SlideShare a Scribd company logo
Project Risk
Management
+
Risk analysis is a systematic process to estimate the
level of risk for identified and approved risks. This
involves estimating the probability of occurrence
and consequence of occurrence and converting the
results to a corresponding risk.
The approach used depends upon the data available
and requirements levied on the project level.
Risk analyses are often based on detailed information
that may come from a variety of techniques, including
but not limited to:
Analysis of plans and related documents
Experience and interviewing
Relevant lessons-learned studies
Results from tests
…cont’d
There are two methods of risk analysis
Qualitative approach and
Quantitative approaches
Qualitative approach use the probability of occurrence and
consequence of occurrence scales together with a risk mapping
matrix to convert the values to risk levels.
When a qualitative risk analysis is performed, risk ratings can
be used as an indication of the potential importance of risks on
the program and often expressed as low, medium, and high (or
possibly low, medium low, medium, medium high, and high).
Quantitative approaches use the technique such as expected
value ,decision tree analysis, payoff matrices, and modeling
and simulation.
Project problems can be reduced as much
as 90% by using risk analysis
Positives:
More info available during planning
Improved probability of success/optimum
project
Negatives:
Project cut due to risk level
Risks have been thoroughly examined and included in project
plans, resulting in risk reduction. Information about possible risks
is available throughout the project, resulting in a better decision-
making process
Project objectives might be affected by certain risks, allowing the
objectives to be improved
Many of the project weaknesses have been identified in advance
and are incorporated into the project plan.
Decrease the number of changes made to the project plan during
project execution, resulting in higher chances of project success
Risk Management Process
Risk
management
plan and control
Document risk
management
plan
Define
objectives
Identify risk
Quantify
risk
Develop
response
Benefits of Risk Assessment
 Protects project investments
 Proactive management – early warning
 Achieve project objectives
 High Risk: Substantial impact on cost, technical
performance, or schedule. Substantial action required to
alleviate issue. High-priority management attention is
required.
 Medium Risk: Some impact on cost, technical
performance, or schedule. Special action may be required
to alleviate issue. Additional management attention may be
needed.
 Low Risk: Minimal impact on cost, technical
performance, or schedule. Normal management oversight
is sufficient.
Quantitative risk analysis outputs are
1. Prioritized risk lists,
2. Probabilistic cost estimates at completion per project phase
and probabilistic schedule estimates for key milestones to
help the project manager allocate reserve accordingly,
3. Probabilistic estimates of meeting desired technical
performance parameters and validating technical
performance of key components
4. Estimates of the probability of meeting cost, technical
performance, and schedule objectives (e.g., determining the
probability of achieving the planned estimate at completion)
 Updated Risk Register
 Probabilistic analysis for project success (time and cost)
 Updated priority of risk events
 Trends in risk analysis
….cont’d
Interviewing
Decision Tree
Analysis
Monte Carlo
Simulation
The Monte Carlo process is an attempt to create a series of
probability distributions for potential risks, randomly sample the
distributions, and transform the numbers into useful information
that reflects quantification of the associated cost, technical
performance or schedule risks.
Project Risk Management
 Monte Carlo simulations used to
