Integrating BIM and LEAN for Project Delivery
Construction of a Major Hospital in Jordan.
1
2
Who We Are
• Top 22nd ENR int. Contractors
• High safety and environment
consciousness.
• Operates in all continents mainly
• in MEA
• Around 6 B revenues
• Around 150K employees
• Around 1 B construction machineries.
Who We Serve
Heavy Civil
Process Plant
Oil and Gas
Infrastructure and Networks
Road and Bridges
Buildings
Pipelines
Introduction to CCC
Level1
Level6
Level5
Level4
Level3
Level2
PaymentEvaluation
WeeklyScheduleUpdate
MasterPlanning
SeniorManagementReports
Level7
Cut
20%
Assemble/Tack
45%
ShopWeld
35%
FabricatePipework
56.2%
Fabricate
60%
Install
40%
FabErec.P.Support
8.2%
FabricateEquipmentPipework
23.83%
FabricateRackPipework
7.64%
PipeFabrication
23%
PipeInstallation
26%
EquipmentErection
7%
ProcessAreas
44.7%
Offsites&Utilities
20.4%
CommBuildingandShelters
5.9%
MainPlant
86%
AreaB
6%
Pipelines
8%
Project
King Hussein Cancer Centre Project
Project Controls/ Room Completion System
3
KHCC Scope of Work
The project includes Architectural
Finishes and MEPPackages.
The project duration is 730calendardays
commencing 1st April 2014
The current workforce is 850persons
and more than 40sub-contractors
The Hospital consists of 182roomsand is
comprised of two towers 10 and 12
floors above ground floor sharing the
ground floor and three basement floors
with an approximate total built-up area
of 84,360squaremetres.
4THE JOINT VENTURE OF CONSOLIDATED CONTRACTORS GROUP (OFFSHORE) (CCC) AND HADDADIN ENGINEERING COMPANY FOR CONTRACTING
5
Challenges
• Relatively small projects with high
complexity
• A hospital by definition:
• Many systems
• Multiple room configurations
• A lot of specialties and subcontract
• Utilize CCC Project Controls Strategy:
• Hybrid system of BIM/AWP/Lean
techniques
• Fast track Finishing / Handover phase of
hospital
Project Control Strategy
• Reliant Pull-Driven Technique optimize supply chain rather than sub optimization
• Assure availability of resources before start of activity.
• Emphasize productivity through the full work chain vs. individual activities
• Prevent sub-optimization
• Partnering
• Standardized Project Work Breakdown Structure
• Project/Area/SubArea/Fragnet/Activity/Object/Operation
• Integrated EPC schedule with Emphasis on Handover and Construction Activities. (effective
supply chain)
• 3D model built with WBS in mind and used as primary scope management tool.
• Early on Cooperation with the Partners/ EDI definition.
• 3 Month Look Ahead Schedule/ Material forward plan
• 3 week Look Ahead Schedule
7
WBS
BIM
scope of
work
Fragnet
templates
FEL
3 Week
Look
Ahead
Work
order
QC &
Punch
listing
Invoice
Room completion system is based on integrated set of methodologies
8
Work Breakdown Structure - WBS
It is a deliverable oriented hierarchy for a project that would
organize the project’s team work into manageable sections.
9
Building project’s WBS
Project
Area1
Sub-area1
Fragnet 1 Fragnet 2
Activity 1
Object1 Object2
Operation1 Operation2
Object3 Object4
Activity 2 Activity 3
Fragnet 3 Fragnet 4
Area2
Sub-area3 Sub-area3 Sub-area4
Level 1
Level 2
Level 3
Level 4
Level 5
Level 6
Level 7
Level 1 - KHCC Construction
Level 2 - Area Location: Building1&2, Building Facades, Roof Works, External Works and Generator Building.
Level 3 - Zone Level: Floor Plans at specified Levels and Areas, Stairs, Shafts, Elevators, External areas.
Level 4 – Phase/Fragnet: Structural, Open space, finishing, building envelope, etc.
Level 5 - Activity: Unique Activity ID from Primavera
Level 6 - Object: Objects tagged as per BIM authoring
Level 7 - Operation: Operation templates as per object type and method statement (Work of One Crew)
WBS Implementation
10
11
Building Information Modelling - BIM
It is an intelligent 3D model based process that would provide a control
tools for all project’s stakeholders during the project life.
WBS
BIM
Standardized BOQs as scope measurement
12
• Define BOQ, the basic way of measuring content
of work
• Identify measurement methodology using any of
the international standards such as SMM 7, RIC’s,
etc…
• A BIM model is developed based on the tender
documents and specification using BOQ and
standardized WBS.
• Full MTO (Material Take-Off) is extracted from
the BIM model detailed to the BOQ level. The
MTO is linked to CCC estimation software where
pricing is developed using crew-based
estimation.
09210: Plastering ORIGINAL
QTY BIM QTY
9/1/1 1- Supply and applying sand / cement
exposed plastering layer for internal walls,
composed ofbase and finish coats. The work
includes spatter, wire mesh at the joints
betweenwalls and columns and allaccessories
for complete work accordingto specifica m2
64,548 57,200.50
09310: Porcelain & Ceramic Tiles:
2- Supply, delivery and install non-slippery
Prcelain tiles for floors of toilets, bathrooms,
pantry, terraces, cafeteria and kitchens;
according to the finish schedule, approved
samples, pattern, shop drawings and
specifications. The work includes scree
9/2/1 30 x30 x0.90 cm(R-PTNS-2) m2
1,156 1110.25
9/2/2 25 x25 x0.90 cm(O-PTNS-1&2) m2
1,349 1360.3
9/2/3 15 x15 x0.90 cm(O-PT-1) m2
