PERT AND CPM
PROJECT MANAGEMENT
ARCHITECTURE
SITI YAUMILIA SALSA
Project
Combination of interrelated activities
Executed in logical sequence
Accomplishment of a desired objective
Project Management
• Management is generally perceived as concerned with planning, organizing, and
control of an ongoing process or activity.
• Project Management is concerned with control of an activity for a relatively short
period of time after which management effort ends.
• Primary elements of Project Management to be discussed:
Project Team
Project Planning
Project Control
Network analysis is the general name given to certain specific techniques which can
be used for the planning, management and control of projects.
 Methods used for network planning are:
CPM
PERT
 Managing a project with network planning methods involves four steps:
1. Describing the Project.
2. Diagramming the Network.
3. Estimating time of completion.
4. Monitoring Project Progress.
Network Planning
HISTORY OF PERT/CPM
Developed by
the US Navy
for the
planning and
control of the
Polaris missile
program
The emphasis
was on
completing
the program in
the shortest
possible time.
PERT
Developed by
Du Pont to
solve project
scheduling
problems
The emphasis
was on the
trade-off
between the
cost of the
project and its
overall
completion
time
CPM
CPM - Critical Path Method
Drafting the design of
Programme or Project
Evaluation of drafted
Programme or Project
Review of evaluated
Programme or Project
PERT -
Project Evaluation & Review Techniques
To analyze and represent the tasks
involved in completing a given project
Accommodates the variation in event
completion time
Event-oriented technique rather than
start- and completion-oriented
Commonly used in conjunction with
the critical path method
Basic Terms In Network Analysis
Activity
Event
Constraints
Network Diagram
Critical Path
Steps in PERT/CPM
4. CONTROLLING
3. ALLOCATION OF RESOURCES
2. SCHEDULING
1. PLANNING
PERT/CPM
Project managers reply on PERT/CPM to help them answer questions such as:
• What is the total time to complete the project?
• What are the scheduled start and finish dates for each specific activity?
• Which activities are critical and must be completed exactly as scheduled to keep the
project on schedule?
• How long can noncritical activities be delayed before they cause an increase in the
project completion time?
Both PERT and CPM
• Graphically display the precedence relationships & sequence of
activities
• Estimate the project’s duration
• Identify critical activities that cannot be delayed without delaying the
project
• Estimate the amount of slack associated with non-critical activities
Framework for PERT and CPM
• Define the Project. The Project should have only a single start activity
and a single finish activity.
• Develop the relationships among the activities.
• Draw the "Network" connecting all the activities.
• Assign time and/or cost estimates to each activity
• Compute the critical path.
• Use the Network to help plan, schedule, monitor and control the
project.
PERT Diagrams
• Activity-on-node diagrams:
• Maybe more than one single start and end node
• Nodes represent activities
• Arrows indicate precedence
• Activity-on-arrow diagrams:
• One single start and one single end node
• An arrow represents a task, while a node is the
completion of a task
• Arrows represent activities
• Nodes indicate beginning/end of activities
13
Dummy Activities
• Sometimes it is necessary to insert dummy activities (duration
zero) in order to maintain the clarity of the diagram and the
precedence relationships between activities.
• In activity-on-arrow PERT diagrams, each activity must be uniquely
identifiable by its start and end nodes.
• However, sometimes multiple tasks have the same predecessors
and successors.
14
DUMMY ACTIVITY
Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
nodes
1 3
2
2) When two or more activities share the same
precedence activity but not all the precedence are
shared.
1 53
6
7
2 4
Determining the Critical Path
• Step 1: Make a forward pass through the network as follows: For each
activity i beginning at the Start node, compute:
• Earliest Start Time (ES) = the maximum of the earliest finish times of all activities
immediately preceding activity i. (This is 0 for an activity with no predecessors.). This is
the earliest time an activity can begin without violation of immediate predecessor
requirements.
• Earliest Finish Time (EF) = (Earliest Start Time) + (Time to complete activity i. This
represent the earliest time at which an activity can end.
The project completion time is the maximum of the Earliest Finish Times at
the Finish node.
Determining the Critical Path
• Step 2: Make a backwards pass through the network as follows: Move
sequentially backwards from the Finish node to the Start node. At a given node, j,
consider all activities ending at node j. For each of these activities, (i,j), compute:
• Latest Finish Time (LF) = the minimum of the latest start times beginning at
node j. (For node N, this is the project completion time.). This is the latest time
an activity can end without delaying the entire project.
• Latest Start Time (LS) = (Latest Finish Time) - (Time to complete activity (i,j)).
This is the latest time an activity can begin without delaying the entire project.
Determining the Critical Path
• Step 3: Calculate the slack time for each activity by:
Slack = (Latest Start) - (Earliest Start), or
= (Latest Finish) - (Earliest Finish).
A critical path is a path of activities, from the Start node to the Finish
node, with 0 slack times.
A Simple Project
Activity Immediate
Predecessor
Expected
Time
A - 5
B - 6
C A 4
D A, B 2
Precedence Diagram
ES Earliest Starting (time)
EF Earliest Finishing
LS Latest Starting
LF Latest Finishing
Slack Difference Time
PERT AND CPM PROJECT MANAGEMENT
• Activity time estimates usually can not be made with certainty.
• PERT used for probabilistic activity times.
• In PERT, three time estimates are used: most likely time (m), the optimistic
time (a) , and the pessimistic time (b).
• These provide an estimate of the mean and variance of a beta distribution:
• mean (expected time):
• variance:
6
b4mat 
2
6
a-b










