Wind Resource Potential
Wind speed dispersion follows a continuous probability frequency of values
occurrence at different sample spaces of the density function
(IbTroen.et.al, 1989).
𝑓 𝑢 =
𝑘
𝐴
(
𝑢
𝐴
) 𝑘−1
exp[−(
𝑢
𝐴
) 𝑘
]
(eq.2) Sound power level d(IEC-61-400-14)
Figure 2 Weibull distribution
Feasibility analysis of the power potential of small and medium scale wind projects in Leeds area
Author: Antonios Phinios STUDENT ID: 200728144, Supervisor: Prof. Alison Tomlin
0
20
40
60
80
100
120
0 5 10 15 20 25 30
PowerOutput(kW)
Wind speed (m/s)
GHRE-FD-100
ACKNOWLEDGEMENTS AND REFERENCES
ACKNOWLEDGEMENTS: Professor Alison Tomlin /James Goodwin/ Katrina Adam /University of Leeds/ Phinios
Demetrios
REFERENCES: J.T Millward Hopkins.et.al, A.S.T., L. Ma, D.B Ingham, M. Pourkashanian. 2012. Mapping the wind resource over UK
cities. 55, p9.
Noise and Statutory Nuisance Act 1993.
Ib Troen.et.al, E.L.P. 1989. European Wind Atlas.
IEC.61400. 2005. Wind Turbines: Design Requirements (IEC 61400-1)
DECC. 2015a. Feed In Tariff Scheme.
Wind.Measurement.International. 2015. Operational and Maintenance Costs for Wind Turbines. [Online]. Available from:
http://www.windmeasurementinternational.com/wind-turbines/om-turbines.php
OBJECTIVES
1. Identify Leeds urban wind resource availability for small
medium development with respect to legislative restrictions.
2. Convert wind resource potential to power potential
3. Specify potential sites for development.
4. Investigate investment potential for the purposed
development.
5. Extrapolate financial benefits to development potential.
RESULTS
1. Five sites of interest were identified with mean wind speeds
range of 6-8m/s applicable for wind turbine development of 16-
40% capacity factors (Table 2).
2. Most of the turbines have a payback period time of 6-7 years,
and a 500kW investment turbine is returned at year 5 (Figure 3).
3. Wind turbine of 20kW can provide electricity at 14 households
per year with average consumption of 3.3GWhe (Table 3).
4. Wind turbine of 100kW nominal power can support 250 vehicle
charging requirement (Figure 4).
5. Wind turbine of 500kW nominal power can support charging
requirements of 68 electric buses/ year with energy demands
of 3kWh/km on a 24km/day route (Figure 4)..
FUTURE WORK PROPOSALS
Comprehensive study to determine development potential of
Micro-Grid public transport charging infrastructure in Leeds.
INTRODUCTION
Effective energy systems desire certainty, versatility, sustainability and stability to meet both ends supply and demand. As power demand increases in urban areas, network operators find it difficult to stabilise both variables; often resulting to degradation of the
local network. Distributed generation is the key factor providing versatility, whereas wind energy integration supports the decentralisation of power dependence.
Investment Potential
Restrictions
Sites specification
RESEARCH ACTIVITY
Restriction: Input information , Turbine Selection Site Identification: Wind Resource Potential (m/s) Site Specification: Power potential (m/s)→(kW)→(kWh)
Investment potential (kWh)→(£) →(utilities)
Investment Potential
• Net Present Value (NPV) sum of all discounted annual cash flows
associated with the project.
• N lifetime of the project
• discount rate (d) Net product prices annual (i) reductions
• Export Fraction (x): Supply effectiveness of the turbine in terms utilization
Low export fraction: (0%) HIGH utilization
High export fraction (100%) high TRANSMMITANCE
Setting a step of 20% export fraction the influence of direct utility on turbine
investment is estimated and presented (Figure 3)
Generated electricity (Table 2) from wind turbines at all
heights is assumed to be employed to support
either community energy or electric mobility.
1. Community Energy:
Average household consumption: 3,300kWh/year
(OFGEM, 2011) , Grid carbon intensity (UK) is
426gCO2/kWh (Earth Notes, 2015) the benefits can
compromise from environmental and technical
perspective (Table 3).
Table 3: Community energy utilization scenario
2. Transport Electrification
Request of charge calculations for Light Duty
Vehicles (LDV) and High Duty Vehicles (HDV) are
summarised (Tables 4,5).and graphically represented
(Figure 4).
