SlideShare a Scribd company logo
Determining Activities' Duration in the
Construction Schedule
Muhammad Zubair
B.E., MS (UK), PMP
An Activity, Lag, or Event?
An activity:
 Duration > 0, uses resource and has a budget
A lag:
 Duration > 0, does not use resource, does not have budget
An event (or milestone):
 Duration = 0, does not use resource , does not have budget
 An event likely has a responsibility, i.e. someone responsible
Activities Duration Slide No. 2
Who Determines Durations?
It is strongly recommended for the scheduler not to
assign durations without consulting with the teams
(crews / subcontractors) leaders.
In the end, the project manager must take a careful
look at the schedule and approve it; perhaps with
some adjustments.
 This implies the approval of all team leaders and subs.
Activities Duration Slide No. 3
How are Durations Determined?
Several methods are used to determine durations,
ranging from objective / calculated to subjective /
guesstimated:
A. Calculations based on average past performance or expected
production for a worker or a crew.
B. Calculations based on given equipment production rate.
C. Estimation based on expert opinion.
D. Estimation based on comparing to numbers in a reference.
 With assumptions in all cases.
Activities Duration Slide No. 4
Source of Production Rates
1. Contractor’s own past records
 How close is the item considered to the one compared to?
2. Ask crew leaders / subcontractors
3. Commercial databases such as RS Means or Spon's
price book
4. Internet
 How reliable?
Activities Duration Slide No. 5
How are Durations Determined?
Most importantly: Have all factors impacting the
production been considered?
A. In the “database”, and
B. The considered project and activity?
Activities Duration Slide No. 6
Productivity Numbers
When keeping a production rate in the database (or
importing it), some factors have to be considered:
1. Labor skill level.
2. Amount of resources allocated
3. Weather conditions
4. Design complexity
5. Learning curves
6. Fatigue
7. Multi-shift turnover
8. Soil condition (for excavation)
9. Height (for masonry, painting,
etc.)
10. QA/QC and safety requirements
11. Work minutes / hour
12. Jobsite logistics and congestion
13. Any unexpected evets?
14. Does it represent “average
production” to you?
Activities Duration Slide No. 7
Productivity Numbers
Now you have a “base” number as a reference, you
need to make proper adjustments based on the
current job situation.
 You can start with the same previous factors.
 For cost estimating purpose, there are other factors too.
Activities Duration Slide No. 8
Adjusting Numbers
Factors that have to do
with:
 The design of the project
 The climate / weather:
 Temperature, humidity,
wind, precipitation,
visibility, lightning,
 Location / terrain /
elevation
 Jobsite congestion and
condition
 Workforce type and skill
level
 Crew composition
 Type and condition of
equipment and tools
used
 Availability and readiness
of materials
 Management style
 Safety regulations
Activities Duration Slide No. 9
Importance of Durations Accuracy
1. Knowing how long the crews are needed
2. Calculating the cost of the activity
3. Determining the dates for dependent / succeeding
activities
4. Calculating the expected finish date for the project
• So in general, the accuracy of activities’ duration
impacts both the time and cost aspects of the project.
Activities Duration Slide No. 10
Inaccurate Durations
Impact of inaccurate durations
 Delayed crews
 Subcontractors conflicts
 Wasted money
 Shortage of materials / crews (if actual date is earlier)
 Possible problems with cash flow
 Disrupted plans and chaos
 Impact on succeeding activities as well as the entire project
Activities Duration Slide No. 11
Items in the RS Means Database
Activities Duration Slide No. 12
Items in the RS Means Database
Labor hours per CY =
𝐿𝑎𝑏𝑜𝑟 ℎ𝑜𝑢𝑟𝑠 𝑝𝑒𝑟 𝑑𝑎𝑦
𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦
=
12
800
= 0.015
Activities Duration Slide No. 13
4,200 SF Elevated slab, 4 use, 18’ high
Duration = 4200 / 495 = 8.5 ≈ 9 days
Labor hours = 4200 x 0.097 = 407.4, or
= 6 x 8 x 8.5 = 408
=
6 ∗ 8
495
# of
workers
Hours/
day
Activities Duration Slide No. 14
Multi-Stage Activities
Those activities performed by the same crew but with
different nature or location
 Wood framing
 Flooring
Those activities performed by different crews but
result in completion of same finished product
 Reinforced concrete items
Keep it as one activity or split it?
Use the KISS principle!
Activities Duration Slide No. 15
Pictures from
https://pixabay.com/
Activities Duration Slide No. 16
Concrete Work
Picture from https://pixabay.com/
Activities Duration Slide No. 17
Simplify…
In general, it is better to break the activity whenever
its portions are separated physically or by time.
 This simplifies all calculations: productivity, time, and money
 This also reduces the use of Start-to-Start (SS) and Finish-to-
Finish (FF) relationships and lags, which simplifies even more.
Activities Duration Slide No. 18
Intermittent Activities
Electrical work: one activity, 23 days
Electrical work: two activities, 4, and 3 days
Electrical work
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Days
Rough-in Finish
Electrical Rough-in
Electrical Finish
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Days
Activities Duration Slide No. 19
Discontinuous Activities
It will be better to separate intermittent activities
when segments are separated by time periods
This is better for control and many other scheduling
functions
