Session 3:
Economic assessment of PV
and wind for energy planning
IRENA Global Atlas
Spatial planning techniques
2-day seminar
Central questions we want to answer
1. Once we know how much electricity can be produced in our country with given resources
(technical potential), we will be able to estimate their generation costs
2. As all available data comes with uncertainties, we should know
a. how sensitive results react on changing input parameters, and,
b. what socio-economic effect highly uncertain input data could have.
2
3
©
RENAC
2014
Irradiation on tilted plane (Wh/m²/a)
Energy generation costs at specific site (€/Wh)
Conversion horizontal solar radiation to optimally
tilted plane
Optimal tilt angle
Energy output calculation
Pre-conversion
losses
Conversion losses
System losses (%)
CAPEX
OPEX
WACC
Life time
Economic
parameters (PV
plant and grid
connection)
Annual energy prod. (Wh/km2/a)
PV capacity per area (W/km2)
Areas potentially suitable for PV systems (km2)
Site assessment (solar atlas data, solar radiation
(kWh/m²/a); open-land and settlements (roofs)
Exclusion of non-suitable areas
Nature conservation areas
Exclusion of non-suitable built-up areas
(i.e. non-suitable roofs)
Transport, supply and communication
infrastructure; very remote areas
Areas technically not suitable (high
slope and above certain altitude, etc.)
Landscape, historic area, other non-
usable land (glaciers, rivers, roads etc.)
Areas potentially suitable for PV systems (km2)
Priority areas for PV (km2),
potentially installed capacity (W), potentially
generated energy (Wh/a) and costs
Energy policy
analysis
Economic
assessment
Performance
Ratio
done
done
CAPEX
=
Capital
expenditure,
OPEX
=
Operation
expenditure,
WACC
=
Weighted
average
cost
of
capital
(debt,
equity)
Contents
1. Levelized cost of electricity (LCOE)
2. Worked example: LCOE sensitivity of PV projects
3. Worked example: LCOE sensitivity of wind projects
4. Worked example: Effects of data uncertainty on the LCOE of PV
4
1. LEVELIZED COST OF
ELECTRICITY (LCOE)
5
Levelized Cost of Electricity (LCOE)
• Calculates the average cost per unit electricity. LCOE takes into account the time value
of money (i.e. capital costs).
Where:
• LCOE: Average Cost of Electricity generation in $/unit electricity
• I0: Investment costs in $
• At: Annual total costs in $ in each year t
• Qel: Amount of electricity generated
• i: Discount interest rate in %
• n: useful economic life
• t: year during the useful life (1, 2, …n)
6
2. LCOE SENSITIVITY OF
PV PROJECTS
Worked example:
7
Worked example – Grid-tied PV in Egypt
• Project type: Grid-tied
• Location at latitude: 20° North
• Reference irradiation (GHI): 2,500 kWh/m²/a
• Reference specific yield (P50): 1,880 MWh/MWp
• System size: 10 MWp
• Specific project CAPEX: 2.000.000 USD/MWp
• Project annual OPEX: 1.5% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 30 years
• Inverter replacements: 2
• Solar panel degradation: 0,7% p.a. (linear)
8
LCOE sensitivity (absolute)
9
Baseline LCOE: 123 USD/MWh
LCOE sensitivity (relative)
10
Baseline LCOE: 123 USD/MWh
3. LCOE SENSITIVITY OF
WIND PROJECTS
Worked example:
11
Worked example – Grid-tied wind project Egypt
(variation A)
• Project type: Grid-tied wind
• Location: Egypt / south-west of Cairo
• Average wind speed @ 80m: 7.3 m/s
• Wind distribution, shape parameter: 3.5
• Wind distr., scale parameter: 8.11
• Technical availability: 97%
• Reference specific yield (P50): 3,202 MWh/MW (techn. Availability considered)
• Capacity factor: 36.6%
• System size: 8 MW (4 turbines)
• Specific project CAPEX: 4.000.000 USD per turbine
• Project annual OPEX: 3.0% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 20 years
12
LCOE sensitivity (absolute) – Wind speed only
13
Baseline LCOE: 87.6 USD/MWh
LCOE sensitivity (absolute) – other parameters
14
Baseline LCOE: 87.6 USD/MWh
Worked example – variation B:
lower wind speed & lower shape parameter
• Project type: Grid-tied wind
• Location: Egypt / south-west of Cairo
• Average wind speed @ 80m: 7.3 m/s 5.5 m/s
• Wind distribution, shape parameter: 3.5 m/s 1.5 m/s
• Wind distr., scale parameter: 6.11
• Technical availability: 97%
• Reference specific yield (P50): 2,054 MWh/MW (techn. Availability considered)
• Capacity factor: 23.5%
• System size: 8 MWp (4 turbines)
• Specific project CAPEX: 4.000.000 USD per turbine
• Project annual OPEX: 3.0% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 20 years
15
LCOE sensitivity (absolute) – Wind speed only
16
Baseline LCOE: 136.6 USD/MWh
LCOE sensitivity (absolute) – other parameters
17
Baseline LCOE: 136.6 USD/MWh
