CCP Certification Technical Paper
EXTENSION OF TIME CLAIMS IN OIL AND GAS
CONSTRUCTION PROJECTS
December 25th
, 2016
AACE Membership Number 289940
2 
TABLE OF CONTENTS
List of Figures ………………………………………………………………. 3
Abstract ……………………………………………………………………… 4
Introduction …………………………………………………………….……. 5
1.Event ………………………………………………………………….…… 5
1.1 General Conditions …………………………………………….…... 5
1.2 Particular Conditions ………………………………………….….… 7
2.Records …………………………………………………………….……... 10
3.Baseline Schedule ……………………………………………………….. 11
4.Liability ……………………………………………………………………. 14
5.Type of Claims …………………………………………………………… 16
6.Claim Preparation ………………………………………………………... 18
7.Response …………………………………………………………………. 19
8.Settlement ………………………………………………………………… 20
Conclusion …………………………………………………………………... 21
Bibliography………………………………………………………………….. 22
3 
List of Figures
Figure 1 “Critical Path Delay Analysis”.................................................. 13
Figure 2 “Time Impact Analysis“……………………………………….…. 15
4 
Abstract
This document is dedicated to projects especially in Oil and Gas field
wherein, in light of rapid and continuous development of the construction
process and under intense competition in order to acquire reasonable
profits, they are facing naturally lot of delays and disruptions which lead to
exert huge efforts for proving these delays.
As Extension of Time (EOT) claim involves countless of complex issues
and most often resulting with difference scenarios between projects parties,
establishing and presenting an adequate claim is essential for a contractor
as it must demonstrate its claim with substantiated evidences with
existence of all supporting documents that probably be reason of success
in preserving its rights and subsequently, gaining a full or partial
compensation (prolongation costs) with considering protocols that both
parties agreed upon for jurisdiction while occurrence of any delays during
the course of the project.
5 
Introduction
The Oil and Gas industry is one of the most critical and complicated
construction process projects especially, during construction phase as it
contains a lot of complexities and incessant implementations which it
requires experienced contractors that have special abilities to enable them
to work in unusual and interchanging atmospheres.
1. Event
In spite of considering all major and secondary factors that might
affect the work progress during the establishment of the baseline
schedule for the project, such as conducting contingencies reserves
for known events, schedule slippage will occur in some of the
activities that might affect the progress which it is usually named as
(EVENTS), some of these factors can be covered under the following
conditions:
1.1 General Condition
Generally, can affect all types of projects including oil and gas:
1- Force Majeure (Expected and Unexpected events)
2- Employees strike.
3- Inefficient time estimate for some activities due to low experience.
6 
4- Disputes due to ambiguity/discrepancy in the scope of work
between the tender documents and documents during construction
phase (for example responsibility matrix discrepancies)
5- Scope of work modifications/changes due to client requirements
and deviation in technical specifications.
6- Unavailability of sufficient number or skilled resources for activities
execution.
7- Delay in submission of construction drawings (IFC or AFC).
8- Frequent changing in engineering drawings/deliverables whether it
is client’s scope or contractor’s scope (In case of EPC projects)
that might be affecting commencement or continuation/completion
of the construction activities.
9- Failure to comply with project procurement plan which it will lead to
delay in delivery of material(s) or equipment in EPC projects.
10- Neglecting the non-working days (day-offs) during a year (National
holidays, Climatic holidays and Religious holidays).
11- Work suspension due to interface problem or payments delay.
7 
1.2 Particular Condition
Specified for oil and gas projects:
1- Work condition at site:
 Handling, demolishing and rerouting of underground and
above ground existing utilities neither mentioned in tender
drawings nor mentioned in any as built drawings for previous
executed projects that are located in the same place.
 Failure of selecting appropriate constructability method with
consideration of site condition and surrounding factors and
utilities.
 Issuing work permits with all related attached documents that
are time consuming for the issuance and renewal of permits
such as; Confined Space Entry (CSE), Job Safety Analysis
(JSA), Risk Assessments (RA), etc.
2- Health, Safety and Environment (HSE) precautions/requirements
which stringent than the ones in normal construction projects
such as the use of special Personal Protective Equipment (PPE).
3- Unanticipated Gas leakage (Specially H2S gas) in refineries
and petrochemical plants which it requires an immediate
personal evacuation.
8 
4- Strict security requirements at restricted areas (Brown Fields)
especially during personal entering/exiting the site.
5- Special studies required for Oil and Gas projects such as:
 SIMOPS: Simultaneous Operations Study, which is a
study that clarifying the flow of construction process with
consider other contractors within the same proposed
location of the construction and consider the interfering
activities within the same contractor scope of work that
require high professional coordination between all project
disciplines.
 HAZOP: Hazard and Operability, it is a study for identifying
all proposed risks that might be affecting project resources
during operation stage.
 HAZID: Hazard Identification, it is a study for identifying all
potential hazards and threats effecting safety of people
and environment.
 QRA: Quantitative Risk Assessment, is to identify the
potential hazards and their consequences which are
included evaluate risks resulting from these hazards (such
9 
as fire, explosion and toxic release etc.) on human
population.
 SIL: Safety Integrity Level, is to identify risks to persons,
environment, assets and considering potential hazards
arising from the failure of safety instrumented systems and
associated facilities in the plant.
Usually these studies prepared during the commencement of
the construction activities and might be affecting the progress of
work; subsequently, will lead to modifying the constructability
methods which it depends upon the contractor professionalism.
These events are varies in terms of its impact on the project where it
can be classified based on types, degree of influence and ownership,
some events can cover its impacts before occurrence for example
contractor can absorb part of these prospective events by considering
additional time for some activities while schedule preparation in order
to cover any unexpected events that can affect activity execution
during execution stage.
10 
2. Records
The second stage in preparation of successful Extension of Time claims is
to record all the events during project phases irrespective of the importance
or worthless of the event. This stage is considered as the most important
step to prepare a strong EOT claim.
For documenting events in the project, there are many types of records
such as:
1- Daily, weekly and monthly reports.
2- Minutes of Meetings.