If not separated, it may skew the percent complete
and other dependent functions
Activities Duration Slide No. 20
Discontinuous Activities
Obtain Permit (90 days)
Apply for
permit,
1 day Permit
issued
Lag, 89 days
Or
Activities Duration Slide No. 21
Logic and Duration
A
B
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Days
Clear and Grub
Excavation
A
B
1 2 3 4 5 6 7 8 9 10 11 Days
Clear and Grub
Excavation
3
FS
relationship:
17 days
SS
relationship
with lag:
11 days
A1
A2
B
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
C & G -1
C & G -2
Excavation
FS relationship
with splitting:
11 days
Activities Duration Slide No. 22
Unplanned Stoppage
Excavation was planned for 7 continuous days (Case
A)
But a technical problem forced a 6-day pause (Case B)
 Importance of activity notes
Excavation
1 2 3 4 5 6 7
Excavation
1 2 3 4 5 6 7 8 9 10 11 12 13
Dewatering
A
B
Activities Duration Slide No. 23
Multiple Crews
Multiple crews (2+)
Issues to be considered:
 Coordination
 Available space for work and safety
 Available equipment and maintenance
 Supervision, administration
Crew #1
Crew #2
Activities Duration Slide No. 24
Multiple Shifts
Multiple shifts (2+)
Issues to be considered:
 Coordination, turn-over
 Supervision, administration
 Night lighting, security, facilities, and services
 Same equipment? Maintenance
 Productivity may not be the same (different weather
conditions, visibility)
 2nd (and 3rd) shift pay: Overtime?
Crew #1
Crew #2
Activities Duration Slide No. 25
Multiple Crews and Shifts
Multiple crews and shifts (2+)
Issues to be considered:
 Coordination, turn-over
 Available space for work and safety
 Available equipment and maintenance
 Supervision, administration
 Night lighting, security, facilities, and services
 Productivity may not be the same for different shifts
 2nd (and 3rd) shift pay: Overtime?
Crew #1A
Crew #2A
Crew #1B
Crew #2B
Activities Duration Slide No. 26
Duration Adjustment
For the excavation crew that has a recorded
production rate of 800 CY / day, assume that adverse
conditions results in 20% productivity reduction.
Calculate adjusted:
1. Daily production
2. Labor hours / unit
3. Unit cost
Activities Duration Slide No. 27
Duration Adjustment
Adjusted daily production:
 800 CY/day * (100% - 20%) = 640 CY / day
Adjusted labor hours per unit:
 0.015 / (100% - 20%) = 0.01875 ≈ 0.019
 Or,
𝐿𝑎𝑏𝑜𝑟 ℎ𝑜𝑢𝑟𝑠 𝑝𝑒𝑟 𝑑𝑎𝑦
𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦
=
12
640
= 0.01875 ≈ 0.019
Note that as one parameter increases, the other one
decreases, and vice versa
Activities Duration Slide No. 28
Let’s Not Forget…
The accurate estimation of crew production is important
to both estimating and scheduling
Unit Price =
𝐶𝑟𝑒𝑤 𝐶𝑜𝑠𝑡 𝑝𝑒𝑟 𝑑𝑎𝑦
𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦
Duration =
𝑇𝑜𝑡𝑎𝑙 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦
𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦
Unit price and duration are inversely proportional to
production rate
Constant
Constant
Activities Duration Slide No. 29
Activities with Variable (Non-
Linear) Production
There are several ways to deal with activities with
non-linear production:
1. If the productivity variation (non-linearity) is small, you can
ignore it. For example, installing concrete blocks for a 5’ or 6’
wall.
2. Split the activity to homogeneous activities (each with
assumed linearity)
3. Use the software tools to divide the activity into steps and
distribute the resources per step
Activities Duration Slide No. 30
Duration Risk Management
How do you account for risk in the project?
 At the activity level, i.e. part of the duration?
 At the entire project level, i.e. independent of activities’
duration? or
 Both?
Activities Duration Slide No. 31
Duration Uncertainty
Excavation
10 days
Most Likely
Duration
Optimistic
Duration
8
Pessimistic
Duration
18
Xo
XP
Expected
Duration
11
Duration Risk
Allowance
Activities Duration Slide No. 32
Time Contingency
It is not recommended to add extra time to activity
duration due to risk calculations, but the risk impact is
estimated for the entire path, and added within the
project but outside the activities.
 If added within the activity, it will be used no matter what.
 It will become the “norm” for next time.
 So keep the activities durations lean!
 Activity duration may still have little “fluff” due to rounding.
Activities Duration Slide No. 33
What If?
What if the start of the project was postponed for a
month or more?
Slide No. 34
Activities Duration
Duration While Updating
When updating the schedule, officially or unofficially,
certain activities will be off the track; ahead or behind.
 If the schedule variance is small, it can be dismissed as
normal and expected variation.
 If the schedule variance is major, you need to analyze and
pinpoint the cause:
A. Something went wrong with this activity,
B. Certain factors were not considered when estimating the
duration, or
C. The number in the database was inaccurate
Slide No. 35
Activities Duration
Duration While Updating
Example: An excavation activity, 11,500 CY, using a
crew with an estimated production of 700 CY/day.
 Estimated duration = 11,500 / 700 = 16.43 ≈ 17 days
 Five days later, 2,420 CY only were excavated:
 Baseline % complete = 30.4%, Actual % complete = 21.0%
 If everything was normal, i.e. no unexpected problems, then
remaining duration must be corrected based on actual
production, 484 CY/day:
 RD = 24 – 5 = 19 days, and NOT 17 – 5 = 12 days
Slide No. 36
Activities Duration
Keep in Touch…
Any comments?
Any questions?
mail@edgescom.in
Activities Duration Slide No. 37

