Demystifying Earned Value
Understanding Earned Value Management (EVM)
17th June 2025
Today’s speakers.
Behnam Sarani, ChPP, AtkinsRéalis
• Project Director
• Transportation
• APM ChPP Assessor
© 2024 Association for Project Management 2
Manish Khanna, FAPM, PMP, CEng, AtkinsRéalis
• Project Controls Manager
• Transportation
• Volunteer with APM, PMP, IET
Agenda
© 2024 Association for Project Management 3
1. Introduction to Earned Value
Management (EVM)
2. Key Concepts and Terminology
3. Key Performance Indicators
4. Core Components of EVM
5. Calculating Earned Value
6. Benefits of Using EVM
7. Challenges
8. Quick Quiz
Aims of today
© 2024 Association for Project Management 4
Introduction
• EVM combines scope, time, and cost to measure project performance
• Tracks actual progress vs planned progress
• Provides early warning on cost and schedule issues
• Enables data-driven decisions and forecasting
• Widely used in both public and private sector projects
© 2024 Association for Project Management 5
Introduction - What is Earned Value?
• A measure of progress that expresses costs committed and work achieved in the
same units. (APM Glossary of Project Management Terms; Project management
Glossary | Terms used by project professional (apm.org.uk).
• A way to measure project progress using budgeted values
• Expresses work completed in £ terms
• Compares actual progress against the baselined plan
• Helps identify if you’re ahead/behind schedule or over/under budget
• Answers: “How much value have we earned for the money spent?
© 2024 Association for Project Management 6
Introduction - Why Use Earned Value?
• Gives a quick*, structured snapshot of project progress
• Highlights if a project is on time and on budget
• Flags overspend or delays early so action can be taken
• Makes performance easy to track and communicate
• Supports resource planning and package-level control
• Widely used in work package management and formal reporting
© 2024 Association for Project Management 7
Key Concepts and Terminology
There are various terms used in the calculation and interpretation of Earned Value. These are the
main ones you’ll come across:
PV (BCWS) – Planned Value (This is the Budgeted Cost of Work Scheduled)
The authorized budget assigned to the scheduled work
Calculated as Planned %age complete x budget.
EV (BCWP) – Earned Value (This is the Budgeted Cost of Work Performed).
The value of work actually preformed, expressed in terms of approved budget
Calculated as Actual %age complete x overall budget.
AC (ACWP) – Actual Cost (This is the Actual Cost of Work Performed)
The actual cost on the project (or Work Package) to date.
Cost Variance (CV) = EV – AC if CV is positive, we are under budget
Schedule Variance (SV) = EV – PV if SV is negative, we are behind schedule
© 2024 Association for Project Management 8
Note: Accurate and consistent measurement of %age complete and actual cost is important
if we want to derive meaningful metrics
Key Performance Indicators
These measures can be used to produce some useful indicators.
CPI - Cost Performance Index
Derived by dividing EV by AC = EV/AC or BCWP/ ACWP
>1.00 means the project is under budget; <1.00 means the project is over budget.
SPI - Schedule Performance Index
Derived by dividing EV by PV or BCWP/ BCWS
>1.00 means the project is ahead of schedule; <1.00 means the project is behind schedule.
CPI and SPI allow for early identification of potential project overruns or delays.
© 2024 Association for Project Management 9
Core Components of EVM
These are few of the structural and procedural elements to implement EVM effectively.
1. Work Breakdown Structure (WBS) – A hierarchical decomposition of the total scope of work to
accomplish project objectives
2. Integrated Baseline – Combines scope, schedule and cost baselines to measure performance
3. Performance Measurement Baseline (PMB) – The time phased budget plan against which
project performance is measured.
4. Data Collection and Reporting - Regular tracking of PV, EV, and AC to assess progress.
5. Forecasting - Using current data to predict future project outcomes (e.g., EAC, Estimate to
Complete).
© 2024 Association for Project Management 10
Calculating Earned Value
Assume Project A with an overall budgeted cost (BC) of £75000
At this point, progress %age complete has been calculated as 10%. Actual cost has been recorded as £5000, and budgeted cost
at this point (BCWS) is £7000.
