ENVIRONMENTAL IMPACT ASSESSMENT
ENVIRONMENTALIMPACT ASSESSMENT
A study to identify, predict, evaluate, and communicate
information about the impacts on the environment of a
proposed project and to detail out the mitigating measures prior
to project approval and implementation.
An aid to the environmental planning
A preventive process in environmental management.
To avoid costly mistakes in project planning and
development.
Required under the Env’al Quality Order
(Prescribed Premise) (Environmental Impact Assessment)
1987 (Refer to p.189 – Text EQA 1974).
2.
EIA
EIA
E (Environmental)
–begin at an EARLY stage of a development (able to
identify opportunities and constraints (gives guidance in
the final design of the project).
I (Impact):
– INTEGRATED manner ( emphasized engineering and
economic aspects + env’al components).
A (Assessment):
– ALWAYS continue to accumulate data throughout the
project cycle, monitoring the implementation of
environmental protection measures and suggestion mid-
course correction to the management.
3.
OBJECTIVES OF EIA
OBJECTIVESOF EIA
1. To examine and select the best from
project options.
2. To identify and incorporate into project
plan, appropriate abatement and
mitigating measures.
3. To predict and determine significant
residual environmental impact.
4. To identify the environmental costs and
benefits of the project to the community.
4.
CONCEPTS OF EIA
CONCEPTSOF EIA
1.
1. Need for a project (social, economic, cultural).
Need for a project (social, economic, cultural).
2.
2. Project Options (sites, design, etc.)
Project Options (sites, design, etc.)
3.
3. Mitigating and abatement measures.
Mitigating and abatement measures.
4.
4. Environmental data collection (e.g., geology, soil,
Environmental data collection (e.g., geology, soil,
land-use, water, special features, climate, etc.).
land-use, water, special features, climate, etc.).
5.
5. Public participation (e.g., community needs, social
Public participation (e.g., community needs, social
acceptability).
acceptability).
6.
6. Costs and benefits of EIA (e.g., implied values,
Costs and benefits of EIA (e.g., implied values,
monetary values).
monetary values).
7.
7. Monitoring environmental impacts (check to improve
Monitoring environmental impacts (check to improve
future planning).
future planning).
5.
PROJECT DEVELOPMENT PROCESS
PROJECTDEVELOPMENT PROCESS
1. Social needs.
2. Social objectives.
3. Engineering objectives.
4. Base-line data and analysis.
5. Preparation of alternative plans – projections and formulation.
6. Selection of plans.
7. Technical, social, economic, and environmental reviews.
8. Final design.
9. Construction.
10. Operation and management.
NOTE: 1-7 – Planning Phase
3-10 – Engineering involvement.(refer to Figure (Hand-out)).
6.
PROCESS IN PREPARINGEIA
PROCESS IN PREPARING EIA
1. PROJECT
MANAGEMENT
Dev. Objectives.
Project components
2. ENVIRONMENTAL
COMPONENTS –
–
affected by development
affected by development
Physical characteristics
Physical characteristics
Hydraulic regime
Hydraulic regime
Water quality
Water quality
Socio-economy
Socio-economy
ecology
ecology
7.
Process (Cont.)
Process (Cont.)
3.IDENTIFICATION &
ASSESSMENT OF
IMPACTS:
Qualitative and quantitative
Significant impact – to what
extent (e.g., rainfall)
– Type of rain
– Type of soil
– Amount of soil eroded
– Effects – siltation, DO,
BOD.
4. MITIGATING
MEASURES
Engineering measures –
erosion of soil (silt trap); oil
(oil trap).
Environmental mngt. Plan.
Project options – alternatives.
ENVIRONMENTAL IMPACT
ENVIRONMENTAL IMPACT
ASSESSMENT
ASSESSMENT
System approach
System approach
Preliminary site and project evaluation
Preliminary site and project evaluation
Scoping
Scoping
Baseline studies
Baseline studies
Formatting
Formatting
Prediction methods
Prediction methods
10.
1. System approach
1.System approach
• Study of nature
Study of nature
• A major task is to sort /differentiate the changes
A major task is to sort /differentiate the changes
caused by a project from those changes as part of
caused by a project from those changes as part of
natural cycles
natural cycles
2. Preliminary Site and Project Evaluation
• Review report
• Ask question: Why (need)?; What (area)?;
• Where (location)?; When (start/end)?; How (methods);
• Who and Whom?