3- Official letters.
4- Transmittals and submittals.
5- Updated time schedules.
6- Electronic mails (which it will be considered as a secondary
document comparing to official letter).
7- Dated photos.
When recording the events, Contractor should take into consideration the
chronological order while preparing his database for the events which it will
support his claim, in this case client can easily understand the sequential
order of these events and its consequences that caused the delay in the
project.
11 
3. Baseline Schedule
The most important document that contractor can stand on it is the
approved baseline schedule which as is the most reliable document that
project parties could invoke in case of arisen disputes.
In spite of existence of time schedule in contract document but it does not
cover the overall construction activities for the project; thus, preparation of
detailed schedule (level three or level four time schedule) is essential and
to get approval of that baseline schedule especially in complicated projects
it needs to run of arduous negotiations where each party from the project
wants to shift the responsibility to the other party such as given permittivity
in the implementation of the activities by place some conditions for
execution, that condition is (Milestone).
Milestone is an significant event related to the beginning or end of activity
or set of activities for committing both parties of the project, for example
fixing material delivery date drives the client to deliver the material exact on
time otherwise contractor cannot commence the activity, in the other side
fixing pre-commissioning and commissioning date which oblige the
contractor to complete construction activities on time otherwise the plant
will be delayed from the production on the set time.
Creating measurements performance standards for the project is very
important as we have mentioned previously, with presence of approved
baseline schedule where we can measure project work performance on
12 
each periodical update against original plan and consequently, discovering
all present and predictable forecast deviations between the original plan
and the current project status; then, act accordingly. Sometimes all project
parties conform to change or modify baseline schedule in case of major
changes in project scope of work; therefore, new baseline schedule will be
agreed upon and all future performance measurements will be compared
with that new baseline.
In order to justify the deviations between original and updated plan,
contractor shall prepare delay analysis which consists of all incorporated
events that affected the work progress into all activities on critical path(s) of
the project baseline schedule from the start date of each activity until its
completion date and sometimes new critical path(s) could be generated as
a result of occurrence from these events. This process is known as Time
Impact Analysis (TIA) and usually can be displayed by bar charts with
these events causing the delay can be placed as new activities added to
the updated schedule in order to demonstrate the delay in one or more
activities; these additional events are named (FRAGNET) which will be
clarified in Figure (1).
Updating the time schedule in the early stage enable contractor to discover
any delay that might occur and its impact on the work progress. As the
contractor is recording all events from the beginning, contractor should
study each event that affected or might affect the schedule and segregate
all recorded events that might cause delays during work progress by
13 
filtering all events impacting the work progress at the project and evaluating
each event that could cause project delays and classifying these events
according to the responsibilities of each party; this step is (Event Liability
for the Delay).
Figure 1 — Critical Path Delay Analysis
(Case Study-Author previous project)
14 
4. Liability
Usually liability of the events that causing the delay can be defined in
contract documents which clarify the obligations of each party and based
on that, each party can claim the other based on the contract clauses; for
example; a client can be invoked to contract clauses regarding delays and
applying liquidated damages or penalties as result of contractor’s failure
due to its inability to implement its obligations and thus, all delays are solely
attributable by him (such as poor performance or delay in execution set of
construction activities), on the contrary from the Contractor as his position
more difficult to prove their eligibility to claim and here comes the
importance of recording all events as It is possible to guarantee the
contractors’ rights.
Sometimes it could be occurrence of two (2) events or more that
influencing the specific activity or more at the same time, Contractor should
specify liability of each party, consequently it may be considered as
concurrent delay and in that time, contractor is eligible for extra time that
extended beyond concurrently occurred if he successes to prove his
entitlement.
In Figure 2, we can understand how each party owns the reason for delay
and in which exact time it is affecting whether the starting or during
15 
PROJECT :
WORK ORDER NO. :
SCHEDULE REVISION :
PLANNED
DURATION
IMPACTED
DURATION
(Calendar Days) (Calendar Days) OTHERS HEISCO OTHERS
1 UG-CT-1000TO 1050 CABLETRENCH-REG.05 16-Feb-14
1.LATECLEARANCETO STARTEXCAVATION
2.DATESADVISED BYSC&T. 258 1-Nov-14 30-Dec-14 - 258.00 59 16-Apr-14 16 75 2-May-14 - 16.00 274.00 15-Jan-15 - 274.00
1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013
2)ContractorLetterRef:L-109,Date:22ndOctober 2013
3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014
4)ContractorLetterRef:L-183,Date:14thJune 2014
5)MutuallyAgreedDates
6)Subcontractor's LetterRef:L/0225,0226,0227
7)MOM-WCR-048,049,050
8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15)
2 UG-CT-165TO 190 CABLETRENCH-TGTU.99 06-Feb-14
1.LATECLEARANCETO STARTEXCAVATION
2.DATESADVISED BYSC&T. 305 8-Dec-14 1-Jan-15 - 305.00 24 02-Mar-14 49 73 20-Apr-14 - 49.00 354.00 19-Feb-15 - 354.00
1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013
2)ContractorLetterRef:L-109,Date:22ndOctober 2013
3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014
4)ContractorLetterRef:L-183,Date:14thJune 2014
5)MutuallyAgreedDates
6)Subcontractor's LetterRef:L/0225,0226,0227
7)MOM-WCR-048,049,050
8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15)
3 RD-PV-1000TO 1050 CONCRETEPAVING-REG.05 03-May-14
1.DELAYINSTART
2.DELAYINSUBSEQUENTACTIVITY(CABLETRENCH)
257 15-Jan-15 14-Mar-15 - 257.00 58 30-Jun-14 2 60 2-Jul-14 - 2.00 259.00 16-Mar-15 - 259.00
1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013
2)ContractorLetterRef:L-109,Date:22ndOctober 2013
3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014
4)ContractorLetterRef:L-183,Date:14thJune 2014
5)MutuallyAgreedDates
6)Subcontractor's LetterRef:L/0225,0226,0227
7)MOM-WCR-048,049,050
8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15)
4 RD-PAV-100TO 150 CONCRETEPAVING-TGTU.99 11-Feb-14
1.DELAYINSTART
2.DELAYINSUBSEQUENTACTIVITY(CABLETRENCH)
399 17-Mar-15 4-Apr-15 - 399.00 18 01-Mar-14 40 58 10-Apr-14 - 40.00 439.00 14-May-15 - 439.00
1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013
2)ContractorLetterRef:L-109,Date:22ndOctober 2013
3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014
4)ContractorLetterRef:L-183,Date:14thJune 2014
5)MutuallyAgreedDates
6)Subcontractor's LetterRef:L/0225,0226,0227
7)MOM-WCR-048,049,050
8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15)
5 RACK-FP-1000to1300 FIREPROOFING 26-May-14
DELAYINHAND OVER OFP/R INREG.05&TGTU-99FROMMECHANICAL&
E&I
265 15-Feb-15 5-Mar-15 - 265.00 18 30-Jun-14 39 57 8-Aug-14 - 39.00 304.00 13-Apr-15 - 304.00
1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013
2)ContractorLetterRef:L-109,Date:22ndOctober 2013
3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014
4)ContractorLetterRef:L-183,Date:14thJune 2014
5)MutuallyAgreedDates
6)Subcontractor's LetterRef:L/0225,0226,0227
7)MOM-WCR-048,049,050
8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15)
6 UG-ICTR-200 PAVING-COMMONAREA 20-Jan-14
LIMITED OPENWORKFRONTDUETO SCAFFOLDINGREMOVALRELATED
TO MRTAWORK.