Shape parameter more sensitive!!!
Conclusions on sensitivities and for scenario
development
• Variations of the shape parameter of the Weibull distribution of wind can have very
different effects depending on the chosen scenario
 In variation A (high wind, high shape factor), varying of the shape factor only had a
very little effect on the LCOE.
 In variation B (lower wind, lower shape factor), varying of the shape factor had a
considerable effect on the LCOE.
 Reason: the chosen wind turbine for the scenario has a power curve which operates
better under stronger winds. The Weibull function produces a wind distribution
where relative low wind speeds occur comparably often.
 It is crucial for wind scenario developments, to chose appropriate turbines for sites
with different wind speeds and wind speed distributions.
18
Comparison of Weibull curves for
variations A (left ) + B (right)
19
4. EFFECTS OF DATA
UNCERTAINTY ON THE
LCOE OF PV
Worked example:
20
Why data quality is so important
• All data comes with uncertainties:
 Measurements are always subject to deviations, and ,
 models used for predictions can never simulate what happens in reality.
• It is obvious that the lower uncertainty is the more accurate predictions will be. This, in
turn, will enable us to make better estimates.
• In the following, we will demonstrate how good data (i.e. data with low uncertainties) will
potentially help saving funds for PV Power Purchase Agreements.
21
Uncertainty assumptions
• Low resolution NASA SSE data: +/- 13,7%
• Average Meteonorm 7 data: +/- 7,5%
• Best ground measurement at site: +/- 3,0%
• Important note: Besides uncertainty of irradiation data, there is also uncertainty within
the simulation model and nameplate capacity. However, the latter are comparably small
so that we will, to keep the example simple, only look at resource uncertainty. In real-life,
when it comes to detailed project development, one should always ask the project
developer to provide information about his uncertainty assumptions.
22
Worked example – Grid-tied PV in Egypt
• Project type: Grid-tied
• Location at latitude: 20° North
• Reference irradiation: 2500 kWh/m²/a
• Reference specific yield (P50): 1880 MWh/MWp
• System size: 10 MWp
• Specific project CAPEX: 2.000.000 USD/MWp
• Project annual OPEX: 1.5% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 30 years
• Inverter replacements: 2
• Solar panel degradation: 0,7% p.a. (linear)
23
Exceedance probability (alternative view)
24
P50: 1880 MWh/MWp
P90
LCOE depends on quality of meteo data
25
LCOE is key factor for PPA tariff calculation
• Assuming a 10% premium on the LCOE as margin for IPP
 Best case: 128 USD/MWh +10% = 141 USD/MWh
 Worst case: 149 USD/MWh +10% = 164 USD/MWh
 Delta: 23 USD/MWh (incl. 10% premium)
26
Country sets a 5% PV goal by 2020
• Sample: Egypt
• Total electricity demand 2012: 109 TWh (Source: indexmundi.com)
• 5% of total: 5.45 TWh
• PPA tariff difference: 23 USD/MWh
• „Unnecessary“ payments in 2020: 5,450,000 MWh * 23 USD/MWh =125.4 Mio USD
• PV power needed: 3,014 MWp (with best P90 value)
27
„Unnecessary“ payments due to inaccurate data
• PV power needed by 2020: 3,014 MWp (with best P90 value)
• Aviodable payments: 376 Mio USD
28
29
©
RENAC
2014
Irradiation on tilted plane (Wh/m²/a)
Energy generation costs at specific site (€/Wh)
Conversion horizontal solar radiation to optimally
tilted plane
Optimal tilt angle
Energy output calculation
Pre-conversion
losses
Conversion losses
System losses (%)
CAPEX
OPEX
WACC
Life time
Economic
parameters (PV
plant and grid
connection)
Annual energy prod. (Wh/km2/a)
PV capacity per area (W/km2)
CAPEX
=
Capital
expenditure,
OPEX
=
Operation
expenditure,
WACC
=
Weighted
average
cost
of
capital
(debt,
equity)
Areas potentially suitable for PV systems (km2)
Site assessment (solar atlas data, solar radiation
(kWh/m²/a); open-land and settlements (roofs)
Exclusion of non-suitable areas
Nature conservation areas
Exclusion of non-suitable built-up areas
(i.e. non-suitable roofs)
Transport, supply and communication
infrastructure; very remote areas
Areas technically not suitable (high
slope and above certain altitude, etc.)
Landscape, historic area, other non-
usable land (glaciers, rivers, roads etc.)
Areas potentially suitable for PV systems (km2)
Priority areas for PV (km2),
potentially installed capacity (W), potentially
generated energy (Wh/a) and costs
Energy policy
analysis
Economic
assessment
Performance
Ratio
done
done done
Thank you very much for your
attention!
Volker Jaensch
Renewables Academy (RENAC)
Phone +49 30 52 689 58-85
jaensch@renac.de
www.renac.de

