Cash Flow Meeting Period May 2025 - After Meeting
Cash Flow Meeting Period May 2025 - After Meeting
金額 金額
件数 項目 件数
Amount (RP) in Amount (RP) in Fluctuation
No. Item Number
May '2025 Apr '2025
竣工後3カ月以上未入金(リテンションを除く
1 AR unpaid over 3 month or more from project closed (excluding 2 504,277,727 981,796,264 -477,518,537 -48.64%
retention)
竣工後1カ月以上未請求(リテンションを除く)
2 0 0 0 0 #DIV/0!
Unbilled AR over 1 month from project closed except retention
締切後2ヶ月以上未入金
3 6 1,641,528,757 1,477,845,147 163,683,610 11.08%
Billing AR over 2 Month
請求-コスト(未竣工工番のみ) マイナス1億ルピア以下
4 41 (43,903,034,632) (41,675,199,951) -2,227,834,681 5.35%
Billing - Cost only continue projects under -100 milion RP
仮受注比率9%以上、3か月未満(仮受注比率100%及び雑小案件除く)
6 Tentative contract (Add. Work) >9%、Less than 3 Month (excl. 0 - - 0 #DIV/0!
tentative contract 100% and Various Project)
3カ月以上仮受注
7 9 22,007,847,931 11,741,247,931 10,266,600,000 87.44%
Tentative contract over 3 month
未請求リテンション
8 4 4,047,115,000 4,047,115,000 0 0.00%
Unbilled Retention
合計
90 91,308,510,789 83,420,997,371 7,887,513,418 9.46%
Total
竣工後3カ月以上未入金(リテンションを除く)
since Close
AR unpaid over 3 month or more from project closed (excluding retention) project
2 504,277,727 116,581,968
入金 入金
件数 工事番号 工事件名 竣工月 受注先 完工未収残高 理由 担当者 完工未収残高 理由
(予定) (予定)
Balance---> 387,695,759
1 229,234,365
2 158,461,394
387,695,759
竣工後1カ月以上未請求(リテンションを除く)
Unbilled AR over 1 month from project closed except retention
0 0
請求 入金
件数 工事番号 工事件名 竣工月 受注先 完工未収残高 理由 担当者 理由
(予定) (予定)
Closed Billing Received
No. Project No. Project Name Customer Balance of AR Reason in Jun'25 PIC Reason in May'25
YY/MM (Terget) (Terget)
3
締切後2ヶ月以下未入金
Billing AR over 2 Month Based on
Invoice
6 1,641,528,757 -
入金
件数 工事番号 工事件名 竣工月 受注先 完工未収残高 理由 Amount 担当者 Apr-25 理由
(予定)
Cust Payment
Closed Invoice Rec'v by Received Received
No. Project No. Project Name Customer Balance of AR Schedule (Term Reason in Jun 2025 already Received PIC Balance of AR Reason in May 2025
MMM/YY Cust (Target) (Target)
of Payment)
Rp. 37,074,000.- Will be Cancel invoice Reason: Internal YPMI Production Eng, there was
YAMAHA MOTOR PARTS YAMAHA MOTOR PARTS because revise PO from MPO to FAPO (Fix incorrect input about the PO, which must be as
K. Shimonuri/Rony
6 202418052 MANUFACTURING MANUFACTURING 116,439,000 21/01/2025 2/28/2025 July 2025 Asset PO); - 37,074,000 FAPO.
Teguh/Giri S.
INDONESIA INDONESIA others Rp. 79,365,000.- waiting They will send the PO Revision (28/05/2025)--> and
agreement. Will be paid on July 2025 also the supporting documents must be received in
complete by TSRT.
