McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved.
17
17
Project
Management
17-2
Learning Objectives
Learning Objectives
 Discuss the behavioral aspects of projects
in terms of project personnel and the
project manager.
 Discuss the nature and importance of a
work breakdown structure in project
management.
 Give a general description of PERT/CPM
techniques.
 Construct simple network diagrams.
17-3
Learning Objectives
Learning Objectives
 List the kinds of information that a PERT or
CPM analysis can provide.
 Analyze networks with deterministic times.
 Analyze networks with probabilistic times.
 Describe activity “crashing” and solve
typical problems.
17-4
Unique, one-time operations designed to
Unique, one-time operations designed to
accomplish a specific set of objectives in a limited
accomplish a specific set of objectives in a limited
time frame.
time frame.
Build A
A Done
Build B
B Done
Build C
C Done
Build D
Ship
JAN FEB MAR APR MAY JUN
On time!
Projects
Projects
17-5
Project Management
Project Management
 How is it different?
 Limited time frame
 Narrow focus, specific objectives
 Less bureaucratic
 Why is it used?
 Special needs
 Pressures for new or improves products or
services
17-6
Project Management
Project Management
 What are the Key Metrics
 Time
 Cost
 Performance objectives
 What are the Key Success Factors?
 Top-down commitment
 Having a capable project manager
 Having time to plan
 Careful tracking and control
 Good communications
17-7
Project Management
Project Management
 What are the Major Administrative
Issues?
 Executive responsibilities
 Project selection
 Project manager selection
 Organizational structure
 Organizational alternatives
 Manage within functional unit
 Assign a coordinator
 Use a matrix organization with a project leader
17-8
Project Management
Project Management
 What are the tools?
 Work breakdown structure
 Network diagram
 Gantt charts
 Risk management
17-9
Planning and Scheduling
Planning and Scheduling
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Locate new
facilities
Interview staff
Hire and train staff
Select and order
furniture
Remodel and install
phones
Move in/startup
Gantt Chart
17-10
 Deciding which projects to implement
 Selecting a project manager
 Selecting a project team
 Planning and designing the project
 Managing and controlling project resources
 Deciding if and when a project should be
terminated
Key Decisions
Key Decisions
17-11
Project Manager
Project Manager
Responsible for:
Work Quality
Human Resources Time
Communications Costs
17-12
 Temptation to understate costs
 Withhold information
 Misleading status reports
 Falsifying records
 Comprising workers’ safety
 Approving substandard work
Ethical Issues
Ethical Issues
17-13
Project Life Cycle
Project Life Cycle
Concept
Feasibility
Planning
Execution
Termination
Management
17-14
Work Breakdown Structure
Work Breakdown Structure
Project X
Level 1
Level 2
Level 3
Level 4
Figure 17.2
17-15
PERT and CPM
PERT and CPM
PERT: Program Evaluation and
Review Technique
CPM: Critical Path Method
 Graphically displays project activities
 Estimates how long the project will take
 Indicates most critical activities
 Show where delays will not affect project
17-16
The Network Diagram
The Network Diagram
 Network (precedence) diagram – diagram of
project activities that shows sequential
relationships by the use of arrows and nodes.
 Activity-on-arrow (AOA) – a network diagram
convention in which arrows designate activities.
 Activity-on-node (AON) – a network diagram
convention in which nodes designate activities.
 Activities – steps in the project that consume
resources and/or time.
 Events – the starting and finishing of activities,
designated by nodes in the AOA convention.
17-17
The Network Diagram (cont’d)
The Network Diagram (cont’d)
 Path
 Sequence of activities that leads from the starting
node to the finishing node
 Critical path
 The longest path; determines expected project
duration
 Critical activities
 Activities on the critical path
 Slack
 Allowable slippage for path; the difference the
length of path and the length of critical path
17-18
Project Network – Activity on
Project Network – Activity on
Arrow
Arrow
1
2
3
4
5 6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Hire and
train
Remodel
Move
in
Figure 17.4
AOA
17-19
Project Network – Activity on
Project Network – Activity on
Node
Node
1
2
3
5
6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Remodel
Move
in
4
Hire and
train
7
S
Figure 17.4
AON
17-20
Network Conventions
Network Conventions
a
b
c a
b
c
a
b
c
d
a
b
c
Dummy
activity
17-21
Time Estimates
Time Estimates
 Deterministic
 Time estimates that are fairly certain
 Probabilistic
 Estimates of times that allow for variation
17-22
Example 1
Example 1
1
2
3
4
5 6
8 weeks
6 weeks
3 weeks
4 weeks
9 weeks
11 weeks
1 week
Locate
facilities
Order
furniture
F
u
r
n
i
t
u
r
e
s
e
t
u
p
Interview
Hire and train
Remodel Move
in
Deterministic
Deterministic
time estimates
time estimates
Figure 17.5
17-23
Example 1 Solution
Example 1 Solution
P a t h L e n g th
( w e e k s )
S la c k
1 - 2 - 3 - 4 - 5 - 6
1 - 2 - 5 - 6
1 - 3 - 5 - 6
1 8
2 0
1 4
2
0
6
Critical Path
17-24
 Network activities
 ES: early start
 EF: early finish
 LS: late start
 LF: late finish
 Used to determine
 Expected project duration
 Slack time
 Critical path
Computing Algorithm
Computing Algorithm
17-25
Probabilistic Time Estimates
Probabilistic Time Estimates
 Optimistic time
 Time required under optimal conditions
 Pessimistic time
 Time required under worst conditions
 Most likely time
 Most probable length of time that will be
required
17-26
Probabilistic Estimates
Probabilistic Estimates
Activity
start
Optimistic
time
Most likely
time (mode)
Pessimistic
time
to tp
tm te
Figure 17.8
Beta Distribution
17-27
Expected Time
Expected Time
te = to + 4tm +tp
6
te = expected time
to = optimistic time
tm = most likely time
tp = pessimistic time
17-28
Variance
Variance