v
Probabilistic Activity Times
PERT AND CPM PROJECT MANAGEMENT
Difference Between PERT & CPM
Probabilistic Model
Non-repetitive Jobs like planning
& scheduling of programmes
Results calculated on basis of
Events
Related with activities of
uncertain time
Deterministic Model
Repetitive Jobs like residential
construction
Results calculated on basis of
activities
Related with activities of Well
Known time
PERT CPM
Advantages of PERT/CPM
Reduction in cost
• Elimination of Risk in Complex activity
Flexibility
• Optimisation of Resources
Reduction of Uncertainties
Disadvantages of PERT/CPM
Network charts tend to be large
Lack of a timeframe on most PERT/CPM charts makes it
harder to show status
When PERT/CPM charts become unwieldy, they are no
longer used to manage the project
Planning & Implementation required skillful personnel
PERT TABLE
NO. ACTIVITY
KOEFISIEN Days Labors
Toptimis
(a)
Tmostlikely
(m)
Tpesimis
(b)
Texpected
(Te)
Variance
(v)
A PREPARATION, MINING AND LAND 32 6,10,16 8,5/6,4 6 10 16 10,33333333 2,777777778
B FOUNDATION AND CONCRETE CONSTRUCTION 240 40,60,80 8,6,4 40 60 80 60 44,44444444
C COUPLE AND PLASTERING CONSTRUCTION 12 2,4,6 6,4,3 2 4 6 4 0,444444444
D FLOOR AND WALL INSTALLATION 12 1,1,4 4,4,1 4 10 12 9,333333333 1,777777778
E ROOF CONSTRUCTION 42 6,7,11 7,6,4 11 14 21 14,66666667 2,777777778
F CEILING INSTALLATION 4 1,1,4 4,4,1 1 1 4 1,5 0,25
G INSTALLATION KUSEN, DOOR AND WINDOW 15 2,3,5 8,5,3 2 3 5 3,166666667 0,25
H EQUIPMENT INSTALLATION DOOR AND WINDOW 6 1,2,3 6,3,2 1 2 3 2 0,111111111
I INSTALLATION OF SANITARY 24 3,4,6 8,6,4 3 4 6 4,166666667 0,25
J1 SEPTIC TANK 10 4,5,10 3,2,1 4 5 10 5,666666667 1
J2 PLUMBING 7 3,4,7 3,2,1 3 4 7 4,333333333 0,444444444
K1 PLN INSTALLATION 1 1,1,2 2,1,1 1 1 2 1,166666667 0,027777778
K2 CABLE 3 1,2,3 3,2,1 1 2 3 2 0,111111111
K3 FINISHING 1 1.2.3 2,1,1 1 1 2 1,166666667 0,027777778
L PAINTING 7 1,1,3 1,1,3 3 4 7 4,333333333 0,444444444
M FINISHING 8 3,4,8 3,2,1 3 4 8 4,5 0,694444444
PERT DIAGRAM
A B C
K1
E F
J2J1
G
I
D
L H
K2
I K3 M
NO. ACTIVITY Texpected (Te)
A PREPARATION, MINING AND LAND 10,33
B FOUNDATION AND CONCRETE CONSTRUCTION 60
C COUPLE AND PLASTERING CONSTRUCTION 4
D FLOOR AND WALL INSTALLATION 9,33
E ROOF CONSTRUCTION 14,67
F CEILING INSTALLATION 1,5
G INSTALLATION KUSEN, DOOR AND WINDOW 3,17
H EQUIPMENT INSTALLATION DOOR AND WINDOW 2
I INSTALLATION OF SANITARY 4,17
J1 SEPTIC TANK 5,67
J2 PLUMBING 4,34
K1 PLN INSTALLATION 1,17
K2 CABLE 2
K3 FINISHING 1,17
L PAINTING 4,34
M FINISHING 4,5
0M
4,5
0
117,4
112,9
112,9
117,4
S ^ = 54,25
S=7,365459931328117
Z=(120-115,5)/ 7,365
Z= 0,61
Z= 74,8 %
NO. ACTIVITY
Variance (v)
CRITICAL
PATH
A PREPARATION, MINING AND LAND 2,777777778 YA
B FOUNDATION AND CONCRETE CONSTRUCTION 44,44444444 YA
C COUPLE AND PLASTERING CONSTRUCTION 0,444444444 YA
D FLOOR AND WALL INSTALLATION 1,777777778 YA
E ROOF CONSTRUCTION 2,777777778 YA
F CEILING INSTALLATION 0,25 YA
G INSTALLATION KUSEN, DOOR AND WINDOW 0,25 YA
H EQUIPMENT INSTALLATION DOOR AND WINDOW 0,111111111 YA
I INSTALLATION OF SANITARY 0,25 YA
J1 SEPTIC TANK NO
J2 PLUMBING NO
K1 PLN INSTALLATION NO
K2 CABLE NO
K3 FINISHING 0,027777778 YA
L PAINTING 0,444444444 YA
M FINISHING 0,694444444 YA
S^2 54,25
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
THANK YOU