• Go to site (take a good look for yourself)
• Meet local people, ketua kampung, etc.
11.
3. Scoping
• Consultother agencies, JPS, Forestry, Fisheries, marine,
etc.
• For confirmation
• Phone calls, fax, etc.
• Consult other experts, bodies, individuals.
• Geographic scope; boundary not too rigid; 3 km radius – JAS
• Time horizon
• Project schedule
• Project phasing
• long-term or short term
• Scoping meeting: call for presentation; refer to past /
previous EIA reports
12.
• Ranking prioritiesand alternatives
• How significant
• Relevancy
• Quantitative (not only qualitative).
• Compare with standards.
4.
4. Baseline Studies (Refer to Handouts).
Baseline Studies (Refer to Handouts).
• In-situ
In-situ
• Desk study
Desk study
• Analyses
Analyses
• Surveys
Surveys
• Refer to other studies.
Refer to other studies.
Notes: (Systematic surveys, monitoring, existing
Notes: (Systematic surveys, monitoring, existing
environment, Contents of EIA (Project Devmt.,
environment, Contents of EIA (Project Devmt.,
Description of Existing Env. (physical, chemical,
Description of Existing Env. (physical, chemical,
biological, & human); Identification & Assessment of
biological, & human); Identification & Assessment of
Impacts); Mitigation Measures; EMP (Monitoring
Impacts); Mitigation Measures; EMP (Monitoring
Program).
Program).
13.
BASELINE STUDIES
BASELINE STUDIES
States existing (and past) state of the
States existing (and past) state of the
environment.
environment.
Continuously through systematic surveys and
Continuously through systematic surveys and
monitoring.
monitoring.
Data from a well-studied site – better
Data from a well-studied site – better
understdng.
understdng.
14.
Descriptions ofenvironment:
Descriptions of environment:
1.
1. Topography and physical charact.
Topography and physical charact.
2.
2. Soils and geology.
Soils and geology.
3.
3. Meteorology and climatologic.
Meteorology and climatologic.
4.
4. Drainage system and hydrologic regime.
Drainage system and hydrologic regime.
5.
5. Land use.
Land use.
6.
6. Water quality.
Water quality.
7.
7. Air quality.
Air quality.
8.
8. Noise levels.
Noise levels.
9.
9. Traffic and transportation.
Traffic and transportation.
10.
10. Socio-economic.
Socio-economic.
11.
11. Amenities and utilities.
Amenities and utilities.
12.
12. Flora and fauna…etc. (other relevant issues).
Flora and fauna…etc. (other relevant issues).
Check-list
Check-list
• A reminderof all possible relationships and
A reminder of all possible relationships and
impacts – out which the significant issues are
impacts – out which the significant issues are
assessed/ analyzed in detail.
assessed/ analyzed in detail.
• Stimulates investigation.
Stimulates investigation.
Project Activities
Project Activities Environmental Impact
Environmental Impact
1.
1.Construction
Construction
•Land clearing
Land clearing
•Etc…..
Etc…..
•soil erosion
soil erosion
•Dust
Dust
•Noise..
Noise..
2.
2.Operation
Operation
•Wastewater
Wastewater
•Etc….
Etc….
• water quality
water quality
• odour
odour
17.
• Leopold matrixby Dr. Luna Leopold
Leopold matrix by Dr. Luna Leopold
• X – axis – all development activities
X – axis – all development activities
• Y – axis – all relevant environmental components
Y – axis – all relevant environmental components
• Each intersection can be used to indicate a possible impact or give
Each intersection can be used to indicate a possible impact or give
ratings of magnitude and importance.
ratings of magnitude and importance.
Ratings (1,2,3,or 4)
Ratings (1,2,3,or 4)
Environmental component
Project Activities
Project Activities
Where:
1. Significant environmental enhancement
2. Potentially significant adverse impact for which a design solution has been
identified
3. Potentially significant adverse impact – insufficient data/information to make
any reliable prediction.
4. Significant adverse residual impact.
18.
Example:
Example:
Land clearing
Land clearingEarthwork
Earthwork …
…..
..
Water
Water 2
2 2
2
Air
Air 2
2 2
2
Noise
Noise 2
2 2
2
…
…..
.. ..
.. ..
..
