Very Low Level and
Moderate Levels for PMF discharge. Based on its analysis, the spillway capacity is still reliable and capable of
flowing return period discharge from Q2 to Q1000.
Keywords: failure risk, first order second moment, reliability, safety factor, spillway, Wonogiri dam.
170
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
A. INTRODUCTION
The geographical location of the Wonogiri dam is at 7°50'- 8°S and 110°50'-110°58'E and is
included in the administrative area of Wuryorejo village, Wonogiri Regency, Bengawan Solo River
Region. The Wonogiri Dam is a rock-fill type dam with a soil core which is a multifunctional dam
including flood control, irrigation water supply, hydroelectric power generation, and tourist
attractions. The Wonogiri Dam was built in 1976 and began operating in 1982 (Ariansyah,
Sobriyah, & Wahyudi, 2013). The operation of the Wonogiri Multipurpose Dam refers to the
Decree of the Minister of Public Works No. 229/KPTS/1986 concerning Guidelines for
Exploitation and Maintenance of the Wonogiri Multipurpose Dam which was later revised by the
Bengawan Solo River Basin Development Master Project in July 1994 with CWL at +135.30 m
(Haryanto, Jayadi, & Istiarto, 2022). There have been several changes in land use in the upstream
area of the Bengawan Solo River (Adidarma, 2010). Those conditions potentially increase the
discharge into the Wonogiri Dam. In the recent years, many researchers have been doing the risk
analysis for the spillway (Akbari, G., 2013, Maghrebi, M., ghezelsofloo, A., & alimirzaei, H. 2018,
Pambudi et. al 2023, Renaningsih, Saraswati. 2018).
All themes of the research above are on the analysis of the effect of water flow characteristic
after or before the spillway or dam failure. The spesific analysis on the water flowing in the spillway
itself not yet been discused in the assesment of risk based on the spillway capacity. This paper aims
to analyze the risk of the spillway capacity in the Wonogiri Dam due to the changes of discharge
caused by changes in land cover. This study also use the quantitative and semi-quantitative methods
to be more realistic due to the probability of occurences.
B. METHODOLOGY
The design flood discharges are calculated from the surface runoff. Surface runoff is obtained
from hydrological analysis results. The design rainfall is calculated by the regional rain height in the
catchment area. Regional rain is then subjected to frequency and double mass curve analysis
(Fauziyah, Sobriyah, & Susilowati, 2013).
171
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
This method uses a comparison of the cumulative annual rainfall in the study area with the annual
cumulative rainfall of the corresponding station. The data suitability test is in the form of a straight line
and if there is a deviation, the deviating data is validated for the amount of deviation that occurs. The
threshold method is needed to find out the maximum and minimum values of the existing data to be said
to be feasible or not feasible (Harto, Analisis Hidrologi, 1993). The distribution methods used in this
study include Normal, Log Normal, Gumbel, Pearson type III, and Log Pearson type III. The outputs of
distribution methods were tested using the Chi-Square and Smirnov Kolmogorov methods. Effective
rainfall is obtained by analyzing the distribution of hourly rainfall for each return period. Calculation of
flood discharge is carried out using a Synthetic Unit Hydrograph (Damayanti, Limantara, & Haribowo,
2022). A hydrograph is a graph that describes the relationship between flow elements (height and
discharge) to time (Harto, Teori, Masalah, Penyelesaian, 2000). The amount of discharge that occurs from
regional rainfall is calculated using the Snyder, SCS, Nakayasu, Gama-I, ITB-1, and ITB-2 Synthetic Unit
Hydrographs.
172
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
(3)
Where R and L mean the value of resistances and loads; and is the standard deviation; is
the coefficient of difference; and (x) shows the cumulative standard of the normal distribution
evaluated by x.
Semi-quantitative risk analysis
Risk assessment is an assessment by comparing the level or risk criteria that have been set. Risk
assessment can be carried out in three ways: qualitative, quantitative and semi-quantitative. Risk
assessment using a semi-quantitative method is calculated using three main parameters (equation 4),
namely probability, exposure, and consequence, where the multiplication of these three parameters
shows the magnitude of the risk value (Fine, 1971). Risk assessment is carried out using a semi-
quantitative method calculated by declaring each parameter into a certain value. These values are
defined according to certain criteria and levels presented in Tables 1 to 4.