Balance---> 1,641,528,757
BUMITANGERANG
2 202401007 BT COCOA 197,025,000 21/02/2025 29/08/2025
MESINDOTAMA
GLOBAL MULTINIAGA GLOBAL MULTINIAGA
3 202408017 26,500,000 29/08/2025
INDONESIA INDONESIA
JOTUN WATER BASED
4 202201071 PRODUCTION FACILITY ( MEP JOTUN INDONESIA 9,747,154,064 06/01/2025 31/12/2025
SERVICE )
JOTUN INDONESIA - NEW 31/12/2025,
5 202208062 JOTUN INDONESIA 7,380,145,936
WATER BASED FACTORY 31/12/2026
29/08/2024,
30/01/2026,
7 202308040 MURIA SUMBA MANIS MURIA SUMBA MANIS 477,481,959 28/11/2024,
31/03/2026
30/12/2024
TAISEI PULAUINTAN
11/10/2024, 28/11/2025,
8 202301033 DAIKIN FACTORY PROJECT CONSTRUCTION 13,396,291,133
19/02/2025 28/03/2026
INTERNATIONAL
36,207,754,576
0
請求-コスト(未竣工工番のみ) マイナス1億ルピア以下
Billing - Cost only continue projects under -100 milion RP
41 462,788,314,000 93,825,849,176 137,728,883,808 354,168,146,145 (43,903,034,632) 14,794,318,679 12,981,874,455 795,607,925.00 3,538,500,000.00
請求
件数 工事番号 工事件名 契約名 受注先 契約額 請求額 コスト 請求-コスト Billing (Target) 理由 担当者 理由
Remaining Contract (予定)
Billing Cost Billing - Cost June'25 June'25 May'25
No. Project No. Project Name Contract Name Customer Contract Amount including this period Target Billing Reason in June'25 PIC Target May'25 Reason in May '25
① ② ①-② (Already Issue) (Target) (Already Issue)
Progress Approved on June 12, 2025 Rp. 372,593,169.- Already issued invoice on May 08, 2025 Rp.
Target IPC on June 20, 2025. In connection with civil works 241,114,119.- In connection with civil works very late, we
JIMBARAN very late, we negotiated with JGH to propose Fix Payment. negotiated with JGH to propose Fix Payment. JGH not
JIMBARAN GREENHILL VILLA R.02, Benny S./Vebry
2 202201038 01 GREENHILL VILLA JIMBARAN GREENHILL 32,982,960,000 23,960,500,280 24,419,160,097 9,022,459,720 (458,659,817) June 2025 372,593,169 JGH not approved but can progress material onsite 100% 241,114,119.00 - approved but can progress material onsite 100% and site
R.03, R.04 E./Neno
R.02, R.03, R.04 and site progress. Target Submit Progress Claim July 2025 progress. Target Submit Progress Claim June 2025 (Rp.
(Rp. 210,000,000), Next Submit Progress Aug 2025 100,000,000),
(Rp.200,000,000). Next Submit Progress July 2025 (Rp.120,000,000).
TAISEI PULAUINTAN
CHATERAISE Already issued invoice on June 03, 2025 Rp. Benny S./Vebry
4 202401079 01 CHATERAISE INDONESIA CONSTRUCTION 4,177,000,000 835,400,000 1,127,987,368 1,681,509,432 (292,587,368) 6/3/2025 1,660,090,568
INDONESIA 1,660,090,568.- E./Tarnoja
INTERNATIONAL
Trench-3: Already received the LOA from Promatrix & - Waiting Contract from Promatrix for GTN JKT02 for
waiting sign from both sides, will receive PO: 15% DP, 52% Trench-3 (IDR.12 bio), but will try to receive in early
GTN JKT02 - progress I (progress 60%) target until end of June 2025, June'25.
TRENCH 3, L1
GTN JKT02 - TRENCH 3, L1 ( WIRING Benny S./Vebry
5 202401087 01 ( WIRING & PRO-MATRIX PTE LTD 188,633,000,000 - 1,424,955,752 188,633,000,000 (1,424,955,752) There are postponed construction works for 3~6 months for - - - There are postponed construction works for 3~6 months
& TERMINATION WORK ) E./Rio S.
TERMINATION Trench-4, Mechanical & Electrical Works. But still tried to for Trench-4, Mechanical & Electrical Works. But still tried
WORK ) negotiate, and already submitted additional cost for to negotiate, and already submitted additional cost for
Preliminary about IDR.1.8 bio(3 months), and IDR. 2.4 bio (6 Preliminary about IDR.1.8 bio (3 months), and IDR. 2.4 bio
months), (6 months).
