2
Most read
4
Most read
7
Most read
Power Transformer Testing and
Commissioning GuidelinesR Sahoo
Procedure of Power Transformer Testing and
Commissioning
In Transformer testing and commissioning, it can be classified into power and
distribution transformers. It rating plate show nominal voltage, current of the primary
and secondary voltage at several of the tap changer, connection symbols (vector
group), % impedance weight of oil etc.
Before starting transformer testing some of the per-commissioning checks a physical
inspection of the transformer is to be carried out along with the general arrangement
drawing. The parts mentioned on the drawing are to be checked for physical mounting.
Check the following points before start the Transformer testing and commissioning:-
1. Oil leakage from bushing, valves, air release plugs, etc.
2. The direction of mounting of Buchholz relay, as per arrow on the relay; the arrow
should point towards the conservator.
3. Oil level in condenser bushing.
4. Oil level of the main tank and OLTC (On load Tap Changer) tank should be up
to the filling mark on MOG ( Minimum oil level gauge)
5. Earthed at two points.(Very important before starting the transformer testing)
6. Stoppers provided for locking of wheels.
7. Test taps on HV (High voltage) condenser bushing are fixed.
8. Valves on each radiator, both top and bottom should be open.
9. Valves on either side Buchholz relay should be open.
10. Arcing horns for the bushing, if provided to be set as per manufacturer’s
instructions. If LAs are provided for the transformer, it is advisable to set the
arcing horn distance a bit higher.
11. The tightness of conductor/cables on the transformer, HV side, LV side and
neutral to be checked.
12. Check resistance and IR (Insulation resistance) values of NGR (Neutral Ground
Resistor), if provided.
13. Ensure that oil is filled in OTI (Oil Temperature Indicator) and WTI (Winding
temperature Indicator) pockets.
14. Check that colour of silica gel in breathers of main conservator and OLTC (On
load Tap Changer) conservator is blue.
15. Oil in breather cups to be filled up to level indicated.
16. The diaphragm of explosion vent, if provided to be checked.
In Transformer Testing following electrical checks are to be carried out and results
recorded in the test reports.
Prior to ratio check OLTC (On load Tap Changer) if provide is to be made functional
OLTC can be of two types,
 OLTC inbuilt in the main tank
 OLTC separate chamber type
i. For in-built OLTC (diverter switch) ensure that the lamp on the drive mechanism
(DM) is same as the one in the display on the main tank. Then connection the
main operating rod between the OLTC DM and diverter switch. Conduct
mechanical operations on the OLTC taking it through all the taps. Ensure that
the final end position (upper and lower limit) switches operate.
ii. During the raise / lower operation note that direction of operating mechanism.
Switch off the 3 PH-AC supply and check the operation of raise / lower
contractor as per commands from DM.
iii. With OLTC at some intermediate tap, switch on the 3 phase supply and give
either raise / lower command to the OLTC. Check whether the mechanism is
moving in the right direction for the command given. If the direction is reverse,
switch off the AC and DC supply, verify that the phase sequence of the supply
is correct, if not correct reverse the phase sequence at the motor terminal box.
iv. Observe the operation of LOTC and check blocking of operation at the end
positions.
v. Verify that insertion of manual operating handle cuts off electrical operation.
vi. Test the Automatic Voltage Regulating Relay (AVRR), if provided perform an
automatic operation from the AVRR.
Transformer Testing:-
1-Ratio test:-
Apply 3 ph., 415V to high voltage winding
of the transformer and, ensure the induced voltage on the low voltage terminals at all
taps. Ensure variation in secondary volts as the taps are changed and compare the
results with manufacturers test report or ratio mentioned on transformer nameplate. If
delta tertiary stabilizing winding is provided (usually provided for Y Y transformers),
open the delta shorting link and measure the voltage across the two terminals during
ratio test it should be negligible. Refer above figure
2-Vector group test:
Transformer-vector-group
Make a test set up as per figure. Ensure that neutral of HV / LV are isolated from earth.
Measure the voltage as per test format EFS / Transformer.
3. No load / Magnetizing current test:-
Remove the shorting between primary &
secondary and measure the currents in all the phases while maintaining the supply at
primary. This test is done at a nominal tap and at the minimum and maximum taps.
Expected currents – Ir / Iy / IB – 1:0.0:1 for star transformer — Ir / Iy / Ib 1: 1:1.3 – for
delta transformer the currents should be in the order of mA. Refer the above figure.