More Related Content

PDF
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
PDF
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
PDF
IRJET- Implementing Zero Energy Efficiency in Residential Building
PDF
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
PPT
Solar Barge
PPT
Drivers and Barriers in the current CSP market
DOCX
1115161Wind Power Now, Tomorrow C.P. (Case) .docx
PPTX
Two difficulties
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IRJET- Implementing Zero Energy Efficiency in Residential Building
Renewable Energy in Nordic Countries - Alf Bjorseth - SCATEC - April 2010
Solar Barge
Drivers and Barriers in the current CSP market
1115161Wind Power Now, Tomorrow C.P. (Case) .docx
Two difficulties

Similar to 16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf (20)

PDF
19346954 Photovoltaics
PPTX
5.5 off main-grid technologies for power generation in rural contexts
PPTX
DG SYSTEM SELECTION IN URBAN AREA
PPTX
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
PDF
Cost development of renewable energy technologies
PDF
Session 6 - Presentation by Georgian Industrial Group
PDF
March9 2009-workshop-slides
PDF
Wind Vs Conventional Electricity Economics
PPT
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
PPT
COSTMODEL_IDETC_2010_Jie
PPTX
Energy Efficiency and Sustainability: Safaricom Perspective
 
PPT
Major_Proj_Ramya
PPTX
performance optimization of Solar pv plant through Micro inverter
PDF
SHAMS Dubai
PDF
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
PPTX
Utilizing solar+storage to obviate natural gas peaker plants
PDF
Energetic payback time of PV: In Germany and Tunisia
PDF
Introduction to Grid forming inverter.pdf
PDF
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
PDF
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
19346954 Photovoltaics
5.5 off main-grid technologies for power generation in rural contexts
DG SYSTEM SELECTION IN URBAN AREA
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Cost development of renewable energy technologies
Session 6 - Presentation by Georgian Industrial Group
March9 2009-workshop-slides
Wind Vs Conventional Electricity Economics
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
COSTMODEL_IDETC_2010_Jie
Energy Efficiency and Sustainability: Safaricom Perspective
 
Major_Proj_Ramya
performance optimization of Solar pv plant through Micro inverter
SHAMS Dubai
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
Utilizing solar+storage to obviate natural gas peaker plants
Energetic payback time of PV: In Germany and Tunisia
Introduction to Grid forming inverter.pdf
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
Ad

More from Mohamed Salah (9)