Still tentative Contract Rp. 2,945,089,000.- target PO on July Already issued invoice on May 16, 2025 Rp. 214,229,750.-
RENOVASI AREA 2025 Benny & Others still tentative Contract Rp. 2,945,089,000.-
RENOVASI AREA TRIBECA CENTRAL
8 202401010 01 TRIBECA CENTRAL CPM ASSETS INDONESIA 6,270,089,000 3,097,420,375 5,317,961,332 3,172,668,625 (2,220,540,957) S./Luterson/Edy 214,229,750.00 - target PO is July'25
PARK MALL
PARK MALL on process negotiation, since there is still a price difference Wibowo
between the request from the Owner and Taiyo.
Benny Can't work yet since waiting for the machine customers to
AISAN NASMOCO Target Finish work in End June 2025 Rp. 1,555,200,000.-
9 202401053 01 AISAN NASMOCO INDUSTRI-1 TAKENAKA INDONESIA 1,944,000,000 388,800,000 1,455,672,811 1,555,200,000 (1,066,872,811) July 2025 S./Senswedy/Edi - - arrive. Target work in June 2025 Rp. 1,555,200,000.-
INDUSTRI-1 target billing July 2025.
Darma target billing July 2025.
PANASONIC INDUSTRIAL Not Finished yet, Waiting for Production in July 2025, Finish
Benny Finish work is End May 2025, target billing June 2025 Rp.
10 202401054 01 PICID MM2100 PICID MM2100 COMPONENTS 1,000,000,000 300,000,000 607,794,785 700,000,000 (307,794,785) Aug 2025 work by the end of July 2025, target billing in August 2025 - -
S./Senswedy/Ricky F. 700,000,000.-
INDONESIA Rp. 700,000,000.-
TAKASAGO Finish works Aug 2025 Rp. 500,000,000.- target billing Sep. Benny
TAKASAGO INTENATIONAL Finish works June 2025 Rp. 500,000,000.- target billing
12 202401082 01 INTENATIONAL KAJIMA INDONESIA 1,321,000,000 - 678,183,480 1,321,000,000 (678,183,480) Sep 2025 2025. (Backward work schedule from the customer). S./Senswedy/Edi - -
INDONESIA July 2025.
INDONESIA Darma
FCC - Waiting sign progress claim 95% Rp. 818.900.000,- target Waiting sign progress claim 95% Rp. 818.900.000,- target
Rustandi/Heriyanto/
15 202401070 01 MODIFICATION FCC - MODIFICATION OHC - 4TON JAYA OBAYASHI 862,000,000 - 566,429,284 862,000,000 (566,429,284) June 2025 818,900,000 billing June End 2025 (since JO not received yet PO), already - - billing June 2025 (Already received PO on May 08, 2025
Shalahuddin
OHC - 4TON confirmed Mr. Edi (JO): target sign until 27 June'25 Rp. 862,000,000.-)
UNI-CHARM
UNI-CHARM INDONESIA 1ST Payment Term : 100% after completion. Target completion Rustandi/Heriyanto/
17 202401090 01 INDONESIA 1ST KAJIMA INDONESIA 1,355,000,000 - 184,206,244 1,355,000,000 (184,206,244) July 2025
FACTORY End July 2025 Rp.1.355.000.000,- Budhiawan Cahyo
FACTORY
Page 5 of 12
請求-コスト(未竣工工番のみ) マイナス1億ルピア以下
Billing - Cost only continue projects under -100 milion RP
41 462,788,314,000 93,825,849,176 137,728,883,808 354,168,146,145 (43,903,034,632) 14,794,318,679 12,981,874,455 795,607,925.00 3,538,500,000.00
請求
件数 工事番号 工事件名 契約名 受注先 契約額 請求額 コスト 請求-コスト Billing (Target) 理由 担当者 理由
Remaining Contract (予定)
Billing Cost Billing - Cost June'25 June'25 May'25
No. Project No. Project Name Contract Name Customer Contract Amount including this period Target Billing Reason in June'25 PIC Target May'25 Reason in May '25
① ② ①-② (Already Issue) (Target) (Already Issue)
Already issued invoice on June 09, 2025 Rp. Rustandi/Heriyanto/ Work finished at the end of May 2025, Completion
22 202401092 01 HLI GREEN POWER HLI GREEN POWER HLI GREEN POWER 680,000,000 - 343,913,815 - (343,913,815) 6/9/2025 680,000,000 - -
