5. Scheduling is process of determining the interrelationship of associated
timings of operations.
Basis for monitoring and controlling project.
Based on Work Breakdown Structure (WBS)
PROJECT SCHEDULING
7. NETWORK SCHEDULING
Network Scheduling is a method of scheduling
activities by joining them in a series of inter-
connected links which reflect relationships of
activities as assigned by the planner
8. The project can be broken down into a group of activities.
Each activity can be assigned a duration.
The logic relationship between activities are known and fixed in
the network chain.
BASIC ASSUMPTIONS FOR A NETWORK
SCHEDULE
9. Both use same calculations, almost similar.
Main difference is probabilistic and deterministic in time estimation.
PERT
CPM
Program Evaluation and
Review Technique
developed by the US
Navy with Booz
Hamilton Lockheed
for the Polaris
Missile/Submarine
program 1958
Critical Path Method
Developed by El Dupont
for Chemical Plant
Shutdown Project-
about same time as PERT
TECHNIQUES FOR NETWORK SCHEDULING
11. DEFINITION
The program (or project) evaluation and review technique, commonly
abbreviated PERT, is a statistical tool, used in project management,
which was designed to analyse and represent the tasks involved in
completing a given project & to illustrate the flow of events in a project.
12. In certain projects like
research and development,
new product introductions,
it is difficult to estimate the
time of various activities.
Hence PERT is used in such
projects with a probabilistic
method using three time
estimates for an activity, rather
than a single estimate, as shown
in Figure. Fig: PERT using probabilistic Method with 3 Time
Estimation
CONT..
13.
OPTIMISTIC TIME (t0):
“ If every thing goes well.” It is minimum time in the past data but not a
crash time.
PESSIMISTIC TIME (tP):
“If every thing goes badly”. It is maximum time in past data.
MOST LIKELY TIME (tm):
“The average of all normal times in past data”.
3 PERT DURATIONS
14. The activity duration is subjected to variability due to
i. Varying resource demand
ii. Work process itself
iii. Insufficient data available to estimate for characterizing the work
process exactly.
REASONS FOR VARIABILITY IN ACTIVITY
DURATION
15. “Probability is a measure of uncertainty”
Everyone knows the meanings of the statement that an event is
Almost Certain
Highly Probable
About 50-50
Highly Unlikely
Highly Improbable
CONT..
16. PERT only attempts to quantify these statements in a precise and objective way.
Probability is expressed on a scale that runs from 0 to 1
Zero(0) represent “IMPOSSIBALITY”
One(1) represent “CERTAINTY”
The number in between zero and one represent varying degree of likelihood.
That is why probability is known to be a measure of uncertainty
CONT..
17. PERT PLANNING INVOLVE THE FOLLOWING STEPS:
2)Determine the
proper sequence
of the activities
3)Construct a
network diagram
4) Estimate the time
require for each
activity
5) Determine the
critical path
1) Identify the
specific activity
& events
PROCESS
18. 1) Identify Activities & Events :
The activities are tasks require to complete the project. The events marking the
beginning & end of one or more activities.
2)Determine the proper sequence of the activities :
This step may be combine with the activity identification step since the activity
sequence is event for some task .
Other tasks may require more analysis to determine exact order in which they
must be perform .
CONT..
19. 3.Construct a network diagram :
Using the activity sequence information , a network diagram can be drawn showing
the sequence of the serial & parallel activities. The activities are depicted by
arrow lines & milestones are depicted by circles.
4.Estimate the time required for activity :
A distinguishing feature of PERT is its ability to deal with uncertainty in
activity completion times by using the 3 time estimates.
CONT..
20. 5. Determine the critical path :
The critical path is determine by adding the times for the activities in each
sequence & determining the longest path in project. The critical path determines
the total time required.
6.Update the PERT chart as the project progresses :
Make adjustment in the PERT chart as the project progresses. As the project
unfolds ,the estimated times can be replaced with actual times. The PERT chart may
be modified & improved to reflect the new situation.
