SlideShare a Scribd company logo
Topic 9:
Project Scheduling
Topic 9 : Project Scheduling
 Project scheduling is a mechanism to communicate what tasks need to get done
and which organizational resources will be allocated to complete those tasks in
what timeframe.
 The following are the steps needed to schedule a project:
o Define Activities : Create Work Breakdown Structure (WBS) and a
deliverables diagram and organize them by mapping out the tasks .
o Do Estimates : Determine the time and effort it will take to complete them.
o Determine Dependencies : Place a bit of slack in your schedule to
accommodate these related tasks.
o Assign Resources : Finalize the planned schedule by deciding what
resources you are going to need to get those tasks done on time.
 Estimate Activity Duration Inputs
o This process has several tools and techniques ;-
-Expert Judgement, -Analogous Estimating, -Parametric Estimating
-Three-Point Estimating, -Group decision-making techniques, -Reserve Analysis
 3 Point Estimating
o Three-point estimating uses three estimates that when averaged come up with
final estimate.
• Most likely estimate – assumes there are no disaster and activity can be
completed as planned
• Optimistic estimate – fastest time frame in which your resource can
complete the activity
• Pessimistic – Assumes the worst happens and it takes much longer than
planned to get the activity completed
o Formula to calculate the expected duration : E = (O + P + M) / 3
o E=Expected, O = Optimistic, M = Most Likely
o The formula for standard deviation which helps to determine the confidence level
as below : E : (Pessimistic – Optimistic) / 6
 Expert Judgement - The staff members who will perform activities will most
accurately estimate them
 Analogous Estimating ( also called as top-down estimating, an expert
judgement) - Actual duration of a similar activity completed on previous project
will be used to determine the duration of current activity.
 Bottom Up Estimating – Is the most accurate approach to estimate cost and
duration. Setting the estimates of the amount of work, duration and cost at the
task level lets you combine them into estimates of higher-level deliverables and
the project as a whole
 Parametric Estimating - Quantitatively based estimating method that multiplies
the quantity of work by the rate or uses an algorithm in conjunction with historical
data to determine the cost, budget or duration estimates.
 Group decision-making techniques (brainstorming and the Delphi or nominal
group techniques)
o Brainstorming is an old-age technique where all participants have an
opportunity to speak up.
o Delphi technique is similar to brainstorming in that you involve subject matter
experts in determining estimates.
 Reserve Analysis
o Contingency reserve - a portion of time added to the schedule to account
for risk
o Management reserve - used for unknown events that have not been
previously identified
Resource Optimization Techniques
 Resource Leveling - also called as resource-based method is used when the
resources are overallocated and only available at certain times or when they are
assigned to more than one activity at a time. The purpose to use this technique is
to balance out the resource assignments to get tasks completed without
overloading the individual.
 Resource Smoothing - Resource smoothing accommodates resource availability
by modifying activities within their float times without changing the critical path or
project end date. More tasks are given to team members who are under allocated
.
 Reverse Resource - This technique requires the resources to be scheduled in
reverse order in order to assign this key resource at the correct time.
Modeling techniques
 Include the use of what-if scenario analysis and simulation
o What-If scenario : uses different sets of activity assumptions to produce
multiple project durations
o Simulation use a range of probable activity durations for each activity, and
those ranges are then used to calculate a range of probable duration results
for the project itself.
o Monte Carlo is a simulation technique that runs the possible activity durations
and schedule projections many many times to come up with the schedule
projections and their probability, critical path duration estimates and float
time.
Schedule Compression
 Mathematical analysis that’s used to shorten the project schedule duration without
changing the project scope in order to accomplish all activities sooner than
estimated.
o Crashing – accomplished by adding resources to the critical path.Crashing
the schedule can lead to increased risk and increased cost.
o Fast tracking – Performing 2 tasks or project phase in parallel that were
previously scheduled to start sequentially. It increases the project risk and
might cause the project team to re-work the tasks.
Project schedule can be presented in many forms ;
 Project schedule network diagram
 Gantt chart
 Milestone
Start
Activity
1
Activity
2
Activity
3 Activity
5
Activity
4 Activity
6
Task Name Jan Feb Mar Apr May
Planning
Design
Implementation
Milestone Scheduled date Actual Date Responsible
Testing completed 04/12/19 - Rachel
Acceptance and Signoff 07/12/19 15/12/19 Cindy
Project Closure 15/12/19 31/12/19 Carmen