More Related Content

PPTX
MARKS IN YOUR POCKET PMP for PMP Preparation
ssusera09841
 
PPT
Resource-Allocation.ppt
TecnicoItca
 
PPT
Project planning-and-control
Jatindra Malik
 
PPTX
2.06 time management 1
reddvise
 
PPTX
PROJECT-ANALYSIS-TOOL-PPT.pptx
PHOEBEANNEARTECHE1
 
PPTX
Final Review
Amit Binglesh
 
PPT
Case Dragonfly
mukul joshi
 
PPT
Session 5 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
MARKS IN YOUR POCKET PMP for PMP Preparation
ssusera09841
 
Resource-Allocation.ppt
TecnicoItca
 
Project planning-and-control
Jatindra Malik
 
2.06 time management 1
reddvise
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PHOEBEANNEARTECHE1
 
Final Review
Amit Binglesh
 
Case Dragonfly
mukul joshi
 
Session 5 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 

Similar to Estimating-Durations-Activities-EDGE.pdf (20)

PDF
Awe k2 midterms
Karen Tay
 
PPT
Intro to PM.ppt
Chandrabhan Seniya
 
PPTX
Materi 08 ( Project Management for Manufacturing ).pptx
BudyAriyanto1
 
PDF
Awe k2 midterms finals
Karen Tay
 
PPT
PERT CPM solution project Management 508
asadulislam6021
 
PPT
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
PPTX
Lecture 5 Project Scheduling-PERT.pptx
drnafeesa5
 
DOCX
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
PDF
pert and crm examples full class course.pdf
samblazeobaseemo
 
