Project Management
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 2
Objectives
 To explain the main tasks undertaken by project
managers
 To introduce software project management and to
describe its distinctive characteristics
 To discuss project planning and the planning process
 To show how graphical schedule representations are
used by project management
 To discuss the notion of risks and the risk
management process
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 3
Topics covered
 Management Activities
 Project Planning
 Project Scheduling
 Risk Management
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 4
 Concerned with activities involved in ensuring
that software is delivered on time and on
schedule and in accordance with the
requirements of the organisations developing
and procuring the software.
 Project management is needed because
software development is always subject to
budget and schedule constraints that are set
by the organisation developing the software.
Software project management
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 5
 The product is intangible.
 The product is uniquely flexible.
 Software engineering is not recognized as an
engineering discipline with the sane status as
mechanical, electrical engineering, etc.
 The software development process is not
standardised.
 Many software projects are 'one-off' projects.
Software management distinctions
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 6
 Proposal Writing.
 Project Planning and Scheduling.
 Project Costing.
 Project Monitoring and Reviews.
 Personnel Selection and Evaluation.
 Report Writing and Presentations.
Management activities
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 7
 These activities are not peculiar to software
management.
 Many techniques of engineering project
management are equally applicable to
software project management.
 Technically complex engineering systems tend
to suffer from the same problems as software
systems.
Management commonalities
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 8
Project staffing
 May not be possible to appoint the ideal people to work
on a project
• Project budget may not allow for the use of highly-paid
staff;
• Staff with the appropriate experience may not be
available;
• An organisation may wish to develop employee skills
on a software project.
 Managers have to work within these constraints
especially when there are shortages of trained staff.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 9
Project planning
 Probably the most time-consuming project
management activity.
 Continuous activity from initial concept through
to system delivery. Plans must be regularly
revised as new information becomes available.
 Various different types of plan may be
developed to support the main software project
plan that is concerned with schedule and
budget.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 10
Types of project plan
Plan Description
Quality plan Describes the quality procedures and standards that will be
used in a project. See Chapter 27.
Validation plan Describes the approach, resources and schedule used for
system validation. See Chapter 22.
Configuration
management plan
Describes the configuration management procedures and
structures to be used. See Chapter 29.
Maintenance plan Predicts the maintenance requirements of the system,
maintenance costs and effort required. See Chapter 21.
Staff development
plan.
Describes how the skills and experience of the project team
members will be developed. See Chapter 25.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 11
Project planning process
Establish the project constraints
Make initial assessments of the project parameters
Define project milestones and deliverables
while project has not been completed or cancelled loop
Draw up project schedule
Initiate activities according to schedule
Wait ( for a while )
Review project progress
Revise estimates of project parameters
Update the project schedule
Re-negotiate project constraints and deliverables
if ( problems arise ) then
Initiate technical review and possible revision
end if
end loop
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 12
The project plan
 The project plan sets out:
• The resources available to the project;
• The work breakdown;
• A schedule for the work.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 13
Project plan structure
 Introduction.
 Project organisation.
 Risk analysis.
 Hardware and software resource
requirements.
 Work breakdown.
 Project schedule.
 Monitoring and reporting mechanisms.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 14
Activity organization
 Activities in a project should be organised to
produce tangible outputs for management to
judge progress.
 Milestones are the end-point of a process
activity.
 Deliverables are project results delivered to
customers.
 The waterfall process allows for the
straightforward definition of progress
milestones.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 15
Milestones in the RE process
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 16
Project scheduling
 Split project into tasks and estimate time and
resources required to complete each task.
 Organize tasks concurrently to make optimal
use of workforce.
 Minimize task dependencies to avoid delays
caused by one task waiting for another to
complete.
 Dependent on project managers intuition and
experience.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 17
The project scheduling process
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 18
Scheduling problems
 Estimating the difficulty of problems and hence
the cost of developing a solution is hard.
 Productivity is not proportional to the number
of people working on a task.
 Adding people to a late project makes it later
because of communication overheads.
 The unexpected always happens. Always
allow contingency in planning.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 19
Bar charts and activity networks
 Graphical notations used to illustrate the
project schedule.
 Show project breakdown into tasks. Tasks
should not be too small. They should take
about a week or two.
 Activity charts show task dependencies and
the the critical path.
