Irbm 24
Irbm 24
BRIDGE MANUAL
2024
I
II
III
IV
PREFACE TO INDIAN RAILWAYS BRIDGE MANUAL-2024
V
VI
CONTENTS
VII
209 Details of common repair techniques 15
PART D - MAINTENANCE OF SUPER STRUCTURE-REINFORCED CEMENT 19
CONCRETE & PRESTRESSED CONCRETE BRIDGES
210 Periodical maintenance 19
211 Common defects and repair/strengthening techniques 19
PART E - MAINTENANCE OF SUPER STRUCTURE STEEL GIRDERS 20
212 Loss of camber in steel girders 20
212A A Residual Fatigue Life Assessment of old steel girders 20
213 Cracks in steel works 21
214 Strengthening of weak girders 21
215 Replacement of loose rivets 21
215A Maintenance of HSFG Bolts 23
216 Corrosion and its prevention 23
217 Protective Coatings by painting. 23
218 Metallising & Epoxy based Paints 27
219 Maintenance of welded girders 29
PART F - MAINTENANCE OF COMPOSITE GIRDERS 30
220 Action taken for maintenance of composite girders 30
PART G - MAINTENANCE OF BED BLOCKS 31
221 Various defects and their remedies 31
PART H - MAINTENANCE OF BEARING 31
222 Bearings 31
PART I - GENERAL PRECAUTIONS 33
223 Precautions while carrying out maintenance works on bridges 33
224 Dismantling of Arch Bridges 33
225 Tractive Efforts Limitation 35
PART J - INSPECTION, MAINTANANCE AND CONSTRUCTION OF RUB/SUBWAY 36
VIII
312 Vertical Clearance 42
313 Free Board (F) 42
314 Standard of substructure for new railway lines 43
315 Final Project Report in the case of important Bridges 43
316 Choice of Foundations for Bridges 43
317 Approval of bridge drawings for doublings, gauge conversions, new lines and 44
other bridge works
318 Approval of bridge drawings for Dedicated Freight Corridor lines 44
IX
431 Setting out of the Piers on the top of well 60
432 Construction of well Cap (Entablature) 60
X
614 Trial Shop Erection 76
615 Preparation of surface 76
616 Field erection 77
617 Welded Girders 77
618 Painting of new Girders 78
619 Choice of a suitable method of girder erection 78
620 Preliminary Arrangements before girder erection 78
621 Erection by use of cranes 79
622 Erection with Derricks 80
623 End launching methods 80
624 Side slewing method 82
625 Launching of triangulated girders on the trestles 82
626 Launching of girders by using service span 83
627 End launching of open web girders with the help of launching nose 83
628 Erection by cantilevering method 83
629 Enveloping Method 84
PART D - CONSTRUCTION OF HEIGHT GAUGES 84
630 Height Gauges 84
XI
717 Provision of Anemometer on Bridges 94
XII
1010 General 116
1011 Schedule of Inspection of Cuttings 116
1012 Vulnerable Cuttings – Identification and Special Precautions 117
1013 Points to be noted during Inspection of cuttings 117
1014 Inspection of Boulder nets provided in cuttings 118
1015 Inspection of Rock bolts provided in Cuttings/Tunnels. 118
1016 Action to be taken in case of Boulder fall 118
1017 Action to be taken for maintenance of cuttings 119
XIII
1218 Laying of Boilers 144
1219 Transfer of Boilers 144
XIV
LIST OF ANNEXURES
Annexure Particulars of Sketch/Proforma Para reference
2/1 Provision of Bridge Number on Parapet Wall 203
2/2 Curtain Wall, Drop Wall and Flooring 204
2/3 Toe Wall and Pitching 205
2/4 Cracks in Arches-types 208
2/5 Cracks in Arches-types 208
2/6 Pressure Grouting Machine 209
2/7 Cement Pressure Grouting 209
2/8 Epoxy Grouting 209
2/9 Guniting Machine 209
2/10 Sliding Centralized Bearings 222
2/11 Roller & Rocker Bearings 222
2/12 Elastomeric and PTFE Bearings 222
2/13 Caution Indicator for TE Limitation 225
2/14 TE Limit Operation Indicator 225
2/15 Termination Indicator for TE Limitation 225
2/16 Position for TE Limit Operation Indicator 225
2/17 Assessment of Residual Fatigue Life of Old Steel Girder 212
4/1 Method of Setting out a Multiple Span Bridge without a Base Line 401
4/2 Method of Setting out a Multiple Span Bridge with the Help of a Base 401
Line
4/3 Arrangements for Founding Pipe Culvert 402
4/4 Typical Section of Abutment & Pier with Open and Raft Foundation 403
4/5 Excavation with Shoring 403
4/6 Single Wall Sheet Pile Coffer Dam 404
4/7 Double Sheet Pile Coffer Dam 404
4/8 Temporary Wooden Pile Bridge 405
4/9 Rig used for Driving Precast Piles 411
4/10 Construction of Bored Cast in-situ Pile Using Bentonite Slurry 415
4/11 Cross Section of a Well Foundation 418
4/12 Typical RCC Well Curb 418
4/13 Island forConstruction of Well in Water 421
4/14 Assembly of Caisson at Site of Pier 422
4/15 Arrangement for Grounding of Caissons 422
4/16 Type of Rail Chisels Used in Well Sinking 423
4/17 Sand Blow in a Well 423
4/18 Methods of Tilt Correction 424
4/19 Typical Air Lock Arrangement 426
4/20 Founding of Wells on Rock 427
XV
5/1 Deleted
5/2 Replacement of cast iron screw piłes by bored piles 512
5/3 Strengthening of piers and abutments 513
5/4 Encasement and replacement of bed block 514
5/5 Rehabilitation of arch bridges by various methods 515
5/6 Rehabilitation with slabs 516
5/7 Box pushing technique 517
5/8 Rehabilitation of parapets 518
6/1 Types of piers 604
6/2 Types of abutments, wing walls and returns 604
6/3 Back fill material and Weep holes behind abutments 605
6/4 Sequence of work in an arch 608
6/5 Erection by use of launching girders and cantilever method 610
6/6 Cantilever launching and incremental launching of precast elements 610
6/7 Erection with derrick 622
6/8 Launching with rail clusters 623
6/9 Launching by Dip lorry and "Linking and rolling" (by skidding) 623
6/10 Use of BFR and launching pad in launching 623
6/11 Use of trestles and service span in launching 625 & 626
6/12 Use of launching nose and Derrick crane for launching of girders 627 & 628
7/1 Proforma for recording gauge, afflux and velocity 711
7/2 Cross section of river bed after floods 711 & 712
7/3 Survey plan of river 712
7/4 Cross section of guide bunds 712
7/5 Proforma of flood reports 715
7/6 Rain fall statement 716
8/1 Braiding pattern in rivers 803
8/2 Meander pattern in alluvial rivers 805 & 814
8/3 Different forms of guide bund 810
8/4 Layout of a guide bank 810
8/5 Types of spurs 811
8/6 Typical layout of porcupine 811
9/1 Proforma of structural steel inspection register 901
10/1 Proforma of Tunnel inspection register 1003
10/2 Proforma of cutting register 1010
11/1 Proforma of inspection register for steel work in bridges 1102
11/2 Proforma of inspection for steel work in bridges of 12.2m & above 1102
11/2a Proforma for inspection of PSC Bridge/Composite Girder Bridge 1102
11/3 Instructions to be printed in bridge inspection register 1103
XVI
11/4 Index of bridges 1103
11/5 General key plan for Bridge Inspection Register Details 1103
11/6 Details of classification of structures 1103
11/7 Details about inscription plaques 1103
11/8 Proforma of bridge register for Major and Important bridges 1103
11/9 Proforma of bridge register for inspection of Major & Important bridges 1103
11/0 Proforma of bridge register for details of Minor bridges 1103
11/11 Proforma for inspection of Minor bridges 1103
11/12 Procedure for rivet testing 1107
11/13 Sample rivet test register 1102
11/14 PSC girders camber measuring method 1107
11/15 Details of tools and equipment for inspection of bridges 1109
12/1 Proforma of form of agreement for hire of plant 1215
14/1 List of books of reference 1401
XVII
XVIII
DUTIES OF BRIDGE OFFICIALS
CHAPTER I
DUTIES OF BRIDGE OFFICIALS
PART A
DUTIES OF ASSISTANT ENGINEER
101 General
(1) The Assistant Engineer is generally responsible for the maintenance and safety of all way & works
including bridges in his charge; for the accuracy, quality and progress of new works and control
over all expenditure in relation to budget allotment.
(2) The duties of the Assistant Engineer are detailed in various chapters of Indian Railways Permanent
Way Manual, Works Manual and Bridge Manual. His essential duties in respect of bridges and
other steel structures are detailed here under.
102 Inspection of Bridges
a) The Assistant Engineer shall inspect every Bridge including Road over / under Bridges once
a year by a date specified by Chief Engineer after monsoon. This inspection shall cover,
i) Foundation and flooring, substructure, protective works, bed blocks, track over bridg-
es and the approaches including guard rails and other appurtenances of all Bridges,
pipes, RCC Boxes, superstructure of arches, RCC & PSC slab bridges etc.
ii) General condition of steel work of girders and bearings with special attention to places
liable to corrosion.
iii) General condition of all RCC, Composite and PSC girders and their bearings.
b) deleted
c) Wherever necessary, he shall jointly inspect canal and irrigation crossings with his counter
part of State P.W.D. or Irrigation Department.
d) The inspection of bridges shall be carried out as per Chapter XI.
e) He should send extracts of the orders regarding action to be taken by the Inspectors arising
out of his inspection for compliance with a copy to Divisional Engineer.
f) He should submit the Bridge registers with his certificate of completion of Bridge inspections
to his Divisional Engineer.
g) He shall arrange to maintain the flood records upto date as detailed in Para 710. He will also
maintain the Rivers and Flood register as detailed in Para 714.
103 He shall inspect every tunnel in the sub division once a year before monsoon and maintain the
records of his inspection.
104 Maintenance of Bridges and Structures
(1) He shall be responsible for the maintenance and repairs to foundations, flooring, sub structures,
protective works, bed blocks, track over bridges and the approaches including guard rails and other
appurtenances, pipes, RCC Boxes, superstructure of all arches, RCC and PSC slabs, steel work
of girder spans less than 12.2 m clear and other type of bridges except composite, RCC, PSC and
steel girders of spans 12.2 m and more.
(2) All other steel structures like FOB, Sheds / Shelters etc.
1
DUTIES OF BRIDGE OFFICIALS
(3) He should arrange for the expeditious repairs, as and when required.
PART B
DUTIES OF ASSISTANT (BRIDGE) ENGINEER/ DIVISIONAL (BRIDGE) ENGINEER
IN CHARGE OF BRIDGES IN DIVISION
PART C
DUTIES OF BRIDGE INSPECTOR
2
DUTIES OF BRIDGE OFFICIALS
d) Superstructure including bearings of all Steel girders of span 12.2 m and above, RCC, PSC
and composite girder bridges once in five years on planned basis.
e) Other nominated steel structures, being maintained by him, once in five years.
f) Proper installation of Bearings before allowing traffic on any Bridge
(2) Records of inspection:
He will record the details of each one of the inspections in the register maintained for the purpose
as detailed in chapter XI.
(3) Maintenance of bridges and other structures:
He shall maintain the following structures in good condition by taking immediate action to carry out
necessary repairs, painting, oiling and greasing, etc.
a) Superstructure and bearing of all Steel bridges of span 12.2m and above, PSC, RCC and
composite girders.
b) Other steel structures as specified by Chief Engineer.
(4) He will be responsible for the erection of steel girders for all major bridges, PSC girders.
(5) He will be responsible for the erection of workshop structures and Flood light towers, if ordered by
the Chief Engineer.
(6) He will be responsible for the accountal and periodical verification of stores, tools and plants in his
charge.
108 Knowledge of Rules and Regulations
(1) Every Bridge Inspector shall have in his possession copies of the following codes and manuals
with all upto date correction slips:
i) Indian Railways Permanent Way Manual, Bridge Manual and Works Manual,
ii) Indian Railway General and Subsidiary Rules,
iii) Indian Railway Code for the Engineering Department,
iv) Schedule of dimensions,
v) Circulars issued by the higher authorities.
(2) He shall be well acquainted with the rules, regulations and procedures concerning his work and
duties as enjoined in the above codes and manuals. He shall keep himself in touch with the orders
and circulars issued by higher authorities from, time to time and efficiently act upon them.
(3) He shall ensure that all staff working under him are well acquainted with the relevant rules and
working methods and efficiently perform their duties. They should be examined periodically as
specified, on appointment, and on promotion.
109 Co-ordination with Permanent way, works and staff of other Departments
The Bridge Inspector should keep close co-ordination with the staff of way, works, signalling,
electrical, traction and other departments, when they are required to work jointly.
110 Accompanying on Inspections of Higher officials
When the Bridge Inspector accompanies a periodical/ special inspection by the higher officials, he
should have with him the following registers and documents pertaining to his section, other than
the codes and manuals mentioned in Para 108.
a) Relevant Working Time Tables
3
DUTIES OF BRIDGE OFFICIALS
4
DUTIES OF BRIDGE OFFICIALS
b) The leave availed by each man should be recorded in the leave register to his account
before the musters are despatched to the Assistant/Divisional Engineer's (Bridge) office.
(2) Witnessing payments to staff
a) Payment to both permanent and temporary staff on the section will be made by the pay clerk
in the presence of the Bridge Inspector who will witness and will be responsible for correct
identification of the payee and should satisfy himself that the correct amount is paid.
b) The certificate at the foot of the paysheet should be filled in by him as payment of each batch
of workmen is completed, specifying both in words and figures the amount paid on each
date. If a person is not present, "Not Paid" should be immediately written against his name,
when subsequently payment is made, the kilometrage (mileage) or place at which he is paid
should be entered and separately certified as such on the pay sheet.
c) If the Bridge Inspector working in the section is not readily available, another Inspector may
be authorised by AEN (Bridges) to witness payment on the section.
(3) Other establishment matters
a) General conditions of railway service and rules relating to the conduct and discipline of
railway servants are contained in the relevant chapter of the Indian Railway Establishment
Code.
b) Medical examination - The bridge inspector should ensure that all staff including casual
labour are sent for medical examination on appointment, promotion and for periodical
medical examination as laid down in the relevant rules.
c) Service Cards: He will arrange to maintain the service cards/ leave account of all the
permanent staff working under him. Service card should be prepared as soon as appointments
to permanent vacancies are made. In the case of casual labour he will arrange to issue
the necessary service card to them and will maintain the L.T.I. register. All increment and
promotions should be noted in the service cards and duly attested by the Assistant Engineer/
Divisional Engineers (Bridges).
d) Provision in the various acts:
He will ensure that the relevant provisions of payment of wages Act, Workmen's Compensation
Act, Contract labour regulation and abolition act, Industrial Disputes Act and rules made
thereunder, Hours of Employment Regulations, etc. as amended from time to time are
complied with.
e) Promotion to higher grades:
i) The Bridge Inspector should maintain, in manuscript form, records of staff working
under him in which he shall enter merits and demerits of each as and when such
entries are justified.
ii) The normal procedure for promotion should be by "Trade Tests." Qualified men will be
entitled to promotion by seniority within their own groups.
iii) He will initiate prompt action for filling up the vacancies by referring to the Assistant
engineer/Divisional Engineer (Bridges).
f) He will arrange to carry out the other establishment work such as issue of passes, preparation
of pay bills etc. as may be allotted to him by the administration.
g) He will ensure proper training of the artisan and other skilled men working under him at the
appropriate time.
5
DUTIES OF BRIDGE OFFICIALS
PART D
DUTIES OF PERMANENT WAY AND WORKS INSPECTORS
116 General
While Chapter I of Indian Railways Permanent Way Manual and Chapter I of Indian Railways Works
Manual deal with the duties and responsibilities of PWI and IOW with respect to permanent Way
and Works respectively, the following paras deal with their duties and responsibilities with regard
to bridges & tunnels.
117 Inspection
(1) Once a year during prescribed months prior to monsoon, Permanent Way Inspector or Inspector
of Works, as per the practice on the railways, shall inspect every bridge including ROB/RUB in his
section covering the following:
a) Foundations, Substructures and bed blocks of all bridges.
b) Protective works.
c) Superstructures of all RCC and PSC slab bridges and masonry bridges.
6
DUTIES OF BRIDGE OFFICIALS
d) Detailed inspection of steel work of girders less than 12.2m clear span once in 5 years.
e) General condition of superstructure of all other type of bridges and their bearings.
f) Obstruction to water ways, if any.
g) Tunnels in his section to be inspected after monsoon.
He will record the details of his inspection in manuscript register in the prescribed proforma
and submit a certificate of inspection to the Assistant Engineer by the prescribed date.
(2) Inspection by Permanent Way Inspector specifically:
Once a year during prescribed months prior to monsoon, Permanent Way Inspector shall inspect:
a) The track and approaches of all bridges.
b) Run off frames and foot-paths over bridges, if any.
118 Maintenance
(1) Permanent Way Inspector or Inspector of Works, as the case may be, shall be responsible for
the up-keep and maintenance of all the items of bridges mentioned in Para 117. He shall also be
responsible for the maintenance of bridge appurtenances like notice boards, name boards, trolley
refuges, sand bins and marking of HFLs etc.
(2) The Permanent Way Inspector shall also be responsible for the posting of bridge watchman,
wherever necessary and ensure their effective functioning.
7
MAINTENANCE OF BRIDGES
CHAPTER II
MAINTENANCE OF BRIDGES
PART A
GENERAL
8
MAINTENANCE OF BRIDGES
9
MAINTENANCE OF BRIDGES
PART B
MAINTENANCE OF FOUNDATIONS, PROTECTIVE WORKS AND WATERWAYS
10
MAINTENANCE OF BRIDGES
and at closure bunds. Disturbed pitching should be reset properly by making up the slopes
if necessary.
Slope pitching are rested on toe wall with proper foundation. Damaged toe wall can lead to
slipping of pitching, and therefore, it should be rebuilt with a proper foundation (Annexure
2/3).
PART C
MAINTENANCE OF SUBSTRUCTURE
11
MAINTENANCE OF BRIDGES
bridges.
ii) Adequacy of existing weep holes be checked and if required, additional weep holes of
proper size be provided.
iii) Choked weep holes be cleaned and made functional.
iv) The back fill material should be granular and should not contain expansive soil like
black cotton soil etc. Proper filter layer be provided behind the masonry. The back fill
material should be changed if so warranted.
b) The excessive earth pressure can be taken care of by either providing masonry or cement
concrete buttress. However, care should be taken that the reduction in water way, if any,
does not adversely affect the parameters like afflux, clearances etc.
c) For tackling undermining/scour and other rehabilitation problems Para 204 and 513 may be
referred to.
(4) Cracks in masonry / concrete:
Cracks may occur due to loss of strength of masonry/concrete because of age, excessive dynamic
impact and settlement or any other damage to foundations.
a) Vertical cracks:
Vertical cracks may occur due to differential settlement of the foundation or excessive
shearing stresses in the substructure. The cracks should be monitored by providing tell
tales. If these show signs of propagation, a detailed study should be made to identify the
causes before taking remedial measures.
b) Horizontal cracks:
These are more serious and these could be due to inadequacy of section, defect in
construction, failure of back fill drainage or excessive horizontal loads etc. The remedial
measures should be decided after identifying the cause, based on results of analytical study
and field observations. Generally grouting with cement or epoxy mortar and jacketing are
used as remedial measures.
12
MAINTENANCE OF BRIDGES
cracks indicate serious weakness in the arch and need proper investigation and adoption of
appropriate strengthening measures including rebuilding in worst cases.
iii) Crushing of masonry:
The probable causes of crushing of masonry of the arch and remedial measures are as
follows:
Probable Cause Remedial Action
a). Leaching of mortar in the joints. Raking out the mortar and deep Pointing/grouting
b) Weathering of masonry Pointing together with grouting
c) Excessive loading Reducing the imposed load or strengthening the arch
d) Inadequate cushion over arch. Providing the minimum cushion or strengthen the arch.
13
MAINTENANCE OF BRIDGES
ii) If the above cracks open i) Rib shortening. i) Same as "d' above.
under traffic. ii) Distortion of arch ring. ii) Strengthening of arch.
iii) Excessive back pressure.
e) Cracks in spandrel wall Sinking of pier Remedial measures for arresting
above pier (Annexure 2/5) sinking of foundation and grouting
cracks thereafter.
