2
Most read
8
Most read
21
Most read
CATHODIC PROTECTION
OF ONSHORE OIL WELLS
Prepared by : Abinash Padhy
Email: abinash.cp@gmail.com
Introduction
 CP is the cost effective control of external well casing corrosion. CP is
an important tool because maintaining casing integrity is essential to oil
and gas production, water and gas injection, and gas storage fields.
 When a leak develops, production (or injection) usually ceases until the
leak is repaired or a liner is installed. When corrosion is severe, the
casing can collapse and the well may have to be abandoned, which can
result in lost reserves.
CP of Well Casings Vs. Pipelines
 The pipe is vertical to the surface rather than parallel.
 Pipe-to-soil potential measurements can only be made at the end from which the current
is drained. Potentials cannot be directly measured along the outside surface of the
casing.
 Well casings are connected by threaded collars rather than welded connections, which
may increase the resistance of the metallic path.
 Soil/formation changes with length/depth.
 Well casings are typically installed without an organic coating on the OD (outside
diameter), although most have a partial cement coating.
 Long lengths of the production casing are shielded from CP by surface and intermediate
casing strings.
Cathodic Protection For Oil Wells
Limitations
 CP can mitigate corrosion only on the exposed external surfaces of
a well casing. A conventional CP system has no effect on the
internal surfaces of the well casing or any production equipment
inside the well casing. Because of space restrictions, it is not
practical to install a long anode (or series of anodes) that is
capable of protecting the inside of the well casing.
 CP is only effective on those external surfaces of the casing strings
which are in direct contact with the environment. Conductor pipe,
surface casing, and intermediate casing will shield the areas of the
production casing string contained within it.
Notes
 A metallic well casing that is not installed through a corrosive
formation and does not have a permanent flow-line does NOT require
cathodic protection. However, if a foreign impressed current anode
bed is within 200 meters of this type of well, electrical bonding shall
be implemented to minimize the probability of Downhole
interference.
 The farther the anode bed is placed from the subject well, the deeper
the well can be protected and the more even its current distribution.
Notes
 A metallic well casing that has not been coated with Fusion Bonded Epoxy (FBE) and
is installed within a metallic or non-metallic cellar and backfilled shall be provided with
two prepackaged 27.5 kg (60 lb) magnesium anodes installed inside the wellhead
cellar to provide supplemental cathodic protection for the landing base area.
 Supplemental galvanic anodes for permanent protection of the landing base area are
not required for well casings that:
*Do not have cellars
*Are installed in cellars that are not backfilled, or
* Are FBE coated through the cellar area. .
 Corrosivity increases in deeper layers of soil where formation is restricted by salt and
concentration cells may formed.
Coated Casing
 A well casing with an external non-conductive coating (typically Fusion Bond Epoxy
or FBE). The coating must be applied to all sections of the casing in contact with soil
or formation, from surface to the bottom of the casing or to a depth determined to
facilitate external corrosion mitigation with cathodic protection through the relevant
down hole corrosive aquifers.
 Casings that have been coated over the upper two or three joints of casing only are
not “coated casings”. Coating applied to well casings is not applied as a corrosion
barrier. It is applied to reduce the total amount of CP required or to extend the
influence of the applied CP.
 Coated well casings do not require a dedicated negative cable and are not restricted
by the 2 km separation imposed on CP systems with multiple uncoated well casings.
Uncoated Casing
 A well casing that is either bare (no external coating), or may have an
external coating applied to the shallow sections of casing to minimize
corrosion in the landing base or surface soils.
 Uncoated well casings separated by less than 2 km may utilize a
single CP power source.
Investigation for Corrosion Damage
1. Exact depth of the screw socket connections
2. Reduction from the average wall thickness
3. Attach by internal corrosion penetration.
** Methods 1 & 2 are electromagnetic or eddy
current While Method 3 is a mechanical system
similar to caliper pig.
