PMP® Sample
Questions
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the
development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every
attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.
However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially
published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or
expressed by OSP International LLC.
This presentation will showcase free sample
PMP® questions that will help and guide
you in studying for your PMP® exam
Find more free sample questions when you visit
www.free-pm-exam-questions.com and
free.pm-exam-simulator.com
1. ____________ is the total cost to produce the product or service of the
project while meeting the quality standards plus the operating cost.
A. Total Cost of Ownership
B. Estimated Cost
C. Cost of Quality
D. Budgeted Cost
Hint:What is the total cost of a product?.
Sample PMP® Exam Question
The correct answer is A
Explanation:Total Cost of Ownership is the total cost
of a product including the development cost, quality
activities cost, and operating costs. Cost of Quality
means the Cost of Quality activities only. Neither
Budgeted Cost nor Estimated Cost are the actual costs
to produce the product.
Answer and Explanation
2. Tim is working on an electronic manufacturing project and he wants to establish a
warranty for some of the precision parts he is buying. What risk response strategy is he
using?
A. Mitigate
B. Avoid
C. Accept
D. Transfer
Hint:Tim is shifting the negative impact of the risk.
Sample PMP® Exam Question
The correct answer is D
Explanation: Risk transfer requires shifting some or all of
the negative impact of a threat, along with the ownership
of the response.Taking out insurance or a warranty
transfers the risk from the owner to the other party.
Answer and Explanation
3. In your project, you want to ensure that each requirement adds business value by
linking it to the business and project objectives. This also provides a means to track
requirements throughout the project life cycle, helping to ensure that requirements
approved in the requirements documentation are delivered at the end of the project.
The document that helps to achieve this is called:
A. Requirements Documentation
B. Brainstorming
C. Requirements Management Plan
D. RequirementsTraceability Matrix
Hint: This question is asking you how to trace the requirements from project beginning to end.
Sample PMP® Exam Question
The correct answer is D
Explanation:The RequirementsTraceability Matrix is a
table that links requirements to their origin and traces
them throughout the project life cycle.The
implementation of a RequirementsTraceability Matrix
helps ensure that each requirement adds business value
by linking it to the business and project objectives. It
provides a means to track requirements throughout the
project life cycle, helping to ensure that requirements
approved in the requirements documentation are
delivered at the end of the project.
Answer and Explanation
4.What is risk tolerance?
A. Risks created by tolerating customer behavior
B. Willingness to accept varying degrees of risk
C. Risks created by zero tolerance
D. Being tolerant if stakeholders are willing to accept risks
Hint: Look for the "least strange" answer.
Sample PMP® Exam Question
The correct answer is B
Explanation: Do you feel that three of these choice are odd?
Correct, they are and they were included intentionally.
Sometimes you can expect to find some ""funny"" answer
choices. Risk tolerance is the stakeholders' willingness to
accept varying degrees of risk.
Answer and Explanation
5. The total authorized budget for your IT project is $160,000 and Management
Reserves are $20,000. You want to measure cost performance to see how the project
is doing. In this context, the cost performance is against measured which of the
following budget amounts?
A. $180,000
B. $160,000
C. $20,000
D. $140,000
Hint:The Cost Baseline includes all authorized budgets.The Cost Baseline is used to measure the
Cost Performance of the project.
Sample PMP® Exam Question
The correct answer is B
Explanation: Cost Performance is measured against
authorized budget. Management Reserves are not added
to the Cost Performance Baseline and are not used for
measuring cost performance.
Answer and Explanation

More Related Content

PPTX
AI for Business Process Management
PDF
Hexagonal symfony
PDF
Use Body Language to Rock Your Next Presentation
PPTX
Business Process Monitoring and Mining
PPTX
Chaos theory
PPTX
The Power of Partnering: Driving Source-to-Pay Success with Zycus Partner Con...
PPT
Session 6 gdas pmp study group presentation
PDF
Pm study project risk management test
AI for Business Process Management
Hexagonal symfony
Use Body Language to Rock Your Next Presentation
Business Process Monitoring and Mining
Chaos theory
The Power of Partnering: Driving Source-to-Pay Success with Zycus Partner Con...
Session 6 gdas pmp study group presentation
Pm study project risk management test

Similar to PMP Exam Sample Questions (20)

PPTX
PMP Sample Questions Set 5
PDF
PMP Sample Questions Set 5
PPTX
PMP Exam Sample Questions Set 4
PDF
PMP Five Sample Questions
PDF
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PPTX
PMP Exam Sample Questions Set 6
PDF
PMP Exam Sample Questions
PDF
PMP Exam Sample Questions
PDF
Pmp Five Sample Questions
PDF
Sample PMP Exam Questions
PDF
PMP Exam Sample Questions
PDF
PMP® Sample Questions Set #2
PDF
PMP Lite Mock Exam2.pdf
PDF
Pmp test 03
PDF
PMP Sample Questions Set 3
PDF
PMP® Sample Questions 6
PDF
Pmp sample questions set2
PDF
Pmp test 01
PDF
PMP Sample Questions Set3
PDF
PMP Exam Sample Questions
PMP Sample Questions Set 5
PMP Sample Questions Set 5
PMP Exam Sample Questions Set 4
PMP Five Sample Questions
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions
PMP Exam Sample Questions
Pmp Five Sample Questions
Sample PMP Exam Questions
PMP Exam Sample Questions
PMP® Sample Questions Set #2
PMP Lite Mock Exam2.pdf
Pmp test 03
PMP Sample Questions Set 3
PMP® Sample Questions 6
Pmp sample questions set2
Pmp test 01
PMP Sample Questions Set3
PMP Exam Sample Questions
Ad

More from OSP International LLC (20)

PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free PMP Exam Sample Question of the Week
PDF
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
Ad