14
MAINTENANCE OF BRIDGES
15
MAINTENANCE OF BRIDGES
16
MAINTENANCE OF BRIDGES
17
MAINTENANCE OF BRIDGES
II) Air Compressor with a capacity of 10 cum per minute and which can develop a pressure
of upto 7 kg/cm².
iii) Placing nozzle with hose.
d) Specification of materials used:
i) Ordinary Portland cement to IS: 269. (Other special cements can be used for special
applications requiring higher strength or early setting)
ii) Sand conforming to IS: 383 and graded evenly from fine to coarse as per Zone II and
III with a nominal max. size of 6mm.
iii) Coarse aggregate, when used, should conform to IS: 383, with a maximum nominal
size of 10 to 12.5 mm.
iv) Water conforming to IS: 456.
v) Admixture as recommended.
vi) Reinforcing bars, as per IS: 432 or welded wire fabric conforming to IS: 1566 may be
used as required.
vii) Water cement ratio 0.35 to 0.50 by weight.
e) Preparation of surface: All weathered or deteriorated material should be removed until the
surface exposed is sound and properly shaped to receive the gunite (Shotcrete). The surface
should be cleaned of all loose and foreign materials with an air/water jet. If the joint mortar is
weak, the joint should be raked to about 10mm depth and all loose, dry mortar scraped out.
Exposed reinforcement should be cleaned free of rust, scale etc. and given a coat of neat
cement or any other anti-corrosive material, Porous surface should be kept damp for several
hours before guniting.
f) Form work: The forms where required shall be plywood or other suitable material set true
to line and dimension. They should be adequately braced and constructed so as to permit
the escape of air and rebound during the guniting operation (particularly in the case of thick
members).
g) Reinforcement: Depending on the thickness and nature of the work; reinforcement may
consist of either round bars, or welded wire fabric 3mm diameter. Sufficient clearance should
be provided around the reinforcement. The minimum clearance between the reinforcement
and form or other back up material may vary between 12mm for the mortar mix and wire
fabric reinforcement to 50mm for the concrete mix and 16mm dia reinforcing bars. However,
the minimum cover for reinforcement shall be as per IS: 456. The minimum wire mesh
spacing should be 50 mm by 50 mm. Clear spacing between bars should be atleast 65 mm.
For repair work, the reinforcement should be fixed to existing masonry by wiring to nails
driven into the masonry and rigidly secured.
h) Preparing the gunite: The cement and sand in specified proportion are premixed and placed
in the feeding chamber, the same is then fed into the working chamber through a cone valve
controlled from outside. The mixture, after passing through an agitator is then carried in
suspension by compressed air through the delivery hose to the nozzle. The mixing time shall
not be less than one minute. As the material passes through the nozzle body, it is hydrated
with water introduced in the form of a fine needle spray. The amount of water added is
adjusted so that the in-place gunite/shotcrete is adequately compacted and it neither sags
nor shows excessive rebound. The mix used generally ranges from 1:3 to 1:4.5 and moisture
content of the mixture before placing in the machine should be within 3 to 6%
18
MAINTENANCE OF BRIDGES
i) Uniform air pressure is maintained at the nozzle outlet. For lengths of hose upto 30m, the air
pressure is 3kg/cm2 or more. For longer lengths the pressure is increased by 0.35kg/cm2 for
each additional 15m of hose and by 0.35kg/cm2 for each staging of 7.5m that the nozzle is
raised above the gun.
j) Placing: The total thickness of gunite required should be built up in a number of layers with
an interval of about 4 hours. Each layer is built up by making several passes or loops of the
nozzle over the working area. The distance of the nozzle from the work, usually between
0.5 and 1.5m, should be such as to give the best results. Particular care should be taken
when gunning through and encasing reinforcing bars. (For walls, columns and beams, the
application should begin at the bottom). In guniting slabs, the nozzle should be held at a
slight angle so that the rebound is blown on to the completed portion.
k) Rebound: The rebound is mortar or concrete which bounces off the surface during the
application. Rebound should not be worked back into the construction and should be
rejected.
l) Before laying additional layer, the first layer should be allowed to take its initial set. Then
all laitance, loose material and rebound should be removed. The surface should be tested
with a hammer for drummy areas which should be carefully cut out and replaced with the
succeeding layer.
m) Curing: The surfaces should be kept continuously wet for at least 7 days.
n) Shotcreting by the wet process requires special equipment and can be used for building up
thick layer. For further details reference can be made to IS: 9012 "Recommended Practice
for shotcreting".
PART D
MAINTENANCE OF SUPER STRUCTURE - REINFORCED CEMENT
CONCRETE AND PRESTRESSED CONCRETE BRIDGES
19
MAINTENANCE OF BRIDGES
b) Dormant cracks
c) Active cracks whose cause of cracking has been determined and remedial action has been
taken.
(2) Other Strengthening techniques:
a) External prestressing of concrete girders both in longitudinal and vertical directions can be
successfully adopted as a strengthening measure. Vertical prestressing may be adopted
to prevent separation of deck slabs which are generally cast in situ over precast girders.
Longitudinal prestressing may be adopted to strengthen the girder and to increase its flexural
strength. Longitudinal prestressing may be resorted to in cases where girders are required
to carry increased load or the existing prestressed cables have deteriorated.
b) Established techniques such as external bonding of steel plates etc. can also be adopted for
which specialist literature may be referred.
PART E
MAINTENANCE OF SUPER STRUCTURE-STEEL GIRDERS
20
MAINTENANCE OF BRIDGES
inadequate. On such bridges, Instrumentation may be carried out for continuous monitoring of the
critical members to detect imminent fatigue cracks, initiating from the rivet holes & hidden under
the rivet heads.
(3) Ultra Sonic Flaw Detection (USFD), Acoustic Emission Technique (AET) and Oscillation
measurements etc. may be used for determining the proper scheme of instrumentation in consultation
with RDSO.
21
MAINTENANCE OF BRIDGES
resorted to.
(2) The following points should be kept in mind while carrying out the rivetting work.
a) In pneumatic rivetting, the driving of the rivet, filling of the hole and formations of the head
should be done by snap mounted pneumatic hammer by delivering quick hard blows on
practically white hot rivet. The rivet head should be held tightly against the member through
a pneumatically hand pressed dolly.
b) The rivet shank should be about 1.5mm less than the diameter of the drilled hole.
c) The length of the rivet shank may be worked out by the formula
L = G + 1.5D + 1mm for every 4mm of grip or part thereof for snap head rivet.
L = G + 0.5D + 1mm for every 4mm of grip or part thereof for counter sunk rivet.
where
L = length of rivet shank
G = length of grip in mm
D = diameter of rivet in mm
d) While rivetting a loose joint, not more than 10% rivets should be cut at a time. Besides, each
rivet should be replaced immediately after cutting, with a turned bolt of adequate diameter
and length and then only the next rivet should be cut. In 50% of the holes cut parallel drifts
of correct diameter may be used; using turned bolts for the other 50%.
e) It is preferable to drill a rivet out than to use a rivet burster as the latter cuts the rivet head in
shear, imparting very heavy shock to the adjoining group of rivets.
f) In a joint where only a few rivets are loose, the adjoining rivets are also rendered loose while
bursting the loose rivets. In any case, after the loose rivets in a joint are replaced, it is very
necessary that all the rivets in the assembly are rechecked for tightness.
g) At locations where replacing rivets is difficult, turned bolts of appropriate diameter and length
may be used.
h) The rivet must be heated almost to a white heat and to a point when sparks are just beginning
to fly off. The whole rivet must be brought to the same heat. The rivet should be driven and
the snap removed within 20 seconds of the rivet leaving the fire.
j) The rivet must be driven straight, while hot, keeping the hammer coaxial. The rivetter must
have his staging at a height which enables him to put the whole weight of his body behind
the hammer. This prevents it from bouncing.
k) Rivets conforming to IRS specifications only should be used.
l) Adequate air pressure of 5.6 to 7 kg/cm2 should be ensured for opening of the tools.
m) In the case of long bridges, the air compressor may be centrally located at a suitable trolley
refuge, with main pipe line running in both directions with suitable tappings.
(3) The following guide-lines may be followed for replacement of loose rivets in plate girders. Renewal
of slack rivets should be taken up for:
i) All rivets which are hand loose or which have lost 50% of their head by corrosion.
ii) All hammer loose rivets where corrosion has set in between the head and the plate.
iii) In end stiffeners when the percentage of hammer loose rivets is >30%
iv) In flange splices when the number of hammer and hand loose rivets is 30% or more of the
22
MAINTENANCE OF BRIDGES
total rivets on any side of the splice location, all the rivets should be renewed.
v) All hammer loose rivets at main angle to web connection upto 1/12 span from either support
of the girder.
vi) When loose rivets in end connections of lateral and cross bracings of plate girder spans
require renewal, all the rivets in the end connections should be renewed.
vii) Subject to the conditions in (1) and (ii) above, rivets, though hammer loose, need not be
renewed under the following locations:
a) In the lap or butt joints of trough flooring,
b) Through angle or tee intermediate stiffeners on girders,
c) At main angle to web connections except those covered in (v),
d) In flange plates,
e) In web splices.
23
MAINTENANCE OF BRIDGES
This is the single most important factor in ensuring good performance, as the presence of rust
under the paint film can cause its failure. Removal of rust, oil, grease and dirt is also necessary to
ensure adequate adhesion of paint film to the surface.
a) The minimum requirements of a surface prepared for painting are:
i) It should be clean, dry and free from contaminants.
ii) It should be rough enough to ensure adhesion of the paint film. However, it should not
be so rough that the film cannot cover the surface peaks.
b) Any one or a combination of the following methods (i to iv) for surface preparation may
be used, where rust has appeared in many places and existing primary coat of paint has
developed cracks, blistering, peeling, brittleness etc.
i) Manual hand cleaning: The cleaning of surface is done with the use of emery paper, wire
brushes, scrapers, etc. This is adopted for spot cleaning during normal maintenance
to remove rust, scale or old coatings
ii) Cleaning with power driven tools: Oil and grease are first removed. Heavy scale and
rust are then removed by hand tools. Residual rust and mill scales are removed by
hammer or rotary action of hand held power driven tools.
iii) Blast cleaning (sand or grit blasting): It consists of cleaning the surface with the help
of high velocity impact of abrasives (sand or grit) against the surface. It removes rust,
mill scale (oxidisation) and old paints along with some of the base metals and creates
a base for good adhesion. It is the most effective method of surface preparation.
iv) Flame cleaning: The process consists of localised application of an oxy-acetylene
flame on the steel surface. After the application of the flame the rust can be removed
by wire brushes. Flame cleaning should not be done on plates with thickness 10mm
or less as it may lead to permanent distortion of such plates.
v) In the case of maintenance painting where only the finishing coat of paint shows signs
of deterioration and the primary coat of paint is sufficiently in good condition adhering
to the metal firmly and there are no signs of rust, the surface should be washed with
lukewarm water containing 1 to 2% detergent to remove salt deposits and grime. After
this, the surface is to be dried, lightly wire brushed and sand papered. On this prepared
surface only the finishing coat of paint should be applied.
vi) Temporary coatings If, for any reason, painting cannot immediately follow surface
preparation, corrosion can be prevented for a short time by means of temporary
coating of Linseed oil applied uniformly and thinly (one third litre on 10m² area will be
sufficient). Modern prefabrication primers which are easier to apply and give better
protection are also available.
(2) Choice of suitable paints:
The following system of paints may be adopted for painting of Bridge girders:
a) In areas where there is no severe corrosion
i) Priming Coat : One coat of ready mixed paint zinc chromate priming to IS:104, followed
by one coat of ready mixed paint red oxide zinc chrome priming paint to IS: 2074.
OR
Two coats of zinc chromate red oxide primer to IRS -P-31.
ii) Finishing coat.
24
MAINTENANCE OF BRIDGES
Two cover coats of paint to IS: 13607 with colour/shade to be specified by Zonal
Railway or any other approved paint applied over the primer coats.
Note: (i) The colour/shade of finishing coat should be generally matching with the Smoke Grey
colour/shade No. ISC 692 mentioned in IS: 5-2004.
(ii) The colour/shade can be changed by CВЕ as per the local requirements
b) In areas where corrosion is SEVERE
i) Priming Coat: One coat of ready mixed paint zinc chromate priming to IS: 104, followed
by one coat of zinc chrome red oxide priming to IS: 2074.
ii) Finishing coat: Two coats of aluminium paint to IS: 2339.
c) In case where the priming coat is in good condition the steel work is painted with two coats
of paint to IS:13607 with colour/shade to be specified by Zonal Railway or paint aluminium
to IS 2339 depending on the severity of corrosion.
Note: (i) The colour/shade of finishing coat should be generally matching with the Smoke Grey
colour/shade No. ISC 692 mentioned in IS: 5-2004.
(ii) The colour/shade can be changed by CBE as per the local requirements.
(3) Conditions for obtaining good painting:
a) Painting should be done in dry and reasonably warm conditions. The relative humidity should
not be above 90%.
b) Dew frequently condenses on a structure during night and hence painting at night and in the
early hours of morning should be avoided.
c) Painting should be avoided during rainy season and in adverse weather conditions (dust
storm, mist, fog, etc.)
d) Control of paint film thickness:
i) It is desirable to control and check the thickness of paint applied to a structure. The
wet film thickness can be monitored by means of the wet film gauges from the rate of
paint consumption at intervals during application. To provide a recognizable surface
appearance and assist in rapid visual inspection during the course of the work, a
reference patch or patches of required thickness should be painted on the structure.
Measurements of Dry Film Thickness (DFT) should be done systematically over the
whole structure and results assessed. Attention should be paid not only to the average
DFT but also to uniformity of application. The normal thickness as also the minimum
thickness of the dry film should be specified and ensured during execution. It would be
desirable to specify the number of measurements to be made (at least one reading for
each sq. m. of area painted will be reasonable).
ii) Measurement of dry film thickness (DFT) : The following instruments may be used to
measure the DFT.
Electronic coating thickness gauge
Elcometer (Magnetic thickness gauge) Dial Type,
Surface profile gauge (dial type)
Most of the instruments work on magnetic or electro magnetic principles and indicate
the total thickness of the paint coat including the primary readings. Readings must,
therefore, be taken after surface preparation and after completion of painting to arrive
at the DFT.
25
MAINTENANCE OF BRIDGES
26
MAINTENANCE OF BRIDGES
27
MAINTENANCE OF BRIDGES
28
MAINTENANCE OF BRIDGES
aluminium.
d) In the event of any localised damage to the metallised coating of aluminium, as
evidenced by traces of rust, the affected portion should be thoroughly cleaned of all
rust before the priming and top coats of paints are applied. Rust streaks caused by
droppings from the track or by contact with hook bolt lips should not be mistaken for
corrosion.
vi) Precautions to be taken while inspecting metallised girders:
The use of testing hammers for rivet testing, or any other operation shall not be resorted to
since these can damage the metallised coating. Any looseness of the rivets in bracings etc.,
may be detected from visible signs such as the appearance of rust under the rivet head.
(2) Epoxy based Paints
i) Surface Preparation:
a) Remove oil/grease from the metal surface by using petroleum hydrocarbon solvent to
IS: 1745.
b) Prepare the surface by sand or grit blasting to Sa 2 ½ to IS: 9954 i.e. near white
metallic surface.
ii) Painting:
a) Primer coat:
b) Apply by brush airless spray two coats of epoxy zinc phosphate primer to RDSO
specification No. M&C/PCN-102/86 to 60 microns minimum dry film thickness (DFT)
giving sufficient time gap between two coats to enable first coat of primer to hard dry.
b) Intermediate coat: Apply by brush/airless spray-one coat of epoxy micaceous iron
oxide to RDSO specification No. M&C/PCN- 103/86 to 100 microns minimum DFT
and allow it to hard dry.
c) Finishing coat:
Apply by brush/airless spray two coats of polyurethane aluminium finishing to RDSO
Specification No. M&C/PCN-110/88 for coastal locations or polyurethane red oxide
(red oxide to ISC 446 as per IS:5) to RDSO Specification No. M&C/PCN-109/88 for
other locations to 40 microns minimum DFT giving sufficient time gap between two
coats to enable the first coat to hard dry. The finishing coats to be applied in shop and
touched after erection, if necessary.
29
MAINTENANCE OF BRIDGES
d) If identical locations exist elsewhere in the girder, they should also be closely examined.
e) Significance and severity of crack should be studied on the load carrying capacity of the
girder.
f) Repair or retrofit scheme should be prepared after fully investigating the cause of the crack.
(2) Repair of cracks:
a) The method of repair of crack should be decided based on the location and severity of the
crack.
b) If the crack is propagating in a direction perpendicular to the stress in member, holes 20 or
22 mm dia may be drilled at crack ends to arrest the crack propagation. The edge of holes
should be placed at visible ends of the crack. After holes are drilled it should be checked
that crack tips have been removed and turned bolts of 20 or 22 mm dia as the case may be
should be provided in the holes and fully tightened. Any reduction in strength of girder due
to the crack and drill of holes should be given due consideration.
c) Permanent measures may consist of the cracked member being retrofitted with rivetted or
bolted splice or where feasible the entire member may be replaced.
d) Field welding should not be undertaken for repair of cracks, unless they are of a minor
significance. The repair should be done by trained welders and the repaired portions
examined visually and/or by non destructive testing.
PART F
MAINTENANCE OF COMPOSITE GIRDERS
220 The following action should be taken for maintenance of composite girders
a) The welded steel portion of the composite girder should be maintained as per the procedure detailed
in Paras 219, 220 and 221.
b) If separation of the concrete deck slab from the steel girder is noticed, the location and length
should be marked distinctly with paint for easy identification. Repair and retrofit scheme should be
prepared after fully investigating the cause of the problem. Epoxy grouting may be done to bind
the deck slab and the girder where the defect is noticed and the girder should be kept under close
observation. If the epoxy grouting is not found effective, vertical prestressing or strapping may be
necessary for which holes should be drilled in the deck slab near the girder in the affected location
and vertical prestressing/ strapping provided.
c) The drainage system of the deck slab should be thoroughly cleaned and repaired as necessary
before the on set of monsoon.
d) Wearing coat where provided, should be maintained.
e) Any deficiencies / defects noticed during inspection should be attended to promptly.
30
MAINTENANCE OF BRIDGES
PART G
MAINTENANCE OF BED BLOCKS
221 The various defects and their remedies are outlined below
a) Improper seating of bearings: Due to uneven contact area, gaps exist between bed block
and base plate. Cracks even develop due to improper seating of bearing.
b) Shaken bed blocks: The bed blocks start loosening if they are of isolated type and a gap
develops between surface of bed blocks and surrounding masonry. In such cases the remedy
is grouting with cement mortar ensuring adequate curing and allowing sufficient time for the
mortar to set. If bed block is shaken, the same should be inspected under traffic for visible
movements and only then it should be confirmed as a shaken bed block. Action may be
taken to either encase the bed block or replace it by through bed blocks. Precast bed blocks
can be cast and bonded with epoxy resin mortar. (For details Para 514.3 may be referred)
c) Cracking and crushing of masonry: In these cases the most effective remedy would be to
replace the bed blocks with an insitu, RCC, through bed block and attending to the cracks in
the substructure.
PART H
ΜΑΙΝΤΕΝΑNCE OF BEARINGS
222 Bearings
(1) Types of bearings: The bearing transfers the forces coming from the superstructure to the
substructure. It also allows for necessary movements in the superstructure which are caused by
temperature variations. The following types of bearings are generally used.
a) Sliding bearing permitting rotation and translation (Annexure 2/10)
b) Rocker and Roller bearing (Annexure 2/11), with or without oil bath, permitting rotation
and translation respectively. Oil bath bearings are generally provided for new girders of
spans above 76.2m and for other open web girders, whether new or existing, in case it is
considered difficult to lift the girders for periodic greasing.
c) Elastomeric bearings (Annexure 2/12) permitting rotation and translation
d) P.T.F.E. Bearings (Annexure 2/12) permitting rotation and translation
(2) Maintenance of sliding and roller & rocker bearings:
a) All bearings should be generally cleaned and greased once in three years.
b) In the case of sliding bearings, the girder is lifted a little over 6mm and the bearing surfaces
cleaned with kerosene oil and a mixture of black oil. Grease and graphite in a working
proportion may be applied on bearing surfaces and the girder lowered. Jacking beams may
be inserted wherever necessary.
c) The roller and rockers are lifted from their position (by adequate slinging). The bearings
are scraped, polished with zero grade sand paper and grease graphite in sufficient quantity
applied evenly over the bearings, rockers and rollers before the bearings are lowered. The
knuckle pins of both the free and fixed end should also be greased. While lifting fixed ends,
31
MAINTENANCE OF BRIDGES
the space between girders (in case of piers), or between the girder and the ballast wall (in
case of abutment) at the free ends should be jammed with wedges to prevent longitudinal
movement of the girders.
d) Phosphor bronze bearings need not be greased as they are corrosion resistant and retain
the smooth surface.
e) The tooth bar of the roller assembly should be placed vertically at mean temperature. It
will be better to indicate in the completion drawings of bridge stress sheet, the maximum
expansion, and range of temperature for which the bearing is designed, so that the slant at
the time of greasing can be decided depending on the temperature obtained at the time of
greasing.
f) In the case of roller bearings with oil bath, dust covers should invariably be provided to keep
the oil free from dirt. Wherever oil bath bearings are provided, inspection of the bearings,
after removal of the casings to the extent necessary, should be carried out at least once in
5 years. Checking of oil level, draining out as necessary to detect and remove any water
collected at the bottom and replenishing the oil, should be done annually. The oil in oil bath
bearing must be changed completely once in every 5 years
(3) Elastomeric bearings:
a) Elastomeric bearings are made of natural or synthetic rubber of shore hardness of
approximately 50 to 70. They are very stiff in resisting volume change but are very flexible
when subjected to shear or pure uniaxial tension. They are generally reinforced with steel
plates in alternate layers to reduce bulging. When used with a steel or concrete girder these
permit moderate longitudinal movements and small rotations at the ends.
b) These bearings require periodic cleaning. They may require replacement in service
depending on the condition and usage.
c) Whenever problems such as excessive bulging, tearing, off- loading, vibrations etc. are
noticed, suitable action for repair/rectification shall be taken. If repair/ rectification is not
feasible, action for replacement of such bearings shall be initiated.
d) If results of inspection are not conclusive to warrant replacement of bearings but doubts
arise regarding performance of bearings, 'two representative bearings shall be taken out
from service and tested. The result of tests shall be compared with codal provisions to take
further decision.
e) When replacing any Elastomeric Bearing, then all bearings in one line of support (in
transverse direction to traffic) of a span to be replaced so as to maintain same stiffness level.