……
…… ..
.. ..
..
Human employment
Human employment 1
1 1
1
19.
Project Activities
Project Activities
Sourceof Pollution
Source of Pollution *
*
Significant
Significant
environmental
environmental
Impacts
Impacts *
*
Proposed mitigating
Proposed mitigating
measures
measures *
*
Residual
Residual
Impacts
Impacts *
*
DOE’s
DOE’s
Comment
Comment *
*
2. Impacts during
2. Impacts during
the operation
the operation
phase
phase
a) Wastewater
a) Wastewater
discharge
discharge
• an estimated 2422
an estimated 2422
m3/d of wastewater
m3/d of wastewater
will be discharged
will be discharged
by development.
by development.
Sequence:
*Notes: Filling out a matrix is not equivalent to performing an EIA - A matrix can
systematically identify potential important impacts warranting more careful attention.
20.
6. Prediction Methodsand Models.
6. Prediction Methods and Models.
• Extrapolation, interpolation, and analogy.
Extrapolation, interpolation, and analogy.
• Model.
Model.
• Standards.
Standards.
• Capacity and threshold concept.
Capacity and threshold concept.
21.
TYPICAL CONTENT OFEIA
TYPICAL CONTENT OF EIA
1.
1. PROJECT DEVELOPMENT.
PROJECT DEVELOPMENT.
2.
2. DESCRIPTION OF THE EXISTING
DESCRIPTION OF THE EXISTING
ENVIRONMENT.
ENVIRONMENT.
3.
3. IDENTIFICATION & ASSESSMENT
IDENTIFICATION & ASSESSMENT
OF IMPACTS.
OF IMPACTS.
4.
4. MITIGATION MEASURES.
MITIGATION MEASURES.
5.
5. ENVIRONMENTAL MONITORING
ENVIRONMENTAL MONITORING
PROGRAM (EMP)
PROGRAM (EMP)
22.
TYPICAL CONTENT OFEIA
TYPICAL CONTENT OF EIA
1.
1. PROJECT DEVELOPMENT
PROJECT DEVELOPMENT
• What? Dev. Concepts, utilities, services.
What? Dev. Concepts, utilities, services.
• Where? Location.
Where? Location.
• Who? Initiator, proponents, consultants.
Who? Initiator, proponents, consultants.
• Why? Statement of needs.
Why? Statement of needs.
• Whom? Public communities who will benefit.
Whom? Public communities who will benefit.
• How? Project activities – esp. construction phase:
How? Project activities – esp. construction phase:
land clearing, earthworks, infrastr., bldgs, constr.
land clearing, earthworks, infrastr., bldgs, constr.
methods, wastes disposal, dredging/excavation,
methods, wastes disposal, dredging/excavation,
reclamation.
reclamation.
• When? Project schedule (duration, phasing, work
When? Project schedule (duration, phasing, work
schedule).
schedule).
23.
2.
2. DESCRIPTION OFTHE EXISTING
DESCRIPTION OF THE EXISTING
ENVIRONMENT.
ENVIRONMENT.
i.
i. Physical:
Physical: Topography/physical charact., geology
Topography/physical charact., geology
& soil, drainage system & hydrologic regime;
& soil, drainage system & hydrologic regime;
land use; traffic & transportation; noise levels;
land use; traffic & transportation; noise levels;
meteorology; river morphology; etc.
meteorology; river morphology; etc.
ii.
ii. Chemical:
Chemical: Air quality; water quality.
Air quality; water quality.
iii.
iii. Biological:
Biological: Ecology; Flora & fauna; Habitat.
Ecology; Flora & fauna; Habitat.
iv.
iv. Human:
Human: Socio-economic (Social Impact
Socio-economic (Social Impact
Assessment – SIA); aesthetics & culture; health,
Assessment – SIA); aesthetics & culture; health,
safety, well-being, etc.
safety, well-being, etc.
24.
3.
3. IDENTIFICATION &ASSESSMENT
IDENTIFICATION & ASSESSMENT
OF IMPACTS
OF IMPACTS
Only the relevant, critical, significant
Only the relevant, critical, significant
impacts.
impacts.
Qualitative and quantitative assessment.
Qualitative and quantitative assessment.
Duration, frequency & intensity.
Duration, frequency & intensity.
Loss – tangible & intangible.
Loss – tangible & intangible.