Estimate risk in the design of service centers;
Measure time to complete key milestones in a project;
Estimate the cost of developing, fabricating, & maintaining
an item.
Uses of Monte Carlo simulation
 A common method/tool to determine whether a risk
is considered low, moderate, or high by combining
the two dimensions of a risk:
 its probability of occurrence, and
 its impact on objectives if it occurs.
2x2 Impact/Probability Matrix
Green: Low Risk (Passive Acceptance – workarounds)
Yellow: Moderate Risk (Active Acceptance –
contingency)
Red: High Risk (Risk Response Planning)
Impact
Probability
HighLow
Low High
Likelihood Class
Likelihood of Occurrence
(events/year)
Not Likely (NL)
<0.01% chance of
occurrence
Low (L)
0.01 - 0.1% chance of
occurrence
Moderate (M)
0.1 - 1% chance of
occurrence
High (H)
1 - 10% chance of
occurrence
Expected (E)
>10% chance of
occurrence
Consequen
ce Health and Safety
Extreme
Fatality or multiple fatalities
expected
High
Severe injury or disability likely;
or some potential for fatality
Moderate
Lost time or injury likely; or
some potential for serious
injuries; or small risk of
fatality
Low
First aid required; or small risk
of serious injury
Negligible No concern
 The process of numerically analyzing the
effect of identified risks on the project’s
objectives In particular, the project schedule
and the project costs.
 Quantify possible outcomes for the project
 Assess probability of achieving specific project
objectives
 Identify risks requiring most attention
 Identify realistic and achievable cost, schedule,
or scope targets, given project risks
 Determine best management decision when
conditions or outcomes are uncertain
 Risks during the Project/idea Initiation phase:
–Unavailable subject matter experts
–Poor definition of problem or project
–No feasibility study
–No or unclear objectives
Taking….cont’d
 Risks during the Project Planning phase:
No risk management plan
Spotty planning
Underdeveloped requirements and
specifications
Unclear statement of work
No management or stakeholder support
Poor role definition
Inexperienced team
Lack of skills
 Risks during the Project Execution phase
 Changes in schedule
 No control systems in place
 Unskilled labour
 Material availability or poor quality material
 Unreliable suppliers
 Unexpected price increase (not budget for it)
 Strikes
 Weather
 Regulatory requirements
….cont’d
Risks during the Project Close-out /
termination phase:
Unacceptable to customer
Poor quality product/project
Budget problems
Penalties to be paid for exceeding the time
parameter of the project
The basics of risk management
Identify the risk
Analyse the probability the risk will occur and the
potential impact of the risk
Determine the overall severity of the risk
Determine which risks are the most important for
further action
Document a response plan for the risk
– Accept the risk
– Avoid the risk
– Monitor the risk
– Transfer the risk
Project standards for risk management
Risk Management Plan
Procurement
Contingency Reserves
Alternative Strategies
Insurance
Management Reserves
◦ Created for unpredictable risks
Contingency Reserves
◦ Created for predictable risks
 Approaches used for developing contingency allowances:
Budgeting a standard allowance for contingencies and applying it to
all projects.
Identifying a percentage of additional cost or time needed, based on
past experience.
Pinpointing the most likely risks for a project, assessing the
probability that they will occur, identifying the possible
consequences, and then allotting contingencies based on these
results.
◦ Exploit
◦ Share
◦ Enhance
◦ Acceptance
)
◦ Avoid
◦ Transfer
◦ Mitigate
◦ Acceptance
Questions the project team should
ask when determining a risk:-
Why should the risk be accepted?
What are the potential benefits?
Are the potential benefits worth the
risk?
What are the potential losses?
What is the possibility of failure?