CP For Onshore Well Casings
 DEDICATED ICCP SYSTEM
 SHARED ICCP SYSTEM
 GALVANIC CP SYSTEM
Cathodic Protection For Oil Wells
CP POWER SUPPLY
Photovoltaic Galvanic AC Powered
Air
Cooled/Oil
Cooled
Single
Phase/Three
Phase
Remote monitoring unit
 Signal Transmitters,
or
 A Remote Monitoring Unit (RMU)
 Operating parameters to be monitored
 Communication system to be decided
 Software to be decided
Design
Estimate current requirement.
Design test groundbed for E log I test.
Determine anode-well separation.
Size photo voltaic power system.
Design anode suited to power source.
Design
 Soil Resistivity Survey
 Site Information- Buried structures within 200 m of the proposed
anode bed & well casing.
 Field verified operating data for existing CP equipment within 200
meters of the proposed anode bed or associated well casing.
 Site tests on each relevant type of well casing to determine the
respective resistance to ground are required.
Design
 Permanent buried flare lines and blow down lines on a well pad shall be
made permanently electrically continuous with the well casing or the
negative circuit of the well casing CP system.
 The use of a photovoltaic CP power supply shall be assessed from an
economic perspective for cathodic protection of new wells located more
than 3 kilometers from the nearest 4.16 kV or 13.8 kV power line.
 Resistors shall not be designed into a multi-well CP system, however, if
during commissioning, adequate current distribution is not achieved, If
resistors are approved as stated above, they shall be welded tap
adjustable or fixed (non-adjustable) resistors and shall be 0.15 ohms or
less
Distance from Anode Bed-Well casings &
Other protected Structures
 For an anode bed discharging 25 amperes or more, a
minimum distance of 150 meters shall be maintained between
the nearest anode and the well casing.
 For an anode bed discharging less than 25 amperes, a
minimum distance of 75 meters shall be maintained between
the nearest anode and the well casing
Mathematical Modeling for Current
Requirement
 Schremp-Newton. The technique is a modification of the Pope attenuation model
used for pipelines. The Schremp- Newton model requires only some wellhead
potential measurements collected from a specific well already under CP. This is a
useful technique for single wells that have minimal interference effects. It is the
preferred procedure for calculating downhole potentials for various currents on an
actual well casing.
 Dabkowski. Resistivities at various depths and well patterns are required for input.
Dabkowski's model allows the effects of many different resistivity layers to be
evaluated. It also can evaluate interference effects of multiple anode beds and wells.
 BEM (boundary element model). This model is currently in use to evaluate
current requirements and potentials on complex structures, such as offshore
platforms. Because of difficulty in setting up input files with layered resistivities,
convergence problems, and their CPU intensive nature, BEMs are not commonly used
to evaluate well casing CP
Interference
 In oilfields with high paraffin content, the
production tubing has to be cleaned by heating every
week to remove the paraffin deposits. The heating of
the pipe takes place while a DC of about 1.2 kA is fed
into the production tubing from the wellhead.
 During the heating period the lower part of the
casing is anodically polarized, this can interfere with
the wells within a radius of 1000 m.
CP Monitoring for well casings
Protection Criteria
 Incase of separate protection current supply for flow lines, the
pipe/soil On potential should be -1.5 V CSE.
 Interference can only be suppressed by an equal potential bond
to the cathodically protected structure.
Conclusion
1. Identify the candidate wells.
a. Search well files.
b. Record date and depth of leak (and other related well data).
c. Use open hole logs to correlate leaks with specific geologic formations.
d. Create a cumulative leak plot and estimate current/future repair cost.
e. Verify cause of leaks with inspection logs.
2. Determine casing current requirement.
a. Use Dabkowski's model.
b. Install a pilot anode bed and energize.
c. Use Schremp-Newton's model to adjust current on test wells.
d. Log test wells 90 to 180 days after final adjustment.
3. Design and install the field-wide system.
a. Determine the anode bed type and depth.
b. Decide on the number of wells per anode bed.
c. Calculate the number of anodes and amount of backfill.
d. Estimate the total installed cost and run economic justification.
e. Establish a time table and begin system installation.