Recently uploaded (20)

PDF
anganwadi services for the b.sc nursing and GNM
PDF
Fun with Grammar (Communicative Activities for the Azar Grammar Series)
PDF
Compact First Student's Book Cambridge Official
PDF
faiz-khans about Radiotherapy Physics-02.pdf
PDF
fundamentals-of-heat-and-mass-transfer-6th-edition_incropera.pdf
PDF
Farming Based Livelihood Systems English Notes
PPTX
Power Point PR B.Inggris 12 Ed. 2019.pptx
PDF
Diabetes Mellitus , types , clinical picture, investigation and managment
PPT
hsl powerpoint resource goyloveh feb 07.ppt
PPTX
Theoretical for class.pptxgshdhddhdhdhgd
PPTX
Thinking Routines and Learning Engagements.pptx
PPTX
Why I Am A Baptist, History of the Baptist, The Baptist Distinctives, 1st Bap...
PDF
CAT 2024 VARC One - Shot Revision Marathon by Shabana.pptx.pdf
PDF
Nurlina - Urban Planner Portfolio (english ver)
PPTX
Neurological complocations of systemic disease
PDF
Hospital Case Study .architecture design
PPTX
Integrated Management of Neonatal and Childhood Illnesses (IMNCI) – Unit IV |...
PPT
Acidosis in Dairy Herds: Causes, Signs, Management, Prevention and Treatment
PDF
Everyday Spelling and Grammar by Kathi Wyldeck
PPTX
2025 High Blood Pressure Guideline Slide Set.pptx
anganwadi services for the b.sc nursing and GNM
Fun with Grammar (Communicative Activities for the Azar Grammar Series)
Compact First Student's Book Cambridge Official
faiz-khans about Radiotherapy Physics-02.pdf
fundamentals-of-heat-and-mass-transfer-6th-edition_incropera.pdf
Farming Based Livelihood Systems English Notes
Power Point PR B.Inggris 12 Ed. 2019.pptx
Diabetes Mellitus , types , clinical picture, investigation and managment
hsl powerpoint resource goyloveh feb 07.ppt
Theoretical for class.pptxgshdhddhdhdhgd
Thinking Routines and Learning Engagements.pptx
Why I Am A Baptist, History of the Baptist, The Baptist Distinctives, 1st Bap...
CAT 2024 VARC One - Shot Revision Marathon by Shabana.pptx.pdf
Nurlina - Urban Planner Portfolio (english ver)
Neurological complocations of systemic disease
Hospital Case Study .architecture design
Integrated Management of Neonatal and Childhood Illnesses (IMNCI) – Unit IV |...
Acidosis in Dairy Herds: Causes, Signs, Management, Prevention and Treatment
Everyday Spelling and Grammar by Kathi Wyldeck
2025 High Blood Pressure Guideline Slide Set.pptx

PMP Exam Sample Questions

  • 1. PMP® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  • 2. This presentation will showcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3. 1. ____________ is the total cost to produce the product or service of the project while meeting the quality standards plus the operating cost. A. Total Cost of Ownership B. Estimated Cost C. Cost of Quality D. Budgeted Cost Hint:What is the total cost of a product?. Sample PMP® Exam Question
  • 4. The correct answer is A Explanation:Total Cost of Ownership is the total cost of a product including the development cost, quality activities cost, and operating costs. Cost of Quality means the Cost of Quality activities only. Neither Budgeted Cost nor Estimated Cost are the actual costs to produce the product. Answer and Explanation
  • 5. 2. Tim is working on an electronic manufacturing project and he wants to establish a warranty for some of the precision parts he is buying. What risk response strategy is he using? A. Mitigate B. Avoid C. Accept D. Transfer Hint:Tim is shifting the negative impact of the risk. Sample PMP® Exam Question
  • 6. The correct answer is D Explanation: Risk transfer requires shifting some or all of the negative impact of a threat, along with the ownership of the response.Taking out insurance or a warranty transfers the risk from the owner to the other party. Answer and Explanation
  • 7. 3. In your project, you want to ensure that each requirement adds business value by linking it to the business and project objectives. This also provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. The document that helps to achieve this is called: A. Requirements Documentation B. Brainstorming C. Requirements Management Plan D. RequirementsTraceability Matrix Hint: This question is asking you how to trace the requirements from project beginning to end. Sample PMP® Exam Question
  • 8. The correct answer is D Explanation:The RequirementsTraceability Matrix is a table that links requirements to their origin and traces them throughout the project life cycle.The implementation of a RequirementsTraceability Matrix helps ensure that each requirement adds business value by linking it to the business and project objectives. It provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. Answer and Explanation
  • 9. 4.What is risk tolerance? A. Risks created by tolerating customer behavior B. Willingness to accept varying degrees of risk C. Risks created by zero tolerance D. Being tolerant if stakeholders are willing to accept risks Hint: Look for the "least strange" answer. Sample PMP® Exam Question
  • 10. The correct answer is B Explanation: Do you feel that three of these choice are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some ""funny"" answer choices. Risk tolerance is the stakeholders' willingness to accept varying degrees of risk. Answer and Explanation
  • 11. 5. The total authorized budget for your IT project is $160,000 and Management Reserves are $20,000. You want to measure cost performance to see how the project is doing. In this context, the cost performance is against measured which of the following budget amounts? A. $180,000 B. $160,000 C. $20,000 D. $140,000 Hint:The Cost Baseline includes all authorized budgets.The Cost Baseline is used to measure the Cost Performance of the project. Sample PMP® Exam Question
  • 12. The correct answer is B Explanation: Cost Performance is measured against authorized budget. Management Reserves are not added to the Cost Performance Baseline and are not used for measuring cost performance. Answer and Explanation