 (tp – to)2
36

= variance
to = optimistic time
tp = pessimistic time
17-29
Example 5
Example 5
1-3-4
a
3-4-5
d
3-5-7
e
5-7-9
f
2-4-6
b
4-6-8
h
2
-
3
-
6
g
3-4-6
i
2
-
3
-
5
c
Optimistic
time
Most likely
time
Pessimistic
time
17-30
Example 5 Time Estimates
Example 5 Time Estimates
2.83
a
4.00
d
5.0
e
7.0
f
4.00
b
6.0
h
3
.
3
3
g
4.17
i
3
.
1
7
c
Tabc = 10.0
Tdef = 16.0
Tghi = 13.50
17-31
Path Probabilities
Path Probabilities
Z =
Specified time – Path mean
Path standard deviation
Z indicates how many standard deviations
of the path distribution the specified tine
is beyond the expected path duration.
17-32
17
Weeks
Weeks
Weeks
Weeks
10.0
16.0
13.5
1.00
1.00
a-b-c
d-e-f
g-h-i
Example 6
Example 6
17-33
Time-cost Trade-offs: Crashing
Time-cost Trade-offs: Crashing
 Crash – shortening activity duration
 Procedure for crashing
 Crash the project one period at a time
 Only an activity on the critical path
 Crash the least expensive activity
 Multiple critical paths: find the sum of
crashing the least expensive activity on
each critical path
17-34
Time-Cost Trade-Offs: Crashing
Time-Cost Trade-Offs: Crashing
Total
cost
Shorten
Shorten
Cumulative
cost of
crashing
Expected indirect costs
Optimum
CRASH
Figure 17.11
17-35
6
a
4
d
5
c
10
b
9
e
2
f
Example 7
Example 7
17-36
Advantages of PERT
Advantages of PERT
 Forces managers to organize
 Provides graphic display of activities
 Identifies
 Critical activities
 Slack activities 1
2
3
4
5 6
17-37
Limitations of PERT
Limitations of PERT
 Important activities may be omitted
 Precedence relationships may not be
correct
 Estimates may include
a fudge factor
 May focus solely
on critical path
1
2
3
4
5 6
142 weeks
17-38
Goldratt’s Critical Chain
Goldratt’s Critical Chain
 Goldratt’s insight on project management
 Time estimates are often pessimistic
 Activities finished ahead of schedule often go
unreported
 With multiple projects, resources needed for one
project may be in use on another
17-39
 Computer aided design (CAD)
 Groupware (Lotus Notes)
 CA Super Project
 Harvard Total Manager
 MS Project
 Sure Track Project Manager
 Time Line
Project Management Software
Project Management Software
17-40
 Imposes a methodology
 Provides logical planning structure
 Enhances team communication
 Flag constraint violations
 Automatic report formats
 Multiple levels of reports
 Enables what-if scenarios
 Generates various chart types
Advantages of PM Software
Advantages of PM Software
17-41
 Risk: occurrence of events that have
undesirable consequences
 Delays
 Increased costs
 Inability to meet specifications
 Project termination
Project Risk Management
Project Risk Management
17-42
 Identify potential risks
 Analyze and assess risks
 Work to minimize occurrence of risk
 Establish contingency plans
Risk Management
Risk Management
17-43
Summary
Summary
 Projects are a unique set of activities
 Projects go through life cycles
 PERT and CPM are two common
techniques
 Network diagrams
 Project management software available
17-44
Video: Work Breakdown
Video: Work Breakdown
17-45
Video: Project Materials/Delays
Video: Project Materials/Delays
17-46
Video: Project Scheduling
Video: Project Scheduling
17-47
Video: PERT/CPM
Video: PERT/CPM