4. Monitor and adjust the system.
a. Energize anode beds and adjust to design current density.
b. Check for interference on foreign wells and pipelines.
c. Optionally run a CPP log to determine effects from the field wide system.
d. Establish a monitoring, adjustment, and maintenance program

More Related Content

PDF
PDF
Well Completion Design.pdf
PPTX
Wireline Operaciones - corta.pptx
PDF
Coiled Tubing Conveyed Perforations
PDF
Drilling Rig Components ( Illustrated Glossary )
PDF
Cathodic Protection
PPT
A Brief Introduction to Coiled Tubing: What is it? What to do with it?, pumps...
PDF
Side sliding door ssd
Well Completion Design.pdf
Wireline Operaciones - corta.pptx
Coiled Tubing Conveyed Perforations
Drilling Rig Components ( Illustrated Glossary )
Cathodic Protection
A Brief Introduction to Coiled Tubing: What is it? What to do with it?, pumps...
Side sliding door ssd

What's hot (20)

PDF
Completion equipment packer part #2
PDF
Well abandonment process procedures
PPTX
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
PDF
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
PPTX
Well intervention
PDF
104980410 control-valve-calibration-procedure-fisher-hc6010
PDF
CEEM Advanced Hydraulic Workover Unit
PDF
Oil Production Facilities
PDF
Wellheads and Flow Lines.pdf
PDF
PDF
Wellhead function, rating and selection
PDF
Ssd spm
DOC
packer de produccion
PDF
Coiled tubing Equipments .pdf
PPT
well control (1)
PDF
Overview of subsea production systems
PPTX
Cathodic protection fundamentals
PDF
Liner hanger design and operations
PPTX
GLOSARIO DE COMPLETACIÓN DE POZOS PETROLEROS
PPTX
Well control equipment
Completion equipment packer part #2
Well abandonment process procedures
Hydraulic workover and snubbing solutions, رضا مصطفوی طباطبایی
SPII Compact Wellhead - Worldwide Oilfield Machine Inc.
Well intervention
104980410 control-valve-calibration-procedure-fisher-hc6010
CEEM Advanced Hydraulic Workover Unit
Oil Production Facilities
Wellheads and Flow Lines.pdf
Wellhead function, rating and selection
Ssd spm
packer de produccion
Coiled tubing Equipments .pdf
well control (1)
Overview of subsea production systems
Cathodic protection fundamentals
Liner hanger design and operations
GLOSARIO DE COMPLETACIÓN DE POZOS PETROLEROS
Well control equipment
Ad

Similar to Cathodic Protection For Oil Wells (20)

PDF
Thiết kế đường ống trên bờ
PPTX
external & internal corrosion monitoring
PPTX
PDF
training-presentation-on-cathodic-pritection_compress.pdf
PPTX
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
DOCX
A Training Report Of Saltlake 132/33kv Substation
PDF
Presentation: AC Mitigation Case Histories
PDF
Ccs for solar power pv plant
PDF
Ccs for solar power pv plant
PDF
Thiet ke duong_ong_tren_bo
PPTX
Seismic response of steel beams coupling concrete walls
PPTX
Module-2 - Copy.pptxIt is a crucial process for creating specific region with...
PDF
ملزمة
PDF
Nbc2016 and iec information jmv lps
PDF
Drilling Engineering - Casing Design
PDF
Your electrical safety specilist for all equipments Powered AC and DC
PDF
3-Cs Eucas 2015 Poster v2
PDF
Jmv presentation solar
PPTX
Impressed Current Cathodic Protection System Design ICCP
Thiết kế đường ống trên bờ
external & internal corrosion monitoring
training-presentation-on-cathodic-pritection_compress.pdf
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
A Training Report Of Saltlake 132/33kv Substation
Presentation: AC Mitigation Case Histories
Ccs for solar power pv plant
Ccs for solar power pv plant
Thiet ke duong_ong_tren_bo
Seismic response of steel beams coupling concrete walls
Module-2 - Copy.pptxIt is a crucial process for creating specific region with...
