Telemark University College
Norway
Modelling the system dynamics of islanding asynchronous
generators
10th International Modelica Conference 2014
Håkon Molland Edvardsen Dietmar Winkler
Telemark University College
Norway
12th
March 2014
I. Introduction What is it about?
What is it about?
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
I. Introduction What is it about?
What is it about?
Figure : Broken surge arrester
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
I. Introduction What is it about?
What is it about?
Figure : Broken surge arrester
Figure : End-termination of supply cable
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
II. Practical Background Location
Location
Where in Europe?
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 3 / 18
II. Practical Background Location
Location
Locally
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 4 / 18
II. Practical Background The power stations
The power stations
Grunnå and Sagbekken 1 and Sagbekken 2&3
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
II. Practical Background The power stations
The power stations
Grunnå and Sagbekken 1 and Sagbekken 2&3
Figure : Grunnåi (Synch - 15MW)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
II. Practical Background The power stations
The power stations
Grunnå and Sagbekken 1 and Sagbekken 2&3
Figure : Grunnåi (Synch - 15MW)
Figure : Sagbekken 2&3 (Asynch 75+75 &
75+250 kW)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
II. Practical Background The power stations
The power stations
Reinstul - 18kW (traditional Norwegian power station)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
II. Practical Background The power stations
The power stations
Reinstul - 18kW (traditional Norwegian power station)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
II. Practical Background The power stations
The power stations
Total capacity
Grunnåi: 15MW - synchronous
Sagbekken 1: 2x100kW & 200kW - asynchronous
Sagbekken 2: 75kW & 250kW - asynchronous
Sagbekken 3: 75kW & 75kW - asynchronous
Total: 15.85MW
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 7 / 18
II. Practical Background What happend?
What happend?
Possible sequence
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 8 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
IV. Modelling The Lønnestad radial
The Lønnestad radial
Using Electric Power Library
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 10 / 18
IV. Modelling The self-excitation
The self-excitation
Model of one asynchronous generator
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 11 / 18
IV. Modelling The self-excitation
The self-excitation
Simulation results, no capacitance, disconnection at t = 1s
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 12 / 18
IV. Modelling The self-excitation
The self-excitation
Simulation results, influence of reactive and active load, disconnection at t = 1s
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
IV. Modelling The self-excitation
The self-excitation
Simulation results, influence of reactive and active load, disconnection at t = 1s
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
IV. Modelling Ground fault
Ground fault
Sub-model Sagbekken 1
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 14 / 18
IV. Modelling Ground fault
Ground fault
Model of Lønnestad radial with phase to ground fault
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 15 / 18
IV. Modelling Ground fault
Ground fault
Simulation results
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
IV. Modelling Ground fault
Ground fault
Simulation results
Took 1.5 seconds from ground
fault until total disconnect
Maximum voltage reached:
53.36kV
Phase C over 30kV for
0.7 seconds
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Simulations showed possible voltage build-up of 50kV within 0.4s!
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Simulations showed possible voltage build-up of 50kV within 0.4s!
Correct parameterisation of protection relays crucial
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Simulations showed possible voltage build-up of 50kV within 0.4s!
Correct parameterisation of protection relays crucial
Need to take self-excitation effect into account
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Telemark University College
Norway Thank you for your attention!
Questions?
Dietmar.Winkler@hit.no
Acknowlegdements:

More Related Content

PDF
Annual report card Owen Barry
PDF
Identification of Reactive Power Reserve in Transmission Network
PDF
High voltage megger electric shock Omer Saeed
PDF
Electrical protection in mines John Ainsworth
PPTX
anti islanding technology(passive)
PPTX
Island Detection and Control Techniques
PDF
Getting up close and personal with rc ds Bernard Gittins
DOCX
Final draft GRADED UNIT REPORT 5THMAY (1) (1) (1) (Repaired) - for merge
Annual report card Owen Barry
Identification of Reactive Power Reserve in Transmission Network
High voltage megger electric shock Omer Saeed
Electrical protection in mines John Ainsworth
anti islanding technology(passive)
Island Detection and Control Techniques
Getting up close and personal with rc ds Bernard Gittins
Final draft GRADED UNIT REPORT 5THMAY (1) (1) (1) (Repaired) - for merge

