DELAY ANALYSIS OF A CONSTRUCTION PROJECT- A CASE STUDY
Mr. Nagarjun Gowda B.S1, Ms. Chethana K.N2
1Assistant Professor, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India
2Student, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Construction technology has become an essential
part of any of the project, for timely and economical
completion of the project. A proper construction planning
and schedule acts as a main role ford different purposes. By
using the schedule, we can know the merely completion of
the project, contractors can recruit the necessary
manpower; can demand shifts or equipments to speed up
the project. The most important function of the project
management is to plan and control the project objective like
time, budget and setting out of resource productivity
standards to achieve the objectives of the project. Delay
happens in all construction projects. Where construction
project will vary in size, some will be in small. In vast
projects, analysis should be done for the purpose on making
right decisions on time and cost compensation claims. Many
type of software’s are available to plan, execute and control
the project; with the help of these software’s the project
management has become easier to evolve the construction
project. Large quantities of different kind of resources are
required for execution and the risk is more in case of big
projects. So, planning and scheduling in big projects is
essential. In this study, an effort is made in planning,
scheduling and delay analysis and updating of various
activities which is done using MS project.
Key Words: Construction Management, Planning,
Delay, Labour Productivity, Scheduling, Tracking.
1. INTRODUCTION
Construction industry plays an important role in the
economic growth of a country. It is the process of
implementing the plans, ideas, standards, specifications
and assigning the resources into a physical facility to meet
the specific requirements of owner.
Construction management can be defined as the
accomplishment of results through the combined effort of
the consultant, client and designer. Construction is a very
unique and creative practice which coverts four M’s of the
construction-Material, Manpower, Machinery and Money
into a systematic structure. Thus construction management
contains Planning, Executing and monitoring the
construction activities in a specific project.
1.1 Project Planning, Scheduling and Controlling
The main aim of the construction management is to plan
and schedule the resources within the frame work of a
project. The guidelines and procedures of the construction
management direct the managers how to utilize the
resources during the construction process. Before
execution of the work on the site all kinds of office works
such as planning, designing, estimating, negotiating,
purchasing, scheduling, controlling etc. should be done
carefully.
1.2 Construction Delay Analysis
Delay is one of the common problems in the construction
project. Delay of a construction project is defined as late
completion of the project as compared to the planned
schedule. Construction delays are often resulting of
miscommunication between contractors, subcontractors,
owners and suppliers.
These types of unrealistic exceptions are usually avoided
by clean and efficient planning mechanism, which clearly
specifies the work and timetable to be used. Delays in
construction project are quite expensive; sometimes they
may result in severe damages to the involved parties.
1.3 Objective of the Study
 Detailed literature study to define the various causes
of delay in construction projects
 Study on ongoing Project site to observe the activities
and to identify delay factors
 Determination of Critical Path using MS Projects
 The analysis also involves the process of scheduling
and tracking of a construction project activities in
software and related catch up programs due to delays.
2. METHODOLOGY
 Site Investigation.
 Studying Of BOQ & Drawings.
 Study On Labor Productivity.
 Scheduling.
 Tracking & updating of project.
 Delay Analysis.
 Results & conclusions.
2.1 Brief Details of Project
Nature Walk is a Villa project consisting of 14 Villas of
3BHK and 4 BHK.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1729
 Name of the project: Nature Walk Project.
 Location: KR Puram, Bengaluru.
 Contractor: Sri Laxmi Constructions.
 Client: Renaissance Holdings.
 Built up Area: 8400 sq-ft-9880 sq-ft.
 Super Built-up Area: 9450 sq-ft – 11115 sq-ft.
 Site area: 14 Acres.
 Building Type: Villas.
 Number of floors: G+2.
 Total number of Villas: 147.
2.2 Project Specification
 Structure
- Villas are Reinforced Cement Concrete with G+2
Floor.
 Concrete
- M10 grade for PCC, M25 grade for Footing, Columns,