680,000,000.- Dini Cahyo submitted in June 2025 Rp. 680,000,000.-
On Process Installation Work. Will be end of June 2025, and There is still a machine that will arrive in mid-June 2025,
VARIOUS PLANT- SUZUKI INDOMOBIL K. Shimonuri/Rony
26 202418059 18 SUZUKI INDOMOBIL MOTOR 210,000,000 63,000,000 174,287,140 147,000,000 (111,287,140) July 2025 the target billing in July 2025, the amount of Rp. - - the target finish works at the end of June, and the target
Q4-CIKARANG-3 MOTOR Teguh/Bhekti
147,000,000,- billing in July, the amount of Rp. 147,000,000,-
MURAKAMI DELLOYD
MURAKAMI DELLOYD INDONESIA, Already issued invoice on June 12, 2025 Rp.
INDONESIA, SUZUKI
VARIOUS PLANT- SUZUKI INDOMOBIL MOTOR, 95,500,000.- (Murakami Project), Hekikai Project target K. Shimonuri/Rony
27 202518001 18 INDOMOBIL MOTOR, 307,200,000 - 136,185,210 211,700,000 (136,185,210) 6/12/2025 95,500,000
Q1-CIKARANG MARUKA INDONESIA, HEKIKAI billing July 2025 Rp. 57,000,000.- Others finish work end of Teguh/Bhekti
MARUKA INDONESIA,
INDONESIA June 2025, Target Billing July 25 Rp. 74,700,000.-
HEKIKAI INDONESIA
BAPP already submit on June 02, 2025. Target sign & Billing
on July 2025 Rp.6,930,000,000.- Prepare BAPP until Mid of May 25, Target submit BAPP end
MURIA SUMBA K. Shimonuri/Rony
30 202408034 08 MURIA SUMBA MANIS - AVATAR MURIA SUMBA MANIS 27,500,000,000 5,500,000,000 8,776,185,550 22,000,000,000 (3,276,185,550) July 2025 Prog.I: 4.9 mio (cut off 15 May'25) - - of May, Inspection, Review & Sign on June 25 & Billing
MANIS - AVATAR Teguh/Cahya Agung
Prog II: 1.4 mio Rp.3,000,000,000 on July 25.
YAMAHA MOTOR PARTS Already issued invoice on June 04, 2025 Rp.
VARIOUS PLANT- MANUFACTURING 21,600,000.- Other waiting for work finish end of June
YPMI, AT INDONESIA, FCC K. Shimonuri/Rony Already issued invoice on May 02, 2025 Rp. 55,000,000.-
32 202418052 18 Q4-KIIC INDONESIA, FCC 1,895,000,000 1,223,000,000 1,409,856,528 650,400,000 (186,856,528) 6/4/2025 21,600,000 2025, Target billing on July 2025 Rp. 123,300,000.- (YPMI) 239,700,000.00 -
INDONESIA Teguh/Giri S. (AT Indonesia) & Rp. 184,700,000.- (YPMI)
KARAWANG INDONESIA, AT And 1 Contract, Due to revise PO waiting for DM Approval for
INDONESIA edit contract Rp. 253,600,000.-
Submit completion 16/06/2025, target billing on June 2025, K. Shimonuri/Rony Finish works at the end of June 2025, target billing in July
35 202408041 08 TPR INDONESIA TPR INDONESIA TPR INDONESIA 885,500,000 265,650,000 566,640,625 619,850,000 (300,990,625) June 2025 619,850,000 - -
Amount Rp.619.850.000,- T./Setiawan Efendi 2025, Amount Rp. 619.850.000,-
VARIOUS PLANT- Submit completion 16/06/2025, Target billing on Jun 2025 K. Shimonuri/Rony Schedule shutdown on June 2025, Target billing on July
36 202418062 18 TPR INDONESIA TPR INDONESIA 450,000,000 135,000,000 332,930,375 315,000,000 (197,930,375) July 2025 315,000,000 - -
Q4-CIKARANG-5 Amount Rp.315,000,000.- T./Setiawan Efendi 2025 Amount Rp.315,000,000.-
Already received PO, now waiting for completion letter sign Still waiting for PO for tentative contract, Target PO end of
VARIOUS PLANT- K. Shimonuri/Rony
37 202418047 18 TIRTA INVESTAMA MEKARSARI TIRTA INVESTAMA 182,000,000 - 115,049,234 182,000,000 (115,049,234) June 25 182,000,000 & GR, target billing June 25, Rp. 182,000,000 - - May 2025, Target Billing mid June 2025, Amount Rp.
