SlideShare a Scribd company logo
ME6005
PROCESS PLANNING AND COST
ESTIMATION
• UNIT I INTRODUCTION TO PROCESS
PLANNING
• UNIT II PROCESS PLANNING ACTIVITIES
• UNIT III INTRODUCTION TO COST ESTIMATION
• UNIT IV PRODUCTION COST ESTIMATION
• UNIT V MACHINING TIME CALCULATION
UNIT III INTRODUCTION TO COST
ESTIMATION
• Importance of costing and estimation
• Methods of costing-elements of cost
estimation
• Types of estimates
• Estimating procedure
• Estimation labor cost, material cost
• Allocation of over head charges
• Calculation of depreciation cost
What is mean by cost estimation?
• Estimation of the expected cost of producing a
job
• Executing a manufacturing order before the
actual production is taken up
• Predicting what new products will cost before
they are made.
Definition
Costing or cost accounting means classifying,
recording and allocating the appropriate
expenditure for determining the cost of
production and achieved by keeping a
continuous record of all the costs involved in
manufacturing
REASONS FOR DOING
ESTIMATES
• Should the product be produced?
• When a company designs a new product
• To assist management in making an
intelligent decision about producing the
product.
General procedure
• A cost estimate must be developed for jigs,
fixtures, tools, dies and gauges.
• Also, the cost of any capital equipment must
be entered into the estimate. These figures are
usually supplied through quotation by vendors.
• An estimate of this nature will include a vast
amount of details, because if management
approves the project, the estimate now
becomes the budget.
OBJECTIVES OR PURPOSE OF
ESTIMATING
(i) To establish the selling price of a product.
(ii) To ascertain whether a proposed product can be
manufactured and marketed
profitably.
(iii) To determine how much must be invested in
equipment.
(iv) To find whether parts or assemblies can be more
cheaply fabricated or purchased from outside (make or
buy decision).
(v) To determine the most economical process, tooling or
material for making a product.
FUNCTIONS OF ESTIMATING
(i) To calculate the cost of new material needed to
manufacture a product.
(ii) To find the cost of parts to be purchased from
outside vendors.
(iii) To find the cost of equipment, machinery, tools, jigs
and fixtures etc. required to be
purchased to make the product.
(iv) To calculate the direct and indirect labour cost
associated with the manufacture of the
product, based upon work study.
(v) To calculate various overhead charges associated
with the product.
Cont.…
(vi) To decide about the profit to be charged, taking into
consideration other manufacturers of same product in the
market.
(vii) To calculate the selling price of the product.
(viii) To maintain records of previous estimating
activities of the company for future
references.
(ix) To decide the most economical method of making the
product.
(x) To submit cost estimates with the competent authority
for further action.
COMPONENTS OF A COST ESTIMATE
OR JOB ESTIMATE
1. Cost of design.
2. Cost of drafting.
3. Cost of research and development.
4. Cost of raw materials.
5. Cost of labour.
6. Cost of inspection
7. Cost of tools, jigs and fixtures.
8. Overhead cost
1. Cost of Design
• The cost of design of a component or product is
estimated by ascertaining the expected time for the
design of that component
• The estimate design time multiplied by the salary of
designer per unit time gives the estimated cost of
design
• If the design of the component is done by some
outside agency, the total amount paid to outside
agency gives the cost of design.
2. Cost of Drafting
• Once the design of the component is
complete, its drawings have to be prepared
by draftsman
• The expected time to be spent in drawing or
drafting is estimated and is then multiplied by
the standard drafting rate or by the salary of
the draftsman per unit time to get estimated
cost of drafting
3. Cost of Research and Development
Work
• Before taking up the manufacturing of actual
components/parts considerable time and
money has to be spent on research and
development.
• The research may be theoretical, experimental
or developmental research.
• The cost of R and D can be estimated by
considering various items of expenditure
incurred during R and D work
4. Cost of Raw Material
(i) A list of all the materials used in the manufacture of the
product is made which includes
the direct as well as indirect materials.
(ii) The quantity (weight or volume) of all the material
expected to be used in the manufacture of the product is
estimated. The allowance for material wastage, spoilage and
scarp are also added for each component/part.
(iii) Cost of each material is estimated by multiplying the
estimated quantity of each material with its estimated future
price. The estimate of future price of a material is made keeping
in view of present prices and general trends and variations.
(iv) Estimated cost of all the materials is added to get the overall
estimated material cost.
5. Cost of Labour
• The cost of labour involved in the manufacture of a
product is estimated by estimating the labour time
needed to manufacture the product and multiplying it
by cost of labour per hour.
• In order to estimate the labour time expected to be
spent on a job, one must have thorough knowledge of
the various operations to be performed, machines to
be used, sequence of operations, tools to be used and
labour rates
6. Cost of Inspection
• A product being manufactured is inspected at
various stages during its manufacture.
• It may be inspection of raw material or in-
process inspection or inspection of finished
goods.
7. Cost and Maintenance Charges of
Tools, Jigs and Fixtures
• The cost of tools, jigs, fixtures etc., is estimated
considering their present prices, market trend and the
number of times a particular tool can be used during
its life-time.
• The estimated cost divided by the number of jobs it
can make, gives the tool cost per unit produced
8. Overhead Costs
• Overhead or indirect costs are those which are not
incurred specifically for any one order or product and
these can not be charged directly to a specific order or
product
• The overhead costs may be estimated by referring
to the records of overhead costs in similar items
produced in past
ESTIMATE FORM
METHODS OF COSTING
• 1. Job costing or order costing,
• 2. Batch costing,
• 3. Process costing,
• 4. Departmental costing,
• 5. Operating cost method,
• 6. Unit cost method, and
• 7. Multiple cost method.
Classification of cost
• 1. Classification of cost according to elements
• (i) Materials cost (ii) Labour cost
• (iii) Overheads
• 2. Classification of cost according to function
• (i) Production cost
• ii) Administrative cost
• (iii) Selling cost
• (iv) Overhead cost
• 3. Classification of cost according to variability
• (i) Fixed cost
• (ii) Variable cost
• (iii) Semi-variable cost
• 4. Classification of cost into direct and indirect costs
• (i) Direct cost
• (ii) Indirect cost