 Bar charts show schedule against calendar
time.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 20
Task durations and dependencies
Activity Duration (days) Dependencies
T1 8
T2 15
T3 15 T1 (M1)
T4 10
T5 10 T2, T4 (M2)
T6 5 T1, T2 (M3)
T7 20 T1 (M1)
T8 25 T4 (M5)
T9 15 T3, T6 (M4)
T10 15 T5, T7 (M7)
T11 7 T9 (M6)
T12 10 T11 (M8)
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 21
Activity network
star t
T2
M3
T6
Finish
T10
M7
T5
T7
M2
T4
M5
T8
4/7 /03
8 da ys
14/7 /03 15 da ys
4/8/03
15 da ys
25/8/03
7 da ys
5/9/03
10da ys
19/9/03
15 da ys
11/8/03
25 da ys
10 da ys
20 da ys
5 da ys
25/7 /03
15 da ys
25/7 /03
18/7 /03
10 da ys
T1
M1 T3
T9
M6
T11
M8
T1
2
M4
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 22
Activity timeline
4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9
T4
T1
T2
M1
T7
T3
M5
T8
M3
M2
T6
T5
M4
T9
M7
T1
0
M6
T1
1
M8
T1
2
Star t
Finish
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 23
Staff allocation
4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9
T4
T8 T1
1
T12
T1
T3
T9
T2
T6 T1
0
T7
T5
Fred
Jane
Anne
Mary
Jim
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 24
Risk management
 Risk management is concerned with
identifying risks and drawing up plans to
minimise their effect on a project.
 A risk is a probability that some adverse
circumstance will occur
• Project risks affect schedule or resources;
• Product risks affect the quality or performance of
the software being developed;
• Business risks affect the organisation developing
or procuring the software.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 25
Software risks
Risk Affects Description
Staff turnover Project Experienced staff will leave the project before it is finished.
Management change Project There will be a change of organisational management with
different priorities.
Hardware unavailability Project Hardware that is essential for the project will not be
delivered on schedule.
Requirements change Project and
product
There will be a larger number of changes to the
requirements than anticipated.
Specification delays Project and
product
Specifications of essential interfaces are not available on
schedule
Size underestimate Project and
product
The size of the system has been underestimated.
CASE tool under-
performance
Product CASE tools which support the project do not perform as
anticipated
Technology change Business The underlying technology on which the system is built is
superseded by new technology.
Product competition Business A competitive product is marketed before the system is
completed.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 26
The risk management process
 Risk Identification
• Identify project, product and business risks;
 Risk Analysis
• Assess the likelihood and consequences of these
risks;
 Risk Planning
• Draw up plans to avoid or minimise the effects of
the risk;
 Risk Monitoring
• Monitor the risks throughout the project;
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 27
The risk management process
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 28
Risk identification
 Technology risks.
 People risks.
 Organisational risks.
 Requirements risks.
 Estimation risks.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 29
Risks and risk types
Risk type Possible risks
Technology The database used in the system cannot process as many transactions per second
as expected.
Software components that should be reused contain defects that limit their
functionality.
People It is impossible to recruit staff with the skills required.
Key staff are ill and unava ilable at critical times.
Required training for staff is not available.
Organisational The organisation is restructured so that different management are responsible for
the project.
Organisational financial problems force reductions in the project budge t.
Tools The code generated by CASE tools is inefficient.
CASE tools canno t be integrated.
Requirements Changes to requirements that require major design rework are proposed.
Customers fail to understand the impact of requirements change s.
Estimation The time required to deve lop the software is underestimated.
The rate of defect repair is underestimated.
The size of the software is underestimated.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 30
Risk analysis
 Assess probability and seriousness of each
risk.
 Probability may be very low, low, moderate,
high or very high.
 Risk effects might be catastrophic, serious,
tolerable or insignificant.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 31
Risk analysis (i)
Risk Probabilit
y Effects
Organisational financial problems force reductions in
the project budge t.
Low Catastrophic
It is impossible to recruit staff with the skills required
for the project.
High Catastrophic
Key staff are ill at critical times in the project. Moderate Serious
Software components that should be reused contain
defects which limit their functionality.
Moderate Serious
Changes to requirements that require major design
rework are proposed.
Moderate Serious
The organisation is restructured so that different
manage ment are responsible for the project.
High Serious
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 32
Risk analysis (ii)
Risk Probabilit
y Effects
The database used in the system cannot process as
many transactions per second as expec ted.
Moderate Serious
The time required to deve lop the software is
underestimated.
High Serious
CASE tools canno t be integrated. High Tolerable
Customers fail to understand the impact of
requirements change s.