Beams & Slabs.
 Steel
- High Yield Strength Deformed bars Fe-500 is used.
 Masonry Work
- 4” & 6” Internal and External Concrete block walls.
 Plastering
- External sand faced plaster.
- Internal plaster with putty.
 Painting
- External Walls-Cement texturing with Apex/Ace
emulsion.
 Windows
- UPVC.
 Flooring
- Balcony -Anti Skid Tiles, Kitchen- Vitrified Tiles,
Living/Dining- Marble, Granite.
2.3 Labor Productivity and Manpower Requirement
The required manpower for each activity for carrying out
that particular activity efficiently without compromising
on the quality is allocated and calculated based on labor
productivity.
Table: 2.1 Duration delay table
Task Name Duration Baseline
Duration
Nature Walk Project B-
08
472 days 406 days
VILLA 99 & 100 439 days 360 days
Nature Walk Project B-08
Sub Structure 106 days 88 days
Earthwork 6 days 5 days
Plain cement concrete 59 days 50 days
Footing 37 days 30 days
Plinth Beam 48 days 40 days
Ground Floor 63 days 59 days
1st floor 62 days 52 days
2nd Floor 36 days 28 days
Staircase 13 days 10 days
Block Work 99 days 75 days
Wall Tiling 21 days 15 days
Plastering 132 days 101 days
Internal Plastering 53 days 37 days
Ceiling Plastering 24 days 19 days
Wall Plastering 40 days 28 days
External Plastering 76 days 59 days
Painting 50 days 46 days
Internal Painting 42 days 32 days
External Painting 20 days 39 days
3. CONCLUSIONS
On analyzing it’s been found there is a delay of 66 days in
the completion of the project. The critical activities of the
project are foundation, casting the floor slab, block work,
external plastering, painting and doors. Inspire of critical
activities, there are some additional activities where the
project experienced difficulties in execution and delay in
completion.
From the delay analysis an amount of Rs. 620200/- has
been incurred to the project which is an additional loss to
the project and simultaneously over shoots the budget
allocated to the project. The main causes of the delay in
the project are both excusable and non-excusable delays,
which are identified by the occurrence and experience.
The main delays were recorded and the loss of
productivity and cost loss has been calculated.
In this study, the main causes of the delay occurrence are
rain, unskilled labors, shortage of skilled labor, poor
workmanship, shortage of labors, inadequate of
availability of materials, non-availability of materials,
delay in payment to the contractor by client, partial
payments to labor by contractors. These delays imply that
contract related delays require adequate attention,
because these delays topped with huge loss to the
company and project duration overrun. Time overrun and
cost overrun effects are more in this project. So, necessary
action should be adopted to avoid the delays which lead to
project loss.
REFERENCES
[1] Megha Desai and Rajiv Bhatt (April 2013). “Critical
Causes of Delay in Residential Construction Projects: Case
Study of Central Gujarat Region of India”, International
Journal of Engineering Trends and Technology, Vol. 4,
Issue 4, pp 767-768.
[2] Siddesh K. Pai and J. Raj Bharath (March 2013).
“Analysis of Critical Causes of Delays in Indian
Infrastructure Projects”, International Journal of
Innovative Research and Development, Vol. 2, Issue 3, pp
251-263.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1730
[3] Enas Fathi Taher and R. K. Pandey (Feb 2013). “Study
of Delay in Project Planning and Design Stage of Civil
Engineering Projects”, International Journal of
Engineering and Advanced Technology, Vol. 2, Issue 3, pp
456-461.
[4] M. Haseeb, Xinhai-Lu, Aneesa Bibi, Maloof-ud-Dyian
and Wahab Rabbani (Sept 2011). “Problems of Projects
and Effects of Delays in the Construction Industry of
Pakistan”, Australian Journal of Business and Management
Research, Vol. 1, No. 5, pp 41-50.
[5] Abedi M., Fathi M. S. and Mohammad M. F. (2011).
“Effects of Construction Delays on Construction Project
Objectives”, Scientific Conference Malaysia.
[6] Aswathi R and Ciby Thomas (December 2013).
“Development of a Delay Analysis System for a Railway
Construction Project”, International Journal of Innovative
Research in Science, Engineering and Technology, ICEE,
Vol. 2, Special Issue 1, pp 531-541.
[7] Murali Sambasivan and Yau Wen Soon (2007). “Causes
and Effects of Delays in Malaysian construction industry”,
International Journal of Project Management, 25, pp 517-
526.
[8] Sadi A. Assaf and Sadiq Al-Hejji (2006). “Causes of
delay in large construction projects”, International Journal
of Project Management, ELSEVIER, 24, pp 349-357.
[9] Abdalla M. Odeh and Hussaien T. Battaineh (2002).
“Causes of Construction delay: traditional contracts”,
International Journal of Project Management, PERGAMON,
20, pp 67-73.