358 13-Jan-15 31-Jan-15 - 358.00 18 22-Mar-14 44 62 5-May-14 - 44.00 402.00 16-Mar-15 - 402.00
1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013
2)ContractorLetterRef:L-109,Date:22ndOctober 2013
3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014
4)ContractorLetterRef:L-183,Date:14thJune 2014
5)MutuallyAgreedDates
6)Subcontractor's LetterRef:L/0225,0226,0227
7)MOM-WCR-048,049,050
8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15)
30-Jun-14 14-May-15 TOTALDELAYS= 318.00
UpdatedSchedule-Rev.02-FinishDateasof14May2015
EXTENSION OF TIMEREQUEST (EOT)
TIMEIMPACT ANALYSIS(TIA)*
Civil& BuildingWorks
XXXXXX
ORIGINALCOMPLETION DATE=
START DELAYS DURATION DELAYS TOTALDELAYS
LIABILITY LIABILITY LIABILITY
ACTIVITYID.SL.NO.
CRITICAL/NEAR
CRITICALACTIVITIES PLANNED
START
DELAYEVENT(S)
RELEVANT CORRESPONDENCES
IMPACTED
FINISH
IMPACTED
START
DELAYS
SUBCONT-
RACTOR
OTHERS
PLANNED
FINISH
SUBCONT-
RACTOR
DELAYS
IMPACTED
FINISH
IMPACTED
FINISH
TOTAL
execution of the activity and consequently, how it impacts the project
completion date.
Figure 2 — Time Impact Analysis
(Case Study-Author previous project)
16 
5. Type of Claims
When we are planning to claim, Contractor shall be fully aware of what he
wants from the owner's claim and is the claim value worth to and which type of
claim he will conduct as there are many type of claims such as excusable or
non-excusable and compensable or non-compensable, for excusable and
compensable, contractor is claiming for both time extension and prolongation
cost due to additional scope of work which in required more time and cost, and
for compensable claim sometimes client requests from the contractor to
accelerate the work progress by increasing the productivity; therefore,
contractor will add more recourses to crash the schedule and complete the
work before original completion date, and for excusable claim sometime
contractor requests additional time only if he delayed some activities and he
realized that more time to execute the activities are required or due to some
circumstances that are beyond contactor’s control that required extension of
time with acceptance from client to postpone completion date without applying
any penalties.
As it is globally standard, some contracts referred to FIDIC clauses in case of
disputes existence which are clearly identifying the right to claim for extension
of time or prolongation cost or both, there are some clauses regarding the
disputes in this field such as:
17 
1- Sub-clause 1.9 (Delay Drawings or Instructions) – Extension of time and
costs.
2- Sub-clause 2.1 (Right of Access to Site) – Extension of time and costs.
3- Sub-clause 4.7 (Setting Out) – Extension of time and costs.
4- Sub-clause 4.12 (Unforeseeable Physical Condition) – Extension of time
and costs.
5- Sub-clause 4.24 (Fossils) – Extension of time and costs.
6- Sub-clause 8.4(a) (Extension of Time for Completion) – Variations -
Extension of time.
7- Sub-clause 8.4(c) (Extension of Time for Completion) – Exceptionally
Adverse Climatic Condition - Extension of time and Costs.
8- Sub-clause 8.4(d) (Extension of Time for Completion), Unforeseeable
Shortage as a result of Government Legislation - Extension of time and
Cost.
9- Sub-clause 13.8 (Adjustment in Changes in Legislation) – Additional
Payment.
10- Sub-clause 16.1 (Contractor’s Entitlement to Suspend Work) – Extension
of time and Cost.
11- Sub-clause 17.4 (Consequences of Employer’s Risks) – Extension of
time and Cost.
18 
12- Sub-clause 19.4 (Consequences of Force Majeure) – Extension of time
and Cost.
6. Claim Preparation
In order to prepare strong and convincing claims, Contractor has to ensure
to properly prepare a log of all events that occurred during project life cycle
that affected the work progress by chronological order; then, contractor has
to incorporate all these events on the approved baseline schedule as
described before to check whether any implications were negatively
affecting the progress or not by using delay analysis method.
In case of existence of any impacts from these events, Contractor must
analyze each event to check which party is responsible of each event and
therefore, how owns the delay. Contractor has to notify the client regarding
each event that affecting the project work progress at such date with
clarifying all consequences of these events whether it will impact time or
cost or both.