ملزمة
Nbc2016 and iec information jmv lps
Drilling Engineering - Casing Design
Your electrical safety specilist for all equipments Powered AC and DC
3-Cs Eucas 2015 Poster v2
Jmv presentation solar
Impressed Current Cathodic Protection System Design ICCP
Ad

Cathodic Protection For Oil Wells

  • 1. CATHODIC PROTECTION OF ONSHORE OIL WELLS Prepared by : Abinash Padhy Email: [email protected]
  • 2. Introduction  CP is the cost effective control of external well casing corrosion. CP is an important tool because maintaining casing integrity is essential to oil and gas production, water and gas injection, and gas storage fields.  When a leak develops, production (or injection) usually ceases until the leak is repaired or a liner is installed. When corrosion is severe, the casing can collapse and the well may have to be abandoned, which can result in lost reserves.
  • 3. CP of Well Casings Vs. Pipelines  The pipe is vertical to the surface rather than parallel.  Pipe-to-soil potential measurements can only be made at the end from which the current is drained. Potentials cannot be directly measured along the outside surface of the casing.  Well casings are connected by threaded collars rather than welded connections, which may increase the resistance of the metallic path.  Soil/formation changes with length/depth.  Well casings are typically installed without an organic coating on the OD (outside diameter), although most have a partial cement coating.  Long lengths of the production casing are shielded from CP by surface and intermediate casing strings.
  • 5. Limitations  CP can mitigate corrosion only on the exposed external surfaces of a well casing. A conventional CP system has no effect on the internal surfaces of the well casing or any production equipment inside the well casing. Because of space restrictions, it is not practical to install a long anode (or series of anodes) that is capable of protecting the inside of the well casing.  CP is only effective on those external surfaces of the casing strings which are in direct contact with the environment. Conductor pipe, surface casing, and intermediate casing will shield the areas of the production casing string contained within it.
  • 6. Notes  A metallic well casing that is not installed through a corrosive formation and does not have a permanent flow-line does NOT require cathodic protection. However, if a foreign impressed current anode bed is within 200 meters of this type of well, electrical bonding shall be implemented to minimize the probability of Downhole interference.  The farther the anode bed is placed from the subject well, the deeper the well can be protected and the more even its current distribution.
  • 7. Notes  A metallic well casing that has not been coated with Fusion Bonded Epoxy (FBE) and is installed within a metallic or non-metallic cellar and backfilled shall be provided with two prepackaged 27.5 kg (60 lb) magnesium anodes installed inside the wellhead cellar to provide supplemental cathodic protection for the landing base area.  Supplemental galvanic anodes for permanent protection of the landing base area are not required for well casings that: *Do not have cellars *Are installed in cellars that are not backfilled, or * Are FBE coated through the cellar area. .  Corrosivity increases in deeper layers of soil where formation is restricted by salt and concentration cells may formed.
  • 8. Coated Casing  A well casing with an external non-conductive coating (typically Fusion Bond Epoxy or FBE). The coating must be applied to all sections of the casing in contact with soil or formation, from surface to the bottom of the casing or to a depth determined to facilitate external corrosion mitigation with cathodic protection through the relevant down hole corrosive aquifers.  Casings that have been coated over the upper two or three joints of casing only are not “coated casings”. Coating applied to well casings is not applied as a corrosion barrier. It is applied to reduce the total amount of CP required or to extend the influence of the applied CP.  Coated well casings do not require a dedicated negative cable and are not restricted by the 2 km separation imposed on CP systems with multiple uncoated well casings.
  • 9. Uncoated Casing  A well casing that is either bare (no external coating), or may have an external coating applied to the shallow sections of casing to minimize corrosion in the landing base or surface soils.  Uncoated well casings separated by less than 2 km may utilize a single CP power source.
  • 10. Investigation for Corrosion Damage 1. Exact depth of the screw socket connections 2. Reduction from the average wall thickness 3. Attach by internal corrosion penetration. ** Methods 1 & 2 are electromagnetic or eddy current While Method 3 is a mechanical system similar to caliper pig.