Moderate Tolerable
Required training for staff is not available. Moderate Tolerable
The rate of defect repair is underestimated. Moderate Tolerable
The size of the software is underestimated. High Tolerable
The code generated by CASE tools is inefficient. Moderate Insignificant
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 33
Risk planning
 Consider each risk and develop a strategy to
manage that risk.
 Avoidance strategies
• The probability that the risk will arise is reduced;
 Minimisation strategies
• The impact of the risk on the project or product will
be reduced;
 Contingency plans
• If the risk arises, contingency plans are plans to
deal with that risk;
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 34
Risk management strategies (i)
Risk Strategy
Organisational
financial problems
Prepare a briefing document for senior manage ment
showing how th e project is making a very important
contribution to the goals of the business.
Recruitment
problems
Alert customer of potential difficulties and the
possibility of delays, investigate buying-in
components.
Staff illness Reorganise team so that there is more overlap of work
and people therefore understand each other’s jobs.
Defective
components
Replace potentially defective components with bough t-
in components of known reliability.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 35
Risk management strategies (ii)
Risk Strategy
Requirements
changes
Derive traceability information to assess requirements
change impact, maximise information hiding in the
design.
Organisational
restructuring
Prepare a briefing document for senior manage ment
showing how th e project is making a very important
contribution to the goals of the business.
Database
performance
Investigate the possibility of buying a higher-
performance database.
Underestimated
development time
Investigate buying in components, inve stigate use of a
program generator
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 36
Risk monitoring
 Assess each identified risks regularly to decide
whether or not it is becoming less or more
probable.
 Also assess whether the effects of the risk
have changed.
 Each key risk should be discussed at
management progress meetings.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 37
Risk indicators
Risk type Potential indicators
Technology Late delivery of hardware or support software, many reported
technology problems
People Poor staff morale, poor relationships amongst team member,
job availability
Organisational Organisational gossip, lack of action by senior management
Tools Reluctance by team members to use tools, complaints about
CASE tools, demands for higher-powered workstations
Requirements Many requirements change requests, customer complaints
Estimation Failure to meet agreed schedule, failure to clear reported
defects
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 38
Key points
 Good project management is essential for project
success.
 The intangible nature of software causes problems for
management.
 Managers have diverse roles but their most significant
activities are planning, estimating and scheduling.
 Planning and estimating are iterative processes
which continue throughout the course of a
project.
©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 39
 A project milestone is a predictable state
where a formal report of progress is presented
to management.
 Project scheduling involves preparing various
graphical representations showing project
activities, their durations and staffing.
 Risk management is concerned with
identifying risks which may affect the project
and planning to ensure that these risks do not
develop into major threats.
Key points

More Related Content

PPT
Unit-3-Risk-mgmt.ppt
PPT
project managnement.ppt
PDF
ch5.pdf
PDF
Software Engineering - Ch5
PPT
PPT
Project Management (Soft)
PPT
Project-management.ppt
PPT
ch04.ppt
Unit-3-Risk-mgmt.ppt
project managnement.ppt
ch5.pdf
Software Engineering - Ch5
Project Management (Soft)
Project-management.ppt
ch04.ppt

Similar to Project Management.pdf (20)

PPT
Project Scheduling, Planning and Risk Management
PPT
ch04 all about software project managen
PPT
PROJECT MANAGEMENT
PPT
project management in software engineering
PPT
Project management
PPTX
04. Project planning and management.pptx
PPT
Ch5 - Project Management
PPT
Chapitulo 5
PPT
PPT
PPTX
Project Management System Architecture for Today
PDF
SE_Chapterrrrrrrrrrrrrrrrrrrrrrrrrr3.pdf
PPT
8.project management chapter 8
PPT
GATPO_Software.ppt
PDF
PDF
Cs414 lec1 f2014
PDF
Computer current applications
Project Scheduling, Planning and Risk Management
ch04 all about software project managen
PROJECT MANAGEMENT
project management in software engineering
Project management
04. Project planning and management.pptx
Ch5 - Project Management
Chapitulo 5
Project Management System Architecture for Today
SE_Chapterrrrrrrrrrrrrrrrrrrrrrrrrr3.pdf
8.project management chapter 8
GATPO_Software.ppt
Cs414 lec1 f2014
Computer current applications
Ad

Recently uploaded (20)

PPTX
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
PPTX
Unit IImachinemachinetoolopeartions.pptx
DOCX
An investigation of the use of recycled crumb rubber as a partial replacement...