More Related Content

PPTX
Project management techniques
PPSX
Project management
PPTX
Different Arduino Boards
PPT
Jain architecture final 1
PPT
TYPES OF FOUNDATION(PPT)
PDF
Construction technology presentation
PPTX
Tender Process | A Complete Procurement Guide
DOCX
Jaw crusher
Project management techniques
Project management
Different Arduino Boards
Jain architecture final 1
TYPES OF FOUNDATION(PPT)
Construction technology presentation
Tender Process | A Complete Procurement Guide
Jaw crusher

What's hot (20)

PPTX
Project Management - Critical path method
PPTX
Critical Path Method (CPM) & Network Analysis
PPT
Project planning and Scheduling
PPT
crashing of project
PPTX
Project monitoring and control & planning for monitoring
PDF
CPM AND PERT
PPTX
PROJECT SCHEDULE
PPTX
PERT and CPM
PPTX
Pert & cpm project management
PPTX
Project planning and scheduling techniques
PPTX
Pert and CPM
PPTX
Project Cost Management - PMBOK6
PPT
Critical path method (cpm)
ODP
Critical path method
PPT
09. Project Cost Management
PDF
Critical path method(cpm)
PPTX
Project Management PERT and CPM
PPTX
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
PDF
time cost trade off
PPTX
Project Time Management
Project Management - Critical path method
Critical Path Method (CPM) & Network Analysis
Project planning and Scheduling
crashing of project
Project monitoring and control & planning for monitoring
CPM AND PERT
PROJECT SCHEDULE
PERT and CPM
Pert & cpm project management
Project planning and scheduling techniques
Pert and CPM
Project Cost Management - PMBOK6
Critical path method (cpm)
Critical path method
09. Project Cost Management
Critical path method(cpm)
Project Management PERT and CPM
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
time cost trade off
Project Time Management
Ad

Viewers also liked (20)