More Related Content

DOCX
Project management-Report
SYEDA KANWAL NOREEN
 
PDF
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET Journal
 
PDF
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
PDF
Construction Project Scheduling of MK Apartment using MS Project 2013
IRJET Journal
 
PDF
Delay Analysis in Construction of Redevelopment Residential Project
IRJET Journal
 
PDF
The significant Causes and effects of delays in Ghadir 2206 residential project
IOSR Journals
 
PDF
Msc Structural Engineering and Mechanics Dissertation
Alexandros Alexandrou
 
PDF
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 
Project management-Report
SYEDA KANWAL NOREEN
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
Construction Project Scheduling of MK Apartment using MS Project 2013
IRJET Journal
 
Delay Analysis in Construction of Redevelopment Residential Project
IRJET Journal
 
The significant Causes and effects of delays in Ghadir 2206 residential project
IOSR Journals
 
Msc Structural Engineering and Mechanics Dissertation
Alexandros Alexandrou
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 

What's hot (17)

DOCX
KAIA Project Management Plan[1]
Dr Andrew Kimmance PhD, MSc, BSc, MAPM, CIOB, AHEA
 
DOC
Project Management Plan Template
Simplilearn
 
DOC
RESUME.1
Vijay Babu
 
PDF
APM_AEB_FINAL
Macie De Stefano
 
PDF
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
DOC
Project management-plan
Tran Tien
 
DOCX
Swapnil Resume
Swapnil Jadhav
 
DOCX
project plan document(ppd)
maamir farooq
 
PDF
8 Project Plan
tuomasniinimaki
 
DOCX
Project management plan_template
Raquel Shirazi
 
PDF
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Sankalp Swarnkar
 
PDF
Brijesh
brijeshswami
 
PDF
Proposed project plan template
Michelle Joja
 
DOCX
Resume_VRGOLI_BTECH_CHEMICAL
Venkateshwarulu Goli
 
PDF
Henry CV
Henry Jayahar
 
PDF
A Study in Construction Delays of Residential Structures
IRJESJOURNAL
 
DOCX
CV ,VK JHA
vishnu kant jha
 
Project Management Plan Template
Simplilearn
 
RESUME.1
Vijay Babu
 
APM_AEB_FINAL
Macie De Stefano
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
Project management-plan
Tran Tien
 
Swapnil Resume
Swapnil Jadhav
 
project plan document(ppd)
maamir farooq
 
8 Project Plan
tuomasniinimaki
 
Project management plan_template
Raquel Shirazi
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Sankalp Swarnkar
 
Brijesh
brijeshswami
 
Proposed project plan template
Michelle Joja
 
Resume_VRGOLI_BTECH_CHEMICAL
Venkateshwarulu Goli
 
Henry CV
Henry Jayahar
 
A Study in Construction Delays of Residential Structures
IRJESJOURNAL
 
CV ,VK JHA
vishnu kant jha
 
Ad

Similar to IRJET - Delay Analysis of a Construction Project- A Case Study (20)

PDF
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET Journal
 
PDF
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
PDF
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
PDF
Delay Analysis in Industrial Projects by using Relative Importance Index Method
IRJET Journal
 
PDF
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
PDF
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
IRJET Journal
 
PDF
Management For Construction Project:-Various Aspects Of Delay
IRJET Journal
 
PDF
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
PDF
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET Journal
 
PDF
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
PDF
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ijtsrd
 
PDF
76 s201905
IJRAT
 
PPTX
Delay analysis of raw water reservoir and pumping Station
chetlapally balakrishna
 
PDF
Delay Analysis for an On-Going Residential Project
IRJET Journal
 
PDF
Causes of delay in indian transportation
eSAT Publishing House
 
PDF
Causes of delay in indian transportation infrastructure projects
eSAT Journals
 
PDF
Delay Analysis of National Highway NH 44 Using Primavera Software
ijtsrd
 
PDF
D012261521
IOSR Journals
 
PDF
Time delay and cost escalation in construction works
vivatechijri
 
PDF
Impact of delayness on construction projects
IRJET Journal
 
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
IRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
IRJET Journal
 
Management For Construction Project:-Various Aspects Of Delay
IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ijtsrd
 
76 s201905
IJRAT
 
Delay analysis of raw water reservoir and pumping Station
chetlapally balakrishna
 
Delay Analysis for an On-Going Residential Project
IRJET Journal
 
Causes of delay in indian transportation
eSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
eSAT Journals
 