PPTX
DOC-20230811-WA0054..pptx busnises plangood
ssuser4f8f65
 
PPT
15 Deliv template
Leanleaders.org
 
PPTX
Pert Analysis
Kaizer Dave
 
PPT
Project-Planning
Ron Drew
 
PPTX
1 Element Of a Netwok Construction .pptx
ayushbansal098123
 
PPTX
Chapter 3.pptx
BetshaTizazu2
 
PPTX
Lecture 4 - Engineering project Scheduling.pptx
muhammadbilalzahid4
 
PPT
4-ProjectPlanning.ppt
DuraisamySubramaniam1
 
PDF
unit plan for project building in s/w.pdf
VivekGarg886735
 
PPTX
Project scheduling and planning ppt for study
VibhaV39
 
PPTX
Howe Street Basic Project Approach
JasonLhota1
 
Awe k2 midterms
Karen Tay
 
Intro to PM.ppt
Chandrabhan Seniya
 
Materi 08 ( Project Management for Manufacturing ).pptx
BudyAriyanto1
 
Awe k2 midterms finals
Karen Tay
 
PERT CPM solution project Management 508
asadulislam6021
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Lecture 5 Project Scheduling-PERT.pptx
drnafeesa5
 
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
pert and crm examples full class course.pdf
samblazeobaseemo
 
DOC-20230811-WA0054..pptx busnises plangood
ssuser4f8f65
 
15 Deliv template
Leanleaders.org
 
Pert Analysis
Kaizer Dave
 
Project-Planning
Ron Drew
 
1 Element Of a Netwok Construction .pptx
ayushbansal098123
 
Chapter 3.pptx
BetshaTizazu2
 
Lecture 4 - Engineering project Scheduling.pptx
muhammadbilalzahid4
 
4-ProjectPlanning.ppt
DuraisamySubramaniam1
 
unit plan for project building in s/w.pdf
VivekGarg886735
 
Project scheduling and planning ppt for study
VibhaV39
 
Howe Street Basic Project Approach
JasonLhota1
 
Ad

Recently uploaded (20)

PPTX
Integrating Hydrogen as Fuel in the Circular Economy.pptx
Dr. Fayaz Ahmad Malla
 
PPTX
Oil & Gas Laboratory Services Saudi Arabia.pptx
ETLCO
 
DOCX
Privatizing the Planet A Philosophical Critique of Capitalism’s Impact on Hum...
Lynn Taylor
 
PPTX
Membrane concentration in Dairy industry: ultrafiltration and reverse osmosis...
RupaliKoundal1
 
PPTX
PM Surya Ghar Solar Revolution............
Dr. Fayaz Ahmad Malla
 
DOCX
Emergency Fuel Oil Storage Welded Steel Tanks for Critical Needs.docx
AllenLin596164
 
PDF
indonesia-sustainable-transformation.pdf
YudiSaputra43
 
PPTX
Session 9: Panel 3 - Sports for Climate Change
ipcc-media
 
PPTX
Environmental Management & Sustainable Development.pptx
PoojaShetty805509
 
DOCX
Hydraulic Oil Waste Management Welded Steel Tank Solutions.docx
AllenLin596164
 
PPTX
Forests The Lungs of Our Planet Forests
rt8932484
 
PDF
DOC-20250402-fhfmjfjffgfgfjfjWA0041..pdf
tauseefalaman11
 
PPTX
Green Hydrogen Mission India’s Shift Towards Clean Energy.pptx
Dr. Fayaz Ahmad Malla
 
PDF
Wicked Cool Mystic Newsletter_MyRWA2025.pdf
dariaclark1
 
PPTX
Angle Pair.pptx Angle Pair.pptx Angle Pair.pptx Angle Pair.pptx Angle Pair.pp...
YuseiFudo10
 
PPTX
Session 7 - Working Group II - Impacts, Adaptation and Vulnerability
ipcc-media
 
PDF
Rose_ Floriculture_ cultivation and its managment.pdf
bisensharad
 
PDF
Point of view from fans of Evan Roderick.pdf
Evan Roderick
 
PPTX
"Nature & Life: A Vital Connection"
yatrisheldiya1503
 
PDF
Fruit Ripening _Second Year + Third Year PDF.pdf
bisensharad
 
Integrating Hydrogen as Fuel in the Circular Economy.pptx
Dr. Fayaz Ahmad Malla
 
Oil & Gas Laboratory Services Saudi Arabia.pptx
ETLCO
 
Privatizing the Planet A Philosophical Critique of Capitalism’s Impact on Hum...
Lynn Taylor
 
Membrane concentration in Dairy industry: ultrafiltration and reverse osmosis...
RupaliKoundal1
 
PM Surya Ghar Solar Revolution............
Dr. Fayaz Ahmad Malla
 
Emergency Fuel Oil Storage Welded Steel Tanks for Critical Needs.docx
AllenLin596164
 
indonesia-sustainable-transformation.pdf
YudiSaputra43
 
Session 9: Panel 3 - Sports for Climate Change
ipcc-media
 
Environmental Management & Sustainable Development.pptx
PoojaShetty805509
 
Hydraulic Oil Waste Management Welded Steel Tank Solutions.docx
AllenLin596164
 
Forests The Lungs of Our Planet Forests
rt8932484
 
DOC-20250402-fhfmjfjffgfgfjfjWA0041..pdf
tauseefalaman11
 
Green Hydrogen Mission India’s Shift Towards Clean Energy.pptx
Dr. Fayaz Ahmad Malla
 
Wicked Cool Mystic Newsletter_MyRWA2025.pdf
dariaclark1
 
Angle Pair.pptx Angle Pair.pptx Angle Pair.pptx Angle Pair.pptx Angle Pair.pp...
YuseiFudo10
 
Session 7 - Working Group II - Impacts, Adaptation and Vulnerability
ipcc-media
 
Rose_ Floriculture_ cultivation and its managment.pdf
bisensharad
 
Point of view from fans of Evan Roderick.pdf
Evan Roderick
 
"Nature & Life: A Vital Connection"
yatrisheldiya1503
 
Fruit Ripening _Second Year + Third Year PDF.pdf
bisensharad
 
Ad

Estimating-Durations-Activities-EDGE.pdf

  • 1. Determining Activities' Duration in the Construction Schedule Muhammad Zubair B.E., MS (UK), PMP
  • 2. An Activity, Lag, or Event? An activity:  Duration > 0, uses resource and has a budget A lag:  Duration > 0, does not use resource, does not have budget An event (or milestone):  Duration = 0, does not use resource , does not have budget  An event likely has a responsibility, i.e. someone responsible Activities Duration Slide No. 2
  • 3. Who Determines Durations? It is strongly recommended for the scheduler not to assign durations without consulting with the teams (crews / subcontractors) leaders. In the end, the project manager must take a careful look at the schedule and approve it; perhaps with some adjustments.  This implies the approval of all team leaders and subs. Activities Duration Slide No. 3
  • 4. How are Durations Determined? Several methods are used to determine durations, ranging from objective / calculated to subjective / guesstimated: A. Calculations based on average past performance or expected production for a worker or a crew. B. Calculations based on given equipment production rate. C. Estimation based on expert opinion. D. Estimation based on comparing to numbers in a reference.  With assumptions in all cases. Activities Duration Slide No. 4
  • 5. Source of Production Rates 1. Contractor’s own past records  How close is the item considered to the one compared to? 2. Ask crew leaders / subcontractors 3. Commercial databases such as RS Means or Spon's price book 4. Internet  How reliable? Activities Duration Slide No. 5
  • 6. How are Durations Determined? Most importantly: Have all factors impacting the production been considered? A. In the “database”, and B. The considered project and activity? Activities Duration Slide No. 6
  • 7. Productivity Numbers When keeping a production rate in the database (or importing it), some factors have to be considered: 1. Labor skill level. 2. Amount of resources allocated 3. Weather conditions 4. Design complexity 5. Learning curves 6. Fatigue 7. Multi-shift turnover 8. Soil condition (for excavation) 9. Height (for masonry, painting, etc.) 10. QA/QC and safety requirements 11. Work minutes / hour 12. Jobsite logistics and congestion 13. Any unexpected evets? 14. Does it represent “average production” to you? Activities Duration Slide No. 7
  • 8. Productivity Numbers Now you have a “base” number as a reference, you need to make proper adjustments based on the current job situation.  You can start with the same previous factors.  For cost estimating purpose, there are other factors too. Activities Duration Slide No. 8
  • 9. Adjusting Numbers Factors that have to do with:  The design of the project  The climate / weather:  Temperature, humidity, wind, precipitation, visibility, lightning,  Location / terrain / elevation  Jobsite congestion and condition  Workforce type and skill level  Crew composition  Type and condition of equipment and tools used  Availability and readiness of materials  Management style  Safety regulations Activities Duration Slide No. 9