DOCX
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
PPT
Programmable Logic Controller PLC and Industrial Automation
PDF
Mechanics of materials week 2 rajeshwari
PPTX
Chapter-8 Introduction to Quality Standards.pptx
PPTX
Micro1New.ppt.pptx the main themes if micro
PPTX
chapter 1.pptx dotnet technology introduction
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PPT
UNIT-I Machine Learning Essentials for 2nd years
PPTX
DATA STRCUTURE LABORATORY -BCSL305(PRG1)
PPTX
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
PDF
IAE-V2500 Engine for Airbus Family 319/320
PPTX
MAD Unit - 3 User Interface and Data Management (Diploma IT)
PDF
Micro 4 New.ppt.pdf a servay of cells and microorganism
PPTX
Design ,Art Across Digital Realities and eXtended Reality
PPTX
Wireless sensor networks (WSN) SRM unit 2
PDF
ASPEN PLUS USER GUIDE - PROCESS SIMULATIONS
PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
Unit IImachinemachinetoolopeartions.pptx
An investigation of the use of recycled crumb rubber as a partial replacement...
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
Programmable Logic Controller PLC and Industrial Automation
Mechanics of materials week 2 rajeshwari
Chapter-8 Introduction to Quality Standards.pptx
Micro1New.ppt.pptx the main themes if micro
chapter 1.pptx dotnet technology introduction
Environmental studies, Moudle 3-Environmental Pollution.pptx
UNIT-I Machine Learning Essentials for 2nd years
DATA STRCUTURE LABORATORY -BCSL305(PRG1)
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
IAE-V2500 Engine for Airbus Family 319/320
MAD Unit - 3 User Interface and Data Management (Diploma IT)
Micro 4 New.ppt.pdf a servay of cells and microorganism
Design ,Art Across Digital Realities and eXtended Reality
Wireless sensor networks (WSN) SRM unit 2
ASPEN PLUS USER GUIDE - PROCESS SIMULATIONS
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
Ad

Project Management.pdf

  • 1. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 1 Project Management
  • 2. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 2 Objectives  To explain the main tasks undertaken by project managers  To introduce software project management and to describe its distinctive characteristics  To discuss project planning and the planning process  To show how graphical schedule representations are used by project management  To discuss the notion of risks and the risk management process
  • 3. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 3 Topics covered  Management Activities  Project Planning  Project Scheduling  Risk Management
  • 4. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 4  Concerned with activities involved in ensuring that software is delivered on time and on schedule and in accordance with the requirements of the organisations developing and procuring the software.  Project management is needed because software development is always subject to budget and schedule constraints that are set by the organisation developing the software. Software project management
  • 5. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 5  The product is intangible.  The product is uniquely flexible.  Software engineering is not recognized as an engineering discipline with the sane status as mechanical, electrical engineering, etc.  The software development process is not standardised.  Many software projects are 'one-off' projects. Software management distinctions
  • 6. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 6  Proposal Writing.  Project Planning and Scheduling.  Project Costing.  Project Monitoring and Reviews.  Personnel Selection and Evaluation.  Report Writing and Presentations. Management activities
  • 7. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 7  These activities are not peculiar to software management.  Many techniques of engineering project management are equally applicable to software project management.  Technically complex engineering systems tend to suffer from the same problems as software systems. Management commonalities
  • 8. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 8 Project staffing  May not be possible to appoint the ideal people to work on a project • Project budget may not allow for the use of highly-paid staff; • Staff with the appropriate experience may not be available; • An organisation may wish to develop employee skills on a software project.  Managers have to work within these constraints especially when there are shortages of trained staff.
  • 9. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 9 Project planning  Probably the most time-consuming project management activity.  Continuous activity from initial concept through to system delivery. Plans must be regularly revised as new information becomes available.  Various different types of plan may be developed to support the main software project plan that is concerned with schedule and budget.
  • 10. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 10 Types of project plan Plan Description Quality plan Describes the quality procedures and standards that will be used in a project. See Chapter 27. Validation plan Describes the approach, resources and schedule used for system validation. See Chapter 22. Configuration management plan Describes the configuration management procedures and structures to be used. See Chapter 29. Maintenance plan Predicts the maintenance requirements of the system, maintenance costs and effort required. See Chapter 21. Staff development plan. Describes how the skills and experience of the project team members will be developed. See Chapter 25.