EV = 10% X 75000 = £7500
AC = £5000
PV = £7000
CV = EV-AC = 7500 – 5000 = £2500
SV = EV-PV = 7500 – 7000 = £ 500
CPI = EV/AC = 7500 / 5000 = 1.5
SPI = EV/ PV = 7500 / 7000 = 1.07
You can calculate ‘Estimate At Completion’ by diving project budget by the CPI = BC / CPI = £75000 / 1.5 = £50000
Hence, if you have a CPI of 1.5 your Estimate at Completion (EAC) is going to be under budget
© 2024 Association for Project Management 11
Trend Curve
Over time, it can be extremely useful to monitor trends and understand how current project performance compares to planned
performance.
• Shows how project performance evolves over time
• Helps spot patterns, not just isolated issues
• Reveals if variances are short-term blips or ongoing trends
• Supports more accurate forecasting and planning
© 2024 Association for Project Management 12
EV Trend Analysis
However, it is more helpful to understand
Earned Value trend as this could help to
predict problems
© 2024 Association for Project Management 13
But…be Cautious
What’s needed:
• A baselined schedule and budget
• A consistent way to measure progress
• Accurate, timely data (not best guesses)
Common pitfalls:
• Relying on inconsistent or poor-quality inputs
• Misinterpreting metrics in isolation (e.g. CPI looks good, but SPI is tanking)
• Treating EVM as a “tick-box” or just a maths exercise
• Reporting progress based on optimism, not evidence
© 2024 Association for Project Management 14
Challenges
• Requires accurate and timely data collection
• Needs robust baselines for both schedule and budget to produce meaningful results
• Can be complex to implement and maintain, especially on large or fast-moving projects
• Relies on consistent progress measurement and reliable data inputs
• May face resistance from teams unfamiliar with EVM or unsure how to use it
• Demands consistent application across all phases of the project to be effective
© 2024 Association for Project Management 15
Benefits
• Provides an objective snapshot of both cost and schedule performance
• Key performance indicators like CPI and SPI enable early detection of potential overruns or delays
• Tracking trends in ACWP, BCWS, and BCWP helps predict issues before they escalate
• Helps identify resource inefficiencies and areas needing corrective action
• Trends show current project performance and also help forecast future risks, improving decision-
making
• Enhances communication among project stakeholders
• Improves overall project planning and control
© 2024 Association for Project Management 16
Quick Quiz – Maths time ☺
© 2024 Association for Project Management 19
• Project Budget: £100,000
• At halfway point:
• EV = £40,000
• AC = £60,000
Question:
• What’s your CPI?
• What does it tell you?
Quick Quiz - Myth or Fact?
© 2024 Association for Project Management 20
1. If CPI > 1.0, your project is under budget
2. Earned Value (EV) is the same as Actual Cost (AC)
3. A Schedule Performance Index (SPI) of 0.8 means you’re ahead of schedule
4. Earned Value Management is only useful at the end of a project
5. The formula for CPI is: EV divided by AC
6. You can use EVM effectively without a baselined schedule
7. You can change the method of assessing % complete on a project without changing baseline
Quick Quiz – What would you do?
© 2024 Association for Project Management 21
You’re reviewing a monthly report.
• CPI = 1.2 (under budget)
• SPI = 0.75 (significantly behind schedule)
Question: What would you do?
a) Celebrate the cost performance
b) Re-baseline the project
c) Investigate the delay and replan if needed
ISO Standard for Earned Value Management (EVM) - ISO 21508:2018
This standard provides guidance on the principles and practices of Earned Value
Management (EVM) within the context of project and programme management. It is applicable to any
organization—public or private, regardless of size or sector—and to any type of project or programme.
ISO 21508:2018 includes:
• Terms and definitions relevant to EVM.
• Purpose and benefits of using EVM.
• Integration of EVM with broader project or programme management practices.
• Process descriptions and an overview of EVM processes.
• Basic requirements for an EVM system.
• Guidance on using an EVM system effectively.
© 2024 Association for Project Management 22
Title - Earned value management in project and programme management
Project Controls in 21st Century
© 2024 Association for Project Management 23
Project Controls in the 21st Century
APM members can claim 10% discount on
hardback and paperback publications by using
code APMMEM10 at checkout. Plus, FREE
member digital copy downloads on named
titles.
© 2024 Association for Project Management 24
Thank you,
next steps
or any questions?
by Behnam Sarani & Manish Khanna
Project Director & Deputy HPPM & Project Controls Manager
Email@apm.org.uk
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf

IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf

  • 1.