What's hot (19)

PDF
High voltage truck protection and fire prevention Paul Edwards
PDF
Managing earthing hazards around pole top transformers at mines and quarries ...
PDF
Significant incident review 415 v arc flash - Michael Wood
PPT
1. electricity markets_ Transmission
PDF
Transformer Failure Due to Circuit Breaker Induced Switching Transients
PDF
Transformer Failure Due to Circuit Breaker Induced Switching Transients
PDF
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
PDF
Review on Islanding Detection Methods for Photovoltaic Inverter
PDF
Semikron data sheet_skkh_57_07897942
PPTX
Islands in power systems
PPTX
Wind farm grid issues
PDF
energy harvesting though piezo
DOCX
Building service project2
PDF
Qeg user-manual-3-25-14
PPTX
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
PDF
Thesis presentation
PDF
QEG build-manual-25-mar-15
PDF
Quantum energy generator (qeg) new paradigm distribution guidelines
High voltage truck protection and fire prevention Paul Edwards
Managing earthing hazards around pole top transformers at mines and quarries ...
Significant incident review 415 v arc flash - Michael Wood
1. electricity markets_ Transmission
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
Review on Islanding Detection Methods for Photovoltaic Inverter
Semikron data sheet_skkh_57_07897942
Islands in power systems
Wind farm grid issues
energy harvesting though piezo
Building service project2
Qeg user-manual-3-25-14
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
Thesis presentation
QEG build-manual-25-mar-15
Quantum energy generator (qeg) new paradigm distribution guidelines
Ad

Viewers also liked (12)

PDF
Study on Excitation system in Power sector
PPT
synchronous generator excitation
PPTX
Major electrical equipment in power plants
PPT
Functions and performance requirements of excitation systems
DOCX
Brushless DC Excitation Systems
PPTX
Alternatorexcitation
PPTX
Alternator excitation systems
PPTX
Brushless excitation
PPSX
Excitation system for alternator
PDF
Three Phase Synchonours Generator and AVR
PPSX
Excitation System & capability curve of synchronous generator
PDF
Loss of excitation
Study on Excitation system in Power sector
synchronous generator excitation
Major electrical equipment in power plants
Functions and performance requirements of excitation systems
Brushless DC Excitation Systems
Alternatorexcitation
Alternator excitation systems
Brushless excitation
Excitation system for alternator
Three Phase Synchonours Generator and AVR
Excitation System & capability curve of synchronous generator
Loss of excitation
Ad

Similar to Modelling the system dynamics of islanding asynchronous generators / Telemark University (20)

PPTX
bus bar protection for advance power system
PPTX
TOPIC 6.2- Power System Faults and Protection System.pptx
PDF
D.pdf
PPTX
Power System Faults and Protection System
PPT
Electrical Protection systems in Thermal power stations.ppt
PDF
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
PPTX
Electric fault at forsmark nuclear power plant
PPT
ECE4762011_Lect22.ppt
PPTX
Overvoltage phenomenon
PPTX
CONCEPT OF SYMMETRICAL COMPONENT AS A TECHNIQUE FOR ANALYSIS OF FAULT AND IMP...
PDF
Ground Fault in OH lines
PPTX
Malay ppt psa
PDF
An Excitation Failure Detection Scheme for Alternators Using Fuzzy Inference ...
PPT
Ece4762011 lect22
PDF
Impact of Renewables on Transmission System Protection
PPTX
Module 1 Power System Protection(18EE72).pptx
PDF
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
PPTX
Protection against over voltage
PPTX
Transient in Power system
PPTX
seminar KASHIFFFFFFFFFFFFFFFFFFFFFF.pptx
bus bar protection for advance power system
TOPIC 6.2- Power System Faults and Protection System.pptx
D.pdf
Power System Faults and Protection System
Electrical Protection systems in Thermal power stations.ppt
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Electric fault at forsmark nuclear power plant
ECE4762011_Lect22.ppt
Overvoltage phenomenon
CONCEPT OF SYMMETRICAL COMPONENT AS A TECHNIQUE FOR ANALYSIS OF FAULT AND IMP...
Ground Fault in OH lines
Malay ppt psa
An Excitation Failure Detection Scheme for Alternators Using Fuzzy Inference ...
Ece4762011 lect22
Impact of Renewables on Transmission System Protection
Module 1 Power System Protection(18EE72).pptx
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Protection against over voltage
Transient in Power system
seminar KASHIFFFFFFFFFFFFFFFFFFFFFF.pptx