  • 10. Importance of Durations Accuracy 1. Knowing how long the crews are needed 2. Calculating the cost of the activity 3. Determining the dates for dependent / succeeding activities 4. Calculating the expected finish date for the project • So in general, the accuracy of activities’ duration impacts both the time and cost aspects of the project. Activities Duration Slide No. 10
  • 11. Inaccurate Durations Impact of inaccurate durations  Delayed crews  Subcontractors conflicts  Wasted money  Shortage of materials / crews (if actual date is earlier)  Possible problems with cash flow  Disrupted plans and chaos  Impact on succeeding activities as well as the entire project Activities Duration Slide No. 11
  • 12. Items in the RS Means Database Activities Duration Slide No. 12
  • 13. Items in the RS Means Database Labor hours per CY = 𝐿𝑎𝑏𝑜𝑟 ℎ𝑜𝑢𝑟𝑠 𝑝𝑒𝑟 𝑑𝑎𝑦 𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦 = 12 800 = 0.015 Activities Duration Slide No. 13
  • 14. 4,200 SF Elevated slab, 4 use, 18’ high Duration = 4200 / 495 = 8.5 ≈ 9 days Labor hours = 4200 x 0.097 = 407.4, or = 6 x 8 x 8.5 = 408 = 6 ∗ 8 495 # of workers Hours/ day Activities Duration Slide No. 14
  • 15. Multi-Stage Activities Those activities performed by the same crew but with different nature or location  Wood framing  Flooring Those activities performed by different crews but result in completion of same finished product  Reinforced concrete items Keep it as one activity or split it? Use the KISS principle! Activities Duration Slide No. 15
  • 17. Concrete Work Picture from https://pixabay.com/ Activities Duration Slide No. 17
  • 18. Simplify… In general, it is better to break the activity whenever its portions are separated physically or by time.  This simplifies all calculations: productivity, time, and money  This also reduces the use of Start-to-Start (SS) and Finish-to- Finish (FF) relationships and lags, which simplifies even more. Activities Duration Slide No. 18
  • 19. Intermittent Activities Electrical work: one activity, 23 days Electrical work: two activities, 4, and 3 days Electrical work 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Days Rough-in Finish Electrical Rough-in Electrical Finish 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Days Activities Duration Slide No. 19
  • 20. Discontinuous Activities It will be better to separate intermittent activities when segments are separated by time periods This is better for control and many other scheduling functions If not separated, it may skew the percent complete and other dependent functions Activities Duration Slide No. 20
  • 21. Discontinuous Activities Obtain Permit (90 days) Apply for permit, 1 day Permit issued Lag, 89 days Or Activities Duration Slide No. 21
  • 22. Logic and Duration A B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Days Clear and Grub Excavation A B 1 2 3 4 5 6 7 8 9 10 11 Days Clear and Grub Excavation 3 FS relationship: 17 days SS relationship with lag: 11 days A1 A2 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 C & G -1 C & G -2 Excavation FS relationship with splitting: 11 days Activities Duration Slide No. 22
  • 23. Unplanned Stoppage Excavation was planned for 7 continuous days (Case A) But a technical problem forced a 6-day pause (Case B)  Importance of activity notes Excavation 1 2 3 4 5 6 7 Excavation 1 2 3 4 5 6 7 8 9 10 11 12 13 Dewatering A B Activities Duration Slide No. 23
  • 24. Multiple Crews Multiple crews (2+) Issues to be considered:  Coordination  Available space for work and safety  Available equipment and maintenance  Supervision, administration Crew #1 Crew #2 Activities Duration Slide No. 24
  • 25. Multiple Shifts Multiple shifts (2+) Issues to be considered:  Coordination, turn-over  Supervision, administration  Night lighting, security, facilities, and services  Same equipment? Maintenance  Productivity may not be the same (different weather conditions, visibility)  2nd (and 3rd) shift pay: Overtime? Crew #1 Crew #2 Activities Duration Slide No. 25