More Related Content

PPTX
Software engineering 11 project scheduling
Vaibhav Khanna
 
PPTX
Project scheduling and tracking
Computer_ at_home
 
PPTX
Project Schedule Management - Sequence Activities - PMP Workgroup
Tùng Trần Thanh
 
PPTX
Project planning and scheduling techniques
Shivangi Saini
 
DOCX
Project schedule Management - PMP/CAPM
Mudassir Iqbal
 
PDF
Scheduling
Emanuele Della Valle
 
PDF
Introduction to schedule management
Essam Lotffy, PMP®, CCP®
 
PPTX
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 
Software engineering 11 project scheduling
Vaibhav Khanna
 
Project scheduling and tracking
Computer_ at_home
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Tùng Trần Thanh
 
Project planning and scheduling techniques
Shivangi Saini
 
Project schedule Management - PMP/CAPM
Mudassir Iqbal
 
Introduction to schedule management
Essam Lotffy, PMP®, CCP®
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 

What's hot (19)

DOCX
Project scheduling
Jaafer Saeed
 
PPT
Project time management
Jack Pumpuni Frimpong-Manso
 
PDF
construction project planing
SANJEEV Wazir
 
PPT
Project Time Management
mohamed elashri
 
PPTX
Project scheduling
Carla Fair-Wright
 
PPTX
Project Scheduling
Baker Khader Abdallah, PMP
 
PPTX
Project Schedule Management - PMBOK6
Agus Suhanto
 
PPT
5. project activity and risk planning
Jeanette C. Patindol
 
PPTX
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu
 
PPTX
project management
Patrick McPartland, E.I.T.
 
PPTX
Time Management within IT Project Management
rielaantonio
 
PPSX
Project Management 4 Schedule Management
grmkslideshare
 
PPTX
PROJECT SCHEDULE
Ajeesh Mk
 
PPTX
Project scheduling and tracking
Computer_ at_home
 
PDF
Project Scheduling and Control Projects
haroldtaylor1113
 
PPT
Project planning-and-control
Jatindra Malik
 
PPTX
Project control. Management
Marius Miron
 
PDF
A brief on project time management
Imran Jamil
 
PPTX
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Project scheduling
Jaafer Saeed
 
Project time management
Jack Pumpuni Frimpong-Manso
 
construction project planing
SANJEEV Wazir
 
Project Time Management
mohamed elashri
 
Project scheduling
Carla Fair-Wright
 
Project Scheduling
Baker Khader Abdallah, PMP
 
Project Schedule Management - PMBOK6
Agus Suhanto
 
5. project activity and risk planning
Jeanette C. Patindol
 
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu
 
project management
Patrick McPartland, E.I.T.
 
Time Management within IT Project Management
rielaantonio
 
Project Management 4 Schedule Management
grmkslideshare
 
PROJECT SCHEDULE
Ajeesh Mk
 
Project scheduling and tracking
Computer_ at_home
 
Project Scheduling and Control Projects
haroldtaylor1113
 
Project planning-and-control
Jatindra Malik
 
Project control. Management
Marius Miron
 
A brief on project time management
Imran Jamil
 
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Ad

Similar to Project Scheduling (20)