Restrictions were extracted as map
information in accordance with eq.1
Turbine Selection
Turbine selection was based primarily on nominal power and secondarily on
their technical specifications as provided by the manufacturers.
Acoustic assessment was performed for each turbine to evaluate the
minimum acceptable distance (r) from households.
(eq. 1) Sound power level dispersion (IEC-61-400-14)
Input Information
Leeds urban mean wind speed and direction
information was assessed from a previous
study.(J.T Millward Hopkins.et.al, 2012)
Therefore the broad area of investigation is
restricted based on the information provided
(Figure 1).
(Figure 1) Area of investigation
Restrictions with
correspondence to the limit of
42dBLAeq,5 mins(Regulatory Office,1993)
[Noise and statutory nuisance
act 1993]
Lp (dB) 42
Lw (dB) Sound power level
Q Directivity factor (=1)
r (m) Slant distance
𝐿 𝑝 = 𝐿 𝑤 − 10 ∗ log(
𝑄
4𝜋𝑟2
)
In accordance with the UK Weibull
Specifications(IbTroen.et.al, 1989)
mean wind speed distribution is
estimated for all potential sites and at
all heights:
h(m): 20 25 30 35 50
Weibull Distribution
Specifications (UK)
Shape factor
(k)
1.8
Scale factor
(A)
1.124
WindATLAS exclusions:
Frequencies
(f)
<0.01
umean (m/s) ≤3m/s
Height (m) >50
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.09
0 1.5 3 4.5 6 7.5 9 10.5 12 13.5
Probability
Wind Speed (m/s)
POINT A
POINT B
Poly. (POINT A)
Poly. (POINT B)
Heights
(m)
[LONG. , LAT.] [0] Umean
Turbine
Type
Annual
Generated
Energy
(GWh/year
)
Capacity
Factor
(Cp)
20 [53.762 , -1.675] 6.02
CF20 52 29%
WindEN-45 62 16%
25 [53.767 , -1.683] 7.1
GHRE-FD-
100
309 37%
30 [53.764 , -1.676] 6.8
GHRE-FD-
101
288 35%
35 [53.844 , -1.428] 7.7
NPS-60 299 44%
GHRE-FD-
100
399 42%
GEV-MP-
250
429 20%
50 [53.840 , -1.428] 8
GEV-MP-
275
545 23%
WTN-500 2148 40%
Power Potential
Power performance tests as provided by
manufacturers(IEC61-400-12) specify the power
output of a turbine at various speeds,
therefore:
• wind speed information (m/s)
is extracted to power (kW)
• and the distributive characteristics
of wind speed f(1)
• are converted to f(hours/annum)
The outcome is annual energy generated
(kWh/year) for all turbine types at all
specified sites and heights(Table 2).
Table (2) Annual energy generated for all turbine types
CF20
(20m)
GHRE-
FD-100
(25m)
GHRE-
FD-100
(30m)
NPS-60
(35m)
GHRE-
FD-100
(35m)
GEV-
MP-
250
(35m)
GEV-
MP-
275
(50m)
WTN-
500
(50m)
x(0%) 12 7 7 5 5 10 11 4
x(20%) 13 7 7 6 5 11 11 4
x(40%) 14 7 8 6 6 11 11 4
x(60%) 15 8 8 6 6 12 12 5
x(80%) 16 8 9 7 6 13 13 4
x(100%) 17 9 9 7 6 14 13 5
0
2
4
6
8
10
12
14
16
18
20
Years
x(0%)
x(20%)
x(40%)
x(60%)
x(80%)
x(100%)
𝑵𝑷𝑽 =
𝑵=𝟏
𝑵
𝑪𝒂𝒔𝒉 𝑭𝒍𝒐𝒘 𝑵
(𝟏 + 𝒅) 𝑵
𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 £ = 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 − 𝐼𝑛𝑐𝑜𝑚𝑒 𝐹𝑙𝑜𝑤
𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 £ = 𝐶𝐴𝑃𝐸𝑋 + 𝑂𝑃𝐸𝑋
𝐼𝑛𝑐𝑜𝑚𝑒 𝐹𝑙𝑜𝑤 = 𝐹𝑔 + 𝐹𝑒 𝑥 + 𝐸 1 − 𝑥 𝑌𝑖(1 − 𝑓)𝑖−1
Figure 3 payback period for all turbine types with varying export fraction
Development potential
Community Energy
Height (m) 20 25 30 35 50
Annual electricity
generated (GWh/year)
43 238 256 355 1779
Households/year 13 75 81 112 566
tnCO2/year (savings)
1833 10145. 10891 15126 75780
HDV
Energy
Demands
(kWh/km)
Average
Route
Daily (km)
Energy
Consumption
(kWh/year)
3 25 27375
LDV
BEV Diesel Car
Battery
Capacity
(kWh)
Consum
ption
(kWh/km
)
Daily
distance
Travel
Consum
ption
(kWh/ye
ar)
Gco2/km
Daily
Distance
(km)
Annual
Emissions
(tnCO2/yea
r
25 0.2 15 1095 110 15 6.03
0 1000 2000
20
35
50
Height (m)
20 35 35 50 50
HDV 2 10 14 17 68
LDV 41 245 340 433 1706
HDV
LDV
Figure 4 LDV HDV charging availability per year

More Related Content

PDF
Application of resistance energy model to optimising electric power consumpti...