(4) Teflon or P.T.F.E. bearings:
a) The coefficient of friction between steel and PTFE is quite low. The mating surface which
forms the upper component of the bearing is stainless steel with good surface finish. The
PTFE can be unfilled or filled with glass fibre or other reinforcing material. Its bonding
property is very poor. Hence it is preferable to locate the PTFE by confinement and fitting of
half the PTFE thickness in recess in a metallic matrix.
b) These are used either to provide rotation by sliding over cylindrical or spherical surfaces or
to provide horizontal sliding movement over flat surface or a combination of both. Where
there are large displacements accompanied with relatively small loadings, as in case of
centrifugal loads, wind loads or seismic loads, PTFE sliding bearings are utilised.
c) These bearings also require periodic cleaning of the bearing surface.
32
MAINTENANCE OF BRIDGES
The interface should be protected from dust. Lubricating the mating surface by silicon grease
reduces the coefficient of friction and is desirable.
PART I
GENERAL PRECAUTIONS
33
MAINTENANCE OF BRIDGES
(iii) Engage four parties to remove soil. First party will start removing soil from the Section
'A1. It means start removing soil in the section-1 from top level and depth upto the level
of crown of arch i.e. Part 'A' as shown in the sketch. Second party will simultaneously
remove the soil from Section-2 Part 'A' i.e., A2. It means soil from top level to the depth
up to the crown. Third and four parties shall work in section A3 & A4.
(iv) After completing A1, A2,A3 & A4, follow the sequence Section-A5, A6, A7, A8, and
then A9, A10, A11 & A12 and then A13 & A14. After this exercise Section A is cleared.
This procedure ensures that there are no unbalanced lateral forces.
(v) Similarly follow the same sequence for removing soil of Part -B:
(vi) Provide thick nylon netting supported on piers so as to arrest any falling debris as
shown in fig 1(c).
(vii) Now each of four parties should break spandrel wall S1, S2, S3 & S4 simultaneously
under block, as some debris can fall on track.
(viii) After breaking spandrel wall, arch barrel of section 1, 2, 3 & 4 shall be broken under
block protection by each of four parties. In next block, section 5, 6, 7 & 8 shall be
34
MAINTENANCE OF BRIDGES
35
MAINTENANCE OF BRIDGES
be of retro-reflective type.
(4) If locos are not able to haul the train, which gets stuck near or on the bridges where TE is limited
and required tractive effort is more than 30t per Loco, the driver should not apply more tractive effort
and should ask for assisting engine for clearing the train. This instruction should be incorporated
in the Working Time Table so that all operating staff is aware of the instructions
(5) Operation of TE Limitation on such bridges as given above is to be made part of Learning of Loco
Pilots and Astt. Loco Pilots. This item should be monitored by Loco Inspectors and Safety Counselors
during their routine inspection
PART J
INSPECTION, MAINTENANCE AND CONSTRUCTION OF RUB/ SUBWAY
Inspection, Maintenance and Construction of RUB/Subway shall be carried out as per RDSO
guideline no. BS-138 "Guideline for Inspection, Maintenance & Construction of RUBs/Subways"
with latest revision.
36
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
CHAPTER III
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF
BRIDGES
37
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
38
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
39
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
be indicated by arrows.
b) Three cross sections for the river bed are required to be plotted to a natural scale of 5
metres. to a cm. Where the width of the river in flood exceeds 1000 metres, the scale may be
reduced. For river width greater than 500 metres, the cross section should be plotted in two
halves. The cross sections should be taken at typical points selected at intervals of about
2 kms. On each cross section, the levels of the highest known flood, ordinary flood and
ordinary low water should be indicated by lines with reduced levels. On the cross section
taken on the center line of railway, an elevation of the proposed bridge should be drawn to
a scale in its proper position. The chainage should be indicated on the cross section. Where
borings or trial pits have been made, their position, with a note on results should also be
given.
40
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
41
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
42
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
43
INVESTIGATION AND SURVEY FOR CONSTRUCTION OF BRIDGES
(3) Pile foundation can be quite economical, particularly where the foundations have to be built very
deep or taken through deep layers of soil subjected to little scour. Larger diameter piles can be
provided to take care of large horizontal forces when the foundations are deep. Larger diameter
piles can also be provided for foundation depths beyond the limit of pneumatic operations.
(4) Well foundation provides a solid and massive foundation for heavy loads and large horizontal
forces. This has a larger cross sectional area and hence the total foundation bearing capacity is
much larger than what may be offered by a cluster of piles. The well provides a very good grip
when taken sufficiently deep and hence is most suited for river beds subjected to heavy scour.
317 Approval of bridge drawings for doublings, gauge conversions, new lines and other bridge
works:
(i) ln case of new lines / doublings / gauge conversions, General Arrangement Drawings (GADs) for
Railway Bridges where linear waterway is being reduced or vertical clearances are inadequate
and where construction is likely to affect any of the existing Bridges (during construction or during
service), after clearance of concerned divisional branch officers and DRM, shall be approved by
Chief Bridge Engineer (CBE) of the concerned Zonal Railway. GADs of all other Railway Bridges
shall be approved by concerned Chief Engineer/Construction.
(ii) General Arrangement Drawings for all Railway Bridges on open line shall require approval of Chief
Bridge Engineer of the concerned Zonal Railway.
(iii) General Arrangement Drawings and Launching schemes of all ROBs/RUBs/FOBs/Rail flyovers
which shall affect the existing lines, after clearance of concerned divisional branch officers and
DRM, shall require approval of Chief Bridge Engineer of the concerned Zonal Railway. GADs and,
Launching schemes of all other ROBs/RUBs/FOBs/Rail flyovers shall be approved by concerned
Chief Engineer/Construction.
(iv) The structural design and drawing work for the Bridge works (Railway Bridges/ROBs/RUBs/FOBs/
Rail flyovers etc.) being executed by Open line organisation shall be carried out by Bridge branch
at HQ level of the concerned Zonal Railway.
(v) The structural design and drawing work for the Bridge works (Railway Bridges/ROBs/RUBs/FOBs/
Rail flyovers etc.) being executed by Construction organisation shall be carried out and approved
by Construction organisation.
318 Approval of bridge drawings for Dedicated Freight Corridor lines:
(i) General Arrangement Drawings for railway bridges where linear waterway is being reduced or
vertical clearances are inadequate and where new bridge (during construction or during service)
is likely to affect any of existing bridges, shall be approved by Chief Bridge Engineer of concerned
zonal railway. GADs of all other bridges shall be approved by the officer nominated to work as CBE
by DFCCIL.
(ii) General Arrangement Drawings and Launching schemes of all ROBs/RUBS/FOBs/Rail flyovers
shall require approval of Chief Bridge Engineer of concerned zonal railway.
(iii) The structural design and drawing work for the bridge works (railway bridges /ROBs/RUBs/FOBs/
Rail flyovers etc.) shall be prepared and approved by the officer nominated to work as CBE by
DFCCIL. However, in case of Rail flyovers, proof checking of the designs by IIT is mandatory.
44
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
CHAPTER-IV
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
45
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
PILE FOUNDATIONS
46
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
Timber piles may, however, be used for temporary restoration of traffic. They should, be replaced
with permanent structures. A typical arrangement of a temporary wooden pile bridge is shown in
Annexure 4/8.
47
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
48
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
b) For non-cohesive soils, Hiley’s formula is more reliable than other formulae. (Appendix-B of
IS 2911 Part -I, section -I ). Hiley’s formula is not reliable in cohesive soils.
c) Load test is most desirable. The load test on pile should be carried out four weeks after
casting the pile.
d) Resistance due to skin friction will be available only below the scour line and this must be
taken into account in all the three methods.
(2) Factor of safety for Pile Foundations:
a) The factor of safety shall be judiciously chosen after considering the following:
i) Reliability of the ultimate bearing capacity of pile;
ii) Type of superstructure and type of loading;
iii) Allowable total/differential settlement of the structure;
iv) Experience of similar structures near the site.
b) The minimum factor of safety with static or dynamic formula shall be 2.5. The value to
be selected for the factor of safety shall, however, take into account, the allowable total
settlement and differential settlement of the structure as a whole.
The ultimate load capacity should be obtained, whenever practicable, from a load test (initial)
(as per IS: 2911/ (Part 4)-1985).
Factor of safety for assessing safe load on piles from load test data should be increased in
unfavourable conditions where:
(i) Settlement is to be limited or unequal settlement avoided as in the case of accurately
aligned machinery or a superstructure with fragile finishing.
(ii) Large impact or vibrating loads are expected.
(iii) The properties of the soil may be expected to deteriorate with time, and
(iv) The live load on a structure carried by friction piles is a considerable portion of the total
load and approximates to the dead load in its duration.
(3) Bearing capacity of a pile group:
The bearing capacity of a pile group may be either of the following:
i) Equal to the bearing capacity of individual piles multiplied by the number of piles in the
group, or
ii) It may be less than the above.
The former holds true in the case of friction piles, cast or driven into progressively stiffer
materials or in end bearing piles. In friction piles installed in soft and clayey soils, it is normally
smaller. For driven piles in loose sandy soils the group value may be higher due to the effect
of compaction. In such a case, a load test should be made on a pile from the group after all
the piles in the group have been installed.
NOTE- Reference should be made to IS: 2911 (1979) Code of Practice for Design and
Construction of Pile Foundation (Revised) for further details while designing the piles and
pile groups.
49
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
50
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
51
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
part way up the pile, to prevent laitance from being entrapped within the pile.
(8) All tremie tubes should be scrupulously cleaned after use.
(9) Normally concreting of the piles should be uninterrupted. In an exceptional case of interruption of
concreting, but which can be resumed within 1 or 2 hours, the tremie shall not be taken out of the
concrete. Instead, it shall be raised and lowered slowly, from time to time to prevent the concrete
around the tremie from setting. Concreting should be resumed by introducing a little richer concrete
with a slump of about 200 mm for easy displacement of the partly set concrete. If the concreting
cannot be resumed before final setting of concrete already placed the pile so cast may be rejected
or accepted with modifications.
(10) In case of withdrawal of tremie out of the concrete either accidentally or to remove a choke in the
tremie, the tremie may be reintroduced in the following manner to prevent impregnation of laitance
or scum lying on top of the concrete deposited in the bore.
The tremie shall be gently lowered on to the old concrete with very little penetration initially. A
vermiculite plug should be introduced in the tremie. Fresh concrete of slump between 150 mm
and 175 mm should be filled in the tremie which will push the plug forward and will emerge out of
the tremie displacing the laitance/scum. The tremie will be pushed further in steps making fresh
concrete sweep away the laitance/scum in its way. When tremie is buried by about 60 to 100 cm,
concreting may be resumed.
(11) In case of concreting through tremie or such tubes which are subsequently withdrawn, the concrete
shall be placed in sufficient quantity to ensure that during withdrawal of the tube a sufficient head of
concrete is maintained to prevent the in-flow of soil and water or bentonite slurry (Refer Annexure
4/10).
(12) The top of the concrete in a pile shall be brought above the cut-off level to permit removal of all
laitance and weak concrete before capping and to ensure good concrete at the cut off level for
proper embedment into the pile cap.
WELL FOUNDATIONS
52
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
holes. The overall length of the well generally is restricted to twice the width.
53
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
54
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
enclosing the area of the island may be provided. Upto 1.5 metre depth, bamboo piles may
be used and timber ballies may be used upto 3 metre depth. The piles are lashed together
with strap, wire ropes or coir ropes. Bamboo matting is then fixed along the inside faces of
the piles and the space between the mattings is filled with puddle sand bags. Beyond 13
metre depth, steel sheet piles should be used. The piles should have a grip of at least 3
metres. Sand bags should be dumped outside the island as a protection against scour. In
cases, where velocity is high, wire netting (crates) filled with boulders may be used. (Refer
Annexure 4/13).
55
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
or diesel winches of suitable capacity can be used for operating the grabs or dredgers. For faster
sinking of wells of 6 metre diameter and above, suitable cranes may be used.
(2) Well Sinking through clay and hard strata:
a) In stiff clay strata or in strata with compact sand, shingle and boulders, the use of rail chisel
may be required. Use of chisels can be avoided if hammer grabs are used.
A sketch of rail chisel commonly in use on Indian Railways is shown in Annexure 4/16.
b) For sinking through stiff clay and other hard strata buoyancy effect of the soil may be reduced
by dewatering the well to increase its effective weight.
c) If due to heavy skin friction, the well is held in a floating condition, air or water jets may be
used on the outer periphery of the well for reducing the friction. For this purpose pipes of 4
to 5 cm. dia. fitted with nozzles can be incorporated in the well close to the outside periphery,
particularly in the curb portion and also for some height of the steining above.
d) When any of the above methods is not effective, a few sticks of gelignite can be detonated
under the water below the cutting edge. This results in shaking of the well and reducing the
skin friction, which helps in its further sinking. Charging should be started with small quantities
in each dredge hole at a time and gradually increased. When there is more than one dredge
hole, such charging and detonation should be done in all the holes simultaneously.
(3) Precautions to be taken during well sinking:
a) Blowing of Sand:
Great caution is necessary when dewatering of well is done at shallow depths or when the
well has not gone into the soil by at least 1 metre. The difference in the hydraulic pressure
inside and outside the well may create a passage for rush of sand from outside the well
resulting In “blowing of the sand”. Sand blowing can endanger the safety of men working
inside the well and can also cause sudden tilting of the well. Seepage of water should be
carefully watched during sinking and should be checked by putting sand bags over the area
where such seepage is noticed. In severe cases of sand blowing, large quantity of the sand
is sucked into the well and a funnel shaped depression is formed outside the well as shown
in Annexure 4/17. Empty gunny bags and branches of the tree with green leaves may be
thrown into the funnel and dredging continued till the sand blow gets arrested. The well can
then be dewatered completely and excavation continued.
b) Quick sand condition:
Quick sand conditions may occur when fine sand or silt underlie an impervious layer of clay
with a considerable hydraulic pressure below the clay layer. As soon as the layer of clay is
pierced through, a steep hydraulic gradient is established across a fine sand or silt under the
clay and it either starts rushing upwards or is in a state of incipient motion. It has no shear
strength in this state and allows the well to sink into it without offering any resistance. In most
cases, the sand rises to a considerable height above the cutting edge and remains there in
spite of continuous dredging. The problem can be faced to a certain extent if the steining of
the well is raised to a considerable height when the cutting edge is well within the clay layer.
The level of water inside the well should also be raised by pumping in water.
Dewatering should not be tried under any circumstance and no one should be allowed
inside the well when quick sand condition develops. By keeping the water level inside the
well higher, a hydraulic gradient is established in the reverse direction and the quick sand
condition is not allowed to develop.
56
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
Even if it does develop, there is considerable margin of safety and the well does not sink
below the bed level.
c) While sinking wells in deep water, divers with their equipment should be present for
emergencies.
57
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
This can be adopted only when sinking is done under dewatered conditions either by
pumping or using compressed air. The side which is lower is packed with sand bags and
excavation is carried out only on the high side. This method should be used cautiously if the
depth of the well is shallow and when the well is resting on a sloping rock surface.
58
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
f) The steining concrete for wells to be sunk using pneumatic caissons should be as dense as
possible to reduce the pore pressure caused by air under pressure trying to escape through
fine pores in concrete.
g) The joints should be made as air tight as possible to prevent escape of air. Water proof
cement plastering can be resorted to on the inside face of steining.
59
CONSTRUCTION OF FOUNDATIONS FOR BRIDGES
60
REHABILITATION OF BRIDGES
CHAPTER V
REHABILITATION OF BRIDGES
502 In case of introduction of new type of locomotives, rolling stock and other train compositions with
increased loads (vertical and longitudinal) special strengthening measures may be required as per
relevant code provisions and guide lines.
61
REHABILITATION OF BRIDGES
62
REHABILITATION OF BRIDGES
63
REHABILITATION OF BRIDGES
remains workable). For best results use of polythene vessels, hand gloves and safety glasses is
recommended while working with epoxy compounds
515 Arch bridges
(1) In case of cracks in arches, pressure grouting with cement mortar at a pressure 4 to 6 kg/cm2 is
generally quite effective
(2) If pressure grouting is not effective, one of the following alternative methods may be adopted:
a) Construction of a suitably designed box culvert under the arch and filling the intermediate
space between the arch and the box with lean cement concrete (Annexure 5/5a). This
method may be adopted when the HFL is not high.
b) Construction of a box culvert abutting one of the abutment dismantling the other abutment,
when the HFL is high or the waterway is inadequate (Annexure-5/5b).
c) Closed ring jacketting, where a slight reduction in waterway is permissible (Annexure 5/5c).
Specially designed folded plate design can be successfully adopted in the above case
(Annexure 5/5f).
d) Jacketting below intrados: For strengthening of distressed arches, jacketting below intrados
is preferable, if the resultant reduction in waterway is permissible. In such cases, new arches
should be designed as under:
i) to take the entire load by itself where the existing arch has transverse crack(s).
ii) to take the entire load by composite action with the existing arch ring, where the
existing crack(s) are all longitudinal or there are no signs of distress in the existing
arch and if effective bond could be ensured between the new and old arch ring.
e) Jacketting above extrados: In some special cases, external (extrados) jacketting of the arch
is resorted to, after relieving the arch by temporary girders. In such cases, the new arch ring
should be designed to take the entire loads i.e. dead and live loads etc.
f) Where the HFL is high, it may be advantageous to convert the arch bridge into a slab top
by suitable raising and strengthening the masonry of the piers/abutments and using pre-
cast reinforced cement concrete/ prestressed concrete slabs over them. Alternatively arch
relieving girders maybe used. The arches can be retained where there is adequate cushion
above them. In other cases, the arch may be dismantled, either during a line block or under
temporary relieving arrangement but before placing of the slab/girder. (Annexure 5/4d and
e).
(3) In the case of strengthening (i.e. by jacketting) of abutments and piers of arch bridges, the design
should always be on the basis of composite action of the new material acting along with the existing
one. It should, however, be ensured that a proper bond is established between the existing masonry
and new material by suitable means such as dowels and post grouting through grout holes to be
left while casting the jacket.
(4) In all cases of cracked masonry, whether in arches or in abutments and piers, all the cracks should
be plugged by pressure grouting before the additional material (jacket) is provided.
(5) In all cases of jacketting, precautions mentioned in Para 513(b) should be followed. In cases of
jacketting below intrados, the space in between the new arch ring and the existing arch ring should
be pressure grouted, for which hole should be provided in new arch ring.
64
REHABILITATION OF BRIDGES
(6) Jacketting works should be done under suitable speed restriction. Depending upon location, extent
of exposure, type of soil etc., speed restriction may be as under:
i) Jacketting below bed level. 15 km/h to 30 km/h depending on the
extent of exposure, type of soil etc
ii) Jacketting from bed level to springing level. 30 km/h to 50 km/h depending on
condition of masonry
iii) Jacketting of arch ring when designed for the full 30 km/h to 50 km/h depending on the
design load. condition of arch ring and cushion
iv) Jacketting of arch ring when designed by taking 15 km/h.
composite action with existing arch.
The above speed restrictions may be relaxed after the completion of work as per the following
guidelines, if jacketting is carried out using ordinary Portland cement conforming to IS: 269:
i) 50 km/h after 7 days of last concreting;
ii) 75 km/h after 14 days of last concreting; and
iii) Normal sectional speed after 28 days of last concreting.
To reduce the duration of speed restriction, rapid hardening cement to IS 8041 may be used.