More from Modelon (20)

PPTX
Vehicle Dynamics Library - Overview
PPTX
Vapor Cycle Library - Overview
PPTX
Thermal Power Library - Overview
PPTX
Pneumatics Library - Overview
PPTX
Liquid Cooling Library - Overview
PPTX
Jet Propulsion Library - Overview
PPTX
Heat Exchanger Library - Overview
PPTX
Hydro Power Library - Overview
PPTX
Hydraulics Library - Overview
PPTX
Fuel System Library Overview
PPTX
Fuel Cell Library - Overview
PPTX
Electric Power Library - Overview
PPTX
Electrification Library - Overview
PPTX
Engine Dynamics Library - Overview
PPTX
Environmental Control Library - Overview
PPTX
Aircraft Dynamics Library - Overview
PPTX
Air Conditioning Library - Overview
PDF
Fuel System Library - Overview
PPTX
FMI Composer Overview
PPTX
Model Testing Toolkit - Overview
Vehicle Dynamics Library - Overview
Vapor Cycle Library - Overview
Thermal Power Library - Overview
Pneumatics Library - Overview
Liquid Cooling Library - Overview
Jet Propulsion Library - Overview
Heat Exchanger Library - Overview
Hydro Power Library - Overview
Hydraulics Library - Overview
Fuel System Library Overview
Fuel Cell Library - Overview
Electric Power Library - Overview
Electrification Library - Overview
Engine Dynamics Library - Overview
Environmental Control Library - Overview
Aircraft Dynamics Library - Overview
Air Conditioning Library - Overview
Fuel System Library - Overview
FMI Composer Overview
Model Testing Toolkit - Overview

Recently uploaded (20)

PPT
Comprehensive Java Training Deck - Advanced topics
PPTX
chapter 1.pptx dotnet technology introduction
PDF
Mechanics of materials week 2 rajeshwari
PPTX
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
PPTX
WN UNIT-II CH4_MKaruna_BapatlaEngineeringCollege.pptx
PPTX
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
PDF
V2500 Owner and Operatore Guide for Airbus
PPTX
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
PDF
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
PDF
Beginners-Guide-to-Artificial-Intelligence.pdf
PPTX
Design ,Art Across Digital Realities and eXtended Reality
PDF
Engineering Solutions for Ethical Dilemmas in Healthcare (www.kiu.ac.ug)
PPTX
Real Estate Management PART 1.pptxFFFFFFFFFFFFF
PPTX
SC Robotics Team Safety Training Presentation
DOCX
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
PPTX
Unit IImachinemachinetoolopeartions.pptx
PDF
Cryptography and Network Security-Module-I.pdf
PPT
Programmable Logic Controller PLC and Industrial Automation
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
PDF
VTU IOT LAB MANUAL (BCS701) Computer science and Engineering
Comprehensive Java Training Deck - Advanced topics
chapter 1.pptx dotnet technology introduction
Mechanics of materials week 2 rajeshwari
SE unit 1.pptx by d.y.p.akurdi aaaaaaaaaaaa
WN UNIT-II CH4_MKaruna_BapatlaEngineeringCollege.pptx
ARCHITECTURE AND PROGRAMMING OF EMBEDDED SYSTEMS
V2500 Owner and Operatore Guide for Airbus
Module1.pptxrjkeieuekwkwoowkemehehehrjrjrj
MACCAFERRY GUIA GAVIONES TERRAPLENES EN ESPAÑOL
Beginners-Guide-to-Artificial-Intelligence.pdf
Design ,Art Across Digital Realities and eXtended Reality
Engineering Solutions for Ethical Dilemmas in Healthcare (www.kiu.ac.ug)
Real Estate Management PART 1.pptxFFFFFFFFFFFFF
SC Robotics Team Safety Training Presentation
ENVIRONMENTAL PROTECTION AND MANAGEMENT (18CVL756)
Unit IImachinemachinetoolopeartions.pptx
Cryptography and Network Security-Module-I.pdf
Programmable Logic Controller PLC and Industrial Automation
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
VTU IOT LAB MANUAL (BCS701) Computer science and Engineering

