Analysis of
Proposed
Development #1
Presented by BinaMok Project Management
and Cost Consultant Team
The Team:
Director: Mok Po Yi
Members:
Chin Weng Lok
Darren Loong Chi Yoong
Lee Jian Ru
Pang Khai Shuen
Sherlyn Ang Tse Yun
Project Description
❖ Freehold land
❖ 10 acres 1 rood 10 pole = 449,213 ft2
❖ Bought 3 years ago
❖ RM15/ft2
❖ Bank loan: RM6,500,000.00
❖ Development Area = 449,213 ft2 x 60%
= 269,528 ft2
Strength & Weaknesses
Strengths
1. Strategic location
a. In close proximity to the city centre, shopping complex and
universities.
2. High population density
a. According to world population review (2018), Subang Jaya is
home to as many as 708,296 people.
Strength & Weaknesses
3. High effective demand for houses and shop/ office lots
a. High student population as there are a lot of universities nearby.
b. Food and beverage businesses would opt for the shop lots in the
proposed site as it would be able to cater to the student.
Strength & Weaknesses
Weaknesses:
1. Inadequate Ingress/Egress
a. Only one ingress from LDP highway, one egress to Bandar Sunway
b. Two other high density developments that share the same main road
2. Limited Parking Facilities
a. Risk of excessive roadside parking unless development is gated & guarded
Benchmark Project
360 Acres
Residential -
300 Acres
Commercial -
60 Acres
● Total Gross Development Value =
Approx. RM 1 billion
Benchmark Project (Cont’d)
Price of double-storey
terraced house
RM 350,000
Size per unit 20ft x 70 ft
Number of double-storey
terraced houses
600 units
Total area of double-storey
terraced houses
1400 ft2 x 600 units
= 840,000 ft2
Unit price per square feet RM 250.00
GDV RM250.00 x 840,000
= RM 210,000,000.00
Concept Design
- 30% low cost house
- 15% shop office
- 55% terrace house
Quality Management
Pre-construction stage
Identification of project goal :
● Best value for money
● Expected gross profit - 30% from GDV
● Expected completion - end of December of 2014
● Expected budget - RM38 million
Procurement method: Traditional Procurement Method
Pre-construction stage
Design review
● Aim:
○ To keep design changes to a
minimum
○ To achieve high quality design
● Done by project team
● Using a design review checklist
Pre-construction stage
● Tender document and specification
Quality Assessment System in
Construction (QLASSIC)
Must score above 70%
British Standard (BS) Standardise the technical specification
Building Information Modelling (BIM) ● Visualise building design
● Detect clash
● Enable contractor to understand the complexity of the project
Value Engineering Change Proposal
(VECP)
● Allow contractor to have alternative proposal
● Reduce construction cost
● Improve quality
● Grant incentive to contractors
Pre-construction stage
Pre-qualification
Criteria for selecting potential contractor:
● Financial capacity
● Organisational capacity
● Performance capacity
● Resource availability
● Occupational health and safety management
● Quality management
● Relevant experience
Construction Stage
● A Project Quality Plan (PQP) to ensure a smooth execution of works
during construction stage is essential.
● Our PQP was prepared to satisfy the requirements in ISO 9001:2015
- Quality Management System Requirements.
Construction Stage
Quality Objectives:
✓ Proper planning of construction activities within a realistic timeframe and
control delays within 10%.
✓ Continuous review and control of costs to ensure completion of works
are within +/- 5% of budget.
✓ Constantly meeting with health and safety requirements in accordance to
the Occupational Health and Safety Assessment Series (OHSAS) 18000.
✓ Achieving minimum 80% client satisfaction in all construction activities to
maintain healthy relationship.
Construction Stage
Quality Policies:
1. Establish clearly defined responsibility and authority for compliance.
2. Translate client’s goals and objectives from the Contract Documents to top quality completed
facility while meeting the applicable standards.
3. Ensure the highest level of quality by maintaining supervised controls and written instructions
governing Quality Control procedures and practices.
4. Complete and maintain accurate records of inspections and tests.
5. Clearly specify procedures to ensure that quality requirements are communicated to all levels of
the field organization.
6. Identify and take corrective measures against non-conformance of quality related aspects and
ensuring all corrective measures are properly implemented and documented.
Construction Stage
PROJECT MANAGER
ARCHITECT QC COORDINATOR
HEALTH AND SAFETY
MANAGER
STRUCTURAL
INSPECTOR
M&E
INSPECTOR
ARCHITECTURAL
INSPECTOR
Construction Stage
Inspection and Test Plans (ITP):
● To identify, plan and provide a record of project specific inspections
and tests from project commencement to completion.
● Responsibility of the QC Coordinator and Consultant Inspectors.
● 4 Types of ITP:
1. Field inspection
2. Approved material inspection
3. Material test inspection
4. Re-work procedure
Post Construction Stage
Operation and Maintenance
-Maintenance is the process to be done to prevent the deterioration in the building and to
repair the damages towards the building.
-The life cycle cost of project should be taken into consideration during feasibility study,
such as operation and maintenance cost.
-It could create a great impact on the overall life cycle cost of the construction project during
post construction stage.
-Once the project is completed and the building is ready to function and occupied, it
becomes part of the operating system.
-The operation and maintenance (O&M) includes repair and replacement
(R&R), usually associated with the quality of the constructed project.
Post Construction Stage
Operation and Maintenance
Documents required to operate and maintain the completed facility, which are
submitted by the contractor during the testing, commissioning and handover phase of
the construction project:
I. As-built Drawings
II. Operation and Maintenance Manuals
III. Operating Procedures
IV. Source Information for Availability of Spare Parts of the Installed Works
Post Construction Stage
Operation and Maintenance Program
-The operation and maintenance personnel should be engaged and involved in
determining maintenance requirements which to be included into the design.
-The following procedures must be followed to create an effective and efficient
Operation and Maintenance Program:
● Ensure that as-built drawings for all systems are up to date and readily
available
● Ensure that operational procedures and manuals for the installed
equipments are readily available
● A master schedule for operation and preventive/predictive maintenance
must be prepared
Post Construction Stage
Operation and Maintenance Program
● Follow the manufacturer’s recommendations for maintenance of
equipment and systems
● Implement preventive maintenance programs complete with
maintenance schedules and records of all maintenance performed
for the equipment and systems installed in the facility or project
● Ensure the maintenance personnels are well trained and have full
knowledge of the equipment and systems installed which he is
responsible to operate and maintain
● Implement a monitoring program that provides function of
tracking documenting of equipment performance to identify and
diagnose potential problems
Risk Management
Introduction:
4 Stages of Risk Management:
1. Identification
2. Analysing
3. Responding
4. Monitoring
Identification of Risks
External Risks:
1. Political – Government Regulations, GST, Change of Government
2. Economic – Exchange Rate, GDP Growth
3. Social – Demographics, Cultural Trends, Population Size
4. Technological – IBS Scoring System 50%
5. Environmental – Pollution, Traffic planning
6. Legal – Local Authority
Identification of Risks
Internal Risks:
1. Pre-construction
a. Technical – Poor Buildability
b. Financial – Funding
2. Construction
a. Safety – Safety Officer
b. Material – Material Testing
c. Personnel – Unregistered Foreign Workers
3. Post-construction
a. Operation & Maintenance – After Sales Service
Assessment/ Analysis of Risk
Qualitative
- Delphi Technique
(brainstorming)
- SWIFT
- Bow-tie analysis
- Probability Consequence
Quantitative
- Sensitivity Analysis
- Expected Monetary Value
(EMV)
- Monte Carlo Simulation
- Decision Tree analysis
Recommendation of Risk Assessment
- We have chosen to use probability/consequence risk matrix.
- This is because the risk matrix showcases the probability as well as the
impact of a risk. This will enable us to shift our focus on the main driver of
the risk and mitigate the risk.
Response/Controlling Risks
❖ Avoidance/Prevention/Elimination
Eliminate project’s risk is to change the scope of project or, worst scenario, cancel it
❖ Reduction/Mitigation
Hire experts to manage high-risk activities in construction projects
❖ Transfer/Insure
Purchasing an insurance policy, warranties, performance bonds, guarantees or by outsourcing the work
❖ Retention/Tolerate
Changing of law which contemplated in the Uniform Building By-Laws (UBBL)
Monitoring Risks
- Continuous operative control of the effectiveness of the risk control
measures
- Helps to discover new risks, keep track of identified risks and eliminate
past risks from the risk assessment and project
- Monitoring of the risk is to supervise the status of the risks and take
corrective actions if needed
- Risk reassessment, status meetings and risk register updates must be
carried out continuously in order to improve the project work as the pros
and cons will be established
THANK YOUPlease give us an A thank you!

More Related Content

PDF
Value Management Assignment (Slides)
Pang Khai Shuen
 
PPTX
Value management presentation slides
Doreen Yeo
 
PDF
Vm report
Jessyca Than
 
DOCX
Vm assignment (5)
Yong Sy
 
PPTX
MEASUREMENT 4 SLIDES
wendyteosy
 
PPTX
Value management presentation
Koh Chiun Liang
 
PDF
ECA Workshop - Brief
Kai Yun Pang
 
PDF
SITE ANALYSIS REPORT
ong93
 
Value Management Assignment (Slides)
Pang Khai Shuen
 
Value management presentation slides
Doreen Yeo
 
Vm report
Jessyca Than
 
Vm assignment (5)
Yong Sy
 
MEASUREMENT 4 SLIDES
wendyteosy
 
Value management presentation
Koh Chiun Liang
 
ECA Workshop - Brief
Kai Yun Pang
 
SITE ANALYSIS REPORT
ong93
 

What's hot (20)

PDF
Value Management Group Assignment
Arissa Loh
 
PDF
Value Management Assignment (Report)
Pang Khai Shuen
 
PPTX
Cost management in Buildings
JIT KUMAR GUPTA
 
DOCX
Green building index
hott1771
 
PDF
Assignment - Preliminary Cost Appraisal
Kai Yun Pang
 
PDF
Intelligent building envelopes
Rajat Nainwal
 
PDF
Assignment 2 - Resort Proposal at Pulau Langkawi
Kai Yun Pang
 
PDF
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
Atiqah Ghazali
 
PDF
Project management assignment 1
Weng Chuan
 
PPTX
COST EFFECIENT CHAP 1 ppt.pptx
abedamtie
 
PDF
PM Final Assignment Report
Melvin Lim
 
PPTX
New materials used in building industry
Tanzil Faraz
 
PDF
SUSTAINABLE, ENERGY EFFICIENT BUILDING MATERIALS AND TECHNOLOGIES
Samanth kumar
 
PDF
Pinnacle sunway services
Celine Tan
 
PPT
History of arch...
joannaPG
 
PDF
Architecture Design Project Report
douglasloon
 
PPTX
Green Building Index
BC Chew
 
PDF
Assignment - Single Storey Show House (Presentation)
Kai Yun Pang
 
PPTX
Alejanro Aravena
Ariel Garcia
 
PPT
GreenStudio - Chapter 4 2 7 Shading Devices
Galala University
 
Value Management Group Assignment
Arissa Loh
 
Value Management Assignment (Report)
Pang Khai Shuen
 
Cost management in Buildings
JIT KUMAR GUPTA
 
Green building index
hott1771
 
Assignment - Preliminary Cost Appraisal
Kai Yun Pang
 
Intelligent building envelopes
Rajat Nainwal
 
Assignment 2 - Resort Proposal at Pulau Langkawi
Kai Yun Pang
 
NATIONAL MOSQUE - CULTURE AND HISTORY 2 REPORT
Atiqah Ghazali
 
Project management assignment 1
Weng Chuan
 
COST EFFECIENT CHAP 1 ppt.pptx
abedamtie
 
PM Final Assignment Report
Melvin Lim
 
New materials used in building industry
Tanzil Faraz
 
SUSTAINABLE, ENERGY EFFICIENT BUILDING MATERIALS AND TECHNOLOGIES
Samanth kumar
 
Pinnacle sunway services
Celine Tan
 
History of arch...
joannaPG
 
