Concept of ATC Loss Calculation
(By Jayant Sinha, DGM (IT))

In absence of feeder metering in the past, substantial portion of T&D loss,
including theft of electricity was attributed to agricultural consumption. While,
agricultural consumption was around 20-25%, utilities were showing it as 35-40%
and correspondingly T&D losses were shown as 20-25%. Also, T&D loss was being
computed by showing electricity bills issued to consumers as accrued income, and
not on the basis of actual collection. Therefore, T&D loss figures did not capture
the major gap between the billing and the collection, over and above large scale of
theft. To get over this problem, the concept of Aggregate Technical & Commercial
(ATC) loss was introduced.
ATC Loss calculation
It is the difference between energy input units into the system and the units for
which the payment is collected.
T&D Loss do not capture losses on account of non-realisation of payments.
ATC Loss is the actual measure of overall efficiency of the distribution business as
it measures both technical as well as commercial losses.

ATC Loss(%) = (Energy Input – Energy Realised)X100
Energy Input
Energy Realised = Energy Billed X Collection Efficiency
Collection Efficiency (%) =

Amount Realised X100
Amount Billed

Main reasons for Technical Losses
• Overloading of existing lines and substation equipments
• Absence of up gradation of old lines and equipments
• Low HT: LT ratio
• Poor repair and maintenance of equipments
• Non-installation of capacitors for power factor correction
Main reasons for Commercial Losses
• Low metering/ billing/ collection efficiency
• Theft of electricity by illegal connection
• Tampering of metering system
• Low accountability of employees and corruption
• Absence of Energy Audit and Accounting

More Related Content

PDF
Location | property tax management
Steven Eady
 
PDF
TPS FINAL REDACTED
Bryant Kuehner
 
PDF
Assessable Cost Allocation | Linear & Land Considerations
Steven Eady
 
PPTX
Making tax digital
Catherine Machalinski ACMA
 
PPTX
Real-Time Economy Penttinen 2013
Esko Penttinen
 
PDF
Wise Men offerings in Energy & utilities
Wise Men
 
PDF
What to consider when integrating energy into Facilities Management
eSightEnergy
 
PPT
AT & C LOSSES
Agam Deep
 
Location | property tax management
Steven Eady
 
TPS FINAL REDACTED
Bryant Kuehner
 
Assessable Cost Allocation | Linear & Land Considerations
Steven Eady
 
Making tax digital
Catherine Machalinski ACMA
 
Real-Time Economy Penttinen 2013
Esko Penttinen
 
Wise Men offerings in Energy & utilities
Wise Men
 
What to consider when integrating energy into Facilities Management
eSightEnergy
 
AT & C LOSSES
Agam Deep
 

Similar to Wp 5-concept of atc loss calculation (20)

PPT
TRANSMISSION AND DISTRIBUTION LOSSES IN POWER SYSTEM
pavanganwgar
 
PPTX
At&C loss 66 batch Aryabhatta of registration
Er. Bhavik Dholakia
 
PPTX
MODERN ATC
CMA Jitendra Ahire
 
PDF
Data
Ranjith Kumar
 
PDF
BRIEFING NOTE: IMPACT OF ROOFTOP SOLAR BY C&I CONSUMERS ON TANGEDCO’S FINANCES
AurovilleConsulting
 
PDF
Cost Segregation Analysis - The Emerging Practice Of Quantity Surveyors And ...
theijes
 
PPTX
AT&C LOSSES In RAPDRP
Abhishek Kumar
 
PPT
A Presentation on ARR & Tariff Proposal of CESU for FY 2007-08
mymailspramod
 
PPT
Tariff
MdSazibMollik
 
PPT
CESU_07-08_Staff_Presentation_during_hearing.ppt
MdSazibMollik
 
PPT
Rotating.ppt
MdSazibMollik
 
PDF
Power plus distribution new
Shivansh Tyagi
 
PDF
Power plus distribution new
Shivansh Tyagi
 
PDF
An Energy Fraud Detection Scheme for Power Utilities
IJERA Editor
 
PPTX
C H A P T E R 6 T H E O R Y O F C O S T
Ejarn Jijan
 
PPT
Activity based costing
Rahul Kumar
 
PDF
BRIEFING NOTE: RECOVERY OF TANGEDCO’S FIXED COSTS FOR GENERATION, DISTRIBUTIO...
AurovilleConsulting
 
PPT
Chapter 3 presentation
dphil002
 
PPT
theory of Cost nbvyvbjbjbvyvvbugughih.ppt
HarithasVadali2
 
PPT
Graduation Presentation
aburakan69
 
TRANSMISSION AND DISTRIBUTION LOSSES IN POWER SYSTEM
pavanganwgar
 
At&C loss 66 batch Aryabhatta of registration
Er. Bhavik Dholakia
 
MODERN ATC
CMA Jitendra Ahire
 
BRIEFING NOTE: IMPACT OF ROOFTOP SOLAR BY C&I CONSUMERS ON TANGEDCO’S FINANCES
AurovilleConsulting
 
Cost Segregation Analysis - The Emerging Practice Of Quantity Surveyors And ...
theijes
 
AT&C LOSSES In RAPDRP
Abhishek Kumar
 
A Presentation on ARR & Tariff Proposal of CESU for FY 2007-08
mymailspramod
 
CESU_07-08_Staff_Presentation_during_hearing.ppt
MdSazibMollik
 
Rotating.ppt
MdSazibMollik
 
Power plus distribution new
Shivansh Tyagi
 
Power plus distribution new
Shivansh Tyagi
 
An Energy Fraud Detection Scheme for Power Utilities
IJERA Editor
 
C H A P T E R 6 T H E O R Y O F C O S T
Ejarn Jijan
 
Activity based costing
Rahul Kumar
 
BRIEFING NOTE: RECOVERY OF TANGEDCO’S FIXED COSTS FOR GENERATION, DISTRIBUTIO...
AurovilleConsulting
 
Chapter 3 presentation
dphil002
 
theory of Cost nbvyvbjbjbvyvvbugughih.ppt
HarithasVadali2
 
Graduation Presentation
aburakan69
 
Ad

Wp 5-concept of atc loss calculation

  • 1. Concept of ATC Loss Calculation (By Jayant Sinha, DGM (IT)) In absence of feeder metering in the past, substantial portion of T&D loss, including theft of electricity was attributed to agricultural consumption. While, agricultural consumption was around 20-25%, utilities were showing it as 35-40% and correspondingly T&D losses were shown as 20-25%. Also, T&D loss was being computed by showing electricity bills issued to consumers as accrued income, and not on the basis of actual collection. Therefore, T&D loss figures did not capture the major gap between the billing and the collection, over and above large scale of theft. To get over this problem, the concept of Aggregate Technical & Commercial (ATC) loss was introduced. ATC Loss calculation It is the difference between energy input units into the system and the units for which the payment is collected. T&D Loss do not capture losses on account of non-realisation of payments. ATC Loss is the actual measure of overall efficiency of the distribution business as it measures both technical as well as commercial losses. ATC Loss(%) = (Energy Input – Energy Realised)X100 Energy Input Energy Realised = Energy Billed X Collection Efficiency Collection Efficiency (%) = Amount Realised X100 Amount Billed Main reasons for Technical Losses • Overloading of existing lines and substation equipments • Absence of up gradation of old lines and equipments • Low HT: LT ratio • Poor repair and maintenance of equipments • Non-installation of capacitors for power factor correction Main reasons for Commercial Losses • Low metering/ billing/ collection efficiency • Theft of electricity by illegal connection • Tampering of metering system • Low accountability of employees and corruption • Absence of Energy Audit and Accounting