4-Short circuit Current test:
With the transformer at nominal tap, apply 3ph 415 V to the primary and adequate
shorting on the secondary side ( depending on % impedance ) ensure bushing CT
(Current Transformer )secondaries and WTI CT secondaries are through a) Measure
currents in primary and secondary b) Check the current in CT secondary bushing
CT,WTI CT, LDC CT . Repeat point (a) at maximum & minimum taps.
5-Core balance test:-
Apply 415V between phase-phase (for delta transformer) and phase-neutral (for star
transformer) on secondary side. Ensure that adequate safety precautions are taken
on the primary side, as the high voltage will be induced. Measure the current and
voltage for the following phases – For Delta Transformer Vry, Vyb, Vbr For star
transformer -Vry, Vyb, Vbr, Vrn, Vyn, Vbn.
6-Insulation Test:-
Up to 6.6KV an insulation tester of 2.5 KV may be used and beyond 6.6 KV, 5 KV
voltage level may be used.
Polarisation index records by IR value at 10/1 min ratio.
Dielectric absorption 60 / 30 sec ratio Polarisation index 10/1 min ratio Interpretation
----- Less than 1 Unsatisfactory
1 to 1.25 1 to 2 Dubious
1.4 to 1.6 2 to 4 Good
More than 1.6 4 Very good
Note: IR values of delta tertiary stabilizing winding should also be taken with earth and
with HV and LV winding.
7-Transformer Oil Testing:-
Prior to the charging of transformer confirm the healthiness of the oil by testing the
dielectric strength of oil. The oil is to be tested at 2.5 mm gap. 6 nos reading have to
be taken and an average of these reading is the breakdown voltage of the oil.
8-Special Test:-
Winding resistance should be carried out with 24 V battery. Rheostat with 10 A rating,
along & digital multimeter, two pole switch Circuit as per figure connect the battery to
one winding of the transformer and adjust the current to 2A. Measure the voltage at
bushings. Winding resistance calculated should be compared with factory test results.
Do not disconnect the wires without reducing the current avoid voltage spikes.
A winding resistance test should be done after all the other tests have been completed.
Note: –In transformer testing, if more than one run of cable per phase is used on the
transformer LV side, it should be confirmed that there is no cross-over of phases
between any run. Such a crossover would result in a dead short circuit on the LV side
of the transformer. This can be verified during a no-load magnetizing current test the
magnetizing current on the transformer HV side should be in the order of mA, with the
Characteristics
Equipment
Voltage
Test
Method
Frequency of Test
Permissible
Limits
Remedial
action
Break Down voltage > 170 KV
70 - 170 KV
< 70 KV
IEC 156 Immediately prior charging > 50 KV
> 40 KV
> 30 KV
Reconditioning
all the LV side cables connected. Alternatively, thus can be confirmed during the
transformer differential stability test.
Prior to energizing ensure the following in transformer testing:-
I. Cleaning of the transformer, especially the bushing. Ensure that all protections
are operative. Buchholz relay may be tested by using the test screw, or by
pumping in air with a bicycle pump, or by draining oil from the relay after closing
both side valves.
II. Air release from the transformer is to be done from air release plugs on the
main tank, radiators, HV & LV bushing, Buchholz relay and OLTC prior to
charging of transformer. Do not release air from the condenser bushing as they
are hermetically sealed.
III. Check operation of OTI / WTI, ensure oil in the temperature probe pots.
IV. All interconnecting valves are the open position.
V. Check IR value between each winding to earth, and between windings. Neutral
earthing is to be disconnected for this purpose.
VI. Check that HV and LV neutral earthing has been re-connected after megger
test.
VII. Earthing and delta shorting of tertiary stabilizing winding (if provided), to be
checked.
VIII. Proper setting of OTI & WTI to be done.
IX. Perform trip test from all the transformer protections, including Buchholz relay,
PRD, Oil surge relay, OTI, and WTI.
X. All protection relays to be properly set.
XI. Reset the maximum reading pointer (MRP) of OTI & WTI.
XII. Ammeter selector switches should be selected to read some phase current.
XIII. All MCBs, fuses, and switches in Marshalling boxes, Craps, isolator cubicles
and breaker cubicles should be in the circuit.
XIV. If the transformer is provided with an OLTC, energize it at Tap#1; if the
transformer is provided with an off-circuit tap changer, energize it at the nominal
tap.
Testing of Fan control Cubicle:-
Fan control cubicle houses the control and hardware for running of cooling fans with
the fans running the transformer can be loaded to the specified rating on the nameplate
(ONAF).
The fans are started with the operation of WTI contact. Preferably S1 should be
allocated to run the fans. Normally two banks of 4 fans are provided on the radiators.
IN each bank one fan is spare and three fans will run continuously until that contact
from WTI drops out. Prior to starting of fans following thing have to be checked:-
1. Measure IR value of the fan motors.
2. Check for free rotation of fan blades (rotor), ensure that they do not foul with
the radiators.
3. Ensure proper earthing of motors, fixing of fan on the frames
4. Check for proper setting of overload relays.
After the fans have been started the direction of airflow should be checked. The flow
of air should be on towards the radiator fins.
Check operation of the fan circuit in auto and manual mode and also confirm the
changeover of standby fan in case of fan failure.
After Energizing the Transformer:-
1. If OLTC is provided, run the tap changer from Tap #1 up to the nominal tap.
2. Check the phase sequence and magnitude of the transformer secondary
voltage at the incoming line PTs.
3. If the transformer is an extension to an existing system, do the phasing out w.r.t
the existing PTs.
4. Check for any abnormal sound or vibration in the transformer.
5. Keep the transformer energized on no-load for 24 hours; take a reading of OTI,
WTI and current.

More Related Content

PPTX
Testing of transformer
PPS
Distribution Transformer testing, West Bengal, India
PDF
Testing of Transformer (AREVA)
PPTX
Transformer Diagnostics | Sweep Frequency Response Analysis
PPTX
Quality circle
PPT
Installation Operation & Maintenance of 33kV & 11kV Switchgear
PPT
Operation and maintenance of transformer
PDF
Transformer testing
Testing of transformer
Distribution Transformer testing, West Bengal, India
Testing of Transformer (AREVA)
Transformer Diagnostics | Sweep Frequency Response Analysis
Quality circle
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Operation and maintenance of transformer
Transformer testing

What's hot (20)

PPTX
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
PPTX
Ppt on protection of power transformers
PDF
Transformer testing on sight and off sight
PPT
Transformer
PPT
Testing and Condition Monitoring of Substation Equipments
PDF
Testing of transformer
PDF
Introduction to mv switchgear
PPTX
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
PDF
Substation Maintenance
PDF
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
PPTX
Stability test of transformer
PDF
Power system protection topic 1
PDF
Transformer & OLTC
PDF
TRANSFORMER VECTOR GROUP.pdf
PPTX
Transformer Repair Workshop Report [EEE]
PPT
Installation, Testing and Troubleshooting of Transformers
PPTX
Basics of overcurrent protection
PPTX
Transformer maintenance
PPT
Understanding transformer vector group
PDF
Testing of Transformers.
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Ppt on protection of power transformers
Transformer testing on sight and off sight
Transformer
Testing and Condition Monitoring of Substation Equipments
Testing of transformer
Introduction to mv switchgear
TESTING AND COMMISSIONING OF ELECTRICAL EQUIPMENTS. TESTING OF CURRENT TRANSF...
Substation Maintenance
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
Stability test of transformer
Power system protection topic 1
Transformer & OLTC
TRANSFORMER VECTOR GROUP.pdf
Transformer Repair Workshop Report [EEE]
Installation, Testing and Troubleshooting of Transformers
Basics of overcurrent protection
Transformer maintenance
Understanding transformer vector group
Testing of Transformers.
Ad

Similar to Power transformer testing and commissioning guidelines r (20)

PDF
Chapter 5 mukesh gurjar
PPT
Testing of transformers and reactors.ppt
PPT
TESTING,MAINTENANCE&PROTECTION.ppt
PPT
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
PPT
TESTING,MAINTENANCE&PROTECTION.ppt
PPT
Testing,maintenance&protection
PPTX
tcee-161003100321.pptx
PPTX
Maintenance schedule of Substation.
PDF
Substation commissioning1
PDF
Substation commissioning1
PDF
REPORT -VALLUR THERMAL POWER PLANT
PPTX
Unit 1-2-b
PPT
PROTECTIVE DEVICES & MAINTENANCE.ppt
PPT
transformers.ppt
PPTX
Testing, Maintenace and Protection of Transformer.pptx
PPTX
Presentation OutDoorSwithGear(AIS) .pptx
PPTX
Voltage Regulation
PPTX
220kv grid wapda town lahore
PPTX
220 KV Substation Operation & Maintenance
PPTX
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
Chapter 5 mukesh gurjar
Testing of transformers and reactors.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
Testing,maintenance&protection
tcee-161003100321.pptx
Maintenance schedule of Substation.
Substation commissioning1
Substation commissioning1
REPORT -VALLUR THERMAL POWER PLANT
Unit 1-2-b
PROTECTIVE DEVICES & MAINTENANCE.ppt
transformers.ppt
Testing, Maintenace and Protection of Transformer.pptx
Presentation OutDoorSwithGear(AIS) .pptx
Voltage Regulation
220kv grid wapda town lahore
220 KV Substation Operation & Maintenance
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
Ad

Recently uploaded (20)

PPTX
DRUGS USED FOR HORMONAL DISORDER, SUPPLIMENTATION, CONTRACEPTION, & MEDICAL T...
PDF
My India Quiz Book_20210205121199924.pdf
PDF
Skin Care and Cosmetic Ingredients Dictionary ( PDFDrive ).pdf
PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
MICROENCAPSULATION_NDDS_BPHARMACY__SEM VII_PCI Syllabus.pdf
PDF
Civil Department's presentation Your score increases as you pick a category
PDF
Farming Based Livelihood Systems English Notes
PDF
Myanmar Dental Journal, The Journal of the Myanmar Dental Association (2013).pdf
PPTX
MICROPARA INTRODUCTION XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
PDF
CRP102_SAGALASSOS_Final_Projects_2025.pdf
PDF
Journal of Dental Science - UDMY (2021).pdf
PPTX
Climate Change and Its Global Impact.pptx
PDF
Journal of Dental Science - UDMY (2022).pdf
PPTX
Education and Perspectives of Education.pptx
PDF
HVAC Specification 2024 according to central public works department
PDF
semiconductor packaging in vlsi design fab
PDF
LEARNERS WITH ADDITIONAL NEEDS ProfEd Topic
PPTX
INSTRUMENT AND INSTRUMENTATION PRESENTATION
DRUGS USED FOR HORMONAL DISORDER, SUPPLIMENTATION, CONTRACEPTION, & MEDICAL T...
My India Quiz Book_20210205121199924.pdf
Skin Care and Cosmetic Ingredients Dictionary ( PDFDrive ).pdf
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
FORM 1 BIOLOGY MIND MAPS and their schemes
MICROENCAPSULATION_NDDS_BPHARMACY__SEM VII_PCI Syllabus.pdf
Civil Department's presentation Your score increases as you pick a category
Farming Based Livelihood Systems English Notes
Myanmar Dental Journal, The Journal of the Myanmar Dental Association (2013).pdf
MICROPARA INTRODUCTION XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
CRP102_SAGALASSOS_Final_Projects_2025.pdf
Journal of Dental Science - UDMY (2021).pdf
Climate Change and Its Global Impact.pptx
Journal of Dental Science - UDMY (2022).pdf
Education and Perspectives of Education.pptx
HVAC Specification 2024 according to central public works department
semiconductor packaging in vlsi design fab
LEARNERS WITH ADDITIONAL NEEDS ProfEd Topic
INSTRUMENT AND INSTRUMENTATION PRESENTATION

Power transformer testing and commissioning guidelines r

  • 1. Power Transformer Testing and Commissioning GuidelinesR Sahoo Procedure of Power Transformer Testing and Commissioning In Transformer testing and commissioning, it can be classified into power and distribution transformers. It rating plate show nominal voltage, current of the primary and secondary voltage at several of the tap changer, connection symbols (vector group), % impedance weight of oil etc.
  • 2. Before starting transformer testing some of the per-commissioning checks a physical inspection of the transformer is to be carried out along with the general arrangement drawing. The parts mentioned on the drawing are to be checked for physical mounting. Check the following points before start the Transformer testing and commissioning:- 1. Oil leakage from bushing, valves, air release plugs, etc. 2. The direction of mounting of Buchholz relay, as per arrow on the relay; the arrow should point towards the conservator. 3. Oil level in condenser bushing. 4. Oil level of the main tank and OLTC (On load Tap Changer) tank should be up to the filling mark on MOG ( Minimum oil level gauge) 5. Earthed at two points.(Very important before starting the transformer testing) 6. Stoppers provided for locking of wheels. 7. Test taps on HV (High voltage) condenser bushing are fixed. 8. Valves on each radiator, both top and bottom should be open. 9. Valves on either side Buchholz relay should be open. 10. Arcing horns for the bushing, if provided to be set as per manufacturer’s instructions. If LAs are provided for the transformer, it is advisable to set the arcing horn distance a bit higher. 11. The tightness of conductor/cables on the transformer, HV side, LV side and neutral to be checked. 12. Check resistance and IR (Insulation resistance) values of NGR (Neutral Ground Resistor), if provided. 13. Ensure that oil is filled in OTI (Oil Temperature Indicator) and WTI (Winding temperature Indicator) pockets. 14. Check that colour of silica gel in breathers of main conservator and OLTC (On load Tap Changer) conservator is blue. 15. Oil in breather cups to be filled up to level indicated. 16. The diaphragm of explosion vent, if provided to be checked. In Transformer Testing following electrical checks are to be carried out and results recorded in the test reports. Prior to ratio check OLTC (On load Tap Changer) if provide is to be made functional OLTC can be of two types,
  • 3.  OLTC inbuilt in the main tank  OLTC separate chamber type i. For in-built OLTC (diverter switch) ensure that the lamp on the drive mechanism (DM) is same as the one in the display on the main tank. Then connection the main operating rod between the OLTC DM and diverter switch. Conduct mechanical operations on the OLTC taking it through all the taps. Ensure that the final end position (upper and lower limit) switches operate. ii. During the raise / lower operation note that direction of operating mechanism. Switch off the 3 PH-AC supply and check the operation of raise / lower contractor as per commands from DM. iii. With OLTC at some intermediate tap, switch on the 3 phase supply and give either raise / lower command to the OLTC. Check whether the mechanism is moving in the right direction for the command given. If the direction is reverse, switch off the AC and DC supply, verify that the phase sequence of the supply is correct, if not correct reverse the phase sequence at the motor terminal box. iv. Observe the operation of LOTC and check blocking of operation at the end positions. v. Verify that insertion of manual operating handle cuts off electrical operation. vi. Test the Automatic Voltage Regulating Relay (AVRR), if provided perform an automatic operation from the AVRR. Transformer Testing:- 1-Ratio test:- Apply 3 ph., 415V to high voltage winding of the transformer and, ensure the induced voltage on the low voltage terminals at all taps. Ensure variation in secondary volts as the taps are changed and compare the results with manufacturers test report or ratio mentioned on transformer nameplate. If delta tertiary stabilizing winding is provided (usually provided for Y Y transformers), open the delta shorting link and measure the voltage across the two terminals during ratio test it should be negligible. Refer above figure 2-Vector group test:
  • 4. Transformer-vector-group Make a test set up as per figure. Ensure that neutral of HV / LV are isolated from earth. Measure the voltage as per test format EFS / Transformer. 3. No load / Magnetizing current test:- Remove the shorting between primary & secondary and measure the currents in all the phases while maintaining the supply at primary. This test is done at a nominal tap and at the minimum and maximum taps. Expected currents – Ir / Iy / IB – 1:0.0:1 for star transformer — Ir / Iy / Ib 1: 1:1.3 – for delta transformer the currents should be in the order of mA. Refer the above figure. 4-Short circuit Current test: With the transformer at nominal tap, apply 3ph 415 V to the primary and adequate shorting on the secondary side ( depending on % impedance ) ensure bushing CT (Current Transformer )secondaries and WTI CT secondaries are through a) Measure currents in primary and secondary b) Check the current in CT secondary bushing CT,WTI CT, LDC CT . Repeat point (a) at maximum & minimum taps. 5-Core balance test:- Apply 415V between phase-phase (for delta transformer) and phase-neutral (for star transformer) on secondary side. Ensure that adequate safety precautions are taken on the primary side, as the high voltage will be induced. Measure the current and voltage for the following phases – For Delta Transformer Vry, Vyb, Vbr For star transformer -Vry, Vyb, Vbr, Vrn, Vyn, Vbn. 6-Insulation Test:- Up to 6.6KV an insulation tester of 2.5 KV may be used and beyond 6.6 KV, 5 KV voltage level may be used. Polarisation index records by IR value at 10/1 min ratio.