PDF
Ba35291294
PDF
Micro Wind Turbine paper
PPTX
WFO_SDM_2012_Souma
PPT
COSTMODEL_IDETC_2010_Jie
PDF
Power system operation considering detailed modelling of the natural gas supp...
PDF
Feasibility Study of a Grid Connected Hybrid Wind/PV System
PDF
Improving the delivered power quality from WECS to the grid based on PMSG con...
Application of resistance energy model to optimising electric power consumpti...
Ba35291294
Micro Wind Turbine paper
WFO_SDM_2012_Souma
COSTMODEL_IDETC_2010_Jie
Power system operation considering detailed modelling of the natural gas supp...
Feasibility Study of a Grid Connected Hybrid Wind/PV System
Improving the delivered power quality from WECS to the grid based on PMSG con...

What's hot (19)

PDF
Improved Performance of DFIG-generators for Wind Turbines Variable-speed
PDF
Energy Distance on an Electric Power Grid
PDF
A New Compensation Control Strategy for Grid-connected Wind Turbine and Fuel ...
PDF
IRJET- Modelling of a PMSG Wind Turbine with Voltage Control
PDF
PI and LQR controllers for Frequency Regulation including Wind Generation
PDF
A probabilistic multi-objective approach for FACTS devices allocation with di...
PDF
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
PPTX
Renewable Energy for Cell-Phone Towers
PDF
Impact of compressed air energy storage system into diesel power plant with w...
PPTX
VIDMAP_Aviation_2014_Souma
PDF
Experimental Verification of the main MPPT techniques for photovoltaic system
PDF
Dynamic Analysis of Power Cable in Floating Offshore Wind Turbine
PDF
Design and Simulation Analysis of Outer Stator Inner Rotor DFIG by 2d and 3d ...
PDF
Evaluation of the Energy Performance of the Amougdoul Wind Farm, Morocco
PDF
Performance Analysis of Antenna Selection Techniques in MIMO-OFDM System with...
PDF
Design and analysis of an external rotor internal-stator doubly fed induction...
PDF
Ijetr011932
PDF
IRJET- A Review of MPPT Algorithms Employed in Wind Energy Conversion System
PDF
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
Improved Performance of DFIG-generators for Wind Turbines Variable-speed
Energy Distance on an Electric Power Grid
A New Compensation Control Strategy for Grid-connected Wind Turbine and Fuel ...
IRJET- Modelling of a PMSG Wind Turbine with Voltage Control
PI and LQR controllers for Frequency Regulation including Wind Generation
A probabilistic multi-objective approach for FACTS devices allocation with di...
Resource aware wind farm and D-STATCOM optimal sizing and placement in a dist...
Renewable Energy for Cell-Phone Towers
Impact of compressed air energy storage system into diesel power plant with w...
VIDMAP_Aviation_2014_Souma
Experimental Verification of the main MPPT techniques for photovoltaic system
Dynamic Analysis of Power Cable in Floating Offshore Wind Turbine
Design and Simulation Analysis of Outer Stator Inner Rotor DFIG by 2d and 3d ...
Evaluation of the Energy Performance of the Amougdoul Wind Farm, Morocco
Performance Analysis of Antenna Selection Techniques in MIMO-OFDM System with...
Design and analysis of an external rotor internal-stator doubly fed induction...
Ijetr011932
IRJET- A Review of MPPT Algorithms Employed in Wind Energy Conversion System
Novel Adaptive Controller for PMSG Driven Wind Turbine To Improve Power Syste...