More Related Content

PPTX
chapter17.pptx
PPT
1604805469-ch-17.ppt
PPT
Project-Management.ppt
PPT
Project management
PPT
C10 project management
PPT
C10 project management
PPT
CPM-PERT.ppt
PPT
MGT-Ch07.ppt
chapter17.pptx
1604805469-ch-17.ppt
Project-Management.ppt
Project management
C10 project management
C10 project management
CPM-PERT.ppt
MGT-Ch07.ppt

Similar to chapter17hellllhjmhjmhnbjjtyhghdfghth.ppt (20)

PPTX
Project management
PDF
project managment lesson mechanical engineering
PPT
EO notes Lecture 27 Project Management 2.ppt
PPTX
Chapter 17.pptx of operations management
PPTX
PROJECT-ANALYSIS-TOOL-PPT.pptx
PPTX
Pb602 operation management chapter 7
PDF
Cpm n pert
PPTX
Stevenson 13e chapter_17
PDF
Critical path presentation for timely project completion
PPT
Introduction to Project Management
PPT
Chap003
PPT
scheduling in project managment - introducton
PPT
Project Management
PPTX
PPT
Project management
PPTX
Project Management Fundamental
PPTX
Slides 2015 for contact 1
PPT
chapter 6.ppt
PPTX
Pert cpm-120421125920-phpapp02
PPTX
PROJECT-SCHEDULING-pptx.pptx
Project management
project managment lesson mechanical engineering
EO notes Lecture 27 Project Management 2.ppt
Chapter 17.pptx of operations management
PROJECT-ANALYSIS-TOOL-PPT.pptx
Pb602 operation management chapter 7
Cpm n pert
Stevenson 13e chapter_17
Critical path presentation for timely project completion
Introduction to Project Management
Chap003
scheduling in project managment - introducton
Project Management
Project management
Project Management Fundamental
Slides 2015 for contact 1
chapter 6.ppt
Pert cpm-120421125920-phpapp02
PROJECT-SCHEDULING-pptx.pptx
Ad

Recently uploaded (20)

PPTX
Integrated Management of Neonatal and Childhood Illnesses (IMNCI) – Unit IV |...
PDF
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
PPTX
BSCE 2 NIGHT (CHAPTER 2) just cases.pptx
PDF
Chevening Scholarship Application and Interview Preparation Guide
PPTX
PLASMA AND ITS CONSTITUENTS 123.pptx
PDF
African Communication Research: A review
PDF
PUBH1000 - Module 6: Global Health Tute Slides
PDF
Disorder of Endocrine system (1).pdfyyhyyyy
PDF
anganwadi services for the b.sc nursing and GNM
PDF
Nurlina - Urban Planner Portfolio (english ver)
PPTX
pharmaceutics-1unit-1-221214121936-550b56aa.pptx
PPTX
Diploma pharmaceutics notes..helps diploma students
PDF
Journal of Dental Science - UDMY (2022).pdf
PDF
fundamentals-of-heat-and-mass-transfer-6th-edition_incropera.pdf
PPTX
Climate Change and Its Global Impact.pptx
PDF
Horaris_Grups_25-26_Definitiu_15_07_25.pdf
PDF
Skin Care and Cosmetic Ingredients Dictionary ( PDFDrive ).pdf
PDF
Health aspects of bilberry: A review on its general benefits
PDF
Lecture on Viruses: Structure, Classification, Replication, Effects on Cells,...
PDF
Hospital Case Study .architecture design
Integrated Management of Neonatal and Childhood Illnesses (IMNCI) – Unit IV |...
LIFE & LIVING TRILOGY - PART - (2) THE PURPOSE OF LIFE.pdf
BSCE 2 NIGHT (CHAPTER 2) just cases.pptx
Chevening Scholarship Application and Interview Preparation Guide
PLASMA AND ITS CONSTITUENTS 123.pptx
African Communication Research: A review
PUBH1000 - Module 6: Global Health Tute Slides
Disorder of Endocrine system (1).pdfyyhyyyy
anganwadi services for the b.sc nursing and GNM
Nurlina - Urban Planner Portfolio (english ver)
pharmaceutics-1unit-1-221214121936-550b56aa.pptx
Diploma pharmaceutics notes..helps diploma students
Journal of Dental Science - UDMY (2022).pdf
fundamentals-of-heat-and-mass-transfer-6th-edition_incropera.pdf
Climate Change and Its Global Impact.pptx
Horaris_Grups_25-26_Definitiu_15_07_25.pdf
Skin Care and Cosmetic Ingredients Dictionary ( PDFDrive ).pdf
Health aspects of bilberry: A review on its general benefits
Lecture on Viruses: Structure, Classification, Replication, Effects on Cells,...
Hospital Case Study .architecture design
Ad

chapter17hellllhjmhjmhnbjjtyhghdfghth.ppt

  • 1. McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 17 17 Project Management
  • 2. 17-2 Learning Objectives Learning Objectives  Discuss the behavioral aspects of projects in terms of project personnel and the project manager.  Discuss the nature and importance of a work breakdown structure in project management.  Give a general description of PERT/CPM techniques.  Construct simple network diagrams.
  • 3. 17-3 Learning Objectives Learning Objectives  List the kinds of information that a PERT or CPM analysis can provide.  Analyze networks with deterministic times.  Analyze networks with probabilistic times.  Describe activity “crashing” and solve typical problems.
  • 4. 17-4 Unique, one-time operations designed to Unique, one-time operations designed to accomplish a specific set of objectives in a limited accomplish a specific set of objectives in a limited time frame. time frame. Build A A Done Build B B Done Build C C Done Build D Ship JAN FEB MAR APR MAY JUN On time! Projects Projects
  • 5. 17-5 Project Management Project Management  How is it different?  Limited time frame  Narrow focus, specific objectives  Less bureaucratic  Why is it used?  Special needs  Pressures for new or improves products or services
  • 6. 17-6 Project Management Project Management  What are the Key Metrics  Time  Cost  Performance objectives  What are the Key Success Factors?  Top-down commitment  Having a capable project manager  Having time to plan  Careful tracking and control  Good communications
  • 7. 17-7 Project Management Project Management  What are the Major Administrative Issues?  Executive responsibilities  Project selection  Project manager selection  Organizational structure  Organizational alternatives  Manage within functional unit  Assign a coordinator  Use a matrix organization with a project leader
  • 8. 17-8 Project Management Project Management  What are the tools?  Work breakdown structure  Network diagram  Gantt charts  Risk management
  • 9. 17-9 Planning and Scheduling Planning and Scheduling MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Locate new facilities Interview staff Hire and train staff Select and order furniture Remodel and install phones Move in/startup Gantt Chart
  • 10. 17-10  Deciding which projects to implement  Selecting a project manager  Selecting a project team  Planning and designing the project  Managing and controlling project resources  Deciding if and when a project should be terminated Key Decisions Key Decisions
  • 11. 17-11 Project Manager Project Manager Responsible for: Work Quality Human Resources Time Communications Costs
  • 12. 17-12  Temptation to understate costs  Withhold information  Misleading status reports  Falsifying records  Comprising workers’ safety  Approving substandard work Ethical Issues Ethical Issues
  • 13. 17-13 Project Life Cycle Project Life Cycle Concept Feasibility Planning Execution Termination Management
  • 14. 17-14 Work Breakdown Structure Work Breakdown Structure Project X Level 1 Level 2 Level 3 Level 4 Figure 17.2
  • 15. 17-15 PERT and CPM PERT and CPM PERT: Program Evaluation and Review Technique CPM: Critical Path Method  Graphically displays project activities  Estimates how long the project will take  Indicates most critical activities  Show where delays will not affect project
  • 16. 17-16 The Network Diagram The Network Diagram  Network (precedence) diagram – diagram of project activities that shows sequential relationships by the use of arrows and nodes.  Activity-on-arrow (AOA) – a network diagram convention in which arrows designate activities.  Activity-on-node (AON) – a network diagram convention in which nodes designate activities.  Activities – steps in the project that consume resources and/or time.  Events – the starting and finishing of activities, designated by nodes in the AOA convention.
  • 17. 17-17 The Network Diagram (cont’d) The Network Diagram (cont’d)  Path  Sequence of activities that leads from the starting node to the finishing node  Critical path  The longest path; determines expected project duration  Critical activities  Activities on the critical path  Slack  Allowable slippage for path; the difference the length of path and the length of critical path
  • 18. 17-18 Project Network – Activity on Project Network – Activity on Arrow Arrow 1 2 3 4 5 6 Locate facilities Order furniture Furniture setup Interview Hire and train Remodel Move in Figure 17.4 AOA