PPTX
TIME MANAGEMENT chapter(6), PMBOK5
Hisham Ali,PMP
 
PPTX
5. PMP Training - Time management
Qais Ur Rehman Rasooli, PMP
 
PPSX
Planning and Resourcing a Project
Nishant Munjal
 
PDF
Topic 11 - Project Schedule Management.pdf
HuyNguyen657394
 
PPTX
Time management
Mostafa Elgamala
 
PPTX
Tools & Techniques.pptx
Aarthi393502
 
PPT
Intro to PM.ppt
Chandrabhan Seniya
 
PPTX
Day 3 Schedule -walaa (3).pptx
MohanadRabea1
 
PPT
Chapter-5-Scheduling-and-Resource-Allocation.ppt
TecnicoItca
 
PPTX
Nce603 mod unit2
MODASSAR ANSARI
 
PPT
Project Time Management
dyaksa hanindito
 
DOCX
ESTIMATION techniques analogy advantages
BARATH800940
 
DOCX
PMP Study Notes
Mike Burch
 
PPTX
4) PTM & PCM .pptx
MuhammadAmanAzam
 
PPT
Project Planning Scheduling
Sadhanandavel Ramdoss
 
PPTX
PMNM101 Lesson 2 2022.pptx
SydneyJaydeanKhanyil
 
PPT
Episode 23 : PROJECT TIME MANAGEMENT
SAJJAD KHUDHUR ABBAS
 
PPTX
AWIN presentation it's only logical-a scheduling overview
Danielle Murphy
 
PPTX
Parthiv_Scheduling_Presentation_One.pptx
mibgamingbgmi
 
PPTX
06 projecttimemanagement
Dhamo daran
 
TIME MANAGEMENT chapter(6), PMBOK5
Hisham Ali,PMP
 
5. PMP Training - Time management
Qais Ur Rehman Rasooli, PMP
 
Planning and Resourcing a Project
Nishant Munjal
 
Topic 11 - Project Schedule Management.pdf
HuyNguyen657394
 
Time management
Mostafa Elgamala
 
Tools & Techniques.pptx
Aarthi393502
 
Intro to PM.ppt
Chandrabhan Seniya
 
Day 3 Schedule -walaa (3).pptx
MohanadRabea1
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
TecnicoItca
 
Nce603 mod unit2
MODASSAR ANSARI
 
Project Time Management
dyaksa hanindito
 
ESTIMATION techniques analogy advantages
BARATH800940
 
PMP Study Notes
Mike Burch
 
4) PTM & PCM .pptx
MuhammadAmanAzam
 
Project Planning Scheduling
Sadhanandavel Ramdoss
 
PMNM101 Lesson 2 2022.pptx
SydneyJaydeanKhanyil
 
Episode 23 : PROJECT TIME MANAGEMENT
SAJJAD KHUDHUR ABBAS
 
AWIN presentation it's only logical-a scheduling overview
Danielle Murphy
 
Parthiv_Scheduling_Presentation_One.pptx
mibgamingbgmi
 
06 projecttimemanagement
Dhamo daran
 
Ad

More from Reema (20)

PPTX
CSS Basic Introduction
Reema
 
PPTX
Google Analytics Course For Beginners
Reema
 
PPTX
Conclusion Of The Course
Reema
 
PPTX
Introduction
Reema
 
PPTX
Create A Texture Pattern:
Reema
 
PPTX
Creating The Footer:
Reema
 
PPTX
Creating The Main Content Area
Reema
 
PPTX
Create The Quick Quote Section:
Reema
 
PPTX
Create The Featured Project Section:
Reema
 
PPTX
Creating The Navigation Bar:
Reema
 
PPTX
Creating The Logo:
Reema
 
PPTX
Prepare Your Photoshop Document:
Reema
 
PPTX
Conclusion Of The Course
Reema
 
PPTX
Adding A Dash In jQuery:
Reema
 
PPTX
Introduction To jQuery:
Reema
 
PPTX
Introduction To JavaScript Ajax
Reema
 
PPTX
Introduction To JavaScript
Reema
 
PPTX
Responsive Web Development
Reema
 
PPTX
How To Add CSS The Correct Way.
Reema
 
PPTX
CSS Basic Introduction, Rules, And Tips
Reema
 
CSS Basic Introduction
Reema
 
Google Analytics Course For Beginners
Reema
 
Conclusion Of The Course
Reema
 
Introduction
Reema
 
Create A Texture Pattern:
Reema
 
Creating The Footer:
Reema
 
Creating The Main Content Area
Reema
 
Create The Quick Quote Section:
Reema
 
Create The Featured Project Section:
Reema
 
Creating The Navigation Bar:
Reema
 
Creating The Logo:
Reema
 
Prepare Your Photoshop Document:
Reema
 
Conclusion Of The Course
Reema
 
Adding A Dash In jQuery:
Reema
 
Introduction To jQuery:
Reema
 
Introduction To JavaScript Ajax
Reema
 
Introduction To JavaScript
Reema
 
Responsive Web Development
Reema
 
How To Add CSS The Correct Way.
Reema
 
CSS Basic Introduction, Rules, And Tips
Reema
 

Recently uploaded (20)