Ad

Viewers also liked (16)

PDF
certificate forklift02
PDF
certificate forklift01
PDF
Marechal DN Robust Decontactor - Industrial Plugs & Sockets
PDF
Unit 1 Story 2 Shiloh
PPTX
Relief agencies
PPTX
James Sherman – Personal Growth
PPTX
Curso de programacion
PDF
Silicon Solar Brochure - AquaJet 12V Medium Output Solar Fountain Pump
PDF
Base_Brand Launch_LoRes
PPT
Materiales Didácticos de Matematicas
PDF
Silicon Solar Brochure - EnviroLight Solar Billboard Lighting Systems
DOCX
LA PARTICIPACIÓN DE LOS PADRES DE FAMILIA EN LA ADQUISICIÓN DE LA LECTURA EN ...
PDF
JTCA on Minto's Potter's Key subdivision
PPT
Arrazakeria
PPTX
biomass presentation
PDF
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
certificate forklift02
certificate forklift01
Marechal DN Robust Decontactor - Industrial Plugs & Sockets
Unit 1 Story 2 Shiloh
Relief agencies
James Sherman – Personal Growth
Curso de programacion
Silicon Solar Brochure - AquaJet 12V Medium Output Solar Fountain Pump
Base_Brand Launch_LoRes
Materiales Didácticos de Matematicas
Silicon Solar Brochure - EnviroLight Solar Billboard Lighting Systems
LA PARTICIPACIÓN DE LOS PADRES DE FAMILIA EN LA ADQUISICIÓN DE LA LECTURA EN ...
JTCA on Minto's Potter's Key subdivision
Arrazakeria
biomass presentation
Baur PD Partial Discharge Portable System - PD-TaD 60 Portable PD Diagnostics...
Ad

Similar to poster (20)

PPT
Wind energy
PDF
Wind turbines in farm locations: opportunities, barriers and solutions - Davi...
PDF
EUREC-NTUA Projects - Carlos Silva
DOCX
Wind site evaluation assign Steven Sweeney K00181764
PPS
Blake Lapthorn green breakfast with Gregory Dix, Associate Director of Savills
PPT
28328791-Wind-Energy-ppt.ppt
PPTX
1_1 Wind Energy Technology SLIEDS SHOWN IN CLASS ME 568 Jul-Dec 2023.pptx
PDF
33kV 66kV A Wind Farm Collection Grid Technical Comparison
PDF
Iaetsd alternate energy in the tractions
PDF
SIMULATION AND DESIGNING OF SMALL SCALE WIND ENERGY SYSTEM FOR RURAL AREA
PPTX
Intro to wind energy
PPT
Session 15 wind power
PDF
Ai33194200
PDF
Ai33194200
PDF
2001 fp5 brochure_energy_env
DOCX
Wind turbine report
PDF
16.pdfexperimental measurements of the performance of a micro-wind turbine lo...
PDF
Farm Wind Energy - David Roe (IEP)
PDF
Design and Analysis of Artificial Intelligence Based Approach for Control of ...
PPT
wind energy
Wind energy
Wind turbines in farm locations: opportunities, barriers and solutions - Davi...
EUREC-NTUA Projects - Carlos Silva
Wind site evaluation assign Steven Sweeney K00181764
Blake Lapthorn green breakfast with Gregory Dix, Associate Director of Savills
28328791-Wind-Energy-ppt.ppt
1_1 Wind Energy Technology SLIEDS SHOWN IN CLASS ME 568 Jul-Dec 2023.pptx
33kV 66kV A Wind Farm Collection Grid Technical Comparison
Iaetsd alternate energy in the tractions
SIMULATION AND DESIGNING OF SMALL SCALE WIND ENERGY SYSTEM FOR RURAL AREA
Intro to wind energy
Session 15 wind power
Ai33194200
Ai33194200
2001 fp5 brochure_energy_env
Wind turbine report
16.pdfexperimental measurements of the performance of a micro-wind turbine lo...
