Round Robin Algorithm Scheduling Algorithm
RR Scheduling Example:
There are six processes named as P1, P2, P3, P4, P5 and P6. Their arrival time and burst time are given
below in the table. The time quantum of the system is 4 units. Calculate Average waiting time and
average turn around time.
Process ID Arrival Time Burst Time
1 0 5
2 1 6
3 2 3
4 3 1
5 4 5
6 6 4
Answer:
According to the algorithm, we have to maintain the ready queue and the Gantt chart. The structure of
both the data structures will be changed after every scheduling.
Ready Queue:
Initially, at time 0, process P1 arrives which will be scheduled for the time slice 4 units. Hence in the
ready queue, there will be only one process P1 at starting with CPU burst time 5 units.
P1
5
GANTT chart:
The P1 will be executed for 4 units first.
P1
0 4
Ready Queue
Meanwhile the execution of P1, four more processes P2, P3, P4 and P5 arrives in the ready
queue. P1 has not completed yet, it needs another 1 unit of time hence it will also be added
back to the ready queue.
Process P2 P3 P4 P5 P1
Burst Time 6 3 1 5 1
GANTT chart
After P1, P2 will be executed for 4 units of time which is shown in the Gantt chart.
P1 P2
0 4 8
Ready Queue
During the execution of P2, one more process P6 is arrived in the ready queue. Since P2 has
not completed yet hence, P2 will also be added back to the ready queue with the remaining
burst time 2 units.
P3 P4 P5 P1 P6 P2
3 1 5 1 4 2
GANTT chart
After P1 and P2, P3 will get executed for 3 units of time since its CPU burst time is only 3
seconds.
P1 P2 P3
0 4 8 12
Ready Queue
Since P3 has been completed, hence it will be terminated and not be added to the ready queue.
The next process will be executed is P4.
P4 P5 P1 P6 P2
1 5 1 4 2
GANTT chart
After, P1, P2 and P3, P4 will get executed. Its burst time is only 1 unit which is lesser then the
time quantum hence it will be completed.
P1 P2 P3 P4
0 4 8 11 12
Ready Queue
The next process in the ready queue is P5 with 5 units of burst time. Since P4 is completed
hence it will not be added back to the queue.
P5 P1 P6 P2
5 1 4 2
GANTT chart
P5 will be executed for the whole time slice because it requires 5 units of burst time which is
higher than the time slice.
P1 P2 P3 P4 P5
0 4 8 11 12 16
Ready Queue
P5 has not been completed yet; it will be added back to the queue with the remaining burst time
of 1 unit.
P1 P6 P2 P5
1 4 2 1
GANTT Chart
The process P1 will be given the next turn to complete its execution. Since it only requires 1
unit of burst time hence it will be completed.
P1 P2 P3 P4 P5 P1
0 4 8 11 12 16 17
Ready Queue
P1 is completed and will not be added back to the ready queue. The next process P6 requires
only 4 units of burst time and it will be executed next.
P6 P2 P5
4 2 1
GANTT chart
P6 will be executed for 4 units of time till completion.
P1 P2 P3 P4 P5 P1 P6
0 4 8 11 12 16 17 21
Ready Queue
Since P6 is completed, hence it will not be added again to the queue. There are only two
processes present in the ready queue. The Next process P2 requires only 2 units of time.
P2 P5
2 1
GANTT Chart
P2 will get executed again, since it only requires only 2 units of time hence this will be
completed.
P1 P2 P3 P4 P5 P1 P6 P2
0 4 8 11 12 16 17 21 23
Ready Queue
Now, the only available process in the queue is P5 which requires 1 unit of burst time. Since
the time slice is of 4 units hence it will be completed in the next burst.
P5
1
GANTT chart
P5 will get executed till completion.
P1 P2 P3 P4 P5 P1 P6 P2 P5
0 4 8 11 12 16 17 21 23 24
As, we know to calculate:
Turn Around Time = Completion Time - Arrival Time
Waiting Time = Turn Around Time - Burst Time
Process
ID
Arrival
Time
Burst
Time
Completion
Time
Turn Around
Time
(Completion Time –
Arrival Time)
Waiting
Time
(Turn Around Time –
Arrival Time)
1 0 5 17 17 12
2 1 6 23 22 16
3 2 3 11 9 6
4 3 1 12 9 8
5 4 5 24 20 15
6 6 4 21 15 11
Avg Waiting Time = ∑
=(12+16+6+8+15+11)/6
=68/6
= 11.33 ms
Avg Turn Around Time = ∑
=(17+22+9+9+20+15)/6
=92/6
= 15.33 ms
Turn Around time of All Process
Waiting Time of All Process
No of Process
No of Process