Some contracts contain clauses that can be invoked in case of disputes
between owner and the contractor however, based on sub-clause 20.1
19 
(Construction Claims) mentioned in FIDIC, contractor SHALL notify the
client for every event that affecting the work progress within 28 days from
knowing about that event and if contractor notifies the client after 28 days
from knowing about that event, the contractor has no right to claim for any
consequences or implications that resulting from that event occurrence.
Also, based on the same FIDIC sub-clause, Contractor should send full
claim within 42 days from his knowledge about that event and that claim
should contain all demonstrated documents that proving the entitlement for
claim; such as correspondences, minutes of meetings, photos, contract
clauses that set for disputes and of course, the delay analysis.
Contractor can submit one or more claims based on the sequence of
events and their impact on the project also presentation of the claim should
be well prepared with chronologically manner.
7. Response
In the other side, owner has to replay whether by acceptance or rejection
based on its evaluation of contractor’s claim also based on sub-clause 20.1
(Construction Claims) mentioned in FIDIC; the owner (Engineer) in a period
not exceeding 42 days has to reply to the contractor by acceptance or
rejection and some time the engineer prepares a counter claim if he has
20 
some evidences that demonstrating contractor’s responsibility for
occurrence of some events that causing project delay.
In this case analyzing these concurrent delays should be conducted by
both parties in order to specify liabilities’ owners and consequently,
reaching to a mutual agreement that concluded whether contractor is
entitled or not.
8. Settlement
Once receiving and analyzing contractor's claim by owner, project parties
will proceed with negotiations phase which will be the most difficult phase
in claim procedure as each party will defend his position.
In some cases negotiations do not lead to any positive result, both parties
should restore to trusted third party that both parties agreed on its
experience in this field.
Sometimes both parties invoked to third party experienced in claiming
issues that could be consider as representative of each party, some
claiming authors called this phase as Amicable Settlement.
In case of failure of the negotiations which included third party, both parties
will be invoked to arbitration which will be considered at the last stage in
claiming process and which requires a long time to be adjudicated.
21 
Conclusion
The success of Extension of Time claim is associated with many factors
especially in oil and gas Projects. It relies primarily on the experienced
Contractor in that field; however, the most important is to get approved
baseline schedule from client, chronologically recording all events and
notify the client regarding these events with their impacts as early as
possible.
In the meantime, Contractor has to evaluate the feasibility for preparation a
claim for Extension of Time or demanding prolongation cost or both as this
process requires professional expertise with exerting huge efforts to
demonstrate all arguments by valuable evidences in order to obtain
complete compensation.
22 
Bibliography
No. Description
1 Andy Hewitt, 2011
Construction Claims & Responses: effective writing & presentation
First Edition, John Wiley & Sons, Ltd
2 Andy Hewitt, 2016
Construction Claims Intensive Training Course
Kuwait, 24&25 September, 2016
Hewitt Construction Consultancy
3 Society of Construction Low, October, 2002
SCL Delay and Disruption Protocol
Printed by Printmost (Southern) Ltd.
www.scl.org.uk
4 Khaled Ahmed Ali Alnaas, Ayman Hussein Hosny Khalil,
Gamal Eldin Nassar, 2014, Article
Guideline for preparing comprehensive extension of time (EOT) claim
Volume 10, Issue 3, Pages (308 – 316), HBRC Journal
www.sciencedirect.com
5 Jeffrey Badman, 2008
Extension of time claims
Hill International Monthly Article
Construction Management Guide

More Related Content

PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PDF
Claims
PPTX
Eot claims hr__may2012
PPTX
Extension of time Analysis
PPTX
VERTEX Construction Delays and Forensic Schedule Analyses
PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
PDF
Prolongation and HOOH Costs
PDF
EOT Related Cost Compensation Determination
Extension of time (E.O.T) By Ahmed Ibarhim
Claims
Eot claims hr__may2012
Extension of time Analysis
VERTEX Construction Delays and Forensic Schedule Analyses
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Prolongation and HOOH Costs
EOT Related Cost Compensation Determination

What's hot (20)

PDF
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
PDF
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
PPTX
Construction Delay Analysis, Simplified
PDF
50 Planning Fundamentals V5.0 - procedures only
PDF
Time Impact Analysis
PPTX
Baseline schedule review and analysis
PDF
Delay analysis ... wise after the event.
PDF
Essentials of EOT Claims
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PPTX
Forensic schedule analysis acesss
PDF
Delay Analysis and Concurrent Delay
PDF
Schedule Updates
PDF
FIDIC SIlver Book in Power Projects
PPTX
Earned Value Management - Leading & Misleading in Project Control
PDF
Avoiding unrealistic schedules
PDF
Project Schedule Management
PPSX
Schedule-Delay Analysis
PPS
Claims & disputes management
PPTX
Contracts & Claims Management Workshop (Session-1)
PDF
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Construction Delay Analysis, Simplified
50 Planning Fundamentals V5.0 - procedures only
Time Impact Analysis
Baseline schedule review and analysis
Delay analysis ... wise after the event.
Essentials of EOT Claims
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Forensic schedule analysis acesss
Delay Analysis and Concurrent Delay
Schedule Updates
FIDIC SIlver Book in Power Projects
Earned Value Management - Leading & Misleading in Project Control
Avoiding unrealistic schedules
Project Schedule Management
Schedule-Delay Analysis
Claims & disputes management
Contracts & Claims Management Workshop (Session-1)
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Ad

Similar to EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS (20)

PPTX
C. Site managment chapter 5.pptx
PDF
Managing the Construction Claims Effectively
PPTX
Literature review on_ extension of time
PDF
(Essay) HRO & Lean 6 Sigma
PPT
Work scheduling(2)
PPTX
Project planning and construction management UNIT- 2.pptx
PDF
Causes of delays on Construction Projects in Kuwait according to opinion of e...
PDF
Claims Management, Extension of Time (EOT) and Delays Analysis
PPTX
Delay analysis of raw water reservoir and pumping Station
PPTX
Session-02 17-09-2011
PDF
PROJECT REPORT CHALLENGES Hitesh
PDF
Analysis of factors contributing delays and claims in
PDF
Analysis of factors contributing delays and claims in construction projects
PDF
Analysis of factors contributing delays and claims in construction projects
PDF
Attributes affecting success of the residential projects – a review
DOCX
challenges of highway projects in India
PPTX
Construction management I lecture note (QUS 3166).pptx
PPTX
Missing safety during construction
PPTX
6. Project Planning for project management.pptx
PPTX
Claims and insolvencies (1)
C. Site managment chapter 5.pptx
Managing the Construction Claims Effectively
Literature review on_ extension of time
(Essay) HRO & Lean 6 Sigma
Work scheduling(2)
Project planning and construction management UNIT- 2.pptx
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Claims Management, Extension of Time (EOT) and Delays Analysis
Delay analysis of raw water reservoir and pumping Station
Session-02 17-09-2011
PROJECT REPORT CHALLENGES Hitesh
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
Attributes affecting success of the residential projects – a review
challenges of highway projects in India
Construction management I lecture note (QUS 3166).pptx
Missing safety during construction
6. Project Planning for project management.pptx
Claims and insolvencies (1)
Ad

Recently uploaded (20)

PPTX
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
PPTX
Design ,Art Across Digital Realities and eXtended Reality
PDF
Lesson 3 .pdf
PPTX
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
PDF
IAE-V2500 Engine for Airbus Family 319/320
PPTX
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
PDF
Project_Mgmt_Institute_-Marc Marc Marc .pdf
PPTX
AI-Reporting for Emerging Technologies(BS Computer Engineering)
PDF
LS-6-Digital-Literacy (1) K12 CURRICULUM .pdf
PPT
UNIT-I Machine Learning Essentials for 2nd years
PPTX
BBOC407 BIOLOGY FOR ENGINEERS (CS) - MODULE 1 PART 1.pptx
PDF
electrical machines course file-anna university
PDF
Principles of operation, construction, theory, advantages and disadvantages, ...
PPTX
Real Estate Management PART 1.pptxFFFFFFFFFFFFF
PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
PDF
VSL-Strand-Post-tensioning-Systems-Technical-Catalogue_2019-01.pdf
PPTX
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
PPTX
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
PPTX
Solar energy pdf of gitam songa hemant k
CNS - Unit 1 (Introduction To Computer Networks) - PPT (2).pptx
Design ,Art Across Digital Realities and eXtended Reality
Lesson 3 .pdf
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
IAE-V2500 Engine for Airbus Family 319/320
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
Project_Mgmt_Institute_-Marc Marc Marc .pdf
AI-Reporting for Emerging Technologies(BS Computer Engineering)
LS-6-Digital-Literacy (1) K12 CURRICULUM .pdf
UNIT-I Machine Learning Essentials for 2nd years
BBOC407 BIOLOGY FOR ENGINEERS (CS) - MODULE 1 PART 1.pptx
electrical machines course file-anna university
Principles of operation, construction, theory, advantages and disadvantages, ...
Real Estate Management PART 1.pptxFFFFFFFFFFFFF
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
VSL-Strand-Post-tensioning-Systems-Technical-Catalogue_2019-01.pdf
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
Solar energy pdf of gitam songa hemant k

EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS

  • 1.         CCP Certification Technical Paper EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS December 25th , 2016 AACE Membership Number 289940
  • 2. 2  TABLE OF CONTENTS List of Figures ………………………………………………………………. 3 Abstract ……………………………………………………………………… 4 Introduction …………………………………………………………….……. 5 1.Event ………………………………………………………………….…… 5 1.1 General Conditions …………………………………………….…... 5 1.2 Particular Conditions ………………………………………….….… 7 2.Records …………………………………………………………….……... 10 3.Baseline Schedule ……………………………………………………….. 11 4.Liability ……………………………………………………………………. 14 5.Type of Claims …………………………………………………………… 16 6.Claim Preparation ………………………………………………………... 18 7.Response …………………………………………………………………. 19 8.Settlement ………………………………………………………………… 20 Conclusion …………………………………………………………………... 21 Bibliography………………………………………………………………….. 22
  • 3. 3  List of Figures Figure 1 “Critical Path Delay Analysis”.................................................. 13 Figure 2 “Time Impact Analysis“……………………………………….…. 15
  • 4. 4  Abstract This document is dedicated to projects especially in Oil and Gas field wherein, in light of rapid and continuous development of the construction process and under intense competition in order to acquire reasonable profits, they are facing naturally lot of delays and disruptions which lead to exert huge efforts for proving these delays. As Extension of Time (EOT) claim involves countless of complex issues and most often resulting with difference scenarios between projects parties, establishing and presenting an adequate claim is essential for a contractor as it must demonstrate its claim with substantiated evidences with existence of all supporting documents that probably be reason of success in preserving its rights and subsequently, gaining a full or partial compensation (prolongation costs) with considering protocols that both parties agreed upon for jurisdiction while occurrence of any delays during the course of the project.
  • 5. 5  Introduction The Oil and Gas industry is one of the most critical and complicated construction process projects especially, during construction phase as it contains a lot of complexities and incessant implementations which it requires experienced contractors that have special abilities to enable them to work in unusual and interchanging atmospheres. 1. Event In spite of considering all major and secondary factors that might affect the work progress during the establishment of the baseline schedule for the project, such as conducting contingencies reserves for known events, schedule slippage will occur in some of the activities that might affect the progress which it is usually named as (EVENTS), some of these factors can be covered under the following conditions: 1.1 General Condition Generally, can affect all types of projects including oil and gas: 1- Force Majeure (Expected and Unexpected events) 2- Employees strike. 3- Inefficient time estimate for some activities due to low experience.
  • 6. 6  4- Disputes due to ambiguity/discrepancy in the scope of work between the tender documents and documents during construction phase (for example responsibility matrix discrepancies) 5- Scope of work modifications/changes due to client requirements and deviation in technical specifications. 6- Unavailability of sufficient number or skilled resources for activities execution. 7- Delay in submission of construction drawings (IFC or AFC). 8- Frequent changing in engineering drawings/deliverables whether it is client’s scope or contractor’s scope (In case of EPC projects) that might be affecting commencement or continuation/completion of the construction activities. 9- Failure to comply with project procurement plan which it will lead to delay in delivery of material(s) or equipment in EPC projects. 10- Neglecting the non-working days (day-offs) during a year (National holidays, Climatic holidays and Religious holidays). 11- Work suspension due to interface problem or payments delay.