Farm Wind Energy - David Roe (IEP)
Design and Analysis of Artificial Intelligence Based Approach for Control of ...
wind energy

poster

  • 1. Wind Resource Potential Wind speed dispersion follows a continuous probability frequency of values occurrence at different sample spaces of the density function (IbTroen.et.al, 1989). 𝑓 𝑢 = 𝑘 𝐴 ( 𝑢 𝐴 ) 𝑘−1 exp[−( 𝑢 𝐴 ) 𝑘 ] (eq.2) Sound power level d(IEC-61-400-14) Figure 2 Weibull distribution Feasibility analysis of the power potential of small and medium scale wind projects in Leeds area Author: Antonios Phinios STUDENT ID: 200728144, Supervisor: Prof. Alison Tomlin 0 20 40 60 80 100 120 0 5 10 15 20 25 30 PowerOutput(kW) Wind speed (m/s) GHRE-FD-100 ACKNOWLEDGEMENTS AND REFERENCES ACKNOWLEDGEMENTS: Professor Alison Tomlin /James Goodwin/ Katrina Adam /University of Leeds/ Phinios Demetrios REFERENCES: J.T Millward Hopkins.et.al, A.S.T., L. Ma, D.B Ingham, M. Pourkashanian. 2012. Mapping the wind resource over UK cities. 55, p9. Noise and Statutory Nuisance Act 1993. Ib Troen.et.al, E.L.P. 1989. European Wind Atlas. IEC.61400. 2005. Wind Turbines: Design Requirements (IEC 61400-1) DECC. 2015a. Feed In Tariff Scheme. Wind.Measurement.International. 2015. Operational and Maintenance Costs for Wind Turbines. [Online]. Available from: http://www.windmeasurementinternational.com/wind-turbines/om-turbines.php OBJECTIVES 1. Identify Leeds urban wind resource availability for small medium development with respect to legislative restrictions. 2. Convert wind resource potential to power potential 3. Specify potential sites for development. 4. Investigate investment potential for the purposed development. 5. Extrapolate financial benefits to development potential. RESULTS 1. Five sites of interest were identified with mean wind speeds range of 6-8m/s applicable for wind turbine development of 16- 40% capacity factors (Table 2). 2. Most of the turbines have a payback period time of 6-7 years, and a 500kW investment turbine is returned at year 5 (Figure 3). 3. Wind turbine of 20kW can provide electricity at 14 households per year with average consumption of 3.3GWhe (Table 3). 4. Wind turbine of 100kW nominal power can support 250 vehicle charging requirement (Figure 4). 5. Wind turbine of 500kW nominal power can support charging requirements of 68 electric buses/ year with energy demands of 3kWh/km on a 24km/day route (Figure 4).. FUTURE WORK PROPOSALS Comprehensive study to determine development potential of Micro-Grid public transport charging infrastructure in Leeds. INTRODUCTION Effective energy systems desire certainty, versatility, sustainability and stability to meet both ends supply and demand. As power demand increases in urban areas, network operators find it difficult to stabilise both variables; often resulting to degradation of the local network. Distributed generation is the key factor providing versatility, whereas wind energy integration supports the decentralisation of power dependence. Investment Potential Restrictions Sites specification RESEARCH ACTIVITY Restriction: Input information , Turbine Selection Site Identification: Wind Resource Potential (m/s) Site Specification: Power potential (m/s)→(kW)→(kWh) Investment potential (kWh)→(£) →(utilities) Investment Potential • Net Present Value (NPV) sum of all discounted annual cash flows associated with the project. • N lifetime of the project • discount rate (d) Net product prices annual (i) reductions • Export Fraction (x): Supply effectiveness of the turbine in terms utilization Low export fraction: (0%) HIGH utilization High export fraction (100%) high TRANSMMITANCE Setting a step of 20% export fraction the influence of direct utility on turbine investment is estimated and presented (Figure 3) Generated electricity (Table 2) from wind turbines at all heights is assumed to be employed to support either community energy or electric mobility. 