    Demystifying Earned Value UnderstandingEarned Value Management (EVM) 17th June 2025
  • 2.
    Today’s speakers. Behnam Sarani,ChPP, AtkinsRéalis • Project Director • Transportation • APM ChPP Assessor © 2024 Association for Project Management 2 Manish Khanna, FAPM, PMP, CEng, AtkinsRéalis • Project Controls Manager • Transportation • Volunteer with APM, PMP, IET
  • 3.
    Agenda © 2024 Associationfor Project Management 3 1. Introduction to Earned Value Management (EVM) 2. Key Concepts and Terminology 3. Key Performance Indicators 4. Core Components of EVM 5. Calculating Earned Value 6. Benefits of Using EVM 7. Challenges 8. Quick Quiz
  • 4.
    Aims of today ©2024 Association for Project Management 4
  • 5.
    Introduction • EVM combinesscope, time, and cost to measure project performance • Tracks actual progress vs planned progress • Provides early warning on cost and schedule issues • Enables data-driven decisions and forecasting • Widely used in both public and private sector projects © 2024 Association for Project Management 5
  • 6.
    Introduction - Whatis Earned Value? • A measure of progress that expresses costs committed and work achieved in the same units. (APM Glossary of Project Management Terms; Project management Glossary | Terms used by project professional (apm.org.uk). • A way to measure project progress using budgeted values • Expresses work completed in £ terms • Compares actual progress against the baselined plan • Helps identify if you’re ahead/behind schedule or over/under budget • Answers: “How much value have we earned for the money spent? © 2024 Association for Project Management 6
  • 7.
    Introduction - WhyUse Earned Value? • Gives a quick*, structured snapshot of project progress • Highlights if a project is on time and on budget • Flags overspend or delays early so action can be taken • Makes performance easy to track and communicate • Supports resource planning and package-level control • Widely used in work package management and formal reporting © 2024 Association for Project Management 7
  • 8.
    Key Concepts andTerminology There are various terms used in the calculation and interpretation of Earned Value. These are the main ones you’ll come across: PV (BCWS) – Planned Value (This is the Budgeted Cost of Work Scheduled) The authorized budget assigned to the scheduled work Calculated as Planned %age complete x budget. EV (BCWP) – Earned Value (This is the Budgeted Cost of Work Performed). The value of work actually preformed, expressed in terms of approved budget Calculated as Actual %age complete x overall budget. AC (ACWP) – Actual Cost (This is the Actual Cost of Work Performed) The actual cost on the project (or Work Package) to date. Cost Variance (CV) = EV – AC if CV is positive, we are under budget Schedule Variance (SV) = EV – PV if SV is negative, we are behind schedule © 2024 Association for Project Management 8 Note: Accurate and consistent measurement of %age complete and actual cost is important if we want to derive meaningful metrics
  • 9.
    Key Performance Indicators Thesemeasures can be used to produce some useful indicators. CPI - Cost Performance Index Derived by dividing EV by AC = EV/AC or BCWP/ ACWP >1.00 means the project is under budget; <1.00 means the project is over budget. SPI - Schedule Performance Index Derived by dividing EV by PV or BCWP/ BCWS >1.00 means the project is ahead of schedule; <1.00 means the project is behind schedule. CPI and SPI allow for early identification of potential project overruns or delays. © 2024 Association for Project Management 9
  • 10.
    Core Components ofEVM These are few of the structural and procedural elements to implement EVM effectively. 1. Work Breakdown Structure (WBS) – A hierarchical decomposition of the total scope of work to accomplish project objectives 2. Integrated Baseline – Combines scope, schedule and cost baselines to measure performance 3. Performance Measurement Baseline (PMB) – The time phased budget plan against which project performance is measured. 4. Data Collection and Reporting - Regular tracking of PV, EV, and AC to assess progress. 5. Forecasting - Using current data to predict future project outcomes (e.g., EAC, Estimate to Complete). © 2024 Association for Project Management 10
  • 11.