Delay Analysis of National Highway NH 44 Using Primavera Software
ijtsrd
 
D012261521
IOSR Journals
 
Time delay and cost escalation in construction works
vivatechijri
 
Impact of delayness on construction projects
IRJET Journal
 
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
IRJET Journal
 
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
IRJET Journal
 
PDF
Kiona – A Smart Society Automation Project
IRJET Journal
 
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
IRJET Journal
 
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
IRJET Journal
 
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
IRJET Journal
 
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
IRJET Journal
 
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
IRJET Journal
 
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
IRJET Journal
 
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
IRJET Journal
 
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
IRJET Journal
 
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
IRJET Journal
 
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
IRJET Journal
 
PDF
Breast Cancer Detection using Computer Vision
IRJET Journal
 
PDF
Auto-Charging E-Vehicle with its battery Management.
IRJET Journal
 
PDF
Analysis of high energy charge particle in the Heliosphere
IRJET Journal
 
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
IRJET Journal
 
PDF
Auto-Charging E-Vehicle with its battery Management.
IRJET Journal
 
PDF
Analysis of high energy charge particle in the Heliosphere
IRJET Journal
 
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
IRJET Journal
 
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
IRJET Journal
 
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
IRJET Journal
 
Kiona – A Smart Society Automation Project
IRJET Journal
 
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
IRJET Journal
 
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
IRJET Journal
 
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
IRJET Journal
 
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
IRJET Journal
 
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
IRJET Journal
 
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
IRJET Journal
 
BRAIN TUMOUR DETECTION AND CLASSIFICATION
IRJET Journal
 
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
IRJET Journal
 
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
IRJET Journal
 
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
IRJET Journal
 
Breast Cancer Detection using Computer Vision
IRJET Journal
 
Auto-Charging E-Vehicle with its battery Management.
IRJET Journal
 
Analysis of high energy charge particle in the Heliosphere
IRJET Journal
 
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
IRJET Journal
 
Auto-Charging E-Vehicle with its battery Management.
IRJET Journal
 
Analysis of high energy charge particle in the Heliosphere
IRJET Journal
 
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
IRJET Journal
 

Recently uploaded (20)

PDF
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
PDF
Packaging Tips for Stainless Steel Tubes and Pipes
heavymetalsandtubes
 
PDF
20ME702-Mechatronics-UNIT-1,UNIT-2,UNIT-3,UNIT-4,UNIT-5, 2025-2026
Mohanumar S
 
PDF
Construction of a Thermal Vacuum Chamber for Environment Test of Triple CubeS...
2208441
 
PPTX
MT Chapter 1.pptx- Magnetic particle testing
ABCAnyBodyCanRelax
 
PPTX
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
PPT
Understanding the Key Components and Parts of a Drone System.ppt
Siva Reddy
 
PPTX
quantum computing transition from classical mechanics.pptx
gvlbcy
 
PDF
Advanced LangChain & RAG: Building a Financial AI Assistant with Real-Time Data
Soufiane Sejjari
 
PDF
settlement FOR FOUNDATION ENGINEERS.pdf
Endalkazene
 
PDF
Zero carbon Building Design Guidelines V4
BassemOsman1
 
PDF
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
PDF
2025 Laurence Sigler - Advancing Decision Support. Content Management Ecommer...
Francisco Javier Mora Serrano
 
PDF
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
PPTX
sunil mishra pptmmmmmmmmmmmmmmmmmmmmmmmmm
singhamit111
 
DOCX
SAR - EEEfdfdsdasdsdasdasdasdasdasdasdasda.docx
Kanimozhi676285
 
PPTX
IoT_Smart_Agriculture_Presentations.pptx
poojakumari696707
 
PPTX
Victory Precisions_Supplier Profile.pptx
victoryprecisions199
 
PDF
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
PDF
All chapters of Strength of materials.ppt
girmabiniyam1234
 
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
Packaging Tips for Stainless Steel Tubes and Pipes
heavymetalsandtubes
 
20ME702-Mechatronics-UNIT-1,UNIT-2,UNIT-3,UNIT-4,UNIT-5, 2025-2026
Mohanumar S
 
Construction of a Thermal Vacuum Chamber for Environment Test of Triple CubeS...
2208441
 
MT Chapter 1.pptx- Magnetic particle testing
ABCAnyBodyCanRelax
 
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
Understanding the Key Components and Parts of a Drone System.ppt
Siva Reddy
 
quantum computing transition from classical mechanics.pptx
gvlbcy
 
Advanced LangChain & RAG: Building a Financial AI Assistant with Real-Time Data
Soufiane Sejjari
 
settlement FOR FOUNDATION ENGINEERS.pdf
Endalkazene
 
Zero carbon Building Design Guidelines V4
BassemOsman1
 
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
2025 Laurence Sigler - Advancing Decision Support. Content Management Ecommer...
Francisco Javier Mora Serrano
 