65
REHABILITATION OF BRIDGES
66
REHABILITATION OF BRIDGES
67
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
CHAPTER VI
CONSTRUCTION OF SUBSTRUCTURE AND SUPERSTRUCTURE
INCLUDING ERECTION OF GIRDERS
PART A – CONSTRUCTION OF SUBSTRUCTURE
601 General
The function of piers and abutments is to transmit the live load and the dead load of the superstructure
to the foundations. The details of the loading to be considered in the design of substructure are
contained in the IRS Bridge Substructure Code and Bridge Rules and include, inter alia, impact
effect of the live load and the longitudinal forces exerted by it, transverse loading caused by wind
action on the substructure and the live load and due to the pressure exerted by back fill etc.
68
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
604 Piers, abutments and wing walls
(1) Piers, abutments, and wing walls:
a) The size of piers and abutments depends on the construction materials used.
b) Masonry piers are provided with a batter varying from 1 in 24 to 1 in 12. Their width at the top
is determined keeping the minimum space required for seating of the bearings of girders as
also to provide sufficient distance on the outside of the bearings to resist diagonal shearing.
c) For masonry abutments, a front batter of 1 in 16 to 1 in 10 is used: a flatter slope or steppings
are provided in the rear as per design requirements.
d) When piers are reinforced cement concrete, typical sections used are shown in Annexure
6/1.
(2) Wing Walls:
a) The abutments can either be of the conventional type with the front face exposed or of the
buried type when waterway requirement is not the main consideration.
b) In the former case, wing walls are necessary to retain the slopes of the approach banks.
Wing walls can be of the splayed, straight, square or ‘box’ type (Annexure 6/2). Butt joints
should be provided between wing walls and abutment, wing walls and return walls and
for the various tracks, when the bridge is for more than one track to cater for differential
settlement in case of poor soils.
c) Wing and return walls also require provisions of weep holes as in abutments.
69
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
guidelines for concrete mix design, published by the Indian Standards Institution.
(6) Ordinary Portland cement conforming to IS 269 shall be used for plain, reinforced and prestressed
concrete work. Portland blast furnace cement conforming to IS 455 may also be used for plain
and R.C.C. work but not for PSC work. Portland pozzolana cement (IS 1489) shall not be used for
PSC and RCC works. It can be used only for foundation concrete and concrete works in Bridge
substructure where reinforcement is not provided for structural strength. When Portland pozzolana
cement is used it is to be ensured that proper damp curing of concrete is done at least for 14 days
and supporting form work is not removed till concrete has attained at least 75% of design strength.
High strength ordinary Portland cement conforming to IS 8112 (Grade 43) and IS 12269 (Grade
53) may also be used where required from consideration of mix design.
(7) Reinforcement steel shall conform to one of the following specifications :
i. Grade I mild steel & medium tensile steel bars conforming to IS:432 (part-I).
ii. Cold twisted bars conforming to IS : 1786.
iii. Rolled steel made from structural steel conforming to IS: 2062 Grade A and Grade B.
(8) The prestressing steel shall be any one of the following:
i. Plain hard drawn steel wire conforming to IS : 1785 (Part I)
ii. High tensile steel bar conforming to IS : 2090 and
iii. Uncoated stress relieved strand conforming to IS : 6006.
(9) i) Reinforcement steel shall be free of loose mill scales, loose rust and coats of oil, mud or
other material ,while being used.
ii) Cover and spacing of steel shall be uniform and as specified in the drawings.
iii) All ends of binding wires shall be carefully turned inside so that they do not project out of
concrete to induce rusting.
iv) Reinforcement steel shall be adequately secured so that it maintains its position during
casting and vibration of concrete.
(10) Aggregates : Aggregates conforming to IS : 383 shall only be used. They shall be clean. Marine
aggregates shall not be used in concrete unless they are thoroughly washed in potable water and
sulphur and chlorine content are low. The tests on aggregates shall be done in accordance with IS
: 2386 (Part-I) to IS : 2386 (Part VIII)
(11) Water used for mixing and curing concrete shall be clean and free from injurious amounts of oil,
acids, alkalis, salts, sugar, organic materials or other substances which may be deleterious to
concrete or steel. Potable water is generally considered fit for use in concrete. Further details can
be seen in IRS Concrete Bridge Code.
(12) Form work : Form work requirement shall be as per IRS Concrete Bridge Code including stripping
time. In the case of PSC works, support shall not be removed till sufficient prestress has been
imparted to the member.
(13) Special attention shall be given to curing of concrete in order to ensure maximum durability and
minimise cracking. The method of curing shall be as per IRS Concrete Bridge Code.
(14) The appropriate value of minimum cement for different exposure conditions and maximum cement
content for RCC and PSC works as well as the water cement ratio shall be as per the provisions
given in the IRS Concrete Bridge Code. The equipment, material and the proportions of the mix to
be used shall be submitted to and approved by the engineer before the work is started.
(15) i) While transporting concrete from the mixer to the form work, no segregation shall occur nor should
70
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
there be any loss of ingredients. Necessary precaution may be taken to ensure this.
ii) The concrete shall be deposited as nearly as practicable in its final position without rehandling.
It shall be compacted before setting commences. It shall not be subsequently disturbed. The
method shall be such as to avoid segregation. There shall be no displacement of steel or
form work while placing concrete.
(16) Compaction of concrete: All concrete shall be compacted by vibration. Generally internal vibration
shall be used on all sections that are sufficiently large to admit them. The use of mechanical vibrators
complying with IS:2505, IS:2506, IS:2514 and IS:4656 for compacting concrete is recommended.
The following techniques shall be followed for vibration:
i) Vibrators shall be distributed so that the concrete becomes uniformly dense and plastic
mass.
ii) Vibrators shall be used for compaction only and not for moving concrete horizontally along
the form.
iii) For horizontal and vertical operations of vibrators, the spacing of points of vibration shall be
such that the zones of influence overlap.
iv) For concrete deposited in layers, the vibrators shall be inserted vertically and allowed to sink
due to its own weight to the bottom of the layer and be slowly withdrawn. For succeeding
layer, the vibrator shall penetrate the surface of the previous layer. For further details, IRS
Concrete Bridge Code may be referred to.
(17) Bearing areas for members shall be finished to true plane so as to give uniform bearing on the
entire area. Bearing plane shall be horizontal even for the bridges on grades.
(18) In major works, a field laboratory should be set up at the work site which should be equipped with
necessary equipments to carry out the various tests on coarse and fine aggregates, cement, water
and concrete.
71
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
take the load, the temporary structure is removed.
(2) Work on multiple spans:
a) Work can be done simultaneously on a number of spans using more than one set of forms.
b) In this method, due care will have to be taken to see that the horizontal thrust on the pier/
abutment is not such that they give way. This can be guarded against by commencing the
work on the adjacent span and bridging some load to bear on the pier before the support
and the framework used on the previously cast span is removed. A proper sequence of
construction of multiple span arch bridge shown in Annexure 6/4 (a).
c) Supporting arrangement for arches: Over dry beds of streams, stagings can be constructed
from the bed itself. Due care will have to be taken in supporting the staging columns on bed
by giving a suitable timber support to spread the load and to check the stagings at various
stages to see that it does not settle under the load when the casting of superstructure is in
progress.
d) If the work has to be carried out in flowing water of the river, the staging will have to be
supported over shallow thin piles driven in the sand bed for sufficient depth (say 3 to 4m into
the soil).
e) In case the height of the pier is considerable as in high viaducts and staging is to be put
up from bed, it may be difficult and expensive and alternative methods of supporting the
staging from an intermediate level have to be provided. For this purpose, intermediate ribs
are provided on piers to support the temporary floor system over which the false work can
be put up or props erected from bed.
(3) The arch ring or barrel should be cast in segments, the minimum number being two so that the
effects of shrinkage can be countered by casting shrinkage keys between them separately. These
keys are cast after the major shrinkage in the segments take place. Care should be taken in the
sequence of casting segments/units so as to allow for shrinkage and at the same time develop the
strength at appropriate location. A suggested sequence is shown in Annexure 6/4 (b)
(4) An alternative method of erection evolved after development of pre-casting techniques is by
stretching a cable across the span and erecting precast units from either end and staying them
with wires till the last units "crown" is laid and it sets. Cables will be released and removed after
the arch sets and is able to act monolithically.
72
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
girder is moved over this temporary girder or frame, supported at intervals or pulled across. When
the full length of the main girder has come over the launching girder, it is jacked up and temporarily
held in position. The launching girder is then side slowed to take the position of the next girder over
the span. The main girder launched earlier is then lowered into position with the help of jacks.
The launching girder can be then be moved over the next span. A schematic diagram is shown in
Annexure 6/5 (a).
(2) Erection of concrete girders with cranes/derrick:
If the bed is dry, the girders can be cast on the bed and erected by mobile cranes one on either end
or with the help of a suitable derrick in the centre or one derrick each on either end. If the height
of the pier is not much and girders are too heavy to be launched by the available crane or derrick,
the girder can be jacked up from either end on temporary rails (which will also be simultaneously
built up) to pier top level and then side slewed in position. The deck slab can be cast subsequently.
In the case of prestressed concrete girders transverse prestressing will also be involved. For this
purpose, holes should be left in correct position to form ducting. The diaphragm with necessary
ducting should be cast after all the girders are launched correctly and adjusted in position.
Part prestressing is done before individual girders are lifted or launched and remaining cables
are tensioned, some before and balance after or all after the deck is cast according to the design.
Extreme care has to exercised in following the sequence that has been given by the designers as
any deviation can cause a crack or unwanted lateral deflection in the individual girder.
(3) Erection by Cantilevering Method :
For very large spans, cantilevering method may be adopted. In this method, the erection starts from
the abutment end and the erection of the members ahead is done by using a crane which travels
by using the support on the previously erected part structure. Annexure 6 / 5 (b) and 6 / 6 (a)
(4) Incremental launching method :
The method is basically a cantilever erection method for PSC bridges. By adopting this method,
it is possible to effect economy in construction and ensure the quality due to adoption of factory
type production and also ensure quick erection. This method is particularly suitable for launching
continuous girders due to site requirements.
Incremental launching is a highly mechanised bridge girder erection method. Basically, it consists
of manufacturing a prestressed concrete bridge girder segment by segment in a prefabrication
area behind one of the abutments. Each new segment is concreted directly against the preceding
one and after it has hardened and stressed, the structure is jacked forward by the length of one
segment. A steel launching nose is attached in front, to facilitate launching. Gradually the bridge
unit is pushed out over the intermediate piers (Annexure 6/6 (b)).
In this method the span and depth configuration is to be suitably chosen and the cross section
has to be of box or a double T section. The piers should resist forces during launching in excess
of those due in the permanent structure. Design has to take into consideration in advance the use
of this method as the prestressing section requirements have to suitably allow for the same. The
depth of the box girder in relation to the span should be able to cater for the reversal of stress and
for shear in the webs without undue congestion of reinforcement and prestressing tendons.
The temporary support if used for launching need to stay in place until the bridge launching process
has been completed and the final prestressing force applied.
73
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
611 Important points to be borne in mind in the construction of PSC girders
(1) i) The handling and erection stress.
ii) Accessibility of every part of the structure for close inspection.
iii) The design of the end block and bearings should permit periodical inspection and servicing
of the bearings.
(2) Provision shall be made to cater for an additional prestressing forces of 15% of the design
prestressing force, for easy installation of prestressing steel at a later date.
(3) Admixtures/plasticizers of approved type only should be used.
(4) Minimum grade of concrete for PSC work shall be M/35.
(5) In all methods of tensioning, the stress induced in the tendons shall be determined by measurement
of elongation and also independently by direct measurement of force using a pressure gauge or
other means. The two values shall be comparable to each other and the theoretical values within
a tolerance of 5%. Calculations for elongations and gauge readings must include appropriate
allowances for friction, strand wire slippage and other factors as applicable. Breakage of wires in
any one prestressed concrete member shall not exceed 2.5% during tensioning. Wire breakage
after anchorage, irrespective of percentage, shall not be condoned without special investigations.
(6) Prior to stressing of strands, bottom forms should be kept clean and accuracy of alignment ensured.
Form surfaces to be in contact with concrete must be treated with effective release agent. Special
care must be exercised to prevent contamination of strands from release agents, grease or other
coatings.
(7) Cables shall not be left unstressed in ducts for long duration and hence threading of cables in
ducts shall be done just prior to stressing. The initial stress due to prestressing in the cable shall
not exceed 80% of UTS of the cable.
(8) Post tensioning systems shall be installed in accordance with the manufacturer's directions and
proven procedures. Manufactures's recommendations regarding end block details and special
arrangements in anchorage zones applicable to their particular system should be observed.
(9) Details and positions of ducts: Ferrous metal is recommended for duct material. Aluminium should
not be used. Metal ducts must be such that destructive galvanic action on duct and tendon will not
occur.
(10) As the alignment and position of ducts within the member is critical, short kinks and wobbles shall
be avoided. The trajectory of ducts shall not depart from the curve of straight lines shown in the
drawing by more than 1 in 240. The cable position shall not deviate by more than 5 mm from the
designed trajectory vertically. The area and alignment of ducts shall be such that tendons are free
to move within them and there shall be sufficient area left out to permit free passage of grout.
(11) Any slack in the prestressing tendon shall first be taken up by applying a small tension. For arriving
at the extent of correction and the actual elongation, the procedure given in IS : 1343 shall be
followed. The rate of application of load shall be in accordance with manufacturer's recommended
procedure for post tensioning. Slip must be measured at each end and the extension for the total
length.
(12) Anchorage : Anchorage devices for all post tensioning systems must be aligned with the direction
of the axis of tendons at the point of attachment. Concrete surface, against which the anchorage
devices bear must be normal to this line of direction. Accurate measurement of anchorage losses
due to slippage or other causes shall be made and compared with the assumed losses shown in
the post tensioning schedule and when necessary adjustments or corrections shall be made in the
74
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
operation.
(13) The stressed cables shall be grouted immediately after the prestressing operation for the girder is
completed. To avoid possibility of part of the sheathing getting clogged by the over laying concrete,
it shall be ensured that the cables move freely inside the sheath during and also after concreting. All
precautions shall be taken to ensure that the sheathings do not get contaminated with deleterious
chemicals, salts, etc. during the manufacture, storage and installation of the same and they are
watertight.
(14) Protection to prestressing steel : All prestressing steel shall be free of deleterious materials such as
grease, oil, wax, dirt, paint, loose rust, or other similar contaminants that would reduce bond between
steel and concrete. Prestressing steel shall not be contaminated with form release agents used on
forms or beds. High strength steel is to stored under cover to prevent `corrosion. Prestressing steel
with deeply etched or pitted surface will not be permitted for use in PSC work. However, a light
surface rust strongly adhering to the steel is acceptable. Strand surface shall always be inspected
prior to placement of concrete and contaminated ones shall be cleaned with an effective solvent.
(15) Safety: Large tensioning forces which are necessary to all prestressing operations make such
construction very hazardous. It should be ensured that good safety practices are established and
that each employee complies with the same.
(16) Tensioning of the prestressing steel shall not be commenced until all the necessary tests of the
concrete cubes manufactured of the same concrete and cured under the same conditions have
been carried out and the results found satisfactory.
75
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
iii) Use hoop steel around tendons near ends of beams.
iv) Handle only from designated pick up points.
v) Take adequate care during storage, transportation and erection.
(3) Camber :
Camber is the upward deflection which occurs in prestressed concrete flexure members due to
eccentricity of prestressing forces. It does not include dimensional inaccuracies due to errors in
manufacture, improper bearings or other deficiencies of construction.
The anticipated camber due to prestressing shall be computed and shown in the detailed working
drawings. Actual camber shall be measured and compared with the computed values.
(4) Dimensional tolerances may be permitted as provided in IRS Concrete Bridge Code and any other
relevant literature.
PART C –
FABRICATION AND ERECTION OF STEEL GIRDERS
76
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
designer in design, based on slip factor chosen.
77
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
arc welding process, either fully automatic or semi automatic type. The entire length of fillet welds is
checked by NDT methods and all the butt welds in flanges and web are required to be radiographed
and cleared. In the case of composite girders, the top flange plate with channel shear connectors,
welded in staggered arrangement, should be made first, before the I section is made. Suitable jigs
and fixtures are needed for fabricating the members by welding, to reduce the extent of warping
and distortion.
Site welding is generally prohibited. However, in certain unavoidable cases such as repair/
maintenance work for girders in service it can be permitted by Chief Bridge Engineer/ officer
equivalent to the rank of SAG officer and above. During construction, it can be permitted on case
to case basis by an officer equivalent to the rank of Chief Administrative Officer/Construction and
is confined to connections having low stresses, secondary members, bracings etc. The suitability
of parent metal to take welding, should, however, be tested first.
78
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
the Engineer will know by what time he must complete certain jobs and which of the jobs can be
tackled later. When crossing rivers liable to spate, a study of weather conditions should be made
so that precautions may be taken to prevent or minimise the damage in the event of sudden rise
of water level in the river. Weather warning telegram from Indian Meteorological Department may
also be arranged so that the precaution may be taken in case of an expected cyclone which are
very frequent in summer months. Further, an anemometer may be installed at the site of work for
long triangulated spans.
(2) The following arrangements should be made before actual gartering work is started:
a) Plan the sequence of erection work.
b) Move the girder materials to the site by rail or road.
c) Make yard arrangements on one bank of the river or in a nearby station.
d) Arrange the plant and equipment necessary to carry out the work alongwith spares.
e) Test all the equipment to be used in the erection work.
f) First Aid and communication arrangement at site.
g) Arrange for consumable stores.
h) Arrange for necessary traffic blocks.
i) Arrange for a proper organisation with Supervisors, Skilled and Unskilled Staff.
j) Provide facilities for the large labour force that will be employed at site.
79
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
cranes and placed properly on the dip lorries.
viii) The cranes are released and moved on to one approach, at the same time, moving the dip
lorries loaded with load girders, in the same direction.
ix) Old girders are lifted from dip lorries, with the help of cranes and stacked by the side of the
track keeping them clear of infringement. The dip lorries are also removed from the track and
the block section is cleared.
b) A crane with long jib can directly place spans upto 12.2 m. over the piers straight away.
80
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
attached to the underside of the span with the help of clamps and the rails are duly greased
throughout the length to avoid excessive friction. The span is then pulled with the help of
a winch on the opposite side or a pulling tackle. As soon as the span arrives at the proper
position, it is jacked and the rail clusters and skid etc. removed and the span lowered on the
bed plates with felt packings. H.D. bolts are inserted and grouted after aligning the span.
The skidding method is not normally used where the ballast walls are high as this will involve
enormous jacking. This method is used when the girders are to be launched at or near bed
block level. (Annexure 6/8 a)
b) Where 18.3 m. plate girders are involved and water depth and velocity of flow is not much,
the work may be carried out by erecting one or two intermediate trestles in line with the piers
and abutments. The top of the trestles are adjusted to the top of bed blocks of piers and
abutments. Suitably designed rail clusters are laid and the spans are skidded as explained
earlier. (Annexure 6/8 c).
(2) Launching by dip lorry method:-
This is a safer, more convenient and quicker method for launching of multiple spans upto 18.3m.
a) In this method, a cluster of three rails, one on each side are pulled across the opening and
temporary track with wooden sleeper is laid. Distance pieces, clamps etc. are properly fitted
as suggested in the skidding process above. The fully riveted 12.2m span is then brought
onto the approach and one set of dip lorry on either end is inserted under it. The span is then
rolled over the temporary track laid on the rail clusters (Annexure 6/8 b). As soon as the
span comes in proper position, it is supported on jacks and the dip lorry and the rail clusters
are removed in phases. Finally the span is lowered on to the bed block with the jacks. In
case the ballast walls are built earlier, the clusters are laid on suitable wooden cribs. In this
case, the girders would have to be lowered for a considerable height.
b) This method can also be adopted for plate girders of more than12.2m span and where it
is not possible to erect intermediate trestles due to excessive height of the bed from the
rail level. However instead of rail clusters, RSJs 600 x 210 mm in duplicate duly fitted with
diaphragms are laid in the openings on either end by cantilever rolling method, spanning the
openings. These are braced with channel diaphragms out of channels 250 x 80 x 1320mm.
long at suitable intervals. Temporary track is then laid on these RSJ beams with the help
of wooden sleepers to coincide with the approach track. Fully rivetted plate girder span
mounted on sets of dip lorries is then rolled over this temporary track. As soon as the span
comes in position, it is supported on jacks, dip lorries removed, track dismantled and the
beams are shifted apart after removing diaphragms and the span lowered on the bed blocks.
