Chapter 11 –
Project Risk Management
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Identify Risk
SIXTH EDITION
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
11.2 Identify Risks
Identify Risks - Definition
Who is involved in Risk identification?
Identify Risks : ITTO
What is Delphi technique?
What is Risk register?
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Risk Management Processes
Plan Risk
management
Identify Risk
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
Plan Risk Response Implement Risk Monitor Risk
P
MC
P P P
P E
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Determine which risks may affect the project
& document their characteristics
Focuses on documentation of existing risks. It provides
Knowledge & ability to project team, to anticipate events.
Project
Risk1
Risk2
Risk3
Risk4Risk5
Risk6
Risk7
Identify Risk -> Definition
Determine Risks Documenting their characteristics
Document
Risk
Charaterstics1
Charaterstics2
Charaterstics3
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Identification is an iterative process.
Consistent format should be used to ensure each risk is understood
clearly & unambiguously.
Ownership & Responsibility - Project team should be involved in the
process.
The more participants involved in the process will help to identify more
risks.
Identify Risk -> Introduction
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Manager /
Project team
Risk
Management
Experts
Customers &
end users
SME /
Consultants
Project
stakeholders
Industry
representatives
Quality/ HR
experts
Identify Risk -> Stakeholders involved
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Identify Risk ->ITTO
Expert Judgment
Data Gathering
Data analysis
Interpersonal and team skills
Prompt lists
Meetings
Project Management Plan
Project documents
Agreements
Procurement Documents
Enterprise environmental factors
Organizational process assets
Risk Register
Risk Report
Project document updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Management
Plan
Project documents Agreements
Procurement
Documents
Enterprise
environmental factors
Organizational process
assets
Identify Risk ->Inputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Requirements
Manag. Plan
Schedule
Manag. plan
Cost Manag.
Plan
Quality Manag.
Plan
Resource
Manag. Plan
Risk Manag.
Plan
Identify Risk ->Inputs -> PMP
Scope baseline
Schedule
baseline
Cost baseline
Baselines
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project documents Assumption log
Lessons learned
register
Requirements
documentation
Risk Register
Stakeholder
Register
Issue log
Cost estimates Duration Estimates
Identify Risk ->Inputs -> Project documents
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment Data Gathering Data Analysis Prompt lists
Meeting
Interpersonal &
team skills
Identify Risk ->Tools & Techniques
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Gathering Checklist Brainstorming Interviews
Identify Risk ->T&T-> Data Gathering
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Gathering Checklist
Identify Risk ->T&T-> Data Gathering
Risk identification checklists.
Lowest level of RBS can be used as checklist.
Best if Developed based on prior projects.
It is impossible to build exhaustive checklist.
Over reliance over checklist should be avoided.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Analysis
Root cause
analysis
Assumptions &
Constraints
analysis
SWOT analysis
Document
analysis
Identify Risk ->T&T -> Data Analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Analysis
SWOT analysis
• It is a framework for analyzing organization's strengths &
weaknesses, & the opportunities and threats that you face.
Identify Risk ->T&T -> Data Analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data Analysis
Assumptions & Constraints analysis
•It explores the validity of assumptions as they
applied to the project.
•All project assumptions should be verified.
•Changes to assumptions or new assumptions
should be identified.
•Focus on the assumptions that impacts
multiple project objectives.
Document analysis:
•Understand the content of all relevant
documents
•Focus on Scope, cost, time & quality
•Question Assumption, Constraints
•Quality of doc - completeness, consistency
Identify Risk ->T&T -> Data Analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment
Expertize should be considered from groups or individuals with specialized
knowledge in the area of Risk management.
Senior Management Project Stakeholders
PM with similar
project experience
Subject Matter
expert
Consultants
Professional &
technical associates
Identify Risks->T&T->Expert Judgement
Help PM to do
SWOT analysis
Use Delphi
technique to
identify risks.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Prompt lists
Prompt lists are predetermined list of categories.
