Presented
By
K.Lavanya
M.Tech
1
FORMWORK
DEFINITION:
2
 Its is an artificial support provided below and around the precast
or cast insitu concrete work.
 Formwork is commonly made of
 Steel
 wood
 Formwork construction & casting is of prime importance in
concrete industry. It share a significant amount of concrete cost.
 Formwork is designed according to The ACI document SP-4.
Qualities of formwork:
3
It should be water tight
It should be strong
It can be reusable
Its contact surface should be uniform
It should be according to the size of member.
Uses:
4
 Formwork molds the concrete to the desired
shape and size, and controls its position and
alignment.
 It is used to transfer the temporary external
loads.
Major objectives considered in formwork:
5
 Quality
 Safety
 Economy
6
 Quality:
Forms must be designed and built with sufficient stiffness and
accuracy so that the size, shape, position, and finish of the cast concrete
are maintained.
 Safety:
Forms must be built sufficient strength and factor of safety so that
they have the capable of all supporting loads.
 Economy:
Forms must be built efficiently, minimizing time and cost..
Requirements of formwork:
7
 Material should be cheap and re usable,
 It should be practically water proof, so that it should not absorb water
from concrete,
 Swelling and shrinkage should be minimum,
 Strong enough to with stand all external loads,
 Deflection should be minimum,
 Surface should be smooth, and afford easy striping,
 Light in weight, so that easy to transfer,
 Joints should be stiff, so that lateral deformation and leak is minimum .
THREE STAGES:
8
a) Assembly and erection
b) Concrete placement
c) Stripping and dismantling
TYPES OF FORMWORK:
9
Temporary Structure
Temporary structure required to safely support
concrete until it reaches adequate strength
Permanent Structure
Formwork detail for different structural
members
10
In concrete construction formwork is commonly
provided for the following structural members.
o Wall
o Column
o Slabs & Beams
o Stairs
o Chimneys
o Water tanks
o Cooling Towers
Formwork for Wall
11
 It consists of
• Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
 After completing one
side of formwork
reinforcement is
provided at the place
then the second side
formwork is provided.
Wall forms:
12
 Wall forms principally resist the lateral pressure generated by fresh
concrete as a liquid or semi liquid material.
 The pressure can be quite large, certainly many times the magnitude
of live loads on permanent floors.
 So design often involves closely spaced and well-supported members.
 Snap ties, flat ties, loop ties are single use ties usually relatively low
capacity 680 kg to 1450 kg.
 Coil ties, he bolts, she bolts are left embedded in concrete , or it can
be reused.
 The tension capacity of heavy ties around 27,230 kg.
13
Wall forms:
Formwork for Column
14
It consists of the
following
Side & End Planks
Yoke
Nut & Bolts
Two end & two side
planks are joined by the
yokes and bolts.
Column forms:
15
 Column-forms materials tend to vary with the column shape.
 Wood or steel is often used with square or rectangular column.
 Round column forms more typically pre manufactured in a range of
standard diameters, are available in steel, paper board, and fiber
reinforced plastic.
 Round column are more structural efficient compared to square, since
the internal pressures can be resisted by the hoop membrane.
 Round steel forms are generally used for larger columns and bridge
piers and come in diameters about 0.36m to 3mts..
16
Formwork for columns
17
Formwork for Slabs & beams:
18
 It consists of
Sole plates
Wedges
Props
Head tree
Planks
Batten
Ledgers
 Beam formwork
rests on head tree
 Slab form work rests
on battens and joists
 If prop height are
more than 8’ provide
horizontal braces.
Lintel or Beam Formwork:
19
FORMWORK FOR SLAB:
20
FORMWORK FOR STAIRS:
21
It consists of
Vertical & inclined
posts
Inclined members
Wooden Planks or
sheeting
Stringer
Riser Planks
FORMWORK FOR STAIRS:
22
 The sheathing or decking for deck slabs is carried on cross-
joists which are in turn supported on raking ledgers
 The ledgers are generally of 7.5cm x 10cm size .
 The cross- joists may be 5cm x 10cm size
 The riser planks are 4-5 cm thick and equal to the height
of riser
 The riser planks are placed after the reinforcement is
placed in position
FORMWORK FOR STAIRS:
23
FORMWORK FOR STAIRS:
24
FORMWORK FOR CHIMNEYS:
25
For tall chimneys two types of forms techniques are
in generally use in our country
a) Jump form
b) Slip form
26
Jump Form:
In this type jacking bars are either cast in concrete or else
are carried in tubes which are cast in concrete.
After casting a lift, concrete is allowed to set and then
the forms are raised by jacks and the next lift is cast.
Jacks are usually placed about 2m apart and are designed.
27
28
Slip Form:
The slip form method of concrete construction is used
for forming both horizontal and vertical concrete
structures.
It often used for forming highway pavements as
continuous operation.
Slip form methods is also been used for forming various
types of vertical concrete structures.
FORMWORK FOR CHIMNEYS:
29
FORMWORK FOR CHIMNEYS:
30
Removal of formwork:
31
 Time of formwork removal depends on the following factors
1. Type of Cement
1. Rapid hardening cements require lesser time as compared to OPC
(Ordinary Portland Cement)
2. Ratio of concrete mix
1. Rich ratio concrete gain strength earlier as compared to weak ratio
concrete.
3. Weather condition
1. Hydration process accelerates in hot weather conditions as compared to
cold and humid weather conditions.
Time of Removal of formwork:
32
Sr
.
N
o
Structural Member
OPC
(Ordinary
Portland
Cement)
Rapid
Hardeni
ng
Cement
1 Beam sides, walls &
Columns
2-3 Days 2 Days
2 Slab (Vertical Supports remains
intact)
4 Days 3 Days
3 Slab (Complete Formwork
removal)
10 Days 5 Days
4 Beams (Removal of Sheeting,
Props remains intact)
8 Days 5 Days
5 Beams & Arches (Complete
formwork removal) (up to 6 m span)
14 Days 5-8 Days
6 Beams & Arches (Complete
formwork removal) (more than 6 m
span)
21 Days 8-10 Days
Maintenance of formwork:
33
Due to continuous use wooden planks & steel plates
surfaces become uneven and require maintenance.
For wooden formwork use cardboard or plastic fiber
board. Bolt hole places must also be repaired.
For steel formwork plates must be leveled by mallet
and loose corners must be welded.
Cost of formwork
34
 For normal works cost of formwork is about 30%-40% of the
concrete cost.
 For special works cost of formwork is about 50%-60% of the
concrete cost.
 Formwork cost is controlled by the following factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges.
Advantages of steel form work:
35
 It can be used for a no. of times.
 It is non absorbent.
 Smooth finish surface obtained.
 No shrinkage of formwork occurs.
 Easy to use.
 Its volume is less
 Its strength is more.
LOADS ON FORMWORK:
36
Formwork is subjected to following loads:
a) Dead weight of concrete
b) Hydrostatic pressure of the concrete
c) Live load due to working laborers
d) Impact effect at the time of pouring concrete into the
formwork
e) Vibrations transmitted to formwork during pouring
concrete
FORMWORK DESIGN
37
Guiding points in the Design of formwork
 For design purpose, temporary live load due to labor and
equipment including impact may be taken from 3700N/m2
to
4000N/m2
 Dead weight of wet concrete (26000 N/m3
)
 Planks or boards used to form the vertical facing of the columns
or walls is known as sheathing whereas those used for floor slabs
are called decking
38
 The hydrostatic pressure due to fluidity of concrete in the initial stages
of pouring depends upon several factors such as amount of water, size of
aggregates, rate of pouring etc.,
 The hydrostatic pressure is maximum at the time of pouring, but after
some time it starts decreasing, as concrete starts setting and hardening.
This pressure is mainly dependent on the depth of concrete poured
before it starts setting
 Deflection of the sheathing and joists should be limited to a maximum
value of 2.5mm
Contd...
39
 The minimum wind design pressure q not less than 15 psf and
bracing should be designed for at least
w =46 kg/ft- length applied to the top
 The minimum lateral load w, for design of bracing system would
be greater than,
q .(h/2) or 46 kg/ft
Contd...
40
For design practice the maximum pressure is given by:
p = wh
Where,
p => lateral pressure of concrete,
w => unit weight of concrete,
h => depth of fluid or plastic concrete.
Contd...
41
For horizontal pressure of concrete is given by:
For walls constructing R less than 2.1m/hr;
p =150+9000(R/T)
For walls constructing R varies from 2.1m/hr to 3m/hr;
p = 150+(43,400/T)+2800(R/T)
For columns 3m/hr;
p = 150+9000(R/T)
Where, R => rate of vertical placement,
T => time for placement.
DESIGN OF SLAB FORMWORK:
42
Design of slab forms can be summarized in the following design steps:
 Step 1: Estimate design loads
 Step 2: Determine sheathing thickness and spacing of its supports (joist
spacing)
 Step 3: Determine joist size and spacing of supports (stringer spacing)
 Step 4: Determine stringer size and span (shore spacing)
 Step 5: Perform shore design to support stringers
 Step 6: Check bearing stresses
 Step 7: Design lateral bracing
43

More Related Content

PPTX
Chapter 5 formwork
PPT
Formwork
PPTX
FORMWORK.pptx
PPTX
Formwork Presentation for Construction Technology
PPTX
Formwork
PPTX
Formwork
PPTX
Formwork
Chapter 5 formwork
Formwork
FORMWORK.pptx
Formwork Presentation for Construction Technology
Formwork
Formwork
Formwork

What's hot (20)

PPTX
Formwork
PPTX
Scaffoldings
PPTX
Types of formwork
PPTX
Form-work in construction
PPTX
Formwork in civil engineering
PPTX
Brick Masonry and Stone Masonry
PPTX
Framed structures
PPT
PPTX
Presentation1
PDF
Combined footing
PPTX
Soil Properties and Foundation
PPTX
Formwork construction in structures
PPT
Properties of fresh and Hardened Concrete
PPTX
Raft foundation ppt by kamal bhatia
PPTX
Water proofing in buildings
PPTX
Stairs
PPTX
Brick masonary
PPTX
Reinforced column design
PPTX
Chapter 4 (a) stone masonry
PPTX
Buildings Structure system
Formwork
Scaffoldings
Types of formwork
Form-work in construction
Formwork in civil engineering
Brick Masonry and Stone Masonry
Framed structures
Presentation1
Combined footing
Soil Properties and Foundation
Formwork construction in structures
Properties of fresh and Hardened Concrete
Raft foundation ppt by kamal bhatia
Water proofing in buildings
Stairs
Brick masonary
Reinforced column design
Chapter 4 (a) stone masonry
Buildings Structure system
Ad

Viewers also liked (20)

PPT
Building Construction 8. formworks and scaffoldings
PPTX
Different Types of Formwork Syetem Used within Indian Construction Industry
PDF
Form Work
PPTX
Industrial training report
PPT
Formwork design vs falsework design key differences
PPT
Admixture of concrete
PPTX
Slip form Construction Technology
PPTX
Slipform
PDF
Chapter 4
PPTX
DOC
43 privet drive
PPTX
Group no 9
PPTX
Slipform construction
PPTX
Basic Scaffolding Awareness
PPT
Scaffolding
PPTX
Slip formwork technique
PPT
PreCast Construction
PPT
JUMP FORM WORK
PDF
FORM WORK AND SUPPORT WORK
DOCX
Building Construction 8. formworks and scaffoldings
Different Types of Formwork Syetem Used within Indian Construction Industry
Form Work
Industrial training report
Formwork design vs falsework design key differences
Admixture of concrete
Slip form Construction Technology
Slipform
Chapter 4
43 privet drive
Group no 9
Slipform construction
Basic Scaffolding Awareness
Scaffolding
Slip formwork technique
PreCast Construction
JUMP FORM WORK
FORM WORK AND SUPPORT WORK
Ad

Similar to Formwork (20)

PPTX
Formwork
PPTX
Formwork
PPTX
formwork as per IS Code Slip and moving formwork..pptx
PPTX
6. FORMWORK (ACE) 2160601 GTU
PPTX
Formwork For Structural Member. Formwork Engineeringpptx
PPTX
Formwork-Types and Their Advantages
PPTX
PDF
Formwork & Falsework Practice_2009(July)_to AK.pdf
PPTX
Formwork, by prof. sagar raut
PDF
form work-converted pppt new-converted.pdf
PDF
formwork Bco (1) final.pdf
PPTX
FormWork
PPTX
Form Work in civil engineering field.pptx
PPTX
form work - Building construction necessities
PPTX
Formwork by chakamba john
PPTX
Form-woks-additional.pptx
PDF
Formwork
PPTX
Power point presentation on the topic formwork
DOCX
Formwork seminar 2
Formwork
Formwork
formwork as per IS Code Slip and moving formwork..pptx
6. FORMWORK (ACE) 2160601 GTU
Formwork For Structural Member. Formwork Engineeringpptx
Formwork-Types and Their Advantages
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork, by prof. sagar raut
form work-converted pppt new-converted.pdf
formwork Bco (1) final.pdf
FormWork
Form Work in civil engineering field.pptx
form work - Building construction necessities
Formwork by chakamba john
Form-woks-additional.pptx
Formwork
Power point presentation on the topic formwork
Formwork seminar 2

Recently uploaded (20)

PPTX
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
DOCX
An investigation of the use of recycled crumb rubber as a partial replacement...
PPT
UNIT-I Machine Learning Essentials for 2nd years
PPTX
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
PDF
Engineering Solutions for Ethical Dilemmas in Healthcare (www.kiu.ac.ug)
PPTX
Software-Development-Life-Cycle-SDLC.pptx
PPTX
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
PDF
Lesson 3 .pdf
PDF
Project_Mgmt_Institute_-Marc Marc Marc .pdf
PPTX
DATA STRCUTURE LABORATORY -BCSL305(PRG1)
PPTX
CS6006 - CLOUD COMPUTING - Module - 1.pptx
PDF
Artificial Intelligence_ Basics .Artificial Intelligence_ Basics .
PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
PPT
Programmable Logic Controller PLC and Industrial Automation
PPTX
chapter 1.pptx dotnet technology introduction
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PPTX
WN UNIT-II CH4_MKaruna_BapatlaEngineeringCollege.pptx
PDF
Software defined netwoks is useful to learn NFV and virtual Lans
PDF
IAE-V2500 Engine for Airbus Family 319/320
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
An investigation of the use of recycled crumb rubber as a partial replacement...
UNIT-I Machine Learning Essentials for 2nd years
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
Engineering Solutions for Ethical Dilemmas in Healthcare (www.kiu.ac.ug)
Software-Development-Life-Cycle-SDLC.pptx
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
Lesson 3 .pdf
Project_Mgmt_Institute_-Marc Marc Marc .pdf
DATA STRCUTURE LABORATORY -BCSL305(PRG1)
CS6006 - CLOUD COMPUTING - Module - 1.pptx
Artificial Intelligence_ Basics .Artificial Intelligence_ Basics .
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
Programmable Logic Controller PLC and Industrial Automation
chapter 1.pptx dotnet technology introduction
Environmental studies, Moudle 3-Environmental Pollution.pptx
WN UNIT-II CH4_MKaruna_BapatlaEngineeringCollege.pptx
Software defined netwoks is useful to learn NFV and virtual Lans
IAE-V2500 Engine for Airbus Family 319/320