(Annexure 6/9 a)
(3) Cantilever launching of spans by linking (coupling) and rolling:
An alternative method avoiding provision of staging under the span is to assemble the spans,
arrange them, one behind the other, link them up by temporary links and launch them together. In
such a case, the front portion of the girder acts as a cantilever till the nose tip reaches the support
at the other end. As such, it has to be designed to take the cantilever stress during launching. A
further improvement on this is to provide a launching nose of lighter construction and of adequate
length. The spans (12.2m or 18.3 m) to be launched on the bridge are assembled and rivetted up
in one line and linked up with the help of suitable splicing. A tie for the first and second span is fitted
to avoid unwanted deflection of the leading span. A suitable launching nose is attached in front to
reduce the cantilevering weight of the leading span. Rolling platforms are provided on each pier
and abutment under each girder of the spans. The spans are then pulled with the help of a winch
81
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
making use of ordinary rounds as rollers. As soon as the spans occupy the correct position, they
are jacked up and lowered on to the bed blocks after removing the tie members and the splices.
(Annexure 6/9/b)
(4) Launching of girders with the help of a BFR:
At locations where access to the new bridge is available by rail, the launching of girders upto 18.3
m with this method is ideal. In this method, the erection tackle consists essentially of a pair of 600
x 210mm joists. The entire beam balances about a central pivot which consists of 600 x 210mm
joists. The launching beam has a tackle at its balancing end, with a 3 sheaved pulley fixed on the
launching beam and 2 sheaved pulley at the point where the load is taken. There is no counter
weight as the advantage is taken of tare weight of the BFR itself. For the BFR to function as a
counter weight, bolts are provided between the winch end of the launching beam and the BFR.
With this arrangement, a completely assembled, rivetted and sleepered 12.2 m span can be lifted.
(Annexure 6/10 a).
(5) Erection with the help of launching pad:
The BFR method described above can be suitably replaced by a launching pad since the availability
of the BFR is rather difficult. The functioning of this launching pad is identical to that of the BFR and
consists of combination of grillage beams mounted on 4 half sets of dip lorries, forming a kentledge.
A loading trolley in the form of ‘A’ frame with 4 wheels (poney wheels of a steam engine) is provided
in the center as shown in Annexure 6/10 b. A suitable tie is also provided as in the case of BFR.
Kentledge of suitable quantity is provided on the grillage beams for additional safety. The launching
pad is loaded with suitable wedges and other safety appliances. The girder is then lowered with the
help of the winch on the bed blocks to rest on cross rails which are kept provisionally on the bed
blocks. The sling is then removed and the launching pad pushed back to lift second girder. In the
meantime already launched girder is slewed sideways to its correct position with the help of yale
pull. The second girder is then lifted and brought in the opening and lowered with the help of winch.
The sling is then removed and the launching pad pushed back. This girder is similarly slewed side
ways to its correct position. The bracings are then fitted, the cross rails are removed and the span
lowered on the bed plates with felt packings. (Annexure 6/10/b).
82
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
of starred angles forming a square section. The profile of the pier should be such that a platform
could easily be formed. A pair of trestles are fixed in the bed and a platform made between the pier
and abutment. This platform consists of cluster of 90 lbs or 52 kg rails. In the cross-wise direction,
sleepers can be provided. The new girders should then be assembled from this platform. Gantry
girders built up using mostly released steel, should be kept at 3.66 m centers. Steel cribs are
made on the abutments and first pier. The gantry girders should initially be brought on the one end
approach. Making use of pair of gallow trollies located on the erection platform , the gantries are
moved in place. With this gantries, a load can be picked up and moved along the axis of the girder
as well as at right angles. Thus the components of the main girders can be brought to any point on
the platform. After the first main span is assembled, riveted and the track fixed on it, the gantries
could be moved forward by supporting the forward end of the gantries on the gallow trollies located
on the platform of opening No. 2 and the end of the gantries on a dip lorry running on a new track
of span No.1 (Annexure 6/11a). This process is repeated for all spans.
627 End launching of open web girders with the help of launching nose
This method can be adopted for launching of open web girders when the number of spans are more
and the false work can not be erected in the bed. A launching nose fabricated with light sections is
connected to the main girder through a suitably designed temporary connection. The launching nose
can be made of unit construction members and is assembled on rolling arrangements. The girders
are temporarily connected one after the other to act as a counter weight. The whole assembly is
pulled from the far bank by winches and pulleys and wire ropes. Similar restraining winches are
connected at the rear of girder assembly to control the movement of the girders. As the launching
progresses and touching the first pier, the deflection can be neutralised by jacking up the nose and
providing adequate packing. The launching is continued till the main girders reach their respective
supports. The launching nose can then be dismantled and the girders disconnected from each
other. The girders are then lowered on to the bearings, already placed on the piers. (Annexure
6/12a).
83
CONSTRUCTION OF SUBSTRUCTURE AND SUPER- STRUCTURE INCLUDING ERECTION OF
GIRDERS
of girder starts from the abutment and the erection of members ahead is done by using a derrick
crane which travels on the top boom of the previously erected part structure. The first and foremost
is to design and fabricate a derrick crane with a jib of sufficient length, radius and capacity. The
derrick crane is fitted with suitable double flanged wheels, one set on either side, to work on the
track fitted on the top booms.
A winch is fitted to the rotating platform in the front to revolve the crane for various operations. The
rotating is done with the help of wheels, which are working on RSJs, in the circular beam. With the
help of winch, the platform rotates either clock or anticlockwise direction as desired. The jib can be
raised or lowered with the stay rope and the load is lifted by load line wire rope. (Annexure 6/12
b). Suitable arrangement can also be made to operate the crane electrically.
84
RIVERS AND FLOODS
CHAPTER VII
RIVERS AND FLOODS
85
RIVERS AND FLOODS
site, afflux noticed and past history of the bridge are to be taken into account. In fixing the danger
level, a margin of safety should be allowed taking into consideration the characteristics of the river
or stream such as, whether it is subjected to sudden flood or gradually rising floods and whether it
carries floatsam. Fixing of danger level at a higher level than necessary may result in unnecessary
restrictions to traffic and may lead to non seriousness with regard to implications of action required
in case of water level approaching or exceeding danger level.
(4) Danger level shall be the level which is lower of the following:
a) the level which provides adequate vertical clearances;
b) the level which provides minimum free board to approach banks and guide bunds, as
stipulated in clause 4.9 of Bridge Substructure Code,
c) the level of water which is likely to cause an unduly large afflux, say more than 0.5 m, which
may cause large scour endangering the bridge; and
d) the water level which if exceeded may cause excessive scour endangering the bridge.
(5) In cases, where there is no past history of damage or serious threat to the bridge, free boards are
adequate for approach banks and protection works, no excessive afflux say more than 0.5 m is
observed/ anticipated and no excessive scour endangering the bridge has occurred/been anticipated,
the broad guidelines for fixing Danger Level are given below:
a) Girder and Slab Bridges:
Waterway Clearance below bottom of girders(slabs)
i) <6.10m 150 to 300 mm depending on the span and site conditions
ii) >6.10 <12.2 m 450 mm
iii) >12.20 < 30.5 m 600 mm
iv) > 30.50 < 61.0 m 750 mm
v) >61.0 m 1200 mm
b) Arch Bridges:
i) For small arch bridges of spans less than 4.0m, the danger level shall normally be at
the springing level;
ii) For larger spans and for multiple span arches, the danger level shall be at 2/3rd rise
below the crown of the arch;
iii) Where higher HFLs have been recorded in the past, without any dangerous afflux
or scour, or damage to approach embankments, danger level may be raised suitably
at the discretion of Chief Bridge Engineer.
c) Box Culverts:
Danger level at the bottom of slab.
d) pipe Culverts:
Danger level at the top of inside of pipe.
e) Balancing Culverts and bridges:
Danger level at 50mm below top of pier/ abutments in case of culverts with girders and slabs
or the crown intrados of the arch.
(6) The values suggested in sub para (5) above are for general guidance and should be used where
specific guidelines have not been issued by the zonal railways based on the past experience and
86
RIVERS AND FLOODS
local conditions. Railways which have already issued guidelines may review the existing instructions
and supplement the same as considered necessary.
In case where danger to bridge has occurred or the bridge has been seriously threatened, even
though the water level was less than the danger level, the revision of danger level should be
considered.
(7) In case where floods higher than danger level have occurred several times in the past without
causing any damage to the structure, the desirability of revising the danger level may be examined.
(8) Fixing of the Danger level for any new bridge or any revision of the existing Danger level should be
done with the approval of the sectional Divisional Engineer/Senior Divisional Engineer Incharge,
who should record the reasons for revising the Danger level.
(9) All danger levels should be recorded in the bridge inspection register.
(10) Marking danger level:
The danger level should be marked on the abutments or on the first and last pier of the bridge.
In the case of long multiple span bridges, the danger level mark should be repeated suitably on
intermediate piers. These marks should be fixed on the upstream side of the bridge, conspicuously
visible to the inspecting officials, patrolmen and watchmen. The danger level should be marked
with a bright red band 5 cm wide centrally over a white band 10 cm wide for a length of 60 cms.
703A Continuous water level monitoring device shall be used on identified bridges.
87
RIVERS AND FLOODS
88
RIVERS AND FLOODS
“I certify that all monsoon reserve stocks as specified, have been recouped with the exception of
the following for which action has been taken as indicated below: ________________________
________________________________________________________________________
Date : Signature :
Designation :
(6) The annual return of pitching stone, boulder and monsoon reserve should be submitted by each
Divisional Engineer to the Chief Bridge Engineer by specified date after the monsoon. It should
be accompanied by a statement of training works added or abandoned during the year with
recommendation for reduction or increase to the Reserve”.
(7) Permanent remedial measures should be taken as soon as possible in every case and recurring
expenditure avoided or minimised.
(8) Attention to Paras 1125 and 1126 of Indian Railway Permanent Way Manual is drawn regarding
the other monsoon reserves.
89
RIVERS AND FLOODS
90
RIVERS AND FLOODS
and a register should be maintained as per proforma given in Annexure 7/1. In addition to
gauge and afflux readings accurate record of maximum flood levels and the rate of rise and
fall of flood levels must be recorded in the register.
b) Divisional and Assistant Engineers should ensure that gauges are erected and maintained
at all specified bridges both on the upstream and downstream side.
c) Levels painted on gauges should be accurate and all gauges must refer to the same datum.
Where gauges are painted on piers, these should be used only for the purpose of reporting
high flood levels at bridges and not for determining the afflux as it is liable to give incorrect
readings.
d) Afflux gauges should be fixed at a distance of about 30 metre upstream and downstream
of the bridge opening, preferably at near still water so that these are not affected by swiftly
moving currents.
e) Velocity of flow should be recorded using floats or current meter at all the specified bridges.
In non erodable beds, velocity measurements should be made avoiding the regions of
turbulent flow (adjacent to piers) and in case of erodable beds, the measurements should
be made near as well as away from the pier. When current meter is used necessary stagings
or platforms should be provided on the pier.
f) For gauging and velocity measurements, reference may be made to RDSOs Gauging
Manual.
(3) Cross section of rivers during floods:
For such bridges as specified, cross section diagrams of the river bed near about the high flood
level at specified locations on the upstream and downstream side should be prepared to a fixed
scale in the Divisional Engineer's office from particulars submitted by the Assistant Engineer and
copies sent to the Headquarters office by the prescribed date each year. The diagrams should
show the reduced levels of the summer water level, the highest known flood level and the year,
the underside of girders or springing of arch and the rail level. Five years records may be plotted
on each diagram in different colours for comparison. After one set is completed another set for
the next five years should be commenced with the same order of colours. A typical cross section
diagram is at Annexure 7/2.
91
RIVERS AND FLOODS
It is necessary to survey scour holes both on the upstream and downstream after monsoon to find
out the size and depth of the scour holes and the distance of the same from the foundation so that
remedial measures can be planned in time and the works executed before the onset of the next
flood season, as necessary.
A list of all bridges where scour holes exist should be prepared and copy sent to Chief Engineer
every year along with the flood report.
(3) Survey of the course of the river:
a) At each specified bridge, survey of the course of the river to a fixed scale should be made
soon after the monsoon extending to atleast 3 km upstream and 1 km downstream of the
bridge to afford general idea of the efficiency of training works. The distance may be suitably
modified keeping in view the past history at the discretion of the Chief Bridge Engineer. A
tracing of the survey will be prepared in the Divisional Engineer's Office and copies sent
to the Headquarters each year. For comparison, five years record may be plotted on each
survey plan in different colours. After a set is completed, the next set should be commenced
with the same order or colours. A typical survey plan of the course of the river is enclosed as
Annexure 7/3.
b) Where a river course runs parallel to the track with a tendency to encroach towards the
Railway embankment, the course of the river should be surveyed to get a general idea of
the rate of erosion. A danger line should be drawn in the survey plan to indicate as to when
remedial action such as holding the river edge away from the danger line or retiring the
Railway line has to be taken.
(4) Cross section of guide, subsidiary and retired bund:
At the end of the monsoon, cross sections should be taken at every 30 metres along each stone
protected bund or groyne and at every 15 metres apart round each stone armoured mole head by
probing, if necessary and particulars submitted to the Divisional Engineer. Cross sections should
be prepared in the Divisional Engineer‘s office to a fixed scale and copies sent to the Headquarters
office. These cross sections will indicate the position in the slopes and apron, the progress of the
apron pitching towards its ultimate launching position and will bring to light any defects that may
require attention in the dry season. For comparison, five year‘s records may be plotted in different
colours on the same drawing. After one set is completed, the next set should be commenced with
the same order of colours. A typical cross section record maintained is enclosed as Annexure 7/4.
712A 3-D River bed scanning technology shall be used for survey of river bed profile of identified bridges,
where the river is either having a tendency to meander or there is a chronic problem of aggradation/
degradation of river bed due to erodible nature of its bed material.
92
RIVERS AND FLOODS
of training and protection works of the bridges across them, if any, should be maintained by the
Assistant Engineer in a “Rivers and floods” register. This register may be in a manuscript form with
sufficient number of pages allotted for each bridge to cover ten to fifteen years and should contain:
a) Brief history of the bridge and protection works at and away from the bridge site with plans
and sections.
b) Condition of foundation and protection works with particulars of action taken on repairs
required.
c) Particulars of flood damage and remedial measure adopted with reference to Bridge
Inspection register. Blue prints of the cross section diagrams of the bed of the river, survey
plans of the course of the river and cross sections of bunds vide Para 711 and 712 should
be attached to the register for reference. Past register should be carefully preserved.
(2) The Assistant Engineer shall submit the register to the Divisional Engineer by a prescribed date,
indicating the point on which the orders of the Divisional Engineer are required.
The Divisional Engineer shall carefully scrutinise the register, examine such works as called for his
inspection, record his orders regarding the points referred to him and initial against every bridge
or kilometreage in token of his scrutiny. Points on which the Chief Bridge Engineer’s decision is
required shall be clearly indicated.
The register should then be sent to the Assistant Engineer for noting the Divisional Engineer‘s
Orders with instructions to return it within 15 days. The Assistant Engineer should extract the orders
issued by Divisional Engineer and arrange expeditious compliance.
The register should then be forwarded by a prescribed date to Chief Bridge Engineer who will
scrutinise the entries, issue orders regarding matter referred to him endorsing the register to that
effect, and return it to the Divisional Engineer. Subsequent action taken on Chief Bridge Engineer’s
notes should be entered in the register by the Assistant Engineer.
93
RIVERS AND FLOODS
94
RIVER TRAINING AND PROTECTION WORKS
CHAPTER VIII
RIVER TRAINING AND PROTECTION WORKS
95
RIVER TRAINING AND PROTECTION WORKS
load. Medium size boulders, gravel and coarse sand are generally found in the beds. The floods
are of flashy nature. These streams are highly erosive and the erosion proceeds through grinding of
bed load material during transport, formation of deep holes through whirlpools and plunging action
along with cliffs forming the banks, in the higher reaches. These actions go on widening the bed
and deepening the channel. The flow in the channel, except during highest stages, is insufficient
to transport the detritus which gets deposited blocking the original channel; another channel may
then be formed and in course of time the river bed may become a network of such channels with
islands in between. Such streams are called "Braided" stream (Annexure 8/1). All these channels
normally overflow during high floods and the river acquires very wide and shallow cross section.
The rivers in this reach are prone to progressively raise their beds by sediment deposition. Such
rivers are known as "Aggrading" type. In these case, the over bank spills increase year after year,
until occurrence of abnormal floods in a year, when sudden change of course may take place.
(2) Suggested protective measures:
It is not desirable to locate bridge in such reaches. However, if a bridge is to be provided, training
measures in the form of marginal bunds, extending right upto the high ground in the hills are required
to shift the point of aggradation downstream. To reduce the erosive action on the marginal bund
a) Suitable slope protection with boulders or concrete slabs,
b) Adequate toe protection in the form of two rows of in-situ concrete blocks or boulders in wire
crates and
c) Boulders in wire crates forming flexible type apron may be provided.
96
RIVER TRAINING AND PROTECTION WORKS
97
RIVER TRAINING AND PROTECTION WORKS
98
RIVER TRAINING AND PROTECTION WORKS
flow pattern.
The following types of river training works and bank protection measures are generally adopted on
the Indian Railways:
1. Guide Bunds;
2. Spurs (Groynes);
3. Marginal Bunds;
4. Closure Bunds;
5. Assisted cut offs;
6. Boulder Crates and
7. Sausage Crates.
99
RIVER TRAINING AND PROTECTION WORKS
and keeping reserve boulders for maintenance. From this consideration top width may be
taken between 6m to 9m, and side slopes may be taken as 2:1.
g) Side slopes of guide bund needs protection on following counts:-
i) Wave action on the upstream side
ii) Water current along the slopes
iii) Wind action
iv) Rain cuts/Rain water
Most common method is to provide stone pitching. It is necessary to provide 20cm to 30cm
thick graded filter below the pitching. Stone used for pitching is generally man size boulder
of 35 to 55kg so that they cannot be easily displaced by the current. For small works, one
stone thick pitching (25 to 30cm) should suffice. Gaps in between could be filled up by
smaller pieces.
In case of guide bund, the pitching should continue right up to the top of the formation for
the river side, including the curved head on both sides and tail head. For important rivers or
in case of large ponding etc, the pitching should be done on the rear side of the guide bund
also. For approach embankment, on the upstream side, the pitching should continue up to
the free board level which should be determined not only on HFL but also to take care of
velocity head (V2/2g), wave action etc. For the downstream side, pitching may be done up
to the water level based on hydraulic model study or general water level observed.
A good drainage is key for protection of slopes from rain cuts, particularly on high banks of
over 6m height. For this, longitudinal and cross drains should be provided.
Guide bunds and approach embankments particularly in khadir of the river must be constructed
in one go in one season. In case this is not possible, at least, a wedge size equal to angle of
internal friction of the old construction should be removed and the next construction should
be done with proper benching. For slope protection and apron, an overlap may be provided.
h) No spurs projecting from the guide bunds should, in any case, be provided.
j) For design and construction of guide bunds/launching aprons reference may be made to IS:
10751-1994 (Planning and Design of Guide Banks for Alluvial Rivers – Guidelines) and IRC:
89-1997 (Guidelines for Design and Construction of River Training and Control Works for
Road Bridges).
k) A typical lay out of a guide bund is shown in Annexure 8/4.
(3) Apron Protection for Guide Bunds :
a) Apron is provided beyond the toe of the slope of the guide bund, so that when bed is scoured,
the scoured face will be protected by launching of the apron stone or wire crate containing
stone.
b) Following are the important details for design of apron:
i) Thickness of apron
Thickness of apron is governed by thickness of pitching on the slopes of the guide
bund (T). In case of straight portion of guide bund, the thickness of apron through its
width is generally kept as 1.5T. In case of curved portion of guide bund, the thickness
of apron is generally kept as 1.5T at the junction of apron with pitching on the slope
and the same is increased through its width to 2.25T at the end of apron.
ii) Level at which the apron is to be laid
100
RIVER TRAINING AND PROTECTION WORKS
101
RIVER TRAINING AND PROTECTION WORKS
driving wooden bullies or bamboos, filled in with brush wood, with sarkanda mattresses
or other suitable material. These are helpful in causing quick siltation due to damping of
velocity. They are useful when flood velocities are relatively lower and concentration of
suspended sediment load is heavy. They allow water to pass through. permeable structures
are discussed in detail in Para 811(5). Impermeable spurs are made of solid core, constructed
of stones or earth and stones with exposed faces protected by pitching. These spurs can
with stand severe attack better than permeable spurs.
ii) Spurs may be classified as (a) repelling (deflecting) (b) attracting and (c) normal (sedimenting).
Repelling (deflecting) spurs are those which incline upstream at an angle of 60 degree
to 70 degree to the river course and deflect the current towards the opposite bank. They
cause silting in still water on the upstream pocket. Attracting spurs incline downstream and
make the deep channel flow continuously along their noses. They cause scour just on the
downstream side of the head due to turbulence. The river flow is attracted towards the
spur. Normal (sedimenting) spurs are those which are built at right angles to the bank to
keep the stream in a particular position and promote silting between the spurs. They have
practically no effect on the diversion of the current and are mostly used for training of rivers
for navigational purposes.
iii) Spurs are also classified as full height spurs and part height spurs. Where top level is higher
than HFL, it is called a full height spur.
iv) Spurs are also constructed extending into the stream with a “T” head or hockey stick shaped
head, properly armoured to hold the river at a distance. A series of such spurs/groynes
correctly positioned can hold the river at a position away from the point intended to be
protected. The edge of the "T” head should be curved somewhat in the manner of a guide
bund to avoid swirls. Sketches of the various types of spurs may be seen in Annexure 8/5.