The lowest level of RBS is used as prompt list.
strategic frameworks to identifying overall project risks - PESTLE, TECOP, VUCA
Identify Risks->T&T-> Prompt lists
Complexity
Multiple key decision
factors
Volatility
Rate of change
Ambiguity
Lack of clarity about
meaning of an event
Uncertainty
Unclear about the
present
VUCA
Howwellcanyoupredictthe
outcomeofyouractions?
How much do you know about the situation?
+
+- -
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Prompt lists
Identify Risks->T&T-> Prompt lists
PESTLE
Political Economic Social Technological Legal Environmental.
TECOP
Technical Economical Commercial Organizational Political.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Register Risk Report Project doc. updates
Identify Risks->Output->Risk Register
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Register
The output is, initial entries into the risk register, which includes:
Identify Risks->Output->Risk Register
Risk Register:
List of risk
List of initial
POTENTIAL
responses
Potential risk
owners
Root causes of risks
Updated risk
categories
Impact
I
D
Risk Statement Probability Scope Quality Schedule Cost Potential Response
Potential
Owner
1
Project owner on the client
side is replaced.
Low Medium Orient new project owner.
Project
Manager
2
Senior programmer is taken
from the project.
Medium High High
Find replacement
programmer.
Project
Manager
3
External system A is not ready
in time to implement feature
B.
High Low Medium Low
Discuss with stakeholders and
make adjustments as agreed.
Project
Manager
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk
Register
Risk Statement:
Identify Risks->Output->Risk Register
Context Risk Statement
Source Condition Consequences
If (event) occurs due to (driver), the consequences
could result in (impact).
Significant delays in retrieving records due to
current tools for data storage and retrieval practices
may leave the department unable to adequately
respond to Access to Information requests.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project doc. updates Assumption log Issue log
Lessons learned
register
Identify Risks->Output-> Project doc. updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Who is involved in Risk identification?
What is Delphi technique?
What is assumption analysis?
What is SWOT analysis.
What is Risk register?
What is risk statement.
Identify Risks -> Review
By: Anand Bobade (nmbobade@gmail.com)

Chap 11.2 Identify Risks

  • 1.
    By: Anand Bobade([email protected]) Chapter 11 – Project Risk Management PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Identify Risk SIXTH EDITION
  • 2.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) 11.2 Identify Risks Identify Risks - Definition Who is involved in Risk identification? Identify Risks : ITTO What is Delphi technique? What is Risk register? Review
  • 3.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Project Risk Management Processes Plan Risk management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Response Implement Risk Monitor Risk P MC P P P P E
  • 4.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Determine which risks may affect the project & document their characteristics Focuses on documentation of existing risks. It provides Knowledge & ability to project team, to anticipate events. Project Risk1 Risk2 Risk3 Risk4Risk5 Risk6 Risk7 Identify Risk -> Definition Determine Risks Documenting their characteristics Document Risk Charaterstics1 Charaterstics2 Charaterstics3
  • 5.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Risk Identification is an iterative process. Consistent format should be used to ensure each risk is understood clearly & unambiguously. Ownership & Responsibility - Project team should be involved in the process. The more participants involved in the process will help to identify more risks. Identify Risk -> Introduction
  • 6.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Project Manager / Project team Risk Management Experts Customers & end users SME / Consultants Project stakeholders Industry representatives Quality/ HR experts Identify Risk -> Stakeholders involved
  • 7.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Identify Risk ->ITTO Expert Judgment Data Gathering Data analysis Interpersonal and team skills Prompt lists Meetings Project Management Plan Project documents Agreements Procurement Documents Enterprise environmental factors Organizational process assets Risk Register Risk Report Project document updates Inputs Tools & Techniques Outputs
  • 8.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Project Management Plan Project documents Agreements Procurement Documents Enterprise environmental factors Organizational process assets Identify Risk ->Inputs
  • 9.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Project Management Plan Requirements Manag. Plan Schedule Manag. plan Cost Manag. Plan Quality Manag. Plan Resource Manag. Plan Risk Manag. Plan Identify Risk ->Inputs -> PMP Scope baseline Schedule baseline Cost baseline Baselines
  • 10.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Project documents Assumption log Lessons learned register Requirements documentation Risk Register Stakeholder Register Issue log Cost estimates Duration Estimates Identify Risk ->Inputs -> Project documents
  • 11.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Expert Judgment Data Gathering Data Analysis Prompt lists Meeting Interpersonal & team skills Identify Risk ->Tools & Techniques
  • 12.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Data Gathering Checklist Brainstorming Interviews Identify Risk ->T&T-> Data Gathering
  • 13.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Data Gathering Checklist Identify Risk ->T&T-> Data Gathering Risk identification checklists. Lowest level of RBS can be used as checklist. Best if Developed based on prior projects. It is impossible to build exhaustive checklist. Over reliance over checklist should be avoided.