173
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
The risk calculation in equation 4 is often used for situations where work is to be done without
proper safety precautions. Usually such work is done without any mathematical measurement of
hazards. Using the equation (4), the risk is actually calculated and thus, more meaningfully
quàntified. The quantification is achieved by considering the potentíal consequences of an accident,
the exposure factor and the probability factor. The equation is:
R C E P ....................................................................................................................... (4)
Where: R represents the risk score
C represents the consequences
E represents the exposure factor
P represents the probability factor
174
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
175
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
Table 6. The selection of the regional rainfall distribution method using the criterion of distribution parameters
No. Distribution Type Requirement Resukt Note
CS = 0 0.50 Not Satisfy
1 Normal
Ck = 3 -0.06 Not Satisfy
Cs = 3Cv 1.132 0.498 Not Satisfy
2 Log Normal
Cv = 0.6 0.600 0.38 Not Satisfy
Cs < 1.14 0.50 Satisfy
3 Gumbel
Ck < 5.4 -0.06 Satisfy
Cs ≠ 0 0.50 0.50 Satisfy
4 Person III
Cv = 0.3 0.3 0.38 Not Satisfy
Cs < 0 -0.255 -0.255 Satisfy
5 Log Person III
Cv = 0.3 0.3 0.38 Not Satisfy
176
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
177
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
Figure 4. Graph of flood discharge for various Figure 5. Graph of flood discharge for various
return periods of the SUH Snyder return periods of the SUH Snyder
with land cover conditions in 2011 with land cover conditions in 2031
Reservoir routing
Reservoir routing is intended to obtain outflow discharge values that flow through the spillway.
The input data in the reservoir routing process is the flood discharge hydrograph from the Snyder
method for various return periods. The following presents a reservoir routing chart with a flood plan
in Figures 6 and 7.
Figure 6. Graph of spillway outflow for various Figure 7. Graph of spillway outflow for various
return periods with land cover return periods with land cover
conditions in 2011 conditions in 2031
178
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
The calculation of the safety factor (SF) in Table 10 shows that the flood discharge with a
return period of two years (Q2) to a flood discharge with a return period of 1000 years (Q1000) for
land cover in 2011 with a runoff coefficient value (c) of 0.23 has a safety factor value of above one
(SF > 1). Reliability and risk at discharge have a value of 99% with a failure risk level below 1%.
However, a different thing happened to the PMF flood discharge where the SF value was below one
(SF < 1) with a reliability of 34.3% and a risk of failure of 65.70%. This indicates that the spillway
capacity is still capable of carrying the number of outflow discharges that occur during the Q1000
flood discharge conditions. The calculation of the safety factor (SF) in Table 11 shows that the flood
discharge with a return period of two years (Q2) to a flood discharge with a return period of 500
years (Q500) for land cover according to the RTRW until 2031 with a runoff coefficient (c) value of
0.31 has a safety value. The factor is above one (SF > 1). Reliability and risk at discharge have a
value of 97% with a risk of failure below 2.5%. However, different things occur in the Q1000 and
PMF flood discharges where the SF value is below one (SF < 1). This indicates that the spillway
capacity is still capable of carrying several outflow discharges that occur in conditions up to the
Q500 flood discharge.