(3) Location and salient features of a spur/groyne:
i) The space between spurs or groynes generally bears a definite ratio to their length. The
common practice is to keep the spacing at about 2 to 2.5 times the length so as to effectively
protect the bank.
ii) If designed as a full height spur, care should be taken to see that spurs are built sufficiently
high so that they are not overtopped and out flanked by the current during high floods. Free
board of 1 metre is provided.
iii) The side slope of spurs are generally 2:1.
iv) The spurs should be anchored on to high ground.
v) The head of the spur is most vulnerable point for scour and should be well protected on
slopes by pitching and at toe by an apron designed for scour depth of 2.5 to 2.75 times Dlacey
at the mole head. For computation of Dlacey Clause 4.6 of IRS Code of Practice for the Design
of Substructures & Foundations of Bridges may be referred.
vi) Spurs should never be constructed at a point where severe attack is taking place but at
some distance upstream.
vii) Spurs/groynes should be used only in-situation where they are absolutely necessary.
viii) The design of spurs may be finalised preferably through hydraulic model studies.
ix) For design and construction of groynes (spurs)/launching aprons reference may be made to
IS:8408-1994 (Planning and Design of Groynes in Alluvial Rivers – Guidelines) and IRC:89-
1997 (Guidelines for Design and Construction of River Training and Control Works for Road
102
RIVER TRAINING AND PROTECTION WORKS
Bridges).
(4) Maintenance of spurs/ Groynes:
In all cases, satisfactory arrangement should be made for the maintenance of spurs/groynes by
providing access to them during all seasons of the year and keeping boulders as reserve.The
maintenance procedures specified for guide bunds apply equally to spurs/groynes also.
(5) Permeable Structures:
a) Permeable structures can be used either independently or with the support of other
impermeable stone structures or river training and bank protection measures. These
structures are easy to construct, use low cost locally available material and require limited
skill in construction. These are very handy in antierosion works during emergencies in
floods. These structures can also be used in areas where good quality stones are costly
and/or not available. Thus permeable structures are cost effective alternative to the river
training or antierosion works with impermeable spurs. Depending upon the purpose to
serve, the permeable structures are constructed transverse or parallel to the direction of
flow. Permeable structures serve one or more of the following functions:
i) Training the river along a desired course.
ii) Reducing the intensity of flow at the point of river attack.
iii) Creating a slack flow to induce siltation in the vicinity of the permeable structures and
in the downstream reach.
iv) Providing protection to the bank by dampening the velocity of flow along the bank.
b) The permeable structures can be classified as follows:
i) According to function served, namely, diverting and dampening, sedimenting.
ii) According to the method and material of construction, namely, bally, bamboo, tree and
willow structures.
iii) According to the conditions encountered, namely, submerged and nonsubmerged.
iv) According to the type of structure provided, namely, spur type, screen type or
dampeners (revetment) type.
c) The permeable structures are made up of different types of smaller units called elements.
Many elements, made up of bamboos, ballies, RCC poles etc. are arranged in specific
pattern and linked together to form a permeable structure. Different types of elements used
for making permeable structures are as following:
i) Porcupines – Porcupines are typically made up of bamboos/ballies, have cubical/
prism shaped box at the central portion with their legs extending in all directions. The
overall size is 2m to 3m. The central box is filled with stones for stability of individual
unit during floods. (Annexure-8/6 (a&b)).
ii) Cribs – This is a pyramid type of structure made up of bamboos/ballies with a box at
the bottom for holding stones for stability during floods. Size of the box is generally
square of size 2m to 2.5m at the bottom. Total height of the structure is 3m to 4m.
(Annexure-8/6 (c)).
iii) Bally frames - Permeable bally structures are made up of main skeleton of large
bamboos or ballies. Cross ballies are used for stability of the structure.
iv) Tree branches – Branches of trees or trees of short height are hanged from a wire rope
duly weighted with stones and are aligned as a spur projecting into the river. The wire
103
RIVER TRAINING AND PROTECTION WORKS
104
RIVER TRAINING AND PROTECTION WORKS
courses or cause other damages. The marginal bund should normally be built well away from the
active area of the river. The slope should be well protected by turfing. Where a marginal bund has
to be built in the active area of the river, it should be protected with pitching and apron. The earth
for the construction of marginal bund should preferably be obtained form the river side. The upper
end of the marginal bund should be anchored into high ground well above HFL. Marginal bunds
should be inspected every year along with the annual bridge inspection and necessary repairs
should be carried out before the onset of monsoon. Cattle crossing and rodent holes across the
marginal bund should be specially watched and deficiencies made good.
105
RIVER TRAINING AND PROTECTION WORKS
106
RIVER TRAINING AND PROTECTION WORKS
107
FABRICATION, ERECTION, INSPECTION AND MAINTENANCE OF OTHER STEEL STRUCTURES
CHAPTER IX
FABRICATION, ERECTION, INSPECTION AND
MAINTENANCE OF OTHER STEEL STRUCTURES
108
FABRICATION, ERECTION, INSPECTION AND MAINTENANCE OF OTHER STEEL STRUCTURES
109
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
CHAPTER X
INSPECTION AND MAINTENANCE OF
TUNNELS AND DEEP CUTTINGS
PART A - TUNNELS
110
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
111
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
inspection of these cuttings should be carried out as detailed in Paras 1010 to 1012 later in this
Chapter.
(2) Portals at either end: During inspection it should be checked as to whether there are any signs
of slips in the slopes above the portals; whether the masonry is in any way cracked, shaken or
bulging and signs of movement are apparent. "Catch-water drains above the portals should drain
away and not be allowed to percolate into the tunnel or behind the portal masonry.
Trees leaning or hanging on the slopes above the portals should be cut and cleared. Loose boulders,
if any should be removed.
(3) Section of tunnel in relation to moving dimensions: It should be checked as to whether the dimensions
of the tunnel section on straights and curves conform to the diagrams given in the Schedule of
Dimensions.
Stagings mounted on mobile units will be helpful to check the profile.
(4) Tunnel walls and roofing :
a) Lined section: During inspection it should be ascertained whether the lining is in a satisfactory
condition. Seepage through joints in the masonry should be looked for.
Doubtful masonry should be tapped to detect 'drummy' places.
Cracks in the masonry should be marked by red paint, dated tell- tales placed at their
extremities and serially numbered to detect extension.
Pointing of the masonry should be examined for its condition.
b) Unlined Sections: The unlined portions should be examined to find out whether they are
sound.
Doubtful places, such as loose projections should be tapped and identified.
(5) Drainage: The drainage arrangements inside the tunnel and upto the outfall should be inspected. It
should be ensured that the side drains are adequate and function satisfactorily. The drains should
be periodically cleaned.
(6) Tunnel refuges: It should be checked up as to whether these are well maintained and free of
vegetation and other growth.
(7) Ventilation shafts / Adits : It should be ascertained whether these are adequate and maintained free
of vegetation and other growth. For tunnels more than 200m long, level of pollution and temperature
condition should be enquired from the gang and Keyman working in that location of tunnel keeping
in view passenger comfort and working conditions for working inside the tunnel.
(8) Lighting equipment and special tools : The lighting equipment and special tools where supplied
should be in a state of good repair.
Sufficient spare tools should be stocked.
(9) The Track : The track should be examined for good line and level including the approaches.
Rails, sleepers and fastenings should be particularly examined for corrosion, inside the tunnels.
Level pillars and reference marks indicating the correct level and alignment shall be checked
periodically. Renewals should be carried out as and when required on high priority.
112
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
113
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
system. Maximum temperature of air inside tunnel needs to be limited to 500C considering
passengers and workmen comfort.
TABLE 10.01
THRESHOLD LEVELS FOR POLLUTANTS INSIDE TUNNELS
Pollutant Gas 8 hours exposure values 15 minutes exposure values*
CO 50 ppm 400 ppm
NO 25 ppm 35 ppm
NO2 5 ppm 5 ppm
CO2 5000 ppm 18000 ppm
SO2 5 ppm 5 ppm
* These values are from the consideration of passengers comfort and shall depend upon the length of
the tunnel and speed of the train.
iv) Types of Ventilation Systems:
The ventilation in a tunnel can be achieved by:-
a) Natural Ventilation :
When a train traverses inside tunnel at a relatively high speed and ratio of train frontal area
to tunnel cross section is of the order of 0.5 to 0.6, it induces considerable air flow inside
tunnel. This type of ventilation is called as natural ventilation. The amount of induced air flow
will depend upon orientation of tunnel and atmospheric pressure difference between inside
and outside the tunnel. Quantum of induced air flow will be more in tunnels laid parallel to
prevailing wind and having exposed approaches as compared to tunnels sheltered from
prevailing wind. Thus this aspect needs to be considered at the time of deciding orientation
of tunnel. However limitation imposed by terrain and track geometry parameters may not
make it feasible in every case. If length of tunnel is small, the induced air flow may be
sufficient to keep the pollutants concentration and rise in temperature inside tunnel, within
permissible limits. In such case there may not be any necessity for provision of artificial
ventilation.
b) Artificial Ventilation:
In long tunnels induced air flow due to train movement is not sufficient to keep concentration
of pollutant gases under permissible limit inside tunnel. In such cases artificial ventilation may
have to be provided by means of provision of ventilation shafts with or without provision of
electric fans, with suction and delivery arrangement. Where provision of shaft is not feasible,
longitudinal ventilation with the help of an axial blower fan at the portal supplemented by
auxilliary fan of smaller capacity, spaced at suitable intervals along the length of tunnel may
be considered.
v) Design of Ventilation System of Tunnels
(i) The essential requirement of a ventilation system of tunnel are as under:
(a) It should ensure, sufficient airflow relative to moving train, to keep the concentration of
pollutant gases inside tunnel within permissible limilts.
(b) lt should ensure suffcient air flow to prevent locomotives from over-heating and to
keep thermal effects within desirable limits.
(c) It should ensure that pressure transient are within acceptable limits.
114
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
(ii) The amount of air flow and type of ventilation arrangements required depend upon the level
of concentration of pollutants and maximum temperature likely to be attained inside tunnel
due to movement of trains. Level of concentration of pollutants and maximum temperature
likely to be attained inside tunnel depends upon the following factors:
i) Type of locos.
ii) Gradient inside tunnel
iii) Length of train
iv) Speed of the train
v) Time interval between two trains
vi) Ambient temperature
vii) Length of tunnel
viii) Cross section of tunnel
ix) Direction of prevailling winds etc.
(iii) As large no. of factors are involved, it may be difficult to estimate pollutants concentration
& maximum temperature likely to be attained analytically. Thus mathematical modeling
and simulation studies are necessary for design of ventilation system. As factors governing
designs of ventilation system vary considerably from site to site, therefore design for
ventilation of each tunnel has to be developed separately.
(iv) Normally on single line sections, tunnels having length upto 2 kms, may not require provision
of artificial ventilation but it should be ensured that levels of concentration of pollutants
during passage of trains are not likely to exceed threshold levels. Tunnels having length
more than 2 kms may require provisions of artificial ventilation, by means of shaft with or
without provision of fans, depending upon results of simulation studies."
1008 Leakage in tunnels and methods of correction
(1) General :
1.1 Water leakage occurs in most of the old tunnels. It is one of the most aggravating and
difficult problems detrimental to tunnel linings and contributing to muddy track.
1.2 Water leakage usually occurs near the portals or where the depth of cover is less. Underground
streams or springs may contribute to leakage anywhere in the tunnel. Water following an
impervious strata of material may also seep out.
1.3 Leaks generally occur at construction joints; cracks that have developed in the lining, honey
combed sections of concrete and joints of brick or stone lining. Seepage in brick lined tunnels
may be examined carefully as they may cover extensive area.
1.4 Weep holes often fail to function because of their small diameter or their being blocked by
mineral deposits or talus piling up at the back of the wall. This holds up the water behind the
lining which is relieved by the development of seepage and leads to leakage through the
tunnel lining. Old shafts used in construction may be source of seepage of water.
(2) Correction of leakage in tunnels:
2.1 For masonry lined tunnels it is best to bring the water through proper drains into the ditch
rather than try to seal the water at the back of the tunnel lining. Attempts should be made to
open existing weep holes and drains. However, where this is not feasible, new weep holes
and drains should be made.
115
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
Holes should be drilled through the tunnel lining at the wet areas to tap the water.
2.2 The holes should be drilled as near the drain level as possible, depending on the height of
the seepage points and spaced at suitable intervals.
2.3 Construction joints or cracks where seepage is light may be sealed by chipping the crack in
the form of a "V" and caulking with lead wool and by guniting.
2.4 Where seepage in joints or cracks is too great to seal or a definite leak occurs, water should
be carried in recessed drain to the side drain level. A series of holes should be drilled in the
recessed drain channel through the tunnel lining to offer an easy path for escape of water.
The face of the drain may be of brick or shotcrete.
2.5 Very often, leaks around the portals are due to poor drainage over the portal. This may
be due to clogged portal drains and/ or weathered material forming a catch basin over the
portal. Generally it is best to open portal drains and clear the drainage ditches above the
portal.
PART B - CUTTINGS
1010 General
A register for inspection of cuttings should be maintained in the proforma given in Annexure 10/2.
Separate page will be maintained for each cutting. This register should be sent to CBE for his
perusal every year.
116
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
117
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
vi) The condition of retaining walls, weep holes and other protection/strengthening measures.
Instructions as given in Para 1014 and 1015 shall be followed for inspection of Boulder nets
and Rock Bolts respectively.
vii) Availability and condition of warning systems / boards and trolley refuges.
118
INSPECTION AND MAINTENANCE OF TUNNELS AND DEEP CUTTINGS
119
INSPECTION OF BRIDGES
CHAPTER XI
INSPECTION OF BRIDGES
120
INSPECTION OF BRIDGES
121
INSPECTION OF BRIDGES
work, the general condition of the girders and bearings should be examined paying special
attention to places liable to corrosion and stress concentration (in welded girders) and the
condition of paint.
e) Scaffoldings or cradles as may be required for the purpose of detailed inspection should be
arranged.
(2) Bridge Inspection Register :
The Assistant Engineer should record the results of his inspection in ink in the Bridge Inspection
Register, separate registers being maintained for major and minor bridges. For each one of the
important bridges and river training works there to be specified by the Chief Engineer, a separate
Bridge Inspection Register should be maintained.
(3) a) Important bridges are those having a linear waterway of 300 metres or a total waterway of
1000 Sqm or more and those classified as important by the Chief Engineer / Chief Bridge
Engineer, depending on considerations such as depth of waterway, extent of river training
works and maintenance problems.
b) A major bridge is one which has a total water way of 18 linear metres or more or which has
a clear opening of 12 linear metres or more in any one span.
c) Bridges which do not fall in these classifications are termed as minor bridges.
(4) Proforma of Bridge Inspection Register.
a) Important and major bridges :
These bridge registers will contain :
i) instructions to the inspecting official (Annexure 11/3),
ii) index of bridges (Annexure 11/4),
iii) general key plan (Annexure 11/5)
iv) classification of structures (Annexure 11/6)
v) inscription plaques on bridges showing nature and depth of foundation (Annexure
11/7)
vi) proforma for recording details of each bridge (major and important) (Annexure 11/8)
vii) proforma for entering condition of each major and important bridge at the time of
inspection (Annexure 11/9)
b) Minor bridges :
i) these bridge registers will contain items a (i) to (v) above,
ii) proforma for recording the details of each bridge (Annexure 11/10)
iii) proforma for entering the condition of each minor bridge at the time of inspection
(Annexure 11/11)
Notes:
* Details shown in sub-para (a) item (i) to (v) and (b) item (i) should be printed in the top leaves
of the register.
* Sufficient sheets should be allotted for each bridge so that the register may contain the
record of inspection over 10 to 15 years.
* All Old bridge registers must be preserved as a permanent record for reference.
(5) Instructions for making entries in the register.
122
INSPECTION OF BRIDGES
a) Under each heading entry should state clearly whether the previous year's notes have been
attended to.
b) Entries in the column "Condition of the bridge at the time of inspection" should be in the
nature of statements. A defect once mentioned should not be omitted in future years unless
it has been eliminated by rebuilding or strengthening or repairs, in which case a note should
be made to that effect. In addition, details as described in Para 1103 relating to Numerical
Rating System, should be recorded in the relevant columns in the register.
c) In the column "Action taken" the remarks should be in the form that orders have been
issued, e.g.
i) Permanent Way Inspector instructed to renew sleepers,
ii) Bridge Inspector instructed to carry out painting.
d) No bridge which is cracked or in which the masonry is shaken, crushed, bulging, deteriorating
or showing signs of movement or in which the steel work is affected should be described as
"sound".
e) A bridge is to be noted as "requiring special repairs" when the whole or any part of it has to
be rebuilt or undergo heavy repairs.
(6) Numerical Rating System (NRS) :
a) The "Numerical Rating System" for bridge inspection assigns a "Unique Rating Number"
(URN) to represent the physical condition of a bridge. Lower the URN more serious is
the deteriorated condition of a bridge. The system thus helps in identifying progressive
deterioration in the condition of a bridge. URN can be stored in a computer for quick retrieval
and fixing priorities for repairs or rehabilitation.
b) The URN of a bridge is arrived at based on the condition of components and a "Condition
Rating Number" (CRN) assigned to each of them. The various components of a bridge in
sequence, are :
i) foundations and flooring, if any,
ii) masonry / concrete in substructure,
iii) training and protective works, if any,
iv) bed blocks,
v) bearings and expansion arrangements,
vi) superstructure - Girders / Arch / Pipe / Slab etc.
vii) track structure.
c) The CRN is allotted to each of the above components based on their condition at the time of
inspection, using the following scale:
Condition Rating Condition of bridge component
No. (CRN)
1 A condition which warrants rebuilding / rehabilitation immediately
2 A condition which requires rebuilding / rehabilitation on a programmed
basis
3 A condition which requires major / special repairs
4 A condition which requires routine maintenance
123
INSPECTION OF BRIDGES
5 A sound condition
6 Not applicable
0 Not inspected
d) When any component in a bridge is more than one in number CRN is assigned to
each of them and the lowest value used. For example, if a bridge has five piers and
two abutments, and these are given the CRN of 5,4,3,2,5,5,4 then the CRN for the
substructure component of the bridge would be minimum of the above, i.e. 2.
e) If in any bridge, one or more components do not exist, the CRN for such components
shall be shown as 6.
f) From the CRNs for different components of a bridge, an overall Rating Number (ORN)
for the bridge as a whole is then given. The ORN is the lowest of the seven CRNs of a
bridge, except 0.
g) For a major bridge, the URN would comprise of eight digits, the first digit indicating the
ORN and the following seven digits the CRNs of each of its above seven components
in sequence.
For example URN 20362544 of a major bridge would indicate the following:
Digit No. Value Indication
1 2 Whole bridge or one or more of its components require (s) rebuilding / rehabilitation
on a programmed basis
2 0 Foundation and flooring were not inspected
3 3 Substructure requires major / special repairs
4 6 Not applicable, i.e. the bridge does not have any training or protective works
5 2 Bed blocks are cracked and shaking
6 5 Bearings and expansion arrangements are in sound condition
7 4 Superstructure requires routine maintenance
8 4 Track structure requires routine maintenance.
h) URN of a minor bridge shall be represented by its ORN only, i.e. by a single digit to indicate
its overall condition using the guidelines contained in Sub-para (c).
j) The physical condition of a road over bridge is to be represented as for a rail bridge.
k) The CRN of different components of a bridge as evaluated above shall be entered in the
"Box" to be provided in the register at appropriate places.
(7) Follow up of Inspection Notes by Assistant Engineer.
a) The Assistant Engineer should make an extract of the orders under "Action taken column"
and send the same to the Permanent Way Inspector / Inspector of Works / Bridge Inspector
concerned for compliance with a copy to the Divisional Engineer. Arrangements should
be made to carry out the repairs as soon as defects are noticed without waiting for the
completion of inspection of other bridges.
b) If it is not possible to make complete inspection of any bridge owing to the presence of
standing water, the fact should be so stated. The inspection of foundations should be made
no sooner water dries up or conditions make it possible to do so and results recorded as
supplementary entries in the register.
c) All the bridge components which have Condition Rating Number (CRN) as zero should be
124
INSPECTION OF BRIDGES
1104 By Divisional Engineers and Chief Bridge Engineers/Nominated SAG officer in Headquarters
(1) Details of inspection :
a) The Divisional Engineer shall carefully scrutinise the Assistant Engineer's Bridge Inspection
Register and inspect all important bridges and such bridges as called for his inspection.
He shall record his orders regarding the points which require as decision by him and initial
against every bridge in token of scrutiny.
b) He will complete his inspections and scrutiny by a specified date.