PPT
Pert & Cpm
PPT
Pert Cpm Nis
PPTX
Network Problem CPM & PERT
PPTX
Pert cpm
PPT
Project management cpm-pert
PPTX
Tropical comfort
ODP
Pert, cpm and other tools of project management for intrapreneurs
PPTX
Jinmao tower (11) siti yaumilia salsa
PPTX
Pert,cpm, resource allocation and gert
PPTX
Program Evaluation and Review Technique (PERT)
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PPT
Service-Learning Project Simpson Sl2
PDF
Michelle Simpson Assignment #2
PPTX
Cpm and pert - project management
PPTX
cpmpertmy (1)
PPT
跳舞吧,小雅
PPT
爱的奇妙滋味
PPT
米菲在海边
PPT
动物绝对不应该穿衣服
PPT
爷爷变成了幽灵
Pert & Cpm
Pert Cpm Nis
Network Problem CPM & PERT
Pert cpm
Project management cpm-pert
Tropical comfort
Pert, cpm and other tools of project management for intrapreneurs
Jinmao tower (11) siti yaumilia salsa
Pert,cpm, resource allocation and gert
Program Evaluation and Review Technique (PERT)
Project Management Techniques ( CPM & PERT Techniques )
Service-Learning Project Simpson Sl2
Michelle Simpson Assignment #2
Cpm and pert - project management
cpmpertmy (1)
跳舞吧,小雅
爱的奇妙滋味
米菲在海边
动物绝对不应该穿衣服
爷爷变成了幽灵
Ad

Similar to PERT AND CPM PROJECT MANAGEMENT (20)

PPTX
PM-Problems.pptx
PPTX
Pertcpm projectmanagement SIDDANNA M BALAPGOL
PPTX
Pertcpm projectmanagement-120628224438-phpapp02
PPTX
PERT_CPM and other relevant points .pptx
PPT
PROJECT SCHEDULING
PPTX
Ch 5.pptx
PPTX
Ch 5.pptx IS ALL ABOUT PROJECT MANAGMENT AND EVALUATION
PPTX
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
PDF
08_lecture_scheduling.pdf based on project management
PPTX
pert-cpm.pptx
PPTX
Project Management & Engineering Economics
PPTX
CPM AND PERT(critical path method) .pptx
PPT
Cpm n pert lecture 1
PPTX
Quantitative analysis for business decision- Program Evaluation and Review Te...
PPTX
PMP Project Management Basics Tutorial For Beginners
PPTX
CPM, Network Analysis A-O-A, A-O-N, Resource management
PPTX
Project Management.pptx
PPTX
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
PPTX
Software Project Scheduling Diagrams
PDF
Network of first five activities.pdf
PM-Problems.pptx
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement-120628224438-phpapp02
PERT_CPM and other relevant points .pptx
PROJECT SCHEDULING
Ch 5.pptx
Ch 5.pptx IS ALL ABOUT PROJECT MANAGMENT AND EVALUATION
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
08_lecture_scheduling.pdf based on project management
pert-cpm.pptx
Project Management & Engineering Economics
CPM AND PERT(critical path method) .pptx
Cpm n pert lecture 1
Quantitative analysis for business decision- Program Evaluation and Review Te...
PMP Project Management Basics Tutorial For Beginners
CPM, Network Analysis A-O-A, A-O-N, Resource management
Project Management.pptx
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
Software Project Scheduling Diagrams
Network of first five activities.pdf

More from salsa moyara (20)

POT
OVERVIEW PRODUCT M-SYSTEM REINFORCED BRICK DUSASPUN
DOCX
Kepribadian dan kesehatan berdasarkan golongan darah
DOCX
Profile dian pelangi
DOCX
Jurnal Analisis tingkat kenyamanan termal pembeli dan penjual di pasar cipulir
PPTX
analisis tingkat kenyamanan termal di pasar cipulir
ODP
Galileo galilei biography
POT
Ujung genteng beach
POT
Confucianism (khonghuchu)
POT
Tanjung lesung banten
POT
Pulau tidung indonesia
PPTX
Thermal Comfort
ODP
konservasi menara syahbandar
PPTX
slum area on indonesia
PPS
HAK ASASI MANUSIA PASAL 28B
PPTX
The college of new jersey
PPT
Office building design
PPT
Nahwu isim kana
PPT
Marshal student center
PDF
Introduction building construction
PDF
How to prevent corruption
OVERVIEW PRODUCT M-SYSTEM REINFORCED BRICK DUSASPUN
Kepribadian dan kesehatan berdasarkan golongan darah
Profile dian pelangi
Jurnal Analisis tingkat kenyamanan termal pembeli dan penjual di pasar cipulir
analisis tingkat kenyamanan termal di pasar cipulir
Galileo galilei biography
Ujung genteng beach
Confucianism (khonghuchu)
Tanjung lesung banten
Pulau tidung indonesia
Thermal Comfort
konservasi menara syahbandar
slum area on indonesia
HAK ASASI MANUSIA PASAL 28B
The college of new jersey
Office building design
Nahwu isim kana
Marshal student center
Introduction building construction
How to prevent corruption

Recently uploaded (20)

PPTX
Principal presentation for NAAC (1).pptx
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PDF
Computer System Architecture 3rd Edition-M Morris Mano.pdf
PPTX
mechattonicsand iotwith sensor and actuator
PDF
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
PDF
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
PPTX
Software Engineering and software moduleing
PPTX
Amdahl’s law is explained in the above power point presentations
PDF
First part_B-Image Processing - 1 of 2).pdf
PPTX
Module 8- Technological and Communication Skills.pptx
PPT
Programmable Logic Controller PLC and Industrial Automation
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PDF
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
CONTRACTS IN CONSTRUCTION PROJECTS: TYPES
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PPTX
AI-Reporting for Emerging Technologies(BS Computer Engineering)
PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
Project_Mgmt_Institute_-Marc Marc Marc .pdf
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
Principal presentation for NAAC (1).pptx
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
Computer System Architecture 3rd Edition-M Morris Mano.pdf
mechattonicsand iotwith sensor and actuator
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
Software Engineering and software moduleing
Amdahl’s law is explained in the above power point presentations
First part_B-Image Processing - 1 of 2).pdf
Module 8- Technological and Communication Skills.pptx
Programmable Logic Controller PLC and Industrial Automation
distributed database system" (DDBS) is often used to refer to both the distri...
LOW POWER CLASS AB SI POWER AMPLIFIER FOR WIRELESS MEDICAL SENSOR NETWORK
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
CONTRACTS IN CONSTRUCTION PROJECTS: TYPES
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
AI-Reporting for Emerging Technologies(BS Computer Engineering)
Management Information system : MIS-e-Business Systems.pptx
Project_Mgmt_Institute_-Marc Marc Marc .pdf
August 2025 - Top 10 Read Articles in Network Security & Its Applications

PERT AND CPM PROJECT MANAGEMENT

  • 1. PERT AND CPM PROJECT MANAGEMENT ARCHITECTURE SITI YAUMILIA SALSA
  • 2. Project Combination of interrelated activities Executed in logical sequence Accomplishment of a desired objective
  • 3. Project Management • Management is generally perceived as concerned with planning, organizing, and control of an ongoing process or activity. • Project Management is concerned with control of an activity for a relatively short period of time after which management effort ends. • Primary elements of Project Management to be discussed: Project Team Project Planning Project Control
  • 4. Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects.  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. Describing the Project. 2. Diagramming the Network. 3. Estimating time of completion. 4. Monitoring Project Progress. Network Planning
  • 5. HISTORY OF PERT/CPM Developed by the US Navy for the planning and control of the Polaris missile program The emphasis was on completing the program in the shortest possible time. PERT Developed by Du Pont to solve project scheduling problems The emphasis was on the trade-off between the cost of the project and its overall completion time CPM
  • 6. CPM - Critical Path Method Drafting the design of Programme or Project Evaluation of drafted Programme or Project Review of evaluated Programme or Project
  • 7. PERT - Project Evaluation & Review Techniques To analyze and represent the tasks involved in completing a given project Accommodates the variation in event completion time Event-oriented technique rather than start- and completion-oriented Commonly used in conjunction with the critical path method
  • 8. Basic Terms In Network Analysis Activity Event Constraints Network Diagram Critical Path
  • 9. Steps in PERT/CPM 4. CONTROLLING 3. ALLOCATION OF RESOURCES 2. SCHEDULING 1. PLANNING
  • 10. PERT/CPM Project managers reply on PERT/CPM to help them answer questions such as: • What is the total time to complete the project? • What are the scheduled start and finish dates for each specific activity? • Which activities are critical and must be completed exactly as scheduled to keep the project on schedule? • How long can noncritical activities be delayed before they cause an increase in the project completion time?
  • 11. Both PERT and CPM • Graphically display the precedence relationships & sequence of activities • Estimate the project’s duration • Identify critical activities that cannot be delayed without delaying the project • Estimate the amount of slack associated with non-critical activities
  • 12. Framework for PERT and CPM • Define the Project. The Project should have only a single start activity and a single finish activity. • Develop the relationships among the activities. • Draw the "Network" connecting all the activities. • Assign time and/or cost estimates to each activity • Compute the critical path. • Use the Network to help plan, schedule, monitor and control the project.
  • 13. PERT Diagrams • Activity-on-node diagrams: • Maybe more than one single start and end node • Nodes represent activities • Arrows indicate precedence • Activity-on-arrow diagrams: • One single start and one single end node • An arrow represents a task, while a node is the completion of a task • Arrows represent activities • Nodes indicate beginning/end of activities 13
  • 14. Dummy Activities • Sometimes it is necessary to insert dummy activities (duration zero) in order to maintain the clarity of the diagram and the precedence relationships between activities. • In activity-on-arrow PERT diagrams, each activity must be uniquely identifiable by its start and end nodes. • However, sometimes multiple tasks have the same predecessors and successors. 14
  • 15. DUMMY ACTIVITY Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 53 6 7 2 4
  • 16. Determining the Critical Path • Step 1: Make a forward pass through the network as follows: For each activity i beginning at the Start node, compute: • Earliest Start Time (ES) = the maximum of the earliest finish times of all activities immediately preceding activity i. (This is 0 for an activity with no predecessors.). This is the earliest time an activity can begin without violation of immediate predecessor requirements. • Earliest Finish Time (EF) = (Earliest Start Time) + (Time to complete activity i. This represent the earliest time at which an activity can end. The project completion time is the maximum of the Earliest Finish Times at the Finish node.