  • 11. CP For Onshore Well Casings  DEDICATED ICCP SYSTEM  SHARED ICCP SYSTEM  GALVANIC CP SYSTEM
  • 13. CP POWER SUPPLY Photovoltaic Galvanic AC Powered Air Cooled/Oil Cooled Single Phase/Three Phase
  • 14. Remote monitoring unit  Signal Transmitters, or  A Remote Monitoring Unit (RMU)  Operating parameters to be monitored  Communication system to be decided  Software to be decided
  • 15. Design Estimate current requirement. Design test groundbed for E log I test. Determine anode-well separation. Size photo voltaic power system. Design anode suited to power source.
  • 16. Design  Soil Resistivity Survey  Site Information- Buried structures within 200 m of the proposed anode bed & well casing.  Field verified operating data for existing CP equipment within 200 meters of the proposed anode bed or associated well casing.  Site tests on each relevant type of well casing to determine the respective resistance to ground are required.
  • 17. Design  Permanent buried flare lines and blow down lines on a well pad shall be made permanently electrically continuous with the well casing or the negative circuit of the well casing CP system.  The use of a photovoltaic CP power supply shall be assessed from an economic perspective for cathodic protection of new wells located more than 3 kilometers from the nearest 4.16 kV or 13.8 kV power line.  Resistors shall not be designed into a multi-well CP system, however, if during commissioning, adequate current distribution is not achieved, If resistors are approved as stated above, they shall be welded tap adjustable or fixed (non-adjustable) resistors and shall be 0.15 ohms or less
  • 18. Distance from Anode Bed-Well casings & Other protected Structures  For an anode bed discharging 25 amperes or more, a minimum distance of 150 meters shall be maintained between the nearest anode and the well casing.  For an anode bed discharging less than 25 amperes, a minimum distance of 75 meters shall be maintained between the nearest anode and the well casing
  • 19. Mathematical Modeling for Current Requirement  Schremp-Newton. The technique is a modification of the Pope attenuation model used for pipelines. The Schremp- Newton model requires only some wellhead potential measurements collected from a specific well already under CP. This is a useful technique for single wells that have minimal interference effects. It is the preferred procedure for calculating downhole potentials for various currents on an actual well casing.  Dabkowski. Resistivities at various depths and well patterns are required for input. Dabkowski's model allows the effects of many different resistivity layers to be evaluated. It also can evaluate interference effects of multiple anode beds and wells.  BEM (boundary element model). This model is currently in use to evaluate current requirements and potentials on complex structures, such as offshore platforms. Because of difficulty in setting up input files with layered resistivities, convergence problems, and their CPU intensive nature, BEMs are not commonly used to evaluate well casing CP
  • 20. Interference  In oilfields with high paraffin content, the production tubing has to be cleaned by heating every week to remove the paraffin deposits. The heating of the pipe takes place while a DC of about 1.2 kA is fed into the production tubing from the wellhead.  During the heating period the lower part of the casing is anodically polarized, this can interfere with the wells within a radius of 1000 m.
  • 21. CP Monitoring for well casings
  • 22. Protection Criteria  Incase of separate protection current supply for flow lines, the pipe/soil On potential should be -1.5 V CSE.  Interference can only be suppressed by an equal potential bond to the cathodically protected structure.
  • 23. Conclusion 1. Identify the candidate wells. a. Search well files. b. Record date and depth of leak (and other related well data). c. Use open hole logs to correlate leaks with specific geologic formations. d. Create a cumulative leak plot and estimate current/future repair cost. e. Verify cause of leaks with inspection logs. 2. Determine casing current requirement. a. Use Dabkowski's model. b. Install a pilot anode bed and energize. c. Use Schremp-Newton's model to adjust current on test wells. d. Log test wells 90 to 180 days after final adjustment. 3. Design and install the field-wide system. a. Determine the anode bed type and depth. b. Decide on the number of wells per anode bed. c. Calculate the number of anodes and amount of backfill. d. Estimate the total installed cost and run economic justification. e. Establish a time table and begin system installation. 4. Monitor and adjust the system. a. Energize anode beds and adjust to design current density. b. Check for interference on foreign wells and pipelines. c. Optionally run a CPP log to determine effects from the field wide system. d. Establish a monitoring, adjustment, and maintenance program