CONT..
22. Taking all three time estimates into consideration, the expected time of an
activity is arrived at.
The average or mean (ta) value of the activity duration is given by
The variance of the activity time is calculated using the formula,
PERT CALCULATION
23. variance is zero
Activity duration is characterized only by
tm = to= tP
Activity duration becomes a deterministic not probabilistic quantity
WHEN “TO & TP” COINCIDES
24. .
DR. LIAQAT ALI QURESHI
NORMAL DISTRIBUTION CURVE
-3 -2 +3
+2
-1 +1
Frequency
of
occurrence
Scale of random variable “t”
te
96% of the area
99.7% of the area
68% of the area
25. For construction engineering accuracy, probabilities beyond “ 1% “ are generally not required
The area under the density curve between
+1 standard deviation and -1
standard deviation is approximately 68% .
Between “+2 and -2 “ is 96%
Between +3 and -3 standard deviation is 99.7%
DR. LIAQAT ALI QURESHI
CONT…
26. PROJECT’S EXPECTED COMPLETION TIMES
By implying central limit theorem
Probability of completing a project by any specific time, TS , can be determined by using Z-table
based on the standard or normal distribution density curve
Ta = Critical Path’s mean
Longest path standard Deviation=
TS = Any date you choose
Z = Number of deviation from mean
𝑍=
𝑇𝑆−𝑇𝑎
𝜎𝑇
𝜎𝑇𝑎=¿ (𝜎𝑇 𝑎)1/2
DR. LIAQAT ALI QURESHI
28. 3 Pert durations of the activities of a project are given below. If critical path consists of A-B-
D-F-G, find the following:
1)Ta2) σT
3) Probability that the project will close:
(a) By the end of day 31
(b) Before the start of day 37
(c) During day 34
(d) On days 34, 35, & 36
4) Find the date of completion with at least 93 percent confidence.
EXAMPLE 1
29. Activity tO tm tP
A 4 6 8
B 1 7 13
C 5 6 7
D 5 5 11
E 2 4 8
F 1 5 7
G 7 7 7
CONT...
30. SOLUTION
Critical
Act.
t0 tm tP ta
σ2
t
A 4 6 8 6.0 0.45
B 1 7 13 7.0 4.00
D 5 5 11 6.0 1.00
F 1 5 7 4.7 1.00
G 7 7 7 7.0 0.00
TOTAL ∑30.7 ∑6.45
31. Ta = ∑ta rounded to whole number
= 31
σT = √ ∑ σ2
= √ 6.45 = 2.54
TA & σT
32. By the end of day “X” = z-x = P-X
During day “X” = ZX = PX
During days “X,Y,Z” = ZXYZ = PXYZ
After the end of day “X” = ZX- = PX-
NOTATION TO BE USED
33. Z-31 = (Ts - TE) /σT
= 31 - 31 / 2.54
= 0
P-31 = 0.50
= 50 %
(A) BY THE END OF DAY 31
34. (It is equivalent to “By the end of day 36)
Z-36 = (Ts - TE) /σTE
= 36 - 31 / 2.54
= 1.97
P-36 = 0.98
= 98 %
(B) BEFORE THE START OF DAY 37
35. It is equivalent to
“By the end of day 34 - By the end of day 33”
Z-34 = (Ts - TE) /σTE = 34 - 31 / 2.54 = 1.18
P-34 = 0.88 = 88 %
Z-33 = (Ts - TE) /σTE = 33 - 31 / 2.54 = 0.79
P-33 = 0.79 = 79 %
P34 = P-34 - P-33 = 88 - 79 = 9%
(C) DURING DAY 34
36. It is equivalent to
“By the end of day 36 - By the end of day
33”
P34,35,36 = P-36 - P-33
= 98 (from b) - 79 (from c)
= 19%
(D) ON DAYS 34, 35, & 36
37. P = 93 %
Z = 1.5 (from table)
Z = (Ts - TE) /σTE
1.5 = (Ts - 31) / 2.54
Ts = 34.81
Therefore, the completion date = end of
day 35 with at least 93 % confidence.