PPTX
IEC and energy efficiency October 2019.pptx
PPT
Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
PDF
economic-development-guide.pdf
PDF
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
PDF
Wind Energy 101.pdf
PDF
22223.pdf
PDF
40462.pdf
PDF
45834.pdf
PDF
Eqm addendum egypt directory_2017_a5-ar (1)
IEC and energy efficiency October 2019.pptx
Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
economic-development-guide.pdf
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
Wind Energy 101.pdf
22223.pdf
40462.pdf
45834.pdf
Eqm addendum egypt directory_2017_a5-ar (1)
Ad

Recently uploaded (20)

PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
PPTX
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
PPTX
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
PDF
ECT443_instrumentation_Engg_mod-1.pdf indroduction to instrumentation
PPTX
SC Robotics Team Safety Training Presentation
DOCX
An investigation of the use of recycled crumb rubber as a partial replacement...
PPTX
BBOC407 BIOLOGY FOR ENGINEERS (CS) - MODULE 1 PART 1.pptx
PPTX
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
PPTX
Agentic Artificial Intelligence (Agentic AI).pptx
PDF
ST MNCWANGO P2 WIL (MEPR302) FINAL REPORT.pdf
PPTX
Design ,Art Across Digital Realities and eXtended Reality
PPTX
CS6006 - CLOUD COMPUTING - Module - 1.pptx
PDF
Research on ultrasonic sensor for TTU.pdf
PDF
Mechanics of materials week 2 rajeshwari
PPTX
chapter 1.pptx dotnet technology introduction
PDF
IAE-V2500 Engine for Airbus Family 319/320
PDF
Cryptography and Network Security-Module-I.pdf
PDF
Project_Mgmt_Institute_-Marc Marc Marc .pdf
PDF
V2500 Owner and Operatore Guide for Airbus
PPTX
22ME926Introduction to Business Intelligence and Analytics, Advanced Integrat...
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
ECT443_instrumentation_Engg_mod-1.pdf indroduction to instrumentation
SC Robotics Team Safety Training Presentation
An investigation of the use of recycled crumb rubber as a partial replacement...
BBOC407 BIOLOGY FOR ENGINEERS (CS) - MODULE 1 PART 1.pptx
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
Agentic Artificial Intelligence (Agentic AI).pptx
ST MNCWANGO P2 WIL (MEPR302) FINAL REPORT.pdf
Design ,Art Across Digital Realities and eXtended Reality
CS6006 - CLOUD COMPUTING - Module - 1.pptx
Research on ultrasonic sensor for TTU.pdf
Mechanics of materials week 2 rajeshwari
chapter 1.pptx dotnet technology introduction
IAE-V2500 Engine for Airbus Family 319/320
Cryptography and Network Security-Module-I.pdf
Project_Mgmt_Institute_-Marc Marc Marc .pdf
V2500 Owner and Operatore Guide for Airbus
22ME926Introduction to Business Intelligence and Analytics, Advanced Integrat...