  • 11. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 11 Project planning process Establish the project constraints Make initial assessments of the project parameters Define project milestones and deliverables while project has not been completed or cancelled loop Draw up project schedule Initiate activities according to schedule Wait ( for a while ) Review project progress Revise estimates of project parameters Update the project schedule Re-negotiate project constraints and deliverables if ( problems arise ) then Initiate technical review and possible revision end if end loop
  • 12. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 12 The project plan  The project plan sets out: • The resources available to the project; • The work breakdown; • A schedule for the work.
  • 13. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 13 Project plan structure  Introduction.  Project organisation.  Risk analysis.  Hardware and software resource requirements.  Work breakdown.  Project schedule.  Monitoring and reporting mechanisms.
  • 14. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 14 Activity organization  Activities in a project should be organised to produce tangible outputs for management to judge progress.  Milestones are the end-point of a process activity.  Deliverables are project results delivered to customers.  The waterfall process allows for the straightforward definition of progress milestones.
  • 15. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 15 Milestones in the RE process
  • 16. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 16 Project scheduling  Split project into tasks and estimate time and resources required to complete each task.  Organize tasks concurrently to make optimal use of workforce.  Minimize task dependencies to avoid delays caused by one task waiting for another to complete.  Dependent on project managers intuition and experience.
  • 17. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 17 The project scheduling process
  • 18. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 18 Scheduling problems  Estimating the difficulty of problems and hence the cost of developing a solution is hard.  Productivity is not proportional to the number of people working on a task.  Adding people to a late project makes it later because of communication overheads.  The unexpected always happens. Always allow contingency in planning.
  • 19. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 19 Bar charts and activity networks  Graphical notations used to illustrate the project schedule.  Show project breakdown into tasks. Tasks should not be too small. They should take about a week or two.  Activity charts show task dependencies and the the critical path.  Bar charts show schedule against calendar time.
  • 20. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 20 Task durations and dependencies Activity Duration (days) Dependencies T1 8 T2 15 T3 15 T1 (M1) T4 10 T5 10 T2, T4 (M2) T6 5 T1, T2 (M3) T7 20 T1 (M1) T8 25 T4 (M5) T9 15 T3, T6 (M4) T10 15 T5, T7 (M7) T11 7 T9 (M6) T12 10 T11 (M8)
  • 21. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 21 Activity network star t T2 M3 T6 Finish T10 M7 T5 T7 M2 T4 M5 T8 4/7 /03 8 da ys 14/7 /03 15 da ys 4/8/03 15 da ys 25/8/03 7 da ys 5/9/03 10da ys 19/9/03 15 da ys 11/8/03 25 da ys 10 da ys 20 da ys 5 da ys 25/7 /03 15 da ys 25/7 /03 18/7 /03 10 da ys T1 M1 T3 T9 M6 T11 M8 T1 2 M4
  • 22. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 22 Activity timeline 4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9 T4 T1 T2 M1 T7 T3 M5 T8 M3 M2 T6 T5 M4 T9 M7 T1 0 M6 T1 1 M8 T1 2 Star t Finish
  • 23. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 23 Staff allocation 4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9 T4 T8 T1 1 T12 T1 T3 T9 T2 T6 T1 0 T7 T5 Fred Jane Anne Mary Jim
  • 24. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 24 Risk management  Risk management is concerned with identifying risks and drawing up plans to minimise their effect on a project.  A risk is a probability that some adverse circumstance will occur • Project risks affect schedule or resources; • Product risks affect the quality or performance of the software being developed; • Business risks affect the organisation developing or procuring the software.
  • 25. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 25 Software risks Risk Affects Description Staff turnover Project Experienced staff will leave the project before it is finished. Management change Project There will be a change of organisational management with different priorities. Hardware unavailability Project Hardware that is essential for the project will not be delivered on schedule. Requirements change Project and product There will be a larger number of changes to the requirements than anticipated. Specification delays Project and product Specifications of essential interfaces are not available on schedule Size underestimate Project and product The size of the system has been underestimated. CASE tool under- performance Product CASE tools which support the project do not perform as anticipated Technology change Business The underlying technology on which the system is built is superseded by new technology. Product competition Business A competitive product is marketed before the system is completed.