DATE OF COMPLETION
(WITH 93 % CONFIDENCE)
38. An R & D project has a list of tasks to be performed whose time
estimates are given in the Table as follows :
EXAMPLE 2
a.Draw the project network.
b.Find the critical path.
c.Find the probability that the project is completed in 19 days. If the probability is
less that 20%, find the probability of completing it in 24 days.
39. Time expected for each activity is calculated using the formula
Similarly, the expected time is calculated for all the activities.
CONT..
The variance of activitytime is calculated using the formula
Similarly,variances of all the activities are calculated.
41. Calculate the earliest time, ES and Latest time LS for all the
activities.
B)
From the network diagram the critical path is identified as 1-4, 4-6, 6-7, with a project duration
of
22 days.
A) CONSTRUCT A NETWORK DIAGRAM
9 9
ES LS
42. from normal tables, z (-1.3416) = 0.0901
= 0.0901
= 9.01%
(C)The probability of completing the project within 19 days is given by P (Z< Z0 )
To find Zo,
Thus, the probability of completing the R & D project in 19 days is 9.01%.
43. Since the probability of completing the project in 19 days is less than 20% As in question, we
find the probability of completing it in 24 days.
CONT…
from normal tables, z (0.8994) = 0.802
= 0.802
= 80.2%
45. Simple to understand and use.
Show whether the project is on schedule; or behind /ahead of the schedule.
Identify the activities that need closer attention
Determine the flexibility available with activities
Show potential risk with activities
Provide good documentation of the project activities
Help to set priorities among activities & resource allocation as per priority
ADVANTAGES
46. Time Focused Method
Subjective Analysis
Prediction Inaccuracy
Expensive – Too expensive in terms of time consumed, research,
prediction, and resources utilized.
Other Issues with PERT – This method is highly labor-intensive
in nature.
DISADVANTAGES
48. ADVANTAGES OF CPM
Consistent framework for planning, scheduling, monitoring, and controlling project.
Helps proper communications between departments and functions.
Determines expected project completion date.
Determines the dates on which tasks may be started or must be started if the
project is to stay in schedule.
Shows which tasks must be coordinated to avoid resource or timing conflicts.
Shows which tasks may run in parallel to meet project completion date.
48
49. DISADVANTAGES OF CPM
Reliability of CPM largely based on accurate estimates and
assumptions made.
CPM does not guarantee the success of project.
Resources may not actually be as flexible as management hope when
they come to address network float.
Too many activities may the network diagram too complicated.
Activities might themselves have to be broken down into mini
projects.
49
51. COMPARISON CHART
Basis for
Comparison
PERT CPM
Meaning
PERT is a project management technique,
used to manage uncertain activities of a
project.
CPM is a statistical technique
of project management that
manages well defined
activities of a project.
What is it?
A technique of planning and control of
time.
A method to control cost
and time.
Orientation Event-oriented Activity-oriented
Evolution
Evolved as Research &
Development project
Evolved as Construction project
Model Probabilistic Model Deterministic Model
52. Basis for Comparison PERT CPM
Focuses on Time Time-cost trade-off
Estimates Three time estimates One time estimate
Appropriate for
High precision time
estimate
Reasonable time
estimate
Management of Unpredictable Activities Predictable activities
Nature of jobs Non-repetitive nature Repetitive nature
Suitable for
Research and
Development Project
Non-research projects like
civil construction, ship
building etc.
#9:The only difference between the two method is that CPM uses fixed duration for each activity while Pert uses a probability distribution
#13:Optimistic time tO:
It is the shortest time taken to complete the activity. It means that if everything goes well then there is more chance of completing the activity within this time.
Most likely time tm:
It is the normal time taken to complete an activity, if the activity were frequently repeated under the same conditions.
Pessimistic time tp:
It is the longest time that an activity would take to complete. It is the worst time estimate that an activity would take if unexpected problems are faced.