  • 7. 7  1.2 Particular Condition Specified for oil and gas projects: 1- Work condition at site:  Handling, demolishing and rerouting of underground and above ground existing utilities neither mentioned in tender drawings nor mentioned in any as built drawings for previous executed projects that are located in the same place.  Failure of selecting appropriate constructability method with consideration of site condition and surrounding factors and utilities.  Issuing work permits with all related attached documents that are time consuming for the issuance and renewal of permits such as; Confined Space Entry (CSE), Job Safety Analysis (JSA), Risk Assessments (RA), etc. 2- Health, Safety and Environment (HSE) precautions/requirements which stringent than the ones in normal construction projects such as the use of special Personal Protective Equipment (PPE). 3- Unanticipated Gas leakage (Specially H2S gas) in refineries and petrochemical plants which it requires an immediate personal evacuation.
  • 8. 8  4- Strict security requirements at restricted areas (Brown Fields) especially during personal entering/exiting the site. 5- Special studies required for Oil and Gas projects such as:  SIMOPS: Simultaneous Operations Study, which is a study that clarifying the flow of construction process with consider other contractors within the same proposed location of the construction and consider the interfering activities within the same contractor scope of work that require high professional coordination between all project disciplines.  HAZOP: Hazard and Operability, it is a study for identifying all proposed risks that might be affecting project resources during operation stage.  HAZID: Hazard Identification, it is a study for identifying all potential hazards and threats effecting safety of people and environment.  QRA: Quantitative Risk Assessment, is to identify the potential hazards and their consequences which are included evaluate risks resulting from these hazards (such
  • 9. 9  as fire, explosion and toxic release etc.) on human population.  SIL: Safety Integrity Level, is to identify risks to persons, environment, assets and considering potential hazards arising from the failure of safety instrumented systems and associated facilities in the plant. Usually these studies prepared during the commencement of the construction activities and might be affecting the progress of work; subsequently, will lead to modifying the constructability methods which it depends upon the contractor professionalism. These events are varies in terms of its impact on the project where it can be classified based on types, degree of influence and ownership, some events can cover its impacts before occurrence for example contractor can absorb part of these prospective events by considering additional time for some activities while schedule preparation in order to cover any unexpected events that can affect activity execution during execution stage.
  • 10. 10  2. Records The second stage in preparation of successful Extension of Time claims is to record all the events during project phases irrespective of the importance or worthless of the event. This stage is considered as the most important step to prepare a strong EOT claim. For documenting events in the project, there are many types of records such as: 1- Daily, weekly and monthly reports. 2- Minutes of Meetings. 3- Official letters. 4- Transmittals and submittals. 5- Updated time schedules. 6- Electronic mails (which it will be considered as a secondary document comparing to official letter). 7- Dated photos. When recording the events, Contractor should take into consideration the chronological order while preparing his database for the events which it will support his claim, in this case client can easily understand the sequential order of these events and its consequences that caused the delay in the project.
  • 11. 11  3. Baseline Schedule The most important document that contractor can stand on it is the approved baseline schedule which as is the most reliable document that project parties could invoke in case of arisen disputes. In spite of existence of time schedule in contract document but it does not cover the overall construction activities for the project; thus, preparation of detailed schedule (level three or level four time schedule) is essential and to get approval of that baseline schedule especially in complicated projects it needs to run of arduous negotiations where each party from the project wants to shift the responsibility to the other party such as given permittivity in the implementation of the activities by place some conditions for execution, that condition is (Milestone). Milestone is an significant event related to the beginning or end of activity or set of activities for committing both parties of the project, for example fixing material delivery date drives the client to deliver the material exact on time otherwise contractor cannot commence the activity, in the other side fixing pre-commissioning and commissioning date which oblige the contractor to complete construction activities on time otherwise the plant will be delayed from the production on the set time. Creating measurements performance standards for the project is very important as we have mentioned previously, with presence of approved baseline schedule where we can measure project work performance on
  • 12. 12  each periodical update against original plan and consequently, discovering all present and predictable forecast deviations between the original plan and the current project status; then, act accordingly. Sometimes all project parties conform to change or modify baseline schedule in case of major changes in project scope of work; therefore, new baseline schedule will be agreed upon and all future performance measurements will be compared with that new baseline. In order to justify the deviations between original and updated plan, contractor shall prepare delay analysis which consists of all incorporated events that affected the work progress into all activities on critical path(s) of the project baseline schedule from the start date of each activity until its completion date and sometimes new critical path(s) could be generated as a result of occurrence from these events. This process is known as Time Impact Analysis (TIA) and usually can be displayed by bar charts with these events causing the delay can be placed as new activities added to the updated schedule in order to demonstrate the delay in one or more activities; these additional events are named (FRAGNET) which will be clarified in Figure (1). Updating the time schedule in the early stage enable contractor to discover any delay that might occur and its impact on the work progress. As the contractor is recording all events from the beginning, contractor should study each event that affected or might affect the schedule and segregate all recorded events that might cause delays during work progress by