(2) Certificate by Divisional Engineer.
He should endorse on each register, below the Assistant Engineer's certificate as follows:
"I have personally scrutinised this register and inspected all Important bridge and bridges referred to
me and have issued orders regarding all essential points requiring a decision by me. The following
points are submitted to Headquarters for orders.
Bridge No (s) require rehabilitation.
Bridge No (s) have ORN 1 or 2
Bridge No (s) have one or more
CRN as 0 for more than one consecutive inspection
(3) The Divisional Engineer shall inspect all those bridges for which the ORN is 1, 2 or 3 and revise/
confirm the rating given by the ADEN. Bridges having ORN 1or 2 after review shall be inspected
more frequently at various levels and to be placed under close watch. The schedule and level of
inspection of such bridges shall be decided by the Chief Bridge Engineer depending upon severity
of the defects noticed.
(4) Action by Divisional Engineer: He should then send the register to the Assistant Engineer for noting
his orders with instructions to return them within ten days. The Assistant Engineer should then
extract the orders issued by the Divisional Engineer, intimate the same to the Inspectors concerned
and ensure expeditious compliance.
(5) Scrutiny by Chief Bridge Engineer/Nominated SAG officer in Headquarters and action thereon:
The registers should then be forwarded by the Divisional Engineer to Bridge Branch in Headquarters
125
INSPECTION OF BRIDGES
by a specified date. All the registers of major and important bridges sent by divisions should be
examined by CBE. The minor bridge registers sent by a division may be examined by a SAG officer
in Headquarters nominated by PCE for this purpose. Chief Bridge Engineer/ Nominated SAG officer
in Headquarters will issue orders regarding matters referred to them duly endorsing the registers
to the effect. However, observations of inspecting officers in respect of minor bridges which have
been assigned ORN as 1, 2 or 3 and cases where bridge matters are referred by DEN/Sr. DEN
to Headquarters should also be seen by CBE after examination by nominated SAG officer. The
registers should then be returned to the Divisional Engineer latest by a specified date. Subsequent
action taken on the nominated SAG officers and Chief Bridge Engineers Orders should be entered
in register by the Assistant Engineers.
126
INSPECTION OF BRIDGES
127
INSPECTION OF BRIDGES
128
INSPECTION OF BRIDGES
129
INSPECTION OF BRIDGES
g) In case of composite girders the junction between concrete slab and steel girder shall be
inspected for:
i) shear connector and girder connections,
ii) any vertical separation between girder and slab and also the critical locations mentioned
in sub-para 5(f) as applicable to the composite girder.
h) In the case of overstressed girders, the joints where the stresses in rivets in shear and
bearing as per stress sheets are higher than the permissible working stresses should be
examined.
(5) (i) In case of girders having High Strength Friction Grip (HSFG) Bolts:
i) Inspection : The inspection of HSFG bolts shall be done visually for broken and loose bolts.
Hitting HSFG bolts to check looseness is not allowed. Looseness of bolts shall be seen
by rust appearing beneath the bolt head/washer/nut etc or marks left by water or apparent
relative movement between the steel parts joined by the HSFG bolts. The broken/loose bolts
if any, shall be marked by a round circle all around and shall be replaced expeditiously by
new HSFG bolts of same specifications properly tightened Retightening of loose bolts found
during inspection is not allowed in any case.
ii) Use of HSFG bolts for repair/rehabilitation works: Where any girder component/ joint is to be
replaced, HSFG bolts shall be used as follows:
a) Complete joint shall have HSFG bolts. HSFG bolts cannot be used for replacement of
isolated loose rivets.
b) Proper surface preparation shall be done and joint design shall be done based on
design provisions as per Para 7.12 of Steel Bridge Code. Particular care shall be
taken regarding use of appropriate slip factor for the surface preparation done.
(6) The condition of steel work :
a) Action may be taken to ascertain whether the condition of paint is satisfactory and that no
corrosion is taking place.
b) The following part of steel work which are prone to corrosion should be specially examined.
i) where water is likely to collect or parts where alternate wetting and drying can take
place,
ii) where longitudinal timbers are carried in channel stringers and in the troughing of
ballasted deck,
iii) steel work of girders and the under side of over bridges which are liable to corrosion
by the action of fumes from engines and whether they are protected by smoke guards,
iv) seatings of wooden floors or treads of foot over bridges,
v) steel column footings of over bridges where buried in ground,
vi) around bearings of girders where debris can collect,
vii) inaccessible parts of structures like the inside of box girders with insufficient clearance
between the flanges and behind bends of joggled stiffeners.
c) It is difficult to detect cracks in steel work as they are likely to be covered by a film of paint
or corrosion and a careful inspection is necessary for their timely detection.
Locations which must receive attention are:
i) roots of flanges and angles where defects in rolling can initiate cracks,
130
INSPECTION OF BRIDGES
131
INSPECTION OF BRIDGES
g) Track on approaches :
The following points need attention, while inspecting the approaches of the bridge:
i) track geometry on the approaches should be maintained to the best possible standards,
ii) rail joints should be avoided within three metres of a bridge abutment,
iii) the condition of the ballast wall should be checked,
iv) full sections of ballast should be maintained for atleast 50 metres on the approaches.
This portion of the track should be well anchored.
h) Rail Joints: It should be checked weather any rail joint is existing on girder bridges of 6.1m
span and less and on arch bridges having insufficient cushion.
(8) Trolley and safety refuges :
Trolley refuges should be checked to ascertain:
a) Whether these are structurally in good condition.
b) Whether they have been provided :
i) on bridges with main span of less than 100 metres, at every 100 metres,
ii) on bridges with main spans of 100 metres and more, a refuge over each pier.
(9) Foot paths :
a) To ascertain whether the foot paths are properly supported.
b) To check up whether all girder bridges situated within station limits are provided with foot
paths for the convenience of the railway staff.
c) Whether long unballasted girder bridges located between stations are provided with foot
paths for the convenience of Engineering staff.
(10) Painting, marking HFL and Danger level, providing foundation particulars and bridge name boards
: It should be ascertained whether:
a) The date of last painting has been conspicuously painted on the girder and recorded in the
Bridge Inspection Register.
b) The Highest Flood Level and the year in which the flood had occurred has been marked and
recorded in the Bridge Inspection Register.
c) The danger level has been fixed and marked on the pier/ abutment as envisaged in Para
703 and recorded in the Bridge Inspection Register.
d) The direction of the flow has been distinctly marked on the abutment or pier.
e) The plaque showing particulars of foundation have been fixed over every abutment and pier
in accordance with instructions in Annexure 11/7.
f) Name boards have been fixed at either approach of important bridge.
g) The Full Supply Level (FSL) has been marked distinctly at all canal crossings in the same
way as the HFL for other bridges.
h) The Bridge Number Tablets have been provided on the parapet walls of bridges as per
Annexure 2/1.
j) The flood gauges have been provided at important bridges for recording flood levels and
afflux. Any increase in HFL during the previous monsoon should be reported to the Divisional
Engineer.
132
INSPECTION OF BRIDGES
133
INSPECTION OF BRIDGES
(x) To check up whether height gauges are provided as per drawings approved by
Railway/RDSO in approaches of ROB Structures (Steel/RCC/PSC etc.) having top tie
members.
b) Road under bridges:
i) to check up whether height gauges are provided,
ii) to check up whether the bottom of girders have been covered by suitable and approved
means to prevent droppings, falling from passing trains on road users.
(15) Concrete Bridges :
a) The condition of bed blocks and bearings, wherever provided should be checked, items of
inspection being the same as for steel girders.
b) The camber of prestressed concrete girder should be checked by BRI within one year of
installation and once in 5 years afterwards by any reliable method and recorded in Annexure
11/2a. One method which can be adopted for spans upto 30 meters is indicated in Annexure
11 /14. Alternatively the camber can be recorded by using a leveling instrument or theodolite.
The points where the camber is measured should be clearly marked on the underside of
the girders so that the readings taken on different years are comparable. While recording
camber, temperature should also be recorded and successive readings should be recorded
at about the same temperature. Progressive loss of camber is an important indication of
deterioration in the condition of bridge.
c) i) The surface of concrete should be checked by a magnifying glass for any cracks.
ii) The location, width and length of crack, type of crack (longitudinal/transverse/
horizontal/vertical/diagonal) whether it is active or dormant and its behavior under live
load should be carefully noted and documented. Sketches, preferably photographs
should be included. The observation of earlier inspection should be compared for the
purpose of determining whether the crack is developing or otherwise. Efforts should
be made to determine the probable cause of the cracks.
iii) While inspecting one should look for diagonal cracks in the web of main girders near
the support, flexural (vertical) cracks especially in the area of tension steel, cracks
near the bearings and longitudinal cracks at supports of slabs or beam near junction
of main girder with deck slab and at the diaphragms.
d) While checking the PSC girders for cracks particular attention should be paid to the
bearing area, end blocks, anchorage zone, support of main girders, web near girder ends,
diaphragms, junction (interface) of diaphragms with web and at junction of main girder with
deck slab.
e) It should be checked whether sufficient depth of ballast cushion exists under the track
sleepers. The deck slab should be examined after clearing the ballast for any signs of
cracking/disintegration and to see whether there is dampness and whether drainage
arrangement is functioning.
It should also be checked as to whether water proof layer, if provided is intact.
f) It should be examined whether rust streaks / stain marks are visible parallel to reinforcement;
spalling and presence of rust streaks are indicators of corrosion.
g) It should be checked whether there is spalling, caused by separation of the concrete from the
reinforcement. In such cases it should be ascertained as to whether the steel is corroded by
exposing the reinforcement. The location, depth and area/size of spalling should be noted.
134
INSPECTION OF BRIDGES
h) It should be examined whether there is scaling i.e. the gradual and continuing loss of surface
mortar and aggregate over an area. Location, area involved and character of scaling should
be recorded.
i) In case of PSC girders, measurement of loss of deflection should be done. Deflection
measurement should be at centre upto 20m span and at centre & quarter points for spans
more than 20m. Deflection measurements would be entered in column 8 of Annexure 11/9.
j) It should be checked whether there are signs of disintegration of concrete due to poor
workmanship, weathering action, attack by chemicals, etc.
k) Seepage, leakage and efflorescence should be looked for.
(16) Health Monitoring of Very Important Bridges:
Health monitoring of very important bridge should be done periodically by an independent agency.
Health monitoring will include corrosion monitoring, deterioration of material, system damage,
retrofitting, etc. The periodicity of health monitoring is recommended as given below.
Aggressive Environment Other than Aggressive
(Extreme, Very Severe & Severe) Environment (Mild and Moderate)
First Survey 5th Year 5th Year
Subsequent Surveys Interval At 5 years interval At 10 years interval
135
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
CHAPTER XII
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
c) Plant and machinery obtained against sanctioned Officer nominated by the Chief Administrative
works of the construction organization Officer (Construction) /Chief Engineer
d) Plant and machinery obtained against sanctioned Officer nominated by the Chief Engineer.
works of open line.
Note: Provision of this chapter will not apply to plant and machinery used for mechanical laying and
maintenance of track.
(3) Machinery and plant register.
A machinery and plant register should be maintained by the custodian of the equipment. The
machinery and plant register should be maintained in the following proforma:
Sl. Description Maker‘s Maker‘s No, Year of Purchase Machine/ Remarks
No. of the Plant name Specification, type, Purchase cost Plant No.
Capacity, etc. alloted
1 2 3 4 5 6 7 8
136
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
acetylene.
ii) Heavy plant Air receivers
Blocks pulley differential Boilers of all types
Crab
Cranes steam or diesel upto 5 tonne Dredgers
Gantries for girder erection Jacks, screw and hydraulic type,
Jolly boats
Lathes of all description
Machines drilling, grinding, planing, sawing and shaping plant boring
pumps and pumping plant of all description pile driving sets, stone crusher,
sling chains certified, shakles tested and certified, winches and Hoists,
iii) Special plant
a) Cranes steam or diesel above 5 tonne, service girders (spans) and steel work
such as CC crib, trestles etc. for emergencies.
b) Engineering plant reserve should also include
i) Small tools and stores likely to be required in an emergency.
ii) Materials required for maintenance and overhauling of plant and tools.
c) The Chief Engineer may include certain items not shown in the above lists if found
necessary.
(3) Instructions regarding custody, receipts, issue and accountal of Engineering plant reserve are
contained in Chapter XIX of the Indian Railway Code for the Stores Department.
1204 Plant and machinery procured for works against specific sanction/projects
(1) In the case of plant and machinery procured for sanctioned works including track renewals, a yearly
balance return should be submitted by the Executive to the Chief Engineer. A record should also
be kept in the same form by each Assistant Engineer or supervisor of all plant and machinery in
his custody.
(2) Proper Accounts of plant and machinery issued for use by the subordinates of the sub-division
or temporarily lent to contractors, as well as of those articles lent to local bodies and other under
competent authority should be kept in a manuscript register showing:
i) the person to whom lent
ii) description of items lent
iii) date of issue, and
iv) date of return.
137
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
These accounts should be reviewed periodically with a view to ensure that items are returned
without unnecessary delay and in good condition. This applies also to plant and machinery sent out
for repairs. On completion of works, a review should be made of the available plant and machinery
and action taken as indicated in Para 1205.
138
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
139
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
Depot Foreman.
c) While working at site, requisitions for spare parts for plant, irrespective of cost, in the event
of such parts needing replacement may be forwarded directly by the Inspector in charge to
the Depot Foreman for compliance.
In the event of failures, the officials at site may send pneumatic or small hand tools direct
to the plant Depot for exchange along with Issue Notes for the items being returned and
requisitions for the items required.
d) In the event of an emergency such as an accident or breach, the Depot Foreman of the
Engineering Reserve plant Depot shall supply plant and staff as required or message from
the official at site.
140
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
should be prepared for each Division or Department separately by the Depot Foreman
and sent to the Accounts Department within the first week of the following month, a
copy being endorsed to the Engineering Accounts Section.
141
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
The official in charge should bring to the notice of the Depot Foreman and the Divisional Engineer any
excessive consumption of fuel or lubricating oil and any defects in the running of the plant.
142
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
Stores in consultation with the Chief Engineer, after consideration of the original value of the plant,
the time which it has been in use and its condition at the time of return, as also the current purchase
price of new plant. In all cases of "Special plant" purchased for work a kind that is not frequently
undertaken, it should be seen that the value at which such plant is taken into the Engineering Plant
Reserve is as low as possible consistent with the possible price plant may fetch in the market. The
following formula may be used as a guide in all other cases. The value fixed should be entered in
all the copies of the Advice Note (S. 1539) and the several foils disposed of as usual.
Formula:-
The second hand value of a plant is equal to :-
N
R (R-S)
L
Where,
R is the present day price of a new plant; if this is not readily available, R may be estimated
taking the original price as a basis.
N is the age of plant
L is the average total life of the plant, and
S is the scrap value ( previously estimated)".
143
PLANT AND MACHINERY OF THE ENGINEERING DEPARTMENT
until it has been tested at site by hydraulic pressure by the Boiler Inspector and a fresh certificate
has been issued.
144
TRAINING FOR BRIDGE STAFF
CHAPTER XIII
TRAINING FOR BRIDGE STAFF
1301 Types of Training courses
Bridge staff need to be trained for their jobs both through theoretical class room training and practical
work at site using the tools, equipments and machinery. Training is a continuing process right from the
time of recruitment. Following four types of training courses should be organised in the Railway Training
Institutes.
i) Initial courses
ii) Promotional courses
iii) Refresher courses
iv) Special courses
Guidance may be taken from the booklet "Approved Modules for stagewise Training of Group "C" and
"D" staff of Civil Engineering Department'' issued in August 94 by the Ministry of Railways. The Railways
may frame their own course contents if such of those training modules for which the course contents
are not available in this booklet. However, broad guidelines for conducting these courses are given in
the following paragraphs.
145
TRAINING FOR BRIDGE STAFF
topics relevant to the trade for which the Artisan has been recruited.
(4) Initial course for Apprentice Bridge Inspectors :
a) This course will form a part of total one year training of the Apprentice Bridge Inspector and
will be held at the Zonal Training school. This Course will be of two months duration.
b) The class room lectures should include :
i) General working of the Railways and organisation of various departments,
ii) All establishment matters including extant rules and various acts viz. Workmen's
Compensation Act, Factories Act, Industrial Disputes Act, Payment of Wages Act,
Hours of Employment Regulations, Discipline and Appeal Rules, Labour Relations
and Permanent Negotiating Machinery, Rules regarding leave, salary and passes,
maintenance of service records, muster sheets, witnessing of payment to staff, casual
labour, etc.
iii) Duties of Bridge Staff,
iv) Inspection and maintenance of Bridge and steel structures including prestressed
concrete girders which should include overhauling, greasing of bearings, method of
greasing for all types of girders, rivet testing, method of sample testing, loose rivet
diagram, welding techniques, painting, preparation of steel surface for painting,
painting schedule of bridge girders and metallising.
v) Maintenance of Bridge Inspection Register and other registers,
vi) Safety First Rules for protection of staff working on bridges and structures and for
ensuring safety of travelling public and railway property,
vii) General Rules and Subsidiary Rules which should include basics of signalling, train
running including essentials of Absolute Block System,
viii) Schedule of maximum and minimum dimensions,
ix) Track protection rules,
x) Rules for Trollies and Lorries - working of,
xi) Actions during accidents, breaches and emergencies and restoration of through
running,
xii) Procedure of testing new design of plate and PSC girders and obtaining CRS sanction
(Safety Certificate),
xiii) Rebuilding of bridges and changing of bed blocks including temporary arrangement,
xiv) Inspection and maintenance of turn table,
xv) Bridge Rules and General design practices, Specifications for steel - MS, HTS, etc.
xvi) Acquaintance with rationalised steel section available in the market alongwith their
sectional properties, standard bridge spans with their dimensions and schedule,
xvii) Erection of Bridge Girders and Calendar Hamilton spans and other steel structures,
formulation of launching schemes and field organisations,
xviii) Anticorruption, Public relations, Civil duties, labour organisation and leadership,
Incentive,
xix) Fabrication of bridge girders and other steel structures such as platform shelters,
foot over bridges, tank staging, steel cribs, gantries, overhead cranes, turn tables,
Microwave towers etc.
146
TRAINING FOR BRIDGE STAFF
147
TRAINING FOR BRIDGE STAFF
148
TRAINING FOR BRIDGE STAFF
149
BOOKS OF REFERENCES
CHAPTER XIV
BOOKS OF REFERENCES
1401 Books of references listed in Annexure 14/1 and other publications from RDSO and IRICEN /Pune
including Technical Monograms considered essential should be supplied to the Officers and the
Bridge Inspectors of each Division.
The Chief Engineers and the Divisional Engineers offices should be equipped with adequate number
of copies of each publication. The publication should be accounted in the dead stock register.
Officials for whose personal use publications are supplied shall be responsible for their custody
and handing them over prior to retirement from service.
150
ANNEXURES
151
ANNEXURES
152
ANNEXURES
153
ANNEXURES
154
ANNEXURES
155
ANNEXURE 2/6
PARA : 209
SAND BLASTING
QUALITY HOSE PIPE PRIME MOVER
156
ANNEXURES
GROUTING NOZZLE
(
)
DETAIL OF PRESSURE GROUTING MACHINE
ANNEXURES
157
ANNEXURES
158
ANNEXURES
159
ANNEXURES
160
ANNEXURES
161
ANNEXURES
162
ANNEXURES
163
ANNEXURES
164
ANNEXURES
165
ANNEXURES
Annexure-2/17
Para-212 A
ASSESSMENT OF RESIDUAL FATIGUE LIFE OF OLD STEEL GIRDERS
The residual fatigue life assessment shall be carried out systematically as illustrated
in Figure-1 and described below. For notations and methods of analysis IRS Steel
Bridge Code (Updated) shall be referred.
Phase- I Preliminary Evaluation
The aim is to remove existing doubts about safety of the structure using fairly
simple methods and identify critical parts or members in the structure. This is
performed by gathering information on the structure from drawings and design
computations, carrying out a site visit, etc. The assessment is carried out by the
engineer alone by using current codes and by making conservative assumptions
where information is lacking or doubtful. Factor of safety against fatigue shall be
worked out which should be more than one.
Phase- II Detailed investigation
The detailed investigations are carried out if the factor of safety against fatigue
determined in Phase-1 is less than one. The aim is to update information and to
carry out refined assessments only for those members where safety is not ensured.
This is done by doing quantitative inspections and using detailed analytical
procedure based on collection of actual traffic data, actual speeds, updated values
for loads, sectional properties of members as well as more accurate models of
analysis. Here, in addition to the engineer, services of specialized firm, agency
or individual experts are generally required. If there are still doubts left about the
sufficient residual fatigue life, expert investigations are to be called for.