• 5. Classification of cost according to
capital and revenue
• (i) Capital cost
• (ii) Revenue cost
ELEMENTS OF COST
INTRODUCTION TO COST ESTIMATION
Analysis of overhead expanses
• (a) Factory expenses,
• (b) Administrative expenses,
• (c) Selling expenses, and
• (d) Distribution expenses.
COST OF PRODUCT (LADDER OF COST)
1. Prime cost: It consists of direct material cost,
direct labour cost and direct expenses.
Prime cost = Direct material cost + Direct labour cost
+ Direct expenses.
Prime cost is also called as direct cost.
2. Factory cost: It consists of prime cost and
factory expenses.
Factory cost = prime cost + factory expenses.
Factory cost is also named as works cost.
3. Office cost: It consists of factory cost and
administrative expenses.
Office cost = Factory cost + Administrative expenses
It is also named as manufacturing cost (or) cost of
production.
4. Total cost: It includes manufacturing cost and
selling and distribution expenses.
Total cost = Manufacturing cost + selling and
distribution expenses.
Selling price
• If the profit is added in the total cost of the
product, it is called selling price.
Selling price = Total cost + Profit
= Total cost – Loss
xs
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
• Estimate the weight of material required
for manufacturing 220 pieces of shaft as
shown in Fig. The shafts are made of mild
steel which weighs 7.87 gm/cm3 and costs
Rs.100 per kg. Also calculate the material cost
for 220 such shafts.
INTRODUCTION TO COST ESTIMATION
ESTIMATION OF LABOUR COST
• Since the labour cost contributes a
significant amount of total cost of product,
therefore the effective and efficient
determination of labour cost is essential.
• In order to calculate the labour cost,
an estimator must have the · knowledge
of (i) all the operations involved, (ii)
the tools, and (iii) the machines used for
production.
(i) Set up time,
(ii) Operation time,
(a) Handling time, and
(b) Machining time.
(iii) Tear down time,
(iv) Miscellaneous allowances,
(a) Personal allowances,
(b) Fatigue allowances,
(c) Contingency allowances,
(d) Process allowances,
(e) Interference allowances,
(f) Special allowances.
• Set up Time
Set up time is the time required for setting
and fixing the jobs and tools on the machine.
• Operation Time
Operation time is the time required to
perform all the elements of an operation
(a) Handling time
It is the time required for loading and
unloading operations.
(b) Machining time
It is the time taken by the job to perform
the operation on the machine .
• Tear Down Time
Tear down time is the time taken to remove job,
tools, and other auxiliary equipment from the
machine after the last element of operation has
been completed.
• Miscellaneous Allowances:
Allowance is the additional time allowed to
perform the work over and above the basic time.
Standard time = Basic time + Allowances
Types of Allowances
1.Relaxation allowances
(a)Personal need allowances
Personal allowances are provided to the worker to fulfill
his/her personal needs such as washing hands, going to the
lavatory, getting water, tea, etc.
(b) Fatigue allowances.
Fatigue allowances are intended to provide a work
man an opportunity to recover from physiological and
psychological effects of fatigue caused by carrying out a
specified task under specified condition.
2. Contingency allowances,
Contingency allowances are provided for small
unavoidable delays as well as for occasional and minor extra
work.
3. Process allowances
Process allowances are provided to compensate
for enforced idleness during a process.
4. Interference allowances
Interference allowance is provided when two or
more work elements occur simultaneously.
5. Special allowances.
• Special allowances are provided for activities
which are not normally a part of the operation
cycle, but they are essential for satisfactory
performance of the work .
These include the following:
(a) Start-up allowance, (b) Shut-down allowance,
(c) Cleaning allowance. (d) Tool allowance
(d) (f) Changeover allowance.
Calculation of Standard Time
• Standard time is the time allowed to an operator
to carry out the specified task under specified
conditions and defined level of performance.
• Standard time is defined as the total time in
which a job should be completed at standard
performance.
Standard time = Normal time + Allowances
Normal time, also known as basic time, is the time for
carrying out a work at standard rating.
Normal (or basic) time =Observed time x Rating factor
• Rating factor, also known as performance
rating, is a levelling factor to convert
observed timings into normal timings
1.In a manual operation, observed time for a cycle of operation is
0.5 minute and the rating factor as observed by the time study
engineer is 125%. All allowances put together is 15% of normal
time. Estimate the standard time. [A.U, Nov/Dec 2014]
INTRODUCTION TO COST ESTIMATION
2.In a manufacturing process, the observed
time for one cycle of operation is 0.75 minute.
The rating factor is 110%. The following are
the various allowances as the percentage of
normal time.
• Personal allowance = 3%
• Relaxation allowance = 10%
• Delay allowance = 2%
Estimate the standard time.
INTRODUCTION TO COST ESTIMATION
ESTIMATION OF OVERHEADS AND
VARIOUS COST COMPONENTS
• Prime cost
• Factory or workers cost
• Manufacturing or production cost
• Total or ultimate cost, and
• Selling price.
2. Factory cost = Prime cost + Factory expenses
1.For manufacturing a 'milling machine', the
expenditure is tabulated in Table
• Find out (a) Prime cost, (b) Factory cost,
(c) Total cost of production, (d) Cost of
sales, and (e) Selling price.
• Given Data: Refer Table
• To find:
(a) Prime cost, (b) Factory cost,
(c) Production cost, (d) Cost of sales and
(e) Selling price.
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
From the following .data for a sewing machine
manufacturer, prepare a statement showing
prime cost, works/factory cost, production cost, total
cost and profit.
Rs.
• Value of stock of material as on 1.04.2010 26,000
• Material purchased 2,74,000
• Wages to labour 1,20,000
• Depreciation of plant and machinery 8,000
• Depreciation of office equipment 2,000
• Rent, taxes and insurance of factory 16,000
• General administrative expenses 3,400.
• Water, power and telephone bills of factory 9,600
• Water, lighting and telephone bills of office 2,500
• Material transportation in factory 2,000
• Rent of office building 2,000
• Direct expenses 5,000
• Commission and pay of salesman 10,500
• Repair and maintenance of plant 1,00
• Works manager salary 30,000
• Salary of office staff 60,000
• Value of stock of material as on 31.03.2011 36,000
• Sale of products 6,36,000
Solution:
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
3.Calculate prime cost, factory cost, production
cost, total cost and selling price per item from the
data given below in Table for the year 2012-13.
S.No. Particulars Expenses
1 Cost of raw material in stock as on 25,000