1,349 1360.3
9/2/4 10 x10 x0.70 cm(R-PTNS-1) m2
963 720
9/2/5 40 x 40 x 0.90 cm and pattern as per
drawings for Cafeteria (PTCa). m2
212 210
9/2/6 Ditto for Terraces ofappartments (PTTR). m2
1,927 1875
Object naming: WBS/naming conventions/asset tagging
KHCC B1 F-9 HVAC Duct
installation
Dct001 fabrication
Project Building Floor Discipline
P6-
Activity
Object s/n Operation
KHCC-B1-F9-HVAC-Dct001
Project
WBS
BIM TAG
Member
Mark
Unique member mark
Required integrations using the modelled objects
14
BIM Authoring
BOQ
Qty &
Specs.
Primavera
Activity
QC ITP
Estimation and
Budgeting
Object Tag /
OperationActivity ID BOQ code
Cost code
Category code
Resources
Manhours
Equipments
Material
Room numbering
Room Type Colorization
The figure shows rooms located at Floor 9, Area 2. Rooms are colorized based on their type defined in the color legend.
16
Electrical systems identifications
The Cable Trays and
Trunks are modeled
as shown on the side
figure.
The cables are
identified and
colorized based on
the feeding system as
given in the legend.
17
Mechanical systems identification
Mechanical Systems are identified and given a color based on their type.
1818
System identification per room
Intersection between room
and systems are identified:
- Duct Accessories
- Duct Fittings
- Ducts
- Flexible Ducts
- Mechanical Equipment's,
such as FCU, TU, FSD, VD,
..etc.
- Pipes (Includes Drain
Pipes, HVAC Pipes,
Medical Pipes). The Tag
Name can classify the
pipes subsystem.
- Pipe Fittings
19
20
WBS
BIM
S/C
scope of
work
Coordination between Subcontractors
Subcontractor Scope Management
Have an EDI agreement with the sub-contractor
List the subcontractors and their BOQ items
Analyze the subcontracted scope of work related to a section or volume of the model
link in between the drawings/documents and the sub-contractors scope of work
Visualize the construction schedule of one or more subcontractors in a Gantt Chart
Link the sub-contractors operations to fragnets and clearance forms for coordination
 Provide QC inspections, and punch listing for S/C work
 Provide clearance forms to control the relation of the S/C with others
 Subcontractor Invoice checking based on Earned value
EDI agreement with the sub-contractor
Electronic Data Interface meetings are to be done with the sub-contractor to
agree on:
1- Model format coming from the S/C
2- Model Level of detail (LOD)
2- Naming conventions and tagging
3- Data and documents related to the objects/model
4- Update frequency for the data and change management
Defining sub-contractors’ scope graphically and their related BOQ
Adding/removing
subcontractors
BOQ per Subcontractor
Assigned Objects per
subcontractor
24
Fragnets:
Templates of operations in sequence to
complete a room
WBS
BIM
Subcontractors
scope
definition and
coordination
Fragnet
templates
Building the sequence of work as a Fragnet per room type. The sequence of work rely on:
Lean Principles
Sequence of Works (finishing & MEP systems within rooms)
25
26
List of 26 operations for different disciplines within a room
Level 7 Operation link to QC Form
27
Front End Loading - FEL
WBS
BIM
S/C
scope of
work
Fragnet
templates
FEL
FEL (Front End Loading): is the process of checking and preparing of the execution
elements that are required to consider a work front as an open front (Usually on
the Zone/Fragnet Level)
 The check list should include the following:
 Material
 Engineering
 PMV
 HSE
 QCPs
 Accessibility
 HR
 etc..
 FEL main topics per different disciplines
within the work front
 service departments
 Flag as 3M or 3W
 ETA dates
 Status
Front End Loading (FEL)
30
FEL Checklist form sample
31
Identify the open front
The subcontractor is allowed to start work at the selected green area which are designated as Open Front. The highlighted
boundaries in brown are still not ready to start works.
32
- Target Progress from Schedule
- Objects/Operations and their relative weights per Activity with
their MTO
- Crew Availability and their capacities
- Required QC Forms at completion of operations
- FEL to assure availability of drawings, material, procedures, etc.
- Weekly Meetings on Site to validate progress and plan the next
3 weeks (Generate Workorders)
To be ready for the 3 Week Look Ahead Schedule
Weekly Assignment per Crew
WBS
BIM
S/C
scope of
work
Fragnet
templates
FEL
3 Week
Look
Ahead
Site Planning – 3 weeks Look Ahead (Old)
33
34
Lean Site Planner
35
Weekly Three Week Look-Ahead Report (Sample on Period 86)
36
Crew Availability
37
WBS
BIM
S/C
scope of
work
Fragnet
templates
FEL
3 Week
Look
Ahead
Work
order
Work order and progress registry
Digital Pen form
Digital Pen based form work order
40
Room Type Progress Colorization
The Room types are colorized based on their progress. The colors in the legend gives the range of progress percentages.
C3D Progress Colorization By System
C3D colorization method can visualize the actual progress percentage on each system.
41
42
C3D and Subcontractor Progress (per system)
A list of subcontractors with systems related and percentage of progress in colors
C3D and Subcontractor Progress (Per room finishing)
The Floor
Finishes are
illustrated in the
figure presenting
overall progress
on each room
type.
We can allocate
the
responsibilities of
each
subcontractor on
each floor and
observe actual
progress.
43
Standard progress reports
45
QC forms and RFI tracking
WBS
BIM
S/C
scope of
work
Fragnet
templates
FEL
3 Week
Look
Ahead
Work
order
QC &
Punch
listing
C3D Atlas - Room Completion
RoomQCchecklist
Atlasallow:
 TrackingtheAFI
 BuildingQCscope
 Documentprogress
 Handingoverdossier
46
47
C3D Atlas - System Progress Tracking
The selected system on each floor are tracked and followed depending on their ITP’s and form status. This will allow better
operational sequence for the Testing and Commissioning Plan.
48
Punch list forms per rooms and subcontractors
49
Subcontractors Progress and Invoice checking
WBS
BIM
S/C
scope of
work
Fragnet
templates
FEL
3 Week
Look
Ahead
Work
order
QC &
Punch
listing
Invoice
Contractor BOQ Items
Earned Value Calculations
×
51THE JOINT VENTURE OF CONSOLIDATED CONTRACTORS GROUP (OFFSHORE) (CCC) AND HADDADIN ENGINEERING COMPANY FOR CONTRACTING
C3D Planner Cost Loading
Activity Percentage
Completion
Budgeted Cost & rules of
credits per Operations
Total Earned Value for Activity
EV Reporting per WBS
Plan + Budget + contract
Earned Values calculations per Subcontractors
52
ACTIVITY
ID
ZONE
LEVEL
DISCIPLINE (SYSTEM/
SUBSYSTEM)
ACTIVITY ID
DESCRIPTION
SUB-CONTRACTOR
ACTUAL
START
ACTUAL
FINISH
BUDGETED
UNITS %
COMPLETE
COST %
COMPLETE
UNITS
DONE
THIS
PERIOD
ACTUAL
LABOUR
UNITS
BUDGETED
LABOUR
UNITS
ACTUAL
COST
BUDGETED
COST
PRIORIT
Y
ORDER
09A2-MF010 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
INSTALL SPRINKLERS PIPE NETWORK
ULTRA CONTRACTING
COMPANY
27-Oct-14 1-Oct-15 100.00% 100.00% 0 93 93 JOD 8,410.97 JOD 8,410.97 01
09A2-MF020 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
INSTALL H.R.C PIPE NETWORK
ULTRA CONTRACTING
COMPANY
3-Nov-14 2-Sep-15 100.00% 100.00% 0 66 66 JOD 8,410.97 JOD 8,410.97 02
09A2-MF120 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
INSTALL LANDING VALVES FOR FIRE
FIGHTING
ULTRA CONTRACTING
COMPANY
19-May-15 30-Jan-16 95.00% 95.00% 0 6 6 JOD 7,990.42 JOD 8,410.97 03
09A2-MF030 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
PREPARE LOCATION FOR H.R.C
ULTRA CONTRACTING
COMPANY
27-Jun-15 8-Jul-15 100.00% 100.00% 0 21 21 JOD 8,410.97 JOD 8,410.97 04
09A2-MF050 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
INSTALL VALVES FOR FIRE FIGHTING
NETWORK
ULTRA CONTRACTING
COMPANY
21-Oct-15 26-Oct-15 100.00% 100.00% 0 21 21 JOD 8,410.97 JOD 8,410.97 05
09A2-MF060 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
INSTALL SPRINKLERS
ULTRA CONTRACTING
COMPANY
10-Feb-16 20-Feb-16 0.00% 0.00% 0 0 96 JOD 0.00 JOD 4,205.48 06
09A2-MF040 A2-L09
MECHANICAL/ FIRE FIGHTING
SYSTEM
INSTALL H.R.C CABINET AND
ACCESSORIES
ULTRA CONTRACTING
COMPANY
20-Feb-16 3-Mar-16 0.00% 0.00% 0 0 6 JOD 0.00 JOD 8,410.97 07
09A2-MH130 A2-L09 MECHANICAL/ HVAC SYSTEM
INSTALL H/C WATER BLACK STEEL
HVAC PIPES
ISAM MA'ZOOZ
CONTRACTING
30-Oct-14 14-Oct-15 100.00% 100.00% 0 125 125 JOD 8,410.97 JOD 8,410.97 01
09A2-MH080 A2-L09 MECHANICAL/ HVAC SYSTEM
INSTAL FCU AND TERMINAL UNITS
(TU)
ISAM MA'ZOOZ
CONTRACTING
17-Mar-15 2-Nov-15 100.00% 100.00% 0 84 84 JOD 8,410.97 JOD 8,410.97 02
09A2-MH140 A2-L09 MECHANICAL/ HVAC SYSTEM
INSTALL VALVES AND MEASURING
DEVICES FOR HVAC
ISAM MA'ZOOZ
CONTRACTING
9-Dec-15 17-Dec-15 0.00% 0.00% 0 0 42 JOD 0.00 JOD 8,410.97 03
09A2-MH090 A2-L09 MECHANICAL/ HVAC SYSTEM CONNECT FCU AND TU WITH PIPE
ISAM MA'ZOOZ
CONTRACTING
23-Dec-15 6-Jan-16 0.00% 0.00% 0 0 84 JOD 0.00 JOD 8,410.97 04
09A2-MH020 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL VAV DUCT QASRAWI DUCTING 30-Oct-14 29-Sep-15 100.00% 100.00% 0 60 60 JOD 8,410.97 JOD 8,410.97 01
09A2-MH010 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL CAV DUCT QASRAWI DUCTING 30-Oct-14 29-Sep-15 100.00% 100.00% 0 60 60 JOD 8,410.97 JOD 8,410.97 02
09A2-MH100 A2-L09 MECHANICAL/ HVAC SYSTEM CONNECT FCU AND TU WITH DUCT QASRAWI DUCTING 19-Sep-15 8-Oct-15 100.00% 100.00% 0 84 84 JOD 8,410.97 JOD 8,410.97 03
09A2-MH050 A2-L09 MECHANICAL/ HVAC SYSTEM
INSTALL VOLUME DAMPER WITH
ACCESSORIES
QASRAWI DUCTING 1-Oct-15 3-Oct-15 100.00% 100.00% 0 42 42 JOD 8,410.97 JOD 8,410.97 04
09A2-MH120 A2-L09 MECHANICAL/ HVAC SYSTEM
INSTALL FLEXIBLE DUCT AND
DIFFUSERS
QASRAWI DUCTING 19-May-15 27-Feb-16 35.00% 35.00% 0 29 84 JOD 2,943.84 JOD 8,410.97 05
09A2-MG010 A2-L09
MECHANICAL/ MEDICAL GAS
SYSTEM
INSTALL COPPER PIPE NETWORK FOR
M.GAS
ITS 2-Sep-15 5-Nov-15 100.00% 100.00% 0 90 90 JOD 8,410.97 JOD 8,410.97 01
09A2-MG020 A2-L09
MECHANICAL/ MEDICAL GAS
SYSTEM
INSTALL VALVES & FITTINGS ITS 2-Nov-15 10-Nov-15 100.00% 100.00% 0 37 37 JOD 8,410.97 JOD 8,410.97 02
09A2-MG030 A2-L09
MECHANICAL/ MEDICAL GAS
SYSTEM
INSALL MEDICAL GAS ALARM PANELS ITS 14-Nov-15 17-Nov-15 100.00% 100.00% 0 22 22 JOD 8,410.97 JOD 8,410.97 03
09A2-MG040 A2-L09
MECHANICAL/ MEDICAL GAS
SYSTEM
INSTALL GAS OUTLETS ITS 6-Mar-16 20-Mar-16 0.00% 0.00% 0 0 7 JOD 0.00 JOD 8,410.97 04
Weekly Budgeted Cost Progress Report (Sample on Period 87)
53
54
Thank you
Zuhair Haddad
zuhair@ccc.me
CCT – Booth 8

More Related Content

PPTX
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
PDF
Project Scheduling & Controls
Procept Associates
 
PPTX
Qaqc in civil construction
kaladharan pillai
 
DOCX
Bills of quantities
Ar.Vijay Kumar
 
PDF
Construction Contract in Malaysia
Dayat Mohamad
 
PDF
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
PPTX
Professional practice 2
ahmong4
 
PPTX
Estimation and costing of a commercial building
lckr117
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Project Scheduling & Controls
Procept Associates
 
Qaqc in civil construction
kaladharan pillai
 
Bills of quantities
Ar.Vijay Kumar
 
Construction Contract in Malaysia
Dayat Mohamad
 
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Professional practice 2
ahmong4
 
Estimation and costing of a commercial building
lckr117
 

What's hot (20)

PDF
SMM7 Bill of Quantities
Natalie Reid
 
PPTX
Construction Documents
Allan Berry
 
PDF
Professional Practice 1 Group Assignment
Haziq1511
 
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
PPTX
QUANTITY SURVEYING
lizwi nyandu
 
PDF
03 e measurement book-ver-1.0
Amulie Jarjusey
 
DOCX
Civil Engineering Measurment
Sultan M Muzahir
 
PPTX
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
PDF
Quantity surveying drawing FNBE 2014
Felix Vong
 
PPTX
Types of Contract in Construction Management
Shahin MB
 
PDF
Quantity surveying practise
Sasi Cool
 
PDF
Value Management Group Assignment
Arissa Loh
 
DOC
MMC Revision Notes
CKMCforstudents
 
PPT
Quality in Construction
Dr K M SONI
 
PPTX
Sgp4813 measurement of quantities
alanchong88
 
PDF
Assignmenr for pp2 final account
ahmong4
 
PPT
3. construction planning. construction project management
Kabilan Kabi
 
PDF
Pp2 assignment-final
ashleyyeap
 
PDF
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Shrikant Kate
 
PDF
CIDA SBD 02.pdf
Ruwan Sampath Wickramathilaka
 
SMM7 Bill of Quantities
Natalie Reid
 
Construction Documents
Allan Berry
 
Professional Practice 1 Group Assignment
Haziq1511
 
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
QUANTITY SURVEYING
lizwi nyandu
 
03 e measurement book-ver-1.0
Amulie Jarjusey
 
Civil Engineering Measurment
Sultan M Muzahir
 
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
Quantity surveying drawing FNBE 2014
Felix Vong
 
Types of Contract in Construction Management
Shahin MB
 
Quantity surveying practise
Sasi Cool
 
Value Management Group Assignment
Arissa Loh
 
MMC Revision Notes
CKMCforstudents
 
Quality in Construction
Dr K M SONI
 
Sgp4813 measurement of quantities
alanchong88
 
Assignmenr for pp2 final account
ahmong4
 
3. construction planning. construction project management
Kabilan Kabi
 
Pp2 assignment-final
ashleyyeap
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Shrikant Kate
 
Ad

Viewers also liked (20)

PPT
The Information Challenge Managing Construction with BIM
CCT International
 
PDF
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
Rodger McKinley
 
PDF
Make BIM work for you
CCT International
 
PDF
5 Things You Should Be Doing on LinkedIn
LinkedIn for Small Business
 
PPSX
Внедрение BIM в проектных организациях: цели и задачи
Tanya Gadzevych
 
PPTX
Сроки. Ошибки. Стоимость. BIM технологии в помощь руководителям
RnD_SM
 
PDF
Changing the Paradigm Rivers of Information instead of data warehousing
Capgemini
 
PPTX
Contractors: Get BIM Ready!
CCT International
 
PPTX
Radiation and malignancy
Belal El Hawwari
 
PDF
Lean in Hospitals - Lean Transformation in Gwent
Lean Enterprise Academy
 
PPSX
Преимущества и возможности проектирования разделов ОВ и ВК в BIM среде средст...
Tanya Gadzevych
 
PDF
Автоматизация деятельности на основе BIM технологий
КРОК
 
PPT
DCF vs ECF in gastric cancer
Prof. Ahmed Mohamed Badheeb
 
PPTX
Turppp
anas derbashi
 
PPSX
Autodesk: Облачные сервисы в проектном бюро и на стройке
Tanya Gadzevych
 
PPTX
Fiatech 2014 - Big BIM Implementation, Zuhair Haddad
CCT International
 
PDF
Bim support services
HariomSharan
 
PDF
Почему ССС ?
Leon Lunsky
 
PDF
BIM, 4D, Synсhro. Вводная презентация семинара в Москве 19 ноября 2012
Alexey Zotov
 
The Information Challenge Managing Construction with BIM
CCT International
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
Rodger McKinley
 
Make BIM work for you
CCT International
 
5 Things You Should Be Doing on LinkedIn
LinkedIn for Small Business
 
Внедрение BIM в проектных организациях: цели и задачи
Tanya Gadzevych
 
Сроки. Ошибки. Стоимость. BIM технологии в помощь руководителям
RnD_SM
 
Changing the Paradigm Rivers of Information instead of data warehousing
Capgemini
 
Contractors: Get BIM Ready!
CCT International
 
Radiation and malignancy
Belal El Hawwari
 
Lean in Hospitals - Lean Transformation in Gwent
Lean Enterprise Academy
 
Преимущества и возможности проектирования разделов ОВ и ВК в BIM среде средст...
Tanya Gadzevych
 
Автоматизация деятельности на основе BIM технологий
КРОК
 
DCF vs ECF in gastric cancer
Prof. Ahmed Mohamed Badheeb
 
Autodesk: Облачные сервисы в проектном бюро и на стройке
Tanya Gadzevych
 
Fiatech 2014 - Big BIM Implementation, Zuhair Haddad
CCT International
 
Bim support services
HariomSharan
 
Почему ССС ?
Leon Lunsky
 
BIM, 4D, Synсhro. Вводная презентация семинара в Москве 19 ноября 2012
Alexey Zotov
 
Ad

Similar to Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospital in Jordan. (20)

PDF
The Future is Now (5th BIM and Lean Conference 2017)
CCT International
 
PPTX
6.0 CURT CII - Digital Transformation of Construction Industry
CCT International
 
PPTX
Digital Transformation of the Construction Industry
CCT International
 
PPTX
BIM Based Project Controls
CCT International
 
PPTX
MelBIM 190619
Nick Rostin
 
PPTX
Mandated BIM! Are you ready?
CCT International
 
PPTX
Designing to Enhance Construction Planning & Monitoring
CCT International
 
PDF
11.30 uur thomas vandenbergh - uitdagingen bij de introductie van bim binne...
Muriel Walter
 
PDF
Aleks Baltovski
Informa Australia
 
PDF
BIM for Interior Design
Jeff Hong
 
PDF
06Class_Presentation_AS463561.pdf
ssusere16b3b
 
PPTX
BIM In Practice Seminar
CCT International
 
PPT
Sustainability In Government - Bim Webinar
4 All of Us
 
PPT
BIM and digitalization: how to convert these challenges in great chances for ...
ANDECE
 
PDF
Deakin:OU Legacy Proposal
Kieran Maguire
 
PPTX
Building information modeling BIM
fitsum yonas
 
PDF
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
CCT International
 
PDF
Paul Nunn
Informa Australia
 
PPTX
My Lean + BIM Journey [Nathan Wood, Brazil Lean Conference]
Nathan C. Wood
 
PPTX
Technische Universität München November 2014
Neil Marshall
 
The Future is Now (5th BIM and Lean Conference 2017)
CCT International
 
6.0 CURT CII - Digital Transformation of Construction Industry
CCT International
 
Digital Transformation of the Construction Industry
CCT International
 
BIM Based Project Controls
CCT International
 
MelBIM 190619
Nick Rostin
 
Mandated BIM! Are you ready?
CCT International
 
Designing to Enhance Construction Planning & Monitoring
CCT International
 
11.30 uur thomas vandenbergh - uitdagingen bij de introductie van bim binne...
Muriel Walter
 
Aleks Baltovski
Informa Australia
 
BIM for Interior Design
Jeff Hong
 
06Class_Presentation_AS463561.pdf
ssusere16b3b
 
BIM In Practice Seminar
CCT International
 
Sustainability In Government - Bim Webinar
4 All of Us
 
BIM and digitalization: how to convert these challenges in great chances for ...
ANDECE
 
Deakin:OU Legacy Proposal
Kieran Maguire
 
Building information modeling BIM
fitsum yonas
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
CCT International
 
My Lean + BIM Journey [Nathan Wood, Brazil Lean Conference]
Nathan C. Wood
 
Technische Universität München November 2014
Neil Marshall
 

More from CCT International (20)

PDF
BIM, Lean & Advanced Work Packaging - How do they fit together?
CCT International
 
PPTX
Adding Intelligence to AWP
CCT International
 
PPTX
Leveraging C3D® to Ensure Compliance of Site Execution Teams
CCT International
 
PDF
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
CCT International
 
PDF
Roads, Infrastructure and BIM
CCT International
 
PPTX
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
CCT International
 
PDF
IBM Case Study of Maximo Implementation at CCC
CCT International
 
PPTX
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
CCT International
 
PDF
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
CCT International
 
PPTX
Asset Management - Bridging Boundaries in Ongoing Asset Management
CCT International
 
PPTX
Imagine a World Without Isometric
CCT International
 
PPTX
Advanced Work Packaging (AWP) - Reduction to Practice
CCT International
 
PPTX
Smart Construction Site
CCT International
 
PPTX
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
CCT International
 
PPTX
Digital Pens - Firas Hijazi - FIATECH and COMIT
CCT International
 
PPTX
Advanced Work Packaging - CCT Solutions at a Glance
CCT International
 
PPTX
Advanced Work Packaging - Real Life Implementation
CCT International
 
PDF
Top 10 BIM Tips for Contractors
CCT International
 
PPTX
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
CCT International
 
PPTX
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
CCT International
 
BIM, Lean & Advanced Work Packaging - How do they fit together?
CCT International
 
Adding Intelligence to AWP
CCT International
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
CCT International
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
CCT International
 
Roads, Infrastructure and BIM
CCT International
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
CCT International
 
IBM Case Study of Maximo Implementation at CCC
CCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
CCT International
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
CCT International
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
CCT International
 
Imagine a World Without Isometric
CCT International
 
Advanced Work Packaging (AWP) - Reduction to Practice
CCT International
 
Smart Construction Site
CCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
CCT International
 
Digital Pens - Firas Hijazi - FIATECH and COMIT
CCT International
 
Advanced Work Packaging - CCT Solutions at a Glance
CCT International
 
Advanced Work Packaging - Real Life Implementation
CCT International
 
Top 10 BIM Tips for Contractors
CCT International
 
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
CCT International
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
CCT International
 

Recently uploaded (20)

PDF
The Effect of Artifact Removal from EEG Signals on the Detection of Epileptic...
Partho Prosad
 
PDF
Introduction to Ship Engine Room Systems.pdf
Mahmoud Moghtaderi
 
PDF
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
PPTX
Tunnel Ventilation System in Kanpur Metro
220105053
 
PDF
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
PPTX
Information Retrieval and Extraction - Module 7
premSankar19
 
PDF
Zero Carbon Building Performance standard
BassemOsman1
 
PPTX
22PCOAM21 Session 1 Data Management.pptx
Guru Nanak Technical Institutions
 
PDF
Software Testing Tools - names and explanation
shruti533256
 
PDF
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
PPTX
Chapter_Seven_Construction_Reliability_Elective_III_Msc CM
SubashKumarBhattarai
 
PDF
2025 Laurence Sigler - Advancing Decision Support. Content Management Ecommer...
Francisco Javier Mora Serrano
 
PDF
Cryptography and Information :Security Fundamentals
Dr. Madhuri Jawale
 
PPTX
22PCOAM21 Session 2 Understanding Data Source.pptx
Guru Nanak Technical Institutions
 
PDF
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
PPTX
business incubation centre aaaaaaaaaaaaaa
hodeeesite4
 
PPTX
IoT_Smart_Agriculture_Presentations.pptx
poojakumari696707
 
PPTX
Civil Engineering Practices_BY Sh.JP Mishra 23.09.pptx
bineetmishra1990
 
PDF
flutter Launcher Icons, Splash Screens & Fonts
Ahmed Mohamed
 
PPT
SCOPE_~1- technology of green house and poyhouse
bala464780
 
The Effect of Artifact Removal from EEG Signals on the Detection of Epileptic...
Partho Prosad
 
Introduction to Ship Engine Room Systems.pdf
Mahmoud Moghtaderi
 
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
Tunnel Ventilation System in Kanpur Metro
220105053
 
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
Information Retrieval and Extraction - Module 7
premSankar19
 
Zero Carbon Building Performance standard
BassemOsman1
 
22PCOAM21 Session 1 Data Management.pptx
Guru Nanak Technical Institutions
 
Software Testing Tools - names and explanation
shruti533256
 
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
Chapter_Seven_Construction_Reliability_Elective_III_Msc CM
SubashKumarBhattarai
 
2025 Laurence Sigler - Advancing Decision Support. Content Management Ecommer...
Francisco Javier Mora Serrano
 
Cryptography and Information :Security Fundamentals
Dr. Madhuri Jawale
 
22PCOAM21 Session 2 Understanding Data Source.pptx
Guru Nanak Technical Institutions
 
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
business incubation centre aaaaaaaaaaaaaa
hodeeesite4
 
IoT_Smart_Agriculture_Presentations.pptx
poojakumari696707
 
Civil Engineering Practices_BY Sh.JP Mishra 23.09.pptx
bineetmishra1990
 
flutter Launcher Icons, Splash Screens & Fonts
Ahmed Mohamed
 
SCOPE_~1- technology of green house and poyhouse
bala464780
 

Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospital in Jordan.

  • 1. Integrating BIM and LEAN for Project Delivery Construction of a Major Hospital in Jordan. 1
  • 2. 2 Who We Are • Top 22nd ENR int. Contractors • High safety and environment consciousness. • Operates in all continents mainly • in MEA • Around 6 B revenues • Around 150K employees • Around 1 B construction machineries. Who We Serve Heavy Civil Process Plant Oil and Gas Infrastructure and Networks Road and Bridges Buildings Pipelines Introduction to CCC Level1 Level6 Level5 Level4 Level3 Level2 PaymentEvaluation WeeklyScheduleUpdate MasterPlanning SeniorManagementReports Level7 Cut 20% Assemble/Tack 45% ShopWeld 35% FabricatePipework 56.2% Fabricate 60% Install 40% FabErec.P.Support 8.2% FabricateEquipmentPipework 23.83% FabricateRackPipework 7.64% PipeFabrication 23% PipeInstallation 26% EquipmentErection 7% ProcessAreas 44.7% Offsites&Utilities 20.4% CommBuildingandShelters 5.9% MainPlant 86% AreaB 6% Pipelines 8% Project
  • 3. King Hussein Cancer Centre Project Project Controls/ Room Completion System 3
  • 4. KHCC Scope of Work The project includes Architectural Finishes and MEPPackages. The project duration is 730calendardays commencing 1st April 2014 The current workforce is 850persons and more than 40sub-contractors The Hospital consists of 182roomsand is comprised of two towers 10 and 12 floors above ground floor sharing the ground floor and three basement floors with an approximate total built-up area of 84,360squaremetres. 4THE JOINT VENTURE OF CONSOLIDATED CONTRACTORS GROUP (OFFSHORE) (CCC) AND HADDADIN ENGINEERING COMPANY FOR CONTRACTING
  • 5. 5 Challenges • Relatively small projects with high complexity • A hospital by definition: • Many systems • Multiple room configurations • A lot of specialties and subcontract • Utilize CCC Project Controls Strategy: • Hybrid system of BIM/AWP/Lean techniques • Fast track Finishing / Handover phase of hospital
  • 6. Project Control Strategy • Reliant Pull-Driven Technique optimize supply chain rather than sub optimization • Assure availability of resources before start of activity. • Emphasize productivity through the full work chain vs. individual activities • Prevent sub-optimization • Partnering • Standardized Project Work Breakdown Structure • Project/Area/SubArea/Fragnet/Activity/Object/Operation • Integrated EPC schedule with Emphasis on Handover and Construction Activities. (effective supply chain) • 3D model built with WBS in mind and used as primary scope management tool. • Early on Cooperation with the Partners/ EDI definition. • 3 Month Look Ahead Schedule/ Material forward plan • 3 week Look Ahead Schedule
  • 7. 7 WBS BIM scope of work Fragnet templates FEL 3 Week Look Ahead Work order QC & Punch listing Invoice Room completion system is based on integrated set of methodologies
  • 8. 8 Work Breakdown Structure - WBS It is a deliverable oriented hierarchy for a project that would organize the project’s team work into manageable sections.
  • 9. 9 Building project’s WBS Project Area1 Sub-area1 Fragnet 1 Fragnet 2 Activity 1 Object1 Object2 Operation1 Operation2 Object3 Object4 Activity 2 Activity 3 Fragnet 3 Fragnet 4 Area2 Sub-area3 Sub-area3 Sub-area4 Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Level 7
  • 10. Level 1 - KHCC Construction Level 2 - Area Location: Building1&2, Building Facades, Roof Works, External Works and Generator Building. Level 3 - Zone Level: Floor Plans at specified Levels and Areas, Stairs, Shafts, Elevators, External areas. Level 4 – Phase/Fragnet: Structural, Open space, finishing, building envelope, etc. Level 5 - Activity: Unique Activity ID from Primavera Level 6 - Object: Objects tagged as per BIM authoring Level 7 - Operation: Operation templates as per object type and method statement (Work of One Crew) WBS Implementation 10
  • 11. 11 Building Information Modelling - BIM It is an intelligent 3D model based process that would provide a control tools for all project’s stakeholders during the project life. WBS BIM
  • 12. Standardized BOQs as scope measurement 12 • Define BOQ, the basic way of measuring content of work • Identify measurement methodology using any of the international standards such as SMM 7, RIC’s, etc… • A BIM model is developed based on the tender documents and specification using BOQ and standardized WBS. • Full MTO (Material Take-Off) is extracted from the BIM model detailed to the BOQ level. The MTO is linked to CCC estimation software where pricing is developed using crew-based estimation. 09210: Plastering ORIGINAL QTY BIM QTY 9/1/1 1- Supply and applying sand / cement exposed plastering layer for internal walls, composed ofbase and finish coats. The work includes spatter, wire mesh at the joints betweenwalls and columns and allaccessories for complete work accordingto specifica m2 64,548 57,200.50 09310: Porcelain & Ceramic Tiles: 2- Supply, delivery and install non-slippery Prcelain tiles for floors of toilets, bathrooms, pantry, terraces, cafeteria and kitchens; according to the finish schedule, approved samples, pattern, shop drawings and specifications. The work includes scree 9/2/1 30 x30 x0.90 cm(R-PTNS-2) m2 1,156 1110.25 9/2/2 25 x25 x0.90 cm(O-PTNS-1&2) m2 1,349 1360.3 9/2/3 15 x15 x0.90 cm(O-PT-1) m2 1,349 1360.3 9/2/4 10 x10 x0.70 cm(R-PTNS-1) m2 963 720 9/2/5 40 x 40 x 0.90 cm and pattern as per drawings for Cafeteria (PTCa). m2 212 210 9/2/6 Ditto for Terraces ofappartments (PTTR). m2 1,927 1875
  • 13. Object naming: WBS/naming conventions/asset tagging KHCC B1 F-9 HVAC Duct installation Dct001 fabrication Project Building Floor Discipline P6- Activity Object s/n Operation KHCC-B1-F9-HVAC-Dct001 Project WBS BIM TAG Member Mark Unique member mark
  • 14. Required integrations using the modelled objects 14 BIM Authoring BOQ Qty & Specs. Primavera Activity QC ITP Estimation and Budgeting Object Tag / OperationActivity ID BOQ code Cost code Category code Resources Manhours Equipments Material
  • 16. Room Type Colorization The figure shows rooms located at Floor 9, Area 2. Rooms are colorized based on their type defined in the color legend. 16
  • 17. Electrical systems identifications The Cable Trays and Trunks are modeled as shown on the side figure. The cables are identified and colorized based on the feeding system as given in the legend. 17
  • 18. Mechanical systems identification Mechanical Systems are identified and given a color based on their type. 1818
  • 19. System identification per room Intersection between room and systems are identified: - Duct Accessories - Duct Fittings - Ducts - Flexible Ducts - Mechanical Equipment's, such as FCU, TU, FSD, VD, ..etc. - Pipes (Includes Drain Pipes, HVAC Pipes, Medical Pipes). The Tag Name can classify the pipes subsystem. - Pipe Fittings 19
  • 21. Subcontractor Scope Management Have an EDI agreement with the sub-contractor List the subcontractors and their BOQ items Analyze the subcontracted scope of work related to a section or volume of the model link in between the drawings/documents and the sub-contractors scope of work Visualize the construction schedule of one or more subcontractors in a Gantt Chart Link the sub-contractors operations to fragnets and clearance forms for coordination  Provide QC inspections, and punch listing for S/C work  Provide clearance forms to control the relation of the S/C with others  Subcontractor Invoice checking based on Earned value
  • 22. EDI agreement with the sub-contractor Electronic Data Interface meetings are to be done with the sub-contractor to agree on: 1- Model format coming from the S/C 2- Model Level of detail (LOD) 2- Naming conventions and tagging 3- Data and documents related to the objects/model 4- Update frequency for the data and change management
  • 23. Defining sub-contractors’ scope graphically and their related BOQ Adding/removing subcontractors BOQ per Subcontractor Assigned Objects per subcontractor
  • 24. 24 Fragnets: Templates of operations in sequence to complete a room WBS BIM Subcontractors scope definition and coordination Fragnet templates
  • 25. Building the sequence of work as a Fragnet per room type. The sequence of work rely on: Lean Principles Sequence of Works (finishing & MEP systems within rooms) 25
  • 26. 26 List of 26 operations for different disciplines within a room
  • 27. Level 7 Operation link to QC Form 27
  • 28. Front End Loading - FEL WBS BIM S/C scope of work Fragnet templates FEL
  • 29. FEL (Front End Loading): is the process of checking and preparing of the execution elements that are required to consider a work front as an open front (Usually on the Zone/Fragnet Level)  The check list should include the following:  Material  Engineering  PMV  HSE  QCPs  Accessibility  HR  etc..  FEL main topics per different disciplines within the work front  service departments  Flag as 3M or 3W  ETA dates  Status Front End Loading (FEL)
  • 31. 31 Identify the open front The subcontractor is allowed to start work at the selected green area which are designated as Open Front. The highlighted boundaries in brown are still not ready to start works.
  • 32. 32 - Target Progress from Schedule - Objects/Operations and their relative weights per Activity with their MTO - Crew Availability and their capacities - Required QC Forms at completion of operations - FEL to assure availability of drawings, material, procedures, etc. - Weekly Meetings on Site to validate progress and plan the next 3 weeks (Generate Workorders) To be ready for the 3 Week Look Ahead Schedule Weekly Assignment per Crew WBS BIM S/C scope of work Fragnet templates FEL 3 Week Look Ahead
  • 33. Site Planning – 3 weeks Look Ahead (Old) 33
  • 35. 35 Weekly Three Week Look-Ahead Report (Sample on Period 86)
  • 39. Digital Pen based form work order
  • 40. 40 Room Type Progress Colorization The Room types are colorized based on their progress. The colors in the legend gives the range of progress percentages.
  • 41. C3D Progress Colorization By System C3D colorization method can visualize the actual progress percentage on each system. 41
  • 42. 42 C3D and Subcontractor Progress (per system) A list of subcontractors with systems related and percentage of progress in colors
  • 43. C3D and Subcontractor Progress (Per room finishing) The Floor Finishes are illustrated in the figure presenting overall progress on each room type. We can allocate the responsibilities of each subcontractor on each floor and observe actual progress. 43
  • 45. 45 QC forms and RFI tracking WBS BIM S/C scope of work Fragnet templates FEL 3 Week Look Ahead Work order QC & Punch listing
  • 46. C3D Atlas - Room Completion RoomQCchecklist Atlasallow:  TrackingtheAFI  BuildingQCscope  Documentprogress  Handingoverdossier 46
  • 47. 47 C3D Atlas - System Progress Tracking The selected system on each floor are tracked and followed depending on their ITP’s and form status. This will allow better operational sequence for the Testing and Commissioning Plan.
  • 48. 48 Punch list forms per rooms and subcontractors
  • 49. 49 Subcontractors Progress and Invoice checking WBS BIM S/C scope of work Fragnet templates FEL 3 Week Look Ahead Work order QC & Punch listing Invoice
  • 51. Earned Value Calculations × 51THE JOINT VENTURE OF CONSOLIDATED CONTRACTORS GROUP (OFFSHORE) (CCC) AND HADDADIN ENGINEERING COMPANY FOR CONTRACTING C3D Planner Cost Loading Activity Percentage Completion Budgeted Cost & rules of credits per Operations Total Earned Value for Activity EV Reporting per WBS Plan + Budget + contract
  • 52. Earned Values calculations per Subcontractors 52 ACTIVITY ID ZONE LEVEL DISCIPLINE (SYSTEM/ SUBSYSTEM) ACTIVITY ID DESCRIPTION SUB-CONTRACTOR ACTUAL START ACTUAL FINISH BUDGETED UNITS % COMPLETE COST % COMPLETE UNITS DONE THIS PERIOD ACTUAL LABOUR UNITS BUDGETED LABOUR UNITS ACTUAL COST BUDGETED COST PRIORIT Y ORDER 09A2-MF010 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM INSTALL SPRINKLERS PIPE NETWORK ULTRA CONTRACTING COMPANY 27-Oct-14 1-Oct-15 100.00% 100.00% 0 93 93 JOD 8,410.97 JOD 8,410.97 01 09A2-MF020 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM INSTALL H.R.C PIPE NETWORK ULTRA CONTRACTING COMPANY 3-Nov-14 2-Sep-15 100.00% 100.00% 0 66 66 JOD 8,410.97 JOD 8,410.97 02 09A2-MF120 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM INSTALL LANDING VALVES FOR FIRE FIGHTING ULTRA CONTRACTING COMPANY 19-May-15 30-Jan-16 95.00% 95.00% 0 6 6 JOD 7,990.42 JOD 8,410.97 03 09A2-MF030 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM PREPARE LOCATION FOR H.R.C ULTRA CONTRACTING COMPANY 27-Jun-15 8-Jul-15 100.00% 100.00% 0 21 21 JOD 8,410.97 JOD 8,410.97 04 09A2-MF050 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM INSTALL VALVES FOR FIRE FIGHTING NETWORK ULTRA CONTRACTING COMPANY 21-Oct-15 26-Oct-15 100.00% 100.00% 0 21 21 JOD 8,410.97 JOD 8,410.97 05 09A2-MF060 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM INSTALL SPRINKLERS ULTRA CONTRACTING COMPANY 10-Feb-16 20-Feb-16 0.00% 0.00% 0 0 96 JOD 0.00 JOD 4,205.48 06 09A2-MF040 A2-L09 MECHANICAL/ FIRE FIGHTING SYSTEM INSTALL H.R.C CABINET AND ACCESSORIES ULTRA CONTRACTING COMPANY 20-Feb-16 3-Mar-16 0.00% 0.00% 0 0 6 JOD 0.00 JOD 8,410.97 07 09A2-MH130 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL H/C WATER BLACK STEEL HVAC PIPES ISAM MA'ZOOZ CONTRACTING 30-Oct-14 14-Oct-15 100.00% 100.00% 0 125 125 JOD 8,410.97 JOD 8,410.97 01 09A2-MH080 A2-L09 MECHANICAL/ HVAC SYSTEM INSTAL FCU AND TERMINAL UNITS (TU) ISAM MA'ZOOZ CONTRACTING 17-Mar-15 2-Nov-15 100.00% 100.00% 0 84 84 JOD 8,410.97 JOD 8,410.97 02 09A2-MH140 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL VALVES AND MEASURING DEVICES FOR HVAC ISAM MA'ZOOZ CONTRACTING 9-Dec-15 17-Dec-15 0.00% 0.00% 0 0 42 JOD 0.00 JOD 8,410.97 03 09A2-MH090 A2-L09 MECHANICAL/ HVAC SYSTEM CONNECT FCU AND TU WITH PIPE ISAM MA'ZOOZ CONTRACTING 23-Dec-15 6-Jan-16 0.00% 0.00% 0 0 84 JOD 0.00 JOD 8,410.97 04 09A2-MH020 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL VAV DUCT QASRAWI DUCTING 30-Oct-14 29-Sep-15 100.00% 100.00% 0 60 60 JOD 8,410.97 JOD 8,410.97 01 09A2-MH010 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL CAV DUCT QASRAWI DUCTING 30-Oct-14 29-Sep-15 100.00% 100.00% 0 60 60 JOD 8,410.97 JOD 8,410.97 02 09A2-MH100 A2-L09 MECHANICAL/ HVAC SYSTEM CONNECT FCU AND TU WITH DUCT QASRAWI DUCTING 19-Sep-15 8-Oct-15 100.00% 100.00% 0 84 84 JOD 8,410.97 JOD 8,410.97 03 09A2-MH050 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL VOLUME DAMPER WITH ACCESSORIES QASRAWI DUCTING 1-Oct-15 3-Oct-15 100.00% 100.00% 0 42 42 JOD 8,410.97 JOD 8,410.97 04 09A2-MH120 A2-L09 MECHANICAL/ HVAC SYSTEM INSTALL FLEXIBLE DUCT AND DIFFUSERS QASRAWI DUCTING 19-May-15 27-Feb-16 35.00% 35.00% 0 29 84 JOD 2,943.84 JOD 8,410.97 05 09A2-MG010 A2-L09 MECHANICAL/ MEDICAL GAS SYSTEM INSTALL COPPER PIPE NETWORK FOR M.GAS ITS 2-Sep-15 5-Nov-15 100.00% 100.00% 0 90 90 JOD 8,410.97 JOD 8,410.97 01 09A2-MG020 A2-L09 MECHANICAL/ MEDICAL GAS SYSTEM INSTALL VALVES & FITTINGS ITS 2-Nov-15 10-Nov-15 100.00% 100.00% 0 37 37 JOD 8,410.97 JOD 8,410.97 02 09A2-MG030 A2-L09 MECHANICAL/ MEDICAL GAS SYSTEM INSALL MEDICAL GAS ALARM PANELS ITS 14-Nov-15 17-Nov-15 100.00% 100.00% 0 22 22 JOD 8,410.97 JOD 8,410.97 03 09A2-MG040 A2-L09 MECHANICAL/ MEDICAL GAS SYSTEM INSTALL GAS OUTLETS ITS 6-Mar-16 20-Mar-16 0.00% 0.00% 0 0 7 JOD 0.00 JOD 8,410.97 04
  • 53. Weekly Budgeted Cost Progress Report (Sample on Period 87) 53