More Related Content

PPT
10. Project Quality Management
BhuWan Khadka
 
PPSX
Project management
Satish Yadavalli
 
PPT
Risk Management in Project Management
Narudom Roongsiriwong, CISSP
 
PPTX
Project Risk Management
Martin Sillaots
 
PPTX
Project risk management
Aswin prakash i , Xantus Technologies
 
PPT
Project risk management
Dewang Agrawal
 
PPTX
Project Cost Management - PMBOK6
Agus Suhanto
 
10. Project Quality Management
BhuWan Khadka
 
Project management
Satish Yadavalli
 
Risk Management in Project Management
Narudom Roongsiriwong, CISSP
 
Project Risk Management
Martin Sillaots
 
Project risk management
Aswin prakash i , Xantus Technologies
 
Project risk management
Dewang Agrawal
 
Project Cost Management - PMBOK6
Agus Suhanto
 

What's hot (20)

PPTX
Project Risk Management
Kaustubh Gupta
 
PPTX
Project scope management 1
Mohammad Ashraf Khan, PMP
 
PPTX
PROJECT SCHEDULE
Ajeesh Mk
 
PPTX
Risk management
Abhi Kalyan
 
PPT
Introduction-to-project-management
Savaş Şakar
 
ODP
Project life cycle
Jennifer Banzon
 
PPTX
Work breakdown structure ppt
nazi2020
 
PPT
Chapter 1 An Overview Of Project Management
Mahesh Bendigeri
 
PPTX
Project Risk Management
Oleksa Stelmakh
 
PPT
09. Project Cost Management
BhuWan Khadka
 
PPTX
project management concepts
Aswin prakash i , Xantus Technologies
 
PPT
Project organisation structure
sachin kumar sharma
 
PPTX
Project management and project life cycle
Institute of Rural Management
 
PDF
Step by step guide on project risk management
PMC Mentor
 
PPTX
Project management PPT
Raj Sampat
 
PPTX
Project risk management
Yogender Singh Rana
 
PPTX
Presentation on Project Risk Management
Md. Masudur Rahman, PMP
 
PPT
Project planning and control
Venugopal Venkatachalapathy
 
PPTX
Different project management methodologies
Aswin prakash i , Xantus Technologies
 
PPTX
Project Risk Management
cgautam
 
Project Risk Management
Kaustubh Gupta
 
Project scope management 1
Mohammad Ashraf Khan, PMP
 
PROJECT SCHEDULE
Ajeesh Mk
 
Risk management
Abhi Kalyan
 
Introduction-to-project-management
Savaş Şakar
 
Project life cycle
Jennifer Banzon
 
Work breakdown structure ppt
nazi2020
 
Chapter 1 An Overview Of Project Management
Mahesh Bendigeri
 
Project Risk Management
Oleksa Stelmakh
 
09. Project Cost Management
BhuWan Khadka
 
project management concepts
Aswin prakash i , Xantus Technologies
 
Project organisation structure
sachin kumar sharma
 
Project management and project life cycle
Institute of Rural Management
 
Step by step guide on project risk management
PMC Mentor
 
Project management PPT
Raj Sampat
 
Project risk management
Yogender Singh Rana
 
Presentation on Project Risk Management
Md. Masudur Rahman, PMP
 
Project planning and control
Venugopal Venkatachalapathy
 
Different project management methodologies
Aswin prakash i , Xantus Technologies
 
Project Risk Management
cgautam
 
Ad

Viewers also liked (20)

PDF
Risk Analysis
Nishodh Saxena Ph. D.
 
PPTX
Project risk analysis
Akanksha Sinha
 
PPTX
Basic Risk Identification Techniques
Ricardo Viana Vargas
 
PPT
Risk identification
murukkada
 
PDF
Project quality management.ppt msm
Development Associates Link International (DALI) Inc
 
PPT
Spm unit 1
sweetyammu
 
PPTX
Powerpoint Risk Assessment
Steve Bishop
 
PPT
Bond
Girish Soni
 
PPT
Project appraisal and Analysis
Suhail Hussain
 
PPT
Risk analysis and management
gnitu
 
PPT
Risk analysis
saurabhshertukde
 
PPT
Web Security
Bharath Manoharan
 
PDF
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Norrazman Zaiha Zainol
 
PPTX
Risk assessment presentation
mmagario
 
PDF
OHSAS Hazard identification & Risk assessment
TechnoSysCon
 
PDF
Risk assessment principles and guidelines
Haris Tahir
 
PPT
Spm unit 5
sweetyammu
 
PPT
Spm unit2
sweetyammu
 
PDF
Project Management:Life Cycle & Phases.
Ashutosh Mishra
 
PPTX
Project life cycle
Maryam Juma
 
Risk Analysis
Nishodh Saxena Ph. D.
 
Project risk analysis
Akanksha Sinha
 
Basic Risk Identification Techniques
Ricardo Viana Vargas
 
Risk identification
murukkada
 
Project quality management.ppt msm
Development Associates Link International (DALI) Inc
 
Spm unit 1
sweetyammu
 
Powerpoint Risk Assessment
Steve Bishop
 
Project appraisal and Analysis
Suhail Hussain
 
Risk analysis and management
gnitu
 
Risk analysis
saurabhshertukde
 
Web Security
Bharath Manoharan
 
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Norrazman Zaiha Zainol
 
Risk assessment presentation
mmagario
 
OHSAS Hazard identification & Risk assessment
TechnoSysCon
 
Risk assessment principles and guidelines
Haris Tahir
 
Spm unit 5
sweetyammu
 
Spm unit2
sweetyammu
 
Project Management:Life Cycle & Phases.
Ashutosh Mishra
 
Project life cycle
Maryam Juma
 
Ad

Similar to Project Risk Management (20)

PPTX
Risk management
Sushrut Gautam
 
PPT
Chap007
maisuradi
 
PDF
Risk management overview
Hossam Maghrabi
 
PDF
Beyond PMP: Risk Management
abhinayverma
 
PPTX
Risk Management
Hinal Lunagariya
 
PPTX
Project Risk Management
Hayat Denzi
 
PPTX
Project Risk Management (10)
Serdar Temiz
 
PPTX
Lesson III.pptx -Project Risk Management
KassanKaselema
 
PPTX
PMP Training - 11 project risk management
ejlp12
 
PPT
Risk Management
poornimaholla
 
PPT
Project Management Unit 3 Lecture 3.3 (1).ppt
RohitGuleria14
 
PDF
Control only.pdf
NmnKmr2
 
PPTX
Risk based thinking
Ranjeet Singh
 
PPT
Risk Analysis In IT Projects - TNS09
Thomas Danford
 
PPTX
Session 18 4th edition PMP
محمد عصمت عبد الرازق
 
PPTX
Project mngmnt risks3.2
Ananya Indrajith
 
PDF
riskmanagement-170228074706trrrrrrrr.pdf
AteedOlaiya
 
PPT
05-risk_assesment.ppt
KareemRasmy1
 
PPTX
Risk management
Harold Malamion
 
PPT
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 
Risk management
Sushrut Gautam
 
Chap007
maisuradi
 
Risk management overview
Hossam Maghrabi
 
Beyond PMP: Risk Management
abhinayverma
 
Risk Management
Hinal Lunagariya
 
Project Risk Management
Hayat Denzi
 
Project Risk Management (10)
Serdar Temiz
 
Lesson III.pptx -Project Risk Management
KassanKaselema
 
PMP Training - 11 project risk management
ejlp12
 
Risk Management
poornimaholla
 
Project Management Unit 3 Lecture 3.3 (1).ppt
RohitGuleria14
 
Control only.pdf
NmnKmr2
 
Risk based thinking
Ranjeet Singh
 
Risk Analysis In IT Projects - TNS09
Thomas Danford
 
Session 18 4th edition PMP
محمد عصمت عبد الرازق
 
Project mngmnt risks3.2
Ananya Indrajith
 
riskmanagement-170228074706trrrrrrrr.pdf
AteedOlaiya
 
05-risk_assesment.ppt
KareemRasmy1
 
Risk management
Harold Malamion
 
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 

More from Markos Mulat G (10)

PPTX
ERP and CRM Integration for Quality Service Delivery
Markos Mulat G
 
PDF
A Review of FDRE Civil Society Proclamation No.621/2009
Markos Mulat G
 
PDF
Traffic and Transportation Problems in Ethiopia: Manifestations and the Way out
Markos Mulat G
 
PPTX
Continuous Assessment
Markos Mulat G
 
PPTX
Human Resource Information System Applications
Markos Mulat G
 
PDF
Human Resource Information System [HRIS] MBA defence
Markos Mulat G
 
PDF
Performance Appraisal
Markos Mulat G
 
DOCX
HR Audit with checklist
Markos Mulat G
 
PDF
HR Audit in EIC
Markos Mulat G
 
PDF
Pricing in Practice
Markos Mulat G
 
ERP and CRM Integration for Quality Service Delivery
Markos Mulat G
 
A Review of FDRE Civil Society Proclamation No.621/2009
Markos Mulat G
 
Traffic and Transportation Problems in Ethiopia: Manifestations and the Way out
Markos Mulat G
 
Continuous Assessment
Markos Mulat G
 
Human Resource Information System Applications
Markos Mulat G
 
Human Resource Information System [HRIS] MBA defence
Markos Mulat G
 
Performance Appraisal
Markos Mulat G
 
HR Audit with checklist
Markos Mulat G
 
HR Audit in EIC
Markos Mulat G
 
Pricing in Practice
Markos Mulat G
 

Recently uploaded (20)

PPTX
Certificate of Incorporation, Prospectus, Certificate of Commencement of Busi...
Keerthana Chinnathambi
 
PDF
A Complete Guide to Data Migration Services for Modern Businesses
Aurnex
 
DOCX
India's Emerging Global Leadership in Sustainable Energy Production The Rise ...
Insolation Energy
 
PDF
NewBase 26 July 2025 Energy News issue - 1806 by Khaled Al Awadi_compressed.pdf
Khaled Al Awadi
 
PDF
Keppel Ltd. 1H 2025 Results Presentation Slides
KeppelCorporation
 
PPTX
Memorandum and articles of association explained.pptx
Keerthana Chinnathambi
 
DOCX
unit 1 BC.docx - INTRODUCTION TO BUSINESS COMMUICATION
MANJU N
 
PPTX
The Ultimate Guide to Customer Journey Mapping
RUPAL AGARWAL
 
PPTX
Business Plan Presentation: Vision, Strategy, Services, Growth Goals & Future...
neelsoni2108
 
PPTX
Appreciations - July 25.pptxsdsdsddddddsssss
anushavnayak
 
PDF
High Capacity Core IC Pneumatic Spec-Sheet
Forklift Trucks in Minnesota
 
PDF
12 Oil and Gas Companies in India Driving the Energy Sector.pdf
Essar Group
 
PDF
New Royals Distribution Plan Presentation
ksherwin
 
PPTX
Appreciations - July 25.pptxffsdjjjjjjjjjjjj
anushavnayak
 
PDF
NewBase 24 July 2025 Energy News issue - 1805 by Khaled Al Awadi._compressed...
Khaled Al Awadi
 
PDF
Using Innovative Solar Manufacturing to Drive India's Renewable Energy Revolu...
Insolation Energy
 
PDF
Equinox Gold - Corporate Presentation.pdf
Equinox Gold Corp.
 
PPTX
E-Way Bill under GST – Transport & Logistics.pptx
Keerthana Chinnathambi
 
PPTX
Appreciations - July 25.pptxdddddddddddss
anushavnayak
 
PDF
2025 07 29 The Future, Backwards Agile 2025.pdf
Daniel Walsh
 
Certificate of Incorporation, Prospectus, Certificate of Commencement of Busi...
Keerthana Chinnathambi
 
A Complete Guide to Data Migration Services for Modern Businesses
Aurnex
 
India's Emerging Global Leadership in Sustainable Energy Production The Rise ...
Insolation Energy
 
NewBase 26 July 2025 Energy News issue - 1806 by Khaled Al Awadi_compressed.pdf
Khaled Al Awadi
 
Keppel Ltd. 1H 2025 Results Presentation Slides
KeppelCorporation
 
Memorandum and articles of association explained.pptx
Keerthana Chinnathambi
 
unit 1 BC.docx - INTRODUCTION TO BUSINESS COMMUICATION
MANJU N
 
The Ultimate Guide to Customer Journey Mapping
RUPAL AGARWAL
 
Business Plan Presentation: Vision, Strategy, Services, Growth Goals & Future...
neelsoni2108
 
Appreciations - July 25.pptxsdsdsddddddsssss
anushavnayak
 
High Capacity Core IC Pneumatic Spec-Sheet
Forklift Trucks in Minnesota
 
12 Oil and Gas Companies in India Driving the Energy Sector.pdf
Essar Group
 
New Royals Distribution Plan Presentation
ksherwin
 
Appreciations - July 25.pptxffsdjjjjjjjjjjjj
anushavnayak
 
NewBase 24 July 2025 Energy News issue - 1805 by Khaled Al Awadi._compressed...
Khaled Al Awadi
 
Using Innovative Solar Manufacturing to Drive India's Renewable Energy Revolu...
Insolation Energy
 
Equinox Gold - Corporate Presentation.pdf
Equinox Gold Corp.
 
E-Way Bill under GST – Transport & Logistics.pptx
Keerthana Chinnathambi
 
Appreciations - July 25.pptxdddddddddddss
anushavnayak
 
2025 07 29 The Future, Backwards Agile 2025.pdf
Daniel Walsh
 

Project Risk Management

  • 2. + Risk analysis is a systematic process to estimate the level of risk for identified and approved risks. This involves estimating the probability of occurrence and consequence of occurrence and converting the results to a corresponding risk. The approach used depends upon the data available and requirements levied on the project level.
  • 3. Risk analyses are often based on detailed information that may come from a variety of techniques, including but not limited to: Analysis of plans and related documents Experience and interviewing Relevant lessons-learned studies Results from tests
  • 4. …cont’d There are two methods of risk analysis Qualitative approach and Quantitative approaches Qualitative approach use the probability of occurrence and consequence of occurrence scales together with a risk mapping matrix to convert the values to risk levels. When a qualitative risk analysis is performed, risk ratings can be used as an indication of the potential importance of risks on the program and often expressed as low, medium, and high (or possibly low, medium low, medium, medium high, and high). Quantitative approaches use the technique such as expected value ,decision tree analysis, payoff matrices, and modeling and simulation.
  • 5. Project problems can be reduced as much as 90% by using risk analysis Positives: More info available during planning Improved probability of success/optimum project Negatives: Project cut due to risk level
  • 6. Risks have been thoroughly examined and included in project plans, resulting in risk reduction. Information about possible risks is available throughout the project, resulting in a better decision- making process Project objectives might be affected by certain risks, allowing the objectives to be improved Many of the project weaknesses have been identified in advance and are incorporated into the project plan. Decrease the number of changes made to the project plan during project execution, resulting in higher chances of project success
  • 7. Risk Management Process Risk management plan and control Document risk management plan Define objectives Identify risk Quantify risk Develop response
  • 8. Benefits of Risk Assessment  Protects project investments  Proactive management – early warning  Achieve project objectives
  • 9.  High Risk: Substantial impact on cost, technical performance, or schedule. Substantial action required to alleviate issue. High-priority management attention is required.  Medium Risk: Some impact on cost, technical performance, or schedule. Special action may be required to alleviate issue. Additional management attention may be needed.  Low Risk: Minimal impact on cost, technical performance, or schedule. Normal management oversight is sufficient.
  • 10. Quantitative risk analysis outputs are 1. Prioritized risk lists, 2. Probabilistic cost estimates at completion per project phase and probabilistic schedule estimates for key milestones to help the project manager allocate reserve accordingly, 3. Probabilistic estimates of meeting desired technical performance parameters and validating technical performance of key components
  • 11. 4. Estimates of the probability of meeting cost, technical performance, and schedule objectives (e.g., determining the probability of achieving the planned estimate at completion)  Updated Risk Register  Probabilistic analysis for project success (time and cost)  Updated priority of risk events  Trends in risk analysis ….cont’d
  • 13. The Monte Carlo process is an attempt to create a series of probability distributions for potential risks, randomly sample the distributions, and transform the numbers into useful information that reflects quantification of the associated cost, technical performance or schedule risks.
  • 15.  Monte Carlo simulations used to Estimate risk in the design of service centers; Measure time to complete key milestones in a project; Estimate the cost of developing, fabricating, & maintaining an item. Uses of Monte Carlo simulation
  • 16.  A common method/tool to determine whether a risk is considered low, moderate, or high by combining the two dimensions of a risk:  its probability of occurrence, and  its impact on objectives if it occurs.
  • 17. 2x2 Impact/Probability Matrix Green: Low Risk (Passive Acceptance – workarounds) Yellow: Moderate Risk (Active Acceptance – contingency) Red: High Risk (Risk Response Planning) Impact Probability HighLow Low High
  • 18. Likelihood Class Likelihood of Occurrence (events/year) Not Likely (NL) <0.01% chance of occurrence Low (L) 0.01 - 0.1% chance of occurrence Moderate (M) 0.1 - 1% chance of occurrence High (H) 1 - 10% chance of occurrence Expected (E) >10% chance of occurrence Consequen ce Health and Safety Extreme Fatality or multiple fatalities expected High Severe injury or disability likely; or some potential for fatality Moderate Lost time or injury likely; or some potential for serious injuries; or small risk of fatality Low First aid required; or small risk of serious injury Negligible No concern
  • 19.  The process of numerically analyzing the effect of identified risks on the project’s objectives In particular, the project schedule and the project costs.
  • 20.  Quantify possible outcomes for the project  Assess probability of achieving specific project objectives  Identify risks requiring most attention  Identify realistic and achievable cost, schedule, or scope targets, given project risks  Determine best management decision when conditions or outcomes are uncertain
  • 21.  Risks during the Project/idea Initiation phase: –Unavailable subject matter experts –Poor definition of problem or project –No feasibility study –No or unclear objectives
  • 22. Taking….cont’d  Risks during the Project Planning phase: No risk management plan Spotty planning Underdeveloped requirements and specifications Unclear statement of work No management or stakeholder support Poor role definition Inexperienced team Lack of skills
  • 23.  Risks during the Project Execution phase  Changes in schedule  No control systems in place  Unskilled labour  Material availability or poor quality material  Unreliable suppliers  Unexpected price increase (not budget for it)  Strikes  Weather  Regulatory requirements
  • 24. ….cont’d Risks during the Project Close-out / termination phase: Unacceptable to customer Poor quality product/project Budget problems Penalties to be paid for exceeding the time parameter of the project
  • 25. The basics of risk management Identify the risk Analyse the probability the risk will occur and the potential impact of the risk Determine the overall severity of the risk Determine which risks are the most important for further action Document a response plan for the risk – Accept the risk – Avoid the risk – Monitor the risk – Transfer the risk
  • 26. Project standards for risk management Risk Management Plan Procurement Contingency Reserves Alternative Strategies Insurance
  • 27. Management Reserves ◦ Created for unpredictable risks Contingency Reserves ◦ Created for predictable risks  Approaches used for developing contingency allowances: Budgeting a standard allowance for contingencies and applying it to all projects. Identifying a percentage of additional cost or time needed, based on past experience. Pinpointing the most likely risks for a project, assessing the probability that they will occur, identifying the possible consequences, and then allotting contingencies based on these results.
  • 28. ◦ Exploit ◦ Share ◦ Enhance ◦ Acceptance ) ◦ Avoid ◦ Transfer ◦ Mitigate ◦ Acceptance
  • 29. Questions the project team should ask when determining a risk:- Why should the risk be accepted? What are the potential benefits? Are the potential benefits worth the risk? What are the potential losses? What is the possibility of failure?