Monte Carlo Cost Risk
Analysis Reporting
Intaver Institute Inc.
400, 7015, Macleod Trail,
Calgary, AB, Canada
Tel: +1 (403) 692-2252
www.intaver.com
Cost Summary
Cost Histogram and Cumulative Probability
Multiple cumulative
probability plots for
different baselines
Cost Chart
Project Control
Indicators
Baseline Cost
Actual Cost
Risked Cost
Cash Flow
Project Cash Flow Cost for Selected Period of Time
Low
Base
High
Sensitivity Analysis
Task Cost Ranking Risk Cost Ranking
Task: Total Cost vs Variable Cost
Task Total Cost Task Variable Cost
Task: Cost per Resource
View Work for Selected
Resource
Distribution for Work
• White Papers and Articles: http://intaver.com/technology/articles-and-white-
papers/
• Online Tutorials: http://intaver.com/RiskyProjectTutorial
• Risk and Decision Analysis Books: http://www.projectdecisions.org
Contact Details
Michael Trumper
Intaver Institute Inc.
mtrumper@intaver.com
403.692.2252
Additional Resources
Additional Resources
Project Think:
Why Good
Managers Make
Poor Project
Choices
Project Decisions: The
Art and Science
Introduction to Project
Risk Management and
Decision Analysis
Project Risk Analysis
Made Ridiculously
Simple

More Related Content

PPTX
Project Cost Analysis
PPTX
Monte Carlo and Schedule Risk Analysis
PPT
Risk Analysis of Linear Projects
PPT
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
PPTX
How Risk Events and Uncertainties can affect your project
PPTX
Oil and Gas Risk Analysis
PPT
Monte Carlo Schedule Risk Analysis
PPT
Risk Resilient Projects and Project Portfolios
Project Cost Analysis
Monte Carlo and Schedule Risk Analysis
Risk Analysis of Linear Projects
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
How Risk Events and Uncertainties can affect your project
Oil and Gas Risk Analysis
Monte Carlo Schedule Risk Analysis
Risk Resilient Projects and Project Portfolios

What's hot (20)

PPTX
Smart Monte Carlo: Tricks for schedule risk analysis.
PPTX
Project risk analysis in Construction Industry
PPT
Concepts and best practices for the risk register in primavera risk analysis
PPT
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
PPTX
Quantitative Project Risk Analysis
PDF
Introduction to primavera risk analysis ppt
PPT
RiskyProject for Oil and Gas Industry
PPT
Concepts and best practices for the risk register in primavera risk analysis
PPTX
Risk Management
PDF
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
PDF
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
DOC
Cis 500 assignment 6 vo ip part 4 (risk register)
PPS
Pert master risk analysis tool
PDF
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
PDF
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
PPTX
Using Risk Analysis and Simulation in Project Management
PPTX
How to Prioritize Risks with Qualitative and Quantitative Risk analysis
PPTX
‘Monte Carlo’ – so not to go bust!!! - Thursday 14 June 2018 - North West bra...
PDF
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
PPT
Learning_Unit_1
Smart Monte Carlo: Tricks for schedule risk analysis.
Project risk analysis in Construction Industry
Concepts and best practices for the risk register in primavera risk analysis
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Quantitative Project Risk Analysis
Introduction to primavera risk analysis ppt
RiskyProject for Oil and Gas Industry
Concepts and best practices for the risk register in primavera risk analysis
Risk Management
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
Cis 500 assignment 6 vo ip part 4 (risk register)
Pert master risk analysis tool
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
Using Risk Analysis and Simulation in Project Management
How to Prioritize Risks with Qualitative and Quantitative Risk analysis
‘Monte Carlo’ – so not to go bust!!! - Thursday 14 June 2018 - North West bra...
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
Learning_Unit_1
Ad

Similar to Project Cost Risk Analysis - Reporting (20)

PPTX
Building a Real-Time Security Application Using Log Data and Machine Learning...
PDF
Research-Based Innovation with Industry: Project Experience and Lessons Learned
PPTX
Decision framing in Project Management
PPT
Decision Framing in Project Decision-Making
PDF
AVEVA World Conference NA - Patrick Reilly, Vista Projects
PDF
Optimisation of Industrial Processes SimQRi - A Query-oriented Tool for the E...
PPTX
Envisioning the Next Generation of Analytics
PPTX
Risk Event Modeling and Event Chains
PDF
Neo4j in Oil & Gas: Industry Use Cases and Impac
PDF
Data Science Salon: Quit Wasting Time – Case Studies in Production Machine Le...
PDF
1440 track 2 boire_using our laptop
PPTX
Purdue Digital Manufacturing Enterprise Testbed to Launch Summer 2019
PPTX
COMIT community day summer 2018 - main slides
PDF
Global C4IR-1 Masterclass Adryan - Zuehlke Engineering 2017
PDF
Pydata Chicago - work hard once
DOC
Ankit.Srivastava
PDF
Advanced Project Data Analytics for Improved Project Delivery
PDF
Scalable and Cost-Effective Model-Based Software Verification and Testing
PDF
"Anti-patterns of Software Architecture — To defeat enemies, you need to know...
PPT
Solve It Labs Offshore Project Management
Building a Real-Time Security Application Using Log Data and Machine Learning...
Research-Based Innovation with Industry: Project Experience and Lessons Learned
Decision framing in Project Management
Decision Framing in Project Decision-Making
AVEVA World Conference NA - Patrick Reilly, Vista Projects
Optimisation of Industrial Processes SimQRi - A Query-oriented Tool for the E...
Envisioning the Next Generation of Analytics
Risk Event Modeling and Event Chains
Neo4j in Oil & Gas: Industry Use Cases and Impac
Data Science Salon: Quit Wasting Time – Case Studies in Production Machine Le...
1440 track 2 boire_using our laptop
Purdue Digital Manufacturing Enterprise Testbed to Launch Summer 2019
COMIT community day summer 2018 - main slides
Global C4IR-1 Masterclass Adryan - Zuehlke Engineering 2017
Pydata Chicago - work hard once
Ankit.Srivastava
Advanced Project Data Analytics for Improved Project Delivery
Scalable and Cost-Effective Model-Based Software Verification and Testing
"Anti-patterns of Software Architecture — To defeat enemies, you need to know...
Solve It Labs Offshore Project Management
Ad

More from Intaver Insititute (15)

PPTX
RiskyProject Software Version 7.2
PPT
Risk Analysis of Linear Projects
PPTX
RiskyProject 7
PPTX
RiskyProject Software
PPTX
RiskyProject Enterprise
PPTX
Quantiative Risk Analysis for the Aerospace Industry
PPTX
Estimates in Project Management
PPTX
Project Management: Adaptive management
PDF
Risky projectpresentation rus
PDF
Risky project Cloud presentation rus
PDF
Risky projectenterpriseriskmanagement
PDF
Risky Project Lite vs. Professional
PDF
Enterprise Risk Management and Analysis with RiskyProject
PPT
Risky projectcloudpresentation
PPT
Adaptive Project Management
RiskyProject Software Version 7.2
Risk Analysis of Linear Projects
RiskyProject 7
RiskyProject Software
RiskyProject Enterprise
Quantiative Risk Analysis for the Aerospace Industry
Estimates in Project Management
Project Management: Adaptive management
Risky projectpresentation rus
Risky project Cloud presentation rus
Risky projectenterpriseriskmanagement
Risky Project Lite vs. Professional
Enterprise Risk Management and Analysis with RiskyProject
Risky projectcloudpresentation
Adaptive Project Management

Recently uploaded (20)

PPTX
ai agent creaction with langgraph_presentation_
PDF
ahaaaa shbzjs yaiw jsvssv bdjsjss shsusus s
PPTX
Statisticsccdxghbbnhhbvvvvvvvvvv. Dxcvvvhhbdzvbsdvvbbvv ccc
PDF
Grey Minimalist Professional Project Presentation (1).pdf
PDF
technical specifications solar ear 2025.
PPTX
cp-and-safeguarding-training-2018-2019-mmfv2-230818062456-767bc1a7.pptx
PPTX
Tapan_20220802057_Researchinternship_final_stage.pptx
PDF
Tetra Pak Index 2023 - The future of health and nutrition - Full report.pdf
PPTX
recommendation Project PPT with details attached
PPTX
MBA JAPAN: 2025 the University of Waseda
PPT
Image processing and pattern recognition 2.ppt
PPTX
Machine Learning and working of machine Learning
PPTX
machinelearningoverview-250809184828-927201d2.pptx
PPT
statistics analysis - topic 3 - describing data visually
PPTX
The Data Security Envisioning Workshop provides a summary of an organization...
PPTX
ch20 Database System Architecture by Rizvee
PPTX
AI_Agriculture_Presentation_Enhanced.pptx
PPTX
Introduction to Fundamentals of Data Security
PPTX
1 hour to get there before the game is done so you don’t need a car seat for ...
PDF
A biomechanical Functional analysis of the masitary muscles in man
ai agent creaction with langgraph_presentation_
ahaaaa shbzjs yaiw jsvssv bdjsjss shsusus s
Statisticsccdxghbbnhhbvvvvvvvvvv. Dxcvvvhhbdzvbsdvvbbvv ccc
Grey Minimalist Professional Project Presentation (1).pdf
technical specifications solar ear 2025.
cp-and-safeguarding-training-2018-2019-mmfv2-230818062456-767bc1a7.pptx
Tapan_20220802057_Researchinternship_final_stage.pptx
Tetra Pak Index 2023 - The future of health and nutrition - Full report.pdf
recommendation Project PPT with details attached
MBA JAPAN: 2025 the University of Waseda
Image processing and pattern recognition 2.ppt
Machine Learning and working of machine Learning
machinelearningoverview-250809184828-927201d2.pptx
statistics analysis - topic 3 - describing data visually
The Data Security Envisioning Workshop provides a summary of an organization...
ch20 Database System Architecture by Rizvee
AI_Agriculture_Presentation_Enhanced.pptx
Introduction to Fundamentals of Data Security
1 hour to get there before the game is done so you don’t need a car seat for ...
A biomechanical Functional analysis of the masitary muscles in man

Project Cost Risk Analysis - Reporting

  • 1. Monte Carlo Cost Risk Analysis Reporting Intaver Institute Inc. 400, 7015, Macleod Trail, Calgary, AB, Canada Tel: +1 (403) 692-2252 www.intaver.com
  • 2. Cost Summary Cost Histogram and Cumulative Probability Multiple cumulative probability plots for different baselines
  • 3. Cost Chart Project Control Indicators Baseline Cost Actual Cost Risked Cost
  • 4. Cash Flow Project Cash Flow Cost for Selected Period of Time Low Base High
  • 5. Sensitivity Analysis Task Cost Ranking Risk Cost Ranking
  • 6. Task: Total Cost vs Variable Cost Task Total Cost Task Variable Cost
  • 7. Task: Cost per Resource View Work for Selected Resource Distribution for Work
  • 8. • White Papers and Articles: http://intaver.com/technology/articles-and-white- papers/ • Online Tutorials: http://intaver.com/RiskyProjectTutorial • Risk and Decision Analysis Books: http://www.projectdecisions.org Contact Details Michael Trumper Intaver Institute Inc. [email protected] 403.692.2252 Additional Resources
  • 9. Additional Resources Project Think: Why Good Managers Make Poor Project Choices Project Decisions: The Art and Science Introduction to Project Risk Management and Decision Analysis Project Risk Analysis Made Ridiculously Simple

Editor's Notes

  • #2: Welcome to Intaver Institutes video : Monte Carlo Cost Risk Analysis Reporting. We are going to be taking a look at the various analysis and reporting views that are available to assess project cost risk.
  • #3: After running a Monte Carlo simulation, two of the most popular reports are histograms and cumulative probability. In this particular example we have a combined histogram and cumulative probability chart. On the left Y axis is the probability. We can see that the most likely value occurs 9% of the time. On the right Y axis is the cumulative probability values with markers placed at 10 percentile, Mean, and 90 percentile. Cumulative probability is useful for setting cost contingency, which would be the difference between the Deterministic value (the red line) and a cumulative probability with a higher confidence level such as P80. In addition, we can plot multiple cost scenarios representing different risk management strategies as cumulative probability plots. In this particular view we are looking a a pre and post mitigated baselines.
  • #4: The Cost Chart provides a view of the forecasted cost of a project over time for deterministic and risked costs. As we can see, because the project has a high probability of running longer it will cost more. If there are actual costs, they are will be plotted on the chart and project cost control indicators are displayed at the bottom right.
  • #5: The Cash Flow chart shows probabilistic cash flow over set periodicity (Months, Bi-Monthly, Quarterly or Annually). In this particular view, we can see that for the period of February, there is a high probability that costs will be well above the current forecast due to risk. In addition, we can see that because of delays, the project should expect to experience two additional months of costs. Because February shows a large jump in expected cash flow, we can take a look a detailed view of the probabilistic cash flow for that particular period. The large spike on the right is due to a probability of a critical risk occuring.
  • #6: Sensitivity analysis or Tornado charts provides insight into which tasks or risks have the most potential to drive costs in the project. On the left we have a list of tasks ranked by how much their risks and uncertainties impact the cost of the project. On the right, we have a similar ranking of risks. It is extremely likely that the highest ranked risks are assigned to the highest ranked activities. To minimize potential cost overruns, we need to focus our risk management efforts on these tasks and risks.
  • #7: In the previous views we have been looking at project level analysis, however, it is possible to drill down to the activity level to view the cost analysis. On the left, the chart shows us probabilistic total task costs. Of note the histogram is bimodal, which shows two distinct distributions. The one on the left is due to uncertainty or natural variance and the second to the right is due to a serious risk event occurring. The chart on the right shows similar results but for resource costs. In this chart the second distribution is even more distinct so that we know that the risk is tightly correlated with the resources allocated to this activity.
  • #8: If we would like to further investigate the source, we can look at the specific variable work (and therefore costs) for each resource allocated to a specific tasks. This particular view which is very tightly correlated with the previous results would indicate that in order to control costs, we would need to focus on this particular resource as being the root cause of the predicted cost overruns in this activity.
  • #9: Thank you for watching our video on Monte Carlo Cost Risk Analysis Reporting. Please visit our site at intaver.com to learn more about risk analysis and our upcoming videos and webinars.
  • #10: If you are interested in finding out more about Decision Analysis and Risk Management a list of our publications and a variety of resources can be found at our website Project Decisions.org