Architecture Design Project Report
douglasloon
 
Green Building Index
BC Chew
 
Assignment - Single Storey Show House (Presentation)
Kai Yun Pang
 
Alejanro Aravena
Ariel Garcia
 
GreenStudio - Chapter 4 2 7 Shading Devices
Galala University
 
Ad

Similar to Project Management and Development Economics Project (Slides) (20)

PDF
سمینار عزت الله درباره مدیریت کنترول و کاهش دوباره کاری در پروژه های ساختمانی...
engzwaak1996
 
PPTX
KENA PRE.pptx
dagneabera13
 
DOCX
Vinay CV
vinay m s
 
PDF
AYESA Presentation - GC East Coast Railway_12th January.pdf
rinkumandaljis
 
PPTX
Project mangment
Hemant Srivastava
 
PDF
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Amir Mohammed
 
PDF
Warehouse Operations Redefining methodology
AkhilRanjanDubey
 
DOCX
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Devendra Kachhi
 
PPT
Construction process
Mazen Al-Qadi
 
DOC
Turnover Engineer
Manish Kumar.G
 
DOCX
Amir QC
aamir waheed
 
PDF
C3 Projects mining capability statement
Stephen Smith
 
PDF
Balancing Flexibility and Cost Control in Construction Projects
Brown Smith Wallace
 
PDF
JLL_Techno Commercial Proposal_04112023.pdf
Nishit SIDDHPURA
 
PPTX
CHAPTER ONE construction manegmentt.pptx
mijade7306
 
DOC
Sachin be mech_8_yrs_exp
sachin tagalpallewar
 
PDF
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
ahsansaeed78
 
PDF
The Comprehensive Guide to Construction Project Management Process
Geomatrix
 
DOC
Alif_Resume
ALIF RASHEED
 
سمینار عزت الله درباره مدیریت کنترول و کاهش دوباره کاری در پروژه های ساختمانی...
engzwaak1996
 
KENA PRE.pptx
dagneabera13
 
Vinay CV
vinay m s
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
rinkumandaljis
 
Project mangment
Hemant Srivastava
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Amir Mohammed
 
Warehouse Operations Redefining methodology
AkhilRanjanDubey
 
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Devendra Kachhi
 
Construction process
Mazen Al-Qadi
 
Turnover Engineer
Manish Kumar.G
 
Amir QC
aamir waheed
 
C3 Projects mining capability statement
Stephen Smith
 
Balancing Flexibility and Cost Control in Construction Projects
Brown Smith Wallace
 
JLL_Techno Commercial Proposal_04112023.pdf
Nishit SIDDHPURA
 
CHAPTER ONE construction manegmentt.pptx
mijade7306
 
Sachin be mech_8_yrs_exp
sachin tagalpallewar
 
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
ahsansaeed78
 
The Comprehensive Guide to Construction Project Management Process
Geomatrix
 
Alif_Resume
ALIF RASHEED
 
Ad

More from Pang Khai Shuen (20)

PDF
Project Management and Development Economics Project (DE)
Pang Khai Shuen
 
PDF
Project Management and Development Economics Project (PM)
Pang Khai Shuen
 
PDF
Construction Law Assignment BQS Taylor's University
Pang Khai Shuen
 
PDF
Construction Law - Remedies for Breach of Contract
Pang Khai Shuen
 
PPTX
BE Slides updated
Pang Khai Shuen
 
PPTX
BE Presentation Slides
Pang Khai Shuen
 
PDF
BE COST APPRAISAL
Pang Khai Shuen
 
PDF
BE benchmark project cost allocation
Pang Khai Shuen
 
PDF
BE Compiled
Pang Khai Shuen
 
PDF
BE Assignment brief aug 17
Pang Khai Shuen
 
PDF
CSI Personal reflective journal
Pang Khai Shuen
 
PDF
pp2 Final account-1
Pang Khai Shuen
 
PDF
Pp2 coursework 2 BRIEF 201708
Pang Khai Shuen
 
PDF
PP2 COMPILCATION
Pang Khai Shuen
 
PDF
M4 presentation slides
Pang Khai Shuen
 
PPTX
PP1 - Presentation Slides
Pang Khai Shuen
 
PDF
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
PDF
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
PPTX
Estimating Presentation Slides - To Client
Pang Khai Shuen
 
PDF
Elemental Cost Analysis
Pang Khai Shuen
 
Project Management and Development Economics Project (DE)
Pang Khai Shuen
 
Project Management and Development Economics Project (PM)
Pang Khai Shuen
 
Construction Law Assignment BQS Taylor's University
Pang Khai Shuen
 
Construction Law - Remedies for Breach of Contract
Pang Khai Shuen
 
BE Slides updated
Pang Khai Shuen
 
BE Presentation Slides
Pang Khai Shuen
 
BE COST APPRAISAL
Pang Khai Shuen
 
BE benchmark project cost allocation
Pang Khai Shuen
 
BE Compiled
Pang Khai Shuen
 
BE Assignment brief aug 17
Pang Khai Shuen
 
CSI Personal reflective journal
Pang Khai Shuen
 
pp2 Final account-1
Pang Khai Shuen
 
Pp2 coursework 2 BRIEF 201708
Pang Khai Shuen
 
PP2 COMPILCATION
Pang Khai Shuen
 
M4 presentation slides
Pang Khai Shuen
 
PP1 - Presentation Slides
Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
Estimating Presentation Slides - To Client
Pang Khai Shuen
 
Elemental Cost Analysis
Pang Khai Shuen
 

Recently uploaded (20)

PPTX
How to Close Subscription in Odoo 18 - Odoo Slides
Celine George
 
DOCX
Unit 5: Speech-language and swallowing disorders
JELLA VISHNU DURGA PRASAD
 
PDF
Antianginal agents, Definition, Classification, MOA.pdf
Prerana Jadhav
 
PDF
UTS Health Student Promotional Representative_Position Description.pdf
Faculty of Health, University of Technology Sydney
 
PDF
The-Invisible-Living-World-Beyond-Our-Naked-Eye chapter 2.pdf/8th science cur...
Sandeep Swamy
 
PPTX
Five Point Someone – Chetan Bhagat | Book Summary & Analysis by Bhupesh Kushwaha
Bhupesh Kushwaha
 
PPTX
Python-Application-in-Drug-Design by R D Jawarkar.pptx
Rahul Jawarkar
 
PDF
Health-The-Ultimate-Treasure (1).pdf/8th class science curiosity /samyans edu...
Sandeep Swamy
 
PDF
What is CFA?? Complete Guide to the Chartered Financial Analyst Program
sp4989653
 
PDF
RA 12028_ARAL_Orientation_Day-2-Sessions_v2.pdf
Seven De Los Reyes
 
PPTX
Artificial-Intelligence-in-Drug-Discovery by R D Jawarkar.pptx
Rahul Jawarkar
 
PDF
Review of Related Literature & Studies.pdf
Thelma Villaflores
 
PDF
1.Natural-Resources-and-Their-Use.ppt pdf /8th class social science Exploring...
Sandeep Swamy
 
PDF
2.Reshaping-Indias-Political-Map.ppt/pdf/8th class social science Exploring S...
Sandeep Swamy
 
PPTX
PPTs-The Rise of Empiresghhhhhhhh (1).pptx
academysrusti114
 
PPTX
Introduction to pediatric nursing in 5th Sem..pptx
AneetaSharma15
 
PPTX
How to Manage Leads in Odoo 18 CRM - Odoo Slides
Celine George
 
PDF
Study Material and notes for Women Empowerment
ComputerScienceSACWC
 
PPTX
Dakar Framework Education For All- 2000(Act)
santoshmohalik1
 
PPTX
Information Texts_Infographic on Forgetting Curve.pptx
Tata Sevilla
 
How to Close Subscription in Odoo 18 - Odoo Slides
Celine George
 
Unit 5: Speech-language and swallowing disorders
JELLA VISHNU DURGA PRASAD
 
Antianginal agents, Definition, Classification, MOA.pdf
Prerana Jadhav
 
UTS Health Student Promotional Representative_Position Description.pdf
Faculty of Health, University of Technology Sydney
 
The-Invisible-Living-World-Beyond-Our-Naked-Eye chapter 2.pdf/8th science cur...
Sandeep Swamy
 
Five Point Someone – Chetan Bhagat | Book Summary & Analysis by Bhupesh Kushwaha
Bhupesh Kushwaha
 
Python-Application-in-Drug-Design by R D Jawarkar.pptx
Rahul Jawarkar
 
Health-The-Ultimate-Treasure (1).pdf/8th class science curiosity /samyans edu...
Sandeep Swamy
 
What is CFA?? Complete Guide to the Chartered Financial Analyst Program
sp4989653
 
RA 12028_ARAL_Orientation_Day-2-Sessions_v2.pdf
Seven De Los Reyes
 
Artificial-Intelligence-in-Drug-Discovery by R D Jawarkar.pptx
Rahul Jawarkar
 
Review of Related Literature & Studies.pdf
Thelma Villaflores
 
1.Natural-Resources-and-Their-Use.ppt pdf /8th class social science Exploring...
Sandeep Swamy
 
2.Reshaping-Indias-Political-Map.ppt/pdf/8th class social science Exploring S...
Sandeep Swamy
 
PPTs-The Rise of Empiresghhhhhhhh (1).pptx
academysrusti114
 
Introduction to pediatric nursing in 5th Sem..pptx
AneetaSharma15
 
How to Manage Leads in Odoo 18 CRM - Odoo Slides
Celine George
 
Study Material and notes for Women Empowerment
ComputerScienceSACWC
 
Dakar Framework Education For All- 2000(Act)
santoshmohalik1
 
Information Texts_Infographic on Forgetting Curve.pptx
Tata Sevilla
 

Project Management and Development Economics Project (Slides)

  • 1. Analysis of Proposed Development #1 Presented by BinaMok Project Management and Cost Consultant Team
  • 2. The Team: Director: Mok Po Yi Members: Chin Weng Lok Darren Loong Chi Yoong Lee Jian Ru Pang Khai Shuen Sherlyn Ang Tse Yun
  • 3. Project Description ❖ Freehold land ❖ 10 acres 1 rood 10 pole = 449,213 ft2 ❖ Bought 3 years ago ❖ RM15/ft2 ❖ Bank loan: RM6,500,000.00 ❖ Development Area = 449,213 ft2 x 60% = 269,528 ft2
  • 4. Strength & Weaknesses Strengths 1. Strategic location a. In close proximity to the city centre, shopping complex and universities. 2. High population density a. According to world population review (2018), Subang Jaya is home to as many as 708,296 people.
  • 5. Strength & Weaknesses 3. High effective demand for houses and shop/ office lots a. High student population as there are a lot of universities nearby. b. Food and beverage businesses would opt for the shop lots in the proposed site as it would be able to cater to the student.
  • 6. Strength & Weaknesses Weaknesses: 1. Inadequate Ingress/Egress a. Only one ingress from LDP highway, one egress to Bandar Sunway b. Two other high density developments that share the same main road 2. Limited Parking Facilities a. Risk of excessive roadside parking unless development is gated & guarded
  • 7. Benchmark Project 360 Acres Residential - 300 Acres Commercial - 60 Acres ● Total Gross Development Value = Approx. RM 1 billion
  • 8. Benchmark Project (Cont’d) Price of double-storey terraced house RM 350,000 Size per unit 20ft x 70 ft Number of double-storey terraced houses 600 units Total area of double-storey terraced houses 1400 ft2 x 600 units = 840,000 ft2 Unit price per square feet RM 250.00 GDV RM250.00 x 840,000 = RM 210,000,000.00
  • 9. Concept Design - 30% low cost house - 15% shop office - 55% terrace house
  • 11. Pre-construction stage Identification of project goal : ● Best value for money ● Expected gross profit - 30% from GDV ● Expected completion - end of December of 2014 ● Expected budget - RM38 million Procurement method: Traditional Procurement Method
  • 12. Pre-construction stage Design review ● Aim: ○ To keep design changes to a minimum ○ To achieve high quality design ● Done by project team ● Using a design review checklist
  • 13. Pre-construction stage ● Tender document and specification Quality Assessment System in Construction (QLASSIC) Must score above 70% British Standard (BS) Standardise the technical specification Building Information Modelling (BIM) ● Visualise building design ● Detect clash ● Enable contractor to understand the complexity of the project Value Engineering Change Proposal (VECP) ● Allow contractor to have alternative proposal ● Reduce construction cost ● Improve quality ● Grant incentive to contractors
  • 14. Pre-construction stage Pre-qualification Criteria for selecting potential contractor: ● Financial capacity ● Organisational capacity ● Performance capacity ● Resource availability ● Occupational health and safety management ● Quality management ● Relevant experience
  • 15. Construction Stage ● A Project Quality Plan (PQP) to ensure a smooth execution of works during construction stage is essential. ● Our PQP was prepared to satisfy the requirements in ISO 9001:2015 - Quality Management System Requirements.
  • 16. Construction Stage Quality Objectives: ✓ Proper planning of construction activities within a realistic timeframe and control delays within 10%. ✓ Continuous review and control of costs to ensure completion of works are within +/- 5% of budget. ✓ Constantly meeting with health and safety requirements in accordance to the Occupational Health and Safety Assessment Series (OHSAS) 18000. ✓ Achieving minimum 80% client satisfaction in all construction activities to maintain healthy relationship.
  • 17. Construction Stage Quality Policies: 1. Establish clearly defined responsibility and authority for compliance. 2. Translate client’s goals and objectives from the Contract Documents to top quality completed facility while meeting the applicable standards. 3. Ensure the highest level of quality by maintaining supervised controls and written instructions governing Quality Control procedures and practices. 4. Complete and maintain accurate records of inspections and tests. 5. Clearly specify procedures to ensure that quality requirements are communicated to all levels of the field organization. 6. Identify and take corrective measures against non-conformance of quality related aspects and ensuring all corrective measures are properly implemented and documented.
  • 18. Construction Stage PROJECT MANAGER ARCHITECT QC COORDINATOR HEALTH AND SAFETY MANAGER STRUCTURAL INSPECTOR M&E INSPECTOR ARCHITECTURAL INSPECTOR
  • 19. Construction Stage Inspection and Test Plans (ITP): ● To identify, plan and provide a record of project specific inspections and tests from project commencement to completion. ● Responsibility of the QC Coordinator and Consultant Inspectors. ● 4 Types of ITP: 1. Field inspection 2. Approved material inspection 3. Material test inspection 4. Re-work procedure
  • 20. Post Construction Stage Operation and Maintenance -Maintenance is the process to be done to prevent the deterioration in the building and to repair the damages towards the building. -The life cycle cost of project should be taken into consideration during feasibility study, such as operation and maintenance cost. -It could create a great impact on the overall life cycle cost of the construction project during post construction stage. -Once the project is completed and the building is ready to function and occupied, it becomes part of the operating system. -The operation and maintenance (O&M) includes repair and replacement (R&R), usually associated with the quality of the constructed project.
  • 21. Post Construction Stage Operation and Maintenance Documents required to operate and maintain the completed facility, which are submitted by the contractor during the testing, commissioning and handover phase of the construction project: I. As-built Drawings II. Operation and Maintenance Manuals III. Operating Procedures IV. Source Information for Availability of Spare Parts of the Installed Works
  • 22. Post Construction Stage Operation and Maintenance Program -The operation and maintenance personnel should be engaged and involved in determining maintenance requirements which to be included into the design. -The following procedures must be followed to create an effective and efficient Operation and Maintenance Program: ● Ensure that as-built drawings for all systems are up to date and readily available ● Ensure that operational procedures and manuals for the installed equipments are readily available ● A master schedule for operation and preventive/predictive maintenance must be prepared
  • 23. Post Construction Stage Operation and Maintenance Program ● Follow the manufacturer’s recommendations for maintenance of equipment and systems ● Implement preventive maintenance programs complete with maintenance schedules and records of all maintenance performed for the equipment and systems installed in the facility or project ● Ensure the maintenance personnels are well trained and have full knowledge of the equipment and systems installed which he is responsible to operate and maintain ● Implement a monitoring program that provides function of tracking documenting of equipment performance to identify and diagnose potential problems
  • 25. Introduction: 4 Stages of Risk Management: 1. Identification 2. Analysing 3. Responding 4. Monitoring
  • 26. Identification of Risks External Risks: 1. Political – Government Regulations, GST, Change of Government 2. Economic – Exchange Rate, GDP Growth 3. Social – Demographics, Cultural Trends, Population Size 4. Technological – IBS Scoring System 50% 5. Environmental – Pollution, Traffic planning 6. Legal – Local Authority
  • 27. Identification of Risks Internal Risks: 1. Pre-construction a. Technical – Poor Buildability b. Financial – Funding 2. Construction a. Safety – Safety Officer b. Material – Material Testing c. Personnel – Unregistered Foreign Workers 3. Post-construction a. Operation & Maintenance – After Sales Service
  • 28. Assessment/ Analysis of Risk Qualitative - Delphi Technique (brainstorming) - SWIFT - Bow-tie analysis - Probability Consequence Quantitative - Sensitivity Analysis - Expected Monetary Value (EMV) - Monte Carlo Simulation - Decision Tree analysis
  • 29. Recommendation of Risk Assessment - We have chosen to use probability/consequence risk matrix. - This is because the risk matrix showcases the probability as well as the impact of a risk. This will enable us to shift our focus on the main driver of the risk and mitigate the risk.
  • 30. Response/Controlling Risks ❖ Avoidance/Prevention/Elimination Eliminate project’s risk is to change the scope of project or, worst scenario, cancel it ❖ Reduction/Mitigation Hire experts to manage high-risk activities in construction projects ❖ Transfer/Insure Purchasing an insurance policy, warranties, performance bonds, guarantees or by outsourcing the work ❖ Retention/Tolerate Changing of law which contemplated in the Uniform Building By-Laws (UBBL)
  • 31. Monitoring Risks - Continuous operative control of the effectiveness of the risk control measures - Helps to discover new risks, keep track of identified risks and eliminate past risks from the risk assessment and project - Monitoring of the risk is to supervise the status of the risks and take corrective actions if needed - Risk reassessment, status meetings and risk register updates must be carried out continuously in order to improve the project work as the pros and cons will be established
  • 32. THANK YOUPlease give us an A thank you!