1. Community Energy: Average household consumption: 3,300kWh/year (OFGEM, 2011) , Grid carbon intensity (UK) is 426gCO2/kWh (Earth Notes, 2015) the benefits can compromise from environmental and technical perspective (Table 3). Table 3: Community energy utilization scenario 2. Transport Electrification Request of charge calculations for Light Duty Vehicles (LDV) and High Duty Vehicles (HDV) are summarised (Tables 4,5).and graphically represented (Figure 4). Restrictions were extracted as map information in accordance with eq.1 Turbine Selection Turbine selection was based primarily on nominal power and secondarily on their technical specifications as provided by the manufacturers. Acoustic assessment was performed for each turbine to evaluate the minimum acceptable distance (r) from households. (eq. 1) Sound power level dispersion (IEC-61-400-14) Input Information Leeds urban mean wind speed and direction information was assessed from a previous study.(J.T Millward Hopkins.et.al, 2012) Therefore the broad area of investigation is restricted based on the information provided (Figure 1). (Figure 1) Area of investigation Restrictions with correspondence to the limit of 42dBLAeq,5 mins(Regulatory Office,1993) [Noise and statutory nuisance act 1993] Lp (dB) 42 Lw (dB) Sound power level Q Directivity factor (=1) r (m) Slant distance 𝐿 𝑝 = 𝐿 𝑤 − 10 ∗ log( 𝑄 4𝜋𝑟2 ) In accordance with the UK Weibull Specifications(IbTroen.et.al, 1989) mean wind speed distribution is estimated for all potential sites and at all heights: h(m): 20 25 30 35 50 Weibull Distribution Specifications (UK) Shape factor (k) 1.8 Scale factor (A) 1.124 WindATLAS exclusions: Frequencies (f) <0.01 umean (m/s) ≤3m/s Height (m) >50 0 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 0 1.5 3 4.5 6 7.5 9 10.5 12 13.5 Probability Wind Speed (m/s) POINT A POINT B Poly. (POINT A) Poly. (POINT B) Heights (m) [LONG. , LAT.] [0] Umean Turbine Type Annual Generated Energy (GWh/year ) Capacity Factor (Cp) 20 [53.762 , -1.675] 6.02 CF20 52 29% WindEN-45 62 16% 25 [53.767 , -1.683] 7.1 GHRE-FD- 100 309 37% 30 [53.764 , -1.676] 6.8 GHRE-FD- 101 288 35% 35 [53.844 , -1.428] 7.7 NPS-60 299 44% GHRE-FD- 100 399 42% GEV-MP- 250 429 20% 50 [53.840 , -1.428] 8 GEV-MP- 275 545 23% WTN-500 2148 40% Power Potential Power performance tests as provided by manufacturers(IEC61-400-12) specify the power output of a turbine at various speeds, therefore: • wind speed information (m/s) is extracted to power (kW) • and the distributive characteristics of wind speed f(1) • are converted to f(hours/annum) The outcome is annual energy generated (kWh/year) for all turbine types at all specified sites and heights(Table 2). Table (2) Annual energy generated for all turbine types CF20 (20m) GHRE- FD-100 (25m) GHRE- FD-100 (30m) NPS-60 (35m) GHRE- FD-100 (35m) GEV- MP- 250 (35m) GEV- MP- 275 (50m) WTN- 500 (50m) x(0%) 12 7 7 5 5 10 11 4 x(20%) 13 7 7 6 5 11 11 4 x(40%) 14 7 8 6 6 11 11 4 x(60%) 15 8 8 6 6 12 12 5 x(80%) 16 8 9 7 6 13 13 4 x(100%) 17 9 9 7 6 14 13 5 0 2 4 6 8 10 12 14 16 18 20 Years x(0%) x(20%) x(40%) x(60%) x(80%) x(100%) 𝑵𝑷𝑽 = 𝑵=𝟏 𝑵 𝑪𝒂𝒔𝒉 𝑭𝒍𝒐𝒘 𝑵 (𝟏 + 𝒅) 𝑵 𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤 £ = 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 − 𝐼𝑛𝑐𝑜𝑚𝑒 𝐹𝑙𝑜𝑤 𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 £ = 𝐶𝐴𝑃𝐸𝑋 + 𝑂𝑃𝐸𝑋 𝐼𝑛𝑐𝑜𝑚𝑒 𝐹𝑙𝑜𝑤 = 𝐹𝑔 + 𝐹𝑒 𝑥 + 𝐸 1 − 𝑥 𝑌𝑖(1 − 𝑓)𝑖−1 Figure 3 payback period for all turbine types with varying export fraction Development potential Community Energy Height (m) 20 25 30 35 50 Annual electricity generated (GWh/year) 43 238 256 355 1779 Households/year 13 75 81 112 566 tnCO2/year (savings) 1833 10145. 10891 15126 75780 HDV Energy Demands (kWh/km) Average Route Daily (km) Energy Consumption (kWh/year) 3 25 27375 LDV BEV Diesel Car Battery Capacity (kWh) Consum ption (kWh/km ) Daily distance Travel Consum ption (kWh/ye ar) Gco2/km Daily Distance (km) Annual Emissions (tnCO2/yea r 25 0.2 15 1095 110 15 6.03 0 1000 2000 20 35 50 Height (m) 20 35 35 50 50 HDV 2 10 14 17 68 LDV 41 245 340 433 1706 HDV LDV Figure 4 LDV HDV charging availability per year