Table 10. Calculation of safety factor and risk of failure for year 2011 with the value of c = 0.23
Load Resistance
Return Average Load Ω Average Resistance Ω SF Pɣ Risk
Period Load Nominal Resistance Nominal
(Ln) (Rn)
2 22.19 27.49 0.35 13.78 99.71% 0.29%
5 29.90 37.03 0.35 10.23 99.69% 0.31%
10 35.00 43.35 0.35 8.74 99.67% 0.33%
20 39.90 49.41 0.35 7.66 99.65% 0.35%
25 41.46 51.34 0.35 7.38 99.65% 0.35%
50 46.24 57.26 0.35 905.1 378.74 0.35 6.61 99.63% 0.37%
100 51.00 63.15 0.35 6.00 99.61% 0.39%
200 55.73 69.01 0.35 5.49 99.60% 0.40%
500 77.20 97.21 0.38 3.90 99.50% 0.50%
1000 116.67 151.51 0.44 2.50 99.25% 0.75%
PMF 1133.45 1447.52 0.41 0.26 34.30% 65.70%
179
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
Table 11. Calculation of safety factor and risk of failure for year 2031 with the value of c = 0.31
Load Resistance
Return Average Load Ω Average Resistance Ω SF Pɣ Risk
Period Load Nominal Resistance Nominal
(Ln) (Rn)
2 30.02 37.18 905.1 10.19 99.69% 0.31%
5 41.10 50.89 0.35 7.44 99.65% 0.35%
10 48.03 59.47 0.35 6.37 99.63% 0.37%
20 54.38 67.34 0.35 5.62 99.60% 0.40%
25 56.35 69.77 0.35 5.43 99.59% 0.41%
50 79.52 100.40 0.39 905.1 378.74 0.35 3.77 99.49% 0.51%
100 126.89 165.46 0.45 2.29 99.17% 0.83%
200 172.66 227.23 0.47 1.67 98.68% 1.32%
500 238.61 315.22 0.48 1.20 97.52% 2.48%
1000 289.65 382.64 0.48 0.99 96.13% 3.87%
PMF 1350.02 1690.01 0.37 0.22 22.81% 77.19%
Graphs of the relationship between the safety factor and the level of risk of failure on the
spillway are presented in Figure 8 and Figure 9. As the return period increases, the safety factor
value decreases as well as the risk of failure increases. The graph of the relationship between the
flood load Q1000 and the resistance in Figure 10 shows the flood load Q1000 discharge which is still
able to withstand properly seen from the position of the combined graph which is on the right axis.
This is different from the QPMF flood load in Figure 11 where the load position exceeds the
resistance position, and the combined graph is on the left axis line which indicates a high level of
risk. The graph of the relationship between the Q1000 flood load and the resistance in Figure 12
shows the Q1000 flood load which is still able to withstand well, even though there is a risk of failure
of 3.87% seen from the position of the combined graph which is not completely on the right axis.
This is different from the QPMF flood load in Figure 13 where the load position exceeds the
resistance position, and the combined graph is on the left axis line which indicates a high level of
risk.
Figure 8. The graph of the relationship Figure 9. The graph of the relationship
between safety factor and risk level between safety factor and risk level
according to a land cover condition according to a land cover condition
in 2011 (c = 0.23) in 2031 (c = 0.31)
180
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
Figure 10. Graph of the relationship between load, Figure 11. Graph of the relationship between load,
resistance and a combination of both to resistance and a combination of both to
the Q1000 flood discharge for the land the QPMP flood discharge for the land
cover condition in 2011 (c = 0.23) cover condition in 2011 (c = 0.23)
Figure 12. Graph of the relationship between load, Figure 13. Graph of the relationship between load,
resistance and a combination of both to resistance and a combination of both to
the Q1000 flood discharge for the land the QPMP flood discharge for the land
cover condition in 2031 (c = 0.31) cover condition in 2031 (c = 0.31)
2 1 2 1 1 1 2 Very low
5 1 2 1 1 1 2 Very low
10 1 2 1 1 1 2 Very low
20 1 2 1 1 1 2 Very low
25 1 2 1 1 1 2 Very low
181
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
50 1 2 1 1 1 2 Very low
100 1 2 1 1 1 2 Very low
200 1 2 1 1 1 2 Very low
500 1 2 1 1 1 2 Very low
1000 1 2 1 1 1 2 Very low
PMF 4 2 4 4 4 32 Medium
Table 13. Spillway failure risk assessment uses quantitative methods for 2031 land cover
2 1 2 1 1 1 2 Very low
5 1 2 1 1 1 2 Very low
10 1 2 1 1 1 2 Very low
20 1 2 1 1 1 2 Very low
25 1 2 1 1 1 2 Very low
50 1 2 1 1 1 2 Very low
100 1 2 1 1 1 2 Very low
200 1 2 2 2 2 4 Very low
500 1 2 2 2 2 4 Very low
1000 1 2 2 2 2 4 Very low
PMF 4 2 4 4 4 32 Medium
D. CONCLUSION
Changes in land cover conditions in 2011 and RTRW until 2031 did not have a major effect on
changes in the value of the runoff coefficient (c). however, it can be seen that differences in land
cover directly provide different levels of risk. Calculation of the risk and reliability of the spillway
using the quantitative method results that the spillway is still able to work well (SF> 1) up to a flood
discharge of Q1000 with land cover conditions in 2011. Based on the RTRW until 2031 it was found
that several green areas had changed into residential areas which increased the value linear flow
with an increase in discharge in 2031. This condition resulted in the spillway only being able to work
properly until the Q500 flood discharge event. The results of the risk analysis using the semi-
quantitative method provide the same risk values for land cover conditions in 2011 with the RTRW
until 2031. The risk that occurs is at a very low level for floods up to Q1000 and is at a moderate
level for QPMF floods.