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
sunil mishra pptmmmmmmmmmmmmmmmmmmmmmmmmm
singhamit111
 
SAR - EEEfdfdsdasdsdasdasdasdasdasdasdasda.docx
Kanimozhi676285
 
IoT_Smart_Agriculture_Presentations.pptx
poojakumari696707
 
Victory Precisions_Supplier Profile.pptx
victoryprecisions199
 
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
All chapters of Strength of materials.ppt
girmabiniyam1234
 

IRJET - Delay Analysis of a Construction Project- A Case Study

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1728 DELAY ANALYSIS OF A CONSTRUCTION PROJECT- A CASE STUDY Mr. Nagarjun Gowda B.S1, Ms. Chethana K.N2 1Assistant Professor, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India 2Student, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Construction technology has become an essential part of any of the project, for timely and economical completion of the project. A proper construction planning and schedule acts as a main role ford different purposes. By using the schedule, we can know the merely completion of the project, contractors can recruit the necessary manpower; can demand shifts or equipments to speed up the project. The most important function of the project management is to plan and control the project objective like time, budget and setting out of resource productivity standards to achieve the objectives of the project. Delay happens in all construction projects. Where construction project will vary in size, some will be in small. In vast projects, analysis should be done for the purpose on making right decisions on time and cost compensation claims. Many type of software’s are available to plan, execute and control the project; with the help of these software’s the project management has become easier to evolve the construction project. Large quantities of different kind of resources are required for execution and the risk is more in case of big projects. So, planning and scheduling in big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis and updating of various activities which is done using MS project. Key Words: Construction Management, Planning, Delay, Labour Productivity, Scheduling, Tracking. 1. INTRODUCTION Construction industry plays an important role in the economic growth of a country. It is the process of implementing the plans, ideas, standards, specifications and assigning the resources into a physical facility to meet the specific requirements of owner. Construction management can be defined as the accomplishment of results through the combined effort of the consultant, client and designer. Construction is a very unique and creative practice which coverts four M’s of the construction-Material, Manpower, Machinery and Money into a systematic structure. Thus construction management contains Planning, Executing and monitoring the construction activities in a specific project. 1.1 Project Planning, Scheduling and Controlling The main aim of the construction management is to plan and schedule the resources within the frame work of a project. The guidelines and procedures of the construction management direct the managers how to utilize the resources during the construction process. Before execution of the work on the site all kinds of office works such as planning, designing, estimating, negotiating, purchasing, scheduling, controlling etc. should be done carefully. 1.2 Construction Delay Analysis Delay is one of the common problems in the construction project. Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often resulting of miscommunication between contractors, subcontractors, owners and suppliers. These types of unrealistic exceptions are usually avoided by clean and efficient planning mechanism, which clearly specifies the work and timetable to be used. Delays in construction project are quite expensive; sometimes they may result in severe damages to the involved parties. 1.3 Objective of the Study  Detailed literature study to define the various causes of delay in construction projects  Study on ongoing Project site to observe the activities and to identify delay factors  Determination of Critical Path using MS Projects  The analysis also involves the process of scheduling and tracking of a construction project activities in software and related catch up programs due to delays. 2. METHODOLOGY  Site Investigation.  Studying Of BOQ & Drawings.  Study On Labor Productivity.  Scheduling.  Tracking & updating of project.  Delay Analysis.  Results & conclusions. 2.1 Brief Details of Project Nature Walk is a Villa project consisting of 14 Villas of 3BHK and 4 BHK.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1729  Name of the project: Nature Walk Project.  Location: KR Puram, Bengaluru.  Contractor: Sri Laxmi Constructions.  Client: Renaissance Holdings.  Built up Area: 8400 sq-ft-9880 sq-ft.  Super Built-up Area: 9450 sq-ft – 11115 sq-ft.  Site area: 14 Acres.  Building Type: Villas.  Number of floors: G+2.  Total number of Villas: 147. 2.2 Project Specification  Structure - Villas are Reinforced Cement Concrete with G+2 Floor.  Concrete - M10 grade for PCC, M25 grade for Footing, Columns, Beams & Slabs.  Steel - High Yield Strength Deformed bars Fe-500 is used.  Masonry Work - 4” & 6” Internal and External Concrete block walls.  Plastering - External sand faced plaster. - Internal plaster with putty.  Painting - External Walls-Cement texturing with Apex/Ace emulsion.  Windows - UPVC.  Flooring - Balcony -Anti Skid Tiles, Kitchen- Vitrified Tiles, Living/Dining- Marble, Granite. 2.3 Labor Productivity and Manpower Requirement The required manpower for each activity for carrying out that particular activity efficiently without compromising on the quality is allocated and calculated based on labor productivity. Table: 2.1 Duration delay table Task Name Duration Baseline Duration Nature Walk Project B- 08 472 days 406 days VILLA 99 & 100 439 days 360 days Nature Walk Project B-08 Sub Structure 106 days 88 days Earthwork 6 days 5 days Plain cement concrete 59 days 50 days Footing 37 days 30 days Plinth Beam 48 days 40 days Ground Floor 63 days 59 days 1st floor 62 days 52 days 2nd Floor 36 days 28 days Staircase 13 days 10 days Block Work 99 days 75 days Wall Tiling 21 days 15 days Plastering 132 days 101 days Internal Plastering 53 days 37 days Ceiling Plastering 24 days 19 days Wall Plastering 40 days 28 days External Plastering 76 days 59 days Painting 50 days 46 days Internal Painting 42 days 32 days External Painting 20 days 39 days 3. CONCLUSIONS On analyzing it’s been found there is a delay of 66 days in the completion of the project. The critical activities of the project are foundation, casting the floor slab, block work, external plastering, painting and doors. Inspire of critical activities, there are some additional activities where the project experienced difficulties in execution and delay in completion. From the delay analysis an amount of Rs. 620200/- has been incurred to the project which is an additional loss to the project and simultaneously over shoots the budget allocated to the project. The main causes of the delay in the project are both excusable and non-excusable delays, which are identified by the occurrence and experience. The main delays were recorded and the loss of productivity and cost loss has been calculated. In this study, the main causes of the delay occurrence are rain, unskilled labors, shortage of skilled labor, poor workmanship, shortage of labors, inadequate of availability of materials, non-availability of materials, delay in payment to the contractor by client, partial payments to labor by contractors. These delays imply that contract related delays require adequate attention, because these delays topped with huge loss to the company and project duration overrun. Time overrun and cost overrun effects are more in this project. So, necessary action should be adopted to avoid the delays which lead to project loss. REFERENCES [1] Megha Desai and Rajiv Bhatt (April 2013). “Critical Causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region of India”, International Journal of Engineering Trends and Technology, Vol. 4, Issue 4, pp 767-768. [2] Siddesh K. Pai and J. Raj Bharath (March 2013). “Analysis of Critical Causes of Delays in Indian Infrastructure Projects”, International Journal of Innovative Research and Development, Vol. 2, Issue 3, pp 251-263.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1730 [3] Enas Fathi Taher and R. K. Pandey (Feb 2013). “Study of Delay in Project Planning and Design Stage of Civil Engineering Projects”, International Journal of Engineering and Advanced Technology, Vol. 2, Issue 3, pp 456-461. [4] M. Haseeb, Xinhai-Lu, Aneesa Bibi, Maloof-ud-Dyian and Wahab Rabbani (Sept 2011). “Problems of Projects and Effects of Delays in the Construction Industry of Pakistan”, Australian Journal of Business and Management Research, Vol. 1, No. 5, pp 41-50. [5] Abedi M., Fathi M. S. and Mohammad M. F. (2011). “Effects of Construction Delays on Construction Project Objectives”, Scientific Conference Malaysia. [6] Aswathi R and Ciby Thomas (December 2013). “Development of a Delay Analysis System for a Railway Construction Project”, International Journal of Innovative Research in Science, Engineering and Technology, ICEE, Vol. 2, Special Issue 1, pp 531-541. [7] Murali Sambasivan and Yau Wen Soon (2007). “Causes and Effects of Delays in Malaysian construction industry”, International Journal of Project Management, 25, pp 517- 526. [8] Sadi A. Assaf and Sadiq Al-Hejji (2006). “Causes of delay in large construction projects”, International Journal of Project Management, ELSEVIER, 24, pp 349-357. [9] Abdalla M. Odeh and Hussaien T. Battaineh (2002). “Causes of Construction delay: traditional contracts”, International Journal of Project Management, PERGAMON, 20, pp 67-73.