Adjustment and adaptability.
Adjustment and adaptability.
Cost-benefit analysis.
Cost-benefit analysis.
4. MITIGATION MEASURES
4.MITIGATION MEASURES
Propose measures to reduce signif. adverse
Propose measures to reduce signif. adverse
impacts.
impacts.
– Abatement - to diminish or reduce; do away
Abatement - to diminish or reduce; do away
with nuisance.
with nuisance.
– Control - directing or restraining; subject to
Control - directing or restraining; subject to
guidance.
guidance.
– Prevention - hinder, stop.
Prevention - hinder, stop.
– Alleviate - lessen, less severe.
Alleviate - lessen, less severe.
– Mitigate - reduce severity, alleviate.
Mitigate - reduce severity, alleviate.
27.
Prediction methods andmodels:
Prediction methods and models:
Structural measures.
Structural measures.
Non-structural measures – management
Non-structural measures – management
plan; zoning; soft approach.
plan; zoning; soft approach.
Give options, alternatives: practical, cost-
Give options, alternatives: practical, cost-
effective; social acceptance.
effective; social acceptance.
Construction phase: Specify all measures
Construction phase: Specify all measures
into the overall design improvement.
into the overall design improvement.
28.
Example of achecklist (Handout)
Example of a checklist (Handout)
(For rural and urban water supply and sanitation projects)
Aspects of EIA – Checklist questions – Comments
Aspects of EIA – Checklist questions – Comments
Column.
Column.
Sources of Impacts (eroded materials, effluents,
Sources of Impacts (eroded materials, effluents,
solid wastes, etc.)
solid wastes, etc.)
Receptors of Impacts (aquatic ecosystems, flora
Receptors of Impacts (aquatic ecosystems, flora
& fauna, historical sites, etc.).
& fauna, historical sites, etc.).
Environmental Impacts (reduction in volume of
Environmental Impacts (reduction in volume of
water supply, liquid/solid wastes, fish stock,
water supply, liquid/solid wastes, fish stock,
diseases, etc.).
diseases, etc.).
Mitigating measures (will it require measures).
Mitigating measures (will it require measures).
Comments.
Comments.
29.
5. ENVIRONMENTAL MONITORING
5.ENVIRONMENTAL MONITORING
PROGRAM (EMP)
PROGRAM (EMP)
Final stage of EIA.
Final stage of EIA.
Continuous improvement – refer to EMS.
Continuous improvement – refer to EMS.
Post-audit.
Post-audit.
Compliance plan
Compliance plan – commitment to comply
– commitment to comply
with regulations, etc.
with regulations, etc.
30.
ENVIRONMENTAL MANAGEMENT SYSTEMS
ENVIRONMENTALMANAGEMENT SYSTEMS
(EMS)
(EMS)
• Kenapa Sistem Pengurusan Alam Sekeliling?
Kenapa Sistem Pengurusan Alam Sekeliling?
• Pencemaran alam sekitar (air, udara, tanah, sungai, airbumi).
Pencemaran alam sekitar (air, udara, tanah, sungai, airbumi).
• Punca (industri, pembangunan).
Punca (industri, pembangunan).
• Kesedaran - pembangunan/ pengeluaran tidak mampan.
Kesedaran - pembangunan/ pengeluaran tidak mampan.
• Kesedaran pihak industri/perniagaan - mengambilkira komponen
Kesedaran pihak industri/perniagaan - mengambilkira komponen
alam sekitar (industri/pembangunan).
alam sekitar (industri/pembangunan).
• Dahulu (ia hanya seperti bercanggah dan risiko).
Dahulu (ia hanya seperti bercanggah dan risiko).
• Sekarang (peluang, keperluan; menjadi persaingan di dalam
Sekarang (peluang, keperluan; menjadi persaingan di dalam
industri).
industri).
• Integrasi aspek alam sekitar di dalam pembangunan, eperasi
Integrasi aspek alam sekitar di dalam pembangunan, eperasi
industri (ada strategi dan polisi alam sekitar; hala-tuju (objektif)
industri (ada strategi dan polisi alam sekitar; hala-tuju (objektif)
alam sekitar dalam pembangunan dan operasi industri).
alam sekitar dalam pembangunan dan operasi industri).
