1. The document provides guidelines for testing and commissioning power transformers, including pre-commissioning checks, electrical checks, and tests to be performed. It details tests such as ratio testing, vector grouping, no-load current, short-circuit current, insulation testing, and checks of protections like the Buchholz relay.
2. Key electrical checks include verifying the on-load tap changer operation, measuring no-load currents, performing short-circuit tests, and measuring insulation resistance. The transformer, oil, and protections must pass all tests before energization.
3. After energization, the transformer is monitored for 24 hours to check for abnormalities before full commissioning.