01.04.2012
2 Raw material purchased 40,000
3 Direct labour cost 14,000
4 Direct expenses 1,000
5 Factory/work overheads 9,750
6 Administrative expenditure 6,500
7 Selling and distribution expenses 3,250
8 Number of items produced 650
9 Cost of raw material in stock as on 15,000
31.03.2013
Net profit of the items is 10% of the total cost of the product.
Given Data: Refer Table
To find:
(a) Prime cost (b) Factory cost (c) Production cost
(d) Total cost (e) Selling price
Solution: It may be noted that 650 number of items were
produced during 2012-13.
INTRODUCTION TO COST ESTIMATION
• A manufacturer is making 100 units of an
item per hour and incurs the following
expenses:
• Direct material cost = Rs. 35
• Direct labour cost = Rs. 200
• Direct expenses = Rs. 75
• Factory on cost = 150% of labour
cost
• Office on cost = 30% of
factory cost
Find out the selling price for a profit of 15% on
the selling price. [A. U., Nov/Dec 2015)
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
ALLOCATION OF OVERHEAD EXPENSES
• The different methods of allocation of overhead expenses
are:
1. By percentage (i.e., allocation by cost proportion)
(a) Percentage on prime cost,
(b) Percentage on direct labour cost, and
(c) Percentage on direct material cost.
2. By hourly rate (i.e., allocation by hourly rate)
(a) Man-hour rate
(b) Machine hour rate, and
(c) Combination of man-hour and machine-hour rate .
3. By unit rate (i.e., allocation by unit rate)
(a) Unit rate method
Allocation by Percentage on Prime Cost
This percentage multiplied by the prime cost of individual
item
gives the part of total overheads to be allocated to that
item of manufacture.
Suitability: This method is suitable (a) where only one type
of product is being manufactured, and (b) where direct
labour and direct material costs are nearly same .
Disadvantages: This method ignores the difference in labour
rates, material, and machines employed for the manufacture
of different items.
A manufacturing firm has total overheads of•
Rs.1,20,000 and total prime cost Rs.2.5 lacs for the year
2002-03. Find out the share of over heads to be allocated to
products A and B
by proportional to prime cost method using the following
data.
Product A ProductB
Direct material cost Rs. 900 Rs. 1000
Direct labour cost Rs. 700 Rs. 600
Direct other expenses Rs. 300 Rs. 250
INTRODUCTION TO COST ESTIMATION
Allocation by Percentage on Direct
Labour Cost
• This percentage of overheads multiplied
by the direct labour on the manufacture
of the item gives the part of total
overhead costs allocated to that item.
• Total overheads of a factory for the year
2000-01 were Rs. 7, 75,750 and total direct
labour wages during that year were
Rs.4,50,000. Find out the overheads
allocation to a product for which direct
labour cost is Rs.950. Use allocation by
proportional to direct labour cost method.
INTRODUCTION TO COST ESTIMATION
Allocation by Percentage on Direct
Material Cost
• In this method, allocation of overheads
depends upon the total direct material cost.
A foundry department of a factory manufacturing
engine crankcase had Rs.1,82,000 as total overheads
while the material cost was Rs.4,20,000. Calculate the
percentage on-cost.
Allocation by Man-hour Rate
• In this method, the overhead cost is
allocated on the total hours spent by the
direct labour and not on the wages paid to
them .
Allocation by Man-hour Rate
A factory has 15 lathes of same make and
capacity and 5 shapers of same make and
capacity. Lathes occupy30 m2 area while shapers
occupy 15 m2 area. During the calendar year,
factory expenses for this section are as follows:
(i) Building rent and depreciation = Rs.
5,000; (ii) Indirect labour and material = Rs.
15,000; (iii) Insurance = Rs. 2,000; (iv)
Depreciation charges of lathes = Rs. 5,000; (v)
Depreciation charges of shapers = Rs. 3,000; (vi)
Power consumption for lathes = Rs. 2,000;
(vii)Power consumption f or shapers= Rs. 1,000.
Find out tile machine hour rate for lathe and
shapers, if all the lathes and shapers work for
25,000 hours and 8,000 hours respectively.
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
Allocation by Combination of Man-
hour and Machine Hour Rate
• This method is used in manufacturing
industries where work in some
departments are carried out by hand
and work in the other departments are
done by machines.
Allocation by Unit Rate
DEPRECIATION
• The reduction in the value and efficiency
of the plant, equipment or any fixed asset
because of wear and tear, due to passage
of time, use and climatic conditions is known
as depreciation.
• Depreciation is the process of allocating the
acquisition cost of the tangible asset less salvage
value, if any, in a systematic and a rational
manner over the estimated life of the asset.
CAUSES OF DEPRECIATION
METHODS OF DEPRECIATION
1. Straight line method
2. Diminishing balance (or reducing balance) method.
3. Sinking fund method.
4. Annuity method
5. Sum of year's digits method.
6. Insurance policy method.
7. Machine-hour method.
8. Production-unit method.
9. Revaluation (or regular valuation) method
10.Retirement method
1. Straight line method
• In this method, the amount of depreciation
is distributed over the useful life of the
machine in equal periodic instalments.
C = Initial cost of the machine in rupees,
S = Scrap (or salvage) value in rupees,
n = Estimated life of the machine in years,
D = Depreciation amount per year.
2.Diminishing Balance (or Reducing
Balance) Method
• The book value of the machine goes on
decreasing as its existence continues. Hence in
this method a certain percentage of the
current book value is taken as depreciation.
c = Initial cost of the machine in rupees,
S = Scrap value in rupees,
p =Fixed percentage for calculating yearly
depreciation
n = Estimated life of the machine in years,
3. Sinking Fund Method
4. Annuity Method
5.Sum of the Year's Digit Method
The scrap value of the asset is deducted from its original cost and the
remaining balance is spread over the asset's life.in decreasing proportion.
Formula used:
"If 'n' is the estimated life of the asset, the rate is calculated each
period as a fraction in which the denominator is always the sum of the
series I, 2, 3,……, n and the numerator for the first period is 'n ',for the
second 'n - l ',and so on."
6.Insurance Policy Method
In this method, an insurance policy
is made for the amount required to replace
the machine at the end of its useful life.
. Premiums are paid on the insurance
policy. When the policy matures, the
insurance company provides sufficient sum
to replace
the machine.
7.Machine Hour Method
8.Production Unit Method
9. Revaluation (or Regular Valuation) Method
The depreciation is equal to the difference
between the values assigned to the asset at the beginning
and end of each year.
10.Retirement Method
whole original cost of the asset is charged to
depreciation expenses in the year in which it is being
retired from the service.
INTRODUCTION TO COST ESTIMATION