PDF
bain-temasek-sea-green-economy-2022-report-investing-behind-the-new-realities...
YudiSaputra43
 
PDF
Infrastructure and geopolitics.AM.ENG.docx.pdf
Andrea Mennillo
 
PPTX
Integrative Negotiation: Expanding the Pie
badranomar1990
 
PPTX
Struggling to Land a Social Media Marketing Job Here’s How to Navigate the In...
RahulSharma280537
 
PPTX
Final PPT on DAJGUA, EV Charging, Meter Devoloution, CGRF, Annual Accounts & ...
directord
 
PPTX
Financial Management for business management .pptx
Hasibullah Ahmadi
 
PDF
Top 10 Corporates in India Investing in Sustainable Energy.pdf
Essar Group
 
PPTX
E-commerce and its impact on business.
pandeyranjan5483
 
DOCX
UNIT 2 BC.docx- cv - RESOLUTION -MINUTES-NOTICE - BUSINESS LETTER DRAFTING
MANJU N
 
PPTX
PUBLIC RELATIONS N6 slides (4).pptx poin
chernae08
 
PPTX
E-Way Bill under GST – Transport & Logistics.pptx
Keerthana Chinnathambi
 
PDF
GenAI for Risk Management: Refresher for the Boards and Executives
Alexei Sidorenko, CRMP
 
DOCX
India's Emerging Global Leadership in Sustainable Energy Production The Rise ...
Insolation Energy
 
PDF
12 Oil and Gas Companies in India Driving the Energy Sector.pdf
Essar Group
 
PDF
NewBase 26 July 2025 Energy News issue - 1806 by Khaled Al Awadi_compressed.pdf
Khaled Al Awadi
 
PDF
Using Innovative Solar Manufacturing to Drive India's Renewable Energy Revolu...
Insolation Energy
 
PDF
Unveiling the Latest Threat Intelligence Practical Strategies for Strengtheni...
Auxis Consulting & Outsourcing
 
DOCX
unit 1 BC.docx - INTRODUCTION TO BUSINESS COMMUICATION
MANJU N
 
PDF
New Royals Distribution Plan Presentation
ksherwin
 
PDF
2025 07 29 The Future, Backwards Agile 2025.pdf
Daniel Walsh
 
bain-temasek-sea-green-economy-2022-report-investing-behind-the-new-realities...
YudiSaputra43
 
Infrastructure and geopolitics.AM.ENG.docx.pdf
Andrea Mennillo
 
Integrative Negotiation: Expanding the Pie
badranomar1990
 
Struggling to Land a Social Media Marketing Job Here’s How to Navigate the In...
RahulSharma280537
 
Final PPT on DAJGUA, EV Charging, Meter Devoloution, CGRF, Annual Accounts & ...
directord
 
Financial Management for business management .pptx
Hasibullah Ahmadi
 
Top 10 Corporates in India Investing in Sustainable Energy.pdf
Essar Group
 
E-commerce and its impact on business.
pandeyranjan5483
 
UNIT 2 BC.docx- cv - RESOLUTION -MINUTES-NOTICE - BUSINESS LETTER DRAFTING
MANJU N
 
PUBLIC RELATIONS N6 slides (4).pptx poin
chernae08
 
E-Way Bill under GST – Transport & Logistics.pptx
Keerthana Chinnathambi
 
GenAI for Risk Management: Refresher for the Boards and Executives
Alexei Sidorenko, CRMP
 
India's Emerging Global Leadership in Sustainable Energy Production The Rise ...
Insolation Energy
 
12 Oil and Gas Companies in India Driving the Energy Sector.pdf
Essar Group
 
NewBase 26 July 2025 Energy News issue - 1806 by Khaled Al Awadi_compressed.pdf
Khaled Al Awadi
 
Using Innovative Solar Manufacturing to Drive India's Renewable Energy Revolu...
Insolation Energy
 