182
Proceeding & Symposium
Civil Engineering, Environmental, and Disaster Risk Management
REFERENCES
Adidarma, W.K. (2010). “Perubahan Banjir Sungai Bengawan Solo Akibat Perubahan Tata Guna
Lahan dan Perubahan Iklim serta Teknik untuk Menekan Peningkatan banjir”. Jurnal Teknik
Hidraulik, 1(2), 167-180. doi: https://doi.org/10.32679/jth.v1i2.238
Akbari, G. (2013). "Dam Instability Risk Analysis of Damaged Spillway". Eng. J., vol. 17, no. 4, pp.
1-8, doi: https://doi.org/10.4186/ej.2013.17.4.1
Altarejos-García, L., Escuder-Bueno, I., Serrano-Lombillo, A., & de Membrillera-Ortuño, M.
(2012). "Methodology for Estimating the Probability of Failure by Sliding in Concrete
Gravity Dams in the Context of Risk Analysis" Structural Safety 36-37, 1-13
Amsori, P. S., Riandini, F., & Kuntoro, A. A. (2015). "Kajian Risiko Overtopping pada Revetment
Akibat Run-up Gelombang Laut: Studi Kasus Pantai Tembok, Kabupaten Buleleng,
Provinsi Bali". Jurnal Teknik Sumber Daya Air, 1(1).
Ariansyah, G.B., Sobriyah, & Wahyudi, A.H. (2013). "Analisis Tinggi Muka Air Waduk Wonogiri
Berdasarkan Data Hujan Jam-Jaman". Matriks Teknik Sipil, 1(4), 446-453,
doi:https://doi.org/10.20961/mateksi.v1i4.37499
Damayanti, A. C., Limantara, L. M., & Haribowo, R. (2022). "Analisis Debit Banjir Rancangan
dengan Metode HSS Nakayasu, HSS ITB-1, HSS Limantara pada DAS Manikin di
Kabupaten Kupang". Jurnal Teknologi dan Rekayasa Sumber Daya Air, 300-313, DOI:
https://doi.org/10.21776/ub.jtresda.2022.002.02.25
Escuder-Bueno, I., Castillo-Rodríguez, J. T., Zechner, S., Jöbstl, C., Perales-Momparler, S., and
Petaccia, G. (2012) "A quantitative flood risk analysis methodology for urban areas with
integration of social research data", Nat. Hazards Earth Syst. Sci., 12, 2843–2863,
https://doi.org/10.5194/nhess-12-2843-2012
Escuder-Bueno , I., Altarejos-García, L., & Serrano-Lombillo, A. (2013). Quantitative risk analysis for
dams – a case study in Sweden. Sweden: Elforsk rapport 13:07.
https://energiforsk.se/en/programmes/dam-safety/reports/dam-safety-quantitative-risk-
analysis-for-dams-2013-07/
Fauziyah, S., Sobriyah, & Susilowati. (2013). "Analisis Karakteristik dan Intensitas Hujan Kota
Surakarta". Matriks Teknik Sipil, 82-89, DOI: https://doi.org/10.20961/mateksi.v1i2.37551
Ferdiansyah, A., Nugroho, E. O., & Soeharno, A. W. H. (2022). Kajian Risiko Banjir Pada Saluran
Drainase Jalan Ir. H. Juanda Bandung. Bulletin of Civil Engineering, 2(2).
https://doi.org/10.18196/bce.v2i2.15514
Fine, W. T. (1971). "Mathematical Evaluation for Controlling Hazards". Journal of Safety Research,
3(4), 157-16.
Fouhy, David, and Bayona Francisco Ríos. Reliability-Based Analysis of Concrete Dams. Thesis, KTH,
Jord- och bergmekanik, 2014. http://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-176867.
Brotowiryatmo, S.H. (1993). Analisis Hidrologi. Gramedia Pustaka Utama, Jakarta.
183
“Pengembangan Material, Teknologi, dan Infrastruktur Berkelanjutan dalam Upaya Mitigasi Bencana”
Surakarta, 27 Juni 2023
184
ISBN 978-602-397-901-1
9 786023 979011