  • 14.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Data Analysis Root cause analysis Assumptions & Constraints analysis SWOT analysis Document analysis Identify Risk ->T&T -> Data Analysis
  • 15.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Data Analysis SWOT analysis • It is a framework for analyzing organization's strengths & weaknesses, & the opportunities and threats that you face. Identify Risk ->T&T -> Data Analysis
  • 16.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Data Analysis Assumptions & Constraints analysis •It explores the validity of assumptions as they applied to the project. •All project assumptions should be verified. •Changes to assumptions or new assumptions should be identified. •Focus on the assumptions that impacts multiple project objectives. Document analysis: •Understand the content of all relevant documents •Focus on Scope, cost, time & quality •Question Assumption, Constraints •Quality of doc - completeness, consistency Identify Risk ->T&T -> Data Analysis
  • 17.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Expert Judgment Expertize should be considered from groups or individuals with specialized knowledge in the area of Risk management. Senior Management Project Stakeholders PM with similar project experience Subject Matter expert Consultants Professional & technical associates Identify Risks->T&T->Expert Judgement Help PM to do SWOT analysis Use Delphi technique to identify risks.
  • 18.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Prompt lists Prompt lists are predetermined list of categories. The lowest level of RBS is used as prompt list. strategic frameworks to identifying overall project risks - PESTLE, TECOP, VUCA Identify Risks->T&T-> Prompt lists Complexity Multiple key decision factors Volatility Rate of change Ambiguity Lack of clarity about meaning of an event Uncertainty Unclear about the present VUCA Howwellcanyoupredictthe outcomeofyouractions? How much do you know about the situation? + +- -
  • 19.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Prompt lists Identify Risks->T&T-> Prompt lists PESTLE Political Economic Social Technological Legal Environmental. TECOP Technical Economical Commercial Organizational Political.
  • 20.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Risk Register Risk Report Project doc. updates Identify Risks->Output->Risk Register
  • 21.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Risk Register The output is, initial entries into the risk register, which includes: Identify Risks->Output->Risk Register Risk Register: List of risk List of initial POTENTIAL responses Potential risk owners Root causes of risks Updated risk categories Impact I D Risk Statement Probability Scope Quality Schedule Cost Potential Response Potential Owner 1 Project owner on the client side is replaced. Low Medium Orient new project owner. Project Manager 2 Senior programmer is taken from the project. Medium High High Find replacement programmer. Project Manager 3 External system A is not ready in time to implement feature B. High Low Medium Low Discuss with stakeholders and make adjustments as agreed. Project Manager
  • 22.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Risk Register Risk Statement: Identify Risks->Output->Risk Register Context Risk Statement Source Condition Consequences If (event) occurs due to (driver), the consequences could result in (impact). Significant delays in retrieving records due to current tools for data storage and retrieval practices may leave the department unable to adequately respond to Access to Information requests.
  • 23.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Project doc. updates Assumption log Issue log Lessons learned register Identify Risks->Output-> Project doc. updates
  • 24.
    PMBOK 6 -All rights reserved; By: Anand Bobade ([email protected]) Who is involved in Risk identification? What is Delphi technique? What is assumption analysis? What is SWOT analysis. What is Risk register? What is risk statement. Identify Risks -> Review
  • 25.