  • 13. 13  filtering all events impacting the work progress at the project and evaluating each event that could cause project delays and classifying these events according to the responsibilities of each party; this step is (Event Liability for the Delay). Figure 1 — Critical Path Delay Analysis (Case Study-Author previous project)
  • 14. 14  4. Liability Usually liability of the events that causing the delay can be defined in contract documents which clarify the obligations of each party and based on that, each party can claim the other based on the contract clauses; for example; a client can be invoked to contract clauses regarding delays and applying liquidated damages or penalties as result of contractor’s failure due to its inability to implement its obligations and thus, all delays are solely attributable by him (such as poor performance or delay in execution set of construction activities), on the contrary from the Contractor as his position more difficult to prove their eligibility to claim and here comes the importance of recording all events as It is possible to guarantee the contractors’ rights. Sometimes it could be occurrence of two (2) events or more that influencing the specific activity or more at the same time, Contractor should specify liability of each party, consequently it may be considered as concurrent delay and in that time, contractor is eligible for extra time that extended beyond concurrently occurred if he successes to prove his entitlement. In Figure 2, we can understand how each party owns the reason for delay and in which exact time it is affecting whether the starting or during
  • 15. 15  PROJECT : WORK ORDER NO. : SCHEDULE REVISION : PLANNED DURATION IMPACTED DURATION (Calendar Days) (Calendar Days) OTHERS HEISCO OTHERS 1 UG-CT-1000TO 1050 CABLETRENCH-REG.05 16-Feb-14 1.LATECLEARANCETO STARTEXCAVATION 2.DATESADVISED BYSC&T. 258 1-Nov-14 30-Dec-14 - 258.00 59 16-Apr-14 16 75 2-May-14 - 16.00 274.00 15-Jan-15 - 274.00 1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013 2)ContractorLetterRef:L-109,Date:22ndOctober 2013 3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014 4)ContractorLetterRef:L-183,Date:14thJune 2014 5)MutuallyAgreedDates 6)Subcontractor's LetterRef:L/0225,0226,0227 7)MOM-WCR-048,049,050 8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15) 2 UG-CT-165TO 190 CABLETRENCH-TGTU.99 06-Feb-14 1.LATECLEARANCETO STARTEXCAVATION 2.DATESADVISED BYSC&T. 305 8-Dec-14 1-Jan-15 - 305.00 24 02-Mar-14 49 73 20-Apr-14 - 49.00 354.00 19-Feb-15 - 354.00 1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013 2)ContractorLetterRef:L-109,Date:22ndOctober 2013 3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014 4)ContractorLetterRef:L-183,Date:14thJune 2014 5)MutuallyAgreedDates 6)Subcontractor's LetterRef:L/0225,0226,0227 7)MOM-WCR-048,049,050 8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15) 3 RD-PV-1000TO 1050 CONCRETEPAVING-REG.05 03-May-14 1.DELAYINSTART 2.DELAYINSUBSEQUENTACTIVITY(CABLETRENCH) 257 15-Jan-15 14-Mar-15 - 257.00 58 30-Jun-14 2 60 2-Jul-14 - 2.00 259.00 16-Mar-15 - 259.00 1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013 2)ContractorLetterRef:L-109,Date:22ndOctober 2013 3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014 4)ContractorLetterRef:L-183,Date:14thJune 2014 5)MutuallyAgreedDates 6)Subcontractor's LetterRef:L/0225,0226,0227 7)MOM-WCR-048,049,050 8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15) 4 RD-PAV-100TO 150 CONCRETEPAVING-TGTU.99 11-Feb-14 1.DELAYINSTART 2.DELAYINSUBSEQUENTACTIVITY(CABLETRENCH) 399 17-Mar-15 4-Apr-15 - 399.00 18 01-Mar-14 40 58 10-Apr-14 - 40.00 439.00 14-May-15 - 439.00 1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013 2)ContractorLetterRef:L-109,Date:22ndOctober 2013 3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014 4)ContractorLetterRef:L-183,Date:14thJune 2014 5)MutuallyAgreedDates 6)Subcontractor's LetterRef:L/0225,0226,0227 7)MOM-WCR-048,049,050 8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15) 5 RACK-FP-1000to1300 FIREPROOFING 26-May-14 DELAYINHAND OVER OFP/R INREG.05&TGTU-99FROMMECHANICAL& E&I 265 15-Feb-15 5-Mar-15 - 265.00 18 30-Jun-14 39 57 8-Aug-14 - 39.00 304.00 13-Apr-15 - 304.00 1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013 2)ContractorLetterRef:L-109,Date:22ndOctober 2013 3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014 4)ContractorLetterRef:L-183,Date:14thJune 2014 5)MutuallyAgreedDates 6)Subcontractor's LetterRef:L/0225,0226,0227 7)MOM-WCR-048,049,050 8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15) 6 UG-ICTR-200 PAVING-COMMONAREA 20-Jan-14 LIMITED OPENWORKFRONTDUETO SCAFFOLDINGREMOVALRELATED TO MRTAWORK. 358 13-Jan-15 31-Jan-15 - 358.00 18 22-Mar-14 44 62 5-May-14 - 44.00 402.00 16-Mar-15 - 402.00 1)Subcontractor's LetterRef:L/0133,Date:13thOctober 2013 2)ContractorLetterRef:L-109,Date:22ndOctober 2013 3)Subcontractor's LetterRef:L/0208,Date:09thJune 2014 4)ContractorLetterRef:L-183,Date:14thJune 2014 5)MutuallyAgreedDates 6)Subcontractor's LetterRef:L/0225,0226,0227 7)MOM-WCR-048,049,050 8)E-mailcorrespondence(Date:15-Dec-14,04-Jan-15,07-Jan-15,10-Jan-15) 30-Jun-14 14-May-15 TOTALDELAYS= 318.00 UpdatedSchedule-Rev.02-FinishDateasof14May2015 EXTENSION OF TIMEREQUEST (EOT) TIMEIMPACT ANALYSIS(TIA)* Civil& BuildingWorks XXXXXX ORIGINALCOMPLETION DATE= START DELAYS DURATION DELAYS TOTALDELAYS LIABILITY LIABILITY LIABILITY ACTIVITYID.SL.NO. CRITICAL/NEAR CRITICALACTIVITIES PLANNED START DELAYEVENT(S) RELEVANT CORRESPONDENCES IMPACTED FINISH IMPACTED START DELAYS SUBCONT- RACTOR OTHERS PLANNED FINISH SUBCONT- RACTOR DELAYS IMPACTED FINISH IMPACTED FINISH TOTAL execution of the activity and consequently, how it impacts the project completion date. Figure 2 — Time Impact Analysis (Case Study-Author previous project)