More Related Content

PPTX
5.2.2. Memory Consistency Models.pptx
PPTX
Operations on Processes
PPTX
Operating system Dead lock
PPTX
Process creation and termination In Operating System
PPT
Divide and Conquer
PPTX
Operating Systems: Process Scheduling
PPTX
Backtracking
PPT
Parallel algorithms
5.2.2. Memory Consistency Models.pptx
Operations on Processes
Operating system Dead lock
Process creation and termination In Operating System
Divide and Conquer
Operating Systems: Process Scheduling
Backtracking
Parallel algorithms

What's hot (20)

PPTX
Brute force method
PDF
DBMS 9 | Extendible Hashing
PPTX
Shortest job first Scheduling (SJF)
PDF
Measures of query cost
DOCX
BANKER'S ALGORITHM
PPTX
Job sequencing with deadline
PPTX
White box & Black box testing
PPTX
Transaction Management
PPT
multiprocessors and multicomputers
PPT
deadlock avoidance
PDF
Course outline of parallel and distributed computing
PDF
TOC 2 | Deterministic Finite Automata
PPSX
ARIES Recovery Algorithms
PPTX
1.7. eqivalence of nfa and dfa
PPTX
Lecture 14 run time environment
PPTX
Pipelining And Vector Processing
PPTX
Cpu scheduling in operating System.
PPTX
Dynamic programming
PDF
Undecidabality
PPTX
First-Come-First-Serve (FCFS)
Brute force method
DBMS 9 | Extendible Hashing
Shortest job first Scheduling (SJF)
Measures of query cost
BANKER'S ALGORITHM
Job sequencing with deadline
White box & Black box testing
Transaction Management
multiprocessors and multicomputers
deadlock avoidance
Course outline of parallel and distributed computing
TOC 2 | Deterministic Finite Automata
ARIES Recovery Algorithms
1.7. eqivalence of nfa and dfa
Lecture 14 run time environment
Pipelining And Vector Processing
Cpu scheduling in operating System.
Dynamic programming
Undecidabality
First-Come-First-Serve (FCFS)
Ad

Similar to Round Robin Algorithm.pdf (20)

PPTX
First Come First Serve (FCFS).pptx
PPTX
CPU-Scheduling-Demo-for-Presentation.pptx
PPTX
operating system scheduling concept lec2
PDF
scheduling-algorithms.pdf
PPT
scheduling-algorithms.ppt
PDF
Lec SRTF, Priority, RR scheduling OS.pdf
PPTX
Cpu scheduling
PPTX
Operating System - FCFS and Priority Scheduling Algorithm and Code
DOCX
Program for FCFS CPU Scheduling.program docx
PPTX
Week 5a.pptx of cpu scheduling operating system class
PPTX
Operating system
PPT
OS-operating systems- ch05 (CPU Scheduling) ...
PDF
International Journal of Engineering Research and Development (IJERD)
PPTX
Operating system
PPTX
Cs problem [repaired]
PPTX
LRTF.pptx
PDF
Fcfs and sjf
PDF
OS Process Chapter 3.pdf
PDF
Hệ Điều Hành - operating system Học viện PTIT
PDF
Comparison Analysis of CPU Scheduling : FCFS, SJF and Round Robin
First Come First Serve (FCFS).pptx
CPU-Scheduling-Demo-for-Presentation.pptx
operating system scheduling concept lec2
scheduling-algorithms.pdf
scheduling-algorithms.ppt
Lec SRTF, Priority, RR scheduling OS.pdf
Cpu scheduling
Operating System - FCFS and Priority Scheduling Algorithm and Code
Program for FCFS CPU Scheduling.program docx
Week 5a.pptx of cpu scheduling operating system class
Operating system
OS-operating systems- ch05 (CPU Scheduling) ...
International Journal of Engineering Research and Development (IJERD)
Operating system
Cs problem [repaired]
LRTF.pptx
Fcfs and sjf
OS Process Chapter 3.pdf
Hệ Điều Hành - operating system Học viện PTIT
Comparison Analysis of CPU Scheduling : FCFS, SJF and Round Robin
Ad