16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf

  • 1. Session 3: Economic assessment of PV and wind for energy planning IRENA Global Atlas Spatial planning techniques 2-day seminar
  • 2. Central questions we want to answer 1. Once we know how much electricity can be produced in our country with given resources (technical potential), we will be able to estimate their generation costs 2. As all available data comes with uncertainties, we should know a. how sensitive results react on changing input parameters, and, b. what socio-economic effect highly uncertain input data could have. 2
  • 3. 3 © RENAC 2014 Irradiation on tilted plane (Wh/m²/a) Energy generation costs at specific site (€/Wh) Conversion horizontal solar radiation to optimally tilted plane Optimal tilt angle Energy output calculation Pre-conversion losses Conversion losses System losses (%) CAPEX OPEX WACC Life time Economic parameters (PV plant and grid connection) Annual energy prod. (Wh/km2/a) PV capacity per area (W/km2) Areas potentially suitable for PV systems (km2) Site assessment (solar atlas data, solar radiation (kWh/m²/a); open-land and settlements (roofs) Exclusion of non-suitable areas Nature conservation areas Exclusion of non-suitable built-up areas (i.e. non-suitable roofs) Transport, supply and communication infrastructure; very remote areas Areas technically not suitable (high slope and above certain altitude, etc.) Landscape, historic area, other non- usable land (glaciers, rivers, roads etc.) Areas potentially suitable for PV systems (km2) Priority areas for PV (km2), potentially installed capacity (W), potentially generated energy (Wh/a) and costs Energy policy analysis Economic assessment Performance Ratio done done CAPEX = Capital expenditure, OPEX = Operation expenditure, WACC = Weighted average cost of capital (debt, equity)
  • 4. Contents 1. Levelized cost of electricity (LCOE) 2. Worked example: LCOE sensitivity of PV projects 3. Worked example: LCOE sensitivity of wind projects 4. Worked example: Effects of data uncertainty on the LCOE of PV 4
  • 5. 1. LEVELIZED COST OF ELECTRICITY (LCOE) 5
  • 6. Levelized Cost of Electricity (LCOE) • Calculates the average cost per unit electricity. LCOE takes into account the time value of money (i.e. capital costs). Where: • LCOE: Average Cost of Electricity generation in $/unit electricity • I0: Investment costs in $ • At: Annual total costs in $ in each year t • Qel: Amount of electricity generated • i: Discount interest rate in % • n: useful economic life • t: year during the useful life (1, 2, …n) 6
  • 7. 2. LCOE SENSITIVITY OF PV PROJECTS Worked example: 7
  • 8. Worked example – Grid-tied PV in Egypt • Project type: Grid-tied • Location at latitude: 20° North • Reference irradiation (GHI): 2,500 kWh/m²/a • Reference specific yield (P50): 1,880 MWh/MWp • System size: 10 MWp • Specific project CAPEX: 2.000.000 USD/MWp • Project annual OPEX: 1.5% of project CAPEX • Discount rate (WACC): 8% • Project duration: 30 years • Inverter replacements: 2 • Solar panel degradation: 0,7% p.a. (linear) 8
  • 11. 3. LCOE SENSITIVITY OF WIND PROJECTS Worked example: 11
  • 12. Worked example – Grid-tied wind project Egypt (variation A) • Project type: Grid-tied wind • Location: Egypt / south-west of Cairo • Average wind speed @ 80m: 7.3 m/s • Wind distribution, shape parameter: 3.5 • Wind distr., scale parameter: 8.11 • Technical availability: 97% • Reference specific yield (P50): 3,202 MWh/MW (techn. Availability considered) • Capacity factor: 36.6% • System size: 8 MW (4 turbines) • Specific project CAPEX: 4.000.000 USD per turbine • Project annual OPEX: 3.0% of project CAPEX • Discount rate (WACC): 8% • Project duration: 20 years 12
  • 13. LCOE sensitivity (absolute) – Wind speed only 13 Baseline LCOE: 87.6 USD/MWh
  • 14. LCOE sensitivity (absolute) – other parameters 14 Baseline LCOE: 87.6 USD/MWh
  • 15. Worked example – variation B: lower wind speed & lower shape parameter • Project type: Grid-tied wind • Location: Egypt / south-west of Cairo • Average wind speed @ 80m: 7.3 m/s 5.5 m/s • Wind distribution, shape parameter: 3.5 m/s 1.5 m/s • Wind distr., scale parameter: 6.11 • Technical availability: 97% • Reference specific yield (P50): 2,054 MWh/MW (techn. Availability considered) • Capacity factor: 23.5% • System size: 8 MWp (4 turbines) • Specific project CAPEX: 4.000.000 USD per turbine • Project annual OPEX: 3.0% of project CAPEX • Discount rate (WACC): 8% • Project duration: 20 years 15
  • 16. LCOE sensitivity (absolute) – Wind speed only 16 Baseline LCOE: 136.6 USD/MWh
  • 17. LCOE sensitivity (absolute) – other parameters 17 Baseline LCOE: 136.6 USD/MWh Shape parameter more sensitive!!!
