Cluster-XXII - CE Meeting 12.02.25
Cluster-XXII - CE Meeting 12.02.25
CLUSTER XXII
Sensitivity: Unclassified
PROJECT AYACUT DETAILS
CCA (Ha)
No. of villages
SL NO Scheme As per CCA(Ha) Block District Intake Source
covered
Contract
1 Kalada 1980 1202 10
2 Patharakhamba 1000 1028 6 Parjang Rengali left Canal
3 Chandrapur 1200 1674 10
4 Gotamara 1800 1998 14
. Gondia
5 Tentulihata 1800 1998 19 Dhenkanal
Sensitivity: Unclassified
MAJOR SCOPE OF MECHANICAL WORKS
SL NO Description UOM Quantity
1 VT Pump (617 Cum/Hr – 1854 Cum/Hr) Nos 46
2 EOT Crane Nos 13
3 Outlet Management System (20 Ha Chak) Nos 962
Sensitivity: Unclassified
MAJOR SCOPE OF ELECTRICAL WORKS
SL NO Description UOM Quantity
1 Transmission line works KM 79
2 DSS Nos 13
3 MSDSS Nos 9
Power Transformer
1 MVA – 2 Nos.
4 1.6 MVA – 6 Nos. Nos 18
3.15 MVA – 8 Nos.
5 MVA – 2 Nos.
Distribution Transformer
5 33/0.433 KV Nos 22
Sensitivity: Unclassified
DESIGN & DRAWING STATUS - CIVIL
SL NO Scheme Pump House Staff Quarters MSDSS
MSDSS-2
3 Patharakhamba Approved Approved
Under Scrutiny With PEC.
MSDSS-7
4 Chittalpur Approved Approved
. Under Location Finalization
MSDSS-6
5 Gopalpur Approved Approved
Under Location Finalization
6 Gotamara Vetted on 30.01.25 Under Scrutiny With PEC
MSDSS-5
Permission required from Rengali Right Under Scrutiny With PEC.
7 Tentulihata Under Scrutiny With PEC
Canal.
MSDSS-1
8 Chhatia II Under Scrutiny With PEC Approved
Under Scrutiny With PEC
MSDSS-4
9 Babandh Under Scrutiny With PEC Approved
Under Scrutiny With PEC
10 Sana Rohila Vetted by PEC Approved MSDSS-8
11 Raniakata Under Scrutiny With PEC Approved Under Location Finalization
6 Chattia II Approved Under Scrutiny With PEC Under Scrutiny With PEC
7 Babandh Approved Approved Under Scrutiny With PEC
8 Lambodharpur Approved Under Scrutiny With PEC Under Scrutiny With PEC
9 Chittalpur Approved Approved Vetted on 30.01.25
10 Gopalpur Approved Approved Under Scrutiny With PEC
11 Sana Rohila Approved Vetted on 21.12.2024 Under Scrutiny With PEC
Transmission line
1 Conductors KM 79 - -
2 Tower Material MT - - - -
.
3 Power Transformers Nos 18 - -
4 Distribution Transformers Nos 22 - -
5 HT Panels Set 16 - -
6 LT Panels Set 13 - -
7 Soft Starter Panel Set 46 - -
9 Battery Charger Set 16 - -
9 CT, PT & VCB Set 9 - -
2 Patharkhamba - - - - - - - - - - -
3 Chandrapur - - - - - - - - - - -
4 Gotamara. 2.88 2.88 - - - 0.57 0.65 0.67 0.70 2.59
5 Tantulihata 6.11 6.11 - - - 1.21 1.37 1.43 1.48 5.50
6 Chattia II - - - - - - - - - - -
7 Babandh 5.18 5.18 - - - 1.02 1.16 1.21 1.26 4.66
8 Lambodharpur - - - - - - - - - - -
9 Chittalpur - - - - - - - - - - -
10 Gopalpur - - - - - - - - - - -
11 Sana Rohila - - - - - - - - - - -
13 Chadheiragada - - - - - - - - - - -
TOTAL (Km) 15 0 15 0 0 0 3 3 4 4 14
Sensitivity: Unclassified
PIPE LAYING STATUS
DI PIPE LAYING PLAN
SL NO SCHEMES LAID %OF
SCOPE TILL JAN’25 BALANCE COM. JAN-25 FEB-25 MAR-25 APR-25 MAY-25 JUN-25 TOTAL
1 Kalada 5.96 0.10 5.86 2% 0.00 0.68 0.78 0.96 1.05 1.10 4.66
2 Patharkhamba 8.51 0.17 8.34 2% 0.98 1.11 1.37 1.50 1.56 6.69
3 Chandrapur 16.24 0.00 16.24 0% 1.87 2.11 2.61 2.86 2.98 12.43
4 Gotamara . 10.48 0.00 10.48 0% 1.20 1.36 1.69 1.85 1.93 8.02
5 Tantulihata 6.05 0.00 6.05 0% 0.69 0.79 0.97 1.06 1.11 4.63
6 Chattia II 25.88 0.38 25.50 1% 2.97 3.37 4.16 4.56 4.76 20.20
7 Babandh 13.13 0.79 12.34 6% 0.15 1.51 1.71 2.11 2.31 2.41 10.84
8 Lambodharpur 12.59 0.23 12.36 2% 0.03 1.45 1.64 2.02 2.22 2.31 9.87
9 Chittalpur 10.98 0.00 10.98 0% 1.26 1.43 1.77 1.93 2.02 8.41
10 Gopalpur 12.10 0.00 12.10 0% 1.39 1.58 1.95 2.13 2.22 9.27
11 Sana Rohila 14.44 5.17 9.27 36% 3.95 1.66 1.88 2.32 2.54 2.65 16.23