  • 26. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 26 The risk management process  Risk Identification • Identify project, product and business risks;  Risk Analysis • Assess the likelihood and consequences of these risks;  Risk Planning • Draw up plans to avoid or minimise the effects of the risk;  Risk Monitoring • Monitor the risks throughout the project;
  • 27. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 27 The risk management process
  • 28. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 28 Risk identification  Technology risks.  People risks.  Organisational risks.  Requirements risks.  Estimation risks.
  • 29. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 29 Risks and risk types Risk type Possible risks Technology The database used in the system cannot process as many transactions per second as expected. Software components that should be reused contain defects that limit their functionality. People It is impossible to recruit staff with the skills required. Key staff are ill and unava ilable at critical times. Required training for staff is not available. Organisational The organisation is restructured so that different management are responsible for the project. Organisational financial problems force reductions in the project budge t. Tools The code generated by CASE tools is inefficient. CASE tools canno t be integrated. Requirements Changes to requirements that require major design rework are proposed. Customers fail to understand the impact of requirements change s. Estimation The time required to deve lop the software is underestimated. The rate of defect repair is underestimated. The size of the software is underestimated.
  • 30. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 30 Risk analysis  Assess probability and seriousness of each risk.  Probability may be very low, low, moderate, high or very high.  Risk effects might be catastrophic, serious, tolerable or insignificant.
  • 31. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 31 Risk analysis (i) Risk Probabilit y Effects Organisational financial problems force reductions in the project budge t. Low Catastrophic It is impossible to recruit staff with the skills required for the project. High Catastrophic Key staff are ill at critical times in the project. Moderate Serious Software components that should be reused contain defects which limit their functionality. Moderate Serious Changes to requirements that require major design rework are proposed. Moderate Serious The organisation is restructured so that different manage ment are responsible for the project. High Serious
  • 32. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 32 Risk analysis (ii) Risk Probabilit y Effects The database used in the system cannot process as many transactions per second as expec ted. Moderate Serious The time required to deve lop the software is underestimated. High Serious CASE tools canno t be integrated. High Tolerable Customers fail to understand the impact of requirements change s. Moderate Tolerable Required training for staff is not available. Moderate Tolerable The rate of defect repair is underestimated. Moderate Tolerable The size of the software is underestimated. High Tolerable The code generated by CASE tools is inefficient. Moderate Insignificant
  • 33. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 33 Risk planning  Consider each risk and develop a strategy to manage that risk.  Avoidance strategies • The probability that the risk will arise is reduced;  Minimisation strategies • The impact of the risk on the project or product will be reduced;  Contingency plans • If the risk arises, contingency plans are plans to deal with that risk;
  • 34. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 34 Risk management strategies (i) Risk Strategy Organisational financial problems Prepare a briefing document for senior manage ment showing how th e project is making a very important contribution to the goals of the business. Recruitment problems Alert customer of potential difficulties and the possibility of delays, investigate buying-in components. Staff illness Reorganise team so that there is more overlap of work and people therefore understand each other’s jobs. Defective components Replace potentially defective components with bough t- in components of known reliability.
  • 35. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 35 Risk management strategies (ii) Risk Strategy Requirements changes Derive traceability information to assess requirements change impact, maximise information hiding in the design. Organisational restructuring Prepare a briefing document for senior manage ment showing how th e project is making a very important contribution to the goals of the business. Database performance Investigate the possibility of buying a higher- performance database. Underestimated development time Investigate buying in components, inve stigate use of a program generator
  • 36. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 36 Risk monitoring  Assess each identified risks regularly to decide whether or not it is becoming less or more probable.  Also assess whether the effects of the risk have changed.  Each key risk should be discussed at management progress meetings.
  • 37. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 37 Risk indicators Risk type Potential indicators Technology Late delivery of hardware or support software, many reported technology problems People Poor staff morale, poor relationships amongst team member, job availability Organisational Organisational gossip, lack of action by senior management Tools Reluctance by team members to use tools, complaints about CASE tools, demands for higher-powered workstations Requirements Many requirements change requests, customer complaints Estimation Failure to meet agreed schedule, failure to clear reported defects
  • 38. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 38 Key points  Good project management is essential for project success.  The intangible nature of software causes problems for management.  Managers have diverse roles but their most significant activities are planning, estimating and scheduling.  Planning and estimating are iterative processes which continue throughout the course of a project.
  • 39. ©Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 39  A project milestone is a predictable state where a formal report of progress is presented to management.  Project scheduling involves preparing various graphical representations showing project activities, their durations and staffing.  Risk management is concerned with identifying risks which may affect the project and planning to ensure that these risks do not develop into major threats. Key points