Phase-III Expert investigation
For problems with large consequences in terms of risks or of costs related to
a decision, a team of experts should be called in order to check carefully the
conclusions and proposals reached in Phase II. Discussions and further assessments
using specific tools (field observation of stresses by instrumentation, probabilistic
methods, fracture mechanics, etc.) can also be carried out to help in reaching
decisions. Detailed investigations using time history of stresses measured and
stress range histograms derived can be done by employing Palmgren - Minor rule
of cumulative damage to arrive at a more sophisticated estimate of residual fatigue
life. In case, residual fatigue life is still insufficient, remedial measures are to be
taken as per Phase-IV.
Phase-IV Remedial measures
The aim is to propose measures to have a fit for service structure with sufficient
Different measures can be taken, such as:
1. intensify monitoring
166
ANNEXURES
167
ANNEXURES
168
ANNEXURES
169
ANNEXURES
170
ANNEXURES
171
ANNEXURES
172
ANNEXURES
173
ANNEXURES
174
ANNEXURES
175
ANNEXURES
176
ANNEXURES
177
ANNEXURES
178
ANNEXURES
179
ANNEXURES
180
ANNEXURES
181
ANNEXURES
182
ANNEXURES
183
ANNEXURES
184
ANNEXURES
185
ANNEXURES
186
ANNEXURES
187
ANNEXURES
188
ANNEXURES
189
ANNEXURES
190
ANNEXURES
191
ANNEXURES
192
ANNEXURES
193
ANNEXURES
194
ANNEXURES
195
ANNEXURES
196
ANNEXURES
197
ANNEXURES
198
ANNEXURES
199
ANNEXURES
200
ANNEXURES
201
ANNEXURES
202
ANNEXURES
203
ANNEXURES
204
ANNEXURES
205
ANNEXURES
206
ANNEXURES
207
ANNEXURES
208
ANNEXURES
209
ANNEXURES
210
ANNEXURES
211
ANNEXURES
212
ANNEXURES
213
ANNEXURES
214
ANNEXURES
215
ANNEXURES
Annexure - 7/1
Para - 711.2
MEASUREMENTS DURING MONSOON
Gauge and afflux records of river: _______________________________
Bridge Number: _____________________________________________
For the Year: _______________________________________________
Kilometerage of Bridge Ilocation : _______________________________
Rail level : _________________________________________________
Highest Flood level recorded so far: _______________________________
216
ANNEXURES
217
ANNEXURES
218
ANNEXURES
219
ANNEXURES
Annexure - 7/5
Para - 715
FLOOD REPORTS
Sr. Between Details Date of Date of Method Rough Rough Details of
No. Stations of Occurence restoration of cost of cost of Detention
Damages of braches Repairs Damage restoration to /
Temporary Cancellation
& of trains if
Permanent any
1 2 3 4 5 6 7 8 9
Annexure - 7/6
Para - 716
Rainfall Statement for _____________________ Station
Sta- Months Total De-
tions for part-
the ment
Year from
Nor-
mal
September
November
December
February
October
January
August
March
April
May
June
July
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
220
ANNEXURES
221
ANNEXURES
222
ANNEXURES
223
ANNEXURES
224
ANNEXURES
225
ANNEXURES
226
ANNEXURES
227
ANNEXURES
228
ANNEXURES
229
ANNEXURES
230
ANNEXURES
231
ANNEXURES
232
ANNEXURES
233
ANNEXURES
234
ANNEXURES
235
ANNEXURES
236
ANNEXURES
237
ANNEXURES
238
ANNEXURES
(ANNEXURE-ll/2a)
Para 1102.2
PROFORMA FOR INSPECTION OF PSC BRIDGE I COMPOSITE GIRDERS
Bridge No. ............................. chainage............................... Block Section.......................
In Section ......................... UP/DN/SL/No. of Multiple Line ...................................
Sub Division .................................. Division ................................. Name of Stream /
River ............................. Completion Drawing Nos: ............................
(All relevant Completion Drawing of Girder, Bearings & Expansion Joints are to be
attached at the beginning of PSC Inspection Register and Inspection of Steel Work in
Composite Girder Bridges to be rontinued as per Annexure 11/1 & 11/2.)
239
ANNEXURES
240
ANNEXURES
Span Type-II
Span Type-III
19. Details of
a. Trolley refuges
b. Safety refUges
c. Foot Path
d. Railing
e. Sand Bins
241
ANNEXURES
242
ANNEXURES
NOTE: Camber to be measured at the Centre of Girder (L/2) only. However, If the length of girder is
more than 20 m, camber to be measured at 3 locations.
243
ANNEXURES
244
ANNEXURES
245
ANNEXURES
246
ANNEXURES
Annexure 11/3
Para 1103.4
BRIDGE INSPECTION REGISTER
1. Instructions for inspection purpose : Para 1107 of the Indian
Railway Bridge Manual may be got printed on the Bridge Inspection
Register which details out the instructions for inspection purposes.
2. Instructions for entering the Bridge Register :
a) Under each heading entry should state whether the previous
year's notes have been attended to.
b) Entries in the column "Condition of bridge at the time of
inspection" should be in the nature of statements. A defect once mentioned
should not be omitted in future years unless it has been eliminated by
rebuilding or repair in which case a note should be made to that effect.
c) In the column "Action taken", the remarks should be in the form
that orders have been issued, e.g.
i) Permanent Way Inspector instructed to renew sleepers,
ii) Bridge Inspector instructed to carry out painting.
d) No bridge which is cracked or in which the masonry is shaken,
crushed, bulging, deteriorating or showing signs of movement or in which
the steel work is affected should be described as "sound".
e) Should it be impossible to make complete inspection of any
bridge owing to the presence of standing water, the fact should be recorded.
The inspection of foundations should be made no sooner water dries up or
conditions make it possible to do so and results recorded as supplementary
entries in the Bridge Inspection Register.
247
ANNEXURES
Annexure 11/4
Para 1103.4
INDEX OF BRIDGES
Section _____________________ DN/UP _____________________
From Km _____________________ To Km ______________________
248
ANNEXURES
249
ANNEXURES
Annexure 11/6
Para 1103.4
CLASSIFICATION OF STRUCTURES
Earthernware pipe - -
250
ANNEXURES
Girder road over bridge - Iron or steel girder bridge over the line
Note :- A bridge on the skew should have the word "skew" entered against
type of bridge and its span, square and skew should be given.
251
ANNEXURES
Annexure 11/7
Para 1103.4
INSCRIPTION PLAQUES ON BRIDGES SHOWING
NATURE AND DEPTH OF FOUNDATIONS
On all bridges of 3 m (10ft.) span or over, particulars of the nature and
depth of foundations should be inscribed on a CC or stone slab fixed on each pier
and abutment.
1. The information to be recorded should be :
a) Nature of foundation e.g. wells, piles and open,
b) Nature of strata passed through and reached,
c) Depth from rail level to the bottom of foundations and top of foundations.
2. The following abbreviations should be used in the inscriptions:
WL Well foundation
ON Open foundation
SP Screw Pile foundation
TP Timber pile foundation
CP Concrete pile foundation
IC Iron cylinder
SC Steel cylinder
CN Concrete
CCN Cement Concrete
PSC Prestressed concrete
BF Bottom of foundation
TF Top of foundation
TA Top of apron
TI Top of invert
BD Bottom of drop wall
RL Rail level
RL-BF Depth from rail level to bottom of foundation
RL-TF Depth from rail level to top of foundation
S Sand
C Clay
G Gravel or shingle
252
ANNEXURES
M Moorum
R Rock
BC Black cotton soil
K Kunker
A Alluvium
3. Other symbols may be used if required such as :
WW Wing Wall
US Up Stream
DS Down Stream
TP Top of Pitching
BP Bottom of Pitching
WN Wire Netting
CW Crib Work
4. For example a plaque inscribed thus and bui~ on top of pier:
WL
RL-BF 74
RL - TF 34
S 25
C 15
Will indicate that the pier is founded on a well, the bottom of which is at
74ft below rail level and top 34 ft below rail level and that 25 ft of sand and 15
ft of clay were passed through and the well rested on clay. If the inscriptions had
been made after the metric measurements came into force, the numbers on the
inscription will indicate the depths in metres and to distinguish from FPS units,
letter "m" should be added e.g. RL-BF 20m.
5. On bridges already built it may be impossible to give so much details, in
that case a simple inscription such as
RL - BF 69
R
will suffice
This will indicate that the foundation is on rock at a level of 69 ft below
rail level.
Note: Most of the existing bridges contain plaques with inscriptions in FPS
Units. On new bridges, plaque inscriptions in MKS Units should be adopted.
253
ANNEXURES
Annexure 11/8
Para 1103.4
PROFORMA FOR MAJOR AND IMPORTANT BRIDGES
1. General :
Division ______________ Sub Division ___________________ Section _______________________
Br. NO _____________________________ Span details ____________________________________
Name of river ________________________ Class of structure _______________________________
Type of girder ________________________ strength of girder _______________________________
Rail level ___________________________ m High flood level _____________________________ m
Danger level _________________________ m
Bottom of girder/slab or crown of arch _________________________________________________ m
Abutment: Materials of construction
i) (with splayed wing walls)
ii) (with parallel wing walls)
Pier: Type
Strength of : Piers
Abutments
Wing walls
Depth of cushion __________________________ m below bottom of sleeper (for arch slab top and
pipe bridges only)
2. Previous history regarding high flood, scour, erosion, suspension
of traffic etc.
3. Record of afflux : ___________________ year _____________ Max.afflux ____________________
4 Foundation details ______________________________ Velocity of flow ______________________
Pier / Details of wells/ piles/open B.F. T.F. Bed Floor Thickness Safe
Abutment level level of fioor scour
limit
1 2 3 4 5 6 7 8
254
ANNEXURES
255
ANNEXURES
Annexure 11/9
Para 1103.4
PROFORMA FOR INSPECTION OF MAJOR AND IMPORTANT BRIDGES
CONDITION OF THE BRIDGE AT THE TIME OF INSPECTION
Date of Foundation and Masonry Protective works and Bed
inspection flooring extent Condition, waterway scour, slips or Blocks
of scour and extent of settlements, sanctioned Cracks,
damage defect in reserve available and tendency
substructure whether wateway is clear to move
1 2 3 4 5
Other items like trolley Action taken on Initial of inspecting Initilas of higher
refuges/foot paths, fire last year's notes official and URN officials with
fighting equipment etc. remarks
16 17 18 19
256
ANNEXURES
Annexure 11/10
Para 1103.4
FOR MINOR BRIDGES
Details of the Bridge
Minor Bridges:
257
ANNEXURES
Annexure 11/11
Para 1101.2 & 1103.4
PROFORMA FOR INSPECTION OF MINOR BRIDGES
Annexure 11/12
Para 1107.5
PROCEDURE FOR RIVET TESTING
258
ANNEXURES
a) Plate girders:
i) Plate girders under 12.2 m nominal length will not be included in the
rivet test programmes. No routine tests need be carried out on such spans but
Bridge Inspectors will during their detailed inspections of all steel work, satisfy
themselves that the few rivetted connections (particularly in bracings) are in
efficient order.
ii) Plate girder of 12.2 m and over nominal length will have samples of
their rivets taken in the categories detailed as follows:
259
ANNEXURES
260
ANNEXURES
Annexure 11/13
Para 1102.2
SAMPLE RIVET TEST REGISTER
Bridge No. ________________ Span No. _______________ at km ________
Girder type & No ____________________ Nominal length ______________
Date of test ________________________
Note: 1. For details of rivet categories refer to the note printed in the
Annexure 11/12.
2. Loose rivet diagram to be given for identification of joints.
261
ANNEXURES
262
ANNEXURES
Annexure 11/15
Para 1109
TOOLS AND EQUIPMENT FOR INSPECTION OF BRIDGE
Sl. No. Tool/Equipment Purpose Required For*
1 2 3 4
1. Rivet testing For testing looseness of rivets A, B, C,
hammer (110g) D, E
2. Inspection cum For checking hollow pocket/ A,B,C
chipping hammer honeycomb In masonry and
concrete stnucture including PSC
by tapping and for examining the
extent of corrosion, adherence
of paint on girders, and for
removing loose scales
3. Elcometer (coating For measuring thickness of paint, A or B
thickness gauge) metalised coating, etc.
4. Pocket steel tape For measuring gap between A,B,C
(3m) girders or between girder and
abutment, dimension of steel
members, size of cracks, etc.
5. Straight edge (1 m) For checking deformation / A,B,C
distortion/buckling of steel
components, bulge of masonry
structure, etc.
6. Metallic tape (30m) For taking measurements such A,B,C,
as clear span, overall length of D, E
girders, etc.
7. Log line with 20 kg. For measuring scour depth, B
lead ball lifting/lowering of tools and (as
tackles for examination purpose, required)
etc.
8. Probing rod For checking firmness of ground B
and scour measurements
263
ANNEXURES
264
ANNEXURES
** Only for officials who have bridges with large waterways requiring
the use of boats to be decided by CBE.
265
ANNEXURES
Annexure- 12/1
Para 1215
FORM OF AGREEMENT FOR HIRE OF PLANT
266
ANNEXURES
267
ANNEXURES
the point where the plant is stationed, at public tariff rates, to be borne by
the Hirer. The Railway may at its discretion permit the purchase of the
spare wearable parts from outside sources provided it is satisfied that the
parts correct to specification only will be used.
8. I n the case of breakage or loss of any part of accessory other
than the parts liable to wear out referred to in the Appendix'S', the cost
of replacement shall be shared between the Railway and the Hirer in
accordance with the rules in this respect in force on the Railway from time
to time. The share to be borne by Railway as determined in accordance
with the rules in force on the Railway shall be final and conclusive.
9. In the event of the loss of the entire plant, the cost shall be divided
between the Hirer and Railway on the basis laid down in rules in force on
the Railway from time to time. The cost that may be determined by the
Railway shall be final and the Hirer shall pay his share of the cost to the
Railway.
10. The Hirer shall not make over, under-let or otherwise transfer or
part with, the whole or any part of the plant and materials taken on hire
without the consent in writing of the Railway which shall have absolute
discretion to grant refuse such consent and at any time revoke such
consent, if given. Such consent shall not relieve the Hirer of any of the
responsibilities or obligations under this agreement.
11. During the period the plant is on hire with the Hirer, the Hirer
shall be responsible to ensure that any inspection certificate or license
required under any Government Act for the time being in force is obtained
in due time. The Hirer shall also be responsible for seeing that all required
precautions are observed in using the plant and for any accident which may
occur from the use of the plant.
12. The Railway shall be given all reasonable access to the plant and
such facilities as may be necessary to satisfy itself that the plant is being so
used as to avoid any unnecessary wear or loss or under risk.
13. The Railway reserves to itself the right to recall the plant without
assigning any reasons by giving two week's notice to the Hirer or at any
time without notice in the event of its being required by the Railway for
268
ANNEXURES
269
ANNEXURES
Witness:
Signed by ___________
(in the presence of)
270
ANNEXURES
APPENDIX 'A'
TO AGREEMENT FORM
(Para 1215)
Schedule of hire charges to accompany Agreement
No _____________________________
Dated ___________________________
Sr. Description of Unit Quantity Rate of hire per Remarks
No. Material month/day
In figures in words
Rs. Paise
____________________ ____________________
Hirer Chief Engineer
Appendix 'B'
TO AGREEMENT FORM
(Para 1215)
List of wearable parts to Accompany Agreement No _____________
dated ______________________________________________________
Sr. No Description of Materials Unit Quantity Remarks
1 2 3 4 5
____________________ ____________________
Hirer Chief Engineer
271
ANNEXURES
Annexure 14/1
Para 1401
List of Books of Reference
Item Publication Offices which should be equipped with a copy of the
No. publication
For the Dy. Chief Divisional Asstt. Bridge
personal use of Engineer Engineer's Engineers Inspector's
such Officers /Bridges Office Office Office
and Inspectors Hd.Ors.
as may be Office
prescribed
by the Chief
Engineer
1 2 3 4 5 6 7
1 Act Indian - 1 1 - -
Boilers and
Manual
of Boiler
Inspection as
issued
2 Act Indian - 1 1 - -
Electricity
and rules
issued
and State
Government
Publications.
3 Act Indian - 1 1 - -
Explosive
and State
Government
Publications
4 Act Indian - 1 1 - -
Factories
and State
Government
Publication
272
ANNEXURES
1 2 3 4 5 6 7
5 Act Indians - - 1 1 -
Mines
and State
Government
Publication
6 Act Indian - 1 1 1 -
Petroleum
and State
Government
Publication
and
Petroleum
rules
7 Act, Indian - 1 1 1 -
Railway
8 Act, Land - 1 1 1 -
Acquisition
and State
Govt.
Publications
9. Act, - 1 1 1 1
Payment of
Wages with
Notifications
as issued
10 Act, - 1 1 1 1
Workmen's
Compensation
11 Alphabetical - 1 1 1 1
list of
Railway
Stations
12 Code Indian - 1 1 1 1
Railway for
the Engg.
department
13 Code, lndian - 1 1 - -
Railway for
the Stores
Department
273
ANNEXURES
1 2 3 4 5 6 7
14 Code, Indian - 1 1 - -
Railway for
the Mechanical
Department
15 Code, Indian - 1 1 - -
Railway for
the Accounts
Department
16 Code, lndian - 1 1 1 1
Railway
Establishment
17 Code Indian - 1 1 1 -
Railway
General
18 Indian - 1 1 1 1
Railway
Establishment
Manual
19 Indian 1 1 1 1 1
Railway
Permanent
Way Manual
20 Indian Railway 1 1 1 1 1
works Manual
21 Indian 1 1 1 1 1
Railway
Bridge
Manual
22 Manual, - 1 1 - -
Signaling and
Interlocking
23 Manual, 1 1 1 1 1
Accidents
or circulars
Pertaining to
accident.
24 Price lists - 1 1 1 1
of Stores
or Stores
Nomenclature
and circulars as
applicable
274
ANNEXURES
1 2 3 4 5 6 7
25 Red Tariff - 1 1 1 -
No. 16, Indian
Railway
Conference
Association
26 Regulations, - 1 1 1 1
Hours of
Employment
with
notifications as
issued
27 Rules, General 1 1 1 1 1
and subsidiary
parts I & II
28 Rules reg. - 1 1 1 1
Leave, Passes
& PTOs
29 "Safety First" 1 1 1 1 1
rules
30 Schedule of 1 1 1 1 1
Dimensions
31 Schedule of - - 1 1 -
Powers of
Divisional &
Asst. Engineers.
32 Special Orders 1 1 1 1 1
on matters
of general
importance
concerning the
staff as issued.
33 Standing - - 1 1 -
orders
Operating
Department
34 Telegraph - 1 1 1 1
Code
35 Works - 1 1 1 1
Hand book
of general
Conditions of
Contract and
Specifications
for Materials
and Works
275
ANNEXURES
1 2 3 4 5 6 7
36 Working of - 1 1 1 1
Cranes and
Hoists, as
issued.
37 Chief - 1 1 1 1
Engineer's
Circulars on
Bridges.
38 River - 1 1 - -
Training and
Protection
Work for
Railway
Bridges-
Monograms
by IRICEN
Pune.
39 Monsoon - 1 1 1 1
Instructions
issued by the
Railway.
40 IRS Code of - 1 1 1 -
Practice for
the Design of
substructures
and
foundations
of bridges.
41 Code of - 1 1 - -
practice for
design and
construction,
of Pile
foundation (4
parts) IS:2911
42 Gauging - 1 1 - -
Manual
issued by
RDSO
276
ANNEXURES
1 2 3 4 5 6 7
43 IRS Code of - 1 1 1 -
practice for
fabrication
and erection
of steel work
for Microwave
towers (self
Supporting
type)
44 Manual of - 1 1 1 1
Inspection and
Maintenance
of Concrete
Bridges issued
by RDSO
(1990).
45 Arch Bridge - 1 1 - -
code 1982
46 Report of - - 1 1 -
the sub
committee on
the rebuilding
of Railway
Bridges-
RDSO
47 Bridge - 1 1 1 1
Inspection and
maintenance
by IRICEN/
Pune.
48 Report of the - 1 1 1 -
committee
on Numerical
Ratings of
Bridges
49 Guidelines - 1 - - 1
on fabrication
of welded
Bridge Girders
(Report
No. c-277),
March'94
issued by
RDSO.
277
ANNEXURES
1 2 3 4 5 6 7
50 Study made - 1 1 1 1
to reduce
frequency of
painting of
Railway steel
bridge girders /
structures
51 Quality - 1 1 1 1
Assurance
Programme
for prestressed
concrete
construction
issued by
RDSO (1991)
52 Guidelines for - 1 1 1 1
Inspection,
Maintenance
and
Rehabilitation
of long Span
prestressed
concrete
bridges issued
by RDSO (July
1993)
53 Maintenance - 1 1 1 1
and
Rehabilitation
of masonry
bridges issued
by RDSO
(August 93)
54 Guidelines for - 1 1 1 1
inspection and
maintenance of
Welded Bridge
girders issued
by RDSO
(December 90)
278