  • 5. Dielectric absorption 60 / 30 sec ratio Polarisation index 10/1 min ratio Interpretation ----- Less than 1 Unsatisfactory 1 to 1.25 1 to 2 Dubious 1.4 to 1.6 2 to 4 Good More than 1.6 4 Very good Note: IR values of delta tertiary stabilizing winding should also be taken with earth and with HV and LV winding. 7-Transformer Oil Testing:- Prior to the charging of transformer confirm the healthiness of the oil by testing the dielectric strength of oil. The oil is to be tested at 2.5 mm gap. 6 nos reading have to be taken and an average of these reading is the breakdown voltage of the oil. 8-Special Test:- Winding resistance should be carried out with 24 V battery. Rheostat with 10 A rating, along & digital multimeter, two pole switch Circuit as per figure connect the battery to one winding of the transformer and adjust the current to 2A. Measure the voltage at bushings. Winding resistance calculated should be compared with factory test results. Do not disconnect the wires without reducing the current avoid voltage spikes. A winding resistance test should be done after all the other tests have been completed. Note: –In transformer testing, if more than one run of cable per phase is used on the transformer LV side, it should be confirmed that there is no cross-over of phases between any run. Such a crossover would result in a dead short circuit on the LV side of the transformer. This can be verified during a no-load magnetizing current test the magnetizing current on the transformer HV side should be in the order of mA, with the Characteristics Equipment Voltage Test Method Frequency of Test Permissible Limits Remedial action Break Down voltage > 170 KV 70 - 170 KV < 70 KV IEC 156 Immediately prior charging > 50 KV > 40 KV > 30 KV Reconditioning
  • 6. all the LV side cables connected. Alternatively, thus can be confirmed during the transformer differential stability test. Prior to energizing ensure the following in transformer testing:- I. Cleaning of the transformer, especially the bushing. Ensure that all protections are operative. Buchholz relay may be tested by using the test screw, or by pumping in air with a bicycle pump, or by draining oil from the relay after closing both side valves. II. Air release from the transformer is to be done from air release plugs on the main tank, radiators, HV & LV bushing, Buchholz relay and OLTC prior to charging of transformer. Do not release air from the condenser bushing as they are hermetically sealed. III. Check operation of OTI / WTI, ensure oil in the temperature probe pots. IV. All interconnecting valves are the open position. V. Check IR value between each winding to earth, and between windings. Neutral earthing is to be disconnected for this purpose. VI. Check that HV and LV neutral earthing has been re-connected after megger test. VII. Earthing and delta shorting of tertiary stabilizing winding (if provided), to be checked. VIII. Proper setting of OTI & WTI to be done. IX. Perform trip test from all the transformer protections, including Buchholz relay, PRD, Oil surge relay, OTI, and WTI. X. All protection relays to be properly set. XI. Reset the maximum reading pointer (MRP) of OTI & WTI. XII. Ammeter selector switches should be selected to read some phase current. XIII. All MCBs, fuses, and switches in Marshalling boxes, Craps, isolator cubicles and breaker cubicles should be in the circuit. XIV. If the transformer is provided with an OLTC, energize it at Tap#1; if the transformer is provided with an off-circuit tap changer, energize it at the nominal tap. Testing of Fan control Cubicle:- Fan control cubicle houses the control and hardware for running of cooling fans with the fans running the transformer can be loaded to the specified rating on the nameplate (ONAF).
  • 7. The fans are started with the operation of WTI contact. Preferably S1 should be allocated to run the fans. Normally two banks of 4 fans are provided on the radiators. IN each bank one fan is spare and three fans will run continuously until that contact from WTI drops out. Prior to starting of fans following thing have to be checked:- 1. Measure IR value of the fan motors. 2. Check for free rotation of fan blades (rotor), ensure that they do not foul with the radiators. 3. Ensure proper earthing of motors, fixing of fan on the frames 4. Check for proper setting of overload relays. After the fans have been started the direction of airflow should be checked. The flow of air should be on towards the radiator fins. Check operation of the fan circuit in auto and manual mode and also confirm the changeover of standby fan in case of fan failure. After Energizing the Transformer:- 1. If OLTC is provided, run the tap changer from Tap #1 up to the nominal tap. 2. Check the phase sequence and magnitude of the transformer secondary voltage at the incoming line PTs. 3. If the transformer is an extension to an existing system, do the phasing out w.r.t the existing PTs. 4. Check for any abnormal sound or vibration in the transformer. 5. Keep the transformer energized on no-load for 24 hours; take a reading of OTI, WTI and current.