Formwork

  • 2. DEFINITION: 2  Its is an artificial support provided below and around the precast or cast insitu concrete work.  Formwork is commonly made of  Steel  wood  Formwork construction & casting is of prime importance in concrete industry. It share a significant amount of concrete cost.  Formwork is designed according to The ACI document SP-4.
  • 3. Qualities of formwork: 3 It should be water tight It should be strong It can be reusable Its contact surface should be uniform It should be according to the size of member.
  • 4. Uses: 4  Formwork molds the concrete to the desired shape and size, and controls its position and alignment.  It is used to transfer the temporary external loads.
  • 5. Major objectives considered in formwork: 5  Quality  Safety  Economy
  • 6. 6  Quality: Forms must be designed and built with sufficient stiffness and accuracy so that the size, shape, position, and finish of the cast concrete are maintained.  Safety: Forms must be built sufficient strength and factor of safety so that they have the capable of all supporting loads.  Economy: Forms must be built efficiently, minimizing time and cost..
  • 7. Requirements of formwork: 7  Material should be cheap and re usable,  It should be practically water proof, so that it should not absorb water from concrete,  Swelling and shrinkage should be minimum,  Strong enough to with stand all external loads,  Deflection should be minimum,  Surface should be smooth, and afford easy striping,  Light in weight, so that easy to transfer,  Joints should be stiff, so that lateral deformation and leak is minimum .
  • 8. THREE STAGES: 8 a) Assembly and erection b) Concrete placement c) Stripping and dismantling
  • 9. TYPES OF FORMWORK: 9 Temporary Structure Temporary structure required to safely support concrete until it reaches adequate strength Permanent Structure
  • 10. Formwork detail for different structural members 10 In concrete construction formwork is commonly provided for the following structural members. o Wall o Column o Slabs & Beams o Stairs o Chimneys o Water tanks o Cooling Towers
  • 11. Formwork for Wall 11  It consists of • Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges  After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 12. Wall forms: 12  Wall forms principally resist the lateral pressure generated by fresh concrete as a liquid or semi liquid material.  The pressure can be quite large, certainly many times the magnitude of live loads on permanent floors.  So design often involves closely spaced and well-supported members.  Snap ties, flat ties, loop ties are single use ties usually relatively low capacity 680 kg to 1450 kg.  Coil ties, he bolts, she bolts are left embedded in concrete , or it can be reused.  The tension capacity of heavy ties around 27,230 kg.
  • 14. Formwork for Column 14 It consists of the following Side & End Planks Yoke Nut & Bolts Two end & two side planks are joined by the yokes and bolts.
  • 15. Column forms: 15  Column-forms materials tend to vary with the column shape.  Wood or steel is often used with square or rectangular column.  Round column forms more typically pre manufactured in a range of standard diameters, are available in steel, paper board, and fiber reinforced plastic.  Round column are more structural efficient compared to square, since the internal pressures can be resisted by the hoop membrane.  Round steel forms are generally used for larger columns and bridge piers and come in diameters about 0.36m to 3mts..
  • 16. 16
  • 18. Formwork for Slabs & beams: 18  It consists of Sole plates Wedges Props Head tree Planks Batten Ledgers  Beam formwork rests on head tree  Slab form work rests on battens and joists  If prop height are more than 8’ provide horizontal braces.
  • 19. Lintel or Beam Formwork: 19
  • 21. FORMWORK FOR STAIRS: 21 It consists of Vertical & inclined posts Inclined members Wooden Planks or sheeting Stringer Riser Planks
  • 22. FORMWORK FOR STAIRS: 22  The sheathing or decking for deck slabs is carried on cross- joists which are in turn supported on raking ledgers  The ledgers are generally of 7.5cm x 10cm size .  The cross- joists may be 5cm x 10cm size  The riser planks are 4-5 cm thick and equal to the height of riser  The riser planks are placed after the reinforcement is placed in position
  • 25. FORMWORK FOR CHIMNEYS: 25 For tall chimneys two types of forms techniques are in generally use in our country a) Jump form b) Slip form