Recently uploaded (20)

PPTX
Research Writing, Mechanical Engineering
PPTX
module 2 renewable energy power plant.pptx
PDF
Project_Mgmt_Institute_- Marc Marc Marc.pdf
PDF
Recent Trends in Network Security - 2025
PDF
PhD defense presentation in field of Computer Science
PDF
1.-fincantieri-investor-presentation2.pdf
PDF
ITEC 1010 - Networks and Cloud Computing
PDF
Design and Implementation of Low-Cost Electric Vehicles (EVs) Supercharger: A...
PDF
The Journal of Finance - July 1993 - JENSEN - The Modern Industrial Revolutio...
PPTX
MODULE 02 - CLOUD COMPUTING-Virtual Machines and Virtualization of Clusters a...
PDF
CB Công Nghiệp Slide .dh bách khoa đà nẵng
PPTX
MODULE 3 SUSTAINABLE DEVELOPMENT GOALSPPT.pptx
PDF
Introduction to Machine Learning -Basic concepts,Models and Description
PDF
B461227.pdf American Journal of Multidisciplinary Research and Review
PPT
linux chapter 1 learning operating system
PDF
02. INDUSTRIAL REVOLUTION & Cultural, Technical and territorial transformatio...
PPT
Basics Of Pump types, Details, and working principles.
PDF
Human CELLS and structure in Anatomy and human physiology
PDF
August 2025 Top read articles in International Journal of Database Managemen...
PPTX
highway-150803160405-lva1-app6891 (1).pptx
Research Writing, Mechanical Engineering
module 2 renewable energy power plant.pptx
Project_Mgmt_Institute_- Marc Marc Marc.pdf
Recent Trends in Network Security - 2025
PhD defense presentation in field of Computer Science
1.-fincantieri-investor-presentation2.pdf
ITEC 1010 - Networks and Cloud Computing
Design and Implementation of Low-Cost Electric Vehicles (EVs) Supercharger: A...
The Journal of Finance - July 1993 - JENSEN - The Modern Industrial Revolutio...
MODULE 02 - CLOUD COMPUTING-Virtual Machines and Virtualization of Clusters a...
CB Công Nghiệp Slide .dh bách khoa đà nẵng
MODULE 3 SUSTAINABLE DEVELOPMENT GOALSPPT.pptx
Introduction to Machine Learning -Basic concepts,Models and Description
B461227.pdf American Journal of Multidisciplinary Research and Review
linux chapter 1 learning operating system
02. INDUSTRIAL REVOLUTION & Cultural, Technical and territorial transformatio...
Basics Of Pump types, Details, and working principles.
Human CELLS and structure in Anatomy and human physiology
August 2025 Top read articles in International Journal of Database Managemen...
highway-150803160405-lva1-app6891 (1).pptx