Q3-SUKABUMI Teguh/Widi A.
145.600.000,- (reason: waiting PO approval, 2 person)
Page 6 of 12
請求-コスト(未竣工工番のみ) マイナス1億ルピア以下
Billing - Cost only continue projects under -100 milion RP
41 462,788,314,000 93,825,849,176 137,728,883,808 354,168,146,145 (43,903,034,632) 14,794,318,679 12,981,874,455 795,607,925.00 3,538,500,000.00
請求
件数 工事番号 工事件名 契約名 受注先 契約額 請求額 コスト 請求-コスト Billing (Target) 理由 担当者 理由
Remaining Contract (予定)
Billing Cost Billing - Cost June'25 June'25 May'25
No. Project No. Project Name Contract Name Customer Contract Amount including this period Target Billing Reason in June'25 PIC Target May'25 Reason in May '25
① ② ①-② (Already Issue) (Target) (Already Issue)
SUMIDEN SERASI SUMIDEN SERASI WIRE Already issued invoice on June 13, 2025 Rp. K. Shimonuri/Arie Waiting completion sign Rp. 1,005,900,000.- target billing
38 202408037 08 SUMIDEN SERASI WIRE PRODUCTS 4,035,000,000 1,210,500,000 1,882,972,146 1,818,600,000 (672,472,146) 6/13/2025 1,005,900,000 - &
WIRE PRODUCTS PRODUCTS 1,005,900,000.- A./Novi H. end of May 2025
VARIOUS PLANT- SUMIDEN SERASI WIRE Already issued invoice on June 05 & 13, 2025 Rp. K. Shimonuri/Arie Waiting completion sign Rp. 460,000,000.- (SSWP Project)
39 202418044 18 SUMIDEN SERASI WIRE PRODUCTS 1,392,000,000 271,000,000 456,554,000 - (185,554,000) 05 & 13/06/2025 1,121,000,000 - 460,000,000.00
Q3-BOGOR PRODUCTS 1,121,000,000.- A./Novi H. target billing end of May 2025
SUMITOMO
SUMITOMO ELECTRIC WINTEC SUMITOMO ELECTRIC Already issued invoice on June 03, 2025 Rp. K. Shimonuri/Rizqi Working schedule until end may 2025, target billing Jun
41 202408043 08 ELECTRIC WINTEC 745,500,000 - 531,836,750 - (531,836,750) 6/3/2025 745,500,000 - -
INDONESIA WINTEC INDONESIA 745,500,000.- N./Umar Riadhi 2025 Rp. 745,500,000.- (100% completion)
INDONESIA
Balance---> (29,108,715,953)
34%
Page 7 of 12
出来高GAP 請求-コスト(未竣工工番のみ) マイナス1億ルピア以上、かつ出来高GAP額マイナス1億ルピア以上
Progress GAP, Billing - Cost only continue projects over -100 milion RP and Progress GAP under -100 milion RP
28 435,474,212,928 367,899,327,440 364,215,172,106 322,854,060,273 41,361,111,833 (19,204,706,742) 14,261,352,532 1,677,175,000
Target Billing
件数 工事番号 工事件名 受注先 契約額 実行予算 利益率 請求額 コスト 請求-コスト 請求進捗 原価進捗 出来高GAP Billing (Target) 理由 担当者 理由
Profit Billing Cost Billing - Cost Progress Cost Progress Progress GAP in June'25 June'25 May'25 May'25
No. Project No. Project Name Contract Name Customer Contract Amount BPP Target Billing Reason in June'25 PIC Reason in May'25
Ratio ① ② ①-② Billing Progress GAP Rupiah (Already Issue) (Target) (Already Issue) (Target)
SURABAYA AUTOCOMP Already issued invoice on June 12, 2025 Rp. Benny S./Vebry
12 202401083 01 SURABAYA AUTOCOMP INDONESIA KAJIMA INDONESIA 2,100,000,000 1,806,060,000 14.00% 1,575,000,000 1,582,933,619 (7,933,619) 75.0% 87.6% -12.6% (265,559,339) 12-Jun-25 525,000,000
INDONESIA 525,000,000.- E./Fariski
Page 8 of 12
出来高GAP 請求-コスト(未竣工工番のみ) マイナス1億ルピア以上、かつ出来高GAP額マイナス1億ルピア以上
Progress GAP, Billing - Cost only continue projects over -100 milion RP and Progress GAP under -100 milion RP
28 435,474,212,928 367,899,327,440 364,215,172,106 322,854,060,273 41,361,111,833 (19,204,706,742) 14,261,352,532 1,677,175,000
Target Billing
件数 工事番号 工事件名 受注先 契約額 実行予算 利益率 請求額 コスト 請求-コスト 請求進捗 原価進捗 出来高GAP Billing (Target) 理由 担当者 理由
Profit Billing Cost Billing - Cost Progress Cost Progress Progress GAP in June'25 June'25 May'25 May'25
No. Project No. Project Name Contract Name Customer Contract Amount BPP Target Billing Reason in June'25 PIC Reason in May'25
Ratio ① ② ①-② Billing Progress GAP Rupiah (Already Issue) (Target) (Already Issue) (Target)
VARIOUS PLANT-Q3-KIIC YAMAHA MOTOR PARTS YAMAHA MOTOR PARTS BAST circulation of sign by YPMI, target billing on K. Shimonuri/Rony Already submit BAST, target billing on May
23 202418036 18 4,301,400,000 3,430,931,332 20.24% 4,020,300,000 3,368,676,510 651,623,490 93.5% 98.2% -4.7% (203,050,379) June 2025 133,200,000 - 133,200,000
KARAWANG MANUFACTURING INDONESIA MANUFACTURING INDONESIA June 2025 Rp. 133.200.000,- (YPMI) T./Giri S. Rp. 133.200.000,- (YPMI)
Waiting Vendor Machine from China Problem VISA Finish works on Middle June 2025, Target
SUMIDEN SERASI WIRE SUMIDEN SERASI WIRE (information by PIC) start on early of July 2025, K. Shimonuri/Arie A./ Invoice on end June 2025, Amount Rp.
25 202418026 18 VARIOUS PLANT-Q2-BOGOR 1,319,000,000 1,083,720,000 17.84% 629,000,000 640,979,600 (11,979,600) 47.7% 59.1% -11.5% (151,138,866) Aug 2025 - -
PRODUCTS PRODUCTS and Billing on Middle August 2025 Rp. Novi H. 690,000.000,- waiting vendor
690,000,000.- machine(early jun'25)
SUMITOMO ELECTRIC SUMITOMO ELECTRIC WINTEC Already issued invoice on June 03, 2025 Rp. Already issued invoice Rp. 261,700,000.-
VARIOUS PLANT-Q4-MM2100 WINTEC INDONESIA, EMBLEM INDONESIA, EMBLEM ASIA, TD 29,600,000.-(SEWI Project) Other waiting sign K. Shimonuri/Rizqi N./ on May 21, 2025, for: Ondo Metal Rp.