  • 26. 26 Jump Form: In this type jacking bars are either cast in concrete or else are carried in tubes which are cast in concrete. After casting a lift, concrete is allowed to set and then the forms are raised by jacks and the next lift is cast. Jacks are usually placed about 2m apart and are designed.
  • 27. 27
  • 28. 28 Slip Form: The slip form method of concrete construction is used for forming both horizontal and vertical concrete structures. It often used for forming highway pavements as continuous operation. Slip form methods is also been used for forming various types of vertical concrete structures.
  • 31. Removal of formwork: 31  Time of formwork removal depends on the following factors 1. Type of Cement 1. Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) 2. Ratio of concrete mix 1. Rich ratio concrete gain strength earlier as compared to weak ratio concrete. 3. Weather condition 1. Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions.
  • 32. Time of Removal of formwork: 32 Sr . N o Structural Member OPC (Ordinary Portland Cement) Rapid Hardeni ng Cement 1 Beam sides, walls & Columns 2-3 Days 2 Days 2 Slab (Vertical Supports remains intact) 4 Days 3 Days 3 Slab (Complete Formwork removal) 10 Days 5 Days 4 Beams (Removal of Sheeting, Props remains intact) 8 Days 5 Days 5 Beams & Arches (Complete formwork removal) (up to 6 m span) 14 Days 5-8 Days 6 Beams & Arches (Complete formwork removal) (more than 6 m span) 21 Days 8-10 Days
  • 33. Maintenance of formwork: 33 Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 34. Cost of formwork 34  For normal works cost of formwork is about 30%-40% of the concrete cost.  For special works cost of formwork is about 50%-60% of the concrete cost.  Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges.
  • 35. Advantages of steel form work: 35  It can be used for a no. of times.  It is non absorbent.  Smooth finish surface obtained.  No shrinkage of formwork occurs.  Easy to use.  Its volume is less  Its strength is more.
  • 36. LOADS ON FORMWORK: 36 Formwork is subjected to following loads: a) Dead weight of concrete b) Hydrostatic pressure of the concrete c) Live load due to working laborers d) Impact effect at the time of pouring concrete into the formwork e) Vibrations transmitted to formwork during pouring concrete
  • 37. FORMWORK DESIGN 37 Guiding points in the Design of formwork  For design purpose, temporary live load due to labor and equipment including impact may be taken from 3700N/m2 to 4000N/m2  Dead weight of wet concrete (26000 N/m3 )  Planks or boards used to form the vertical facing of the columns or walls is known as sheathing whereas those used for floor slabs are called decking
  • 38. 38  The hydrostatic pressure due to fluidity of concrete in the initial stages of pouring depends upon several factors such as amount of water, size of aggregates, rate of pouring etc.,  The hydrostatic pressure is maximum at the time of pouring, but after some time it starts decreasing, as concrete starts setting and hardening. This pressure is mainly dependent on the depth of concrete poured before it starts setting  Deflection of the sheathing and joists should be limited to a maximum value of 2.5mm
  • 39. Contd... 39  The minimum wind design pressure q not less than 15 psf and bracing should be designed for at least w =46 kg/ft- length applied to the top  The minimum lateral load w, for design of bracing system would be greater than, q .(h/2) or 46 kg/ft
  • 40. Contd... 40 For design practice the maximum pressure is given by: p = wh Where, p => lateral pressure of concrete, w => unit weight of concrete, h => depth of fluid or plastic concrete.
  • 41. Contd... 41 For horizontal pressure of concrete is given by: For walls constructing R less than 2.1m/hr; p =150+9000(R/T) For walls constructing R varies from 2.1m/hr to 3m/hr; p = 150+(43,400/T)+2800(R/T) For columns 3m/hr; p = 150+9000(R/T) Where, R => rate of vertical placement, T => time for placement.
  • 42. DESIGN OF SLAB FORMWORK: 42 Design of slab forms can be summarized in the following design steps:  Step 1: Estimate design loads  Step 2: Determine sheathing thickness and spacing of its supports (joist spacing)  Step 3: Determine joist size and spacing of supports (stringer spacing)  Step 4: Determine stringer size and span (shore spacing)  Step 5: Perform shore design to support stringers  Step 6: Check bearing stresses  Step 7: Design lateral bracing
  • 43. 43