More Related Content

PPTX
Boiler Draught (Types, construction and working)
avesahemad
 
PPT
introduction to process planning murugananthan
Murugananthan K
 
PPTX
COMPUTER AIDED PROCESS PLANNING (CAPP)
Victor Al
 
PPTX
Press work
Rahul Pasale
 
PPTX
Unit ii Process Planning
Asha A
 
PPTX
Deep drawing
khushbakhat nida
 
PPT
Introduction to jigs and fixtures
Hasitha Wipulaguna
 
PPT
Jigs and fixtures imp
Bhagyashri Dhage
 
Boiler Draught (Types, construction and working)
avesahemad
 
introduction to process planning murugananthan
Murugananthan K
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
Victor Al
 
Press work
Rahul Pasale
 
Unit ii Process Planning
Asha A
 
Deep drawing
khushbakhat nida
 
Introduction to jigs and fixtures
Hasitha Wipulaguna
 
Jigs and fixtures imp
Bhagyashri Dhage
 

What's hot (20)

PPTX
Numeric control
KANA RAM MEENA
 
DOCX
Product design factors
Supradip Das
 
PPTX
PPT on Lathe machine
Himanshu Yadav
 
PPTX
Tool geometry
Prem Kumar Soni
 
PPTX
METAL CUTTING
Kunj Thummar
 
PPT
Product design specifications 1
University of Engineering &Technology, Lahore
 
PPTX
Industrial engineering unit 2 new
mohsinmmm
 
PPTX
PRODUCTION COST ESTIMATION
MohanKirthik
 
PPTX
Unit 5A Gear Manufacturing Methods
Mechbytes
 
PPTX
Dry expansion evaporators1
Anand Prithviraj
 
PDF
Lathe operations
DEBOLINAMUKHERJEE7
 
PPTX
Lubrication and-cooling-system-presentation
Md Sujon Babu
 
PPT
Gear manufacturing process
KANNANS94
 
PPT
Jigs and Fixture
Kondayya Devarakonda
 
PPTX
Plant site selection and layout
Robin Gulati
 
PPTX
Introduction to Spark ignition four stroke engine
PrabathDissanayake8
 
PPT
Nc programming
Sudhir Reddy
 
PDF
Fluid power automation unit 1 introduction
DineshS158
 
PPTX
LUBRICATING AND COOLING SYSTEM
Ronak Parmar
 
PPT
Tig welding ppt overview
Abhishek Agyarapu
 
Numeric control
KANA RAM MEENA
 
Product design factors
Supradip Das
 
PPT on Lathe machine
Himanshu Yadav
 
Tool geometry
Prem Kumar Soni
 
METAL CUTTING
Kunj Thummar
 
Product design specifications 1
University of Engineering &Technology, Lahore
 
Industrial engineering unit 2 new
mohsinmmm
 
PRODUCTION COST ESTIMATION
MohanKirthik
 
Unit 5A Gear Manufacturing Methods
Mechbytes
 
Dry expansion evaporators1
Anand Prithviraj
 
Lathe operations
DEBOLINAMUKHERJEE7
 
Lubrication and-cooling-system-presentation
Md Sujon Babu
 
Gear manufacturing process
KANNANS94
 
Jigs and Fixture
Kondayya Devarakonda
 
Plant site selection and layout
Robin Gulati
 
Introduction to Spark ignition four stroke engine
PrabathDissanayake8
 
Nc programming
Sudhir Reddy
 
Fluid power automation unit 1 introduction
DineshS158
 
LUBRICATING AND COOLING SYSTEM
Ronak Parmar
 
Tig welding ppt overview
Abhishek Agyarapu
 
Ad

Similar to INTRODUCTION TO COST ESTIMATION (20)

PPTX
INTRODUCTION TO COST ESTIMATION
SIVASHANKAR N
 
PPTX
Unit 3
Aravind Ra
 
PPTX
INTRODUCTION TO COST ESTIMATION
DJAGADEESH1
 
PPTX
PPCE UNIT- 3.pptx
Aravind Ra
 
PPTX
INTRODUCTION TO COST ESTIMATION
SathishkumarM89
 
PPTX
PPCE Unit-3.pptx
DJAGADEESH1
 
PPTX
PPCE Unit-3.pptx
Dr.PERIASAMY K
 
PDF
Process planning and cost estimation unit iii
s Kumaravel
 
PPTX
chapter 3.pptxhhhhhhhhhhhhhhhccccccccccccccccccc
YohannesBerhanu6
 
PPTX
chapter 3.pptx cost Accounting by Dr. YOHANNES
YohannesBerhanu6
 
PPTX
UNIT-3.pptx
PChakravarthyMECH
 
PPTX
LESSON 8 PROCESS COSTING accounting.pptx NEW.pptx
EldaahToi
 
PPTX
cost accounting , Element & cost sheet.pptx
RohitKumarUpadhyay3
 
PPSX
Job costing power point show
Maliha Jahan
 
PPTX
Product costing system
Mah Noor
 
PPT
People Soft Standard Costing Dmug
rcaldwell002
 
PDF
Process design & steps
Asheem Kumar Palo
 
PDF
Icwaicas4
Aayush Sharma
 
PPTX
cost accounting ppt.pptx
RIDDHIDOSHI37
 
INTRODUCTION TO COST ESTIMATION
SIVASHANKAR N
 
Unit 3
Aravind Ra
 
INTRODUCTION TO COST ESTIMATION
DJAGADEESH1
 
PPCE UNIT- 3.pptx
Aravind Ra
 
INTRODUCTION TO COST ESTIMATION
SathishkumarM89
 
PPCE Unit-3.pptx
DJAGADEESH1
 
PPCE Unit-3.pptx
Dr.PERIASAMY K
 
Process planning and cost estimation unit iii
s Kumaravel
 
chapter 3.pptxhhhhhhhhhhhhhhhccccccccccccccccccc
YohannesBerhanu6
 
chapter 3.pptx cost Accounting by Dr. YOHANNES
YohannesBerhanu6
 
UNIT-3.pptx
PChakravarthyMECH
 
LESSON 8 PROCESS COSTING accounting.pptx NEW.pptx
EldaahToi
 
cost accounting , Element & cost sheet.pptx
RohitKumarUpadhyay3
 
Job costing power point show
Maliha Jahan
 
Product costing system
Mah Noor
 
People Soft Standard Costing Dmug
rcaldwell002
 
Process design & steps
Asheem Kumar Palo
 
Icwaicas4
Aayush Sharma
 
cost accounting ppt.pptx
RIDDHIDOSHI37
 
Ad

More from MohanKirthik (20)

PPTX
Mechanical tests of metals
MohanKirthik
 
PPTX
Mechanical properties
MohanKirthik
 
PPTX
Ceramics and composites
MohanKirthik
 
PPTX
Plastics
MohanKirthik
 
PPTX
Non metallic materials --- polymers
MohanKirthik
 
PPTX
Cast iron
MohanKirthik
 
PPTX
Maraging steel
MohanKirthik
 
PPT
HSLA steel
MohanKirthik
 
PPTX
Stainless steel, tool steel
MohanKirthik
 
PPTX
Ferrous metals
MohanKirthik
 
PPTX
Vacuum plasma hardening
MohanKirthik
 
PPT
Case hardening
MohanKirthik
 
PPTX
phase diagram
MohanKirthik
 
PPTX
iron carbon system
MohanKirthik
 
PPTX
heat treatment
MohanKirthik
 
PPTX
cooling curve
MohanKirthik
 
PPTX
PROCESS PLANNING ACTIVITIES
MohanKirthik
 
PPTX
MACHINING TIME CALCULATION
MohanKirthik
 
PPTX
INTRODUCTION TO PROCESS PLANNING
MohanKirthik
 
PPT
Work study
MohanKirthik
 
Mechanical tests of metals
MohanKirthik
 
Mechanical properties
MohanKirthik
 
Ceramics and composites
MohanKirthik
 
Plastics
MohanKirthik
 
Non metallic materials --- polymers
MohanKirthik
 
Cast iron
MohanKirthik
 
Maraging steel
MohanKirthik
 
HSLA steel
MohanKirthik
 
Stainless steel, tool steel
MohanKirthik
 
Ferrous metals
MohanKirthik
 
Vacuum plasma hardening
MohanKirthik
 
Case hardening
MohanKirthik
 
phase diagram
MohanKirthik
 
iron carbon system
MohanKirthik
 
heat treatment
MohanKirthik
 
cooling curve
MohanKirthik
 
PROCESS PLANNING ACTIVITIES
MohanKirthik
 
MACHINING TIME CALCULATION
MohanKirthik
 
INTRODUCTION TO PROCESS PLANNING
MohanKirthik
 
Work study
MohanKirthik
 

Recently uploaded (20)

PDF
July 2025: Top 10 Read Articles Advanced Information Technology
ijait
 
PDF
Traditional Exams vs Continuous Assessment in Boarding Schools.pdf
The Asian School
 
PPTX
22PCOAM21 Session 1 Data Management.pptx
Guru Nanak Technical Institutions
 
PDF
Principles of Food Science and Nutritions
Dr. Yogesh Kumar Kosariya
 
PDF
Introduction to Ship Engine Room Systems.pdf
Mahmoud Moghtaderi
 
PDF
top-5-use-cases-for-splunk-security-analytics.pdf
yaghutialireza
 
PDF
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
PDF
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
PPTX
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
PDF
dse_final_merit_2025_26 gtgfffffcjjjuuyy
rushabhjain127
 
PDF
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
PDF
Biodegradable Plastics: Innovations and Market Potential (www.kiu.ac.ug)
publication11
 
PPTX
Information Retrieval and Extraction - Module 7
premSankar19
 
PPTX
Chapter_Seven_Construction_Reliability_Elective_III_Msc CM
SubashKumarBhattarai
 
PPTX
Civil Engineering Practices_BY Sh.JP Mishra 23.09.pptx
bineetmishra1990
 
PPTX
AgentX UiPath Community Webinar series - Delhi
RohitRadhakrishnan8
 
PDF
20ME702-Mechatronics-UNIT-1,UNIT-2,UNIT-3,UNIT-4,UNIT-5, 2025-2026
Mohanumar S
 
PDF
Zero carbon Building Design Guidelines V4
BassemOsman1
 
PPTX
Victory Precisions_Supplier Profile.pptx
victoryprecisions199
 
PDF
Introduction to Data Science: data science process
ShivarkarSandip
 
July 2025: Top 10 Read Articles Advanced Information Technology
ijait
 
Traditional Exams vs Continuous Assessment in Boarding Schools.pdf
The Asian School
 
22PCOAM21 Session 1 Data Management.pptx
Guru Nanak Technical Institutions
 
Principles of Food Science and Nutritions
Dr. Yogesh Kumar Kosariya
 
Introduction to Ship Engine Room Systems.pdf
Mahmoud Moghtaderi
 
top-5-use-cases-for-splunk-security-analytics.pdf
yaghutialireza
 
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
dse_final_merit_2025_26 gtgfffffcjjjuuyy
rushabhjain127
 
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
Biodegradable Plastics: Innovations and Market Potential (www.kiu.ac.ug)
publication11
 
Information Retrieval and Extraction - Module 7
premSankar19
 
Chapter_Seven_Construction_Reliability_Elective_III_Msc CM
SubashKumarBhattarai
 
Civil Engineering Practices_BY Sh.JP Mishra 23.09.pptx
bineetmishra1990
 
AgentX UiPath Community Webinar series - Delhi
RohitRadhakrishnan8
 
20ME702-Mechatronics-UNIT-1,UNIT-2,UNIT-3,UNIT-4,UNIT-5, 2025-2026
Mohanumar S
 
Zero carbon Building Design Guidelines V4
BassemOsman1
 
Victory Precisions_Supplier Profile.pptx
victoryprecisions199
 
Introduction to Data Science: data science process
ShivarkarSandip
 

INTRODUCTION TO COST ESTIMATION

  • 1. ME6005 PROCESS PLANNING AND COST ESTIMATION
  • 2. • UNIT I INTRODUCTION TO PROCESS PLANNING • UNIT II PROCESS PLANNING ACTIVITIES • UNIT III INTRODUCTION TO COST ESTIMATION • UNIT IV PRODUCTION COST ESTIMATION • UNIT V MACHINING TIME CALCULATION
  • 3. UNIT III INTRODUCTION TO COST ESTIMATION • Importance of costing and estimation • Methods of costing-elements of cost estimation • Types of estimates • Estimating procedure • Estimation labor cost, material cost • Allocation of over head charges • Calculation of depreciation cost
  • 4. What is mean by cost estimation? • Estimation of the expected cost of producing a job • Executing a manufacturing order before the actual production is taken up • Predicting what new products will cost before they are made.
  • 5. Definition Costing or cost accounting means classifying, recording and allocating the appropriate expenditure for determining the cost of production and achieved by keeping a continuous record of all the costs involved in manufacturing
  • 6. REASONS FOR DOING ESTIMATES • Should the product be produced? • When a company designs a new product • To assist management in making an intelligent decision about producing the product.
  • 7. General procedure • A cost estimate must be developed for jigs, fixtures, tools, dies and gauges. • Also, the cost of any capital equipment must be entered into the estimate. These figures are usually supplied through quotation by vendors. • An estimate of this nature will include a vast amount of details, because if management approves the project, the estimate now becomes the budget.
  • 8. OBJECTIVES OR PURPOSE OF ESTIMATING (i) To establish the selling price of a product. (ii) To ascertain whether a proposed product can be manufactured and marketed profitably. (iii) To determine how much must be invested in equipment. (iv) To find whether parts or assemblies can be more cheaply fabricated or purchased from outside (make or buy decision). (v) To determine the most economical process, tooling or material for making a product.
  • 9. FUNCTIONS OF ESTIMATING (i) To calculate the cost of new material needed to manufacture a product. (ii) To find the cost of parts to be purchased from outside vendors. (iii) To find the cost of equipment, machinery, tools, jigs and fixtures etc. required to be purchased to make the product. (iv) To calculate the direct and indirect labour cost associated with the manufacture of the product, based upon work study. (v) To calculate various overhead charges associated with the product.
  • 10. Cont.… (vi) To decide about the profit to be charged, taking into consideration other manufacturers of same product in the market. (vii) To calculate the selling price of the product. (viii) To maintain records of previous estimating activities of the company for future references. (ix) To decide the most economical method of making the product. (x) To submit cost estimates with the competent authority for further action.
  • 11. COMPONENTS OF A COST ESTIMATE OR JOB ESTIMATE 1. Cost of design. 2. Cost of drafting. 3. Cost of research and development. 4. Cost of raw materials. 5. Cost of labour. 6. Cost of inspection 7. Cost of tools, jigs and fixtures. 8. Overhead cost
  • 12. 1. Cost of Design • The cost of design of a component or product is estimated by ascertaining the expected time for the design of that component • The estimate design time multiplied by the salary of designer per unit time gives the estimated cost of design • If the design of the component is done by some outside agency, the total amount paid to outside agency gives the cost of design.
  • 13. 2. Cost of Drafting • Once the design of the component is complete, its drawings have to be prepared by draftsman • The expected time to be spent in drawing or drafting is estimated and is then multiplied by the standard drafting rate or by the salary of the draftsman per unit time to get estimated cost of drafting
  • 14. 3. Cost of Research and Development Work • Before taking up the manufacturing of actual components/parts considerable time and money has to be spent on research and development. • The research may be theoretical, experimental or developmental research. • The cost of R and D can be estimated by considering various items of expenditure incurred during R and D work
  • 15. 4. Cost of Raw Material (i) A list of all the materials used in the manufacture of the product is made which includes the direct as well as indirect materials. (ii) The quantity (weight or volume) of all the material expected to be used in the manufacture of the product is estimated. The allowance for material wastage, spoilage and scarp are also added for each component/part. (iii) Cost of each material is estimated by multiplying the estimated quantity of each material with its estimated future price. The estimate of future price of a material is made keeping in view of present prices and general trends and variations. (iv) Estimated cost of all the materials is added to get the overall estimated material cost.
  • 16. 5. Cost of Labour • The cost of labour involved in the manufacture of a product is estimated by estimating the labour time needed to manufacture the product and multiplying it by cost of labour per hour. • In order to estimate the labour time expected to be spent on a job, one must have thorough knowledge of the various operations to be performed, machines to be used, sequence of operations, tools to be used and labour rates
  • 17. 6. Cost of Inspection • A product being manufactured is inspected at various stages during its manufacture. • It may be inspection of raw material or in- process inspection or inspection of finished goods.
  • 18. 7. Cost and Maintenance Charges of Tools, Jigs and Fixtures • The cost of tools, jigs, fixtures etc., is estimated considering their present prices, market trend and the number of times a particular tool can be used during its life-time. • The estimated cost divided by the number of jobs it can make, gives the tool cost per unit produced
  • 19. 8. Overhead Costs • Overhead or indirect costs are those which are not incurred specifically for any one order or product and these can not be charged directly to a specific order or product • The overhead costs may be estimated by referring to the records of overhead costs in similar items produced in past
  • 21. METHODS OF COSTING • 1. Job costing or order costing, • 2. Batch costing, • 3. Process costing, • 4. Departmental costing, • 5. Operating cost method, • 6. Unit cost method, and • 7. Multiple cost method.
  • 22. Classification of cost • 1. Classification of cost according to elements • (i) Materials cost (ii) Labour cost • (iii) Overheads • 2. Classification of cost according to function • (i) Production cost • ii) Administrative cost • (iii) Selling cost • (iv) Overhead cost • 3. Classification of cost according to variability • (i) Fixed cost • (ii) Variable cost • (iii) Semi-variable cost • 4. Classification of cost into direct and indirect costs • (i) Direct cost • (ii) Indirect cost
  • 23. • 5. Classification of cost according to capital and revenue • (i) Capital cost • (ii) Revenue cost
  • 26. Analysis of overhead expanses • (a) Factory expenses, • (b) Administrative expenses, • (c) Selling expenses, and • (d) Distribution expenses.
  • 27. COST OF PRODUCT (LADDER OF COST) 1. Prime cost: It consists of direct material cost, direct labour cost and direct expenses. Prime cost = Direct material cost + Direct labour cost + Direct expenses. Prime cost is also called as direct cost. 2. Factory cost: It consists of prime cost and factory expenses. Factory cost = prime cost + factory expenses. Factory cost is also named as works cost.
  • 28. 3. Office cost: It consists of factory cost and administrative expenses. Office cost = Factory cost + Administrative expenses It is also named as manufacturing cost (or) cost of production. 4. Total cost: It includes manufacturing cost and selling and distribution expenses. Total cost = Manufacturing cost + selling and distribution expenses.
  • 29. Selling price • If the profit is added in the total cost of the product, it is called selling price. Selling price = Total cost + Profit = Total cost – Loss
  • 30. xs
  • 39. • Estimate the weight of material required for manufacturing 220 pieces of shaft as shown in Fig. The shafts are made of mild steel which weighs 7.87 gm/cm3 and costs Rs.100 per kg. Also calculate the material cost for 220 such shafts.
  • 41. ESTIMATION OF LABOUR COST • Since the labour cost contributes a significant amount of total cost of product, therefore the effective and efficient determination of labour cost is essential. • In order to calculate the labour cost, an estimator must have the · knowledge of (i) all the operations involved, (ii) the tools, and (iii) the machines used for production.
  • 42. (i) Set up time, (ii) Operation time, (a) Handling time, and (b) Machining time. (iii) Tear down time, (iv) Miscellaneous allowances, (a) Personal allowances, (b) Fatigue allowances, (c) Contingency allowances, (d) Process allowances, (e) Interference allowances, (f) Special allowances.
  • 43. • Set up Time Set up time is the time required for setting and fixing the jobs and tools on the machine. • Operation Time Operation time is the time required to perform all the elements of an operation (a) Handling time It is the time required for loading and unloading operations. (b) Machining time It is the time taken by the job to perform the operation on the machine .
  • 44. • Tear Down Time Tear down time is the time taken to remove job, tools, and other auxiliary equipment from the machine after the last element of operation has been completed. • Miscellaneous Allowances: Allowance is the additional time allowed to perform the work over and above the basic time. Standard time = Basic time + Allowances
  • 45. Types of Allowances 1.Relaxation allowances (a)Personal need allowances Personal allowances are provided to the worker to fulfill his/her personal needs such as washing hands, going to the lavatory, getting water, tea, etc. (b) Fatigue allowances. Fatigue allowances are intended to provide a work man an opportunity to recover from physiological and psychological effects of fatigue caused by carrying out a specified task under specified condition. 2. Contingency allowances, Contingency allowances are provided for small unavoidable delays as well as for occasional and minor extra work.
  • 46. 3. Process allowances Process allowances are provided to compensate for enforced idleness during a process. 4. Interference allowances Interference allowance is provided when two or more work elements occur simultaneously. 5. Special allowances. • Special allowances are provided for activities which are not normally a part of the operation cycle, but they are essential for satisfactory performance of the work . These include the following: (a) Start-up allowance, (b) Shut-down allowance, (c) Cleaning allowance. (d) Tool allowance (d) (f) Changeover allowance.
  • 47. Calculation of Standard Time • Standard time is the time allowed to an operator to carry out the specified task under specified conditions and defined level of performance. • Standard time is defined as the total time in which a job should be completed at standard performance. Standard time = Normal time + Allowances Normal time, also known as basic time, is the time for carrying out a work at standard rating. Normal (or basic) time =Observed time x Rating factor
  • 48. • Rating factor, also known as performance rating, is a levelling factor to convert observed timings into normal timings
  • 49. 1.In a manual operation, observed time for a cycle of operation is 0.5 minute and the rating factor as observed by the time study engineer is 125%. All allowances put together is 15% of normal time. Estimate the standard time. [A.U, Nov/Dec 2014]
  • 51. 2.In a manufacturing process, the observed time for one cycle of operation is 0.75 minute. The rating factor is 110%. The following are the various allowances as the percentage of normal time. • Personal allowance = 3% • Relaxation allowance = 10% • Delay allowance = 2% Estimate the standard time.
  • 53. ESTIMATION OF OVERHEADS AND VARIOUS COST COMPONENTS • Prime cost • Factory or workers cost • Manufacturing or production cost • Total or ultimate cost, and • Selling price.
  • 54. 2. Factory cost = Prime cost + Factory expenses
  • 55. 1.For manufacturing a 'milling machine', the expenditure is tabulated in Table
  • 56. • Find out (a) Prime cost, (b) Factory cost, (c) Total cost of production, (d) Cost of sales, and (e) Selling price. • Given Data: Refer Table • To find: (a) Prime cost, (b) Factory cost, (c) Production cost, (d) Cost of sales and (e) Selling price.
  • 59. From the following .data for a sewing machine manufacturer, prepare a statement showing prime cost, works/factory cost, production cost, total cost and profit. Rs. • Value of stock of material as on 1.04.2010 26,000 • Material purchased 2,74,000 • Wages to labour 1,20,000 • Depreciation of plant and machinery 8,000 • Depreciation of office equipment 2,000 • Rent, taxes and insurance of factory 16,000 • General administrative expenses 3,400. • Water, power and telephone bills of factory 9,600 • Water, lighting and telephone bills of office 2,500 • Material transportation in factory 2,000
  • 60. • Rent of office building 2,000 • Direct expenses 5,000 • Commission and pay of salesman 10,500 • Repair and maintenance of plant 1,00 • Works manager salary 30,000 • Salary of office staff 60,000 • Value of stock of material as on 31.03.2011 36,000 • Sale of products 6,36,000 Solution:
  • 63. 3.Calculate prime cost, factory cost, production cost, total cost and selling price per item from the data given below in Table for the year 2012-13. S.No. Particulars Expenses 1 Cost of raw material in stock as on 25,000 01.04.2012 2 Raw material purchased 40,000 3 Direct labour cost 14,000 4 Direct expenses 1,000 5 Factory/work overheads 9,750 6 Administrative expenditure 6,500 7 Selling and distribution expenses 3,250 8 Number of items produced 650 9 Cost of raw material in stock as on 15,000 31.03.2013 Net profit of the items is 10% of the total cost of the product.
  • 64. Given Data: Refer Table To find: (a) Prime cost (b) Factory cost (c) Production cost (d) Total cost (e) Selling price Solution: It may be noted that 650 number of items were produced during 2012-13.
  • 66. • A manufacturer is making 100 units of an item per hour and incurs the following expenses: • Direct material cost = Rs. 35 • Direct labour cost = Rs. 200 • Direct expenses = Rs. 75 • Factory on cost = 150% of labour cost • Office on cost = 30% of factory cost Find out the selling price for a profit of 15% on the selling price. [A. U., Nov/Dec 2015)
  • 69. ALLOCATION OF OVERHEAD EXPENSES • The different methods of allocation of overhead expenses are: 1. By percentage (i.e., allocation by cost proportion) (a) Percentage on prime cost, (b) Percentage on direct labour cost, and (c) Percentage on direct material cost. 2. By hourly rate (i.e., allocation by hourly rate) (a) Man-hour rate (b) Machine hour rate, and (c) Combination of man-hour and machine-hour rate . 3. By unit rate (i.e., allocation by unit rate) (a) Unit rate method
  • 70. Allocation by Percentage on Prime Cost This percentage multiplied by the prime cost of individual item gives the part of total overheads to be allocated to that item of manufacture. Suitability: This method is suitable (a) where only one type of product is being manufactured, and (b) where direct labour and direct material costs are nearly same . Disadvantages: This method ignores the difference in labour rates, material, and machines employed for the manufacture of different items.
  • 71. A manufacturing firm has total overheads of• Rs.1,20,000 and total prime cost Rs.2.5 lacs for the year 2002-03. Find out the share of over heads to be allocated to products A and B by proportional to prime cost method using the following data. Product A ProductB Direct material cost Rs. 900 Rs. 1000 Direct labour cost Rs. 700 Rs. 600 Direct other expenses Rs. 300 Rs. 250
  • 73. Allocation by Percentage on Direct Labour Cost • This percentage of overheads multiplied by the direct labour on the manufacture of the item gives the part of total overhead costs allocated to that item.
  • 74. • Total overheads of a factory for the year 2000-01 were Rs. 7, 75,750 and total direct labour wages during that year were Rs.4,50,000. Find out the overheads allocation to a product for which direct labour cost is Rs.950. Use allocation by proportional to direct labour cost method.
  • 76. Allocation by Percentage on Direct Material Cost • In this method, allocation of overheads depends upon the total direct material cost.
  • 77. A foundry department of a factory manufacturing engine crankcase had Rs.1,82,000 as total overheads while the material cost was Rs.4,20,000. Calculate the percentage on-cost.
  • 78. Allocation by Man-hour Rate • In this method, the overhead cost is allocated on the total hours spent by the direct labour and not on the wages paid to them .
  • 80. A factory has 15 lathes of same make and capacity and 5 shapers of same make and capacity. Lathes occupy30 m2 area while shapers occupy 15 m2 area. During the calendar year, factory expenses for this section are as follows: (i) Building rent and depreciation = Rs. 5,000; (ii) Indirect labour and material = Rs. 15,000; (iii) Insurance = Rs. 2,000; (iv) Depreciation charges of lathes = Rs. 5,000; (v) Depreciation charges of shapers = Rs. 3,000; (vi) Power consumption for lathes = Rs. 2,000; (vii)Power consumption f or shapers= Rs. 1,000. Find out tile machine hour rate for lathe and shapers, if all the lathes and shapers work for 25,000 hours and 8,000 hours respectively.
  • 84. Allocation by Combination of Man- hour and Machine Hour Rate • This method is used in manufacturing industries where work in some departments are carried out by hand and work in the other departments are done by machines.
  • 86. DEPRECIATION • The reduction in the value and efficiency of the plant, equipment or any fixed asset because of wear and tear, due to passage of time, use and climatic conditions is known as depreciation. • Depreciation is the process of allocating the acquisition cost of the tangible asset less salvage value, if any, in a systematic and a rational manner over the estimated life of the asset.
  • 88. METHODS OF DEPRECIATION 1. Straight line method 2. Diminishing balance (or reducing balance) method. 3. Sinking fund method. 4. Annuity method 5. Sum of year's digits method. 6. Insurance policy method. 7. Machine-hour method. 8. Production-unit method. 9. Revaluation (or regular valuation) method 10.Retirement method
  • 89. 1. Straight line method • In this method, the amount of depreciation is distributed over the useful life of the machine in equal periodic instalments. C = Initial cost of the machine in rupees, S = Scrap (or salvage) value in rupees, n = Estimated life of the machine in years, D = Depreciation amount per year.
  • 90. 2.Diminishing Balance (or Reducing Balance) Method • The book value of the machine goes on decreasing as its existence continues. Hence in this method a certain percentage of the current book value is taken as depreciation. c = Initial cost of the machine in rupees, S = Scrap value in rupees, p =Fixed percentage for calculating yearly depreciation n = Estimated life of the machine in years,
  • 91. 3. Sinking Fund Method 4. Annuity Method 5.Sum of the Year's Digit Method The scrap value of the asset is deducted from its original cost and the remaining balance is spread over the asset's life.in decreasing proportion. Formula used: "If 'n' is the estimated life of the asset, the rate is calculated each period as a fraction in which the denominator is always the sum of the series I, 2, 3,……, n and the numerator for the first period is 'n ',for the second 'n - l ',and so on."
  • 92. 6.Insurance Policy Method In this method, an insurance policy is made for the amount required to replace the machine at the end of its useful life. . Premiums are paid on the insurance policy. When the policy matures, the insurance company provides sufficient sum to replace the machine.
  • 93. 7.Machine Hour Method 8.Production Unit Method 9. Revaluation (or Regular Valuation) Method The depreciation is equal to the difference between the values assigned to the asset at the beginning and end of each year. 10.Retirement Method whole original cost of the asset is charged to depreciation expenses in the year in which it is being retired from the service.