    Calculating Earned Value AssumeProject A with an overall budgeted cost (BC) of £75000 At this point, progress %age complete has been calculated as 10%. Actual cost has been recorded as £5000, and budgeted cost at this point (BCWS) is £7000. EV = 10% X 75000 = £7500 AC = £5000 PV = £7000 CV = EV-AC = 7500 – 5000 = £2500 SV = EV-PV = 7500 – 7000 = £ 500 CPI = EV/AC = 7500 / 5000 = 1.5 SPI = EV/ PV = 7500 / 7000 = 1.07 You can calculate ‘Estimate At Completion’ by diving project budget by the CPI = BC / CPI = £75000 / 1.5 = £50000 Hence, if you have a CPI of 1.5 your Estimate at Completion (EAC) is going to be under budget © 2024 Association for Project Management 11
  • 12.
    Trend Curve Over time,it can be extremely useful to monitor trends and understand how current project performance compares to planned performance. • Shows how project performance evolves over time • Helps spot patterns, not just isolated issues • Reveals if variances are short-term blips or ongoing trends • Supports more accurate forecasting and planning © 2024 Association for Project Management 12
  • 13.
    EV Trend Analysis However,it is more helpful to understand Earned Value trend as this could help to predict problems © 2024 Association for Project Management 13
  • 14.
    But…be Cautious What’s needed: •A baselined schedule and budget • A consistent way to measure progress • Accurate, timely data (not best guesses) Common pitfalls: • Relying on inconsistent or poor-quality inputs • Misinterpreting metrics in isolation (e.g. CPI looks good, but SPI is tanking) • Treating EVM as a “tick-box” or just a maths exercise • Reporting progress based on optimism, not evidence © 2024 Association for Project Management 14
  • 15.
    Challenges • Requires accurateand timely data collection • Needs robust baselines for both schedule and budget to produce meaningful results • Can be complex to implement and maintain, especially on large or fast-moving projects • Relies on consistent progress measurement and reliable data inputs • May face resistance from teams unfamiliar with EVM or unsure how to use it • Demands consistent application across all phases of the project to be effective © 2024 Association for Project Management 15
  • 16.
    Benefits • Provides anobjective snapshot of both cost and schedule performance • Key performance indicators like CPI and SPI enable early detection of potential overruns or delays • Tracking trends in ACWP, BCWS, and BCWP helps predict issues before they escalate • Helps identify resource inefficiencies and areas needing corrective action • Trends show current project performance and also help forecast future risks, improving decision- making • Enhances communication among project stakeholders • Improves overall project planning and control © 2024 Association for Project Management 16
  • 17.
    Quick Quiz –Maths time ☺ © 2024 Association for Project Management 19 • Project Budget: £100,000 • At halfway point: • EV = £40,000 • AC = £60,000 Question: • What’s your CPI? • What does it tell you?
  • 18.
    Quick Quiz -Myth or Fact? © 2024 Association for Project Management 20 1. If CPI > 1.0, your project is under budget 2. Earned Value (EV) is the same as Actual Cost (AC) 3. A Schedule Performance Index (SPI) of 0.8 means you’re ahead of schedule 4. Earned Value Management is only useful at the end of a project 5. The formula for CPI is: EV divided by AC 6. You can use EVM effectively without a baselined schedule 7. You can change the method of assessing % complete on a project without changing baseline
  • 19.
    Quick Quiz –What would you do? © 2024 Association for Project Management 21 You’re reviewing a monthly report. • CPI = 1.2 (under budget) • SPI = 0.75 (significantly behind schedule) Question: What would you do? a) Celebrate the cost performance b) Re-baseline the project c) Investigate the delay and replan if needed
  • 20.
    ISO Standard forEarned Value Management (EVM) - ISO 21508:2018 This standard provides guidance on the principles and practices of Earned Value Management (EVM) within the context of project and programme management. It is applicable to any organization—public or private, regardless of size or sector—and to any type of project or programme. ISO 21508:2018 includes: • Terms and definitions relevant to EVM. • Purpose and benefits of using EVM. • Integration of EVM with broader project or programme management practices. • Process descriptions and an overview of EVM processes. • Basic requirements for an EVM system. • Guidance on using an EVM system effectively. © 2024 Association for Project Management 22 Title - Earned value management in project and programme management
  • 21.
    Project Controls in21st Century © 2024 Association for Project Management 23 Project Controls in the 21st Century APM members can claim 10% discount on hardback and paperback publications by using code APMMEM10 at checkout. Plus, FREE member digital copy downloads on named titles.
  • 22.
    © 2024 Associationfor Project Management 24 Thank you, next steps or any questions? by Behnam Sarani & Manish Khanna Project Director & Deputy HPPM & Project Controls Manager [email protected]