  • 18. Conclusions on sensitivities and for scenario development • Variations of the shape parameter of the Weibull distribution of wind can have very different effects depending on the chosen scenario  In variation A (high wind, high shape factor), varying of the shape factor only had a very little effect on the LCOE.  In variation B (lower wind, lower shape factor), varying of the shape factor had a considerable effect on the LCOE.  Reason: the chosen wind turbine for the scenario has a power curve which operates better under stronger winds. The Weibull function produces a wind distribution where relative low wind speeds occur comparably often.  It is crucial for wind scenario developments, to chose appropriate turbines for sites with different wind speeds and wind speed distributions. 18
  • 19. Comparison of Weibull curves for variations A (left ) + B (right) 19
  • 20. 4. EFFECTS OF DATA UNCERTAINTY ON THE LCOE OF PV Worked example: 20
  • 21. Why data quality is so important • All data comes with uncertainties:  Measurements are always subject to deviations, and ,  models used for predictions can never simulate what happens in reality. • It is obvious that the lower uncertainty is the more accurate predictions will be. This, in turn, will enable us to make better estimates. • In the following, we will demonstrate how good data (i.e. data with low uncertainties) will potentially help saving funds for PV Power Purchase Agreements. 21
  • 22. Uncertainty assumptions • Low resolution NASA SSE data: +/- 13,7% • Average Meteonorm 7 data: +/- 7,5% • Best ground measurement at site: +/- 3,0% • Important note: Besides uncertainty of irradiation data, there is also uncertainty within the simulation model and nameplate capacity. However, the latter are comparably small so that we will, to keep the example simple, only look at resource uncertainty. In real-life, when it comes to detailed project development, one should always ask the project developer to provide information about his uncertainty assumptions. 22
  • 23. Worked example – Grid-tied PV in Egypt • Project type: Grid-tied • Location at latitude: 20° North • Reference irradiation: 2500 kWh/m²/a • Reference specific yield (P50): 1880 MWh/MWp • System size: 10 MWp • Specific project CAPEX: 2.000.000 USD/MWp • Project annual OPEX: 1.5% of project CAPEX • Discount rate (WACC): 8% • Project duration: 30 years • Inverter replacements: 2 • Solar panel degradation: 0,7% p.a. (linear) 23
  • 24. Exceedance probability (alternative view) 24 P50: 1880 MWh/MWp P90
  • 25. LCOE depends on quality of meteo data 25
  • 26. LCOE is key factor for PPA tariff calculation • Assuming a 10% premium on the LCOE as margin for IPP  Best case: 128 USD/MWh +10% = 141 USD/MWh  Worst case: 149 USD/MWh +10% = 164 USD/MWh  Delta: 23 USD/MWh (incl. 10% premium) 26
  • 27. Country sets a 5% PV goal by 2020 • Sample: Egypt • Total electricity demand 2012: 109 TWh (Source: indexmundi.com) • 5% of total: 5.45 TWh • PPA tariff difference: 23 USD/MWh • „Unnecessary“ payments in 2020: 5,450,000 MWh * 23 USD/MWh =125.4 Mio USD • PV power needed: 3,014 MWp (with best P90 value) 27
  • 28. „Unnecessary“ payments due to inaccurate data • PV power needed by 2020: 3,014 MWp (with best P90 value) • Aviodable payments: 376 Mio USD 28
  • 29. 29 © RENAC 2014 Irradiation on tilted plane (Wh/m²/a) Energy generation costs at specific site (€/Wh) Conversion horizontal solar radiation to optimally tilted plane Optimal tilt angle Energy output calculation Pre-conversion losses Conversion losses System losses (%) CAPEX OPEX WACC Life time Economic parameters (PV plant and grid connection) Annual energy prod. (Wh/km2/a) PV capacity per area (W/km2) CAPEX = Capital expenditure, OPEX = Operation expenditure, WACC = Weighted average cost of capital (debt, equity) Areas potentially suitable for PV systems (km2) Site assessment (solar atlas data, solar radiation (kWh/m²/a); open-land and settlements (roofs) Exclusion of non-suitable areas Nature conservation areas Exclusion of non-suitable built-up areas (i.e. non-suitable roofs) Transport, supply and communication infrastructure; very remote areas Areas technically not suitable (high slope and above certain altitude, etc.) Landscape, historic area, other non- usable land (glaciers, rivers, roads etc.) Areas potentially suitable for PV systems (km2) Priority areas for PV (km2), potentially installed capacity (W), potentially generated energy (Wh/a) and costs Energy policy analysis Economic assessment Performance Ratio done done done
  • 30. Thank you very much for your attention! Volker Jaensch Renewables Academy (RENAC) Phone +49 30 52 689 58-85 [email protected] www.renac.de