Round Robin Algorithm.pdf

  • 1. Round Robin Algorithm Scheduling Algorithm RR Scheduling Example: There are six processes named as P1, P2, P3, P4, P5 and P6. Their arrival time and burst time are given below in the table. The time quantum of the system is 4 units. Calculate Average waiting time and average turn around time. Process ID Arrival Time Burst Time 1 0 5 2 1 6 3 2 3 4 3 1 5 4 5 6 6 4 Answer: According to the algorithm, we have to maintain the ready queue and the Gantt chart. The structure of both the data structures will be changed after every scheduling. Ready Queue: Initially, at time 0, process P1 arrives which will be scheduled for the time slice 4 units. Hence in the ready queue, there will be only one process P1 at starting with CPU burst time 5 units. P1 5 GANTT chart: The P1 will be executed for 4 units first. P1 0 4 Ready Queue Meanwhile the execution of P1, four more processes P2, P3, P4 and P5 arrives in the ready queue. P1 has not completed yet, it needs another 1 unit of time hence it will also be added back to the ready queue.
  • 2. Process P2 P3 P4 P5 P1 Burst Time 6 3 1 5 1 GANTT chart After P1, P2 will be executed for 4 units of time which is shown in the Gantt chart. P1 P2 0 4 8 Ready Queue During the execution of P2, one more process P6 is arrived in the ready queue. Since P2 has not completed yet hence, P2 will also be added back to the ready queue with the remaining burst time 2 units. P3 P4 P5 P1 P6 P2 3 1 5 1 4 2 GANTT chart After P1 and P2, P3 will get executed for 3 units of time since its CPU burst time is only 3 seconds. P1 P2 P3 0 4 8 12 Ready Queue Since P3 has been completed, hence it will be terminated and not be added to the ready queue. The next process will be executed is P4. P4 P5 P1 P6 P2 1 5 1 4 2 GANTT chart After, P1, P2 and P3, P4 will get executed. Its burst time is only 1 unit which is lesser then the time quantum hence it will be completed.
  • 3. P1 P2 P3 P4 0 4 8 11 12 Ready Queue The next process in the ready queue is P5 with 5 units of burst time. Since P4 is completed hence it will not be added back to the queue. P5 P1 P6 P2 5 1 4 2 GANTT chart P5 will be executed for the whole time slice because it requires 5 units of burst time which is higher than the time slice. P1 P2 P3 P4 P5 0 4 8 11 12 16 Ready Queue P5 has not been completed yet; it will be added back to the queue with the remaining burst time of 1 unit. P1 P6 P2 P5 1 4 2 1 GANTT Chart The process P1 will be given the next turn to complete its execution. Since it only requires 1 unit of burst time hence it will be completed. P1 P2 P3 P4 P5 P1 0 4 8 11 12 16 17 Ready Queue P1 is completed and will not be added back to the ready queue. The next process P6 requires only 4 units of burst time and it will be executed next.
  • 4. P6 P2 P5 4 2 1 GANTT chart P6 will be executed for 4 units of time till completion. P1 P2 P3 P4 P5 P1 P6 0 4 8 11 12 16 17 21 Ready Queue Since P6 is completed, hence it will not be added again to the queue. There are only two processes present in the ready queue. The Next process P2 requires only 2 units of time. P2 P5 2 1 GANTT Chart P2 will get executed again, since it only requires only 2 units of time hence this will be completed. P1 P2 P3 P4 P5 P1 P6 P2 0 4 8 11 12 16 17 21 23 Ready Queue Now, the only available process in the queue is P5 which requires 1 unit of burst time. Since the time slice is of 4 units hence it will be completed in the next burst. P5 1 GANTT chart P5 will get executed till completion. P1 P2 P3 P4 P5 P1 P6 P2 P5 0 4 8 11 12 16 17 21 23 24
  • 5. As, we know to calculate: Turn Around Time = Completion Time - Arrival Time Waiting Time = Turn Around Time - Burst Time Process ID Arrival Time Burst Time Completion Time Turn Around Time (Completion Time – Arrival Time) Waiting Time (Turn Around Time – Arrival Time) 1 0 5 17 17 12 2 1 6 23 22 16 3 2 3 11 9 6 4 3 1 12 9 8 5 4 5 24 20 15 6 6 4 21 15 11 Avg Waiting Time = ∑ =(12+16+6+8+15+11)/6 =68/6 = 11.33 ms Avg Turn Around Time = ∑ =(17+22+9+9+20+15)/6 =92/6 = 15.33 ms Turn Around time of All Process Waiting Time of All Process No of Process No of Process