This document analyzes delays in a 14-villa construction project in Bengaluru, India called Nature Walk. It found that the project was delayed 66 days beyond the original schedule. Critical activities that faced delays included foundation work, floor slab casting, block work, plastering, and painting. The delays were caused by factors like rain, labor shortages, materials shortages, and payment issues. As a result, the project cost Rs. 620200 more than planned. The analysis aims to identify causes of construction delays so owners can minimize risks of cost overruns and schedule delays on future projects.