• Alat (kaedah) - sistematik untuk mencapai polisi dan objektif (e.g.,
Alat (kaedah) - sistematik untuk mencapai polisi dan objektif (e.g.,
Sistem Pengurusan Alam Sekitar dan Audit Alam Sekitar).
Sistem Pengurusan Alam Sekitar dan Audit Alam Sekitar).
31.
•
Kaedah – seragamkansecara menyeluruh, merangkumi
Kaedah – seragamkan secara menyeluruh, merangkumi ‘global’
‘global’
agar ia digunapakai oleh semua mengikut
agar ia digunapakai oleh semua mengikut suatu piawaian.
suatu piawaian.
• Penghasilan EMS ISO 14000 (voluntary): SIRIM and ISO/TC 207.
Penghasilan EMS ISO 14000 (voluntary): SIRIM and ISO/TC 207.
• Generic Standards: Framework for managing env’al impacts of
Generic Standards: Framework for managing env’al impacts of
corporations (Refer to Table 1 (Handout).
corporations (Refer to Table 1 (Handout).
Why Environmental management?
1. Legislation and enforcement
2. Stakeholders’ pressure
• financial institution
• shareholders, employees
• environmental interest group, consumers, general public.
3. Awareness, image, and reputation: responsible, care;
corporate image; impact on business: liability, cost, business;
interruption, negative publicity, damage to image.
32.
4.
4. Competitiveness:
Competitiveness:
• awarenessfor impacts on competitiveness of
awareness for impacts on competitiveness of
environmental aspects of products and
environmental aspects of products and
processes;
processes;
• Trade barriers caused by different standards
Trade barriers caused by different standards
for environmental performance.
for environmental performance.
5.
5. Finance:
Finance:
• Economic instruments (taxes, levies, to
Economic instruments (taxes, levies, to
stimulate decreases in pollution
stimulate decreases in pollution
• Incentives from government, banking and
Incentives from government, banking and
insurance companies.
insurance companies.
Isu berkaitan Alamsekitar dikendalikan dengan 3 cara:
Isu berkaitan Alam sekitar dikendalikan dengan 3 cara:
1.
1. Tiada tindakan (‘NO ACTION’):
• Tidak buat apa-apa – tiada tindakan terhadap apa yg berlaku ke
atas alam sekitar. Sekiranya ambil tindakan - mungkin telah
terlambat.
• Pihak pemaju tidak nampak risiko yang akan berlaku dan atau
peluang di sebalik mengambilkira isu alam sekitar.
2. Bertindak mengikut keperluan, arahan, undang-undang
pematuhan (‘COMPLIANCE MANAGEMENT’):
• Bertindak apabila diarah/suruh terutamanya apabila berlakunya
krisis.
• Mengikut syarat kelulusan
• Baik untuk jangka masa pendek
• Suatu pendekatan yang ‘add-on’ (terasing) di dalam operasi
pembangunan / industri.
37.
3.
3. Pro-aktif (
Pro-aktif(EMS – SISTEM PENGURUSAN ALAM
EMS – SISTEM PENGURUSAN ALAM
SEKITAR
SEKITAR):
):
• Integrasi pengurusan alam sekitar ke dalam pengurusan keseluruhan.
Integrasi pengurusan alam sekitar ke dalam pengurusan keseluruhan.
• Bersistematik – kualiti.
Bersistematik – kualiti.
• Pendekatan ‘built-in’ atau ‘day-to-dayprocess’ (i.e.,menghayatinya
Pendekatan ‘built-in’ atau ‘day-to-dayprocess’ (i.e.,menghayatinya
sebagai satu proses semulajadi yg tertanam di dlm. diri).
sebagai satu proses semulajadi yg tertanam di dlm. diri).
• Pengawasan berterusan dilakukan.
Pengawasan berterusan dilakukan.
• Penyediaan pelan tindakan alam sekitar ( Env. Response Plan) - di
Penyediaan pelan tindakan alam sekitar ( Env. Response Plan) - di
peringkat awal sebelum berlakunya apa-apa krisis lebih bersedia
peringkat awal sebelum berlakunya apa-apa krisis lebih bersedia
menempuh krisis.
menempuh krisis.
• (e.g. tumpahan minyak, pembangunan second link).
(e.g. tumpahan minyak, pembangunan second link).
• Kurang masalah
Kurang masalah
• Kurang perbelanjaan.
Kurang perbelanjaan.