PROJECT CLOSURE REPORT
Section 1. General Information
Job No.: Client / Employer :
Project Title : Consultant / Engineer :
Baseline Actual
Start Date
Completion Baseline Actual
Main Contractor:
Date
Client SAMA Project Team Details
Contact Person (s): Project Manager:
Position: Engineering:
Tel. / Mob. : Planner:
Email: Quantity Surveyor:
QC:
EHS (Safety):
Section 2. Status of Close Out Documents
Description / Document Type Status Comments
2.1 Submission of Operation & Maintenance Manual Yes No N/A
2.2 Submission of As Built Drawings/ Red Markups Yes No N/A
2.3 Submission of all Site Test Reports Yes No N/A
2.4 Submission of FAT Reports Yes No N/A
2.5 Completion of Punch List (updated list to be attached) Yes No N/A
2.6 Governmental or Authorities Permits & Clearances Yes No N/A
2.7 Provision of Software Yes No N/A
2.8 Provision of Extended Warranty Certificates Yes No N/A
2.9 Handing Over of Free Issue Materials to Client Yes No N/A
2.10 Quality Assurance & Inspection Reports Yes No N/A
(only the list including NCR's)
2.11 HSE Reports (Final Statistics including Incident Reports) Yes No N/A
2.12 Handing over of Spares as per specifications, if any Yes No N/A
* All Submission Records to be attached
Page 1 of 3
Section 3. Contractual / Commercial Matters
Section 3a. Commercial Status
S. No. Final Contract Sum Amount Certified Amount Received Outstanding
A. Contractual Issues
1
2
3
B. Variations / Measured Works
1
2
3
C. Claims
1
2
3
Total
Section 3b. Certificates
S.No Description Issued / Not Issued Expected Date Remarks
1 Completion Certificate
2 Defect Liability Certificate (Final)
3 Final Settlement Agreement
4 Claims & Liens Certificate
4 Any Other Certificates
Section 3c. Status of Bond / Insurances
Types of Bond / Insurances Issued Bond No. Bank Expiry Returned
1 Advance Payment Bond Yes No Yes No
2 Performance Bond Yes No
3 Warranty Bond Yes No
4 Insurance Certificates
4a. CAR Yes No
4b. Workmen's Compensation Yes No
4c. Third Party Insurance Yes No
4d. Professional Indemnity Yes No
Section 4. Subcontractors / Vendors
Sl. No. Subcontractor / Vendor PO Reference Items/ Scope Description Issues, If any
1
2
3
Remarks:
Section 5. Others
Sl. No. Description Status If No, When
1 Site Demobilization Yes No
Page 2 of 3
Sl. No. Description Status To Whom
1 Project Documents handed over Yes No
Section 6. Major Open Issues
Issues Planned Resolution Responsible Person / Department
3.1
3.2
3.3
3.4
3.5
Section 7. Lessons Learned (pls. narrate clearly)
Signature: Date:
Print Name:
Title:
Role:
Page 3 of 3