  • 19. 17-19 Project Network – Activity on Project Network – Activity on Node Node 1 2 3 5 6 Locate facilities Order furniture Furniture setup Interview Remodel Move in 4 Hire and train 7 S Figure 17.4 AON
  • 20. 17-20 Network Conventions Network Conventions a b c a b c a b c d a b c Dummy activity
  • 21. 17-21 Time Estimates Time Estimates  Deterministic  Time estimates that are fairly certain  Probabilistic  Estimates of times that allow for variation
  • 22. 17-22 Example 1 Example 1 1 2 3 4 5 6 8 weeks 6 weeks 3 weeks 4 weeks 9 weeks 11 weeks 1 week Locate facilities Order furniture F u r n i t u r e s e t u p Interview Hire and train Remodel Move in Deterministic Deterministic time estimates time estimates Figure 17.5
  • 23. 17-23 Example 1 Solution Example 1 Solution P a t h L e n g th ( w e e k s ) S la c k 1 - 2 - 3 - 4 - 5 - 6 1 - 2 - 5 - 6 1 - 3 - 5 - 6 1 8 2 0 1 4 2 0 6 Critical Path
  • 24. 17-24  Network activities  ES: early start  EF: early finish  LS: late start  LF: late finish  Used to determine  Expected project duration  Slack time  Critical path Computing Algorithm Computing Algorithm
  • 25. 17-25 Probabilistic Time Estimates Probabilistic Time Estimates  Optimistic time  Time required under optimal conditions  Pessimistic time  Time required under worst conditions  Most likely time  Most probable length of time that will be required
  • 26. 17-26 Probabilistic Estimates Probabilistic Estimates Activity start Optimistic time Most likely time (mode) Pessimistic time to tp tm te Figure 17.8 Beta Distribution
  • 27. 17-27 Expected Time Expected Time te = to + 4tm +tp 6 te = expected time to = optimistic time tm = most likely time tp = pessimistic time
  • 28. 17-28 Variance Variance   (tp – to)2 36  = variance to = optimistic time tp = pessimistic time
  • 30. 17-30 Example 5 Time Estimates Example 5 Time Estimates 2.83 a 4.00 d 5.0 e 7.0 f 4.00 b 6.0 h 3 . 3 3 g 4.17 i 3 . 1 7 c Tabc = 10.0 Tdef = 16.0 Tghi = 13.50
  • 31. 17-31 Path Probabilities Path Probabilities Z = Specified time – Path mean Path standard deviation Z indicates how many standard deviations of the path distribution the specified tine is beyond the expected path duration.
  • 33. 17-33 Time-cost Trade-offs: Crashing Time-cost Trade-offs: Crashing  Crash – shortening activity duration  Procedure for crashing  Crash the project one period at a time  Only an activity on the critical path  Crash the least expensive activity  Multiple critical paths: find the sum of crashing the least expensive activity on each critical path
  • 34. 17-34 Time-Cost Trade-Offs: Crashing Time-Cost Trade-Offs: Crashing Total cost Shorten Shorten Cumulative cost of crashing Expected indirect costs Optimum CRASH Figure 17.11
  • 36. 17-36 Advantages of PERT Advantages of PERT  Forces managers to organize  Provides graphic display of activities  Identifies  Critical activities  Slack activities 1 2 3 4 5 6
  • 37. 17-37 Limitations of PERT Limitations of PERT  Important activities may be omitted  Precedence relationships may not be correct  Estimates may include a fudge factor  May focus solely on critical path 1 2 3 4 5 6 142 weeks
  • 38. 17-38 Goldratt’s Critical Chain Goldratt’s Critical Chain  Goldratt’s insight on project management  Time estimates are often pessimistic  Activities finished ahead of schedule often go unreported  With multiple projects, resources needed for one project may be in use on another
  • 39. 17-39  Computer aided design (CAD)  Groupware (Lotus Notes)  CA Super Project  Harvard Total Manager  MS Project  Sure Track Project Manager  Time Line Project Management Software Project Management Software
  • 40. 17-40  Imposes a methodology  Provides logical planning structure  Enhances team communication  Flag constraint violations  Automatic report formats  Multiple levels of reports  Enables what-if scenarios  Generates various chart types Advantages of PM Software Advantages of PM Software
  • 41. 17-41  Risk: occurrence of events that have undesirable consequences  Delays  Increased costs  Inability to meet specifications  Project termination Project Risk Management Project Risk Management
  • 42. 17-42  Identify potential risks  Analyze and assess risks  Work to minimize occurrence of risk  Establish contingency plans Risk Management Risk Management
  • 43. 17-43 Summary Summary  Projects are a unique set of activities  Projects go through life cycles  PERT and CPM are two common techniques  Network diagrams  Project management software available