Unveiling the Latest Threat Intelligence Practical Strategies for Strengtheni...
Auxis Consulting & Outsourcing
 
unit 1 BC.docx - INTRODUCTION TO BUSINESS COMMUICATION
MANJU N
 
New Royals Distribution Plan Presentation
ksherwin
 
2025 07 29 The Future, Backwards Agile 2025.pdf
Daniel Walsh
 

Project Scheduling

  • 2. Topic 9 : Project Scheduling  Project scheduling is a mechanism to communicate what tasks need to get done and which organizational resources will be allocated to complete those tasks in what timeframe.  The following are the steps needed to schedule a project: o Define Activities : Create Work Breakdown Structure (WBS) and a deliverables diagram and organize them by mapping out the tasks . o Do Estimates : Determine the time and effort it will take to complete them. o Determine Dependencies : Place a bit of slack in your schedule to accommodate these related tasks. o Assign Resources : Finalize the planned schedule by deciding what resources you are going to need to get those tasks done on time.
  • 3.  Estimate Activity Duration Inputs o This process has several tools and techniques ;- -Expert Judgement, -Analogous Estimating, -Parametric Estimating -Three-Point Estimating, -Group decision-making techniques, -Reserve Analysis  3 Point Estimating o Three-point estimating uses three estimates that when averaged come up with final estimate. • Most likely estimate – assumes there are no disaster and activity can be completed as planned • Optimistic estimate – fastest time frame in which your resource can complete the activity • Pessimistic – Assumes the worst happens and it takes much longer than planned to get the activity completed o Formula to calculate the expected duration : E = (O + P + M) / 3 o E=Expected, O = Optimistic, M = Most Likely o The formula for standard deviation which helps to determine the confidence level as below : E : (Pessimistic – Optimistic) / 6
  • 4.  Expert Judgement - The staff members who will perform activities will most accurately estimate them  Analogous Estimating ( also called as top-down estimating, an expert judgement) - Actual duration of a similar activity completed on previous project will be used to determine the duration of current activity.  Bottom Up Estimating – Is the most accurate approach to estimate cost and duration. Setting the estimates of the amount of work, duration and cost at the task level lets you combine them into estimates of higher-level deliverables and the project as a whole  Parametric Estimating - Quantitatively based estimating method that multiplies the quantity of work by the rate or uses an algorithm in conjunction with historical data to determine the cost, budget or duration estimates.
  • 5.  Group decision-making techniques (brainstorming and the Delphi or nominal group techniques) o Brainstorming is an old-age technique where all participants have an opportunity to speak up. o Delphi technique is similar to brainstorming in that you involve subject matter experts in determining estimates.  Reserve Analysis o Contingency reserve - a portion of time added to the schedule to account for risk o Management reserve - used for unknown events that have not been previously identified
  • 6. Resource Optimization Techniques  Resource Leveling - also called as resource-based method is used when the resources are overallocated and only available at certain times or when they are assigned to more than one activity at a time. The purpose to use this technique is to balance out the resource assignments to get tasks completed without overloading the individual.  Resource Smoothing - Resource smoothing accommodates resource availability by modifying activities within their float times without changing the critical path or project end date. More tasks are given to team members who are under allocated .  Reverse Resource - This technique requires the resources to be scheduled in reverse order in order to assign this key resource at the correct time.
  • 7. Modeling techniques  Include the use of what-if scenario analysis and simulation o What-If scenario : uses different sets of activity assumptions to produce multiple project durations o Simulation use a range of probable activity durations for each activity, and those ranges are then used to calculate a range of probable duration results for the project itself. o Monte Carlo is a simulation technique that runs the possible activity durations and schedule projections many many times to come up with the schedule projections and their probability, critical path duration estimates and float time.
  • 8. Schedule Compression  Mathematical analysis that’s used to shorten the project schedule duration without changing the project scope in order to accomplish all activities sooner than estimated. o Crashing – accomplished by adding resources to the critical path.Crashing the schedule can lead to increased risk and increased cost. o Fast tracking – Performing 2 tasks or project phase in parallel that were previously scheduled to start sequentially. It increases the project risk and might cause the project team to re-work the tasks.
  • 9. Project schedule can be presented in many forms ;  Project schedule network diagram  Gantt chart  Milestone Start Activity 1 Activity 2 Activity 3 Activity 5 Activity 4 Activity 6 Task Name Jan Feb Mar Apr May Planning Design Implementation Milestone Scheduled date Actual Date Responsible Testing completed 04/12/19 - Rachel Acceptance and Signoff 07/12/19 15/12/19 Cindy Project Closure 15/12/19 31/12/19 Carmen