  • 17. Determining the Critical Path • Step 2: Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Start node. At a given node, j, consider all activities ending at node j. For each of these activities, (i,j), compute: • Latest Finish Time (LF) = the minimum of the latest start times beginning at node j. (For node N, this is the project completion time.). This is the latest time an activity can end without delaying the entire project. • Latest Start Time (LS) = (Latest Finish Time) - (Time to complete activity (i,j)). This is the latest time an activity can begin without delaying the entire project.
  • 18. Determining the Critical Path • Step 3: Calculate the slack time for each activity by: Slack = (Latest Start) - (Earliest Start), or = (Latest Finish) - (Earliest Finish). A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times.
  • 19. A Simple Project Activity Immediate Predecessor Expected Time A - 5 B - 6 C A 4 D A, B 2
  • 21. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Difference Time
  • 23. • Activity time estimates usually can not be made with certainty. • PERT used for probabilistic activity times. • In PERT, three time estimates are used: most likely time (m), the optimistic time (a) , and the pessimistic time (b). • These provide an estimate of the mean and variance of a beta distribution: • mean (expected time): • variance: 6 b4mat  2 6 a-b           v Probabilistic Activity Times
  • 25. Difference Between PERT & CPM Probabilistic Model Non-repetitive Jobs like planning & scheduling of programmes Results calculated on basis of Events Related with activities of uncertain time Deterministic Model Repetitive Jobs like residential construction Results calculated on basis of activities Related with activities of Well Known time PERT CPM
  • 26. Advantages of PERT/CPM Reduction in cost • Elimination of Risk in Complex activity Flexibility • Optimisation of Resources Reduction of Uncertainties
  • 27. Disadvantages of PERT/CPM Network charts tend to be large Lack of a timeframe on most PERT/CPM charts makes it harder to show status When PERT/CPM charts become unwieldy, they are no longer used to manage the project Planning & Implementation required skillful personnel
  • 28. PERT TABLE NO. ACTIVITY KOEFISIEN Days Labors Toptimis (a) Tmostlikely (m) Tpesimis (b) Texpected (Te) Variance (v) A PREPARATION, MINING AND LAND 32 6,10,16 8,5/6,4 6 10 16 10,33333333 2,777777778 B FOUNDATION AND CONCRETE CONSTRUCTION 240 40,60,80 8,6,4 40 60 80 60 44,44444444 C COUPLE AND PLASTERING CONSTRUCTION 12 2,4,6 6,4,3 2 4 6 4 0,444444444 D FLOOR AND WALL INSTALLATION 12 1,1,4 4,4,1 4 10 12 9,333333333 1,777777778 E ROOF CONSTRUCTION 42 6,7,11 7,6,4 11 14 21 14,66666667 2,777777778 F CEILING INSTALLATION 4 1,1,4 4,4,1 1 1 4 1,5 0,25 G INSTALLATION KUSEN, DOOR AND WINDOW 15 2,3,5 8,5,3 2 3 5 3,166666667 0,25 H EQUIPMENT INSTALLATION DOOR AND WINDOW 6 1,2,3 6,3,2 1 2 3 2 0,111111111 I INSTALLATION OF SANITARY 24 3,4,6 8,6,4 3 4 6 4,166666667 0,25 J1 SEPTIC TANK 10 4,5,10 3,2,1 4 5 10 5,666666667 1 J2 PLUMBING 7 3,4,7 3,2,1 3 4 7 4,333333333 0,444444444 K1 PLN INSTALLATION 1 1,1,2 2,1,1 1 1 2 1,166666667 0,027777778 K2 CABLE 3 1,2,3 3,2,1 1 2 3 2 0,111111111 K3 FINISHING 1 1.2.3 2,1,1 1 1 2 1,166666667 0,027777778 L PAINTING 7 1,1,3 1,1,3 3 4 7 4,333333333 0,444444444 M FINISHING 8 3,4,8 3,2,1 3 4 8 4,5 0,694444444
  • 29. PERT DIAGRAM A B C K1 E F J2J1 G I D L H K2 I K3 M NO. ACTIVITY Texpected (Te) A PREPARATION, MINING AND LAND 10,33 B FOUNDATION AND CONCRETE CONSTRUCTION 60 C COUPLE AND PLASTERING CONSTRUCTION 4 D FLOOR AND WALL INSTALLATION 9,33 E ROOF CONSTRUCTION 14,67 F CEILING INSTALLATION 1,5 G INSTALLATION KUSEN, DOOR AND WINDOW 3,17 H EQUIPMENT INSTALLATION DOOR AND WINDOW 2 I INSTALLATION OF SANITARY 4,17 J1 SEPTIC TANK 5,67 J2 PLUMBING 4,34 K1 PLN INSTALLATION 1,17 K2 CABLE 2 K3 FINISHING 1,17 L PAINTING 4,34 M FINISHING 4,5
  • 31. S ^ = 54,25 S=7,365459931328117 Z=(120-115,5)/ 7,365 Z= 0,61 Z= 74,8 % NO. ACTIVITY Variance (v) CRITICAL PATH A PREPARATION, MINING AND LAND 2,777777778 YA B FOUNDATION AND CONCRETE CONSTRUCTION 44,44444444 YA C COUPLE AND PLASTERING CONSTRUCTION 0,444444444 YA D FLOOR AND WALL INSTALLATION 1,777777778 YA E ROOF CONSTRUCTION 2,777777778 YA F CEILING INSTALLATION 0,25 YA G INSTALLATION KUSEN, DOOR AND WINDOW 0,25 YA H EQUIPMENT INSTALLATION DOOR AND WINDOW 0,111111111 YA I INSTALLATION OF SANITARY 0,25 YA J1 SEPTIC TANK NO J2 PLUMBING NO K1 PLN INSTALLATION NO K2 CABLE NO K3 FINISHING 0,027777778 YA L PAINTING 0,444444444 YA M FINISHING 0,694444444 YA S^2 54,25