12 Raniakata 17.47 0.00 17.47 0% 2.01 2.27 2.81 3.08 3.21 13.38
13 Chadheiragada 5.50 0.00 5.50 0% 0.63 0.72 0.88 0.97 1.01 4.21
Sensitivity: Unclassified
PIPE LAYING STATUS
HDPE PIPE LAYING PLAN
1 Kalada 132.23 80.44 51.79 61% 44.70 11.16 12.56 13.95 15.35 16.74 150.2
2 Patharkhamba 122.53 43.99 78.54 36% 35.30 10.34 11.64 12.93 14.22 15.52 108.64
3 Chandrapur 201.34 100.40 100.94 50% 66.74 17.00 19.12 21.25 23.37 25.50 206.64
4 Gotamara . 227.00 4.16 222.84 2% 0.00 19.16 21.56 23.95 26.35 28.74 123.92
5 Tantulihata 226.49 60.37 166.12 27% 40.57 19.12 21.51 23.90 26.29 28.68 179.87
6 Chattia II 219.53 84.22 135.31 38% 45.18 18.53 20.85 23.16 25.48 27.80 200.04
7 Babandh 224.09 126.73 97.36 57% 72.34 18.92 21.28 23.65 26.01 28.38 244.97
8 Lambodharpur 237.55 34.31 203.24 14% 16.79 20.05 22.56 25.07 27.57 30.08 159.64
9 Chittalpur 123.08 26.34 96.74 21% 10.34 10.39 11.69 12.99 14.29 15.59 91.29
10 Gopalpur 100.17 36.70 63.47 37% 13.03 8.46 9.51 10.57 11.63 12.68 89.55
11 Sana Rohila 168.66 97.40 71.26 58% 42.34 14.24 16.02 17.80 19.58 21.36 186.4
12 Raniakata 185.99 34.66 151.33 19% 24.70 15.70 17.66 19.63 21.59 23.55 132.79
13 Chadheiragada 67.35 31.59 35.76 47% 4.37 5.69 6.40 7.11 7.82 8.53 67.14
TOTAL (Km) 2236 761 1475 - 416 189 212 236 260 283 1941
Sensitivity: Unclassified
PUMP HOUSE WORK STATUS
SL No. Scheme Start Date Completion Date Remarks
1 Patharkhamba 21.10.24 Nov’25 Raft Concrete including footings completed, Sump wall
1st lift shuttering Under progress
2 Kalada 21.10.24 Nov’25 Excavation in progress
3 Chittalpur 17.10.24 Dec’25 Well sinking and piling work in progress
4 Chandrapur 23.11.24 Nov’25 Excavation in progress
5
. Gopalpur Feb’25 Jan’26 Permission from DFO to be received for starting the
work
7 Tentulihata Feb’25 Apr’26 PH Land Clearance required from Rengali Right Canal
Division
8 Chattia II Jan’25 Mar’26 Excavation in progress
9 Babandh Feb’25 Jan’26 Private land acquisition under Progress
10 Sana Rohila 17.12.24 Nov’25 Excavation in progress
11 Raniakata Jan’25 Dec’25 Excavation in progress
12 Lambodarpur Feb’25 Apr’26 Private land acquisition under Progress
13 Chadheiragada Feb’25 Nov’25 NOC required from OMC
Sensitivity: Unclassified
SITE VISIT PHOTOGRAPHS
Chattia II Scheme – Puja performed in the presence Raniakata Scheme – Puja performed in the
of CE, Addl. CE, EE – Mega Lift with PMC presence of EE Mega Lift.
Sensitivity: Unclassified
KALADA SCHEME
Sensitivity: Unclassified
CHANDRAPUR SCHEME
Sensitivity: Unclassified
SANAROHILA SCHEME
Sensitivity: Unclassified
RANIAKATA SCHEME
Sensitivity: Unclassified
CHITTALPUR SCHEME WELL-SINKING WORKS
Sensitivity: Unclassified
CHHATIA II
Sensitivity: Unclassified
SITE PROGRESS PHOTOGRAPHS – HDPE PIPE LAYING
Sensitivity: Unclassified
SITE PROGRESS PHOTOGRAPHS –DI PIPE LAYING
Sensitivity: Unclassified
SITE PROGRESS PHOTOGRAPHS –MS PIPE STACKING
Sensitivity: Unclassified
CONSTRUCTION SCHEDULE
Description Dec'23 Mar'24 Jun'24 Jul'24 Sep'24 Dec'24 Mar'25 Jun'25 Sep'25 Dec'25 Mar'26 Apr'26 Jun'26 Sep'26 Oct'26
Survey
Laying of MS pipeline
Laying of DI pipeline
Sensitivity: Unclassified
HINDRANCE
Sl. No. Scheme Description
1 Chittalpur Locals are objecting & stopping the pipe laying works
frequently at site.
3 Babandh Part of pump house land falls under private land and land
acquisition in progress.
4 Lambodarpu Part of pump house land falls under private land and land
r acquisition in progress.
Sensitivity: Unclassified
HINDRANCE
Sl.
No. Scheme Description
Local villagers objecting to start the pipeline & pump house works.
6 Gotamara Discussion with local authorities are in progress to resolve the issue.
Sensitivity: Unclassified
THANK YOU