  • 16. 16  5. Type of Claims When we are planning to claim, Contractor shall be fully aware of what he wants from the owner's claim and is the claim value worth to and which type of claim he will conduct as there are many type of claims such as excusable or non-excusable and compensable or non-compensable, for excusable and compensable, contractor is claiming for both time extension and prolongation cost due to additional scope of work which in required more time and cost, and for compensable claim sometimes client requests from the contractor to accelerate the work progress by increasing the productivity; therefore, contractor will add more recourses to crash the schedule and complete the work before original completion date, and for excusable claim sometime contractor requests additional time only if he delayed some activities and he realized that more time to execute the activities are required or due to some circumstances that are beyond contactor’s control that required extension of time with acceptance from client to postpone completion date without applying any penalties. As it is globally standard, some contracts referred to FIDIC clauses in case of disputes existence which are clearly identifying the right to claim for extension of time or prolongation cost or both, there are some clauses regarding the disputes in this field such as:
  • 17. 17  1- Sub-clause 1.9 (Delay Drawings or Instructions) – Extension of time and costs. 2- Sub-clause 2.1 (Right of Access to Site) – Extension of time and costs. 3- Sub-clause 4.7 (Setting Out) – Extension of time and costs. 4- Sub-clause 4.12 (Unforeseeable Physical Condition) – Extension of time and costs. 5- Sub-clause 4.24 (Fossils) – Extension of time and costs. 6- Sub-clause 8.4(a) (Extension of Time for Completion) – Variations - Extension of time. 7- Sub-clause 8.4(c) (Extension of Time for Completion) – Exceptionally Adverse Climatic Condition - Extension of time and Costs. 8- Sub-clause 8.4(d) (Extension of Time for Completion), Unforeseeable Shortage as a result of Government Legislation - Extension of time and Cost. 9- Sub-clause 13.8 (Adjustment in Changes in Legislation) – Additional Payment. 10- Sub-clause 16.1 (Contractor’s Entitlement to Suspend Work) – Extension of time and Cost. 11- Sub-clause 17.4 (Consequences of Employer’s Risks) – Extension of time and Cost.
  • 18. 18  12- Sub-clause 19.4 (Consequences of Force Majeure) – Extension of time and Cost. 6. Claim Preparation In order to prepare strong and convincing claims, Contractor has to ensure to properly prepare a log of all events that occurred during project life cycle that affected the work progress by chronological order; then, contractor has to incorporate all these events on the approved baseline schedule as described before to check whether any implications were negatively affecting the progress or not by using delay analysis method. In case of existence of any impacts from these events, Contractor must analyze each event to check which party is responsible of each event and therefore, how owns the delay. Contractor has to notify the client regarding each event that affecting the project work progress at such date with clarifying all consequences of these events whether it will impact time or cost or both. Some contracts contain clauses that can be invoked in case of disputes between owner and the contractor however, based on sub-clause 20.1
  • 19. 19  (Construction Claims) mentioned in FIDIC, contractor SHALL notify the client for every event that affecting the work progress within 28 days from knowing about that event and if contractor notifies the client after 28 days from knowing about that event, the contractor has no right to claim for any consequences or implications that resulting from that event occurrence. Also, based on the same FIDIC sub-clause, Contractor should send full claim within 42 days from his knowledge about that event and that claim should contain all demonstrated documents that proving the entitlement for claim; such as correspondences, minutes of meetings, photos, contract clauses that set for disputes and of course, the delay analysis. Contractor can submit one or more claims based on the sequence of events and their impact on the project also presentation of the claim should be well prepared with chronologically manner. 7. Response In the other side, owner has to replay whether by acceptance or rejection based on its evaluation of contractor’s claim also based on sub-clause 20.1 (Construction Claims) mentioned in FIDIC; the owner (Engineer) in a period not exceeding 42 days has to reply to the contractor by acceptance or rejection and some time the engineer prepares a counter claim if he has
  • 20. 20  some evidences that demonstrating contractor’s responsibility for occurrence of some events that causing project delay. In this case analyzing these concurrent delays should be conducted by both parties in order to specify liabilities’ owners and consequently, reaching to a mutual agreement that concluded whether contractor is entitled or not. 8. Settlement Once receiving and analyzing contractor's claim by owner, project parties will proceed with negotiations phase which will be the most difficult phase in claim procedure as each party will defend his position. In some cases negotiations do not lead to any positive result, both parties should restore to trusted third party that both parties agreed on its experience in this field. Sometimes both parties invoked to third party experienced in claiming issues that could be consider as representative of each party, some claiming authors called this phase as Amicable Settlement. In case of failure of the negotiations which included third party, both parties will be invoked to arbitration which will be considered at the last stage in claiming process and which requires a long time to be adjudicated.
  • 21. 21  Conclusion The success of Extension of Time claim is associated with many factors especially in oil and gas Projects. It relies primarily on the experienced Contractor in that field; however, the most important is to get approved baseline schedule from client, chronologically recording all events and notify the client regarding these events with their impacts as early as possible. In the meantime, Contractor has to evaluate the feasibility for preparation a claim for Extension of Time or demanding prolongation cost or both as this process requires professional expertise with exerting huge efforts to demonstrate all arguments by valuable evidences in order to obtain complete compensation.
  • 22. 22  Bibliography No. Description 1 Andy Hewitt, 2011 Construction Claims & Responses: effective writing & presentation First Edition, John Wiley & Sons, Ltd 2 Andy Hewitt, 2016 Construction Claims Intensive Training Course Kuwait, 24&25 September, 2016 Hewitt Construction Consultancy 3 Society of Construction Low, October, 2002 SCL Delay and Disruption Protocol Printed by Printmost (Southern) Ltd. www.scl.org.uk 4 Khaled Ahmed Ali Alnaas, Ayman Hussein Hosny Khalil, Gamal Eldin Nassar, 2014, Article Guideline for preparing comprehensive extension of time (EOT) claim Volume 10, Issue 3, Pages (308 – 316), HBRC Journal www.sciencedirect.com 5 Jeffrey Badman, 2008 Extension of time claims Hill International Monthly Article Construction Management Guide