The program status is green with $6.7 million (52%) of the budget remaining. There are 13 active projects and 2 at risk projects. Overall the projects are on track from a scope, schedule, and budget perspective with the exception of some capability assessment work for the Service Platform. Resource requests have been fulfilled and the remaining budget will be spent by mid-October. Some data integrity issues between systems are being addressed as a risk for the Service Platform.