  • 26. Multiple Crews and Shifts Multiple crews and shifts (2+) Issues to be considered:  Coordination, turn-over  Available space for work and safety  Available equipment and maintenance  Supervision, administration  Night lighting, security, facilities, and services  Productivity may not be the same for different shifts  2nd (and 3rd) shift pay: Overtime? Crew #1A Crew #2A Crew #1B Crew #2B Activities Duration Slide No. 26
  • 27. Duration Adjustment For the excavation crew that has a recorded production rate of 800 CY / day, assume that adverse conditions results in 20% productivity reduction. Calculate adjusted: 1. Daily production 2. Labor hours / unit 3. Unit cost Activities Duration Slide No. 27
  • 28. Duration Adjustment Adjusted daily production:  800 CY/day * (100% - 20%) = 640 CY / day Adjusted labor hours per unit:  0.015 / (100% - 20%) = 0.01875 ≈ 0.019  Or, 𝐿𝑎𝑏𝑜𝑟 ℎ𝑜𝑢𝑟𝑠 𝑝𝑒𝑟 𝑑𝑎𝑦 𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦 = 12 640 = 0.01875 ≈ 0.019 Note that as one parameter increases, the other one decreases, and vice versa Activities Duration Slide No. 28
  • 29. Let’s Not Forget… The accurate estimation of crew production is important to both estimating and scheduling Unit Price = 𝐶𝑟𝑒𝑤 𝐶𝑜𝑠𝑡 𝑝𝑒𝑟 𝑑𝑎𝑦 𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦 Duration = 𝑇𝑜𝑡𝑎𝑙 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝐶𝑟𝑒𝑤 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑒𝑟 𝑑𝑎𝑦 Unit price and duration are inversely proportional to production rate Constant Constant Activities Duration Slide No. 29
  • 30. Activities with Variable (Non- Linear) Production There are several ways to deal with activities with non-linear production: 1. If the productivity variation (non-linearity) is small, you can ignore it. For example, installing concrete blocks for a 5’ or 6’ wall. 2. Split the activity to homogeneous activities (each with assumed linearity) 3. Use the software tools to divide the activity into steps and distribute the resources per step Activities Duration Slide No. 30
  • 31. Duration Risk Management How do you account for risk in the project?  At the activity level, i.e. part of the duration?  At the entire project level, i.e. independent of activities’ duration? or  Both? Activities Duration Slide No. 31
  • 32. Duration Uncertainty Excavation 10 days Most Likely Duration Optimistic Duration 8 Pessimistic Duration 18 Xo XP Expected Duration 11 Duration Risk Allowance Activities Duration Slide No. 32
  • 33. Time Contingency It is not recommended to add extra time to activity duration due to risk calculations, but the risk impact is estimated for the entire path, and added within the project but outside the activities.  If added within the activity, it will be used no matter what.  It will become the “norm” for next time.  So keep the activities durations lean!  Activity duration may still have little “fluff” due to rounding. Activities Duration Slide No. 33
  • 34. What If? What if the start of the project was postponed for a month or more? Slide No. 34 Activities Duration
  • 35. Duration While Updating When updating the schedule, officially or unofficially, certain activities will be off the track; ahead or behind.  If the schedule variance is small, it can be dismissed as normal and expected variation.  If the schedule variance is major, you need to analyze and pinpoint the cause: A. Something went wrong with this activity, B. Certain factors were not considered when estimating the duration, or C. The number in the database was inaccurate Slide No. 35 Activities Duration
  • 36. Duration While Updating Example: An excavation activity, 11,500 CY, using a crew with an estimated production of 700 CY/day.  Estimated duration = 11,500 / 700 = 16.43 ≈ 17 days  Five days later, 2,420 CY only were excavated:  Baseline % complete = 30.4%, Actual % complete = 21.0%  If everything was normal, i.e. no unexpected problems, then remaining duration must be corrected based on actual production, 484 CY/day:  RD = 24 – 5 = 19 days, and NOT 17 – 5 = 12 days Slide No. 36 Activities Duration
  • 37. Keep in Touch… Any comments? Any questions? [email protected] Activities Duration Slide No. 37