Modelling the system dynamics of islanding asynchronous generators / Telemark University

  • 1. Telemark University College Norway Modelling the system dynamics of islanding asynchronous generators 10th International Modelica Conference 2014 Håkon Molland Edvardsen Dietmar Winkler Telemark University College Norway 12th March 2014
  • 2. I. Introduction What is it about? What is it about? Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
  • 3. I. Introduction What is it about? What is it about? Figure : Broken surge arrester Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
  • 4. I. Introduction What is it about? What is it about? Figure : Broken surge arrester Figure : End-termination of supply cable Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
  • 5. II. Practical Background Location Location Where in Europe? Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 3 / 18
  • 6. II. Practical Background Location Location Locally Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 4 / 18
  • 7. II. Practical Background The power stations The power stations Grunnå and Sagbekken 1 and Sagbekken 2&3 Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
  • 8. II. Practical Background The power stations The power stations Grunnå and Sagbekken 1 and Sagbekken 2&3 Figure : Grunnåi (Synch - 15MW) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
  • 9. II. Practical Background The power stations The power stations Grunnå and Sagbekken 1 and Sagbekken 2&3 Figure : Grunnåi (Synch - 15MW) Figure : Sagbekken 2&3 (Asynch 75+75 & 75+250 kW) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
  • 10. II. Practical Background The power stations The power stations Reinstul - 18kW (traditional Norwegian power station) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
  • 11. II. Practical Background The power stations The power stations Reinstul - 18kW (traditional Norwegian power station) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
  • 12. II. Practical Background The power stations The power stations Total capacity Grunnåi: 15MW - synchronous Sagbekken 1: 2x100kW & 200kW - asynchronous Sagbekken 2: 75kW & 250kW - asynchronous Sagbekken 3: 75kW & 75kW - asynchronous Total: 15.85MW Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 7 / 18
  • 13. II. Practical Background What happend? What happend? Possible sequence Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 8 / 18
  • 14. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 15. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 16. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 17. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 18. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 19. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 20. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 21. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 22. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 23. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 24. IV. Modelling The Lønnestad radial The Lønnestad radial Using Electric Power Library Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 10 / 18
  • 25. IV. Modelling The self-excitation The self-excitation Model of one asynchronous generator Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 11 / 18
  • 26. IV. Modelling The self-excitation The self-excitation Simulation results, no capacitance, disconnection at t = 1s Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 12 / 18
  • 27. IV. Modelling The self-excitation The self-excitation Simulation results, influence of reactive and active load, disconnection at t = 1s Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
  • 28. IV. Modelling The self-excitation The self-excitation Simulation results, influence of reactive and active load, disconnection at t = 1s Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
  • 29. IV. Modelling Ground fault Ground fault Sub-model Sagbekken 1 Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 14 / 18
  • 30. IV. Modelling Ground fault Ground fault Model of Lønnestad radial with phase to ground fault Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 15 / 18
  • 31. IV. Modelling Ground fault Ground fault Simulation results Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
  • 32. IV. Modelling Ground fault Ground fault Simulation results Took 1.5 seconds from ground fault until total disconnect Maximum voltage reached: 53.36kV Phase C over 30kV for 0.7 seconds Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
  • 33. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 34. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 35. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 36. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Simulations showed possible voltage build-up of 50kV within 0.4s! Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 37. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Simulations showed possible voltage build-up of 50kV within 0.4s! Correct parameterisation of protection relays crucial Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 38. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Simulations showed possible voltage build-up of 50kV within 0.4s! Correct parameterisation of protection relays crucial Need to take self-excitation effect into account Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 39. Telemark University College Norway Thank you for your attention! Questions? [email protected] Acknowlegdements: