How the use of OEE
                 can drive Operations
                      Excellence
                     Edward Brown

April 24, 2009                      1
OEE for Process
Improvement                                     Topics
Process Improvement
                                 Process Improvement
Why OEE?

The Science of OEE               Why OEE?
Guidelines
                                 The Science of OEE
The Technologies

The Culture of OEE               Guidelines

                                 The Technologies

                                 The Culture of OEE



                      April 24, 2009                     2
OEE for Process
Improvement                              Processes for Improvement
Process
Process Improvement
Improvement                Which of the following Improvement Initiatives is in
Why OEE?                   place, or formally planned to begin within 6 months, at
                           your company?
The Science of OEE
                            Recent     survey of executives
                                 85% - Asset Utilization or OEE Improvement
Guidelines
                                 61% - General Continuous Improvement
The Technologies                 54% - Six Sigma
                                 46% - TPM
The Culture of OEE               38% - Lean Manufacturing
                                 38% - Predictive Maintenance
                                 8% – Other: Software Integration




                      April 24, 2009                                                 3
OEE for Process
Improvement                     Making Process Improvement Work
Process
Process Improvement
Improvement                  The Processes only work when you have:
Why OEE?                        Awareness
                                  Knowing what to measure
The Science of OEE
                                  Knowing how to measure it
Guidelines
                                  Knowing what’s important
The Technologies                Accuracy
The Culture of OEE
                                  Measurements in context
                                  What’s included
                                  What’s excluded
                                Responsibility
                                  Actionable Issues Assigned
                                  Empowerment
                                  Follow-Up


                      April 24, 2009                                  4
OEE for Process
Improvement                            How well do you know that KPI?
Process
Process Improvement
Improvement           Existing KPIs May Be Inadequate
Why OEE?
                      Failing to recognize the limitations of the existing plant
The Science of OEE
                      performance measurement system.
Guidelines
                       What  is included?
The Technologies
                       What  is excluded?
The Culture of OEE
                       Standard across areas or plants?
                       How are Management incentives structured?
                       Is Management more concerned with reporting a high efficiency
                        value rather than focusing on improvement?




                      April 24, 2009                                                    5
OEE for Process
Improvement                     Can We Believe Our Numbers?
Process
Process Improvement
Improvement           How efficient do you think    Most of these companies
Why OEE?              your plant is?                are really operating at only
                      Many mfg companies            30-60% of their true
The Science of OEE
                      believe they are 80-90%       potential as measured by
Guidelines            efficient                     Overall Equipment
                       Andthey are… the way they   Effectiveness (OEE)
The Technologies
                       have come to measure          85%   OEE is “World Class”
The Culture of OEE     themselves.
OEE for Process
Improvement                                        The Way of OEE
Process Improvement
                                      OEE Identifies and Organizes KPI’s
Why OEE?
Why OEE?
                                       Equipment – Downtime, Speed, Quality
The Science of OEE                     Materials – Availability, Quality
Guidelines                             Labor – Availability, Speed, Quality
The Technologies                      Ability to Measure or Compare at any Level
The Culture of OEE                     Specific Machine or Working Cell
                                       Line or Group of Machines/Cells
                                       Production Area or Plant




                      April 24, 2009                                                7
OEE for Process
Improvement                                           Why OEE?
Process Improvement        Overall Equipment Effectiveness Provides a
                           framework for Manufacturing Process Improvement
Why OEE?
Why OEE?
                            New       Product Development
The Science of OEE
                            Product     Changes
Guidelines
                            Reducing      Non-Value Added operations
The Technologies
                            Developing     Equipment Maintenance Strategies
The Culture of OEE          Equipment      Reliability Practices
                            Personnel     Training Effectiveness
                            Improved      Root Cause Analysis
                            Improving     Limiting Constraints




                      April 24, 2009                                           8
OEE for Process
Improvement                        Unlocking Your Inner Super Plant
Process Improvement
                           OEE can be used by Teams to unlock “Hidden
Why OEE?
Why OEE?
                           Capacity” found in almost every plant
The Science of OEE
                           OEE Savings Benefits
Guidelines                   Reduce Capital Expenditures
                             Justify Capital Expenditures
The Technologies
                             Reduce Labor Costs
The Culture of OEE           Reduce Scrap and Rework
                             Reduce Inventory Costs




                      April 24, 2009                                    9
OEE for Process
Improvement                              The Gold Standard
Process Improvement
                           Overall Equipment Effectiveness is becoming the
Why OEE?                   de-facto standard for measuring the efficiency and
                           capability of production processes with consistency
    Science of OEE
The Science of OEE

Guidelines                 OEE Measures Three Critical Factors:
The Technologies            Availability – Whether equipment, material, and
                            personnel are available for production
The Culture of OEE
                             Performance – Whether equipment and personnel
                             are performing to their capacity
                             Quality – Whether the product is being produced
                             correctly the first time (first pass yield)




                      April 24, 2009                                             10
OEE for Process
Improvement                 Capturing the TPM “Six Big Losses”
Process Improvement
                                        OEE
                      Major Losses                          Notes
Why OEE?                                Category
    Science of OEE    Major                                 There is flexibility on where to set the
The Science of OEE
                      Breakdowns                            threshold between a Breakdown
                                        Availability Loss
                                                            (Availability Loss) and a Short Stop
Guidelines
                                                            (Performance Loss).
The Technologies      Setup and
                                        Availability Loss   Includes changeovers.
                      Adjustments
The Culture of OEE    Short                                 Typically only includes stops that are
                                        Performance
                      Stops/Idling                          under 5-10 minutes and that do not
                                        Loss
                                                            require maintenance personnel.
                                                            Causes preventing the process from
                                        Performance
                      Reduced Speed                         running at its theoretical maximum
                                        Loss
                                                            speed (minimum cycle time).
                                                            Bad products during warm-up, startup
                      Startup Rejects   Quality Loss
                                                            or other early production.
                      Production                            Bad Products during steady-state
                                        Quality Loss
                      Rejects                               operation.
OEE for Process
Improvement                                    In A Perfect World
Process Improvement
                           A line with an OEE of 100% runs
Why OEE?
                            All   of the time it is scheduled
The Science of OEE
The Science of OEE

Guidelines
                            No    time loss for Changeovers, Cleaning, Breakdowns

The Technologies
                            Always       runs at the full rated speed
The Culture of OEE
                            No    short stop failures

                            Has       a 1st pass Yield of 100%




                      April 24, 2009                                                 12
OEE for Process
Improvement                            OEE – More than a Number
Process Improvement

Why OEE?              OEE = Availability * Rate * Quality
The Science of OEE
The Science of OEE
                      Example: (.77)*(.65)*(.98)*100% = 49% OEE
Guidelines
                      OEE Element          Components
The Technologies

The Culture of OEE
                          98% yield alone
                           is not enough
                      Availability         Actual runtime / Available time

                      Production Rate      Total production (good & bad) / theoretical
                                           limit

                      Quality              Good quantity / Total quantity

                      April 24, 2009
OEE for Process
Improvement                                  World Class OEE
Process Improvement    OEE = 85% is “World Class”
Why OEE?
                        Very   challenging for a company to operate at
                         this level when OEE is measured accurately.
The Science of OEE
The Science of OEE      We don’t see production lines that are
                         operating at 85% OEE
Guidelines
                        But… we have seen lines operating in the 20 –
The Technologies         30% range!

The Culture of OEE



                                       OEE Factor     World Class


                                       Availability   90.0%

                                       Performance    95.0%

                                       Quality        99.9%

                                       Overall OEE    85.0%




                      April 24, 2009                                      14
OEE for Process
Improvement                                        Reality Check
Process Improvement
                            Majorityof Plants operating at 30 to 40%.
Why OEE?                    Day to day variation can be +/- 15% or more
                                 Scheduling deviations
The Science of OEE
The Science of OEE               Labor overtime
                                 Inventory accumulation
Guidelines

The Technologies                          World Class Pharma OEE

The Culture of OEE                         Number of SKU's          OEE
                             Low SKU Count (1-2)                    83%
                             Medium SKU Count (3-5)                 80%
                             High SKU Count (6-12)                  73%
                             Very High SKU Count (> 20)             63%

                      April 24, 2009                                       15
OEE for Process
Improvement                                  Overall Suggestions
Process Improvement        If you can’t measure it, you can’t (won’t) improve it!
                                Use OEE measurements as part of Process Improvement
Why OEE?
                               program
The Science of OEE
                           Create Downtime Reasons that are Meaningful
Guidelines
Guidelines                      Machine Codes and Ad Hoc entries are a poor foundation

The Technologies           Set performance targets at achievable levels
                                When was theoretical ever reached?
The Culture of OEE
                           Develop an ability to calculate an Accurate Measure of
                           the true capability of a production line
                                Include all significant losses

                           Develop a written factory performance spec that
                           precisely defines what is included, excluded, and
                           special cases.
                                To compare other plant/lines, all OEE measurements must be
                               made in same way
                      April 24, 2009                                                          16
OEE for Process
Improvement                                 Divide and Conquer
Process Improvement
                           Set separate Improvement Targets for:
Why OEE?                    Availability
                            Performance
The Science of OEE          Quality

Guidelines
Guidelines

The Technologies

The Culture of OEE




                      April 24, 2009                               17
OEE for Process
Improvement                               Set Separate Goals
Process Improvement    Reduce  Availability Losses by 10-50%
                        on time basis
Why OEE?

The Science of OEE     Reduce  Performance Losses by 5-20%
                        on time basis
Guidelines
Guidelines                                                              25
The Technologies       Quality Improvement will vary depending 20
                        on the process and industry (0.5%?)
The Culture of OEE                                                                            Defect Loss




                                                                Hours
                                                                15
                                                                                              Perf Loss
                       Improve OEE by 5-10% per year (or                                     Avail Loss
                        more)                                   10                            Sch'd DT
                                                                                              Run Time
                                                                        5

                                                                        0
                                                                             Line Line Line
                                                                               1    2    3




                      April 24, 2009                                                                     18
OEE for Process
Improvement                        Return on Investment
Process Improvement
                      Baseline with 66.5% OEE
Why OEE?
                      19 cases/minute/line              18,194 cases/day/line
The Science of OEE
                      $ 14.00/case (wholesale)       $ 254,722 day/line
Guidelines
Guidelines
                                          Before                      After
The Technologies           Availability     80%                        85%
The Culture of OEE         Performance      84%                        86%
                           Quality         99.0%                      99.2%
                           OEE             66.5%                      72.5%
                                   Revenue Improvement:
                               +1,641 cases/day or $22,974/day
                                 $8.3 million/year
OEE for Process
Improvement                                      Key Technologies
Process Improvement
                                  Automated Downtime
Why OEE?                              Machine Downtime for emergency and short-stops
                                      Labor Tracking for personnel operation timing
The Science of OEE
                                  Structured Downtime Reason Trees
Guidelines
                                      Categorized by product/operation/machine
The Technologies
    Technologies                      Drill Down Capability for Root Cause Analysis
                                      Basis for Process Improvement Charts
The Culture of OEE

                                  Automated Production Counts
                                      First Pass Yield Counts
                                      Rework Counts




                      April 24, 2009                                                    20
OEE for Process
Improvement                                Automated Downtime
Process Improvement
                           Relying on Manually Collected Data
Why OEE?                    Entry  errors
                            Significant effort to collect and analyze
The Science of OEE

Guidelines                 Making decisions based solely on Manually
The Technologies
    Technologies
                           collected Downtime data
                            Isnotoriously unreliable.
The Culture of OEE
                            Are all hours of the day accounted for?
                            Does it match up with actual product produced?
                            Can it account for all the short stops occurring on a
                             typical line (most lines have 1,000 or more short stops /
                             week).




                      April 24, 2009                                                     21
OEE for Process
Improvement                        OEE Without Automation?
Process Improvement

Why OEE?
                                Inaccurate
The Science of OEE
                              Availability Data
Guidelines
                               Inflates OEE
The Technologies
    Technologies                                           Incidents   Total time

The Culture of OEE                                         Manual      Phantom

                      Average        Manual    Automated
                      Downtime      (Before)     (After)
                      Incidents       12          140
                      Duration
                                      15          <2
                      (minutes)
                                                           *Theoretical based on
                      Total time      180         280        95% quality & 95%
                      OEE*           79%         73%           performance
OEE for Process
Improvement                              Operator Input is Important
Process Improvement
                           Selectively involve the operator….
Why OEE?                    Automate   collection of OEE and the supporting downtime data
                              so that good decisions can be made regarding actions that will
The Science of OEE
                              improve OEE.
                                 Time and again, clipboard data collection for OEE and Downtime info
Guidelines
                                  has proven to be of little value
The Technologies
    Technologies                   Operators don’t time themselves
                                   Operators can’t perceive the effect of repetitive problems
The Culture of OEE                 Changeover vs. shift change example
                            But, do not limit yourselves to the automation            layer
                              Can not always provide root cause
                              Downtime reason selection by Operator IS powerful




                      April 24, 2009                                                                    23
OEE for Process
Improvement           Structured Downtime Reasons
Process Improvement

Why OEE?

The Science of OEE

Guidelines

The Technologies
    Technologies

The Culture of OEE
OEE for Process
Improvement                    Downtime Reasons and Drilldown
Process Improvement            Monthly to Current
                                  Downtime
Why OEE?

                      25
The Science of OEE    20
                      15
                      10
Guidelines             5
                       0                                                Line Stop Incidents
                            Equip     Planned Line Stop Rejects
The Technologies
    Technologies            Down       Maint
                                                                  10
                                                                   8
                                    Shift 1   Shift 2   Shift 3
The Culture of OEE                                                 6
                                                                   4
                              Transfer Errors                      2
                                                                   0
                                                                         Raw      Transfer   Quality
                                                                       Material    Error      Hold
                       20                                              Shortage
                       15
                       10
                        5
                        0
OEE for Process
Improvement                            Automate Production Counts
Process Improvement
                           Collecting production counts is simple, effective
Why OEE?                   means to determine First Pass Yields
The Science of OEE
                           Counting Rework cycles for an item more difficult, but
Guidelines                 can make dramatic improvements in Quality
The Technologies
    Technologies

The Culture of OEE




                      April 24, 2009                                                26
OEE for Process
Improvement           Eight Key Elements of Process Improvement
Process Improvement
                                      Management involvement to set the Business
Why OEE?
                                       Objectives and maintain program focus.
The Science of OEE                    Ability to accurately measure productivity in Real-time.
                                      Ability to accurately capture detailed reasons for
Guidelines
                                       efficiency losses, for corrective actions.
The Technologies
                                      Assign Responsibility to Issue Champion
    Culture of OEE
The Culture of OEE                    Empower Issue Champions to Solve Problems
                                      Ability to selectively involve the Operators.
                                      Web Reporting for easy distribution of current
                                       performance to all parties.
                                      Maintain Issue and Resolution Histories




                      April 24, 2009                                                              27
OEE for Process
Improvement                             There’s No “I” in OEE
Process Improvement   Achieving RESULTS requires participation of the entire
Why OEE?              team.
                       Get Operations, Production, Maintenance, Engineering, and Quality
The Science of OEE      on board right from the beginning.
Guidelines

The Technologies

    Culture of OEE
The Culture of OEE




                      April 24, 2009                                                        28
OEE for Process
Improvement                                       Conclusion!
Process Improvement
                           Improved Productivity and Asset Utilization…
Why OEE?                    Always   result in savings that drop right to the Bottom Line
                             (earnings)
The Science of OEE
                            Always result in Reduced Capital Expenditures
Guidelines                  In Good Times, unleashes unused capacity, so volume can
                             ramp up without requiring major investment in more
The Technologies             plants, equipment, and employees.
    Culture of OEE
                            In Bad Times allows plants to:
The Culture of OEE
                              Cut back to only those shifts that are necessary
                              Reduce overtime expenditures
                              Reduce waste
                              Identify and sell under performing assets, reducing
                               depreciation and maintenance costs.




                      April 24, 2009                                                         29
OEE for Process
Improvement                                        Conclusion!
Process Improvement
                       Improved Productivity and Asset Utilization…
Why OEE?
                        Provides       Data to make Suppliers more Accountable
The Science of OEE         EquipmentSuppliers
                           Consumables / Raw Materials Suppliers
Guidelines

The Technologies
                        Gather        Hard Data related to equipment performance.
    Culture of OEE
The Culture of OEE         Identify equipment problems.
                           Justify Capital Improvements   or Asset Reductions.

                        Motivate       Operators and Maintenance Team

                        Drive     Uniformity in Plant Scorecard calculations.




                      April 24, 2009                                                 30
Questions?


                 Web Site: www.AvidSolutionsInc.com


                        Contact Information:

                   Ed Brown – 919.468.4334 x221

                   Eric Mayer – 919.468.4334 x202




April 24, 2009                                      31

More Related Content

PPTX
OEE for Process Improvement
PPTX
6 OEE overview
PDF
The+complete+guide+to+simple+oee
PPTX
Chattanooga sme oee down time presentation
PPSX
OEE Target - ¿What is the basis for your current OEE goal?
PPTX
benefits from calculating overall equipment effectivness
PDF
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
PDF
A Manager's Guide to OEE (Overall Equipment Effectiveness)
OEE for Process Improvement
6 OEE overview
The+complete+guide+to+simple+oee
Chattanooga sme oee down time presentation
OEE Target - ¿What is the basis for your current OEE goal?
benefits from calculating overall equipment effectivness
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
A Manager's Guide to OEE (Overall Equipment Effectiveness)

What's hot (18)

PPTX
Top OEE & Lean Manufacturing Terms Explained
PDF
OEE - The Critical KPI to Drive Manufacturing Productivity
PDF
Tpm principles and concepts
PDF
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
PDF
Overall Equipment Effectiveness
PDF
Benefits of Collecting OEE Data with Production Tracking Software
PPT
OEE Interphex New York 2013
PPT
TO IMPEOVE THE PERFOMANCE OF THE PLANT USING OEE
DOCX
Tpm Diagnostic 4
PDF
OEE Target - ¿What is the basis for your current OEE goal?
PDF
Total Productive Maintenance (TPM)
PPTX
Total productive maintenance (tpm)
PPTX
Oee (overall equipment effectifness)
PPT
PPT
Ims Maint Mgmt Best Practice
Top OEE & Lean Manufacturing Terms Explained
OEE - The Critical KPI to Drive Manufacturing Productivity
Tpm principles and concepts
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
Overall Equipment Effectiveness
Benefits of Collecting OEE Data with Production Tracking Software
OEE Interphex New York 2013
TO IMPEOVE THE PERFOMANCE OF THE PLANT USING OEE
Tpm Diagnostic 4
OEE Target - ¿What is the basis for your current OEE goal?
Total Productive Maintenance (TPM)
Total productive maintenance (tpm)
Oee (overall equipment effectifness)
Ims Maint Mgmt Best Practice
Ad

Viewers also liked (17)

PPTX
Design For OEE (DFOEE)
PDF
Oee guide
PDF
Oee on hana overall equipment effectiveness overview aug 2012 (2)
PPT
Oee Explained
PPTX
The Six Big Losses of OEE
PPTX
Visual Management: Leading with what you can see
PPSX
OEE Apresentação TCC
PDF
Executive Guide to Leveraging OEE
PDF
Understanding Teep vs OEE
PDF
SMED Hunt Activity
PDF
the shortest version of #MINDSHIFT
PDF
Preso: The OEE Story
PPT
Using OEE to Improve Production - Interphex 2012
PPTX
OEE IMPLEMENTATION part 1
PDF
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
PDF
The Data Science behind Predictive Maintenance for Connected Vehicles
PPTX
Autonomous Maintenance (AM)
Design For OEE (DFOEE)
Oee guide
Oee on hana overall equipment effectiveness overview aug 2012 (2)
Oee Explained
The Six Big Losses of OEE
Visual Management: Leading with what you can see
OEE Apresentação TCC
Executive Guide to Leveraging OEE
Understanding Teep vs OEE
SMED Hunt Activity
the shortest version of #MINDSHIFT
Preso: The OEE Story
Using OEE to Improve Production - Interphex 2012
OEE IMPLEMENTATION part 1
IDASANET - AUTOMATISMOS INDUSTRIALES Y APLICACIONES INFORMATICAS
The Data Science behind Predictive Maintenance for Connected Vehicles
Autonomous Maintenance (AM)
Ad

Similar to Integrating OEE and Process Improvement (20)

PPT
Using OEE to Improve Production - Interphex Puerto Rico 2012
PPT
lean & agile
PDF
The Critical KPI to drive Manufacturing Productivity
PDF
The Critical KPI to Drive Manufacturing Productivity
PPT
Jvh Lean Presentation For 2009
PPTX
chemical production control slides
PDF
OEE Fact sheet
PDF
7. cqia (kaizen, 5 s, tpm)
PDF
Factory-Whitepaper-Sustainability-Aptean-Weisman
PDF
Overall Equipment Effectiveness Robert C. Hansen
PDF
Overall Equipment Effectiveness Robert C. Hansen
PDF
What Food Manufacturers Need to Know about Measuring OEE - London Consulting ...
PPTX
Ask the Expert: Lean Leadership - Can We Talk About OEE?
PDF
Overall Equipment Effectiveness Robert C. Hansen
PDF
Tpm introduction-ame
PDF
OPTIMIZING TIME WITH INCREASING PRODUCTIVITY USING LEAN MANUFACTURING AND OVE...
PDF
30120140502015
Using OEE to Improve Production - Interphex Puerto Rico 2012
lean & agile
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
Jvh Lean Presentation For 2009
chemical production control slides
OEE Fact sheet
7. cqia (kaizen, 5 s, tpm)
Factory-Whitepaper-Sustainability-Aptean-Weisman
Overall Equipment Effectiveness Robert C. Hansen
Overall Equipment Effectiveness Robert C. Hansen
What Food Manufacturers Need to Know about Measuring OEE - London Consulting ...
Ask the Expert: Lean Leadership - Can We Talk About OEE?
Overall Equipment Effectiveness Robert C. Hansen
Tpm introduction-ame
OPTIMIZING TIME WITH INCREASING PRODUCTIVITY USING LEAN MANUFACTURING AND OVE...
30120140502015

Recently uploaded (20)

PDF
the role of manager in strategic alliances
DOCX
Center Enamel Enabling Precision and Sustainability in the Netherlands' Advan...
PDF
BeMetals_Presentation_September_2025.pdf
PPTX
Accounting Management SystemBatch-4.pptx
PDF
The Impact of Immigration on National Identity (www.kiu.ac.ug)
PDF
COVID-19 Primer for business case prep.pdf
PPTX
Warehouse. B pptx
PPTX
Hospitality & tourism management.pptxHospitality & tourism management.pptx
PPTX
Enterprises are Classified into Two Categories
PPTX
Hospitality & tourism management.pptxHospitality & tourism management.pptx
PPTX
Biomass_Energy_PPT_FIN AL________________.pptx
PPTX
Supply Chain under WAR (Managing Supply Chain Amid Political Conflict).pptx
PDF
Handouts for Housekeeping.pdfbababvsvvNnnh
DOCX
“Strategic management process of a selected organization”.Nestle-docx.docx
PDF
Не GPT єдиним: можливості AI в бізнес-аналізі | Вебінар з Тетяною Перловською
 
PDF
The Future of Marketing: AI, Funnels & MBA Careers | My Annual IIM Lucknow Talk
PPTX
PwC consulting Powerpoint Graphics 2014 templates
PPTX
PPT Hafizullah Oria- Final Thesis Exam.pptx
PPTX
003 seven PARTS OF SPEECH english subject.pptx
PDF
Handouts for Housekeeping.pdfhsjsnvvbdjsnwb
the role of manager in strategic alliances
Center Enamel Enabling Precision and Sustainability in the Netherlands' Advan...
BeMetals_Presentation_September_2025.pdf
Accounting Management SystemBatch-4.pptx
The Impact of Immigration on National Identity (www.kiu.ac.ug)
COVID-19 Primer for business case prep.pdf
Warehouse. B pptx
Hospitality & tourism management.pptxHospitality & tourism management.pptx
Enterprises are Classified into Two Categories
Hospitality & tourism management.pptxHospitality & tourism management.pptx
Biomass_Energy_PPT_FIN AL________________.pptx
Supply Chain under WAR (Managing Supply Chain Amid Political Conflict).pptx
Handouts for Housekeeping.pdfbababvsvvNnnh
“Strategic management process of a selected organization”.Nestle-docx.docx
Не GPT єдиним: можливості AI в бізнес-аналізі | Вебінар з Тетяною Перловською
 
The Future of Marketing: AI, Funnels & MBA Careers | My Annual IIM Lucknow Talk
PwC consulting Powerpoint Graphics 2014 templates
PPT Hafizullah Oria- Final Thesis Exam.pptx
003 seven PARTS OF SPEECH english subject.pptx
Handouts for Housekeeping.pdfhsjsnvvbdjsnwb

Integrating OEE and Process Improvement

  • 1. How the use of OEE can drive Operations Excellence Edward Brown April 24, 2009 1
  • 2. OEE for Process Improvement Topics Process Improvement  Process Improvement Why OEE? The Science of OEE  Why OEE? Guidelines  The Science of OEE The Technologies The Culture of OEE  Guidelines  The Technologies  The Culture of OEE April 24, 2009 2
  • 3. OEE for Process Improvement Processes for Improvement Process Process Improvement Improvement Which of the following Improvement Initiatives is in Why OEE? place, or formally planned to begin within 6 months, at your company? The Science of OEE  Recent survey of executives  85% - Asset Utilization or OEE Improvement Guidelines  61% - General Continuous Improvement The Technologies  54% - Six Sigma  46% - TPM The Culture of OEE  38% - Lean Manufacturing  38% - Predictive Maintenance  8% – Other: Software Integration April 24, 2009 3
  • 4. OEE for Process Improvement Making Process Improvement Work Process Process Improvement Improvement The Processes only work when you have: Why OEE?  Awareness  Knowing what to measure The Science of OEE  Knowing how to measure it Guidelines  Knowing what’s important The Technologies  Accuracy The Culture of OEE  Measurements in context  What’s included  What’s excluded  Responsibility  Actionable Issues Assigned  Empowerment  Follow-Up April 24, 2009 4
  • 5. OEE for Process Improvement How well do you know that KPI? Process Process Improvement Improvement Existing KPIs May Be Inadequate Why OEE? Failing to recognize the limitations of the existing plant The Science of OEE performance measurement system. Guidelines  What is included? The Technologies  What is excluded? The Culture of OEE  Standard across areas or plants?  How are Management incentives structured?  Is Management more concerned with reporting a high efficiency value rather than focusing on improvement? April 24, 2009 5
  • 6. OEE for Process Improvement Can We Believe Our Numbers? Process Process Improvement Improvement How efficient do you think Most of these companies Why OEE? your plant is? are really operating at only Many mfg companies 30-60% of their true The Science of OEE believe they are 80-90% potential as measured by Guidelines efficient Overall Equipment  Andthey are… the way they Effectiveness (OEE) The Technologies have come to measure  85% OEE is “World Class” The Culture of OEE themselves.
  • 7. OEE for Process Improvement The Way of OEE Process Improvement  OEE Identifies and Organizes KPI’s Why OEE? Why OEE?  Equipment – Downtime, Speed, Quality The Science of OEE  Materials – Availability, Quality Guidelines  Labor – Availability, Speed, Quality The Technologies  Ability to Measure or Compare at any Level The Culture of OEE  Specific Machine or Working Cell  Line or Group of Machines/Cells  Production Area or Plant April 24, 2009 7
  • 8. OEE for Process Improvement Why OEE? Process Improvement Overall Equipment Effectiveness Provides a framework for Manufacturing Process Improvement Why OEE? Why OEE?  New Product Development The Science of OEE  Product Changes Guidelines  Reducing Non-Value Added operations The Technologies  Developing Equipment Maintenance Strategies The Culture of OEE  Equipment Reliability Practices  Personnel Training Effectiveness  Improved Root Cause Analysis  Improving Limiting Constraints April 24, 2009 8
  • 9. OEE for Process Improvement Unlocking Your Inner Super Plant Process Improvement OEE can be used by Teams to unlock “Hidden Why OEE? Why OEE? Capacity” found in almost every plant The Science of OEE OEE Savings Benefits Guidelines  Reduce Capital Expenditures  Justify Capital Expenditures The Technologies  Reduce Labor Costs The Culture of OEE  Reduce Scrap and Rework  Reduce Inventory Costs April 24, 2009 9
  • 10. OEE for Process Improvement The Gold Standard Process Improvement Overall Equipment Effectiveness is becoming the Why OEE? de-facto standard for measuring the efficiency and capability of production processes with consistency Science of OEE The Science of OEE Guidelines OEE Measures Three Critical Factors: The Technologies Availability – Whether equipment, material, and personnel are available for production The Culture of OEE Performance – Whether equipment and personnel are performing to their capacity Quality – Whether the product is being produced correctly the first time (first pass yield) April 24, 2009 10
  • 11. OEE for Process Improvement Capturing the TPM “Six Big Losses” Process Improvement OEE Major Losses Notes Why OEE? Category Science of OEE Major There is flexibility on where to set the The Science of OEE Breakdowns threshold between a Breakdown Availability Loss (Availability Loss) and a Short Stop Guidelines (Performance Loss). The Technologies Setup and Availability Loss Includes changeovers. Adjustments The Culture of OEE Short Typically only includes stops that are Performance Stops/Idling under 5-10 minutes and that do not Loss require maintenance personnel. Causes preventing the process from Performance Reduced Speed running at its theoretical maximum Loss speed (minimum cycle time). Bad products during warm-up, startup Startup Rejects Quality Loss or other early production. Production Bad Products during steady-state Quality Loss Rejects operation.
  • 12. OEE for Process Improvement In A Perfect World Process Improvement A line with an OEE of 100% runs Why OEE?  All of the time it is scheduled The Science of OEE The Science of OEE Guidelines  No time loss for Changeovers, Cleaning, Breakdowns The Technologies  Always runs at the full rated speed The Culture of OEE  No short stop failures  Has a 1st pass Yield of 100% April 24, 2009 12
  • 13. OEE for Process Improvement OEE – More than a Number Process Improvement Why OEE? OEE = Availability * Rate * Quality The Science of OEE The Science of OEE Example: (.77)*(.65)*(.98)*100% = 49% OEE Guidelines OEE Element Components The Technologies The Culture of OEE 98% yield alone is not enough Availability Actual runtime / Available time Production Rate Total production (good & bad) / theoretical limit Quality Good quantity / Total quantity April 24, 2009
  • 14. OEE for Process Improvement World Class OEE Process Improvement OEE = 85% is “World Class” Why OEE?  Very challenging for a company to operate at this level when OEE is measured accurately. The Science of OEE The Science of OEE  We don’t see production lines that are operating at 85% OEE Guidelines  But… we have seen lines operating in the 20 – The Technologies 30% range! The Culture of OEE OEE Factor World Class Availability 90.0% Performance 95.0% Quality 99.9% Overall OEE 85.0% April 24, 2009 14
  • 15. OEE for Process Improvement Reality Check Process Improvement  Majorityof Plants operating at 30 to 40%. Why OEE?  Day to day variation can be +/- 15% or more  Scheduling deviations The Science of OEE The Science of OEE  Labor overtime  Inventory accumulation Guidelines The Technologies World Class Pharma OEE The Culture of OEE Number of SKU's OEE Low SKU Count (1-2) 83% Medium SKU Count (3-5) 80% High SKU Count (6-12) 73% Very High SKU Count (> 20) 63% April 24, 2009 15
  • 16. OEE for Process Improvement Overall Suggestions Process Improvement If you can’t measure it, you can’t (won’t) improve it!  Use OEE measurements as part of Process Improvement Why OEE? program The Science of OEE Create Downtime Reasons that are Meaningful Guidelines Guidelines  Machine Codes and Ad Hoc entries are a poor foundation The Technologies Set performance targets at achievable levels  When was theoretical ever reached? The Culture of OEE Develop an ability to calculate an Accurate Measure of the true capability of a production line  Include all significant losses Develop a written factory performance spec that precisely defines what is included, excluded, and special cases.  To compare other plant/lines, all OEE measurements must be made in same way April 24, 2009 16
  • 17. OEE for Process Improvement Divide and Conquer Process Improvement Set separate Improvement Targets for: Why OEE?  Availability  Performance The Science of OEE  Quality Guidelines Guidelines The Technologies The Culture of OEE April 24, 2009 17
  • 18. OEE for Process Improvement Set Separate Goals Process Improvement  Reduce Availability Losses by 10-50% on time basis Why OEE? The Science of OEE  Reduce Performance Losses by 5-20% on time basis Guidelines Guidelines 25 The Technologies  Quality Improvement will vary depending 20 on the process and industry (0.5%?) The Culture of OEE Defect Loss Hours 15 Perf Loss  Improve OEE by 5-10% per year (or Avail Loss more) 10 Sch'd DT Run Time 5 0 Line Line Line 1 2 3 April 24, 2009 18
  • 19. OEE for Process Improvement Return on Investment Process Improvement Baseline with 66.5% OEE Why OEE? 19 cases/minute/line 18,194 cases/day/line The Science of OEE $ 14.00/case (wholesale) $ 254,722 day/line Guidelines Guidelines Before After The Technologies Availability 80% 85% The Culture of OEE Performance 84% 86% Quality 99.0% 99.2% OEE 66.5% 72.5% Revenue Improvement: +1,641 cases/day or $22,974/day $8.3 million/year
  • 20. OEE for Process Improvement Key Technologies Process Improvement  Automated Downtime Why OEE?  Machine Downtime for emergency and short-stops  Labor Tracking for personnel operation timing The Science of OEE  Structured Downtime Reason Trees Guidelines  Categorized by product/operation/machine The Technologies Technologies  Drill Down Capability for Root Cause Analysis  Basis for Process Improvement Charts The Culture of OEE  Automated Production Counts  First Pass Yield Counts  Rework Counts April 24, 2009 20
  • 21. OEE for Process Improvement Automated Downtime Process Improvement Relying on Manually Collected Data Why OEE?  Entry errors  Significant effort to collect and analyze The Science of OEE Guidelines Making decisions based solely on Manually The Technologies Technologies collected Downtime data  Isnotoriously unreliable. The Culture of OEE  Are all hours of the day accounted for?  Does it match up with actual product produced?  Can it account for all the short stops occurring on a typical line (most lines have 1,000 or more short stops / week). April 24, 2009 21
  • 22. OEE for Process Improvement OEE Without Automation? Process Improvement Why OEE? Inaccurate The Science of OEE Availability Data Guidelines Inflates OEE The Technologies Technologies Incidents Total time The Culture of OEE Manual Phantom Average Manual Automated Downtime (Before) (After) Incidents 12 140 Duration 15 <2 (minutes) *Theoretical based on Total time 180 280 95% quality & 95% OEE* 79% 73% performance
  • 23. OEE for Process Improvement Operator Input is Important Process Improvement Selectively involve the operator…. Why OEE?  Automate collection of OEE and the supporting downtime data so that good decisions can be made regarding actions that will The Science of OEE improve OEE.  Time and again, clipboard data collection for OEE and Downtime info Guidelines has proven to be of little value The Technologies Technologies  Operators don’t time themselves  Operators can’t perceive the effect of repetitive problems The Culture of OEE  Changeover vs. shift change example  But, do not limit yourselves to the automation layer  Can not always provide root cause  Downtime reason selection by Operator IS powerful April 24, 2009 23
  • 24. OEE for Process Improvement Structured Downtime Reasons Process Improvement Why OEE? The Science of OEE Guidelines The Technologies Technologies The Culture of OEE
  • 25. OEE for Process Improvement Downtime Reasons and Drilldown Process Improvement Monthly to Current Downtime Why OEE? 25 The Science of OEE 20 15 10 Guidelines 5 0 Line Stop Incidents Equip Planned Line Stop Rejects The Technologies Technologies Down Maint 10 8 Shift 1 Shift 2 Shift 3 The Culture of OEE 6 4 Transfer Errors 2 0 Raw Transfer Quality Material Error Hold 20 Shortage 15 10 5 0
  • 26. OEE for Process Improvement Automate Production Counts Process Improvement Collecting production counts is simple, effective Why OEE? means to determine First Pass Yields The Science of OEE Counting Rework cycles for an item more difficult, but Guidelines can make dramatic improvements in Quality The Technologies Technologies The Culture of OEE April 24, 2009 26
  • 27. OEE for Process Improvement Eight Key Elements of Process Improvement Process Improvement  Management involvement to set the Business Why OEE? Objectives and maintain program focus. The Science of OEE  Ability to accurately measure productivity in Real-time.  Ability to accurately capture detailed reasons for Guidelines efficiency losses, for corrective actions. The Technologies  Assign Responsibility to Issue Champion Culture of OEE The Culture of OEE  Empower Issue Champions to Solve Problems  Ability to selectively involve the Operators.  Web Reporting for easy distribution of current performance to all parties.  Maintain Issue and Resolution Histories April 24, 2009 27
  • 28. OEE for Process Improvement There’s No “I” in OEE Process Improvement Achieving RESULTS requires participation of the entire Why OEE? team.  Get Operations, Production, Maintenance, Engineering, and Quality The Science of OEE on board right from the beginning. Guidelines The Technologies Culture of OEE The Culture of OEE April 24, 2009 28
  • 29. OEE for Process Improvement Conclusion! Process Improvement Improved Productivity and Asset Utilization… Why OEE?  Always result in savings that drop right to the Bottom Line (earnings) The Science of OEE  Always result in Reduced Capital Expenditures Guidelines  In Good Times, unleashes unused capacity, so volume can ramp up without requiring major investment in more The Technologies plants, equipment, and employees. Culture of OEE  In Bad Times allows plants to: The Culture of OEE  Cut back to only those shifts that are necessary  Reduce overtime expenditures  Reduce waste  Identify and sell under performing assets, reducing depreciation and maintenance costs. April 24, 2009 29
  • 30. OEE for Process Improvement Conclusion! Process Improvement Improved Productivity and Asset Utilization… Why OEE?  Provides Data to make Suppliers more Accountable The Science of OEE  EquipmentSuppliers  Consumables / Raw Materials Suppliers Guidelines The Technologies  Gather Hard Data related to equipment performance. Culture of OEE The Culture of OEE  Identify equipment problems.  Justify Capital Improvements or Asset Reductions.  Motivate Operators and Maintenance Team  Drive Uniformity in Plant Scorecard calculations. April 24, 2009 30
  • 31. Questions? Web Site: www.AvidSolutionsInc.com Contact Information: Ed Brown – 919.468.4334 x221 Eric Mayer – 919.468.4334 x202 April 24, 2009 31