27 202418050 18 3,318,300,000 2,728,739,354 17.77% 3,005,700,000 2,572,810,929 432,889,071 90.6% 94.3% -3.7% (122,982,295) 3-Jun-25 29,600,000 131,500,000 261,700,000 -
CIBITUNG ASIA, TD AUTOMOTIVE AUTOMOTIVE COMPRESSOR completion NSK Project Rp. 21,500,000.- & Umar Riadhi 255.400.000,- andNSK Project Rp.
COMPRESSOR INDONESIA INDONESIA 110,000,000.- target billing June 2025 6.300.000,-
Balance---> (4,943,354,210)
74%
Page 9 of 12
仮受注比率9%以上、3か月未満(仮受注比率100%及び雑小案件除く)
Tentative contract (Add Work) >9%、Less than 3 Month (excl tentative contract 100% and Various Project)
0 -
受領 受領
件数 工事番号 工事件名 受注先 作業内容 暫定契約の証拠 推定数 仮受注金額 コスト 作業進捗 経過日 理由 担当者 仮受注金額 理由
(予定) (予定)
Contract
Total Contract Total FIX Work Received Tentative Received
No Project No Project Name Customer Description Evidence of Tentative Contract Estimate Number Tentative amount Tentative Cost Day Reason in June'25 PIC Reason in May'25
Amount Contract Amount Progress (Target) Apr'25 (Target)
%
Balance---> -
3カ月以上仮受注
Tentative contract over 3 month
9 22,007,847,931 1,129,555,834
受領 受領
件数 工事番号 工事件名 受注先 作業内容 暫定契約の証拠 推定数 仮受注金額 コスト 作業進捗 経過日 理由 担当者 仮受注金額 理由
(予定) (予定)
Contract PO Received
Total FIX Contract Work Received Tentative Amount Received
No. Project No. Project Name Customer Description Evidence of Tentative Contract Estimate Number Total Contract Amount Tentative amount Tentative Cost Budget Finish Date Days Month Reason in May 2025 PIC Reason in May' 2025
Amount Progress (Target) Apr' 2025 (Target)
%
SENAYAN TRIKARYA Installation Water Purifier Apartemen Tower B ( QWCS by Already received PO on June 12, 2025 Rp. Benny S./Luterson/Bayu
3 202401024 01 APARTEMENT RENOVATION TOWER B QWCS by Mr. K. Kobayashi B1.57.00095.25A 21,450,000,000 21,400,000,000 50,000,000 0.23% - 41,250,000 100% 106 4 6/12/2025 50,000,000
SEMPANA Mr. K. Kobayashi ) 50,000,000.- H.
GTN JKT02 - TRENCH 3, L1 ( WIRING & There are postponed construction works for
4 202401087 01 PRO-MATRIX PTE LTD Electrical Works ( WI by Email from Mr. Hirosaki Sasaki ) WI by Email from Mr. Hirosaki Sasaki B1.57.4508.24B 188,633,000,000 0 12,000,000,000 6.36% 1,337,650,185 10,353,771,600 91 3 June 2025 Benny S./Vebry E./Rio S.
TERMINATION WORK ) 3~6 months for Trench-4, Mechanical &
Electrical Works. But still tried to negotiate, and
already submitted additional cost for
Preliminary about IDR.1.8 bio (3 months), and
IDR. 2.4 bio (6 months).
VARIOUS ME-Q4-SEC 5-SCS-G2 (ASTRA Modification Existing Hydrant Pipe, CA Pipe & Cable Rack ( Rustandi/Heriyanto/Andry PO on Process Jaya Obayashi target
5 202411086 11 JAYA OBAYASHI QWCS by Mr. Candra B1.57.00181.25 119,000,000 0 54,000,000 45.38% 38,018,000 45,018,000 100% 127 4 JO Still Negotiation with Owner 54,000,000 May 2025
DAIHATSU MOTOR) QWCS by Mr. Candra ) A. received PO end May 2025
Additional Installation Work for BOPP-3 until 30 November K. Shimonuri/Rony on process procurement, target PO on
WI by Whatsupp form Mr. Adi Wirawan B1.57.04484.24A 498,000,000 13.48% 364,367,000 384,412,089 100% 124 4 Online meeting has been done 02/06/2025, 498,000,000 May 2025
2024 ( WI by Whatsupp form Mr. Adi Wirawan ) Teguh/M. Arifudin L. May 2025
then confirmation final price already info, still
INDOPOLY SWAKARSA waiting for feedback from Indopoly (TOP
6 202408018 08 INDOPOLY SWAKARSA INDUSTRY 3,693,860,000 2,545,660,000.00
INDUSTRY Management Approval).
(additional work) ---> Customer under review
Additional Overtime Installation Work for BOPP-3 until 30 K. Shimonuri/Rony on process procurement, target PO on
WI by Whatsupp form Mr. Adi Wirawan B1.57.04485.24C 650,200,000 17.60% 487,847,969 552,400,000 100% 124 4 man power cost by Purchasing Director. 650,200,000 May 2025
November 2024 ( WI by Whatsup Mr. Adi Wirawan ) Teguh/M. Arifudin L. May 2025
Instalaltion LV Switchboard and Instrument Panel ( WI by Will be issued DM on June 2025 for cancel this
WI by LOI No. 020/JO-HO/JKT09/XII/2024 K. Shimonuri/Rony Will be canceled because work is
7 202408035 08 DATA CENTER JKT-09 JAYA OBAYASHI LOI No. 020/JO-HO/JKT09/XII/2024 with Sign Mr. Hiroyuki B1.57.02671.24A 4,900,000,000 0 4,900,000,000 100.00% 4,155,500 4,163,378,000 149 5 tentative contract because work is suspended, -
with Sign Mr. Hiroyuki Kunita Teguh/Widi suspended, Lock for Cost
Kunita ) Lock for Cost. (Panel work)
Balance---> 20,878,292,097
More than 9% 5%
未請求リテンション
Unbilled Retention
4 4,047,115,000 0
請求 入金
件数 工事番号 工事件名 竣工月 受注先 契約額 リテンション残高 リテンション期日 担当者 リテンション期日
(予定) (予定)
Contract Warranty 2 Years from 12 September 2024 until 12 Contract Warranty 2 Years from 12 September 2024 until 12
1 202301021 DENPASAR RESIDENCE Dec-24 KAJIMA INDONESIA 9,000,000,000 410,000,000 Oct 2026 September 2026, TSRT will submit retention completion after Benny S./Vebry/Christ September 2026, TSRT will submit retention completion after
inspection with Kajima. inspection with Kajima.
Retention payment due date 1 year after completion (Due Retention payment due date 1 year after completion (Due
REPLACEMENT AC APARTEMENT TOWER Benny S./Luterson/Bayu
2 202301067 Dec-24 SENAYAN TRIKARYA SEMPANA 9,590,000,000 479,500,000 Jan 2026 Jan 2026 Date : December 2025) --> Target billing Jan'26 Rp. Date : December 2025) --> Target billing Jan'26 Rp.
B H.
479,500,000.- 479,500,000.-
APARTEMENT PLAZA SENAYAN TOWER A Retention payment due date 6 Month after completion, target Benny S./Luterson/Bayu Retention payment due date 6 Month after completion, target
3 202301062 Mar-25 SENAYAN TRIKARYA SEMPANA 852,300,000 42,615,000 Sep 2025 Sep 2025
&B billing September 2025 Rp. 42,615,000.- H. billing September 2025 Rp. 42,615,000.-
There are remaining Punchlist; must repair the PVC leaks due to
K. Shimonuri/Rizqi the punchlist will be completed in May 2025, billing target May
4 202308009 DJARUM Mar-25 DJARUM 81,876,500,000 3,115,000,000 July 2025 overheated, there are 2 areas of work. Will be completed this
N./Irvan Azra 2025 Rp. 3,115,000,000.-
month, target billing end June or latest, by July 2025.
4,047,115,000